Electrical & Power SPRING EDITION Contents 3 — Do you know the vital requirements for standby power? 13 — Cummins Power Integration Center (PIC) Virtual Tour 14 — Your questions answered: Harmonics solutions for water and wastewater applications 27 — Take an In-Depth Exploration into Cummins State-of-theArt Microgrid Testing Facility 32 — Your questions answered: Critical power: hospital electrical systems 38 — Why decarbonization, ESG initiatives are a bigger priority for building owners 41 — PODCAST: Brian Alessi on decarbonization strategies in building design 2 Do you know the vital requirements for standby power? Back to TOC The ability to provide power to a building or load when utility power is lost can be a critical need for a facility to support vital operations or building and occupant safety O wners, architects, contractors and engineers tend to use the terms emergency/ backup/standby power interchangeably to indicate that during a utility power outage, there is a need to have specific loads or even an entire structure’s power maintained for facility operation. There are distinct differences in the requirements for legally required standby power systems. The first step in designing a robust and code-compliant standby power system for a project is understanding the project requirements. Legally required standby power system loads are generally described as loads, which upon failure of the normal power source, could create hazards or hamper rescue or fire-fighting operations. Depending on the project, there may be a need for various types of loads to be served by alternate power sources. These loads can include emergency loads that are loads legally required by governmental agencies for the purposes essential for safety for human life. Legally required standby loads can also be present in a facility; these include loads that could create hazards or hamper rescue or fire-fighting operations if power is lost. 3 Do you know the vital requirements for standby power? Back to TOC Additionally, optional standby systems may be present that include loads that, when stopped, could cause discomfort, serious interruption of the process or damage to the product or process. Lastly, there may be additional loads that do not Figure 1: Sample project code analysis summary that outlines pertinent information for understanding emergency and standby power requirements. These are typically found on the front pages of the architectural or general project drawings. Courtesy: Design Group Facility Solutions neatly fall into one of the above categories, but are still required based on an owner’s request to be supported by an alternate power system mainly for reasons of convenience, comfort or financial impact. These load types could be considered optional standby loads. There is some overlap between the various power systems above for the same load type. These loads should be classified based on the occupancy of the space as well as the function of the load. Additional clarification and guidance can be found in many of 4 Do you know the vital requirements for standby power? Back to TOC the codes and standards required for the proper design and construction of a building. Standby power codes and standards NFPA 70: National Electrical Code (NEC) Articles 700, 701 and 702 provide directions as to the electrical safety of the installation, operation and maintenance of emergency, standby and optional standby systems. That is to say, the NEC dictates the technical requirements for electrical installations that include: commissioning, testing, capacity and rating, transfer equipment requirements, wiring methods, identification, etc. These NEC articles provide guidance in general for the emergency power supply systems (EPSS) themselves along with other NEC code articles; other codes and standards such as the International Building Code (IBC), the NFPA 101: Life Safety Code, the International Mechanical Code Figure 2: Double-wall diesel generator base-mounted fuel tank rated for required emergency power supply systems class. Courtesy: Design Group Facility Solutions and International Fire Code (IFC), local building codes and amendments, federal and military codes and standards, the Environmental Protection 5 Do you know the vital requirements for standby power? Agency, FM Global and other insurance company requirements, to name just a few, Back to TOC also have specific design criteria requirements. These codes and standards provide further clarity on how loads within specific facilities should be treated. While the NEC is the code that electrical engineers reference most regularly, the designer or engineer cannot rely solely on the NEC for direction; in fact, there are many other sources in which criteria for the proper application of alternate power systems can be found. NFPA 110: Standard for Emergency and Standby Power Systems defines the following: “EPSS: A complete functioning emergency power supply system coupled to a system of conductors, disconnecting means and overcurrent protection devices, transfer switches and all control, supervisory and support devices up to and including the load terminals of the transfer equipment needed for the system to operate as a safe and reliable source of power.” The terms EPSS and standby power supply systems include but are not limited to: • Emergency power systems. • Alternate power systems. • Standby power systems. • Legally required standby systems. 6 Do you know the vital requirements for standby power? • Alternate power sources. Back to TOC NFPA 110 specifies the installation, performance, maintenance and test requirements for EPSSs in terms of types, classes and levels for the categories above, therefore the category terms used depend on the application involved. These types, classes and levels are essential in helping to distinguish the proper classification of the alternate power distribution system. An EPSS class refers to the length of time required for an EPSS to provide power to a load (duration the load can be served) without being refueled (NFPA 110 Table 4.1(a)) as well as the maximum time allowed for the load terminals of transfer equipment to be without acceptable power (how quickly the load needs to receive power, (NFPA 110 Table 4.1(b)). Further, NFPA 110 defines levels for EPSS equipment installation, performance and maintenance requirements. A Level 1 system is where failure of the equipment to perform could result in loss of human life or serious injuries. A Level 2 system is where failure of the EPSS to perform is less critical to human life and safety. NFPA 110 Appendix A is a reference to assist the designer in understanding the intent of what loads might qualify as either Level 1 or Level 2. NFPA 110 provides excellent guidance in understanding the requirement when classifying the requirements of different types of emergency power supply systems, but how does the designer know which components of a building or project are applicable to these classifications? Start with the understanding of the project and its occupancy and use classification in the applicable building code or standard. 