SAP C_S4PPM_2021 Exam Guide
www.ERPPrep.com
Get complete detail on C_S4PPM_2021 exam guide to crack SAP S/4HANA
Portfolio and Project Management. You can collect all information on
C_S4PPM_2021 tutorial, practice test, books, study material, exam questions,
and syllabus. Firm your knowledge on SAP S/4HANA Portfolio and Project
Management and get ready to crack C_S4PPM_2021 certification. Explore all
information on C_S4PPM_2021 exam with number of questions, passing
percentage and time duration to complete test.
SAP S/4HANA Portfolio and Project Management - C_S4PPM_2021
PDF
Introduction to SAP Certified Associate - SAP
S/4HANA Portfolio and Project Management
Exam
SAP S/4HANA Portfolio and Project Management (C_S4PPM_2021) preparation guide
helps you to get focused on exam. This guide also helps you to be on the
C_S4PPM_2021 exam track to get certified with a good score in the final exam.
C_S4PPM_2021 SAP S/4HANA Portfolio and Project
Management Exam Summary
● Exam Name: SAP Certified Associate - SAP S/4HANA Portfolio and Project
Management
● Exam Code: C_S4PPM_2021
● Level: Associate
● Exam Price: $541 (USD)
● Duration: 180 mins
● Number of Questions: 80
● Passing Score: 63%
● Reference Books: S4125 (SAP S/4HANA 2021)
● Schedule Exam: SAP Learning
S/4HANA PPM
1
SAP S/4HANA Portfolio and Project Management - C_S4PPM_2021
PDF
● Sample Questions: SAP S/4HANA Portfolio and Project Management
Certification Sample Question
● Recommended Practice: SAP S/4HANA Portfolio and Project Management
Certification Practice Exam
Exam Syllabus: C_S4PPM_2021 SAP Certified Associate SAP S/4HANA Portfolio and Project Management
Topic Areas
Portfolio Definition
Project Definition
Financial and Capacity
Planning
Topic Details, Courses, Books
Name, explain and configure Portfolio
structures
S4125 (SAP S/4HANA 2021)
Name, explain and configure Project structures
S4125 (SAP S/4HANA 2021)
Describe and configure financial planning and
capacity planning
S4125 (SAP S/4HANA 2021)
Explain and configure integration ot other
components in SAP Portfolio and Project
Integration and Shared Management
Components
S4125 (SAP S/4HANA 2021)
Project and Resource
Planning
Resource Management
Describe and configure project planning and
resource planning
S4125 (SAP S/4HANA 2021)
Name, explain and configure the resource
management process
S4125 (SAP S/4HANA 2021)
Weighting
> 12%
> 12%
> 12%
> 12%
8% - 12%
8% - 12%
Explain and configure the methods to evaluate
Questionnaires Scoring and analyze projects
8% - 12%
and Analytics
S4125 (SAP S/4HANA 2021)
S/4HANA PPM
2
SAP S/4HANA Portfolio and Project Management - C_S4PPM_2021
PDF
SAP C_S4PPM_2021 Certification Sample Questions and
Answers
To make you familiar with SAP S/4HANA Portfolio and Project Management
(C_S4PPM_2021) certification exam structure, we have prepared this sample question
set. We suggest you to try our Sample Questions for S/4HANA PPM C_S4PPM_2021
Certification to test your understanding of SAP C_S4PPM_2021 process with a real
SAP certification exam environment.
C_S4PPM_2021 SAP S/4HANA Portfolio and Project Management Sample
Questions:01. You want to add a report to the side panel of the item detail screen. The new
report should display the up-to-date financial planning values for the item. Which
reporting tool do you use?
Please choose the correct answer.
a) BI report
b) Business Context Viewer
c) Portfolio dashboard
d) Evaluation
02. Your customer wants to use scoring models for portfolio items. You have
verified that the Scoring Model service is assigned to the Portfolio Item object
type and have created a scoring model for items.
Which of the following steps are required to use the scoring model?
Please choose the correct answer.
a) Activate the master switch for user interface settings.
Add the scoring model to the item field in the field service configuration for buckets.
b) Activate the Scoring Model service in custom field configuration for items.
Add the scoring model to the item field in the field service configuration for buckets.
c) Activate the global default settings for scoring models.
Add the scoring model to the item field in the field service configuration for items.
d) Activate the Scoring Model service in custom field configuration for items.
Activate the master switch for user interface settings.
03. You can create a version of a portfolio item directly. What is another way to
create a version of the portfolio item?
Please choose the correct answer.
a) Create a what-if that contains the item.
b) Create a collection that contains the item.
c) Create an initiative that contains the item.
S/4HANA PPM
3
SAP S/4HANA Portfolio and Project Management - C_S4PPM_2021
PDF
d) Create a review that contains the item.
04. How are the capacity planning values of an item rolled up into a bucket?
There are 2 correct answers to this question.
a) Via a review
b) Directly
c) Via a collection
d) Via an initiative
05. What data can you synchronize between a portfolio item and a Project
Management project using Decision Flow Management?
Please choose the correct answer.
a) Metrics
b) Authorizations
c) Documents
d) Costs
06. You have defined the views, categories, and groups for capacity planning in
Customizing. What must you do to display these in capacity planning?
Please choose the correct answer.
a) Enable the field control for capacity categories.
b) Activate the capacity views in Metrics Management.
c) Link the item type to the capacity view.
d) Link the portfolio type to the capacity view.
07. Which objects in Portfolio Management support decision points?
Please choose the correct answer.
a) Portfolio items and initiatives
b) Portfolio items, buckets, and initiatives
c) Portfolio items and projects
d) Portfolio items, buckets, and collections
08. In Project Management, how can you create a project structure that includes
all of the following objects: phases, checklists, checklist items, tasks, and
subtasks?
There are 2 correct answers to this question.
a) Copy a project template during the creation process and include a reference to a
checklist template.
b) Copy a project template during the creation process and resolve checklist references.
c) Create the project definition, the phases, and include task templates.
S/4HANA PPM
4
SAP S/4HANA Portfolio and Project Management - C_S4PPM_2021
PDF
d) Create the project definition, the phases, a reference to a checklist template, and
resolve the checklist reference.
09. In an existing Project Management project, all objects have been released and
all subordinate tasks for the checklist items have been completed. Why does the
status change fail when you try to set the status of the checklist to Finish?
There are 2 correct answers to this question.
a) A checklist item is still open.
b) At least one of the tasks has been confirmed.
c) The checklist item result is set to Not Ok.
d) You are missing the authorization to change the project.
10. What is the purpose of item dependencies in Portfolio Management?
Please choose the correct answer.
a) To link items to Project Management projects
b) To identify time-critical situations
c) To link items to Project System projects
d) To automatically schedule items
Solutions:
QUESTION: 01- Answer: c
QUESTION: 02- Answer: b
QUESTION: 03- Answer: a
QUESTION: 04- Answer: b, d
QUESTION: 05- Answer: b
QUESTION: 06- Answer: d
QUESTION: 07- Answer: a
QUESTION: 08- Answer: b, d
QUESTION: 09- Answer: a, d
QUESTION: 10- Answer: b