ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing Introduction: Job order costing is the method of costing that is applied to determine the cost of specific jobs or lots of production generally manufactured according to customers' specification. The main objective of job costing is to determine profit or loss of each job. Before accepting a job, costs are estimated. It helps in minimizing losses and maximizing profits. The costs per unit can be obtained by dividing the total costs by the number of units produced. Types of Job Order Costing: Job order costing can be sub-divided into the following categories. 1. Factory job costing or job costing 2. Batch costing 3. Contract costing. Factory Job Costing: Factory job costing is used as a means of accumulating cost where products are made to customer's specifications in the factory. Batch Costing: Batch costing is used as a means of accumulating cost where products are made in the factory for stock. Contract Costing: Contract Costing is used as a means of accumulating cost where works are done to the customer’s specifications outside the factory. Salient Features of Job Costing: The salient features of job costing can be mentioned as below: i) Work is carried out against customers' orders and not for maintaining stock sale. ii) Work must be carried out according to the specifications of the customers. iii) Each job can be clearly identified from the other, or at least physical identification is pre-supposed. iv) Each job requires particular attention and skill depending upon the specification. v) Every job does not pass through all the departments. Nature of the job decides through which departments it will pass. vi) There is no standardization of jobs. Each job is a separate non-standard work. vii) Each job is to be charged with its own costs. viii) Work-in-progress at any time depends upon the number of jobs in hand at that time. A separate work-in-progress record is maintained for each job. Advantages of Job Costing: The following advantages are claimed of job costing: i) Profitability of each job can be known separately. ii) Management, based on past job cost records, can make dependable estimates for similar future jobs. iii) Job costing shows the material cost, labor cost, factory overheads, administration overheads, selling and distribution overheads for each job in detail and hence, it facilitates the control of the costs of similar future jobs. iv) On the basis of budgets, the overhead recovery rates may be pre-determined. This makes working out of the incidence of overheads for each job easy, but budgetary control becomes necessary to see that there is no gross overor under-recovery of overheads. v) Under job costing, since each job is clearly distinguished from the other, the spoilage and defectives from each job can be separately known and hence, they can be controlled. vi) Job costing facilitates pricing of each job. Rates of profits, according to different types of jobs, are mentioned in the management policy. The applicable rate is applied on the estimated cost, to ascertain the price. vii) In case of Government contracts of new nature, often the contract price is agreed at certain per cent added to cost (i.e., cost plus contracts). Job costing gives much advantage in this case. viii) Detailed job cost records of the past periods can be preserved and studied to understand the trends of costs of different elements. Disadvantages of Job Costing: The following are the principal disadvantages of job costing: i) The method is costly and laborious owing to much clerical work required to maintain detailed information. ii) Cost records are made after the costs are incurred. So, control becomes impossible, unless proper estimates or standards are set, and control is exercised on the actual expenditure with reference to corresponding estimate or standard. iii) Previous job cost records may fail to guide the future cost, if there is a fundamental change in the market conditions. iv) Errors in estimation or in cost records may bring about sad results. Procedure of Job Order Costing: The