7 Do you know the vital requirements for standby power? Back to TOC Understanding power system intent The building code or standard for a given municipality is dictated by the authority having jurisdiction (AHJ). The AHJ, whether that is the local building department or other governmental agency will determine the building code that is applicable at the time of design. The IBC is a common compliance requirement for many buildings. The IBC defines the following terms: “Emergency power system: A source of automatic electric power of a required capacity and duration to operate required life safety, fire alarm, detection and ventilation systems in the event of a power failure of the primary power. Emergency power systems are required for electrical loads where interruption of the primary power could result in the loss of human life or serious injury.” Figure 3: Exterior diesel generator with base-mounted fuel tank. Courtesy: Design Group Facility Solutions These systems are required to make power available within 10 seconds per NFPA 70 Section 700.12. 8 Do you know the vital requirements for standby power? “Standby power system: A source of automatic electric power of a required capacity Back to TOC and duration to operate required building, hazardous material or ventilation systems in the event of a failure of the primary power. Standby power systems are required for electrical loads where interruption of the primary power could create hazards or hamper rescue or fire-fighting operations.” These systems are required to make power available within 60 seconds per NFPA 70 Section 701.12. NEC Article 701.1, Informational Notes 4 and 5 further correlate the intent of standby system loads as being loads that any interruption of could create a hazard or hamper rescue or fire-fighting efforts and could result in loss of human life (Level 1) or less critical to human life and safety (Level 2). Why standby power systems matter Understanding the intent of the various codes and standards is interesting, but as designers, why should we care? We care because based on the types of loads, different requirements are required for different load types including but not limited to: operation, location and installation. For example, IBC Chapter 909.11 requires that for smoke control systems, the standby power source and its transfer switches shall be in a separate room from the normal power transformers and switchgears. NEC Article 701: 9 Do you know the vital requirements for standby power? Back to TOC • Indicates a legally required standby system shall have the load capacity calculated in accordance with Parts I through IV of Article 220 or other approved method. Figure 4: Dedicated transfer switches for separate emergency power supply systems loads. Courtesy: Design Group Facility Solutions • Dictates the design of the transfer equipment of the standby power system to include allowing the ability to bypass the transfer equipment and the requirement for the transfer equipment to be electrically operated and mechanically held. • Mandates signage at the service entrance identifying each legally required standby power source. • Defines the maximum time allowed for the legally required standby source to become available to support the required loads (60 seconds, or per NFPA 110, Type 60). 10 Do you know the vital requirements for standby power? • Defines the minimum operation time before refueling (two hours, or per NFPA 110, Back to TOC Class 2). • Provides an approved list of alternate power sources that can be used for standby power systems (some of which require AHJ approval). These include: • Public gas system. • Municipal water supply. • Storage batteries. • Generator sets. • Stored energy power systems. • Separate service. • Connection ahead of the service disconnecting means. • Microgrid systems. • The standby power source should be carefully evaluated based on the loads supported and their purpose. 11 Do you know the vital requirements for standby power? It is important to understand that the NEC, IBC, NFPA 110 or other codes and stan- Back to TOC dards are to be used as a guide and minimal compliance standard only. It is impossible for these documents to be comprehensive for every situation, so it is up to the design professional with approval by the AHJ to determine the proper classification of the electrical loads on each project while meeting the owner’s project goals. It is the responsibility of the electrical designer to stay current with the understanding of the ever-changing code requirements. The major building and construction codes typically provide changes on a three-year code cycle. The requirements for standby power systems are no exception. Erika L. Bolger Erika L. Bolger, PE, LEED AP, is a director at Design Group Facility Solutions and has more than 30 years of consulting engineering experience. 12 Cummins Power Integration Center (PIC) Virtual Tour Back to TOC Cummins Power Integration Center (PIC) Virtual Tour Enjoy an exclusive look into the Cummins Power Integration Center (PIC), located in Fridley, MN. Designed by Cummins leading engineers and microgrid advisors, the PIC is one of the largest and most configurable microgrid testing facilities in the world. This virtual tour will provide an in-depth look into this state-of-the-art facility and education on the basics of microgrids. 