Internal Use - Confidential Dell PowerMax Family Installation Guide for PowerMax 2500 June 2024 Rev. 7.0 Internal Use - Confidential Notes, cautions, and warnings NOTE: A NOTE indicates important information that helps you make better use of your product. CAUTION: A CAUTION indicates either potential damage to hardware or loss of data and tells you how to avoid the problem. WARNING: A WARNING indicates a potential for property damage, personal injury, or death. © 2022 - 2024 Dell Inc. or its subsidiaries. All rights reserved. Dell Technologies, Dell, and other trademarks are trademarks of Dell Inc. or its subsidiaries. Other trademarks may be trademarks of their respective owners. Internal Use - Confidential Contents Preface.........................................................................................................................................................................................5 Revision history.................................................................................................................................................................... 7 Chapter 1: Prerequisites................................................................................................................8 Site requirements................................................................................................................................................................ 8 Hardware acclimation times..............................................................................................................................................9 Required tools.......................................................................................................................................................................9 Chapter 2: Position PowerMax 2500 Bay...................................................................................... 11 Cabinet clearance............................................................................................................................................................... 11 Site floor load-bearing requirements.............................................................................................................................12 Preparing the bay for placement....................................................................................................................................12 Moving the bay into position........................................................................................................................................... 12 Removing packaging..........................................................................................................................................................17 Chapter 3: Connect AC Power......................................................................................................18 System AC power components...................................................................................................................................... 18 Connecting power components......................................................................................................................................18 Line cord and jumper configurations............................................................................................................................ 20 Basic PDU: PowerMax 2500 - single-phase power............................................................................................. 21 Intelligent PDU: PowerMax 2500 - single-phase power....................................................................................22 Basic PDU: PowerMax 2500 - three-phase power.............................................................................................24 Intelligent PDU: PowerMax 2500 - three-phase power.................................................................................... 26 Chapter 4: Best Practices for AC Power Connections.................................................................. 27 Best practices overview for AC power connections................................................................................................ 28 Selecting the proper AC power connection procedure........................................................................................... 29 Procedure A: Working with the customer electrician onsite.................................................................................. 30 Procedure A, Task 1: Customer electrician............................................................................................................ 31 Procedure A, Task 2: Dell Customer Engineer .................................................................................................... 32 Procedure A, Task 3: Customer electrician - PowerMax 2500........................................................................35 Procedure B: Verify and connect.................................................................................................................................. 36 Procedure C: Obtain customer verification................................................................................................................ 37 PDU labels........................................................................................................................................................................... 37 PDU label part number............................................................................................................................................... 37 Applying PDU labels.................................................................................................................................................... 37 AC power specifications - single-phase.......................................................................................................................39 AC power specifications - three-phase....................................................................................................................... 40 Chapter 5: Complete the Installation........................................................................................... 41 Grounding a single bay......................................................................................................................................................41 Connect customer network cables to the MSM ...................................................................................................... 42 Site information required................................................................................................................................................. 42 Site information required for eManagement-supported arrays....................................................................... 43 Power on the system....................................................................................................................................................... 44 Contents 3 Internal Use - Confidential Connect a laptop to the system.................................................................................................................................... 45 Configure remote support...............................................................................................................................................45 Validating the installation ............................................................................................................................................... 46 Validating the Firewall...................................................................................................................................................... 46 WFCT errors and recommended actions............................................................................................................... 