procedure of job order costing is as follows: i) Production Order: When an order is received from customers, the production control department allots a production order number. Sometimes, sub-numbers are allotted in addition to one master number if the work is subdivided. BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing ii) Recording of Costs: The costs are collected and recorded for each job under a separate production order number. Based on the production order, the costing department prepares a job cost sheet for each job. The costs are direct materials, direct labor, direct expenses and overhead. iii) Completion of Job: The completion report is sent to the costing department after the completion of a job. The expenditure under each element of cost is totaled and the total job cost is ascertained. Batch Costing: Batch costing is a type of costing. Batch costing is done when production consists of a definite number of articles or production involves limited repetition work. Batch costing is followed in industries like show industry, biscuit factories, ball-point industry. Economic Batch Quantity: EBQ is the batch size that minimizes both the setting up costs and the costs of carrying inventory in stock over a period. Economic Batch Quantity = Where, U= Annual usage in units, S= Setting up costs per Batch, l= Annual rate of interest, C= Unit cost of production. Setting Up Costs: Setting up costs are fixed per batch, per unit cost will decrease with the increase in batch size and per unit cost will increase with the decrease in batch size. Carrying Costs: Carrying costs are costs that are incurred of holding inventory in stock over a period. These costs may include costs of storage, interest on capital blocked in the large stock etc. It will increase with the increase in the size of batch. Exercises: Exercise-1: The Information given below has been taken from the cost records of an engineering works in respect of Job No.-101: Materials: Tk. 4,010. Labor: Department-A: 60 hours @ Tk. 3 per hour; Department-B: 40 hours @ Tk. 2 per hour; Department-C: 20 hours @ Tk. 5 per hour. The overhead expenses are as follows: Variable: Department-A: Tk. 5,000 for 5,000 Labor Hours; Department-B: Tk. 3,000 for 1,500 Labor Hours; Department-C: Tk. 2,000 for 500 Labor Hours. Fixed: Tk. 20,000 for 10,000 working hours. Requirement: Calculate the cost of Job No.-101 and price for the job to give a profit of 25% on the selling price. Job Cost Sheet (Job No.-101) Cost Components Materials Labor: Department-A: 60 hours @ Tk. 3 Per Hour Department-B: 40 hours @ Tk. 2 Per Hour Department-C: 20 hours @ Tk. 5 Per Hour Overhead Expenses: Variable: Department-A: [(Tk. 5,000 ÷ 5,000 Labor Hours) x 60 Hours] Department-B: [(Tk. 3,000 ÷ 1,500 Labor Hours) x 40 Hours] Department-C: [(Tk. 2,000 ÷ 500 Labor Hours) x 20 Hours] Fixed: [(Tk. 20,000 ÷ 10,000 Hours) x (60 + 40 + 20 Hours) Cost of the Job Add: Profit 25% on Sales Price i.e. 33.33% on Cost Selling Price Amount (Tk.) 180 80 100 60 80 80 240 Amount (Tk.) 4,010 360 460 4,830 1,610 6,440 Exercise-2: In an enterprise, factory overheads are charged to jobs based on prime cost. From January-2024 the management decided to charge overheads based on direct labor hours or percentage of direct wages. The following figures are available in the monthly accounts of the enterprise. Manufacturing overhead Tk. 50,000; Direct wages Tk. 25,000 Direct labor hours 50,000. In a particular month, the following figures were available regarding two jobs: BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing Job No. 101 Job No. 201 Direct material Tk. 150 Tk. 150 Direct wages Tk. 20 Tk. 25 Direct labor 10 hours 8 hours Required: Prepare job cost sheet based on direct wages percentage and direct labor hour rate. 1. Calculation based on direct wages percentage: Factory Overhead Rate (Percentage of Direct Wages): = (Total Manufacturing Overhead ÷ Total Direct Wages) x 100 = (50,000 ÷ 25,000) x 100 = 200% Job No. 101: Overhead Applied = Direct Wages x Overhead Rate = 20 x 200% = Tk. 40 Job No. 201: Overhead Applied = Direct Wages x Overhead