13 Your questions answered: Harmonics solutions for water and wastewater applications Back to TOC Technical recommendations for reducing harmonic distortion and improving system capacity and improving system reliability while evaluating installed costs. P roblems associated with harmonic distortion are well understood for many power system applications; however, finding the right solution is challenging. Because of the significant use of variable frequency drives in water and wastewater applications, understanding the appropriate solutions for your application is important. There are at least 10 different technologies and strategies to choose from, each with specific technical and economic advantages. During a webcast on Sept. 12, presenters from Eaton Corporation provided technical recommendations for reducing harmonic distortion and improving system capacity and improving system reliability while evaluating installed costs. Additional questions were answered by Dan Carnovale, Director, Eaton Experience Centers, Eaton Corporation. Question: For what size drive would you consider 18 pulse a good financial choice? Answer: At about 150 HP or more, the cost of an 18-pulse drive is more cost effective than a 6-pulse drive with additional filtering to compensate to an equivalent harmonic level compared to the 18-pulse drive. 14 Your questions answered: Harmonics solutions for water and wastewater Back to TOC Question: Does PV generated power contain harmonics? Answer: PV/solar inverters often have some voltage distortion from the converter, but most are relatively low magnitude. The frequency of the harmonics are usually higher orders from the pulse-width-modulated controls. Question: How will harmonics affect natural cable or bus in electrical system? Answer: 3rd harmonics accumulate on a 3 phase 4 wire system neutral. The 3rd harmonics on the neutral are additive (i.e., if you have 100A of 3rd harmonic on phase A, 80A of 3rd harmonic on phase B and 90A of 3rd harmonic on phase C, you will see 270A of 3rd harmonic on the neutral). Coincidentally, if you have 100A of 60Hz on phase A, phase B and phase C, you will have 0A of 60 Hz on the neutral because the 60 15 Your questions answered: Harmonics solutions for water and wastewater Hz currents are all 120 degrees apart while the 3rd (and odd multiples of 3rd, i.e., 9th, Back to TOC etc.) are all in phase and additive from each phase. Question: Is split AC in home one example for voltage distortion? Answer: Mini-split air conditioners in homes MAY be harmonic producing loads as most of these units have a VFD and would produce harmonic currents. Question: What mitigations can we do at the utilities transformers to solve the harmonics? Answer: At the secondary of the utility transformer, you can use many of the typical harmonic solutions to reduce voltage distortion by offering a low-impedance path — harmonic filters, active filter, pairs of phase shifting transformers, etc. Question: In our thermography surveys, we have seen very hot 200F to 300F filter/choke transformers connected to VFDs. Is this normal? Or does it just show that the filter/choke is working hard to filter out the harmonics? Answer: Line reactors are designed to run hot — some hotter than others. I would check with the reactor vendor to see what they expect as “normal.” Reactors, like transformers, have an X/R ratio that is the ratio of inductance to resistance, and the higher the resistance, the more losses and the more heat. Question: Is there useful information in the IEEE 519-1992 version that would make it desirable to keep/get the 1992 version? 16 Your questions answered: Harmonics solutions for water and wastewater Answer: I personally don’t believe so. I’ve looked through it in detail, and most of it Back to TOC was things like notch depth and more theoretical/mathematical parts that aren’t really relevant to solving the issue of harmonics for the general application. The newer standards get to the key points and summarize well what is important. Question: With a passive filter that has a backup generator, the VFD cabinet manufacturer will introduce a bypass contactor. Will that bypass during a generator, or just at a certain speed? How do you keep the PF from going leading at low loads, any loads, and trip the generator? Answer: With older UPSs, this was a very typical problem, and the passive filters were shut down on the generators at 35% load. A fixed filter (drive dedicated filter with a large capacitor) can be turned off with a contactor on the generator, but sometimes if you need filtering on the generator, you can’t afford to have the filter off. At very light loads, yes, turn off the filter, but at heavy loads, accommodations should be made and tested/modeled to ensure proper operation. By the way, a generator can take a leading load but not too far leading. Question: In the following chain of the power system model, what is the place to tackle the harmonics: utilities substation … utilities switch … at the user yard utilities transformers … at the user yard distribution center … at user yard load (VFD, UPS, etc.)? Answer: Great question. It depends on the goal of taking care of harmonics. If you are trying to fix the problem at the PCC, filter/correct at the user distribution center or higher. If PF correction is the issue, anywhere downstream of the utility will fix the PF, but it may make it difficult to ensure you don’t overload the filter. For very high-voltage 17 Your questions answered: Harmonics solutions for water and wastewater distortion or capacity issues downstream, fix the problem at the load. I2R loss reduc- Back to TOC tion is about 1-4% for both PF correction and for harmonic mitigation, so you won’t get a great payback but you can achieve some. Question: I have recently seen a lot of installs of line filters in front of drives but have no contactors to bring in the caps. The caps are in all of the time. Is this a concern? There is a lot of wasted energy, but my concern is at lower speeds of the drives. Is the filter really doing its job? Answer: Having a cap/filter on at low speed can be an issue with leading PF and higher voltage. I don’t think it will create too much of an issue with kW/losses, but the concern is really just 60 Hz (overvoltage and PF). For drive dedicated filters, they often do have a dedicated contactor to remove the filter branch at very light loads, especially for larger units. Question: Are there any unique considerations for current harmonics on ungrounded power systems? Answer: Current harmonics follow a pattern positive sequence, negative sequence, zero sequence — 1st (+), 2nd (-), 3rd (0), 4th(+), 5th (-), 6th (0), etc. In my experience, the only issues I’ve seen that are different for ungrounded or HRG systems are higher order zero sequence harmonics — i.e., maybe 39th, for