47 Verify that the Windows Firewall is ON................................................................................................................. 49 Install the rear bay doors.................................................................................................................................................50 Appendix A: PowerMax File Installation Procedure...................................................................... 52 4 Contents Internal Use - Confidential Preface Purpose This document describes how to install a PowerMax 2500 array. Audience This document is intended for use by customer support engineers. Related documentation The following publications provide additional information: SolVe Online and SolVe Desktop SolVe provides links to customer service documentation and procedures for common tasks. Go to SolVe Online (https://solve.dell.com/solve/home), or download the SolVe Desktop tool from Dell Technologies Online Support (https://www.dell.com/support/home) and search for SolVe Desktop. From SolVe Online or SolVe Desktop, load the PowerMax and VMAX procedure generator. NOTE: Authenticate (authorize) the SolVe Desktop tool. After it is installed, familiarize yourself with the information under Help. Naming conventions The PowerMaxOS 10 release introduces new terms to standardize terminology across the Dell Power platforms. The new terms are currently used interchangeably in this document. The new terms are: Table 1. PowerMaxOS naming conventions PowerMax 2500 and PowerMax 8500 PowerMax 2000 and PowerMax 8000 Node Director Node Pair Engine DME DAE IB switch MIBE PowerMax File eNAS Typographical conventions Dell Technologies uses the following type style conventions in this document: Table 2. Typographical conventions used in this content Font Description Bold Used for names of interface elements Examples: Names of windows, dialog boxes, buttons, fields, tab names, key names, and menu paths (what the user selects or clicks) Italic Used for full titles of publications referenced in text Preface 5 Internal Use - Confidential Table 2. Typographical conventions used in this content (continued) Font Description Monospace Used for: ● System code ● System output, such as an error message or script ● Pathnames, filenames, prompts, and syntax ● Commands and options Monospace italic Used for variables Monospace bold Used for user input [] Square brackets enclose optional values. | A vertical bar indicates alternate selections. The bar means "or". {} Braces enclose content that the user must specify, such as x or y or z. ... Ellipses indicate nonessential information that is omitted from the example. Where to get help Support, product, and licensing information can be obtained as follows: Product information For documentation, release notes, software updates, or information about Dell Technologies products, go to Dell Technologies Online Support (https://www.dell.com/support/home). Technical support For technical support, go to Dell Technologies Online Support (https://www.dell.com/support/home). To open a service request, you must have a valid support agreement. Contact your Dell Technologies sales representative for details about obtaining a valid support agreement or with questions about your account. Your comments Your suggestions help improve the accuracy, organization, and overall quality of the documentation. Send your comments and feedback to: powermaxcontentfeedback@dell.com 6 Preface Internal Use - Confidential Revision history Table 3. Revision history Revision Description Date released 7.0 Removed outdated appendix on working with non-connected sites June 2024 6.0 Added information about the intelligent PDU October 2023 5.0 ● Removed SPS information incorrectly added in the last release ● Added instructions to not remove bezel when using a micro-HDMI connector April 2023 4.0 Added graphic for three-phase Wye connector April 2023 3.0 ● Updated WFCT installation ● Removed MFT registration ● Removed site information requirements for Cloud Mobility, PowerMax File and eVASA ● Updated instructions for configuring remote support ● Updated IP subnet default addresses December 2022 2.0 ● Removed PowerMax File installation section, replaced with link to Quick Start Guide ● Added micro-HDMI adapter requirement for crash carts September 2022 1.0 First release of the Dell PowerMax Family Installation Guide for PowerMax 2500 July 2022 Preface 7 Internal Use - Confidential 1 Prerequisites Confirm site requirements and check materials on site (kits and tools) before you begin the system installation. Before you begin: ● Complete the Pre-Hardware Install Checklist. To complete the checklist, go to the Symmetrix Procedure Generator and perform the steps in the Pre-Hardware Install Checklist. For information regarding the Symmetrix Procedure Generator, see: EPG Download (https://confluence.cec.lab.emc.com/display/ISG/EPG+Download). ● Review and gather the required site information that is listed in Site information required on page 42. NOTE: PowerMax arrays contain no customer installable parts. Only qualified Dell personnel or partners should move the system bays or perform procedures that install or upgrade the system. Topics: • • • Site requirements Hardware acclimation times Required tools Site requirements Confirm that the customer site meets all requirements before you begin the installation. The following table describes site requirements. See Dell PowerMax Family Site Planning Guide for PowerMax 2500 and PowerMax 8500 for additional information. Table 4. Site requirements Requirement Description Computer room PowerMax systems require a properly equipped computer room with controlled temperature and humidity, proper airflow and ventilation, proper power and grounding, system cable routing facilities, and fire equipment. Power PowerMax systems are fed power from two independent power sources, zone A and zone B. To assure fault tolerant power, customer-supplied AC power must be connected to independent power distribution units (PDUs). System acclimation PowerMax systems must be acclimated to the new environment before hardware is installed. To acclimate the system, place the unpacked system bays in the new operating environment. Open the front and the rear door of each bay and let the system stabilize up to four hours in dry conditions and up to sixteen hours in hot and humid conditions. Do not apply AC power until the system is acclimated to the local environment. See Hardware acclimation times on page 9. 8 Prerequisites Internal Use - Confidential Hardware acclimation times Units must acclimate to the operating environment before applying power. This requires the unpackaged system or component to reside in the operating environment for up to 16 hours in order to thermally stabilize and prevent condensation. Table 5. Hardware acclimation times Transit/storage environment Operating environment temperature Temperature Humidity - Nominal Nominal Nominal 68-72°F (20-22°C) 68-72°F (20-22°C) 40-55% RH 40-55% RH Cold Dry <86°F (30°C) 4 hours <68°F (20°C) <30% RH Cold Damp <86°F (30°C) 4 hours <68°F (20°C) ≥30% RH Hot Dry <86°F (30°C) 4 hours >72°F (22°C) <30% RH Hot Humid 30-45% RH <86°F (30°C) 4 hours Humid 45-60% RH <86°F (30°C) 8 hours Humid ≥60% RH <86°F (30°C) 16 hours <86°F (30°C) 16 hours >72°F (22°C) Unknown Acclimation time 0-1 hour ● If there are signs of condensation after the recommended acclimation time has passed, allow an additional 8 hours to stabilize. ● Systems and components must not experience changes in temperature and humidity that are likely to cause condensation to form on or in that system or component. Do not exceed the shipping and storage temperature gradient of 45°F/hr (25°C/hr). Required tools Tools are required to complete the installation. The following tools and the PDU label are attached at the bottom left at the rear of the rack. Table 6. Tools shipped with the system Description Part Number Customer PDU connection label 046-990-808 3/4" wrench, jam nut 034-000-164 Titan or Mohawk leveling feet adjustment wrench 034-000-165 Bring the following tools to all installations: Table 7. Required tools Tool Uses Screwdrivers - #2 Phillips and flat head Remove and install screws. Prerequisites 9 Internal Use - Confidential Table 7. Required tools (continued) Tool Uses Socket wrench with 7/16 and 9/16 socket Remove the cable retaining bar, if needed. Knife or wire cutter Cut strapping and remove packaging. Crash carts connect to the Control Station in the front of the engine using a micro-HDMI connector. A micro-HDMI adapter is required to connect the monitor to the Control Station. The type of adapter depends on the video input connector ports on the monitor. The adapter is usually one of the following: ● Micro-HDMI to HDMI ● Micro-HDMI to VGA ● Micro-HDMI to DisplayPort (DP) Ensure that the correct adapter is available before using a crash cart onsite. NOTE: To avoid a missing hardware error, thread the micro-HDMI adapter through the bezel by removing and then replacing the bezel. 10 Prerequisites Internal Use - Confidential 2 Position PowerMax 2500 Bay Positioning bays includes considering the layout and placement of the bays in the data center and placement on tiles. Each cabinet sits on four caster wheels to aid in positioning the bay. Once the bay is positioned it can be secured with optional mounting bolts. Topics: • • • • • Cabinet clearance Site floor load-bearing requirements Preparing the bay for placement Moving the bay into position Removing packaging Cabinet clearance This cabinet ventilates from front to back; you must provide adequate clearance to service and cool the system. Depending on component-specific connections within the cabinet, the available power cord length may be shorter than the 15-foot standard. Position PowerMax 2500 Bay 11 Internal Use - Confidential Site floor load-bearing requirements Install the cabinet in raised or non-raised floor environments capable of supporting at least 1,361kg (3,000 lbs.) per cabinet. Your system may weigh less, but requires extra floor support margin to accommodate equipment upgrades and/or reconfiguration. In a raised floor environment: ● 24 x 24 inch or (60 x 60 cm) heavy-duty, concrete filled steel floor tiles are recommended. ● Use only floor tiles and stringers rated to withstand: ○ concentrated loads of two casters or leveling feet, each weighing up to 1,000 lb (454 kg). ○ minimum static ultimate load of 3,000 lb (1,361 kg). ○ rolling loads of 1,000 (454) kg). On floor tiles that do not meet the 1,000 lb rolling load rating, use coverings such a plywood to protect floors during system roll. ● Position adjacent cabinets with no more than two casters or leveling feet on a single floor tile. ● Cutouts in 24 x 24 in tiles must be no more that 8 inches (20.3 cm) wide by 6 inches (15.3 cm) deep, and centered on the tiles, 9 inches (22.9 cm) from the front and rear and 8 inches (20.3 cm) from the sides. Since cutouts will weaken the tile, you can minimize deflection by adding pedestal mounts adjacent to the cutout; the number and placement of additional pedestal mounts relative to a cutout must be in accordance with the floor tile manufacture's recommendations. When positioning the cabinet, take care to avoid moving a caster into a floor tile cutout. Ensure that the combined weight of any other objects in the data center does not compromise the structural integrity of the raised floor and/or the subfloor (non-raised floor). We recommend that a certified data center design consultant inspect your site to ensure that the floor is capable of supporting the system and surrounding weight . Note that actual cabinet weight depends on your specific product configuration; you can calculate your total using the tools available at Dell Power Calculator. Preparing the bay for placement Before moving the system bay to its designated location: ● Remove the rear door from the system bay. ● If the line cords are routed overhead, switch the top covers for overhead routing. Use the AC-TOP-KIT, PowerMax NX TOP ROUTING KIT, SKU# 770-BEDS. Moving the bay into position About this task To position the bay, move it onto the designated tile. Align subfloor or overhead cables in the bay, lower and secure the leveling feet, and install the joining bar that secures the bay into position. NOTE: Systems with three-phase power include one AC main connector for each power zone. Systems with single-phase power use up to three AC main connectors for each power zone. You can route the power cables beneath the subfloor or overhead. See System AC power components on page 18 for more information. Steps 1. Move each bay to its preliminary position on the designated tile. Do one of the following: ● For line cords routed beneath the floor, route them up from the raised floor and connect them to the PDU power connection panel. See Basic PDU: PowerMax 2500 - three-phase power on page 24 for instructions. 12 Position PowerMax 2500 Bay Internal Use - Confidential Figure 1. Align power cables, subfloor routing ● a. For line cords that are routed overhead, loosen the wraps that secure the AC main cables and route them vertically along the rear flange. Use the velcro straps to bundle them together. b. Pull the cables through the top cover. Use the AC-TOP-KIT, PowerMax NX TOP ROUTING KIT, SKU# 770-BEDS. Position PowerMax 2500 Bay 13 Internal Use - Confidential Figure 2. Align power cables, overhead routing NOTE: Do not connect the system to external power in this step. To connect to external power, follow the instructions in Best Practices for AC Power Connections on page 27. 2. From the rear of the system, move the bay into final position over the tile, avoiding the tile cutout with any casters. 3. From the rear of the system, install the cable retaining bars (if previously removed) below the power cables. a. Locate the joining bar, shipped attached to the inside of the bay. b. Install the cable retainer bars. c. Align and install the joining bar at the front and rear of the bay. 14 Position PowerMax 2500 Bay Internal Use - Confidential Figure 3. Install cable retainer bars Position PowerMax 2500 Bay 15 Internal Use - Confidential 4. Lower the front and rear leveling feet to secure the position of the bay. Secure the bay by tightening the jam nut against the bottom of the bay. Figure 4. Lower the system bay 16 Position PowerMax 2500 Bay Internal Use - Confidential Removing packaging After positioning the bays, remove any packaging material from each bay. 1. Open the rear door and remove the pink foam packing material and any other packing material surrounding the components. 