Rate = 25 x 200% = Tk. 50 2. Calculation Based on Direct Labor Hour Rate: Factory Overhead Rate per Direct Labor Hour: Factory Overhead Rate Per Hour = Total Manufacturing Overhead ÷ Total Direct Labor Hours = (50,000 ÷ 50,000 Hours) = Tk. 1 Per Direct Labor Hour Job No. 101: Overhead Applied = Direct Labor Hours x Overhead Rate per Hour = 10 x 1 = Tk. 10 Job No. 201: Overhead Applied = Direct Labor Hours x Overhead Rate per Hour = 8 x 1 = Tk. 8 Job Cost Sheet Preparation: 1. Based on Direct Wages Percentage: Cost Components Job No. 101 (Tk.) Job No. 201 (Tk.) Direct Material 150 150 Direct Wages 20 25 Overhead Applied (200 % of Direct Wages) 40 50 Total Cost 210 225 2. Based on Direct Wages Percentage: Cost Components Direct Material Direct Wages Overhead Applied (Tk. 1 Per Hour) Total Cost Job No. 101 (Tk.) 150 20 10 180 Job No. 201 (Tk.) 150 25 8 183 Exercise-3: A company manufactures goods to customer's specification, on 31 December, cost records show the following information in respect of three incomplete orders: Job No. B-12 D-23 E-O7 Direct Materials 15,000 21,000 29,000 Direct Labor 14,000 16,000 21,000 Factory Overhead 10,500 15,000 18,000 Direct Labor Hour 3,500 5,000 6,000 The jobs are completed during the next two months, Additional materials and labor hours required for completion of the jobs are as follows: Job No. Direct Materials Direct Labor Hour B-12 5,000 1,500 D-23 3,000 2,000 E-O7 4,000 3,000 Factory overhead is charged on tire basis of direct labor hours. Calculate the cost of each job where profit is 20% on the selling price. 1. Calculation of Labor Hour Rate: i) Job No. B-12 = Direct Labor Cost ÷ Direct Labor Hour = (14,000 ÷ 3,500 Hours) = Tk. 4 Per Direct Labor Hour ii) Job No. D-23 = Direct Labor Cost ÷ Direct Labor Hour = (16,000 ÷ 5,000 Hours) = Tk. 3.20 Per Direct Labor Hour iii) Job No. E-07 = Direct Labor Cost ÷ Direct Labor Hour = (21,000 ÷ 6,000 Hours) = Tk. 3.50 Per Direct Labor Hour 2. Calculation of Total Direct Labor Cost: i) Job No. B-12 = 1,500 Hours @ Tk. 4 = Tk. 6,000 Total= (14,000 + 6,000) = Tk. 20,000 BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing ii) Job No. D-23 = 2,000 Hours @ Tk. 3.20 = Tk. 6,400 Total = (16,000 + 6,400) = Tk. 22,400 iii) Job No. E-07 = 3,000 Hours @ Tk. 3.50 = Tk. 10,500 Total = (11,000 + 10,500) = Tk. 31,500 3. Calculation of Total Factory Overhead: i) Job No. B-12 = 1,500 Hours @ Tk. 3 = Tk. 4,500 Total = (10,500 + 4,500) = Tk. 15,000 ii) Job No. D-23 = 2,000 Hours @ Tk. 3 = Tk. 6,000 Total = (15,000 + 6,000) = Tk. 21,000 iii) Job No. E-07 = 3,000 Hours @ Tk. 3 = Tk. 9,000 Total = (18,000 + 9,000) = Tk. 27,000 Cost Components Direct Material Add: Additional Materials Materials Used Direct Labor Prime Cost Factory Overhead Manufacturing Cost Profit (20% on Sale i.e. 25% on Cost) Selling Price Job No. B-12 (Tk.) 15,000 5,000 20,000 20,000 40,000 15,000 55,000 13,750 68,750 Job No. D-23 (Tk.) 21,000 3,000 24,000 22,400 46,400 21,000 67,400 16,850 84,250 Job No. E-07 (Tk.) 29,000 4,000 33,000 31,500 64,500 27,000 91,500 22,875 114,375 Exercise-4: In Janata Corporation costs of completing a job were as follows: Direct Materials 1,200 kg @ Tk. 15; Direct Labor 750 hours @ Tk. 4; Factory Overhead: Fixed Tk. 1,800; Variable Overhead 80% of Direct Labor Cost. The job was sold at Tk. 31,500. The company must quote the price of a new job which requires 33.33% more materials and labor hours to complete. The price of materials and the labor hour rate have increased to 20% and 25% respectively. Required: What price the company should quote to earn the same percentage of profit in cost? Statement of Job Cost (For Old Job) Cost Components Materials (1,200 kg x Tk. 15) Direct Labor (750 Hours x Tk. 4) Amount (Tk.) Prime Cost Factory Overhead: Variable (80% of 3,000) Fixed 2,400 1,800 Cost of Goods Manufactured Add: Profit Selling Price Amount (Tk.) 18,000 3,000 21,000 4,200 25,200 6,300 31,500 Workings: i) New Labor Hours = [750 + (750 x 33.33%)] = 1,000 Hours ii) Price of New Material Rate = Tk. 15 + (Tk. 15 x 20%) = Tk. 18 iii) New Labor Hour Rate = Tk. 4 + (Tk. 4 x 25%) = Tk. 