Concrete Pour Work Plan Location - RBS Ramp Proposed Date - 06 Jan 2025 Duration Structure - Cross Passage (CP-01) 1 2 3 4 5 6 7 8 9 6.25 hrs Concrete Pour Volume Concrete Production Equipment 75 Cum/Hr Concrete Batching Plant Concrete Placing Equipment Static Pump - 1 Static Pump- 2 Concrete Transportation Equipments Transite Mixer Average Concrete Pouring Rate Time Cycle for Concrete transportation Distance Avg Speed Loading Transportation one way Slump test & Cubes sampling Waiting at Location Unloading time Return to plant Washing & Circulation Total Time Rounded off time/trip Qty/Hour/TM Peak Hourly Qty No. Of TM required Duration of Pour Pouring Sequence Site Layout (Plan) during Concrete Works 50 Cum 1.00 No. 1.00 No. 1.00 No. 4.00 Nos. 8.00 Cum/Hr 1.00 KM 20.00 KMPH 10.00 Mins 15.00 Mins 10.00 Mins 10.00 Mins 40.00 Mins 15.00 Mins 5.00 Mins 105.00 Mins 105.00 Mins 3.43 Cum 8.00 Cum 4.00 Nos 6.25 Hrs Down Line UP Line Static Pump 2 Tremie Pipe Static Pump 1 Launching Shaft TM Notes :1. Fix two pump , one in launching shaft and another one in front of CP-01 towrads down line. 2. Fix tremie pipe at launching shaft for lower concrete from surface to shaft ( in pump). 3. Concrete to be transfered from shaft to pouring location by pipe line from one pump to another pump. 4. Total 4 nos vibrators shall be fixed at shutter for vibrating . 5. First start concrete pouring from left side wall upto SPL towards Down Line by first TM. 6. After pouring of first TM , start pouring to right side wall upto SPL. 7. Once concrete pouring completed upto SPL at both side , start pouring for Overt . 8.The above steps shall be implemented to ensure that concrete pour is continuous & no cold joints are formed . 9.In case of delay in concrete supply, the pour from existing transit mixers shall be slowed down and poured at all faces of concrete to maintain continuity & avoid cold joints.