2. Close the rear door after you have confirmed all packing material is removed. Position PowerMax 2500 Bay 17 Internal Use - Confidential 3 Connect AC Power Connect AC power components to external power. Topics: • • • System AC power components Connecting power components Line cord and jumper configurations System AC power components Line cords are packaged separately and shipped with the system. The line cord model shipped depends on the country of install and whether the customer provides single-phase or three-phase power. Connect Dell AC power cords to system PDUs by using the line cord and jumper configurations described in Line cord and jumper configurations on page 20. Systems support single-phase or three-phase customer power configurations. You must connect each redundant AC input cable to the supplied Dell line cord which pertains to the AC input configuration. Three-phase components Systems with three-phase power include an integrated PDU with an AC line cord (P1) for each power zone. The Dell line cord model will be one of the following: Delta: ● AC-PCBL3DHH ● AC-PCBL3DHR Wye: ● ● ● ● AC-PC3YAFLA AC-PC3YAFLE AC-PCBL3YAG AC-PCBL3YL23P NOTE: Despite the differences in the connectors, the installation procedure is the same for Delta or Wye. Single-phase components Systems with single-phase power components include an integrated PDU component with two AC Main connectors per system for each power zone. The line cord model will be one of the following: ● ● ● ● AC-PW40U-US AC-PW40URUS AC-PW40UASTL AC-PW40UIEC3 Connecting power components Verify with the customer that their electrician has complied with power specifications for voltage levels and redundancy, as described in Best practices overview for AC power connections on page 28. If the customer cannot verify this, the system may shut down prematurely in the event of a site power issue. 18 Connect AC Power Internal Use - Confidential Before connecting power, make sure all of the PDU breakers for Zone A and Zone B are in the OFF position. When you are ready to connect AC power, follow the appropriate procedures in Best practices overview for AC power connections on page 28 for your scenario. Connect AC Power 19 Internal Use - Confidential Line cord and jumper configurations Related information Basic PDU: PowerMax 2500 - single-phase power on page 21 Intelligent PDU: PowerMax 2500 - single-phase power on page 22 Basic PDU: PowerMax 2500 - three-phase power on page 24 Intelligent PDU: PowerMax 2500 - three-phase power on page 26 20 Connect AC Power Internal Use - Confidential Basic PDU: PowerMax 2500 - single-phase power A separate line cord powers each node pair in a PowerMax 2500 system on single-phase power. Each line cord energizes the circuit breakers and corresponding PDU outlets. No jumpers are required. Table 8. PowerMax 2500 line cord configurations, single-phase System Components Line cord location Circuit breakers PDU outlets System 3 (upper) Node Pair 2/DME 2 P6 11-12 31-37 Node Pair 1/DME 1 P5 9-10 25-30 Node Pair 2/DME 2 P4 7-8 19-24 Node Pair 1/DME 1 P3 5-6 13-18 Node Pair 2/DME 2 P2 3-4 7-12 Node Pair 1/DME 1 P1 1-2 1-6 System 2 (middle) System 1 (lower) Figure 5. Customer input power outlet, single-phase Connect AC Power 21 Internal Use - Confidential Intelligent PDU: PowerMax 2500 - single-phase power A separate line cord powers each node pair in a PowerMax 2500 system on single-phase power. Each line cord energizes the circuit breakers and corresponding iPDU outlets. System 1 and System 2 Node Pair 1/DME1 require an initial line cord in iPDP1 and the Jumper PDP. When System 2 Node Pair 2/DME 2 or System 3 is added, remove the Jumper PDP and add iPDP2 for additional line cords. ● Jumper PDP: PN 2M5PK ● Single-phase iPDP: PN 9J8N0 CAUTION: Removing the Jumper PDP and adding the second iPDP results in a temporary loss of power for a single power zone for System 2 Node Pair 2/DME 2. CAUTION: You must run Health Check on System 2 before you remove the jumpers and add the line cords for System 3. See Three-phase power: Add a second line cord for System 3 on page 25 for instructions. Table 9. PowerMax 2500 line cord configurations, single-phase System Components Line cords and jumpers Circuit breakers PDU outlets System 3 (upper) Node Pair 2/DME 2 iPDP2-P3 11-12 24-27 9-10 20-23 7-8 16-19 5-6 12-15 3-4 7-11 1-2 1-6 (Remove Jumper PDP, replace with iPDP2) Node Pair 1/DME 1 iPDP2-P2 (Remove Jumper PDP, replace with iPDP2) System 2 (middle) Node Pair 2/DME 2 iPDP2-P1 (Remove Jumper PDP, replace with iPDP2) Node Pair 1/DME 1 iPDP1-P3 Jumper PDP System 1 (lower) Node Pair 2/DME 2 iPDP1-P2 Jumper PDP Node Pair 1/DME 1 iPDP1-P1 Jumper PDP 22 Connect AC Power Internal Use - Confidential Table 10. iPDP and Jumper PDP iPDP locations iPDP Jumper PDP Figure 7. iPDP, single-phase Figure 8. Jumper PDP Figure 6. Location of iPDP-1 and iPDP-2 Connect AC Power 23 Internal Use - Confidential Basic PDU: PowerMax 2500 - three-phase power On three-phase power, System 1 and System 2 require an initial line cord in outlet P1 and a power jumper from J1 to P2. When System 3 is added, remove the jumper and add a second line cord in P2. ● Three-phase DELTA jumper: PN 038-004-435 ● Three-phase WYE jumper: PN 038-004-481 CAUTION: Removing the jumper and adding the second line cord for System 3 results in a temporary loss of power for a single power zone for System 2 Node Pair 2/DME 2. CAUTION: You must run Health Check on System 2 before you remove the jumpers and add the line cords for System 3. See Three-phase power: Add a second line cord for System 3 on page 25 for instructions. Table 11. PowerMax 2500 line cord configurations, three-phase System Components Line cord and jumper location Circuit breakers PDU outlets System 3 (upper) Node Pair 2/DME 2 P2 9-12 25-37 Node Pair 1/DME 1 (Remove jumper and add P2 line cord, if needed) Node Pair 2/DME 2 P1 5-8 13-24 Node Pair 1/DME 1 J1<>P2 Node Pair 2/DME 2 P1 1-4 1-12 Node Pair 1/DME 1 J1<>P2 System 2 (middle) System 1 (lower) Table 12. Customer input power outlets, three-phase Customer input power outlets, three-phase Figure 9. Customer input power outlet, three-phase Delta 24 Connect AC Power Figure 10. Customer input power outlet, three-phase Wye Internal Use - Confidential Three-phase power: Add a second line cord for System 3 Prerequisites Have the following items available before you begin: ● Two three-phase Dell AC line cords. (Dell PDU to customer power cable, for PDU-B and PDU-A.) ● Two energized redundant customer PDU power cables near the rack. Steps 1. Run Health Check on System 2 and ensure it runs without errors. If there are errors, fix them before proceeding. 2. Open PDU-B CB 7 and CB 8. (Outlets 19-24.) PDU-B circuit breakers outlets 19-24 lose power. PDU-A is powering System 2 Engine 2 and DAE 2. 3. Remove the J1<>P2 jumper on PDU-B. 4. Connect one end of a new Dell line cord to PDU-B P2. Connect the other end to the customer's AC power cable. 5. Close PDU-B CB 7 and CB 8. 6. Run Health Check on System 2 again, ensuring it runs without errors. If there are errors, fix them before proceeding to PDU-A. 7. Open PDU-A CB 7 and CB 8. (Outlets 19-24.) PDU-A circuit breakers outlets 19-24 lose power. PDU-B is powering System 2 Engine 2 and DAE 2. 8. Remove the J1<>P2 jumper on PDU-A. 9. Connect one end of the other new Dell line cord to PDU-A P2. Connect the other end to the customer's AC power cable. 10. Close PDU-A CB 7 and CB 8. 11. Run Health Check on System 2 again, ensuring it runs without errors. If there are errors, fix them before proceeding with the system installation. Results Adding the second line cord is complete when Health Check runs without errors on System 2. Connect AC Power 25 Internal Use - Confidential Intelligent PDU: PowerMax 2500 - three-phase power On three-phase power, System 1 and System 2 require an initial line cord in IPDP1 outlet P1 and the Jumper PDP. When System 3 is added, remove the Jumper PDP and add a second line cord in iPDP2 P1. ● Jumper PDP: PN 2M5PK ● Three-phase Delta iPDP: PN CFRGY ● Three-phase WYE iPDP: PN WCCVN CAUTION: Removing the Jumper PDP and adding the second iPDP results in a temporary loss of power for a single power zone for System 2 Node Pair 2/DME 2. CAUTION: You must run Health Check on System 2 before you remove the jumpers and add the line cords for System 3. See Three-phase power: Add a second line cord for System 3 on page 25 for instructions. Table 13. PowerMax 2500 line cord configurations, three-phase System Components Line cords and jumpers Circuit breakers PDU outlets System 3 (upper) Node Pair 2/DME 2 iPDP2-P1 9-12 20-27 Node Pair 1/DME 1 (Remove Jumper PDP, replace with iPDP2) Node Pair 