example, that are capacitively coupled through the natural capacitance of the power system and coupled in from the PWM output of drives. This can show up on some HRG systems as a false issue and can be coupled into other equipment. Use a scope with a good higher frequency FFT to analyze. Question: When would you pick a 6-pulse drive with a line reactor over an AFE drive? Is the performance the same? 18 Your questions answered: Harmonics solutions for water and wastewater Answer: A 6-pulse drive with a 5% reactor will be about 30-40% ITHD at a high load Back to TOC level. An active front end drive may have less than 5% ITHD across loading but may have some high frequency coupled in, but the bigger concern is that it may cost 2X the other drive. In systems that have a lot of drives and smaller drives, usually, 6-pulse with other filtering (maybe even an AHF) will be the best cost-effective solution. Also, if redundancy is used for drives, this is even more the case. Question: Does active filtering consume a significant amount of power? Answer: No, for passive filters. In fact, filtering, if done right, can reduce the I2R losses and reduce your kW consumption. However, for active filtering, because of the AC/ DC/AC conversion, yes, filtering can add a few kW losses depending on the size of the unit. That said, active filters are mostly used for harmonics with PF as a secondary benefit, while passive filters are usually used for PF correction first and to achieve a slight harmonic benefit without risk of resonance. Question: How can a I tell if harmonics are too high during design phase if the VFDs or computer power supplies are unknown? Answer: With experience and measurements of similar systems. The good news about harmonics is that they are relatively predictable, and models reflect well the real world if they are done correctly. For example, you can measure the ITHD from an existing site for a 50 HP drive and get 35%, but in another site get 42% — the difference could be loading of the drive or the source impedance (i.e., drive running at 90% speed versus 70% speed or upstream transformer 300 kVA versus 750 kVA). I would be most careful of over-assuming harmonic currents on a model costing you much more money than necessary. 19 Your questions answered: Harmonics solutions for water and wastewater Question: Can you clarify the difference between I1 and Il? Back to TOC Answer: I1 is the fundamental current (i.e., 60 Hz or 50 Hz) right now for instantaneous measurements — IL is used only for the TDD calculation and is determined at the maximum demand (for example, 15-minute window) during a previous month/year, etc. Since the maximum value for IL is usually higher, TDD is usually lower. The numerator is usually taken as a “high average” value of harmonic current. Question: Do underutilized transformers also contribute to harmonics? Answer: Very low levels of 2nd, 3rd, 4th harmonics show up on the FFT of a transformer (primary) because the magnetizing branch requires these. However, it is almost always there in the background but it is only noticeable when the transformer is lightly loaded. Question: What are the best options for controlling harmonics generated by EC Motors? Answer: EC motors usually have VERY high THD because they often don’t use line reactors — typical numbers may be 80% ITHD. The first step may be a 5% reactor, and then the rest of the solutions are all the same for EC motors versus drives (filters, phase shifting, etc.). Question: Do triplen harmonics only occur in single-phase loads? Answer: Yes, triplen harmonics only appear for three-phase systems with single-phase loads. HOWEVER, you can have 3rd harmonic currents that aren’t actually triplen harmonics flowing between phases. An example is SCR heaters connected L-L on a 480V 20 Your questions answered: Harmonics solutions for water and wastewater system. You will have significant 3rd, 5th, 7th, etc. flowing out one phase and back an- Back to TOC other (not on the neutral). Triplens are considered triplen when they are on each phase to and from a single-phase load and flow back together (in phase) on the neutral. Question: You had mentioned that overheating equipment for a small period of time may not be bad. Are there situations where harmonics could cause overheating to cycle (in other words, the equipment gets hot, then cools, then gets hot again)? Should we be concerned for situations such as this? Answer: Certainly cycling of heating is bad for electrical equipment (depends on how long and the insulation type, etc.). The other concern I should have mentioned is that short-term harmonics may cause a single failure or issue even if they are only there for a few cycles or seconds — like a soft start that creates very high ITHD during startup or harmonic current during transformer inrush. This may excite resonance with capacitors, for example. Question: What were the changes from IEEE 519 2014 to 2022? Answer: The only major change was around DERs (distributed energy resources). The new standard states that if you have DERs and the combined site rated generation is > 10% of the annual average load demand, you must apply current limits from a standard with an applicable scope such as IEEE Std 1547 or IEEE Std 2800, otherwise, apply the limits of IEEE 519 (for < 10%). Question: Is it better for the utility to use a delta-wye transformer? 21 Your questions answered: Harmonics solutions for water and wastewater Answer: In general, yes, for harmonics. You can circulate 3rd in the delta, but it doesn’t Back to TOC benefit the end user as far as that goes. In general, harmonic reduction from transformers is only seen upstream of the transformer. The only exception to this is downstream harmonics are affected by the impedance of the transformer and would be reduced throughout the system (i.e., not allowed to flow or choked like a line reactor), but for the winding type of any transformer, it doesn’t really affect the downstream harmonics. Question: What is the effect of network MVA capacity (PCC)? Answer: MVA capacity simply acts like an impedance, and the lower the MVA, the higher the impedance. Therefore, smaller harmonic loads affect the voltage distortion more on a weak source or lower MVA system. An easy way to think about it is if you put a 30 HP drive on a 30 kVA transformer and measured the downstream voltage distortion, you would get pretty high voltage distortion compared to that same 30 HP drive on a 3 MVA transformer — light load on a big transformer is not noticeable from a harmonic standpoint. Question: For motor protection, on which side of the drive should the CT and PT be installed? Answer: The drive will have motor protection programming built in, and generally you don’t need external CTs like you would on a normal motor protector. But if it did require external CTs, it would be on the output because the drive decouples the motor from the source at the DC link. Question: For small motor, does 18-pulse drive avoid line reactors? 