5 iv) Materials Needs for New Job = 1,200 + (1,200 x 33.33%) = 1,600 kg v) % of Profit Rate on Cost = [(6,300 ÷ 25,200) x 100] = 25% BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing Statement of Job Cost (For New Job) Cost Components Materials (1,600 kg x Tk. 18) Direct Labor (750 Hours x Tk. 4) Amount (Tk.) Prime Cost Factory Overhead: Variable (80% of 5,000) Fixed Amount (Tk.) 28,800 5,000 33,800 4,000 1,800 5,800 39,600 9,900 49,500 Cost of Goods Manufactured Add: Profit (25% on Cost) Selling Price Exercise-5: Acme Ltd. uses two predetermined overhead rates for its products. Overheads are divided based on labor functions and machine operations and separate rates are calculated for each of them. Some jobs depend mainly on manual labor and some others largely on machine operations. For the year ended 31st December, during the year the following estimates have been made: i) Factory Overhead for Labor Functions: Tk. 204,000; ii) Factory Overhead for Machine Operations: Tk. 198,000; iii) Direct Labor Cost: Tk. 240,000; iv) Machine Hours: 36,000 Actual data relating to two jobs are as follows: Job No. 104 Tk. 23,100 Tk. 28,400 200 Direct Material Direct Labor Machine Hours Job No. 105 Tk. 36,600 Tk. 2,400 3,000 Required: a) Predetermined overhead rates b) Cost of two jobs based on two overhead rates c) Cost of the two jobs if a single overhead rate based on direct labor cost was used. 1) Predetermined Overhead Rates: i) Factory Overhead Rates based on Direct Labor Cost = [(Tk. 204,000 ÷ Tk. 240,000) x 100] = 85% ii) Factory Overhead Rates based on Machine Hours = [Tk. 198,000 ÷ 36,000 Machine Hours] = Tk. 5.5 Per Machine Hour 2) Cost of two jobs based on two overhead rates: Statement of Job Cost For Job No. 104 Cost Components Amount (Tk.) Amount (Tk.) Direct Material 23,100 Direct Labor 28,400 Prime Cost 51,500 Factory Overhead: Labor Function (85% of 28,400) 24,140 Machine Operation (200 Hours x Tk. 5.5 Per Hour) 1,100 25,240 Total Cost 76,740 Statement of Job Cost For Job No. 105 Cost Components Direct Material Direct Labor Prime Cost Factory Overhead: Labor Function (85% of 2,400) Machine Operation (3,000 Hours x Tk. 5.5 Per Hour) Amount (Tk.) 2,040 16,500 Total Cost Amount (Tk.) 36,600 2,400 39,000 18,540 57,540 BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing c) Calculation of Single Overhead Rate based on Direct Labor Cost = [{(Tk. 204,000 + 198,000) ÷ Tk. 240,000)} x 100] = 167.50% Statement of Job Cost For Job-104 and Job-105 in Single Overhead Rate Cost Components Job-104 (Tk.) Job-105 (Tk.) Direct Material 23,100 36,600 Direct Labor 28,400 2,400 Prime Cost 51,500 39,000 Factory Overhead: (167.50% of Direct Labor) 47,570 4,020 Total Cost 99,070 43,020 Exercise-6: From the following particulars calculate the cost of Job No.505 and price for the job to give a profit of 25% on the selling price. Material: Tk. 6820 Wage and Variable Overheads Details are as follows: Wage Details Variable Overheads Detail Department Total Rate Per Hour (Tk.) Department Total Cost (Tk.) Total Hour Hours X 60 3 X 5,000 5,000 Y 50 3 Y 4,000 2,000 Z 30 5 Z 2,000 500 The total fixed expenses amounted to Tk. 20,000 for 10,000 working hours. Calculate the cost of Job No. 505 and the price for the job to give a profit of 25% on selling price. Job Cost Sheet (Job No.-505) Cost Components Materials Labor: Department-X: 60 hours @ Tk. 3 Per Hour Department-Y: 50 hours @ Tk. 3 Per Hour Department-Z: 30 hours @ Tk. 5 Per Hour Amount (Tk.) 180 150 150 Prime Cost Overhead Expenses: Variable: Department-X: [(Tk. 5,000 ÷ 5,000 Labor Hours) x 60 Hours] Department-Y: [(Tk. 4,000 ÷ 2,000 Labor Hours) x 50 Hours] Department-Z: [(Tk. 2,000 ÷ 500 Labor Hours) x 30 Hours] Fixed: [(Tk. 20,000 ÷ 10,000 Hours) x (60 + 50 + 30 Hours) Cost of the Job Add: Profit 25% on Sales Price i.e. 33.33% on Cost Selling Price 60 100 120 280 Amount (Tk.) 6,820 480 7,300 560 7,860 2,620 10,480 Exercise-7: ABC Limited manufactures ring binders which are embossed with the customers’ own logo. A customer has ordered a batch of 600 binders. The following illustrates the cost for a typical