2/DME 2 iPDP1-P1 5-8 12-19 Node Pair 1/DME 1 Jumper PDP Node Pair 2/DME 2 iPDP1-P1 1-4 1-11 Node Pair 1/DME 1 Jumper PDP System 2 (middle) System 1 (lower) Table 14. iPDPs and Jumper PDP iPDP locations iPDPs Figure 12. iPDP, three-phase Delta Figure 11. Location of iPDP-1 and iPDP-2 26 Connect AC Power Jumper PDP Figure 13. iPDP, three-phase Wye Figure 14. Jumper PDP Internal Use - Confidential 4 Best Practices for AC Power Connections Select the proper AC power connection procedure depending on the customer's situation on site. Topics: • • • • • • • • Best practices overview for AC power connections Selecting the proper AC power connection procedure Procedure A: Working with the customer electrician onsite Procedure B: Verify and connect Procedure C: Obtain customer verification PDU labels AC power specifications - single-phase AC power specifications - three-phase Best Practices for AC Power Connections 27 Internal Use - Confidential Best practices overview for AC power connections External AC power must be supplied from independent, customer-supplied, power distribution units (PDUs) to assure faulttolerant power. See Two independent customer-supplied PDUs on page 28. For systems operating from three-phase AC power, two independent and isolated AC power sources are recommended for the two individual power zones in each rack. Two independent power sources provide the highest level of redundancy and system availability. If independent AC power is not available, there is a higher risk of data unavailability if a power failure occurs, including individual phase loss in both power zones. Before connecting external AC power to storage bays, verify that the bays have been placed in their final position as explained in the installation guide. Figure 15. Two independent customer-supplied PDUs 28 Best Practices for AC Power Connections Internal Use - Confidential Selecting the proper AC power connection procedure The Dell Customer Engineer must select the proper AC power connection procedure. The following table summarizes the three possible scenarios to connect customer AC power to the storage array. Select the procedure that matches the customer situation. Table 15. Procedure options for AC power connection Situation on site Procedure The customer electrician is available at the installation site. Procedure A - assures fault-tolerant power in the storage array. The customer electrician is NOT available at the installation site, but you have access to customer-supplied, labeled, power cables (beneath a raised floor or overhead). Procedure B The customer electrician is NOT available at the installation site. Customer-supplied PDU source cables are already plugged into the PDU, and you have no access to the customer-supplied power cables. Procedure C Related information Procedure A: Working with the customer electrician onsite on page 30 Procedure B: Verify and connect on page 36 Procedure C: Obtain customer verification on page 37 Best Practices for AC Power Connections 29 Internal Use - Confidential Procedure A: Working with the customer electrician onsite Use this procedure if the customer’s electrician is available at the installation site. This procedure requires three basic tasks that alternate between the customer's electrician, the Dell CE and back to the customer's electrician. ● Task 1: Customer's electrician ● Task 2: Dell Customer Engineer (CE) ● Task 3: Customer's electrician Related information Selecting the proper AC power connection procedure on page 29 30 Best Practices for AC Power Connections Internal Use - Confidential Procedure A, Task 1: Customer electrician About this task NOTE: The customer's electrician performs this task. Steps 1. Verify that the customer-supplied AC source voltage output on each customer-supplied PDU is within the AC power specifications. Measure the voltage output of each power cable as shown in Circuit breakers ON — AC power within specification on page 31. 2. Turn OFF all the relevant circuit breakers in customer-supplied PDU 1 and customer-supplied PDU 2. 3. Verify that the customer-supplied power cables connected to PDU 1 and PDU 2 have no power as shown in Circuit breakers OFF — No AC power on page 31. Figure 16. Circuit breakers ON — AC power within specification Figure 17. Circuit breakers OFF — No AC power Related information AC power specifications - single-phase on page 39 AC power specifications - three-phase on page 40 Best Practices for AC Power Connections 31 Internal Use - Confidential Procedure A, Task 2: Dell Customer Engineer Before connecting power to the PowerMax system, ensure that the power for both zone A and zone B is turned OFF. The Dell Customer Engineer performs this task. WARNING: Do not connect storage bay power zone A and power zone B to the same customer-supplied PDU. If the PDU fails or is turned off during a maintenance procedure, the customer loses power redundancy and risks Data Unavailability (DU). Figure 18. Power zone connections 32 Best Practices for AC Power Connections Internal Use - Confidential Connecting power Steps 1. Confirm that the customer-supplied power cables are labeled and that each label contains the relevant customer-supplied PDU and circuit breaker numbers. If power cables are not equipped with labels, alert the customer. 2. Compare the numbers on the customer-supplied power cables for each storage bay to verify that power zone A and power zone B are powered by a different customer-supplied PDU. 3. Do one of the following to connect power zone A and power zone B in each bay: ● For single-phase power: Connect customer-supplied PDU power cables to the storage bay by connecting to the AC input line cords for power zone A and power zone B as shown below. Rear view System bay Cable connectors are shown as they exit the bo"om rear of the bay. Zone B AC input line cord B Zone A AC input line cord A A B C D E F A B C D E F Ma!ng connector or customer-supplied cable Ma!ng connector or customer-supplied cable Customer’s PDU 1 Customer’s PDU 2 Figure 19. Connecting AC power - single-phase Table 16. PowerMax 2500: Connecting AC power - single-phase, three dual-node pair systems in a rack System Key Basic PDU Intelligent PDU System 3 (UPPER) F P6 iPDP2-P3 E P5 iPDP2-P2 D P4 iPDP2-P1 C P3 iPDP1-P3 B P2 iPDP1-P2 A P1 iPDP1-P1 System 2 (MIDDLE) System 1 (LOWER) ● For three-phase power: Connect customer-supplied PDU power cables to the storage bay by connecting to the AC input line cords for power zone A and power zone B as shown below. Best Practices for AC Power Connections 33 Internal Use - Confidential Rear view System bay Cable connectors are shown as they exit the bo!om rear of the bay. Zone B AC input line cord B Zone A AC input line cord A A B A Mang connector or customer-supplied cable B Mang connector or customer-supplied cable Customer’s PDU 1 Customer’s PDU 2 Figure 20. Connecting AC power - three-phase Table 17. PowerMax 2500: Connecting AC power - three-phase, three dual-node pair systems in a rack System Key Basic PDU Intelligent PDU System 3 (UPPER) B P2 iPDP2-P1 System 2 (MIDDLE) A P1 iPDP1-P1 System 1 (LOWER) A P1 iPDP1-P1 Table 18. PowerMax 2500: Connecting AC power - three-phase 34 Description Key Basic PDU Intelligent PDU Maximum of 2 cords per PDU per power zone per bay A P1 iPDP1-P1 B P2 iPDP2-P1 Best Practices for AC Power Connections Internal Use - Confidential Procedure A, Task 3: Customer electrician - PowerMax 2500 About this task This task applies to the PowerMax 2500 . Steps 1. Working with the Dell Customer Engineer, turn ON all the relevant circuit breakers on the PDU connected to the customersupplied power feed PDU 2. Verify that only power supply LEDs in power zone A are ON or flashing green in every bay in the array. CAUTION: The bay is incorrectly wired if all (power zone A and B) power supply LEDs in a bay are ON or flashing green. Check that the AC power to both storage bay power zones is not supplied by a single PDU (customer-supplied PDU 2). The wiring must be corrected before moving on to the next step. 2. Turn OFF the relevant circuit breakers in customer-supplied PDU 2. Verify that the power supply LEDs that turned green in the previous step changed from green to OFF or flashing yellow. 3. Repeat step 1 and step 2 for power zone B and customer-supplied PDU 1. 4. Turn ON all the relevant circuit breakers in customer-supplied PDU 1 and customer-supplied PDU 2. 5. Label the PDUs as described in Applying PDU labels on page 37. Best Practices for AC Power Connections 35 Internal Use - Confidential Procedure B: Verify and connect About this task Verify and connect customer power components if the two conditions that are listed below are true: ● You have access to customer-supplied, labeled, power cables (beneath raised floor or overhead). ● The customer electrician is not available at the installation site. This procedure requires the Dell Customer Engineer to verify that the customer electrician has complied with power specifications. Once verified, the Dell Customer Engineer makes the required power connections overhead or under the floor. NOTE: Utilize proper strain relief methods when customer-provided power drops are located overhead or wall-mounted. Steps 1. Have the customer verify that their electrician has complied with power specifications for voltage levels and redundancy. If the customer cannot verify the power specifications, provide them with a copy of Procedure A. Inform the customer that their array may prematurely shut down if there is a site power issue. 2. Access the labeled power cables (beneath raised floor or overhead) to verify that the customer-supplied power cables are properly labeled. Figure 21. Circuit breakers OFF — No AC power 3. Compare the numbers on the customer-supplied power cables for each storage bay to verify that power zone A and power zone B are powered by a different customer-supplied PDU. 4. Connect the customer PDU AC cables to the storage bay power zones as described in Procedure A, Task 2. 5. Record the customer-supplied PDU information as described in Procedure A, Task 2. 6. Label the PDUs as described in Applying PDU labels on page 37. Related information Selecting the proper AC power connection procedure on page 29 36 Best Practices for AC Power Connections Internal Use - Confidential Procedure C: Obtain customer verification About this task Perform this procedure if the three conditions listed below are true: ● The customer-supplied PDU source cables are already plugged into the storage bay PDU. ● You have no access to the area below the raised floor. ● The customer's electrician is not available at the installation site. Steps 1. Have the customer verify that their electrician has complied with power specifications for voltage levels and redundancy. If the customer cannot verify this, provide them with a copy of Procedure A. Inform the customer that their array may prematurely shut down in the event of a site power issue. 2. Record the customer-supplied PDU information (AC source voltage) as described in step 1 of Procedure A, Task 1: Customer electrician on page 31 and label the PDUs as described in Applying PDU labels on page 37. Related information Selecting the proper AC power connection procedure on page 29 PDU labels Procedure A, B or C must have been completed before applying labels to the sidewalls of the cabinet. See Selecting the proper AC power connection procedure on page 29 to select the correct procedure. Related information Procedure A: Working with the customer electrician onsite on page 30 Procedure B: Verify and connect on page 36 Procedure C: Obtain customer verification on page 37 PDU label part number ● PDU label: PN 046-990-814 ● Location: OPEN ME FIRST KIT, PN 106-887-306 Applying PDU labels Steps 1. For each bay, locate and complete each PDU label. If necessary, modify the line cord numbers to match your configuration. NOTE: For three-phase power, enter data only in the first two columns. 2. Place each label on the rear cabinet sidewall for sides A and B. Best Practices for AC Power Connections 37 Internal Use - Confidential Customer PDU Information Power Zone A Single PDU Three iPDU P1 P2 P3 P4 P5 P6 P1 P2 N/A N/A N/A N/A 1 iPDP1 iPDP1 iPDP2 iPDP2 iPDP2 Single iPDP P1 P2 P3 P1 P2 P3 Three iPDP1 iPDP2 P1 P1 N/A N/A N/A N/A PDU Panel N/A CB’s N/A N/A 046-990-814_01 Customer PDU Information Power Zone B Single PDU Three iPDU P1 P2 P3 P4 P5 P6 P1 P2 N/A N/A N/A N/A 1 iPDP1 iPDP1 iPDP2 iPDP2 iPDP2 Single iPDP P1 P2 P3 P1 P2 P3 Three iPDP1 iPDP2 P1 P1 N/A N/A N/A PDU N/A Panel N/A CB’s N/A 046-990-814_01 Figure 22. PDU/iPDU label , single-phase and three-phase 38 Best Practices for AC Power Connections N/A Internal Use - Confidential AC power specifications - single-phase Table 19. Input power requirements - Single-phase, North American, International, Australian Specification North American 3-wire connection (2 L & 1 G) L = line or phase, N = neutral, G = ground International and Australian 3-wire connection (1 L & 1 N & 1 G) L = line or phase, N = neutral, G = ground Input nominal voltage 200–240 VAC ± 10% L- L nom 220–240 VAC ± 10% L- N nom Frequency 50–60 Hz 50–60 Hz Circuit breakers 30 A 30/32 A Power zones Two Two PowerMax 2500 minimum input line cord One-node pair, one-DME system: One 30 A or 32 A single-phase line cord per requirements per system power zone for each system. PowerMax 2500 maximum input line cord requirements per system Two-node pair, two-DME system: Two 30 A or 32 A single-phase line cords per power zone. Related information Basic PDU: PowerMax 2500 - single-phase power on page 21 Intelligent PDU: PowerMax 2500 - single-phase power on page 22 Best Practices for AC Power Connections 39 Internal Use - Confidential AC power specifications - three-phase Table 20. Input power requirements - Three-phase, North American, International, Australian Specification North American 4-wire connection International 5-wire connection (3 L & 1 G) (3 L & 1 N & 1 G) L = line or phase, N = neutral, G = ground L = line or phase, N = neutral, G = ground Input voltage a 200–240 VAC ± 10% L- L nom 220–240 VAC ± 10% L- N nom Frequency 50–60 Hz 50–60 Hz Circuit breakers 50 A 30/32 A Power zones Two Two Minimum power requirements at customer site One 50 A three-phase line cord per power zone. One 30 A or 32 A three-phase line cord per power zone. Maximum power requirements at customer site b,c Two 50 A three-phase line cords per power zone. Two 30 A or 32 A three-phase line cords per power zone. An imbalance of AC input currents may exist on the three-phase power source feeding the array, depending on the configuration. The customer's electrician must be alerted to this possible condition to balance the phase-by-phase loading conditions within the customer's data center. b. PowerMax 2500: A second input AC line cord must be added for each power zone when a third PowerMax 2500 system is added to the rack. c. PowerMax 2500: A second input AC line cord must be added for each power zone when the total number of node pairs and DMEs (combined) in a rack reaches seven. a. Related information Basic PDU: PowerMax 2500 - three-phase power on page 24 Intelligent PDU: PowerMax 2500 - three-phase power on page 26 40 Best Practices for AC Power Connections Internal Use - Confidential 5 Complete the Installation Completing the installation involves powering up the system; configuring SCG, WFCT and MFT; initializing the configuraiton; and reinstalling bezels and doors. Topics: • • • • • • • • • Grounding a single bay Connect customer network cables to the MSM Site information required Power on the system Connect a laptop to the system Configure remote support Validating the installation Validating the Firewall Install the rear bay doors Grounding a single bay Equipment correctly installed within the cabinet is grounded through the AC power cables and connectors. In general, supplemental grounding is not required for a single bay. 04 600 33 50 If your site requires external grounding (for example, to a common grounding network beneath the site floor), you can use the grounding lugs provided on each of the cabinet’s bottom supports. CL4827 Figure 23. Location of cabinet ground lugs Complete the Installation 41 Internal Use - Confidential Connect customer network cables to the MSM Steps 1. On Engine 1, connect the customer and guest OS dongle cables, PN 038-004-968, to MSM-1 and MSM-2 ports 3 and 4. 2. On Engine 1, connect the red customer service cable, PN 038-004-436, to MSM-2 port 1. 1 2 3 4 1 PSB1 PSA1 DAE 2 2 PSB2 2 1 4 3 PSA2 2 1 BEM1A 2 1 2ENG 2 3 4 1 2 3 4 4 3 2 2 1 1 3 4 1 2 PSB1 PSB2 PSA2 4 3 1 2 PSB1 DAE 1 PSB2 3 4 1 2 PSA1 2 1 4 3 PSA1 2 1 PSA2 2 1 BEM1A 2 1 ENG 2 1 3 4 1 2 Guest OS 3 4 4 3 2 2 1 1 2 PSB1 PSA2 4 3 ESE/CUST ESE/CUST 1 3 4 PSB2 PSA1 2 1 Guest OS Figure 24. Customer network connections on the MSM 3. Coil the red customer service cable on the rear side wall. Site information required The information in General Site Information on page 42 and Site Connectivity information on page 43 is required before proceeding within this chapter. NOTE: If the array is configured for eManagement, you must obtain additional information before running the initialization script. Gather the general and site connectivity information in the tables listed above, then go to Site information required for eManagement-supported arrays on page 43 to obtain the additional information for eManagement. A unique IP address is required for eManagement. Table 21. General Site Information Description Customer-specific information How to obtain information/example Site name Example: ABC Company Model This is the model number of the installed system. Example: PowerMax 2500 Serial number This is the system serial number of the PowerMax system. Obtain the following information from the customer: Table 22. IP Subnet Information (Optional) Component Listed in Symmwin as: CS-1 NIC-A subnet (default) CS-2 NIC-B subnet (default) 42 Complete the Installation Subnet Configured New Subnet Internal Use - Confidential Table 22. IP Subnet Information (Optional) (continued) Component Listed in Symmwin as: GuestOS GOS subnet (default) Subnet Configured New Subnet Table 23. IP Address Ranges IP Address IPs Range Netmask 255.255.252.0 - - Subnet A 147.178.32.0/22 1024 147.178.32.0 - 147.178.35.255 Subnet B 147.178.36.0/22 1024 147.178.36.0 - 147.178.39.255 Subnet Guest 147.178.40.0/22 1024 147.178.40.0 - 147.178.43.255 Table 24. Site Connectivity information Connection Type CS-1 CS-2 SCG IP Address IP Address Netmask ---------- N/A ------------ Gateway ---------- N/A ------------ Modem Number ---------- N/A ------------ NOTE: Connection type must be the same for both CS-1 and CS-2. Site information required for eManagement-supported arrays For arrays configured for eManagement, you must obtain the following information before running the Install script. ● Valid IPv4 address is in dot-decimal notation such as 240.0.0.0 ● Valid IPv6 address is in hexadecimal notation such as 2001.0DB8:AC10:FE01 ● When gathering the information for the table below, you can have either IPv4 or IPv6, or both. Leave a value blank if it is unused or if the information is not available at this time. Table 25. eManagement Connectivity information Simplified SymmWin Label Description Required information NAT 1A - External Gateway Connectivity Information NAT 1A.IPv4 Address Primary customer IP address for eManagement access via browser. Requires network cable drop to MSM-1. NAT 1A.IPv4 Netmask Netmask value for the (NAT 1A.IPv4 Address) above. NAT 1A.IPv6 Address NAT 1A.IPv6 Net Prefix NAT 2A - External Gateway Connectivity Information NAT 2A.IPv4 Address Secondary customer IP address for eManagement access. Requires network cable drop to MSM-2. NAT 2A.IPv4 Netmask Netmask value for the (NAT 2A.IPv4 Address) above. NAT 2A.IPv6 Address NAT 2A.IPv6 Net Prefix Complete the Installation 43 Internal Use - Confidential Table 26. DNS and NAT Route information for eManagement Simplified SymmWin Label Description Required information Primary.DNS IPv4 Address Primary DNS IP address for eManagement network name resolution. Primary.DNS IPv6 Address Secondary.DNS IPv4 Address Secondary DNS IP address for eManagement network name resolution. Secondary.DNS IPv6 Address NAT 1A.Route IPv4 Address Default gateway address for NAT 1A IPv4 address from eManagement Connectivity information on page 43. NAT 1A.Route IPv4 Netmask Redundant entry, enter same Netmask value defined in eManagement Connectivity information on page 43 for IPv4 addresses. NAT 1A.Route IPv6 Address NAT 1A.Route IPv6 Nat Prefix NAT 2A.Route IPv4 Address Default gateway address for NAT 2A IPv4 address from eManagement Connectivity information on page 43. NAT 2A.Route IPv4 Netmask Redundant entry, enter same Netmask value defined in eManagement Connectivity information on page 43 for IPv4 addresses. NAT 2A.Route IPv6 Address NAT 2A.Route IPv6 Net Prefix Power on the system Turn on the yellow breakers on each PDU. Use the following tables to energize the outlet groups that have components connected to them. NOTE: Do not energize outlet groups that do not have power cables connected to them. Table 27. PowerMax 2500 circuit breaker requirements System Components Circuit breakers PDU outlets System 3 (upper) Engine 2/DAE 2 11-12 31-37 Engine 1/DAE 1 9-10 25-30 Engine 2/DAE 2 7-8 19-24 Engine 1/DAE 1 5-6 13-18 Engine 2/DAE 2 3-4 7-12 Engine 1/DAE 1 1-2 1-6 System 2 (middle) System 1 (lower) Components use the same outlet on the redundant PDUs. For example, in System 1, Engine 1 PSB1 uses outlet #4 on PDU B and Engine 1 PSA1 uses outlet #4 on PDU A. Table 28. PowerMax 2500 outlet map System Component Circuit breaker number Outlet number System 3 (upper) DAE 2 PS1 12 36 44 Complete the Installation Internal Use - Confidential Table 28. PowerMax 2500 outlet map (continued) System System 2 (middle) System 1 (lower) Component Circuit breaker number Outlet number Engine 2 PS1 12 34 DAE 2 PS2 11 33 Engine 2 PS2 11 31 DAE 1 PS1 10 30 Engine 1 PS1 10 28 DAE 1 PS2 9 27 Engine 1 PS2 9 25 DAE 2 PS1 8 24 Engine 2 PS1 8 22 DAE 2 PS2 7 21 Engine 2 PS2 7 19 DAE 1 PS1 6 18 Engine 1 PS1 6 16 DAE 1 PS2 5 15 Engine 1 PS2 5 13 DAE 2 PS1 4 12 Engine 2 PS1 4 10 DAE 2 PS2 3 9 Engine 2 PS2 3 7 DAE 1 PS1 2 6 Engine 1 PS1 2 4 DAE 1 PS2 1 3 Engine 1 PS2 1 1 Connect a laptop to the system The PowerMax 2500 does not have a KVM. You must connect a laptop or external KVM to the system and run required scripts. See PowerMax: How to connect to the PowerMax 2500 & 8500 Control Station at the Customer Site (https://www.dell.com/ support/kbdoc/en-us/000201542) for instructions. Configure remote support It is recommended that you configure remote support. ● Secure Connect Gateway (SCG) version 5.12.00.10 or above is required for PowerMax 2500 remote connectivity. ● SCG is an IP-based, automated connect home and remote support solution and is the preferred method of connectivity. Dell recommends two connections with SCG for connecting to the redundant control station. ● SCG requires port 8443 to be open in the data center. For more information, refer to the CS Connectivity section at PowerMax 10 Page (https://confluence.cec.lab.emc.com/ display/ISG/PowerMax+10+Page). Complete the Installation 45 Internal Use - Confidential NOTE: After the ESE Configuration Setup script is successful, verify the Call Home and connect-in tests are successful before leaving the site. If network access is not available on your laptop, use the Dell VPN to connect the system. Verify that remote client file transfer is working. If network access is not available, contact local triage or the support lab to perform the connect-in test. Validating the installation You must run the Install script before turning the system over to the customer. Before going on-site, refer to Salesforce Article Number 304108 for information on how to determine the correct installation path. Generate the relevant Enhanced Procedure Generator (EPG) procedure before going to the customer site. CAUTION: If the PowerMax system is part of a VxBlock or PowerOne converged infrastructure solution you must use the CPSD procedures in SolVe. Running the C&I script on a PowerMax in a VxBlock or PowerOne solution will destroy the factory set configuration. The Install script uses the following criteria to determine which script to run. The appropriate script will start automatically. ● Verify VMAX Setup script: Dell rack system is at the operating system level with the configuration that the system shipped with. ● C&I script: ○ Dell rack system is at a different operating system level or a different configuration than the system shipped with. ○ A second PowerMax system in a Dell rack. (Second systems are available with some PowerMax models only.) ○ Third-party rack system. Running the script Before turning the system over to the customer, run the Install script as per the EPG procedure you created. NOTE: Do not connect HOST cables until the system has completed the installation process. Validating the Firewall About this task Complete this task after successfully installing or upgrading a system. Steps 1. In Simplified SymmWin, select Scripts > Health Check. As part of the Health Check, Simplified SymmWin verifies that the WFCT is running and configured as expected. ● IF the WFCT is configured as expected, the Health Check does not return any WFCT-related errors. ● IF the WFCT is not configured as expected, the Health Check returns a call home error with a description of the error. Errors can be found in the WFCT log file: ○ PowerMaxOS 5978.xxx.xxx: O:\EMC\WFCT\wfct_data\logging.log ○ PowerMaxOS 10: O:\EMC\logs\wfct\wfct.log 2. If errors occur: a. Evaluate and resolve each error. See WFCT errors and recommended actions on page 47 and use the list of recommended actions to resolve the problem. b. Run Health Check until the logging.log (PowerMaxOS 5978.xxx.xxx) or wfct.log (PowerMaxOS 10) file displays Health Check successful. 3. If the customer requires additional Firewall Products, open the WFCT from the desktop and perform the required changes. NOTE: You must create a new configuration when a customer requires additional Firewall Products. When you create a new configuration, products that are related to a previously active configuration are copied to the new configuration. Do not add or remove anything from the DEFAULT_ACTIVE configuration. 4. Verify that the Windows Firewall is ON. See Verify that the Windows Firewall is ON on page 49. 46 Complete the Installation Internal Use - Confidential WFCT errors and recommended actions Use the table below to identify and resolve WFCT errors. Simplified SymmWin displays error codes and descriptions during a Health Check script. Use the resulting call home error to find the respective solution in the table below. The O:\EMC\WFCT\wfct_data\logging.log (PowerMaxOS 5978.xxx.xxx) or O:\EMC\wfct\wfct.log (PowerMaxOS 10) file contains additional error information. NOTE: Often there is no standard fix for an error. Confer with Engineering to find a resolution. Complete the Installation 47 48 Table 29. WFCT errors and recommended actions Complete the Installation Dial home error code Health Check error code Error message 04.DC.35 10 04.DC.36 Recommended action Files required Files required PowerMaxOS 5978.xxx.xxx PowerMaxOS 10 Firewall mismatch on Indicates a Firewall rule the secondary MMCS mismatch on the secondary or CS MMCS or CS. Run a WFCT repair command from the primary MMCS or CS. ● O:\EMC\WFCT\wfct_data\logging.log ● O:\EMC\INSTALL_LOGS\Enginuity.log ● O:\EMC\Logs\wfct\wfct.log ● O:\EMC\INSTALL_LOGS\Enginuity.log 8 Firewall service not running Indicates that Windows Defender Firewall services are not running on the MMCS or CS. Engineering must analyze the logs. ● O:\EMC\WFCT\wfct_data\logging.log ● O:\EMC\INSTALL_LOGS\Enginuity.log ● O:\EMC\Logs\wfct\wfct.log ● O:\EMC\INSTALL_LOGS\Enginuity.log 04.DC.37 None Firewall monitoring error Indicates a WFCT failure. Engineering must analyze the logs. ● O:\EMC\WFCT\wfct_data\logging.log ● O:\EMC\INSTALL_LOGS\Enginuity.log ● O:\EMC\Logs\wfct\wfct.log ● O:\EMC\INSTALL_LOGS\Enginuity.log 04.DC.38 6 Active and current rule set size mismatch The script calls the WFCT ● O:\EMC\WFCT\wfct_data\logging.log repair automatically. If the ● O:\EMC\INSTALL_LOGS\Enginuity.log script is unable to call the WFCT repair workflow, run the repair manually. ● O:\EMC\Logs\wfct\wfct.log ● O:\EMC\INSTALL_LOGS\Enginuity.log 04.DC.39 7 Mismatch found in the active and current rule set Engineering must analyze the log and system to recommend a resolution. ● O:\EMC\WFCT\wfct_data\logging.log ● O:\EMC\Logs\wfct\wfct.log 04.DC.3A None General firewall issue Engineering must analyze the log and system to recommend a resolution. ● O:\EMC\WFCT\wfct_data\logging.log ● O:\EMC\Logs\wfct\wfct.log 04.DC.3B 11 Windows Firewall service not running on the system Engineering must analyze the log and system to recommend a resolution. ● O:\EMC\WFCT\wfct_data\logging.log ● O:\EMC\Logs\wfct\wfct.log Internal Use - Confidential Internal Use - Confidential Verify that the Windows Firewall is ON About this task Use this task to verify that the Windows Firewall is ON. Steps 1. Use the Windows Search function to search for firewall. 2. Select Windows Defender Firewall with Advanced Security. The Windows Defender Firewall with Advanced Security dialog box opens. 3. Verify that Windows Firewall is on is active for each profile. 4. Close the Windows Defender Firewall with Advanced Security dialog box. Complete the Installation 49 Internal Use - Confidential Install the rear bay doors About this task To install the rear doors: Steps 1. Ensure the spring pins in the top, middle, and bottom hinges are pressed in and locked in the open position. 2. Position the top-door hinge on the bay casing. 3. Release the spring hinge and let it snap in place, securing the upper-door hinge to the bay, as shown in Reinstall rear door on page 50 and Reinstall rear door on page 50. 1 2 Spring pin (open) Spring pin hinge (closed) 3 Figure 25. Reinstall rear door Table 30. Reinstall rear door Key Instruction 1 Align the door with the top and bottom of the bay and move pins into position under the hinge on the rack. 2 Move the pins on each hinge to the closed position. 3 Swing the door toward the bay to clear the inside trim and close it. 4. Repeat step 2 and step 3 for the middle and the bottom-door hinges. The rear door is shipped unlocked. The key is attached to the interior of the door with a tie-wrap. Leave the key there for the customer. 50 Complete the Installation Internal Use - Confidential 5. If present on the front bay door, gently peel the protective, clear film that covers the lettering. Do not rip the film off. Peel it off gently letter by letter. Results Installation of the array is now complete. Complete the Installation 51 Internal Use - Confidential A PowerMax File Installation Procedure For information on configuring PowerMax File, see the Dell PowerMax File Quick Start Guide on the Dell Online Support site at PowerMaxOS 10 (https://www.dell.com/support/home/en-us/product-support/product/powermax-os-10/overview). 52 PowerMax File Installation Procedure