22 Your questions answered: Harmonics solutions for water and wastewater Back to TOC Answer: 18 pulse on very small drives may not be cost effective, but if you do apply an 18-pulse drive on any motor, they usually use an internal reactor as well to gain that additional impedance benefit. In general, though, if you use 18 pulse, you don’t need an additional line reactor. Question: What’s a good “time span” that can cause issues with sensitive equipment? Answer: The IEEE 519 standard, for 95th percentile of measurements (i.e., most of the normal time), you would follow the tables directly in the IEEE 519. For short-term 10 minutes or less, you can exceed the tables as much as 1.5X, and for 3 seconds or less, you can exceed the tables by as much as 2X. Question: Can harmonics generated by one VFD have an effect on the other VFD on the same power source bus? Answer: It is possible that the drive itself can cause enough current distortion to make the voltage in front of it distorted enough to cause issues, but it is very unlikely on a 1:1 basis without other drives or influences. In fact, you can put a 10% reactor in front of a drive and cause a very distorted square wave voltage, but if you think about it, the first thing you do in the drive is convert to DC so a square wave isn’t as big of a deal to convert. If, however, the impedance is so high that the voltage has multiple zero crossings or other waveshape distortions that make it difficult for the diodes to convert the voltage to DC, then the drive may misoperate. 23 Your questions answered: Harmonics solutions for water and wastewater Question: Can you explain why harmonics increase vibration on motor? Back to TOC Answer: Current harmonics follow a pattern positive sequence, negative sequence, zero sequence — 1st (+), 2nd (-), 3rd (0), 4th(+), 5th (-), 6th (0), etc. Generally speaking, negative sequence harmonics cause vibrations in motors so if you have current harmonics causing 2nd, 5th, etc. harmonic voltages, then these vibrations can result from the 60 Hz pushing the motor forward and the negative sequence harmonics resisting that forward motion, causing heat and vibration. Physical vibrations often oscillate at 2X the electrical harmonic frequency — i.e., 5th harmonic would vibrate at 600 Hz or 2 X 300 Hz. Question: Could you clarify the impact of line impedance on the reflected noises and the net distortions? Answer: Source impedance is in series with the harmonic currents generated by the load. Pulling harmonic current through an impedance, by Ohm’s Law, will create a distorted voltage at the same frequency. Therefore, the higher the impedance, the more the voltage distortion. A large transformer has a lower impedance than a small transformer (even if they are the same %Z) by the proportion of the kVA sizes. As far as the effect of that impedance on how much current can be drawn through it, the higher the impedance, the lower the amount of harmonic current the drive or other load is “allowed” to draw or “able” to draw through that impedance. We use the term “choke” because the impedance/reactor/reactance essentially chokes out the current (like squeezing a water hose) and doesn’t allow as much current to flow. Question: What is the trending solution for reducing harmonics at the MV or utility-scale systems? 24 Your questions answered: Harmonics solutions for water and wastewater Answer: For MV systems, for a single drive, 24 pulse systems are the most typical solu- Back to TOC tion. For large systems with multiple sources of harmonics, either fixed, switched multistage filters (capacitor/inductor) are used or for very dynamic MV systems, static var compensators (SVC) are used. They typically have a fixed reactor and switched capacitor in the form of harmonic filters switched with SCR’s. Question: What’s your opinion on relaxing the VTHD from 5% to 8% in IEEE 519? Wouldn’t this extend the harmonic influence to other industrial plants connected to the utility? Answer: I have seen systems that are good at 5, good at 8 and good at 15% VTHD, but I’ve also seen systems that are problematic at 2.5% VTHD, so it starts with what does the load like/see. As far as the neighbors, the IEEE 519 is only about the neighbors and not about how you affect yourself. That said, yes, the influence of a lot of background VTHD will potentially cause your system to have problems that it wouldn’t without them, but that may be more arbitrary than specific. You still need to understand at what level your equipment has problems if you can even determine that (which is hard to do). Question: How does one model a system to determine if harmonics may be a problem? Answer: SKM, CYME and other programs model harmonic currents on a power system and predict harmonic voltage distortion and resonance issues. The way it is done is that you model the impedances at 60 Hz and then “inject” harmonic loads either as individual loads or groups of loads (VFDs, for example) at a downstream bus. Once the model is complete, you run scenarios where the impedance of the power system is 25 Your questions answered: Harmonics solutions for water and wastewater dynamically changed by the frequency (i.e., starts at 60 Hz, then 120 Hz, then 180 Hz, Back to TOC etc.), and then the harmonic currents from the loads are pushed back up through those impedances to calculate the associated voltage drop at that frequency. Once all of the dynamic load flows are done, the RMS totals for current and voltage at each bus are calculated and displayed. For variations in load, source impedance (changing to generator source, for example) or adding capacitors that may cause resonance, new cases are done and compared to the base case. Then, you can apply filters, phase shifting or other solutions and compare the VTHD and ITHD at every bus/branch. Question: Don’t a lot of utilities use delta-wye transformers? Doesn’t that help keep it off the utility? Answer: You can circulate 3rd in the delta on a delta-wye transformer, and that will keep the 3rd, 9th, etc. harmonics from going back on the utility, but the positive and negative sequence harmonics (5th, 7th, 11th, 13th, etc.) will go right through the transformer by the turns ratio and at the same percentage THD on the secondary and primary. In addition, that doesn’t really help you as a user, and it doesn’t guarantee compliance with IEEE 519. In general, harmonic reduction from transformers is only seen upstream of the transformer (in this case, the only benefit would be triplens). Remember that current MUST flow in a loop, and harmonics DO NOT go to ground — they flow out on phase A, for example, and back on B and C. So they go out into the utility system only to return on the other phases, right through the transformer. Gary Cohen Gary Cohen is senior editor and product manager at CFE Media and Technology. 