MECHANIZATION OF TRACK MAINTENANCE
ON INDIAN RAILWAYS
STATUS AND ROADMAP AHEAD
MECHANIZATION OF TRACK MAINTENANCE
ON INDIAN RAILWAYS
IMPORTANT CURRENT REQUIREMENTS
• TRACK MONITORING
• DATA & ANALYSIS (use of AI-ML algorithms)
• OBJECTIVE DECISIONS BASED ON DATA
• TRACK MACHINES FOR MAINTENANCE
• OWNERSHIP & MAINTENANCE OF MACHINES
BY PROFESSIONALS
• SKILL UPGRADATION AND TRAINING
MECHANIZATION OF TRACK MAINTENANCE
• Historically Track was maintained manually with
beater packing
• First track machine was procured in 1963, which was
packing only 200 sleepers per effective hour.
•Now Indian Railway is using fleet of 1364 track
machines for different maintenance activities including
tamping machine with output of 2600 sleepers tamping
per effective hour.
•As a result manpower for P.Way maintenance per
track km has reduced from 3.55 in 2000 to 1.75 per km
in 2017-18 (Reduction of about 1,28,691 staff, 38%,
annual saving of wages about 7721 Cr.).
LEVERAGING TECHNOLOGY
NEW TECHNOLOGIES SELECTED
•Introduction of high output integrated multi-functional
machines
• Machines for daily spot attention UTV, MPT, RBMV
•Covering IR with Rail grind/milling
•Automated unloading of Ballast Hopper
•Mechanized renewal of short stretch
•DS of PF line
•Mechanized unloading of long rails
•Super puller for isolated welding of long rails
•Advance track inspection and monitoring systems
•Skill development – Simulator
•Light weight Small Track Machines
LONG RAIL HANDLING SYSTEMS
•
Long Rail Handling Systems
i. Rail Manipulator
ii. Rail Putler
iii. Rail Threader
This can ensure faster and safe unloading of longer rails with less staff
and (8 against 60 labour) time and avoid initial damage to rails. Will
improve safety.
PRESENT STATUS :
• For 5 long Rail Handling system orders placed by SECR
AUTOMATED BALLAST HOPPER UNLOADING SYSTEM
•
Automated Ballast unloading kits over
2,100 are in operation world over.
• These kits can be fitted on existing
Ballast Hoppers and can be operated
with remote control from safe distance.
• Gates go from open to close in 3
seconds
• Remote controller range is over 500
meters
• Oldest kits in service for more than 20
years
• Needs only 2 people to perform the
ballast unloading operation
PRESENT STATUS :
• A work of 120 hoppers are sanctioned
for trial over 3 Railways. Cost of fitting
120 wagons and also operating all 3
rakes for 2 years is about 18 crores.
MECHANIZATION OF SHORT PATCHES OF TRACK RENEWAL
•RAIL CUM ROAD JCB WITH ATTACHMENTS
PORTALS WITH CROWLERS
PRESENT STATUS :
•16 nos. of portals with crawlers proposed
SUPER PULLER WITH MOBILE FBWP
• Destressing and MFBW of isolated joints in long rails
Present Status :
• 16 No. sanctioned in the 2019-20 Budget
• Tenders under preparation
INTRODUCTION OF MMU
SPOT ATTENTION
OUTSOURCING OF MACHINES
(WET LEASING)
• Railway Board has issued instructions for wet
leasing
of Track Machines
– D.S. of Track with contractual machines
– Track renewal with contractor TRT/TLE
– Work site tamping on a construction project
PRESENT STATUS :
• NR has prepared bid documents
• Lead partner should be an Indian company
• Deliberations on the Contract modalities
INTEGRATED TRACK RECORDING CAR
(TRC)
1.
2.
3.
Indian Railways is having 3 nos. Contact type and 2 nos. contactless
Track Recording Cars for periodic measurement and recording track
parameters.
RDSO is operating and maintaining these cars for recording over IR on
programme basis.
Advance integrated Track Recording Cars used world over are planned
for further procurement with following features:
• Video Recording of Track Components
• Recording of clearances of fixed structure
• High Speed laser based track recordings
• Axle mounted sensors for monitoring oscillation
4.
TRC Data are uploaded on TMS to generate track maintenance input
charts for assigning specific jobs to maintenance units.
Present Status
Contract placed 3 nos. of TRCs RDSO.
• 4 such TRCs are sanctioned in RSP-2018-19.
TURNOUT MEASUREMENT SYSTEM
• The turnout measurement is a time consuming activity. The
mechanized measurement of turnout is need of the day.
• The turnout measurement system developed in Europe can
measure 100 turnouts in 8 hour shift during a day at speed of 5 to
60 kmph. Such machines are already working in Malaysia, Italy,
Belgium, Holland, Germany, France and Denmark and recently
ordered by Japan.
Present Status:
• 15 Nos. sanctioned RSP 2019-20
• Tenders are planned
SELF-PROPELLED USFD TESTING
•Self propelled vehicular USF testing is need of the day
Present Status:
• Tenders opened for 07 numbers
• Sanctions available for 12 More such SPURT Cars
• Efforts on for RCRV based SPURT Cars
NEW TECHNOLOGIES SELECTED
ZERO SPEED TRACK RECORDING CARS
The “zero speed” Track Recording Cars delivers continuous geometry
measurement even if the vehicle stops during the recording run. Visited one
such car worksite at ATM, Milan.
•
•
Presently : 10-15% unrecorded due to unscheduled stoppage and speed
below 20 kmph.
This system will ensure 100% recording of track.
OUTCOME :
(i) Four nos. sanctioned, Tenders are planned.
GROUND PENETRATION RADAR (GPR)
•
•
•
Presently, Ballast cleaning is planned on periodicity of 10 year or
500 GMT
Advance Railway systems used Ground Penetration Radar (GPR)
survey to assess fouling of ballast and ballast penetration in
formation for rational decision on ballast cleaning of track and
formation rehabilitation
The GPR survey is proposed to be adopted on Indian Railways also
for objectively identifying the stretches requiring deep screening.
Can be fixed on TRC for survey up to speed of 160 kmps.
•Clean
•Mostly
Clean
•Fouled
Ballast
•Subgrade
•
•
Work of Rs. 29 crore sanctioned, specifications prepared.
Bids are being invited by RDSO.
AUTOMATED TRACK INSPECTION
1. Presently manual inspection of track is carried out for
condition monitoring of track components.
2. World over video recording of track components through
high resolution and high speed camera to identify track
component defects is used.
3. IR planning to fix such system on high speed LHB OMS
coaches in each Zonal Railway for inspection to reduce
reliance on human inspection to improve safety.
Present status :
• 16 nos. sanctioned in RSP 2018-19
• Bids are being invited by RDSO.
TGMS TROLLEYS FOR DESGIN MODE TAMPING
• To avoid measuring run by tamping machines or manual measurement.
• Portable Track Geometry Measuring System (TGMS) is used to record
track parameter without traffic block to improve utilization of blocks.
• TGMS data can be directly fed to tamping machine as its input data for
tamping.
• This improves productivity of tamping machine by 20-25% besides
quality of work. TGI values improved substantially.
Present Status
• Trials completed. Railway directed to go for service contracts as
required.
DATA RECORDING PROCESSOR (DRP)
• The quality of track parameter achieved by the tamping machines and
machines parameters during tamping can be automatically
documented in DRP (Data Recording Processor) during the working of
machine avoiding manual recording. .
• The following parameters can be recorded by using this configuration.
i. Cant.
vi. Squeezing pressure right
ii. Twist
vii. Tamping depth
iii. Versine
viii. Lifting value (in mm) of L.H. Rail
iv. Squeezing time ix. Lifting value (in mm) of R.H. Rail
v. Squeezing pressure left.
• It will avoid post tamping measuring run or manual recording.
Present Status :
• Specifications of Track Machines have been revised to include DRP
system in Indian Railways.
TURNOUT MEASUREMENT SYSTEM
• Maintenance of turnout is an important activity.
• Turnout measurement is time consuming activity. The mechanized
measurement of turnouts is need of the day.
• Turnout measurement systems on track and off track have been
developed world over.
Present Status:
•16 Nos. sanctioned in RSP 2019-20
• Tender Documents under preparation
PORTABLE TRACK GEOMETRY
MEASUREMENT SYSTEM
•
Presently track parameters are measured manually
•
Portable trolleys are used world over to automatically
record track geometry parameters to reduce reliance on
manual inspection.
•
The track parameters can be recorded at speed of 5 kmph.
Data can be transferred to TMS for run over run analysis.
•
One trolley procured. Draft Specifications uploaded by
RDSO seeking comments from stake holders for regular
adoption over Indian Railways.
OSCILLATION MEASUREMENT SYSTEM (OMS)
•
Measurement of vertical and lateral acceleration is
done using accelerometer to assess running quality of
track.
•
Presently OMS recording is done on different coaches
made available every month. Due to variation in
vehicle oscillation characteristics run over run analysis
of track quality is not possible.
•
Provision of dedicated coaches for OMS recording of
track is under process to facilitate run over run
comparison
of
OMS
data
to
assess
improvement/deterioration of track quality.
SKILL DEVELOPMENT
3X- DYNAMIC TAMPER SIMULATOR
1. Indian Railway Track Machines Training Centre (IRTMTC) is located at
Allahabad for training of Track Machine Operators, Technicians, officers and
P.Way supervisors is now Centralized Training Institute under control of
IRICEN, PUNE.
2. A leading global manufacturer has installed a 3D damping simulator costing
about ₹ 5 crores for HOT-3-X Tamping Machine at IRTMTC at no cost to
Railway.
3. Such simulator is available only in Japan, Malaysia, Germany and Linz
besides IR.
SKILL DEVELOPMENT
TURNOUT TAMPING SIMULATOR
Plasser and Theurer administration has
agreed to provide 4S- Simulators for turnout
tamping at IRTMTC, ALD at no cost to Railways
AXLE BOX ACCELEROMETER
• At present periodic monitoring of track is being done through
Oscillation Monitoring System (OMS)/Track Recording Car
(TRC).
• Axle Box level Accelerometer will facilitate daily monitoring of
track with daily alerts to maintenance staff for locations
requiring urgent attention.
• This will facilitate early attention of defect in track before it goes
to unsafe level.
PRESENT STATUS :
• 40 nos. of such system has been sanctioned in 2018-19 for providing on 40 rakes
of fastest trains on golden quadrilateral and diagonals.
PLSSER
& THEURER&PLANT
VISIT AT
LINZ
TRACK
INSPECTION
MONITORING
SYSTEM
As the Indian Railway is planning to raise the speed of
passenger and freight trains in time to come, the track
Inspection and monitoring system is planned as indicated
below to reduce reliance on human interface :
Periodical inspection by RDSO :
i.
Integrated Track Geometry Monitoring System
(ITGMS),
with
facility
of
component
monitoring, axle box acceleration and
clearance monitoring system up to zero
speeds.
ii.
Ground Penetration Radar (GPR) system for
ballast bed & formation monitoring.
PROPOSED
TRACK INSPECTION
& MONITORING
PLSSER
& THEURER
PLANT VISIT
AT LINZ
SYSTEM
Intermediate Inspections by Zonal Railways :
i.
Dedicated LHB Coaches for Oscillation Monitoring
System (OMS) and Track component monitoring system
with machine vision.
ii. Vehicular USFD testing Cars (SPURT Cars) for each
Railway.
iii. Self-propelled Integrated turnout measurement system.
PROPOSED
TRACK
INSPECTION
& MONITORING
PLSSER &
THEURER
PLANT
VISIT AT SYSTEM
LINZ
Continuous daily monitoring of track :
Spot attention : Axle box mounted unattended accelerometers on
one axle of fastest moving train rakes to generate maintenance alerts
on daily basis.
i. Geometry Measurement : Track Geometry Measurement
(TGM) trolleys for measurement of plain track and turnouts
at required locations.
ii. Broken Rail Detection System :
a.
b.
Ultrasonic Broken Rail Detection System
(UBRD) : South African Technology under trial
in NCR, NR.
Rail Fracture and Intrusion Detection System : Being installed
in 80 km length in NCR for trial purpose.
iv. Flood Level Monitoring System : 114 systems installed.
v. Bank Slip and vulnerable location monitoring : Under trials at 2
locations
vi. Continuous Scour Monitoring at Bridge Foundation :
4 installed on trial in NFR, SR being installed in NR, CR also.
NEW TECHNOLOGIES SELECTED
LIGHT WEIGHT SMALL TRACK MACHINES
(Light Weight Off track
tamping)
(Clamp)
(Light weight abrasive Cutter)
(Battery operated light
weight Rail Drilling Machine )
IR is having indigenously developed machines taking longer time for activities.
OUTCOME :
RDSO is developing specifications and vendor list for light weight machines.
Thank You
TURNOUT MEASUREMENT SYSTEM
• Maintenance of turnout is an important activity.
• Turnout measurement is time consuming activity. The mechanized
measurement of turnouts is need of the day.
• Turnout measurement systems on track and off track have been
developed world over.
• Mobile turnout measurement trolley has been tried over IR and
specifications are under finalisation by RDSO and trials will be
conducted on WR in the second week of November, 2018.
•
AUTOMATED BALLAST HOPPER UNLOADING SYSTEM
•
Automated Ballast unloading kits over
2,100 are in operation world over.
•
These kits can be fitted on existing Ballast
Hoppers and can be operated with remote
control from safe distance.
•
Gates go from open to close in 3 seconds
•
Remote controller range is over 500 meters
•
Oldest kits in service for more than 20
years
•
Needs only 2 people to perform the ballast
unloading operation
•
A work of 120 hoppers is to be sanctioned
by NR for trial over 3 Railways. Cost of
fitting 120 wagons and also operating all 3
rakes for 2 years is about 18 crores.
BALLAST CLEANING MACHINE (BCM)
BALLAST REGULATING MACHINE (BRM)
DYNAMIC TRACK STABILIZER (DTS)
POINTS AND CROSSING TAMPER (PCT 4S)
HIGH OUTPUT TAMPER (HOT-3X)
HIGH OUTPUT TAMPER (HOT-CSM)
MUCK DISPOSAL UNIT (MDU)
MULTI PURPOSE TAMPER (MPT)
RAIL GRINDING MACHINE (RGM)
SHOULDER BALLAST CLEANING MACHINE (SBCM)
UTILITY VEHICLE (UTV)
TRACK RELAYING TRAIN (TRT)
TRACK LAYING EQUIPMENT (TLE/PQRS)
WORKSITE TAMPER
PCCM (T-28)
RAIL THREADER
RBMV
SATELLITE DEPOT AT TRICHI (SR)
•To be provided one for each Division
•Approximate Cost = Rs. 5 Cr with all T&P
•Work can be executed chargeable to track renewals (LSWP) in stages
and provisions in construction projects for track machine maintenance
facilities in that area.