Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 1 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) PROJECT: PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) COMPANY: PETRONAS CHEMICALS METHANOL SDN. BHD. CONTRACT NO.: RFP-000000059837 DOCUMENT TITLE: Project Procurement Plan DOCUMENT REVIEW CLASSIFICATION: X SECURITY CLASSIFICATION: INTERNAL USE A 19-NOV-23 Rev Date IFR Description SM Prep’d By TS Rev’d By KD App’d By SWA WATER ENGINEERING SB Rev’d By Endor’d By App’d By COMPANY © 2023 PETROLIAM NASIONAL BERHAD (PETRONAS). All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright OWNER. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 2 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) TABLE OF CONTENTS 1.0 PROJECT INTRODUCTION ........................................................................................... 4 2.0 PURPOSE ....................................................................................................................... 8 3.0 SCOPE............................................................................................................................ 8 4.0 DEFINITIONS AND ABBREVIATIONS ........................................................................... 8 5.0 REFERENCES ................................................................................................................ 8 6.0 PROCUREMENT STRATEGIES ..................................................................................... 9 7.0 CONTRACTOR’S PROCUREMENT ORGANIZATION CHART ....................................10 8.0 COORDINATION WITH ENGINEERING, CONSTRUCTION AND COMMISSIONING ..14 9.0 PROCUREMENT PROCESS / PROCEDURE................................................................14 10.0 SUPPLIERS AND BIDDERS LIST .................................................................................14 11.0 PROCUREMENT OF CATEGORY ITEM .......................................................................16 12.0 MARKET SURVEY AND SCREENING ..........................................................................16 13.0 REQUEST FOR QUOTATION .......................................................................................17 14.0 PURCHASE ORDER .....................................................................................................20 15.0 DISTRIBUTION OF UNPRICE PURCHASE ORDER .....................................................22 16.0 MATERIAL PLANNING AND CONTROL ......................................................................22 17.0 SURPLUS MATERIALS ................................................................................................25 18.0 TEMPORARY STORAGE YARD ...................................................................................26 19.0 EXPEDITING..................................................................................................................26 20.0 SHIPPING AND TRANSPORTATION............................................................................27 Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 3 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 21.0 CUSTOMS CLEARANCE AND GOVERNMENT TAX EXEMPTION .............................28 22.0 IDENTIFICATION FOR DUTY LEVIES ..........................................................................29 23.0 VENDOR'S AND SUB-CONTRACTOR'S VDRL............................................................29 24.0 INSPECTION AND SURVEILLANCE ............................................................................30 25.0 QUALITY ASSURANCE AND QUALITY CONTROL .....................................................30 26.0 SPARE PARTS AND SPECIAL TOOLS ........................................................................31 27.0 ASSETS REGISTER ......................................................................................................31 28.0 VENDOR SUPPORT ......................................................................................................32 29.0 PERFOMANCE GUARANTEE / SECURITY ..................................................................33 30.0 PROCUREMENT CLOSE OUT ......................................................................................33 LIST OF ATTACHMENTS ATTACHMENT 1 - PROCUREMENT INTERFACE AND COORDINATION ATTACHMENT 2 - MARKET SURVEY SCREENING FORM ATTACHMENT 3 - BIDDERS APPROVAL LIST FORM ATTACHMENT 4 - AWARD RECOMMENDATION ATTACHMENT 5 - PROJECT VENDOR SUB CONTRACTOR LIST ATTACHMENT 6 - PROCUREMENT STATUS REPORT (PSR) ATTACHMENT 7 – LIST OF LONG LEAD ITEM ATTACHMENT 8 – TECHNICAL BID EVALUATION FORM ATTACHMENT 9 – PACKING, MARKING AND SHIPPING INSTRUCTION Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 4 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 1.0 PROJECT INTRODUCTION CONTRACTOR (SWA Engineering Sdn. Bhd,) has been awarded and entered into CONTRACT with the COMPANY for the WORKS in in accordance with the terms and conditions contained in SECTION 2- FORM OF AGREEMENT AND GENERAL TERMS & CONDITIONS of the PROJECT. CONTRACTOR’s SCOPE OF WORK includes the provision of all WORKS, permanent or temporary, necessary to execute and complete the WORKS and to allow CONTRACTOR to achieve all of its obligations under the CONTRACT. The SCOPE OF WORK includes project management, Detailed Engineering Design, interface with other parties, acquiring PERMITS, Procurement, Construction, PRE-COMMISSIONING, COMMISSIONING, HANDOVER, all technical directions, supports and assistance to COMPANY required for START-UP, PERFORMANCE TESTS, and rectification of DEFECTS during WARRANTY PERIOD in accordance with the CONTRACT. 1.1 PROJECT INFORMATION PROJECT NAME PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD., LABUAN, WILAYAH PERSEKUTUAN, MALAYSIA (META) LOCATION LABUAN, WILAYAH PERSEKUTUAN, MALAYSIA PETRONAS Chemicals Methanol Sdn. Bhd. (PCMSB) Plant 1 and Plant 2 are currently experiencing industrial effluent discharge noncompliance, whereby the aqueous process effluents are not able to be treated via existing facilities up to Standard B limit, Industrial Effluent Regulation (IER 2009) prior to release into sea. COMPANY intends to build a Wastewater Treatment Plant Facilities (hereinafter referred to as “FACILITIES”). The FACILITIES shall enable treatment of various effluent streams to ensure compliance to the Industrial Effluent Regulations 2009. Below main FACILITIES aspects have been identified to address the solutions: 1. Open To build a new Wastewater treatment plant at Plant 1 treating the industrial effluents from Plant 1 and Plant 2 Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 5 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 2. To build new check basins at Plant 1 & Plant 2 as retention ponds for several low strength effluents 3. To build new Stream stripper at Plant 1 pre-treating effluent containing high methanol content All the effluent streams shown in Process Flow Diagram (EXHIBIT 20-5-3B PROCESS ENGINEERING SPECIFICATIONS) shall be included as the feedstock in the design of the FACILITIES. PETRONAS Chemicals Methanol Sdn Bhd (PCMSB), Plant 1 and Plant 2 are located at Wilayah Persekutuan Labuan, Malaysia and is in close proximity to the international shipping lane in the South China Sea. CONTRACTOR’S Project objective is to provide EPCC services to build a Wastewater Treatment Plant Facilities (hereinafter referred to as “FACILITIES”). The FACILITIES shall enable treatment of various effluent streams to ensure compliance to the Industrial Effluent Regulations 2009 on time, on budget and deliver expected performance and quality with zero accident/incident. No. 1 Open Milestones EFFECTIVE DATE (ED) 2 Issuance of Purchase Orders (PO) for the last Long Lead Item (LLI) Note: POs for all LLIs shall be issued by the fourth month from ED. 3 Delivery of last LLI to SITE 4 MECHANICAL COMPLETION DATE (MCD) 5 READY FOR START-UP (RFSU) 6 INITIAL ACCEPTANCE (IA) 7 Approval of Final Documentation by COMPANY Date T0 (20th Oct. 2023) T0+M4 (19th Feb. 2024) T0+M16 (19th Feb. 2025) T0+M21 (19th Jul. 2025) T0+M24 (19th Oct. 2025) T0+M25 (19th Nov. 2025) T0+M28 (19th Feb 26) Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 6 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 8 1.2 FINAL ACCEPTANCE (FA) 12 Months from IA* PARTY INVOLVED Parties involved are as follows: 1.3 (i) COMPANY – PETRONAS CHEMICAL Methanol Sdn Bhd (update as per SECTION 2- FORM OF AGREEMENT AND GENERAL TERMS & CONDITIONS) (ii) OWNER – PCMSB*deleted* (iii) CONTRACTOR – SWA Water Engineering Sdn. Bhd (iv) Any other parties (v) VENDOR and SUB-CONTRACTOR – any party or parties (other than the COMPANY), that has or have entered into a contract directly or indirectly with the CONTRACTOR and of any tier, including but not limited to suppliers or vendors of GOOD for the performance of any part of the WORKS. BATTERY LIMIT The Battery Limit within the CONTRACTOR’s scope shall be from the tie-in points of the existing PLANT including the new FACILITIES, but not limited to the following: • Methanol stripping pretreatment system • Effluent collection and transfer facilities • Biological treatment system • Sludge collection and dewatering • Final effluent and check basins Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 7 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) Illustration of the Battery Limit of the PROJECT can be referred in EXHIBIT 17 PROJECT INTERFACE, TIE-INS & BATTERY LIMIT. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 8 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 2.0 PURPOSE This Project Procurement Plan which outlines the procedures and schedule to be implemented by CONTRACTOR for carrying out all procurement and related services as required by the CONTRACT. 2.1 RESPONSIBILITY CONTRACTOR’S Project Procurement Manager (PPM) is responsible in implementation, monitor and update this Project Procurement Plan. PPM is given full authority to delegates and assigned the tasks to his/her Procurement Team to ensure provision of this procedure is achieved timely and quality. 3.0 SCOPE Scope of this Project Procurement Plan covers CONTRACTOR procurement activities necessary to manage, control, evaluate, procure, expedite, inspect (including provision of independent Third Party inspection), transport, ship, load and unload, deliver to SITE and preserve all EQUIPMENT, MATERIALS, SPARE PARTS, Special Tools, Consumables, lubricants and chemicals and any other items required for the WORKS through to the final location at SITE, all in accordance with the requirements specified in the CONTRACT. 4.0 DEFINITIONS AND ABBREVIATIONS Definitions and abbreviations being in this document has similar meaning as per ARTICLE 2 of SECTION 2- FORM OF AGREEMENT AND GENERAL TERMS & CONDITIONS. 5.0 REFERENCES In preparing this Project Procurement Plan, the following document has been referred and shall take precedent over this Project Procurement Plan 1. Open SECTION 2: CONTRACT DOCUMENTS, EXHIBIT 6 – PROCUREMENT (REV 2) Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 9 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) The PPM is responsible to ensure all provision as described in EXHIBIT 6 and this document shall be performed as stated 6.0 PROCUREMENT STRATEGIES CONTRACTOR procurement strategies designed to support overall project management team to achieved Project Objective and Milestone. CONTRACTOR has identified following key factors and its strategies is described in this Project Procurement Plan. No 1 Key Factors Proper Procurement Scheduling Key Strategies Correct timelines of each activity, shipment, logistic and approval requirement 2 Competitive procurement 3 4 5 6 VENDOR or SUB-CONTRACTOR selection through market survey, tendering, TBE, CBE and expediting Capability and performance of VENDORS and SUB-CONTRACTOR VENDOR progress monitoring Expediting Long Lead Item Delivery (LLI) Identification procurement of LLI and early Unexpected natural disaster such as To follow government instruction COVID19 7 Competent Project Team 8 Alignment among all project team Clear job scope, responsibility matrix. member 9 Geographical Challenge Procurement Org. Chart, Training Initial survey, screening, site visit Control procedure in monitoring, managing and reporting of each activity and its progress is listed on List of Attachment. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 10 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 6.1 LiST OF PROCUREMENT CONTROL DOCUMENTS 1. 2. 3. 4. 5. 6. 7. 8. 7.0 Attachment 1 - Procurement Interface and Coordination Attachment 2 - Market Survey Screening Form Attachment 3 - Bidders Approval List Form Attachment 4 - Award Recommendation Attachment 5 - Project Vendor Sub Contractor List Attachment 6 - Procurement Status Report (PSR) Attachment 7 – List of Long Lead Item Attachment 8 – Technical Bid Evaluation Form CONTRACTOR’S PROCUREMENT ORGANIZATION CHART Project Manager Dr Khailash Dhasan Project Procurement Manager Tamarai Muthusamy Senior Procurement Executive Procurement Expeditor Logistic Coordinator/ MATCO 7.1 JOB DESCRIPTION, RESPONSIBILITY OF PROCUREMENT KEY PERSONNEL 7.1.1 PROJECT PROCUREMENT MANAGER • • Open Direct, plans, organizes, oversees, coordinates, and manages the staff and operations of the project procurement, expediting and logistic. Work with other functional head to develop project procurement strategies toward successful project delivery. Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 11 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) • • • • • • • • • • • 7.1.2 SENIOR PROCUREMENT EXECUTIVE • • • Open Coordinate with all discipline i.e., Planning, Engineering, Construction, Commissioning, warehouse to ensure proper scheduling and movement of goods or services. Co-ordination of procurement activities, ensuring effective support is provided to the project Accountable for review and (in absence of Project Manager, approved) of Bidder Approval List and purchase order to SUB-CONTRACTORS. Prepare, update and present Procurement Status Report on weekly and monthly basis. Ensure procurement key dateline such as screening, vendor selection, TRP, RFQ, TC, TBE, CBE is being met Accountable for reviewing and approving suppliers request for payment with respect to SUB-CONTRACTORS, ensuring all obligations are met before payment. Ensure all contract and purchase order close-out is undertaken in a timely manner including the resolution of claims as and when required. Oversee shipment, transportation and logistics services from suppliers to SITE, to meet required on-site dates. Promote safety and awareness among supply chain and SUB-CONTRACTORS aimed at zero accident/incident rate. Ensure all procurement activities are in compliance with project procedures, specifications, regulations, HSE standards and QA/QC requirements. Report to Project Manager Carried procurement activities from market survey till issuance of purchase order as per approved plan and procedure. This cover: - correct vendors selection, prepare Bidder Approval List, compile complete RFQ documents (MR & TRP), issue a RFQ to approved bidders, - review completeness of vendor proposal, coordinate with other discipline to initiate and close queries (clarifications), - coordinate with other discipline in preparation of technical and commercial evaluation (TBE/CBE) and - Prepare recommendation to award to PPM - Ensure all necessary approval from COMPANY for each process obtained. - Issued un-price purchase order to COMPANY and all department i.e. Planning, Engineering, Construction, Commissioning and warehouse. Communicate and update other functional department on procurement activities. Support PPM in planning and coordinates the operations of the project procurement, expediting and logistic. Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 12 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) • • • • • • • • 7.1.3 PROCUREMENT EXPEDITOR • • • • • • • • • • • • • • • • Open Support PPM in preparing and update Procurement Status Report (PSR). Carried procurement key dateline within PSR timeline. Point of communication in between SUB-CONTRACTOR and CONTRACTOR (SWA). Ensure all contract and purchase order close-out is undertaken in a timely manner including the resolution of claims as and when required. Ensure shipment, transportation and logistics services from suppliers to SITE, to meet required on-site dates. Adhere to safety promotion and awareness among supply chain and SUBCONTRACTORS aimed at zero accident/incident rate. Adhere strictly to procurement procedure compliance, project procedures, specifications, regulations, HSE standards and QA/QC requirements. Report to Project Procurement Manager Confirm SUB-CONTRACTOR’s understanding of all deliverables and that the submission or delivery requirements match the project/operation expectations. Review and analyze SUB-CONTRACTOR’s document and data submittal plans. Oversee shipment, transportation and logistics services from suppliers to SITE, to meet required on-site dates. Obtain copy of SUB-CONTRACTOR’s production schedule, confirm the supplier has a complete and capable plan for meeting the delivery requirements Evaluate the SUB-CONTRACTOR’s plans and ability to meet the schedule Identify potential and actual disruptions in the SUB-CONTRACTOR’s submission and delivery schedules Develop and present to the management alternatives for the SUB-CONTRACTOR to improve performance Lead or support the implementation of selected actions to avoid or minimize the impact of SUB-CONTRACTOR schedule disruptions on delivery Perform other procurement discipline tasks such as logistics coordination and material receiving Coordinate material transportation requirement with third party freight forwarder as per agreed shipping terms on Purchase Order Monitor goods arrival at warehouse for material receipt and transfer Consolidate orders at warehouse to keep freight forwarding costs to a minimum Coordinate material transportation requirements with third party freight forwarder Advise PPM on freight forwarding cost against contract rates Authorize freight invoices, receive order arrivals and input shipment status in PRS Other duties as assigned Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 13 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) • • • 7.1.4 LOGISTIC COORDINATOR / MATERIAL CONTROLLER (MATCO) • • • • • • • • • • • • Open Adhere to safety promotion and awareness among supply chain and SUBCONTRACTORS aimed at zero accident/incident rate. Adhere strictly to procurement procedure compliance, project procedures, specifications, regulations, HSE standards and QA/QC requirements. Report to PPM. Responsible for the efficient and effective execution of the inventory control and material storage/distribution processes for efficient movement and transfer to user (i.e., construction, commissioning). Inspect, examines goods or materials received to verify its conformance against purchase specifications. Status of inspected goods or materials must be easily identified and segregated to its classification (such as accepted, rejected or hold). Store goods and materials according to manufacturer recommendation i.e., contamination prevention, open/covered storage, climate control for sensitive component (i.e., electronic or electrical) and its preservation. Clearly identified non-conforming items received and with correction action such as defective, wrong specification, incorrect quantities or poor qualities. Informed Senior Purchasing Executive and Expeditor status receiving inspection and clearly stated the discrepancies, if any. Plans, schedules and coordinates warehouse goods movements to ensure timely availability and delivery of materials and equipment. Arranged transport of materials/equipment from warehouse to SITE. Compiles and maintain manual or computerized records such as material inventory, delivery order and status and location of materials. Take delivery for spares and stored correctly. Check if the items are satisfied that the quantities and specification of the delivered goods match the information on the order. Receive order arrivals and input shipment status in PRS Adhere to safety promotion and awareness among supply chain and SUBCONTRACTORS aimed at zero accident/incident rate. Adhere strictly to procurement procedure compliance, project procedures, specifications, regulations, HSE standards and QA/QC requirements. Report to PPM. Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 14 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 8.0 COORDINATION WITH ENGINEERING, CONSTRUCTION AND COMMISSIONING Coordination and interface for procurement activities from vendors selection till released of materials, goods and/or equipment to construction and, in case of warranty period, to warranty personnel can be refer TO ATTACHMENT 1 – PROCUREMENT INTERFACE AND COORDINATION. Person In-Charge (PIC) is responsible person to ensure procurement activities and task achieved within dateline. 9.0 PROCUREMENT PROCESS / PROCEDURE Once list of MATERIALS and EQUIPMENT to be procured received from engineering or construction, procurement activities shall start with supplier identification and selection, identifying Long Lead Item, critical items or services example Detailed Engineering Design Services. 10.0 SUPPLIERS AND BIDDERS LIST Sub-Contractor, vendors or bidder’s list shall be prioritized as per EXHIBIT 6 – PROCUREMENT (REV2) item 6.4 SOURCE OF EQUIPMENT, MATERIALS, SUPPLIES AND SERVICES, which as follows: i. ii. iii. iv. v. engage Vendor / Original Equipment Manufacturer (OEM) for Category Items; engage PETRONAS’ Vendor Development Program (VDP) vendors; engage companies listed based on the COMPANY’s Recommended Brand as per ATTACHMENT 3 - LIST OF RECOMMENDED BRANDS of this EXHIBIT 6.; engage COMPANY’s PRE-APPROVED SUBCONTRACTOR/VENDOR as listed as per ATTACHMENT 4 - LIST OF PRE-APPROVED SUBCONTRACTORS; engage PETRONAS’ licensed and/or registered companies of this EXHIBIT 6.; The PPM shall ensure that the all SUBCONTRACTOR’s PETRONAS License/ Registration shall remain valid throughout the CONTRACT PERIOD. If any of the required EQUIPMENT, MATERIALS, SUPPLIES or SERVICES is not listed in the PROJECT’s Vendor List, the CONTRACTOR shall pre-qualify its VENDORs and Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 15 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) SUB-CONTRACTORs; and provide the following evidence/supporting document for COMPANY review and approval: i. ii. iii. iv. v. vi. vii. viii. 10.1 Capabilities to meet the specifications, applicable codes and workmanship standards; Capabilities to perform the WORKS proposed; Evaluation of VENDOR’s quality system; Financial stability; Technical support and after sales services; Company profile, experience, track record; Capabilities of meeting schedule as required by the CONTRACT; and Authorized local Malaysian agents/representatives (if any, for foreign supplier/manufacturer). PROJECT VENDOR LIST The PPM will prepare, maintain and submit the Project Vendor List (PVL) for all MATERIALS, EQUIPMENT and SUPPLIES to be procured by CONTRACTOR for COMPANY’s approval. The Project Vendor List (PVL) is a confidential document and at all times, shall be treated as such by all recipients. PVL consists Mandatory and Approved Vendor List as per ARTICLE 6.6.1 and CONTRACTOR’S Proposed Vendor as per 6.6.2 of EXHIBIT 6 – PROCUREMENT (REV 2) Upon COMPANY’s request, CONTRACTOR will provide a detail list of all approved VENDOR, SUBCONTRACTOR and/or manufacturers for all items purchased for the EQUIPMENT and MATERIAL with the following information: a) Equipment tag no.; b) Name of Local (Malaysian) Agent/Company; c) Name of VENDOR, SUBCONTRACTOR and/or manufacturer; d) Address; e) Telephone and facsimile no.; f) Name of contact person; and g) Description of MATERIALS or EQUIPMENTS Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 16 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 10.1.1 CONTRACTOR'S PROPOSED VENDOR CONTRACTOR acknowledged the Specific Vendor List (SVL) is limited against materials and equipment to be procured. CONTRACTOR will develop CONTRACTOR’S Proposed Vendor list based on PETRONAS License selected under applicable SWEC and PETRONAS Registered companies. Where no such companies are not able to deliver or viable to operate in Labuan, CONTRACTOR will submit additional propose vendor list to COMPANY for review and approval. Requirements as stipulated in EXHIBIT 6 item 6.6.2 will be strictly followed. The PPM will coordinate with CONTRACTOR’s Quality Department, HSE and relevant discipline in carrying technical appraisal of the VENDORS. The PPM will submit the Qualification Dossier Document (QDD) to COMPANY for approval, allowing fifteen (15) days prior to issuance of SVL. No procurement activities shall be sought from any VENDORS until the VENDOR is approved to be included into PVL and SVL by COMPANY, unless otherwise being officially instructed or agreed by the COMPANY. Requirement for appraisal and submission of QDD on PETRONAS License and PETRONAS Registered companies is not applicable because these companies already appraised by PETRONAS. 11.0 PROCUREMENT OF CATEGORY ITEM The PPM or Senior Procurement Executive shall undertake and ensure that all CATEGORY ITEMS are sourced through the Global Frame Agreement (GFA) or Frame Agreement (FA) or Price Agreement (PA) so established by the respective CATEGORY MANAGER as stipulated in ATTACHMENT 2 - LIST OF CATEGORY ITEMS AND CATEGORY MANAGER of this EXHIBIT 6. 12.0 MARKET SURVEY AND SCREENING The PPM may at his sole discretion, conduct Market Survey and Screening exercise to assess vendor’s willingness and capabilities. Results from Market Survey and Screening exercise can be used by Procurement to shortlist potential Vendor. Shortlisted vendor shall be pre-approved by COMPANY prior issuance of RFQ. Market Survey and Screening exercise must be carried using ATTACHMENT 2 – MARKET SURVEY & SCREENING FORM. Bidders Approval List for COMPANY approval must be carried using ATTACHMENT 8 – BIDDERS APPROVAL LIST FORM. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 17 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 13.0 REQUEST FOR QUOTATION Request for Quotation (RFQ) is a process to invite approved bidders or service providers to submit their quotation and stand a chance to supply or provide goods or services. Once CONTRACTOR received the price quotations, successful vendor can be chosen that best matches criteria for goods or services. All bidders shall be given equal information and opportunities in a fair and ethical manner. RFQ is essential process for CONTRACTOR procurement activities. The RFQ documents will be the basis for TBE, CBE and Purchase Order. Contents of the RFQ where applicable: • • • • • • • • • • • • • Open Letter of Invitation/Cover Letter with clear date of issuance and BID CLOSING DATE (BCD) CONTRACTOR’s RFQ Standard Documents - Bid Acknowledgement Form - Bidder’s Form of Particulars - Deviation List Form - Terms and Conditions (Corporate Terms or Project Terms) - Vendor Integrity Attestation - Bidder Quality Program requirements based on ISO 90001:2000 or equivalent - Bidder HSE requirements Project name and location Identification of COMPANY (PC Methanol Sdn. Bhd.) as ultimate OWNER. Applicable Code & Standard Instruction to Bidder Scope of Works/Supply Essential specification for products or services to be source e.g., data sheets, specification, personnel requirement, etc. Inspection and testing requirement; ITP, Performance Test with clear reference to applicable standard for methods and acceptance. VENDOR data submittal requirement such as VDRL/MDL Recommended Spare Part List VENDOR Past Experiences VENDOR Current and Expected Workload Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 18 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) The PPM or Senior Purchasing Executive shall manage and coordinate with other department to obtain and compile while ensuring issuance of RFQ to approved bidders is within dateline. 13.1 RFQ ADDENDUM AND VENDOR BID CLARIFICATION During tendering period i.e., from RFQ issuance date till BCD, CONTRACTOR may issue tender addendum due to changes in project requirements. Bidders are allowed to seek bid clarifications and CONTRACTOR must address each of Bidder’s clarifications fairly. The PPM or Senior Procurement Executive shall coordinate with other department e.g., Engineering, Construction, Commissioning, QSHE etc. in getting all clarification responded in timely manners. Unless otherwise specified, last dateline for Bidders to issue any clarifications shall be one (2) week before BCD. 13.2 TECHNICAL BID EVALUATIO (TBE) AND VENDOR & SUB-COONTRACTOR SELECTION RFQ shall be the basis of TBE and Vendor & Sub-Contractor proposal evaluation. Evaluation criteria shall base on: • • • • Completeness of Bidder’s proposal and its quality HSE requirements Quality Management System Scope of Works, requirement for technical specification and performance of the goods or services. • Deviations In complete submission or poor quality may cause Bidder’s proposal being rejected subject to approval by the PPM. Each element of the RFQ requirements must be thoroughly evaluate by qualified personnel. This must be coordinated by the PPM or Senior Procurement Executive. The PPM or Senior Procurement Executive and qualified personnel (TBE Evaluation Team) carrying the TBE shall seek confirmation and clarifications on deviations, ambiguous, inconsistency and/or unusual statement or proposal by Bidder. CONTRACTOR’s evaluation team shall select, evaluate and appoint local or foreign VENDOR and/or SUBCONTRACTOR in accordance with the PROJECT requirements. Only VENDOR and/or SUBCONTRACTOR whose quotations are in compliance with HSE requirements, approved technical specifications and drawings shall be considered Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 19 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) acceptable. Any deviations from the approved specification must have written approval by COMPANY prior to award. COMPANY shall have the option to participate in the HSE and technical assessment/ evaluation and / or subsequent clarification meetings with VENDOR and/or SUBCONTRACTOR. For better understanding of RFQ requirements and timely response by Bidders, the PPM may called for Face-to-Face Clarifications Meeting in between CONTRACTOR and Bidder. Conclusion from Face-to-face meeting must be recorded and treated similar to written clarifications and will be part of evaluation basis. TBE exercise must be recorded and summarize using ATTACHMENT 8 – TECHNICAL BID EVALUATION. Conclusion by TBE Evaluation Team, lead by the PPM or Senior Procurement Executive must clearly state its finding and recommendation. Technical Bid Evaluation report must contain the followings: a) Names and address of the companies invited to quote or bid; b) Technical evaluation report / summary which shall include any deviation to the specification (if any); c) Recommended VENDOR / suppliers; d) Reason for Selection; e) Evaluation of VENDOR / SUBCONTRACTOR quality system and execution plan; f) Evaluation of VENDOR / SUBCONTRACTOR HSE compliance including site access requirement and relevant training records; g) Scheduled Award Date; h) Quoted Delivery Date; i) Reason(s) for rejecting unsuccessful bidders whether it is technical, commercial, delivery etc. 13.3 Open ACCETANCE OF DEVIATION Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 20 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) All deviations, if accepted, must be justified, and obtained approval by COMPANY prior to award. Where deviations involve materials, the PPM or Senior Procurement Executive shall submit Material Approval Form as stipulated in ATTACHMENT 7 – MATERIAL APPROVAL FORM / DEVIATION REQUEST of EXHIBIT 6, for COMPANY’s review and approval in accordance with the drawings, specification and the CONTRACT. 14.0 PURCHASE ORDER Based on the conclusions of the TBE and CBE, Senior Procurement Executive must prepare ATTACHMENT 4 - AWARD RECOMMENDATION which shall be approved by the PPM and Project Manager. No PURCHASE ORDER can be issued as long as COMPANY has not formally approved the corresponding documents such as Specifications, Datasheet, Material Requisitions, including TBE and Award Recommendation unless otherwise being officially instructed by COMPANY. Upon completion of the above processes i.e., TBE, CBE, Award Recommendation with all approval by COMPANY obtained, the PPM can proceed with issuance of Purhase Order (PO) to successful SUB-CONTRACTOR. The Purchase Order must make reference to all clarifications, meetings and RFQ which shall be part of binding documents. The PPM shall extend one (1) copy of unpriced Purchase Order to COMPANY (including its attachment and appendices) for every EQUIPMENT, MATERIALS purchased. Senior Procurement Executive must report procurement activities as per Attachment 6 Procurement Status Report (PSR). PSR is live documents and must be updated and submitted to COMPANY on weekly basis. 14.1 PURCHASE ORDER PARTICULARS As a minimum the following particulars shall appear on Purchase Order a. Project: PROVISION OF ENGINEERING, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICAL METHANOL LABUAN SDN. BHD. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 21 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) a) and Location: LABUAN, FEDERAL TERRITORY, MALAYSIA b) Both COMPANY and CONTRACTOR reference I. COMPANY: RFP-000000059837 II. CONTRACTOR: as per Purchase Order number c) PMT Name, Address and Contact Number; To be Advise d) Item, quantity and unit of measure; e) Description of MATERIALS or EQUIPMENT; f) MATERIALS, SUPPLIES, EQUIPMENT or SPARE PART(s) / Tag number; g) Agreed delivery date(s) for the MATERIALS or EQUIPMENT; h) VENDOR documents (required dates, number of copies) with submission and approval matrix (i.e., CONTRACTOR, inspection agencies, COMPANY, DOSH etc) i) Statement on option clause for one (1) year for placement order for recommended j) EQUIPMENT performance guarantee; k) Warranty period required; l) Reference to Quality Assurance (QA) requirements; m) Production/delivery schedules(s) n) Inspection requirement whether by its own independent inspection, inspection agency or DOSH. o) Procedure to be followed by SUB-CONTRACTOR throughout PURCHASE ORDER duration. p) In case of MATERIAL or EQUIPMENT is subject to COMPANY inspection, a statement that “COMPANY representative or its nominees shall have access to SUB-CONTRACTOR and sub-vendor’s shop during all stages of manufacturing and testing”. The Purchase Order must have instruction to prime VENDORs and SUB-CONTRACTORs to put above identification on all purchase inquiries, orders, etc. issued to secondary VENDORs and SUB-CONTRACTORs. As a minimum Purchase Order from prime VENDORS to secondary VENDORS shall state item (a), (b), (c), (f) and (g) above. 14.2 VARIATION TO PURCHASE ORDER If a change to the design or to other essential requirement of the requisition is made after the PURCHASE ORDER is placed with VENDOR, the PPM shall issue a variation to the requisition and revise as required the relevant documents. The PURCHASE ORDER shall be amended as necessary to account for the change to the requisition. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 22 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) The PPM shall provide COMPANY revised UNPRICE PURCHASE ORDER which reflect all the changes including the relevant technical and commercial attachments. 14.3 VENDOR AND SUB-CONTRACTOR'S ACKNOWLEDGEMENT OF PURCHASE ORDER The PPM or Senior Procurement Executive shall obtain written acknowledgement of compliance and guarantee from all VENDOR that they have accepted the PURCHASE ORDER terms and conditions and are proceeding accordingly. CONTRACTOR shall provide COMPANY with an un-priced copy of PURCHASE ORDER (with acknowledgement by the VENDOR / SUBCONTRACTOR(s)) with all relevant technical and commercial attachments specified under ARTICLE 6.5.3 – PURCHASE ORDER of this EXHIBIT 6. 15.0 DISTRIBUTION OF UNPRICE PURCHASE ORDER The PPM shall extend one (1) copy of UNPRICED PURCHASE ORDER, together with SUB-CONTRACTOR’S acknowledgement (including its attachment and appendices) for every EQUIPMENT, MATERIALS purchased to: a) COMPANY b) If applicable, i. Inspection Agency if applicable ii. Transport/Shipping Agent c) Shall be easily accessible to CONTRACTOR’S project team i. Engineering ii. Construction iii. Commissioning iv. Expeditor v. Warehouse & Logistic Note: all commercial figures and prices must not be stated into UNPRICE PURCHASE ORDER 16.0 Open MATERIAL PLANNING AND CONTROL Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 23 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) The PPM and Logistic Coordinator (MATCO) will prepare and submit materials management which includes: a. Inventory Management b. Warehousing Management c. Project surplus, overage, damage, scrap and discrepancies. 16.1 MATERIAL CONTROL The PPM and MATCO are responsible for the handling and control of EQUIPMENT, MATERIALS and SUPPLIES purchased and ensure that at minimum, below material control functions are performed: a. Receiving of EQUIPMENT, MATERIALS and SUPPLIES; b. Inventory Control; c. Safety; d. Warehousing and material preservation; e. Description of material handling equipment. MATCO must at all times maintain records detailing the above and shall make such records available to COMPANY upon request by COMPANY. Clear material traceability procedure must be employed. This material traceability procedure shall: a. b. c. d. Develop the traceability flowchart and distribute to relevant personnel Implement Positive Material Identification (PMI) on needs basis Segregation in between stainless steel and carbon steel Type of materials grouping such as pipe, fitting, fixtures, electrical, instrument, telecom etc. The followings functions shall be carried by MATCO as minimum: a. During daily stand up meeting and weekly meeting: i. Obtain latest information and data for time schedule, work progress, material status and other relevant documents such as material list, requisition and shipping documents. ii. Monitor construction time schedule and expeditiously coordinate for materials delivery to SITE. iii. Update the PPM and Construction on item (b) below b. Check stock inventory by discipline, forecast status from periodic and cumulated delivery from stock, and take counter-measure when required. c. Prepare and submit monthly material status report. d. Supervise material handling. e. Take action for excess, shortages, and damages of materials found. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 24 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) f. Coordinate with PPM and Senior Procurement Executive to solve problem of materials such as conflict with drawings or specifications, in coordination with the relating functions of the PROJECT The PPM and MATCO must identified and establish adequate space for followings areas: No Description Type of Materials Store 1 Receiving & Inspection Area for open and covered storage Receiving inspection 2 Hold or Reject Area for open and covered storage Hold or reject due to damage, incomplete / wrong deliveries 3 Office or Workstation For warehouse personnel 4 Open Area 5 Covered Area / Warehouse Bricks, sand, aggregate, steels, pipes, large fittings Segregated to avoid contamination and sectionalize by type (i.e., mechanical, electrical, fittings, instrument. Easily damage due to exposure to moisture such as cement, paint 6 Climate Controlled Sensitive electronic, electrical, special tools etc. as per manufacturer recommendation. 