26 Take an In-Depth Exploration into Cummins State-of-the-Art Microgrid Testing Facility I n 2022, Cummins proudly celebrated the opening of a new microgrid laboratory, the Power Integration Center (PIC) at their campus in Fridley, MN. The PIC is one of the largest and most configurable microgrid testing facilities in the world. Regardless of your power system needs (hypothetical or planned), this marvel of a facility is built to test those possibilities in a zero-risk environment. Since its opening, the PIC’s team of engineers have hosted hundreds of tours and simulated a myriad of testing scenarios in collaboration with customers and partners from various markets. Today they’re pulling back the curtain and providing all with an in-depth look into the facility. Take an In-Depth Exploration into Cummins State-of-the-Art Microgrid “This virtual tour is the most detailed look Cummins has provided of the PIC. With it, Back to TOC we’ll be able to demonstrate the capabilities of the facility to customers and partners who can’t make the trip to Fridley and provide education about microgrids to a wider audience,” said Corey Bergendahl, Engineering Manager for the PIC. The four main components of the PIC include: Outdoor Testing Pads The largest part of the lab’s 20,000 square foot design (about four times the area of a basketball court), the outdoor pads provide the dedicated space needed to test any source or load that can be integrated into a microgrid (ex. Gensets, Battery Energy Storage, Hydrogen Fuel Cells and Electrolyzers, EV Chargers, and more). The outdoor testing pads are comprised of: • Five 500 kW Testing Pads • Two 2000 kW Testing Pads • Two 500 kW RLC Load Banks Electrical Mezzanine This area boasts several unique features including: Utility Distribution Substation • Step-Down transformer – 13.8 kV to 480 V 28 Take an In-Depth Exploration into Cummins State-of-the-Art Microgrid • Two 1 MW utility feeds Back to TOC • Distribution switchgear Solar Inverter Testing (Photovoltaic/PV) • 400 kW rooftop solar array • 105 kW DC simulation power supply • Programmable weather scenarios Bi-Directional Inverter Testing (Battery Energy Storage/BESS) • 120 kW battery simulator • Emulates different battery chemistries and size capabilities • Allows you to quickly adjust the state-of-charge for the virtual battery system Main Switchgear Room This room houses a 2 MW switchgear lineup that’s the primary working switchgear utilized for customer simulations within the lab. The switchgear is separated into three buses with tiebreakers in-between and a ring bus around the back allowing for the creation of multiple different power system topologies including: 29 Take an In-Depth Exploration into Cummins State-of-the-Art Microgrid • Isolated Bus Back to TOC • Common Bus • Single Transfer Pair • Dual Transfer Pair • Main-Tie-Main • Dual Transfer Pair with Tie Engineering Control Room The control room acts as the central nervous system for the whole facility. Signals from the sources, loads and connections are brought together for our team of engineers to conduct and visualize the extensive testing needed to evaluate solutions. As governmental regulations change, the cost of operations increases, inclement weather persists and power grid instability runs rampant, the need for reliable and efficient microgrid solutions is more prevalent than ever. The PIC is an answer to those needs and allows customers to thoroughly test solutions with zero operational risk. 30 Take an In-Depth Exploration into Cummins State-of-the-Art Microgrid “The needs of our customers are Back to TOC ever evolving and there’s a heightened focus on dependable, flexible, economically efficient microgrid solutions,” added Bergendahl. “The PIC is our dedication to powering a cleaner future. This facility allows us to lead our customers through their decarbonization journeys, directly tying into our own Destination Zero strategy.” Designed by Cummins Power Systems team of leading engineers and microgrid advisors, the PIC is a collaborative space for engineers, customers, technicians, sales members and microgrid enthusiasts to come together in the name of innovating for a greener future. For more information about the Cummins Power Integration Center (PIC), visit: Power Integration Center | Cummins Inc. 31 Your questions answered: Critical power: hospital electrical systems Back to TOC The Sept. 15, 2016, “Critical Power: Backup power systems” webcast presenters addressed questions not covered during the live event. D esigning hospital electrical systems is more demanding than for conventional commercial buildings because the stakes are so high. When specifying electrical distribution systems in hospitals, engineers must account for the facility’s size, flexibility needs, medical equipment and procedure types, essential (emergency) power needs, and safety requirements. They must design and coordinate electrical protection for all branches and the equipment fed by them. In addition, they must consider whether to apply isolated power systems. The Sept. 15, 2016, “Critical Power: Backup power systems” webcast presenters addressed questions not covered during the live event. The presenters are: • Danna Jensen, PE, LEED AP BD+C, vice president, ccrd, a WSP | Parsons Brinckerhoff Co., Dallas • Robert R. Jones Jr., PE, LEED AP, JBA Consulting Engineers, Las Vegas Q: Describe some typical issues that the local authority having jurisdiction (AHJ) wants corrected. Danna