PROJECT MANAGEMENT POM500 SUMMATIVE ASSESSMENT APRIL 2024 NAME: NTSWAKI SURNAME: LETSELEHA STUDENT NUMBER: 24422954 SUBJECT NAME: PROJECT MANAGEMENT 500 SUBJECT CODE: POM500 DATE:  22 APRIL 2024 Question 1 Risk ID Risk Description Risk 01 Environmental impact and displacement of local community Risk 02 Engineering challenges Impact Description Flooding of large areas of land, loss of biodiversity, and displacement of local communities leading to social unrest and legal challenges. Significant engineering challenges such as digging deep into the riverbed to create a solid foundation for the dam wall, leading to potential delays, cost overruns, and safety hazards. Likelihoo d High Medium Impact Rating Responsible Person High Environmental Compliance Officer High Project Engineer Risk 03 Risk 04 Resource Availability Insufficient skilled labor and resources available locally, leading to recruitment challenges and delays. Political instability Potential for political disputes over ownership and control of the dam, leading to project delays, uncertainty, and increased security risks. Human Resources Manager Medium Low High High Project Manager Question 2 2.1.1 A1 0+5=5 2.1.2 C1 12+3=13 2.1.3 D1=5 2.1.4 E1 =20 2.1.5 E2=25 2.1.6 F1=25 2.1.7 F2=27 2.1.8 Critical path = path 1 A, B, C, F and PATH 2 A, D, E, F Activity Duration ES EF LS LF Float A 5 0 5 0 5 0 B 7 5 12 10 17 5 C 3 12 13 17 20 5 D 15 5 20 5 20 0 E 5 20 25 20 25 0 F 2 25 27 25 27 0 Activity Preceding Durati on A Start 5 B A 7 C B 3 D A 15 E A,D 5 F E 2 2.1.9 Critical path duration= path 1 A, B, C, F =5+7+3+2=17 Path 2 A, D, E, F = 5+15+5+2=27 The longest path is path 2, which is the critical path of the project 27 days (about 4 weeks) which equals 4 weeks. 2.2 Annexure A Cash Flow Template Brought forward Income Total available Expenses Rental fee Labour Materials Total Expenses Closing balance June July August September October Novembe r 0 (140 000) (390 000) (305 000) (220 000) (40 000) 0 (140 000) 450 000 60 000 450 000 145 000 450 000 230 000 720 000 680 000 140 000 110 000 95 000 110 000 95 000 110 000 110 000 140 000 250 000 160 000 365 000 160 000 365 000 160 000 270 000 160 000 160 000 (140 000) (390 000) (305 000) (220 000) (40 000) 520 000 140 000 The cash flow balance at the end of November shows profit of R520 000 but the project cash flow for the previous months end with negative balance until October. This means funding would be required to be organised in future. Question 3 Project Scope Statement Submitted by :Ntswaki Letseleha Current Date :22/04/2024 Contact email :ntswaki.letseleha@gmail.com Project Name :Construction of new manufacturing facility Contact Phone :0747241966 Project Name Project Code :0021 Classification : New construction Version :1,0 Status :Draft Scope Inclusion What Business or technical need will be filled by this project? To address our critical business need for expanding manufacturing capabilities to accommodate growing market demand. Expand manufacturing capabilities at least by 30% to meet the growing demand for our product. This will allow the company to attract new market opportunities. To increase current production facility in order to explore new opportunities. To increase operational efficiency by 12% through improved workflows and the implementation of advanced equipment and assembly lines. This will reduce production costs and improve product quality. To enhance production output and operational efficiency What end-user’s requirement will be addresses? The design will prioritize safety, adhering to all relevant regulations and incorporating comprehensive safety training for employees. The facility will support increase production through advanced equipment and assembly lines. The layout will optimize production processes, minimizing material handling and maximizing worker productivity. Safety will be paramount, adhering to all relevant building codes and safety regulations. The facility will incorporate comprehensive safety training programs for all employees. The layout will optimize workflow, minimizing material and personnel movement. The facility will incorporate Eco-friendly construction practices and energy-efficient features. Employee amenities will be integrated, providing comfortable and accessible workspaces and accessible facilities. The design will prioritize energy efficiency. This could include features like natural lighting, LED fixtures, and potentially solar panels to reduce the environmental impact and operational costs. Employee well-being will be considered by including break rooms, locker facilities, and accessible restrooms that meet disability standards. What deliverable will be produced? Site preparation activities including land clearing, soil testing, and foundation construction. Completion of all site preparation activities ensuring a solid base for the new facility. Construction of a new manufacturing facility with a total floor area as specified on the drawings. The facility will include structural elements, electrical wiring, HVAC systems for temperature control, and a plumbing system for water supply and sanitation. Design and implementation of an optimized interior layout that accommodates production lines, storage areas, employee workspaces, and adheres to all safety regulations.. Optimized interior layout to accommodate production requirements and employee areas, adhering to safety standards. Implementation of energy-efficient building systems (potentially including solar panels). Completion of exterior landscaping. Scope Exclusion What Business or technical need will be filled by this project? Implementation of a new supply chain management system for material tracking. This will be a separate project undertaken by the IT department. Development of a comprehensive training program for operating the new production equipment. While the project team will provide basic familiarization training, in-depth operational training will be handled by the manufacturing department. Construction of a new transportation infrastructure for material distribution. This might be a future project depending on logistics needs. What end-user’s requirement will be addresses? Construction of a cafeteria facility. This may be considered in a future phase depending on budget and employee needs. Integration of advanced technologies beyond the scope of production equipment, such as robotics or automation. pen_spark What deliverable will be produced? Supply chain management system software and its implementation. Detailed employee training programs beyond basic familiarization. Construction of additional buildings beyond the new manufacturing facility.