7 Lockable Area High value, prone to theft materials 8 SPIR & Warranty Spares 9 Fragile 10 Surplus For fragile materials i.e., tiles, glass, sanitary Surplus 11 Disposal Waste – crate, boxes etc. 12 Construction & fabrication consumables Electrode, grinder, glue, nails, screw, cable ties etc. 13 DUTY Exempted Goods As required by Royal Malaysia Customs The PPM and MATCO must make provision and plan for a. Power supply for energizing space heater for panel and electrical equipment, when specified by manufacturer. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 25 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) b. Preservation as specified by manufacturer c. Segregation to avoid contamination and rust d. Walking access area, materials movement route and provision for materials handling. e. Safety f. Security & CCTV During daily stand-up meeting Expeditor shall update MATCO three (3) days in advance, expected arrival of cargo or shipment. MATCO shall inquire from Expeditor packing list, shipment size (dimension, weight, volume), materials handling requirement, storage requirement for warehouse planning. In case available storage area cannot accommodate the above requirement, PPM and MATCO must coordinate with VENDOR and SUB-CONTRACTOR for storage at VENDOR and SUBCONTRACTOR location, or any other location suitable. MATCO shall ensure planned delay of shipment will not affect Required-On-Site delivery by construction. 16.2 MATERIAL IDENTIFICATION See item 14 PURCHASE ORDER PARTICULARS 16.3 MATERIAL SUBSTITUTION Material substitutions shall not be made without the written approval of COMPANY. The PPM or Senior Procurement Executive shall submit Material Approval Form as stipulated in ATTACHMENT 7 – MATERIAL APPROVAL FORM / DEVIATION REQUEST of EXHIBIT 6, for COMPANY’s review and approval. The PPM or Senior Procurement Executive is responsible to record all duly approved substitutions and report them on an on-going basis. See item 13.3 ACCETANCE OF DEVIATION 17.0 Open SURPLUS MATERIALS Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 26 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) During construction period, all SURPLUS MATERIALS will be store at designated area. After completion of the project, CONTRACTOR will arrange for an inventory check with COMPANY. CONTRACTOR will ensure the SURPLUS MATERIAL are properly packed and all the required documentations are available. All SURPLUS MATERIAL record will be kept by CONTRACTOR and be submitted to COMPANY upon completion of the WORK/WORKS. On COMPANY instruction and approval, all SURPLUS MATERIALS shall be removed from SITE. No SURPLUS MATERIALS shall be left or remain at SITE . 18.0 TEMPORARY STORAGE YARD Temporary storage area/yard will be set up by CONTRACTOR within SITE. The layout of temporary storage yard will be submitted to COMPANY once the area identified for approval. Depending on materials and equipment to be temporarily stored at SITE, facilities for temporary storage yard management is similar to warehouse as per item Error! Reference source not found. Error! Reference source not found.. 19.0 EXPEDITING PPM, Project Manager and Engineering Manager CONTRACTOR Purchase Order is issued within timeline. is responsible to ensure Procurement Expeditor task and responsibilities start as soon as CONTRACTOR’s Purchase Order was acknowledged by VENDORs or SUB-CONTRACTOR. Duties and responsibilities of Procurement Expeditor is defined at Error! Reference source not found. Error! Reference source not found. and Attachment 1 – Procurement Interface and Coordination Procurement Expeditor must report in advance any indication which may suggest that a VENDOR or SUB-CONTRACTOR will be unable to maintain promised deliveries. Procurement Expeditor must anticipate problems areas and take action before delays occur. Procurement Expeditor must immediately inform the PPM, any deviations and PPM, must immediately report to COMPANY with explanations for each deviation from schedule and proposed action plan to correct the situations. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 27 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) Where practical, Procurement Expeditor must visit to VENDORS manufacturing facilities to check on progress, facilities workload, manpower and materials availabilities to anticipate delivery schedule. Evidence such prime VENDOR’S Purchase Order to secondary VENDORS, photos, VENDOR’S progress reports, schedule shall be kept. Expediting activities must be recorded at Attachment 6 - Procurement Status Report (PSR). PSR is live documents and must be updated and submitted to COMPANY on weekly basis. 20.0 SHIPPING AND TRANSPORTATION The PPM and Procurement Expeditor is responsible for coordination and delivery of EQUIPMENT, MATERIAL and SUPPLIES to SITE / WORKSITE. CONTRACTOR will engage Multimodal Transportation Operator (MTO) transporters for transportation of MATERIALS and EQUIPMENT required for the WORKS. Attachment 6 - Procurement Status Report (PSR) will be used by CONTRACTOR to monitor and report all shipment and deliveries. Document files and data regarding transportation, deliveries and receiving reports shall be kept current and available to COMPANY when requested. Attachment 8 – Packing, Marking and Shipping Instruction must be used by VENDOR and SUB- CONTRACTOR when preparing MATERIALS and EQUIPMENT for transportation, shipment to CONTRACTOR and documentation requirements. Notification to COMPANY for overseas consignment must include followings information but not limited to; a) Description of the EQUIPMENT, MATERIAL and SUPPLIES to be imported; b) Tonnage or cubic size as applicable; c) Port of Shipment Including Transhipment; d) Estimated Time of Departure (ETD); e) Mode of Shipment; f) Name of Carrier (Shipping Line); g) Port of Arrival; h) Estimated Time of Arrival (ETA); Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 28 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) i) Routing from Port of Arrival to the SITE / WORKSITE; and j) Name of Forwarding Company. 21.0 CUSTOMS CLEARANCE AND GOVERNMENT TAX EXEMPTION CONTRACTOR will engage Transport Agent to manages shipment of MATERIALS and EQUIPMENT from overseas. Procurement Expeditor will coordinate with Transport Agent by providing necessary information and shipping documentation to facilitates custom clearance. For MATERIALS that require Certificate of Approval (COA) from CIDB, CONTRACTOR will be prioritized procurement from manufacturer that has import similar MATERIALS into Malaysia. Evidence such as previous COA and Laboratory Test will be obtain to ensure similar products was successfully imported into Malaysia. To ensure importation of MATERIALS and EQUIPMENT smooth processing of importation, CONTRACTOR will - at least four (4) months prior to the arrival of the EQUIPMENT and MATERIALS at the port of embarkation, CONTRACTOR to complete EXHIBIT 6 Attachment 6 – DUTY EXEMPTION TABLE - plan for forty-five (45) to Sixty (60) days in advance for Customs Authority approval. - Where COMPANY assistance is required, CONTRACTOR will provide, within five (5) working days after importation, of original shipping documents and have available documents required for customs clearance, which include but not limited to a) Customs Declaration Form; b) Ocean Bills of Lading or Air Way Bills; c) Commercial Invoices; d) Packing Lists; e) Insurance Policy Certificate; f) Certificate of Origin; g) Inspection Certificate; and Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 29 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) h) Any other documents which may be required by the authority Information provided in EXHIBIT 6 Attachment 6 – DUTY EXEMPTION TABLE must match above shipping documentation. In addition to the above requirement, one (1) week after the importation of the MATERIALS, CONTRACTOR shall submit three (3) copies of the following information to COMPANY for all original shipping documents: together with a copy of the endorsed customs declaration form for the respective imported MATERIALS: a) Endorsed customs declaration form; b) Commercial invoice; c) Import registration number; d) Tally sheet from Port Authority; e) Description of MATERIALS; f) Make, brand, serial no. and model no.; g) C.I.F. price in Ringgit Malaysia; h) Date of Importation; and i) Quantity imported. 22.0 IDENTIFICATION FOR DUTY LEVIES The PPM and Senior Procurement Executive will indicate items will be imported and tabulated as follows: a) Insured value b) Estimated Import Duty and / or levies, taxes, etc. 23.0 Open VENDOR'S AND SUB-CONTRACTOR'S VDRL Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 30 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) Requirements for VEDOR’S and SUB-CONTRACTOR’S Vendor Data Requisition List (VDRL) shall be established during tendering. Refer to Error! Reference source not found. Error! Reference source not found.. The PPM and Procurement Expeditor shall obtain VDRL on sufficient quantities for internal review, recording and approval status, and transfer all of these documents to and from VENDOR and CONTRACTOR. At the early stage of purchase order, Procurement Expeditor shall coordinate, established and agreed with VENDOR and SUB-CONTRACTOR, format for VDRL as per PROJECT documentation. No MATERIALS or EQUIPMENT shall be released for shipment until VDRL have been formally approved by CONTRACTOR’s inspector and when applicable, Independent Inspection Agency. VDRL shall be received at SITE at least ten (10) working days prior to receipt of EQUIPMENT and MATERIALS at SITE. Status of VDRL must be reported using Attachment 6 - Procurement Status Report (PSR). PSR is live documents and must be updated and submitted to COMPANY on weekly basis. 24.0 INSPECTION AND SURVEILLANCE Requirements for inspection and surveillance of VEDOR’S and SUB-CONTRACTOR’S manufacturing activities shall be established during tendering. Refer to 13.0 REQUEST FOR QUOTATION The PPM and Procurement Expeditor shall coordinate with CONTRACTOR’s Quality Department in scheduling inspection and surveillance requirement. As a minimum following task or documents must be available for inspection and surveillance visit: a. b. c. d. 25.0 Open Copy of UNPRICE PURCHASE ORDER Inspection and Test Plan with clear matrix of HOLD and WITNESS point If applicable, Inspection Agency or Regulatory Inspection Approval Inspection of manufacturing quality record QUALITY ASSURANCE AND QUALITY CONTROL Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 31 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) CONTRACTOR’S Project Quality Management Plan describe management of project quality assurance and quality control being adapted. Prior to any inspection notification to CONTRACTOR or COMPANY shall be as follow: Notice Issued By Local Inspection Overseas Inspection To CONTRACTOR To COMPANY To CONTRACTOR To COMPANY CONTRACTOR - 2 weeks - 4 weeks VENDOR & SUBCONTRACTOR No less than 2 weeks 2 weeks (by CONTRACTOR) No less than 4 weeks 4 weeks (by CONTRACTOR) 26.0 SPARE PARTS AND SPECIAL TOOLS CONTRATCOR shall identified each MATERIALS and EQUIPMENT spares and special tools required during engineering. TRP shall clearly specified type and quantity of spares and special tools that must be supplied by VENDORS and SUB-CONTRACTOR. When requirement of spares and special tools is specified, VENDOR’S and SUBCONTRACTOR’S must quote and CONTRACTOR must ensure requirements for spares and special tools is included in Purchase Order. Refer to 13.0 REQUEST FOR QUOTATION. SECTION 2 EXHIBIT 6-C SPARE PARTS, CONSUMABLES & SPECIAL TOOLS must be used to register spares and special tools. 27.0 ASSETS REGISTER CONTRACTOR will compile the Asset Register throughout the duration of the CONTRACT. The Costs reflected in the Asset Register will be as accurate as the information available to CONTRACTOR at the time of submission. The Asset Register list must be updated progressively and the content of the Asset Register must be finalized by COMPANY. However, the actual cost must be reflected in the Asset Register at the end of the CONTRACT. The submitted Asset Register shall contain the estimated value for each identified item. The estimated value may change and reflect the actual cost including CONTRACTOR’s own cost when the identified item is delivered to SITE (or finished construction). Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 32 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) CONTRACTOR must keep record of all costs associated with Assets Register. Evidence must be made available COMPANY upon request to support tabulated cost in the Asset Register. 28.0 VENDOR SUPPORT CONTRATCOR shall identified REQUIREMENT FOR VENDOR SUPPORT during engineering and tendering stages. TRP shall clearly specified type of specialist expected from VEDNOR and SUB-CONTRACTOR to be mobilized during CONSTRUCTION, PRECOMMISSIONING, COMMISSIONING and START-UP. When requirement for VENDOR SUPPORT is specified, PPM must ensure the provision is included into PURCHASE ORDER. Refer to 13.0 REQUEST FOR QUOTATION. CONTRACTORS will ensure specialist engage from VENDOR and SUB-CONTRACTOR: a. Qualified and having competencies to perform the job. Resume of VENDOR and SUB-CONTRACTOR representative/specialist must be evaluated during TBE, prior to mobilization and if necessary, approved by COMPANY. b. Able to mobilization and demobilization to and from SITE (Labuan) as per required date and duration. c. Meet all permitting and safety requirement to work at SITE. CONTRACTOR must ensure all VENDOR and SUB-CONTRACTOR representative will undergo training, workshop or induction to facilitate approval of work permit or safety requirement. d. CONTRACTOR must ensure VENDOR and SUB-CONTRACTOR representative is legally allow to work at SITE throughout his mobilization and demobilization duration. CONTRACTOR’S Purchase Order must clearly state; “failure by VENDOR and SUBCONTRACTOR to comply with the above requirement will cause its representative to be demobilize immediately. All remedy to rectify the damages shall be solely under VENDOR and SUB-CONTRACTOR account. VENDOR and SUB-CONTRACTOR shall, upon notification by CONTRACTOR, rectify by arranging replacement prior to demobilization of existing personnel. Replacement personnel proposed by VENDOR and SUBCONTRACTOR shall meet similar requirement as stated”. SECTION 2 EXHIBIT 6-C SPARE PARTS, CONSUMABLES & SPECIAL TOOLS must be used to register spares and special tools. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision : A EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 33 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) 29.0 PERFOMANCE GUARANTEE / SECURITY When require, CONTRATCOR will require its VENDOR and SUB-CONTRACTOR to furnish its Performance Guarantee with format to be agreed later. Requirement for performance guarantee shall be clearly specified during tendering and if applicable, stated in CONTTRACTOR’S PURCHASE ORDER. 30.0 PROCUREMENT CLOSE OUT Upon completion of VENDOR and SUB-CONTRACTOR obligation to PURCHASE ORDER, PPM must initiate procurement close out process. One (1) copy of all files relating to goods and services procured for the CONTRACT will be included in Final Documentation. Each file shall contain but not limited to the following: a. Purchase Order and any amendments thereto; b. Purchase Requisition; c. Quotations; d. Bid Evaluations and its Criteria; e. Shipping documents; f. Import Documents; g. Catalogues; h. Specifications; i. Final Acceptance Testing Reports/ Mill Certificates; j. Invoices; and k. Site Progress Photos Notwithstanding the above, PPM shall ensure all procurement documentation is properly kept, and upon request, shall be available to COMPANY. Open Doc No: META-GEN-DD-SWA-0PUR-PLN-0002 Revision EPCC FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE Page 34 of 34 PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) LIST OF ATTACHMENTS ATTACHMENT 1 - PROCUREMENT INTERFACE AND COORDINATION ATTACHMENT 2 - MARKET SURVEY SCREENING FORM ATTACHMENT 3 - BIDDERS APPROVAL LIST FORM ATTACHMENT 4 - AWARD RECOMMENDATION ATTACHMENT 5 - PROJECT VENDOR SUB CONTRACTOR LIST ATTACHMENT 6 - PROCUREMENT STATUS REPORT (PSR) ATTACHMENT 7 – LIST OF LONG LEAD ITEM ATTACHMENT 8 – TECHNICAL BID EVALUATION FORM ATTACHMENT 9 – PACKING, MARKING AND SHIPPING INSTRUCTION . Open : A Procurement Plan ATTACHMENT 1 – Procurement Interface & Coordination Page 1/3 ENGINEERING PROCUREMENT PRE TENDERING PROCUREMENT EXECUTIVE • • • • • • • Technical Requisition Package Bill of Materials Purchase Specifications MDR Catalogues Mill Certificates Manuals • • • • • • • • • • TENDERING STAGE • • Evaluation Bidder proposal against TRP Technical Clarification Evaluate Technical Deviation, if any Accept/Reject Bidder’s Technical Proposal Technical Bid Evaluation • • • • • • • • • EXPEDITOR QUALITY & SHE LOGISTIC COORDINATOR / MATCO Market Survey, if any Bidders List Approval Material Requisition Float/Issue a RFQ Inter-dept coordination for tender/RFQ preparation Ensuring deadline of RFQ, BCD is met PIC • • • Inspection Test Plan Special inspection Establish vendor’s quality & safety system Coordinate Vendor’s queries Ensure completeness of Vendor’s proposal. Compliance to RFQ & Instruction to Bidders Compliance to Delivery Schedule Evaluate Commercial Deviation, if any Prepare Award Recommendation Ensuring deadline of TBE/CBE, PO is met Update PSR PIC • Evaluate vendor quality & safety system CONSTRUCTION AND WARRANTY PERIOD Procurement Plan ATTACHMENT 1 – Procurement Interface & Coordination Page 2/3 ENGINEERING POST PURCHASE / MANUFACTURING PROCUREMENT EXECUTIVE • • • • • Issue PO to Vendor Ensure PO acknowledged by Vendor Resolution on contract/commercial matters Review Vendor’s invoicing and payment Issue UNPRICE PO to COMPANY and other departments EXPEDITOR • • • • • • • • • • DELIVERY CONSTRUCTION PROCUREMENT • • • • LOGISTIC COORDINATOR / MATCO Review Vendor MDR submission plans Review and track vendor schedule Ensuring deadline of EXW/DAP, ROS is met Coordinate for inspection and release Ensure goods is suitably pack and mark Approved shipping documents Update PSR PIC Oversee shipment, route and transportation from Vendor (EXW) to SITE Notify Logistic on goods arrival. Ensure all customs clearance is in place Copy shipping documents to Logistic In case of seaport/airfreight, coordinate for clearance and ground transport to warehouse PIC • • Prepare warehouse for goods receiving such as area and handling equipment. Update PRS • • • Welders qualification Hold / Witness Test QC Surveillance/ Inspection • QA Documentation WARRANTY PERIOD Procurement Plan ATTACHMENT 1 – Procurement Interface & Coordination Page 3/3 ENGINEERING CONSTRUCTION PROCUREMENT PROCUREMENT EXECUTIVE EXPEDITOR LOGISTIC COORDINATOR / MATCO • • WAREHOUSING WARRANTY PERIOD • • • • • • Inspect, accept, reject or hold received goods Warehouse management Preservation Accept Vendor delivery Issued goods to construction / commissioning Update Material Inventory Update PRS PIC • Request construction materials, goods or equipment from warehouse • Request warranty spares from warehouse Project Procurement Plan ATTACHMENT 2 – Market Survey and Screening Form PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. SWA WATER ENGINEERING SDN BHD REQUEST FOR QUOTATION SCREENING / MARKET SURVEY Proj. Doc No SWA No: META-009-MSS-0001 REV Market Survey No : MSS-XXX Date : DD MMMM YYY To : All Vendors 1. BACKGROUND CONTRACTOR (SWA Engineering Sdn. Bhd,) has been awarded the contract for the above PROJECT. CONTRACTOR’s SCOPE OF WORK includes the provision of all WORKS, permanent or temporary, necessary to execute and complete the WORKS and to allow CONTRACTOR to achieve all of its obligations under the CONTRACT. The SCOPE OF WORK includes project management, Detailed Engineering Design, interface with other parties, acquiring PERMITS, Procurement, Construction, PRE-COMMISSIONING, COMMISSIONING, HANDOVER, all technical directions, supports and assistance to COMPANY required for START-UP, PERFORMANCE TESTS, and rectification of DEFECTS during WARRANTY PERIOD in accordance with the CONTRACT. 2. PROJECT INFORMATION PROJECT NAME PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD., LABUAN, WILAYAH PERSEKUTUAN, MALAYSIA (META) LOCATION LABUAN, WILAYAH PERSEKUTUAN, MALAYSIA CONTRACT NO RFP-000000059837 SWA JOB NO J000114 3. OBJECTIVE CONTRACTOR is conducting screening/market survey to assess VENDOR/SUPPLIER/MANUFACTURER capabilities and interest to supply item(s) as describe at following pages as per Terms and Condition stated therein PRODUCT / SERVICE Example WWTP Screw Press. Please refer to attached List 4. RESPONSE TO THIS SURVEY / SCREENING Project Procurement Plan ATTACHMENT 2 – Market Survey and Screening Form PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. SWA WATER ENGINEERING SDN BHD REQUEST FOR QUOTATION SCREENING / MARKET SURVEY Proj. Doc No SWA No: META-009-MSS-0001 REV This market survey / screening must be responded by email to on or before (enter closing date example) 15 NOV 2023 not later than 1700HRS; To : tamarai@swawater.com.au Copy : syedmuhammad@swawater.com.au Failure to response to this market survey/screening may results in Vendor will not be invited during tender exercise 5. VENDOR / MANUFACTURER’S REPLY We are interested/NOT interested* and confirmed will participate in this bid exercise *delete whichever not applicable Vendor / Manufacturer Name Brand / Principal Country of Origin Please advise Delivery Weeks, ARO EXW ______ weeks Does your company have valid PETRONAS for the product category* Does your company have QMS in compliance to ISO 9001 Does your company implement QSHE. If yes, please provide QSHE Policy *Mandatory supporting documents SIGNATURE Company: Contact Person : Telephone Nos. : E Mail : ** END OF THIS SECTION ** DUP Labuan_______weeks ☐ Yes ☐ No. ☐ Yes ☐ No. ☐ Yes ☐ No. Project Procurement Plan ATTACHMENT 3 – Bidders List Approval Form PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) SWA WATER ENGINEERING SDN BHD 1.0 BIDDERS LIST APPROVAL FORM Example 13141100S - The provision of manpower, services and project management for ICT consultancy Background Client PC METHANOL 3.0 Rev: 0 Date: SWA No: META-009-BLA-0001 Objective: To seek SWA & COMPANY (if applicable) approval for following services; Scope of Work Example Advance Work Package & 4D Scheduling Applicable SWEC 2.0 Proj. Doc No 4.0 PR No Mob Date RFQ Date Delivery KLHQ & Labuan Mode of Procurement ☒ Competitive ☐ Single/Sole Source ☐ Proprietary ☐ Safety Justification: example Market survey was issued to all 140 vendors for SWEC 13141100S. 2 responded fully i.e. named principal/software and 1 incomplete - not specifying its principal/software. Balance of the vendors did not response or cannot support this exercise. CONTRACTOR proposed to qualify all 3 responded Vendor to be invited as Bidder for this exercise (RFQ). All proposed vendors are having valid PETRONAS License. Vendor’s responses are attached Attachment 1 – XX Attachment 2 – YYY Attachment 3 – ZZZ 4.0 5.0 5.0 List of Proposed Bidder(s) No Bidders Name 1 XX 2 YYY 3 ZZ Approval * Note: Final selection is subject to Vendor proposal, TBE, CBE and compliance to PROJECT requirements Prepared By Reviewed Approved Buyer Procurement Manager Project Manager COMPANY Approval Project Procurement Plan ATTACHMENT 4 - Award Recommendation Form PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) AWARD RECOMMENDATION META-009-RFQ-0001/AR Reference RFQ No example, META-009-RFQ-0001 BLA No example, META-009-BLA-0001_REV04 TBE No example, META-009-RFQ-0001/TBE Other notes or reference example, BIDDER'S response to TC01 dated 3rd November 2023 Scope of Works / Services 1. example, DETAILED ENGINEERING DESIGN (DED) Successful BIDDER XXXX SDN BHD Conclusion example, Above BIDDER is recommended to be awarded contract for the above Scope of Works/Services based on ….. Note: Prepared & Recommended By Reviewed By Approved By ….................................................. ….................................................. Tamarai Selvi Procurement Manager ….................................................. Khailash Dhasan Project Manager Project Engineer COMPANY'S Approval ….................................................. Name Position Project Procurement Plan ATTACHMENT 5 - Project Vendor Sub Contractor List S W A W A T No 1 Discipline TUAH Consult Sdn Bhd Disc. GEN PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. PROJECT VENDOR AND SUB-CONTRACTOR LIST Week of 6 Nov - 10 Nov 23 19 November, 2023 Tag No VDP Cat Man Item Recom . Brand Not Applicable No No No Products Description Detailed Engineering Design Name of Local (Malaysian) PETRONAS Lic./ Reg. Agent No, if apply SVL CPV Not Applicable No Yes Note: Specific Vendor List consists Mandatory and Approved Vendor List as per ARTICLE 6.6.1 of EXHIBIT 6 – PROCUREMENT (REV 2) SVL CONTRACTOR Proposed Vendor List as per 6.6.2 of EXHIBIT 6 – PROCUREMENT (REV 2) CPV Open Address Telephone / Fax No Contact Person Email Name of VENDOR, SUBCONTRACTOR, Manufacturer, Principal Self Operate Address of VENDOR, SUBCONTRACTOR, Manufacturer, Principal Proejct Procurement Plan ATTACHMENT 6 - Procurement Status Report PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. SWA WATER ENGINEERI Procurement Status Report Summary Week of 6 Nov - 10 Nov 23 Code No 19 November, 2023 Category 1 Mechanical 62 2 Piping 12 3 Instrumentation 24 4 Electrical 16 5 Safety 2 6 Subcontract & Services 24 Total Open Package Total 140 Plan Actual Var. Plan Actual Var. Plan Actual Var. Plan Actual Var. Plan Actual Var. Plan Actual Var. Plan Actual Var. RFQ Issued TBE CBE PO Remarks Last Week This Week Cummulative Last Week This Week Cummulative Last Week This Week Cummulative Last Week This Week Cummulative 0 0 0 0 0 1 1 0 1 1 0 1 1 0 0 0 1 1 0 1 1 0 1 1 0 0 0 1 1 0 1 1 0 0 0 0 1 1 1 1 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 PROCUREMENT STATUS REPORT LLI Definition; 8 months (35 wks) from Port of Origin AWP Tracking Buyer No. RFQ Long Discip Lead line Item L CWA CWP IWP System Category M Package Equipment PIC Tag No Qty ordered EDD (wks) M New WWTP EQ Transfer Pump G-18001 A/B 2 42 2 M New WWTP EQ Tank Blower C-18001 A/B 2 36 3 M New WWTP EQ Tank Diffuser X-18001 1 4 M New WWTP Flash Drum Heat Exchanger E-18001 A/B 2 5 M New WWTP Mixing Tank Mixer MX-18001 1 6 M New WWTP Anoxic Tank Mixer MX-18002 A/B 2 7 M New WWTP Aeration Tank Blower C-18002 A/B/C 3 8 M New WWTP Aeration Tank Diffuser X-18002 A/B 2 9 M New WWTP MBR Filtrate Pump G-18004 A 1 10 M New WWTP MBR Modules FD-18003 A 1 11 M MOS System A MBR Filtrate Pump G-18004 B 1 12 M MOS System B MBR Modules FD-18003 B 1 13 M MOS System C MBR Filtrate Pump G-18004 C 1 14 M MOS System C MBR Modules FD-18003 C 1 C-18003 A/B/C/D 4 36 36 42 42 42 15 M MOS System C Scouring Blower 16 M MOS System C RAS Pump G-18002 A/B/C 3 42 17 M MOS System C WAS Pump G-18003 A/B 2 42 18 M MOS System C RAS Tank Mixer MX-18004 A/B 2 19 M MOS System C MBR Cleaning Pump G-18006 A/B 2 42 20 M MOS System C MBR Filtrate Transfer Pump G-18007 A/B 2 42 21 M MOS System C MBR Drain Pump G-18005 A/B 2 42 22 M MOS System C Flushing Pump G-18011 A/B 2 42 23 M MOS System C Offspec Transfer Pump G-18008 A/B 2 42 24 M Dewatering System Pack Sludge Feed Pump G-18009 A/B/C 3 42 25 M Dewatering System Pack Screw Press FD-18002 A/B 2 17 26 M Dewatering System Pack Sludge Holding Tank Mixer MX-18003 1 27 M Chemical Dosing Polymer Prep Polymer Preparation System TK-18018 A/B 2 28 M Chemical Dosing Polymer Prep Polymer Dosing Pump G-18021 A/B/C 3 29 M H2SO4 Dosing System H2SO4 Dosing Pump/Tank G-18012 A/B 2 30 M NaOH Dosing System NAOH Dosing Pump/Tank G-18013 A/B 2 31 M Molasses Dosing System Molasses Preparation Pump G-18020 A/B 2 32 M Molasses Dosing System Molasses Preparation Tank Mixer MX-18005 1 33 M Molasses Dosing System Molasses Dosing Pump G-18014 A/B 2 34 M Molasses Dosing System Molasses Dosing Tank Mixer MX-18006 1 35 M Phosphoric Acid Dosing System Phosphoric Acid Dosing Pump G-18015 A/B 2 36 M NaOCL Dosing System NAOCL Dosing Pump (MC) G-18018 1 37 M NaOCL Dosing System NAOCL Dosing Pump (CIP) G-18019 1 38 M Citric Acid Dosing System Citric Acid Dosing Pump (MC) G-18016 1 39 M Citric Acid Dosing System Citric Acid Dosing Pump (CIP) G-18017 1 M Sodium Bicorbonate Dosing System Sodium Bicarbonate Preparation System TK-18019 A/B 2 41 M Sodium Bicorbonate Dosing System Sodium Bicarbonate Dosing Pump G-18022 A/B 2 42 M PAC Dosing System PAC Feeding System M-18001 A/B 2 43 M PAC Dosing System PAC Motive Pump G-18023 A/B 2 Open MR Received date Bidders Country of Origin Mode of tender S = Single Material Approval Form RFQ BCD TBE CBE PO Date 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 6-Dec-23 11-Dec-23 10-Jan-24 9-Feb-24 12-Feb-24 19-Feb-24 6-Dec-23 11-Dec-23 10-Jan-24 9-Feb-24 12-Feb-24 19-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 6-Dec-23 11-Dec-23 10-Jan-24 9-Feb-24 12-Feb-24 19-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 6-Dec-23 11-Dec-23 10-Jan-24 9-Feb-24 12-Feb-24 19-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 MECHANICAL 1 40 Schedule 42 42 Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Variance PO Date vs Today PO No Supplier Vendor Contact Details Incoterm Delivery Date (Exwork) Delivery Date (FAS/FOB) PO Delivery Date at Site Tax Exemption Unpriced PO to PMT PROCUREMENT STATUS REPORT LLI Definition; 8 months (35 wks) from Port of Origin AWP Tracking Buyer No. RFQ Long Discip Lead line Item CWA CWP IWP System Category Package Equipment PIC Tag No Qty ordered EDD (wks) 44 M New Check Basin Laboratory Transfer Pit Pump G-18030 A/B 2 42 45 M New Check Basin P1 Transfer Pit-1 Pump G-18031 A/B 2 42 46 M New Check Basin P1 Transfer Pit-2 Pump G-18032 A/B 2 42 47 M New Check Basin P1 Transfer Pit-3 Pump G-18033 A/B 2 42 48 M New Check Basin P1 Transfer Pit-4 Pump G-18034 A/B 2 42 49 M G-18035 A/B 2 50 M 51 M Methanol Stripper Methanol Stripper C-18041 1 52 M Methanol Stripper Stripper Kod V-18041 1 53 54 M Methanol Stripper Condensate Accumulator V-18042 1 M Methanol Stripper Process Water Cooler E-18041 1 55 M Methanol Stripper Steam Condenser E-18042 1 56 M Methanol Stripper LP Condenser Cooler E-18043 1 57 M Methanol Stripper Process Water Pump P-18041 A/B 2 42 58 M Methanol Stripper MP Condensate Pump P-18042 A/B 2 42 59 M Methanol Stripper Off-Spec Tank T-18041 / F18063 2 60 M Methanol Stripper F-109 Blowdown Cooler E-18044 1 61 M Methanol Stripper Off Spec Heater E-18065 1 62 M Methanol Stripper Off-Spec Process Water Pump P-18043 A/B G-18063 A/B 4 42 Start 6-Nov-23 10-Nov-23 New Check Basin P1 Check Basin Transfer Pump HVAC for SubStation Summary for MECHANICAL L P PIPING: 1 P Ball Valves < 2 " (inclusive) 2 P Ball Valves > 2 - 6 " (inclusive) 3 P Ball Valves > 6" 4 P Check Valves < 2 " (inclusive) 5 P Check Valves > 2 - 6 " (inclusive) 6 P Check Valves > 6" 7 P Gate Valves < 2 " (inclusive) 8 P Gate Valves > 2 - 6 " (inclusive) 9 P Gate Valves > 6" 10 P Strainer 11 P Pipe Fittings - Bulks 12 P Piping - Bulks Start 6-Nov-23 Summary for PIPING L I INSTRUMENTATION: 1 I Pressure Gauge 2 I Pressure Transmitter with Diaphragm Seal 3 I Flow Transmitter (Magnetic Type) 4 I Flow Transmitter (Thermal Mass Type) 5 I Flow Transmitter (RTD Type) 6 I Thermowell 7 I Level Transmitter (Non-Contact Radar Type) 8 I Analyser (pH - Sampling Analyser) Open 42 Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available End End 10-Nov-23 27 27 27 27 27 27 Schedule Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual MR Received date Material Approval Form BCD TBE CBE 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 30-Nov-23 5-Dec-23 4-Jan-24 3-Feb-24 6-Feb-24 13-Feb-24 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Att 3 Recomm Brand Rosemount (Emerson) Yokogawa Kontrol (M) S/B Honeywell Engineering S/B Emerson Process Management (M) S/B Yokogawa Kontrol (M) S/B Honeywell Engineering S/B Emerson Process Management (M) S/B Yokogawa Kontrol (M) S/B Honeywell Engineering S/B Emerson Process Management (M) S/B Yokogawa Kontrol (M) S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 Att 3 Recomm Brand Rosemount (Emerson) Yokogawa Kontrol (M) S/B Att 3 Recomm Brand Yokogawa Kontrol S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 Plan Target Actual Plan Target 22-Feb-24 22-Feb-24 22-Feb-24 22-Feb-24 22-Feb-24 Country of Origin Mode of tender S = Single RFQ Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Bidders PO Date Variance PO Date vs Today PO No Supplier Vendor Contact Details Incoterm Delivery Date (Exwork) Delivery Date (FAS/FOB) PO Delivery Date at Site Tax Exemption Unpriced PO to PMT PROCUREMENT STATUS REPORT LLI Definition; 8 months (35 wks) from Port of Origin AWP Tracking Buyer No. RFQ Long Discip Lead line Item CWA CWP IWP System Category Package Equipment 9 I Analyser (pH - Tank Immersed Analyser) 10 I Analyser (DO - Tank Immersed Analyser) 11 I Analyser (ORP - Sampling Analyser) 12 I Analyser (ORP - Tank Immersed Analyser) 13 I Analyser COD - Sampling Analyser) PIC Tag No available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available Instrument List not yet available 14 I Analyser (Turbidity - Sampling Analyser) 15 I Analyser (CI2 - Sampling Analyser) 16 I DCS 17 I ESD 18 I Control Valves 19 I Gauge 20 I FO Cables Bulks 21 I Instrument Cable Bulks 22 I Instrument JB 23 I Telecom Cable (TBC) Bulks 24 I Tubing Bulks E ELECTRICAL: E 380VAC LV Normal Switchboard/MCC and IMCS Package 2 E Distribution Transformer - 2MVA 3 E Emergency Diesel Genset (TBC) 4 E 40kVA UPS C/W Common Bypass & Battery TR 1800 DE1/2 SB 1800 N1/E1 HVAC1800 E! E Switchgear 6 E Busduct - 3200A 7 E 380VAC Emergency Switchboard/MCC 8 E 380VAC VSD Panel 9 E Electrical Distribution Board 10 E IMCS 11 E Power Cables 12 E Junction Boxes 13 E Lighting Bulks 14 E Socket Outlet Bulks 15 E RCU 16 E Earthing & Lightning Protection Open 27 27 27 27 27 27 27 24 24 Start 6-Nov-23 5 Summary for ELECTRICAL EDD (wks) Instrument List not yet available Summary for INSTRUMENT 1 Qty ordered 2 3 End 10-Nov-23 44 Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual MR Received date Bulks End 10-Nov-23 Bidders Country of Origin Mode of tender S = Single RFQ BCD TBE CBE Material Approval Form PO Date 22-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 5-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 10-Feb-24 11-Mar-24 10-Apr-24 13-Apr-24 20-Apr-24 5-Feb-24 Att 3 Recomm Brand Yokogawa Kontrol S/B 10-Feb-24 11-Mar-24 10-Apr-24 13-Apr-24 20-Apr-24 22-Feb-24 Att 2 - Cat Man Item Emerson, Flowserve, GE, Neles, IMI 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 22-Feb-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 23-Mar-24 28-Mar-24 27-Apr-24 27-May-24 30-May-24 6-Jun-24 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5-Jan-24 10-Jan-24 9-Feb-24 10-Mar-24 13-Mar-24 20-Mar-24 6-Dec-23 5-Jan-24 4-Feb-24 7-Feb-24 14-Feb-24 1-Dec-23 Exh 6 Cat Man Items Siemens Energy Sdn Bhd Schneider-Electric Ind. (M) SGB MY S/B ABB Power Grid Malaysia S/B Malaysia Transformer (MTM) Plan Target Actual Plan Target Actual Plan Target Actual 13-Jan-24 18-Jan-24 17-Feb-24 18-Mar-24 21-Mar-24 28-Mar-24 5-Feb-24 10-Feb-24 11-Mar-24 10-Apr-24 13-Apr-24 20-Apr-24 6-Dec-23 5-Jan-24 4-Feb-24 7-Feb-24 14-Feb-24 Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual 1-Dec-23 6-Dec-23 5-Jan-24 4-Feb-24 7-Feb-24 14-Feb-24 5-Jan-24 10-Jan-24 9-Feb-24 10-Mar-24 13-Mar-24 20-Mar-24 5-Jan-24 10-Jan-24 9-Feb-24 10-Mar-24 13-Mar-24 20-Mar-24 5-Feb-24 10-Feb-24 11-Mar-24 10-Apr-24 13-Apr-24 20-Apr-24 22-Feb-24 27-Feb-24 28-Mar-24 27-Apr-24 30-Apr-24 7-May-24 8-Mar-24 13-Mar-24 12-Apr-24 12-May-24 15-May-24 22-May-24 8-Mar-24 13-Mar-24 12-Apr-24 12-May-24 15-May-24 22-May-24 8-Mar-24 13-Mar-24 12-Apr-24 12-May-24 15-May-24 22-May-24 8-Mar-24 13-Mar-24 12-Apr-24 12-May-24 15-May-24 22-May-24 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1-Dec-23 38 Bulks Start 6-Nov-23 Schedule Exh 6 Cat Man Items Siemens Malaysia Sdn Bhd Schneider-Electric Ind. (M) Eaton Industries Pte Ltd ABB Malaysia Sdn Bhd Tenaga Switchgear Sdn Bhd Variance PO Date vs Today PO No Supplier Vendor Contact Details Incoterm Delivery Date (Exwork) Delivery Date (FAS/FOB) PO Delivery Date at Site Tax Exemption Unpriced PO to PMT Appendix 6 - Procurement Status Report (PSR) No. RFQ Discipline GEN Package Equipment GENERAL 1 0001 Detailed Engineering Design (DED) - Main 2 0002 Detailed Engineering Design (DED) - WWTP (Veolia) 3 0003 Detailed Engineering Design (DED) - Methanol Stripper (Sulzer) 4 0004 Site Survey - UG, Soil Investigation, Topography & 3D Scan 5 0005 Advance Work Package & 4D Schedule 6 P-IPF™ (PETRONAS Instrumented Protective Function) 7 P-ELSOR™ (PETRONAS Electrical Safety & Operability Review) 8 P-RBI™ (PETRONAS Risk Based Inspection) 9 FnGMap™ (3D Fire and Gas Mapping) 10 P-EDMS™ (PETRONAS Engineering Data Management System) 11 P-VIP™ (PETRONAS Value Improvement Program) 12 P-ESS (PETRONAS Electrical System Study) 13 PERSIS (PETRONAS Equipment Reliability Strategy & Information System) 14 P-ALARM (PETRONAS Alarm Management) Summary for SUB CON - GEN 16 M MECHANICAL M Mechanical Installation Work - (Boiler erector, CI) S CIVIL & STRUCTURE 17 S Piling Work 18 S Civil & Structure Work - Construction 19 S Fire Protection - Construction S Building Services - Construction P PIPING 20 21 22 23 P Piping - Construction P INSTRUMENT I Instrument - Construction P ELECTRICAL I Electrical - Construction ADDITIONAL SUBCONTRACTING O pe n PI C Schedule process duration (weeks) → MR Received date Bidder Contact Name Email Telephone XX Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual Plan Target Actual 26-Oct-23 26-Oct-23 26-Oct-23 8-Nov-23 8-Nov-23 14-Nov-23 27-Nov-23 27-Nov-23 RFQ BCD Bid Extension Date Quoted Total Bidders Quoted Proposal Sent to Eng/Pro TC1 to Bidders Bidders response TC1 (to Eng Dept) 2 TUAH CONSULT SDN BHD Ir. Fadhir SULZER SINGAPORE PTE LTD Tan Hian Ming CBE PO 2 2 XX 4-Nov-23 4-Nov-23 4-Nov-23 20-Nov-23 3-Nov-23 3-Nov-23 3-Nov-23 10-Dec-23 3-Nov-23 3-Nov-23 3-Nov-23 13-Dec-23 9-Nov-23 9-Nov-23 9-Nov-23 20-Dec-23 Hianmin.tan@sul +65 6800 0041 zer.com 13-Nov-23 20-Nov-23 10-Dec-23 13-Dec-23 20-Dec-23 19-Nov-23 26-Nov-23 16-Dec-23 19-Dec-23 26-Dec-23 30-Nov-23 14-Dec-23 10-Jan-24 13-Jan-24 20-Jan-24 TNF ENERGY SDN BHD KemuncaK Lanai Macroperi PJBumi HES 3-Nov-23 3-Nov-23 3-Nov-23 TBE 29-Oct-23 29-Oct-23 29-Oct-23 13-Nov-23 1 3-Nov-23 3-Nov-23 3-Nov-23 Bidders response TC2 fadhir@tuah.co m.my VEOLIA WATER TECHNOLOGIES & SOLUTION SDN. BHD. 3-Nov-23 3-Nov-23 3-Nov-23 TC2 to Bidders SES SES SES SES SES SES SES SES SES 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 2-Jan-24 7-Jan-24 6-Feb-24 7-Mar-24 10-Mar-24 17-Mar-24 Plan Target Actual 19-Dec-23 24-Dec-23 23-Jan-24 22-Feb-24 25-Feb-24 3-Mar-24 Plan Target Actual Plan Target Actual Plan Target Actual 19-Dec-23 24-Dec-23 23-Jan-24 22-Feb-24 25-Feb-24 3-Mar-24 19-Dec-23 24-Dec-23 23-Jan-24 22-Feb-24 25-Feb-24 3-Mar-24 19-Dec-23 24-Dec-23 23-Jan-24 22-Feb-24 25-Feb-24 3-Mar-24 Plan Target Actual Plan Target Actual Plan Target Actual 18-Jan-24 23-Jan-24 22-Feb-24 23-Mar-24 26-Mar-24 2-Apr-24 Plan Target Actual Plan Target Actual 17-Feb-24 22-Feb-24 23-Mar-24 22-Apr-24 25-Apr-24 2-May-24 Plan Target Actual Plan Target Actual 1-Feb-24 6-Feb-24 7-Mar-24 6-Apr-24 9-Apr-24 16-Apr-24 0 Start 6-Nov-23 End 10-Nov-23 Plan Target Actual Mode of tender S = Single C = Comp PO No PO Delivery Date Subcontractor Total Lead Time (days) VDCS Float Status/ Progress Remarks XX S C META-SWA-TUA009-LTR-0001 TUAH CONSULT SDN BHD BLA 9 Nov 23 Project Procurement Plan ATTACHMENT 7 - Long Lead Item PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. LIST OF LOND LEAD ITEM No MATERIALS or EQUIPMENT SWEC Market Survey Date Delivery Weeks Start End Min Max Worst Case 1 Transformer Recomm List, Cat Man 3-Nov-23 6-Nov-23 18 44 44 2 Horizontal Centrifugal Pump API 610 Recomm List, Cat Man 3-Nov-23 6-Nov-23 42 50 50 3 Switchgear Recomm List, Cat Man 3-Nov-23 9-Nov-23 24 38 38 4 Transmitters Recomm List, Cat Man 6-Nov-23 6-Nov-23 20 25 25 5 Horizontal Centrifugal Pump Non API 24211112P 9-Nov-23 11-Nov-23 11 42 42 6 Electrical Bus Duct 14161100P 3-Nov-23 10-Nov-23 10 20 20 7 Blower & Fan 24211000P 3-Nov-23 11-Nov-23 24 36 36 8 Screw Press 24271400P 9-Nov-23 12-Nov-23 7 17 17 Note: Long Lead Item define as delivery is no less than eight (8) months (approx 35 weeks) Notes propose removed from LLI propose removed from LLI propose removed from LLI Project Procurement Plan ATTACHMENT 8 - Technical Bid Evaluation Form PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) TECHNICAL BID EVALUATION MATRIX META-009-RFQ-0001/TBE Reference RFQ No example META-009-RFQ-0001 BLA No example META-009-BLA-0001_REV04 BIDDER'S Essential Requirement No 1 Bidder Bidder 1 Name XX 1 C 2 C 3 C 4 C 5 C 6 C 1 C 2 C 3 C 4 C 5 6 0.00 ### 7 ### C 6 DA 0 R 0 C 4 DA 0 R 0 BIDDER'S General Requirement No 1 C DA R Bidder Bidder 1 Name XX Full compliance Acceptable Deviation Reject CONCLUSION example Bidder 1 XXX is Technically Acceptable and it is recommended to proceed with commercial evaluation Only one bidder invited as pper BIDDER'S APPROVAL LIST Note: 1. TBE evaluate based on RFQ above 2. Minor scope exclusion and manageable. Refer to Deviation List for scope exclusion. 3. BIDDER'S response to TC01 is attached. Prepared & Recommended By Reviewed By Approved By ….................................................. ….................................................. Tamarai Selvi Procurement Manager ….................................................. Khailash Dhasan Project Manager Project Engineer COMPANY'S Approval ….................................................. Name Position SWA ENGINEERING SDN BHD PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING Proj Doc: (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) TECHNICAL BID EVALUATION SWA Doc No: META-009-RFQ-0001/TBE Tender/Inquiry No:XX Package: XXX PART 1 - GENERAL Criteria Bidder 1 Criteria 1 1 C: Full compliance DA: Partial compliance with deviation R: Unable to supply complete scope of the above. Offered scope of supply not acceptable C Criteria 12 2 C : Less or equal to ED+M6 DA: Between ED+M6 and ED+M8 R : More than ED+M8 C Criteria 13 3 C: Fully comply and able to perform FOE scope. DA: Not applicable R: Unable/not willing to support FOE & As Built scope C Criteria 4 4 C: Fully comply and able to perform work priority per AWP. DA: Not applicable R: Unable/not willing to support FOE & As Built scope add more as require C 6 months Bidder 2 Bidder 3 SWA ENGINEERING SDN BHD PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING Proj Doc: (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD. (META) TENDER BID EVALUATION SWA Doc No: META-009-RFQ-0001/TBE Tender/Inquiry No: XX Package: XXX PART 2 - ESSENTIAL REQUIREMENT Criteria Bidder 1 Criteria 1 1 C: Full compliance DA: Not applicable R: KL Office not available C Criteria 2 2 C: Readilly available. Clear office layout provided DA: Able to provide but modification/renovation require R: Unable to comply C Criteria 3 3 C: Fully comply and able to perform FOE scope. DA: Not applicable R: Unable/not willing to support FOE & As Built scope C Criteria 4 4 C: Full compliance (exclude VMP, SES) DA: With Exception but manageable/acceptable ( less or equal 10% of MDR, exclude SES, VMP) R : Exception > 10% of MDR Criteria 5 C 5 C: Full compliance, readily available with valid license DA : Partially compliance. Balance of softwarre will be made available within ED+M1 R : Unable to comply Add as require C 6 C Bidder 2 Bidder 3 SWA Doc No.: SWA-009-SHP-XXXX Date: Project Procurement Plan Attachment 9 – Packing, Marking and Shipping Instruction PACKING, MARKING, AND SHIPPING INSTRUCTIONS TO VENDORS SWA Doc No.: SWA-009-SHP-XXXX Date: 1. FOREWORD This Specification gives to the VENDORS or SUB-CONTRACTOR of material and equipment the essential instructions for proper preparation and packaging of equipment, materials and supplies to ensure that they will be delivered in satisfactory condition, regardless of destination. All shipments shall comply with these requirements and instructions. Any deviation from this Specification must have the prior written approval of CONTRACTOR Procurement Department. This Specification is applicable to prime VENDORS or SUB-CONTRACTOR and all Sub-VENDORS or SUB-CONTRACTOR. Packing means to efficiently and effectively protect material and equipment, from the moment they leave the factory until they are stored at job site and issued for installation/use. Information and Specifications stated in the inquiry, Material Requisition, or Purchase Order shall take precedence over the requirements set forth herein. 2. SCOPE The requirements are specified so that material as shipped will endure the rigors of: Handling, stacking and transport to plant construction site. Taking in consideration that the materials have to be handled many times. Outside packing must take into consideration risk of exposure to a variety of extreme climatic conditions for inland transport and short & long term storage at the job site. This protection must be effective for a 6 months period after delivery to job site. VENDORS or SUB-CONTRACTOR shall have the materials and equipment strongly packaged and shall take measures to protect them from moisture, rain, dust, rust, corrosion and shock, etc. according to their different shapes and special features to withstand numerous handling, loading and unloading to ensure the materials safe arrival at the site without any damage or corrosion. VENDORS or SUB-CONTRACTOR will be responsible, and shall pay all connected costs, for any loss or damage to material or equipment due to packing that was not adequate for the handling foreseen. 3. PREPARATION OF MATERIAL All equipment and material shall be cleaned internally and externally to remove weld spatter, scale, rust, cuttings, filing, etc., as well as foreign material. Critical wearing surfaces, highly stressed parts, and highly finished surfaces shall be further cleaned by dipping or brushing with a suitable solvent, such as petroleum naphtha or alkaline cleaning compound. Critical function or close tolerance surfaces shall be additionally cleaned to ensure removal of perspiration and fingerprint stains, using any commercially available oil fingerprint remover. After hydro testing, operating, and/or performance test, tanks, vessels, jacketing, piping etc. shall be completely drained and wiped or blown dry. Lint-free rags shall be used for wiping. The use of temporary gaskets for the nozzles with blind flanges (such as manholes ...) is forbidden for transportation purposes. All nozzles with blind flanges shall be closed at VENDORS or SUB-CONTRACTOR shop before transportation installing new gaskets (refer to material requisition for service gasket type) and the bolts shall be tightened accordingly. Vendor is mandatory requested to perform a final control in shop of tightening on any and all equipment joints not to be connected to piping. A final tightening control log SWA Doc No.: SWA-009-SHP-XXXX Date: shall be issued by VENDORS or SUB-CONTRACTOR for each joint and will be included in the final inspection dossier. Final tightening at VENDORS or SUB-CONTRACTOR shop might be waived only upon written authorization by CONTRACTOR for joints to be reopened in field (such as manholes). If in particular cases deviation is authorized, such as: a) b) Joints to be reopened in field (such as manholes). Bolts tightening not performed additional identification shall be clearly marked on the blind flanges involved by means of coloured paint (e.g. red) and proper documents shall be filled in i.e. the Operating & Safety Instruction for the user (including residual risks) and the Packing List. 4. PRESERVATION Painting ▪ Primer and finish coat shall be if and as specified by Painting Job Spec. as per Data Sheets ▪ Non-metallic filler shall not be applied to cast surfaces or welds. ▪ Masking tape applied to such items, as gage glasses, nameplates, etc. shall be left in place after painting. ▪ Machined or highly finished surfaces, rotating or reciprocating machine shafts, packed valve stems and linkages must be kept free of paint. ▪ Stainless steel piping and equipment shall be protected from pitting and chloride contamination when shipped by sea or used at a coastal job site. Rust Prevention ▪ Unpainted machined metal surfaces, both external and internal, shall be cleaned and dried as specified above and amply coated with a rust preventative which will maintain a protective coating for at least two years provided the coating is not burned, dissolved, or mechanically rubbed off. ▪ Several brands of preservation products are available and acceptable providing they conform to the performance requirements above. Acceptable methods of applying rust preventative are spraying, brushing, filling, flushing, etc. through all available openings, or disassembly if necessary, to completely coat and protect all unpainted internal surfaces. Particular attention should be paid to journal surfaces of sleeve bearings and entire anti-friction bearings, to insure complete coating. ▪ ▪ The manufacturer shall wire a large red tag to machine stating: "Caution - This equipment has been treated with a rust preventative and no parts should be disturbed until ready to place in service. If protective coating film is broken, it should be restored for continued storage". ▪ All piping disassembled from equipment for ease of shipment shall have internal surfaces cleaned free of scale and all other foreign matter and coated with a rust preventative. Pickling and cleaning are also acceptable. In either case, all pipe ends shall be securely sealed with moisture-proof paper and wooden flange covers or metal caps. SWA Doc No.: SWA-009-SHP-XXXX Date: ▪ After application of rust preventative, exposed machined surfaces shall be wrapped with a heavy "VPI" treated paper, or other heavy waterproof paper (or plastic) enclosing "VCI" other (Vapour Corrosion Inhibitor) crystals. In all cases, pH of wrapping shall be neutral. The wrapping shall be secured tightly with tape or twine. Sharp edges shall be cushioned to prevent puncture of wrapping. ▪ Spare parts all replacement parts shall be covered with a second wrapping of heavy waterproof paper. ▪ Because of possible damaging effect, care should be exercised to avoid applying rust preventatives to items fabricated of leather, rubber, mica, and similar materials. Protection Of Openings ▪ Flanged openings shall be protected by bolted-on wooden outdoor plywood (min. 1/4" thickness) or metal covers, using at least three bolts. (Wired-on covers are not acceptable). A sealer shall be used between the flange and the cover. After openings have been covered, the joint shall be wrapped with waterproof tape. ▪ Porous bags filled with desiccant shall be hung on the inside of the wooden or metal bolt on covers on all major connections of rotating equipment unless physical size is restrictive. ▪ Threaded metal plugs or caps shall protect exposed pipe threads. Plastic closures and thread protectors are prohibited except with approval from CONTRACTOR. ▪ Plane or butt-weld ends shall be protected by a sheet metal or molded plastic cap, secured to the OD with weatherproof tape. ▪ Important: in capping, tagging or banding ends of stainless steel, do not use galvanized or aluminium wire or strip. ▪ Closures that are part of original equipment shall fit tightly. Flexible Connections ▪ Flexible connections subject to possible damage during shipment shall be disconnected and loose ends adequately supported or protected to prevent damage. Shaft Coupling ▪ Flexible couplings shall be broken, adequately supported, and protected to prevent damage. Rigid couplings shall be shipped as required to provide full protection and safety in transmit and storage. Dehydration ▪ The use of desiccant crystals within an enclosed piece of equipment is of particular importance in high humidity areas subject to wide variation in temperature over a twentyfour-hour period. Location of desiccant should be at suitable intervals to provide uniform distribution. ▪ The quantity of dehydrating agent to be used shall be determined based on the surface area of the moisture barrier, the moisture vapour transmission rate, and the volume of the enclosed space. Additional desiccant should be used if other moisture-absorbent material or supporting