Jensen: The inspectors tend to look for things that are regularly missed, or new additions to the code. A list that I’ve assembled that are typically on the top of the list for items written up during an inspection include: 32 Your questions answered: Critical power: hospital electrical systems • Battery lights in anesthetizing locations Back to TOC • Battery light, life-safety light, and receptacle at automatic transfer switch (ATS) and generator locations • Bond between the normal and critical panelboards in electrical rooms • Patient care area receptacle testing (resistance, contact tension, and millivolt leakage). Q: Can renewable energy sources be integrated with the essential electrical system? Robert R. Jones Jr.: Possibly, but it may be cost-prohibitive. Renewable energy sources are not specifically listed as an acceptable source of power in NFPA 70: National Electrical Code (NEC) Article 517, but battery systems are. A renewable energy source could be used to charge the batteries. However, the demand and consumption requirements of a hospital would likely require a very large battery system. Batteries currently require a lot of physical space and are expensive to maintain. Q: Are there any additional considerations when using a natural gas genset versus a diesel genset for backup power? Jensen: There are two main considerations for using natural gas versus diesel. First, does your local authority consider natural gas as meeting the requirement for onsite storage of fuel (this is a requirement in NFPA 110: Standard for Emergency and Standby Power Systems and the number of hours depends on your facility classification, but typically not less than 24 hours). I have not found many jurisdictions that do. 33 Your questions answered: Critical power: hospital electrical systems Second, is the natural gas generator capable of being up and running and all loads connect- Back to TOC ed to it within 10 seconds? This is a requirement of NFPA 110 for Level 1 systems (which a hospital is classified as). Natural gas engines start slower than diesel and, depending on the size of the engine, may have trouble getting to the required ratings within 10 seconds. Q: Can mobile backup generators not on the premise still be deployed and used to power a hospital during an emergency? Jones: NEC Article 517 requires that a generator be located on the premises and sized to support the essential electrical system (EES) demand. Nothing precludes the installation of provisions to hook up a mobile generator in addition. Applications may include backup of the permanently installed generator due to failure/maintenance or supply of nonessential loads desired to maintain normal operations during an extended loss of utility. Q: What is a good demand factor you would suggest to use in addition to the NEC demand factors to keep generators sized well? Jensen: The demand factors must be used per NEC. There are specific demand factors that can be used for lighting and receptacles in a hospital (NFPA 70-T220.42), elevators (NFPA 70-T620.14), diagnostic equipment (NFPA 70-517.73(A)(2), and so on. You must collect historical data to use the demand calculations listed in NFPA 70-517.30(D). This can be done by compiling a database as shown in the presentation, or by metering the load on the transfer switches and using that data. Q: Which branch should a nurse call system be connected to, life safety or critical? 34 Your questions answered: Critical power: hospital electrical systems Jones: Nurse call systems should be connected to the critical branch. Refer to NEC Back to TOC Article 517.33(A)(5). Q: What about pharmacies? Do those fall under NFPA 99: Health Care Facilities Code? Jensen: It depends on their license. Most are designed to fall under USP 797 (or the newer version 800), however if they are not licensed under the hospital, they are not required to follow NFPA 99. If not, they can even be classified as “B” occupancy since there is not inpatient care provided. Q: You indicated that 36 outlets are required in new operating rooms. Does that mean 36 double-outlet receptacles? Jones: The receptacles provided to satisfy NEC Article 517.19(C) may be any combination of single, duplex, or both. Q: NEC Article 700 requires surge protection device (SPD) protection of all distribution equipment. Does this apply only to the life safety branch? Are SPDs required for critical or equipment somewhere else in the code? Jensen: Yes. The requirement for SPDs listed in NEC Article 700 applies only to the life safety branch because both NEC Article 517 and NFPA 99 state that the life safety branch of the EES shall meet the requirements of article 700 (NFPA 70-517.26 and NFPA 99-6.4.2.2.1.5). SPDs are not required for critical or equipment branches elsewhere in NFPA 99 or NFPA 70-517. 35 Your questions answered: Critical power: hospital electrical systems Q: Are special insulation re- Back to TOC quirements for isolated power THE WORLD IS READY FOR RENEWABLES. WE’LL MAKE SURE YOU’RE READY TOO. conductors still required? Jones: It would be a best practice to design the isolated power system with components to Distributed energy from the leader in power systems integration minimize leakage current from Discover reliable microgrid control at cummins.com line to ground. NEC Article 517.160(A)(6) Fine Print Note 2, which is explanatory only and not actual code, suggests minimizing branch circuit conductor length and the use of conductors with insulation properties of less than a 3.5 dielectric constant and resistance greater than 20,000 meg-ohms at 60°F. Type XHHW conductors are suggested over the use of THHN/THWN. Q: It is my understanding that the separation of emergency circuits begins at the transfer switch, not the up- ©2023 Cummins Inc. stream gear. 15051-Microgrid_Sustainability_Ad_8x10.75_v5.indd 1 4/27/23 9:52 AM 36 Your questions answered: Critical power: hospital electrical systems Jensen: The code does not distinguish one way or the other. However, it is inferred by Back to TOC the diagrams in the handbook and the wording in the text that the “branch” consists of all wiring and feeders, including the upstream overcurrent protective device (OCPD), which must be selectively coordinated. I also have run across many jurisdictions that consider the branch to start at the first OCPD supplying the transfer switch. Q: Nursing home and long-term care facilities require only two branches, correct? Jones: NEC Article 517.41(A) contains the requirements for the EES in nursing homes and limited care facilities. If the facility admits patients who may need to be sustained with life support equipment or performs surgical treatment requiring general anesthesia, an EES is required. The EES is comprised of the life safety branch and the critical branch. Q: Are you allowed to shed the equipment branch to serve a fire pump? Jensen: No. If your system is running as usual (meaning all designed engines are still operational), then all of the required systems must be connected and operational as well. This includes the automatically connected equipment branch. The only time load shed is permitted is if the load is optional to begin with, or you lose an engine or other catastrophe in which additional measures must be taken to keep as many systems operational as possible. Note however, when the fire pump is running and you have a fire in the facility, unless you have an intricate smoke control system, you will likely have a reduced load on the equipment branch b the air handling unit will de-energize upon sensing smoke in its return detector at the unit. Danna Jensen, PE, LEED AP BD+C, and Robert R. Jones Jr., PE, LEED AP 37 Why decarbonization, ESG initiatives are a bigger priority for building owners Back to TOC Decarbonization and ESG initiatives are a major focus for building owners and their tenants, but getting them access to the right data remains a hurdle. B uilding owners and tenants are emphasizing decarbonization more than ever as environmental, social and governance (ESG) initiatives are growing. They’re not only gaining attention for helping the environment, but also because they can help the bottom line. The need to save money and attract tenants is a big priority for building owners since the COVID-19 pandemic. Tenancy is down and they need to find a way to attract customers into their building. In a panel discussion at AHR Expo 2024 at McCormick Place in Chicago, the discussion on “The Future of Energy Management: ESG, Decarbonization, and Electrification” focused on where things currently stand and where they’re headed down the road. “Clients are looking for carbon savings,” said panel moderator Brad White, president of SES Consulting. “Building owners are willing to spend money on decarbonizing their buildings.” Stephanie Poole, a senior decarbonization engineer at SES Consulting, agreed, and noted the shift in emphasis. “It used to be about energy efficiency. Now it’s about decarbonization and we’re working on some very complex projects.” 38 Why decarbonization, ESG initiatives are a bigger priority for building owners Back to TOC She cited an example where a building owner that didn’t have a net zero plan was at risk of losing a valuable tenant, which would have cost them a great deal of money. So they reached out and developed a long-term plan to keep their tenant. This is not a one-off, Poole said. It’s happening more often as owners and compa- Left to right: Leon Wurfel, founder, Bueno; Lauren Scott, VP, marketing and sustainability, Intelligent Spaces Group at Acuity Brands; Stephanie Poole, senior decarbonization engineer at SES Consulting. Courtesy: Chris Vavra, CFE Media and Technology nies shift their priorities and emphasis. For panelist Leon Wurfel, the founder of Bueno Systems, the emphasis on building standards is nothing new in his native Australia. The National Australian Built Environment Rating System (NABERS) has been in effect for years and is required for all new buildings that are more than 1000 square meters and uses a rating system of 0 to 6 stars to help determine how energy-efficient buildings are. He said the system has, “Created a huge amount of opportunity and commercial potential,” noting there was a bit of vanity involved among owners and it helped get buy-in. 39 Why decarbonization, ESG initiatives are a bigger priority for building owners Lauren Scott, VP, marketing and sustainability at Acuity Brands, noted there has been Back to TOC a similar push in Europe and it has helped push technology much further than because there is an incentive in the form of penalties and falling behind in general. Getting the right data to the right people Decarbonization and ESG initiatives are only as good as the data being transmitted. For many building owners, that remains a big hurdle. “The number 1 thing is the quality of data,” Scott said. “Users need access to the right information. Try and find the tools for that measuring and monitoring is key.” She added that there is a labor shortage in general and the companies might be hiring some inexperienced to make sense of the data. This can be overcome with the right funding, but it won’t matter if a quick return on investment (ROI) can’t be shown. Wurfel agreed. “Operationalizing and managing is a challenge. It’s becoming more important as companies rely on the data coming from a building management system (BMS) and putting it into the ESG reporting. Maintaining data quality is important.” Poole said many don’t even know what they have to begin with. “It’s alarming how people don’t know what they have. No concept of what their systems are. That has been the hardest piece. Is your data accurate? Do you know where your systems are?” Have a good dashboard can help, but it depends on context. “Develop dashboards for the right people,” Poole said. “For operators the dashboards will be more complex. Ask each person what they want and make things easier.” Chris Vavra Chris Vavra is web content manager for CFE Media and Technology. 40 PODCAST: Brian Alessi on decarbonization strategies in building design D Back to TOC ecarbonization is often a top priority for new building or retrofit projects, however understanding an owner’s priorities and restrictions can create difficulties in implementing these strategies. Brian Alessi, the sustainability director for Henderson Engineers, gives the audience tips for approaching these conversations and creating building systems that are healthy, sustainable, and resilient. 41 Electrical & Power Thank you for visiting the Electrical & Power eBook! Content Archive 2023 Winter Edition 2023 Fall Edition 2023 Summer Edition 2023 Spring Edition If you have any questions or feedback about the contents in this eBook, please contact CFE Media at customerservice@cfemedia.com We would love to hear from you!
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )