14 August 2024 Project Schedule (With Forking) WBS TASK DESCRIPTION PIC PLAN START PLAN END PLAN DAYS 1 1 1 1 1 1 1 1 Nov Dec Jan Feb Mar Apr May Jun '23 '23 '24 '24 '24 '24 '24 '24 1 1 1 1 1 1 1 1 1 1 1 1 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun '24 '24 '24 '24 '24 '24 '25 '25 '25 '25 '25 '25 1 9 2 3 4 5 6 7 8 1 1 Jul Aug '25 '25 10 11 12 13 14 15 16 17 18 19 20 21 22 1 Project Preparation 1.1 SWS Reinstatement (Pipeline, Pumps and Engine) Mtc 1-Nov-23 30-May-24 212 1.2 Road Maintenance & Land Slide Countermeasure Civil 1-Jan-24 30-May-24 151 1.3 Civil Work (Cellars, Thrust Frame Foundation, Trenches, Pipe Support) Civil 17-Feb-24 30-May-24 104 1.4 Pipeline Tie-in Work & Shop Fabrication Eng 1-Jan-24 213 31-Jul-24 2 Project Execution 2.1 2.2.1 Drilling & Surface Facility Installation Wellpad L 2.2.1.1 RD-L2 ST Drilling Drilling 1-Aug-24 1-Sep-24 32 2.2.1.2 Pipeline Construction, Tie-in & Commissioning Eng 2-Sep-24 1-Oct-24 30 2.2.1.3 Well Testing & Monitoring Well Test 2-Sep-24 31-Oct-24 60 2.2.1.4 RD-L6 Drilling Drilling 6-Sep-24 26-Oct-24 51 2.2.1.5 Pipeline Construction, Tie-in & Commissioning Eng 27-Oct-24 25-Nov-24 30 2.2.1.6 Well Testing & Monitoring Well Test 27-Oct-24 25-Dec-24 60 2.2.1.7 RD-L4 ST Drilling Drilling 31-Oct-24 14-Dec-24 45 2.2.1.8 Pipeline Construction, Tie-in & Commissioning Eng 15-Dec-24 13-Jan-25 30 2.2.1.9 Well Testing & Monitoring Well Test 15-Dec-24 12-Feb-25 60 2.2.2 RD-M1 ST Drilling Drilling 24-Dec-24 6-Feb-25 45 2.2.2.2 Pipeline Construction, Tie-in & Commissioning Eng 7-Feb-25 20-Feb-25 14 2.2.2.3 Well Testing & Monitoring Well Test 7-Feb-25 22-Mar-25 44 Wellpad N 2.2.3.1 RD-N2 ST Drilling Drilling 16-Feb-25 27-Mar-25 40 2.2.3.2 Civil Work for RD-ND ST Tie-in Civil 5-Jan-25 20-Mar-25 75 2.2.3.3 Pipeline Construction, Tie-in & Commissioning Eng 28-Mar-25 11-May-25 45 2.2.3.4 Well Testing & Monitoring Well Test 28-Mar-25 10-Jun-25 75 2.5 2.5.1 1st PRC is expected in Nov ’24 by introducing L2 ST Generation Recovery 1st PRC 2.5.1.1 Plant Generation increase & Monitoring (L2 ST & L6 introduced) Prod 1-Nov-24 7-Nov-24 7 2.5.1.2 Plant Rate Capacity (PRC) Prod 12-Nov-24 12-Nov-24 1 2.5.2 Drilling complete Mar 27th 2025 Wellpad M 2.2.2.1 2.2.3 Drilling start 08 1st 2024 1 2nd PRC 2.5.2.1 Plant Generation increase & Monitoring (N2 ST introduced) Prod 11-Jun-25 17-Jun-25 7 2.5.2.2 Plant Rate Capacity (PRC) Prod 18-Jun-25 18-Jun-25 1 2nd PRC is expected in Jun 18th, 2025 by introducing N2 ST Procurement No. Type Description Status Schedule 1 Service (24000098) Welding Service for Tie-in Work SO Issued 25 Aug 2024 arrive at site 2 Service (24000075) NDE Inspection Service & Certification SO Issued 27 – 30 Sep 204 3 Service (24000099) Thermal Insulation work SO Issued After construction L2,L4,L4 completed 4 Service (24000108) Electrical & Instrumentation installation work for new wells Waiting for proposal 5 Service Crane 50T Rental ITP Issued 27 Aug 2024 arrive at site 6 Material (24000087) Material for tie in work RD-L2, L4 & L6 Waiting for delivery 25 – 27 Aug 2024 arrive at site 7 Material (24000087) Pipe shoe & Saddle for pipe support Waiting for delivery 25 – 27 Aug 2024 arrive at site RD-L2 Piping Construction Scenario ID Task Start Finish 1 Welding Contractor arrival (induction, site preparation) 25-08-24 26-08-24 2 Material arrival & Crane 50T arrival 27-08-24 27-08-24 3 Shop Welding (FCV Spool, Temporary Spool, Flow=T, Branch Piping) 28-08-24 02-09-24 4 RD-L2 Drilling Operations 01-08-24 02-09-24 5 Setup Crane 50T, Field Welding (Counter Weight, Branch Piping, Bleeding Line) 03-09-24 26-09-24 6 Install Temporary Spool (Flowing Test) 27-09-24 27-09-24 7 Radiography Test & Repair (if any) 28-09 24 30-09-24 8 Well Monitoring 01-09 24 30-09-24 9 Flowing Monitoring 1-10-24 30-10-24 10 Remove Temporary Spool and Install FCV 31-10-24 31-10-24 11 Handover to Production (Joint Inspection) 01-11-24 01-11-24 12 Introduce RD-L2 into the system and increase generation test 02-11-24 04-11-24 PRC 1st 05-11-24 Gantt Chart Engineering Engineering Engineering Drilling Engineering Well Testing Well Testing Engineering Engineering 13 Production Production 05-11-24 RD-L2 Flowing Temporary Spool Flowing (Temporary Spool) FCV Remove Temporary inspection and cleaning Install FCV for normal operation Spool for RD-L2 Construction Map Rig L6 L5 L4 L3 L2 L1 Highlight Activities Accommodation FCV Spare No Contractor Service Personnel 1 Intan Lestari Engineering Welding 15 persons 2 Sucofindo NDT 3 persons 3 GMK Crane 2 persons 4 Sartco Aditama Insulation 5 persons Shop Welding Area