batch of 100 binders. Direct Material Direct Labor Machine Set Up Design Artwork Prime Cost Amount (Tk.) 60 20 6 30 116 BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing Direct employees are paid on a piecework basis. ABC Limited absorbs production overheads at a rate of 20% of direct wages cost. 5% is added to the total production cost of each batch to allow for selling, distribution and administration overheads. ABC Limited requires a profit margin of 25% of sales value. The selling price for 600 binders (to the nearest penny) will be: a) 756 b) 772.8 c) 806.4 d) 1,008 Calculation of Selling Price: Prime Cost (Tk. 116 x 6) Overheads (Tk. 20 x 6 x 20%) Selling, Distribution and Administration Overheads (720 x 5%) Total Cost Selling Price [(Tk. 756x 100) ÷ 75] Amount (Tk.) 696 24 720 36 756 1,008 Contract Costing It is a special form of job costing and it is the most appropriate method to be adopted in such industries as building and construction work, civil engineering, mechanical fabrication and ship building. In other words, it is a form of specific order costing which applies where the work is undertaken to customer’s requirements and each order of long duration as compared to job costing. It is also known as terminal costing. The official CIMA terminology defines contract costing as “a form of specific order costing in which costs are attributed to individual contracts.” Basic Features: 1. Each contract itself a cost unit. 2. Work is executed at the customer’s site. 3. The existence of subcontract. 4. Most of the expenses incurred upon the contracts are direct. 5. Cost control is very difficult in contract costing. Types of contracts Generally there are three types of contracts: 1. Fixed Price Contracts: Under these contracts both parties agree to a fixed contract price. 2. Fixed Price Contract with Escalation clause. 3. Cost Plus Contract: Under this contract no fixed price could be settled for a contract. Contract Account: A contract account is a nominal account in nature. It is prepared to find out the cost of the contract and to know profit or loss made on the contract. A contractor may undertake several contracts at a time. For each contract a separate account is opened. In the contract account all direct costs such as material, labour and other direct expenses incurred during an accounting period are debited and the indirect expenses are apportioned on an equitable basis. The differences between the two sides are known as Notional profit or notional loss. Special Terms in Contract Account: 1. Work in Progress: It is the unfinished contract at the end of the accounting period, and it includes the amount of work certified and amount of work uncertified. Work in progress is an asset, shown in the balance sheet by deducting there from any advance received from the contractee. 2. Work Certified: The sales value of work completed as certified by the architect is known as ‘work certified’. In the case of contracts of long duration, the amount payable by the customer to the contractor is based on the sales value of work done as certified by the architect. At the end of the financial year, the total sales value of work done and certified by the architect is credited to the contract account. 3. Work Uncertified: It means work which has been carried out by the contractor but has not been certified by the architect. Sometimes, work which is complete remains uncertified at the end of the financial year. The reasons for the same may be a. Work not sufficient to be certified b. Work has not reached the stipulated stage to qualify for certification. It is always valued at cost and credited to the contract account. 4. Retention Money: Regardless of the amount of work certified, the contractor is paid a specified percentage of the same and the balance is held or retained by the contractee. This is because the contractee must safeguard himself against any contingency arising from the non-fulfillment of the terms of the contract by the contractor. The unpaid balance of work certified, or the amount held back or retained by the contractee is known as ‘retention money’. BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing 5. Subcontract: Sometimes the contractor enters contracts with another contractor to give a portion of work undertaken by him. In such cases the work performed by the subcontractor s forms a direct charge to the contract concerned. Subcontract costs will be shown on the debit side of the contract account. 6. Escalation clause: This is the clause which is provided in the contract to cover up any increase in the price of the contract due to increase in the prices of raw material or labour or in the utilization of any other factors of production. If material and labour utilization exceed a particular limit, the customer agrees to bear the additional cost occasioned by excessive utilization. Here, the contractor must satisfy the customer that excessive utilization is not the result of decreased efficiency. Specimen Form of Contract Account (Unfinished Contract) Amount (Tk.) Amount (Tk.) To Materials xxx By Work-in-Progress: To Labour xxx Work Certified xxx To Plant xxx Work Uncertified xxx xxx To Overheads xxx By Material Returned xxx To Cost of Subcontracts xxx By Plant xxx To Notional Profit C/D (B/F) xxx Less: Depreciation xx xxx By Material Lying at Site xxx xxx xxx To Profit and Loss A/C xxx By Notional Profit B/D xxx To WIP (B/F) xxx xxx xxx Treatment of Plant and Machinery: One of the distinguishing features of a contract is the use of special plant and machinery. The cost of these is capital expenditure, but the usage of these should be reflected in the form of depreciation. There are two distinct methods of charging depreciation. 1. At the time of issue of plant to contract the contract account is debited with the full value of the plant. At the end of the period the contract account is credited with a depreciated value. This method is used when plant and machinery is used at the contract site for a long period. 2. In the second method, the contract account is debited with an hourly rate of depreciation for the number of hours the plant is used on the contract. A cost centre is set up for each machine. An estimate is made is made of the cost such as maintenance, depreciation, driver’s wage etc. to be incurred. The total of this cost is divided by the number of hours that the machine is expected to be used. Profit on Incomplete Contract: In the case of a small contract extending over the financial period, profit or loss on the same may be ascertained by crediting it with the contract price due by the contractee. This procedure cannot be adopted in the case of contracts extending beyond the accounting period and taking a long time for completion. If there is any profit from the incomplete contract, it cannot be taken as actual profit. The profit from the incomplete contract is called notional profit. For determining the amount of profit to be transferred to profit and loss account and making provision for future contingencies, the following guidelines may be kept in mind. 1. When the work has not reasonably advanced (¼ or less than ¼): No profit should be taken to the credit of p/L account in the case of contracts which have just commenced, and a small portion of the work is complete. 2. Where the work is complete more than ¼ but less than ½ of contract price: In this case 1/3 of the notional profit as reduced by the percentage of cash received may be credited to profit and loss account. The usual formula is: 1 Cash Received Notional Profit x ------ x ----------------------3 Work Certified The balance of notional profit shall be kept as reserve till the completion. 3. If the contract completed is more than ½ but less than 90%: Here 2/3 of the notional profit should be taken to profit and loss account. 2 Cash Received Notional Profit x ------ x ----------------------3 Work Certified The balance of notional profit shall be transferred to Work in progress as reserve. It is to be noted that to find out how much portion of contract is completed, work certified should be compared with contract price. 4. If the contract is nearing completion: Here, estimated profit may be ascertained by deducting the total cost of the contract to date plus estimated additional expenses to complete the contract, from the contract price. It is calculated by using the following formula: BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting Job, Batch, Contract Costing Cash Received Estimated Profit x ----------------------Work Certified The loss on an incomplete contract should be fully transferred to the profit and loss account. Exercises: Exercise-1: The following was the expenditure on a contract for Tk. 600,000: Amount (Tk.) Material 120,000 Wages 164,000 Plant 20,000 Overheads 8,600 The cash received on account of the contract was Tk. 240,000, 80% of the work certified. The Value of material in hand was Tk. 10,000. The plant has undergone 20% depreciation. To Materials To Wages To Plant To Overheads To Notional Profit C/D (B/F) To Profit and Loss A/C To Balance C/D Contract Account Amount (Tk.) 120,000 By Material in Hand 164,000 By Plant in Hand 20,000 By Work Certified [(240,000 x 100) ÷ 80] 8,600 13,400 326,000 7,147 By Notional Profit B/D 6,253 13,400 Amount (Tk.) 10,000 16,000 300,000 326,000 13,400 13,400 Exercise-2: XY Ltd signed a contract, the following was the expenditure on a contract for Tk. 600,000. Amount (Tk.) Materials issued to contract 102,000 Plant issued for contract 30,000 Wages 162,000 Other expenses 10,000 Cash received on account of contract up to 31st March 2024 amounted to Tk. 256,000 being 80% of work certified. Of the plant and material charged to the contract plant costing Tk. 3,000 and material costing Tk. 4000 were lost. On 1st March 2024, Plant which cost Rs. 2,000 was returned to the store, the cost of work done but not certified was Tk. 3,000 and material costing Tk. 2,500 were in hand on site. Provide 10% depreciation on plant, reserve 1/3 of profit received and prepare contract account from the above particulars. Contract Account Amount (Tk.) Amount (Tk.) To Materials 102,000 By Work-in-Progress: To Plant 30,000 By Work Certified [(256,000 x 100) ÷ 80] 320,000 To Wages 162,000 By Work Uncertified 3,000 323,000 To Other Expenses 10,000 By Profit and Loss Account: To Notional Profit C/D (B/F) 52,800 Plant Lost 3,000 Material Lost 4,000 7,000 By Plant Returned 2,000 Less: Depreciation 200 1,800 By Material in Hand 2,500 By Material on Site (30,000 – 3,000 – 2,000) 25,000 Less: Depreciation 2,500 22,500 356,800 356,800 To Profit and Loss A/C By Notional Profit B/D 52,800 [(52,800 x 2 x 80) ÷ (100 x 3) 28,160 To Reserve (B/F) 24,640 52,800 52,800 BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong ACC-4807: Advanced Cost Accounting To Contract Account Job, Batch, Contract Costing Work-in-Progress Account Amount (Tk.) 323,000 By Contract Account Reserve By Balance C/D 323,000 Amount (Tk.) 24,640 298,360 323,000 Exercise-3: Mr. Nazmul has undertaken several contracts works. He maintains a separate record for each contract. From the records for the year ending 31-12-23, Prepare contract account for Contract No. 50 and find the amount transferred to profit and loss account. Amount (Tk.) Direct purchase of material 180,000 Material issued from stores 50,000 Wages 244,000 Direct expenses 24,000 Machinery purchased 160,000 Establishment charges 54,000 The contract price was Tk. 1,500,000. Cash received up to 31-12-2023 was Tk. 600,000 which is 80% of work certified. Material at site Tk. 16,000. Depreciation for Machine Tk. 16,000. Contract Account Amount (Tk.) Amount (Tk.) To Materials Direct Purchase 180,000 By Material at Site 16,000 To Material issued from Store 50,000 By Machinery on Hand (160,000 – 16,000) 144,000 To Wages 244,000 By Work Certified [(600,000 x 100) ÷ 80] 750,000 To Direct Expenses 24,000 To Machinery Purchased 160,000 To Establishment 54,000 To Notional Profit C/D (B/F) 198,000 910,000 910,000 To Profit and Loss A/C By Notional Profit B/D 198,000 [(198,000 x 2 x 80) ÷ (100 x 3) 105,600 To Work in Progress Account 92,400 198,000 198,000 BBA-Major in Accounting & Information Systems, Department of Business Administration, International Islamic University Chittagong