structures are included within the enclosed volume. SWA Doc No.: SWA-009-SHP-XXXX Date: ▪ Equipment shipped utilizing dehydrating materials shall be labelled or tagged with an easily observed red sign, reading: "Caution - Desiccant materials are enclosed within this equipment. Do not operate before removing”. Moreover, the identification number of the nozzles where dehydrating materials will be fixed shall be indicated in the label or tagging. Should the integrity of the enclosure be broken before operation, the desiccant must be replaced, and the enclosure resealed for continued storage". Nitrogen blanketing ▪ ▪ VENDORS or SUB-CONTRACTOR shall recommend if Nitrogen blanketing is required to prevent internal corrosion during shipping or storage. VENDORS or SUB-CONTRACTOR is responsible for developing the procedures for Nitrogen blanketing, when needed, and shall submit them for CONTRATOR review. Vessels shipped with nitrogen blanketing shall bear a mark on all blinds covering connections that may allow personnel inside the vessel (either manways or process connections of adequate size) stating what follows: WARNING!!! THIS VESSEL IS FILLED WITH NITROGEN UNDER PRESSURE. BEFORE OPENING ANY BLIND FLANGE, THE NITROGEN PRESSURE MUST BE REDUCED TO THE ATMOSPHERIC BY VENTING THROUGH THE VENT VALVE. BEFORE ANY PEOPLE IS ALLOWED TO ENTER INSIDE THE VESSEL, THE NITROGEN MUST BE BLOWN OUT WITH A FAN TO RESTORE THE AIR AND A BREATHEABLE ENVIRONMENT. SWA Doc No.: SWA-009-SHP-XXXX Date: 5. PACKING CONSTRUCTION The packing construction shall comply with UNI 9151, UNI 10858, UNI 10920, as applicable to the specific case, and shall take into account the general criteria set forth here after. All wooden packing material shall comply with the ISPM 15 - International Standards for Phytosanitary Measures, which means it has been fumigated, and shall bear the relevant IPPC proper mark. Domestic Shipment ▪ Very large and complicated equipment such as compressors, generators, large motors, engines, pressure vessels, etc. not supplied with self supporting base plates, shall be bolted to a skid formed of heavy timbers suitable for sling lift or forklift truck handling, as applicable. This equipment shall be covered on top and sides with heavy waterproof paper, heavy plastic, or tarpaulin and ventilated underneath to permit air circulation. The cover shall be secured to the skid in such a manner that it will not extend beyond the outer edge and be torn when a sling or forklift handles the equipment. ▪ Very large and/or complicated equipment mounted on self-supporting base plates will not require skids. Covering shall be as specified in the previous paragraph. ▪ Medium or small size equipment whether on self-supporting base plates or not, shall be bolted to timber skids suitable for sling-lift or forklift truck handling. All equipment shall be covered on top and sides with heavy waterproof paper or plastic, but ventilated underneath to permit breathing. The cover shall be securely attached to the equipment with tape, twine, or staples. ▪ If required, the equipment (including affixed piping and accessories) shall then be enclosed within a wooden crate or box of ample size and strength to protect it against damage during transportation and handling at the jobsite. ▪ Bulk materials may be bundled or enclosed in burlap sacks, waterproof bags, waterproof fiber box, fiber drums, or metal drums. The type of material will govern the best method for shipment. Shipment shall then be palletized in convenient quantities. ▪ Piping may be shipped as loose pieces except that piping 2” and smaller that will be bundled and strapped to make more rigid assemblies for shipment. Stainless steel pipes 2” diameter and smaller shall be packed in cases. Stainless steel pipes bigger than 2” diameter, may be shipped loose or in bundles with ends adequately protected and plugged with plastic plugs or cap secured by tape. ▪ Piping shall be consolidated as required by CONTRATOR for shipment. Any piping specially cleaned internally prior to shipment shall have ends capped or taped to make them watertight and shall be desiccant protected. ▪ When equipment is shipped in a “blocked-up” condition the requirements of Paragraph 5.2.2 below shall also apply. Export Shipment Or Sea Shipment In general, equipment shall be enclosed in nailed wooden boxes, seaworthy type, supplemented with steel strapping. Crating shall be of adequate strength to permit stacking and shall be reinforced with steel strapping. SWA Doc No.: SWA-009-SHP-XXXX Date: Box Construction ▪ Waterproof paper shall be used to line top, end, and side of all boxes. ▪ Each box shall have screened vent openings, located on the sides, of a size commensurate with size of box, with internal splashboards to prevent entrance of rain as well as to prevent sweating due to fluctuations in temperature. ▪ Any finish-machined item that is blocked for shipment using wood chocks or wood framing shall be isolated from the wood to prevent moisture transmission from the wood to the metal surface. ▪ Large volume equipment such as pressure vessels, large machinery pieces, structural steel, large size pipe, etc., which is inherently weather resistant and capable of withstanding the rigors of transportation may be shipped without being boxed. ▪ Equipment containing stainless steel parts must be boxed and marked: “This material to be stored below deck and not as deck cargo”. ▪ Special shipping fixtures, tarpaulins, etc. are considered to be expendable items and will not be returned to VENDORS or SUB-CONTRACTOR. Requirements applicable to any mode of shipping or to any destination ▪ Small loose parts shall be packed in a separate, sturdy wood box with steel strapping & each part marked with waterproof ink for proper identification. Any such box may be shipped with the main equipment, provided that it is securely attached to the main skid or within the main box. Secure attachment consists of strapping or bolting. Tying or wiring is prohibited. ▪ Small spare and replacement parts shall be packed in a steel-strapped, rugged wood box for rail or truck shipment. A steel-strapped, sturdy, well packed carton is permissible for parcel that are shipped by express courier or air freighted. Large parts, such as rotor assemblies, shall be prepared and enclosed in the same way as the main machinery unless otherwise directed in the purchase order or requisition. ▪ Tools shall be packed in a separate, steel strapped, rugged, wood box, marked “special tools”. However, large pieces, such as disassembly cradles, may be packed in the same way as the main equipment. ▪ Cement and refractory materials shall not be shipped to the construction site earlier than 6 months prior to use. The purchase order will give earliest delivery date. High alumina refractory rapidly deteriorate (particularly in a hot climate), shall required a special shipping schedule. 6. INSTALLATION INSTRUCTIONS AND DRAWINGS One set of installation instructions and drawings shall be included with the shipment in a sealed waterproof envelope, firmly attached directly to the equipment within the packing container. 7. MARKING All packages must bear the following marks applied legibly and indelibly on 3 (three) adjacent sides as per “SHIPPING MARK” sample. Such packages and cases shall contain two copies of their packing list enumerating the parts contained therein (one outside and one inside). SWA Doc No.: SWA-009-SHP-XXXX Date: Major equipment items such as assembled vessels are to be clearly and indelibly marked in characters at least 45 cm. High. The packages will be marked by each VENDORS or SUB-CONTRACTOR consecutively for the whole of each purchase order's sequence of shipments. For example: Shipment N° Cases N° Shipment N° Cases N° 1 partial 1, 2, 3 2 balance 4, 5, 6,……n The shipping documentation provided by the VENDORS or SUB-CONTRACTOR shall be properly packed to withstand numerous handlings, long-distance transportation and to protect damages from moisture and rain. The surface of each package shall be marked as required. The VENDORS or SUB-CONTRACTOR shall stencil on the outside of the shipping packages appropriate instructions for the handling, transport, and storage with letters at least 45 mm high. (where applicable). Packages requiring special handling must be marked additionally with the following customary symbols: ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ Top (indicates the correct, upright position of the package). Fragile (the contents of the package are fragile and must therefore be handled with care). Protect against moisture (the package must be kept in a dry environment). Keep away from heat (the package must be protected from heat). Use no hooks (no hooks may be used when handling this package). Point of gravity (indicates the centre of gravity of a package that is to be handled as a single unit). Sling hare (slinging equipment must be applied as shown in order to lift the package). No hand truck here (hand trucks must not be used on this side to handle the package). Clamp here (clamps must be applied to the sides indicated to handle the package). Stacking weight limitation (indicates the maximum stacking load for packages). Do not destroy barrier (a barrier layer which is (virtually) impermeable to water vapor and contains desiccants for corrosion protection is located beneath the outer packaging. This protection will be ineffective if the barrier layer is damaged. Since the symbol has not yet been approved by the ISO, puncturing of the outer shell must in particular be avoided for any packages bearing the words "Packed with desiccants". Permitted temperature range (indicates the temperature range within which the package must be stored and handled). Do not use forklift truck here (the package must not be handled using forklift trucks). SWA Doc No.: SWA-009-SHP-XXXX Date: 8. DELIVERY POINT All material must be delivered at the following address: as specified at Project Procurement Plan 9. SHIPPING AND NOTIFICATION In the cases where transportation is included in VENDORS or SUB-CONTRACTOR’s scope of supply, shipping shall be arranged only after receipt of the relevant “Shipping Release Notice” (SRN) issued by CONTRATOR. VENDORS or SUB-CONTRACTOR must notify each shipment to the persons indicated in each SRN, and must strictly comply with the instruction given therein, especially as far as time of advance notification and unloading hours specified. The notification must include the following information: * amended to item 6.1.1EXHIBIT 6 a) Description of the EQUIPMENT, MATERIAL and SUPPLIES to be imported; b) Tonnage or cubic size as applicable; c) Port of Shipment Including Transhipment; d) Estimated Time of Departure (ETD); e) Mode of Shipment; f) Name of Carrier (Shipping Line); g) Port of Arrival; h) Estimated Time of Arrival (ETA); i) Routing from Port of Arrival to the SITE / WORKSITE; and j) Name of Forwarding Company. 10. DOCUMENTATION All shipments of project material will require the following documentation: a. b. Commercial Invoice Packing List and all the other documents and authorisations which are needed for the importation of the materials into Labuan, State: Federal Territory, Country: Malaysia. Each document shall have the same material description as per Purchase Order. SWA Doc No.: SWA-009-SHP-XXXX Date: Packing list shall show the following information: a. Project: PROVISION OF ENGINEERING, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICAL METHANOL LABUAN SDN. BHD. b. Location: LABUAN, FEDERAL TERRITORY, MALAYSIA c. Both COMPANY and CONTRACTOR references i. COMPANY: RFP-000000059837 ii. CONTRACTOR: as per Purchase Order number d. PMT Name, Address and Contact Number; To be Advise e. Item, quantity and unit of measure; f. Description of MATERIALS or EQUIPMENT; g. MATERIALS, SUPPLIES, EQUIPMENT or SPARE PART(s) / Tag number; h. CONTRATOR Inspection Release Notice no. (IRN) i. Packages number ... of ... j. Quantity k. Detailed description of material (as per other documents). l. Gross and net weight in Kg m. Type of packing (case, crate, bundle, loose, etc.) n. Packing dimensions (L x W x H) in cm See example of "Packing List" at the end of this specification. NOTE: Above information is mandatory. Documents issued non in conformity with the above requirements will be rejected, particularly if the IRN number not specified. VENDORS or SUB-CONTRACTOR will prepare Packing Lists for the material covered by the respective invoices. The Packing List shall be written in English language. VENDORS or SUB-CONTRACTOR shall place two copies of packing list in each package (one inside and one outside) protected in an appropriate transparent cover. 11. OVERSIZE / HEAVY WEIGHT TRANSPORTATION – SHIPPING DRAWINGS For every shipment of materials and/or equipment, with any of the packages having dimensions and / or weight exceeding the following: Weight Length Width Height 22 Tons 11,50 m 2,30 m 2,30 m Note: based on preliminary survey and subject to changes after route survey and heavy lifting availability VENDORS or SUB-CONTRACTOR shall submit to CONTRATOR no. 3 copies of the preliminary “Shipping Drawing" within 3 months after Purchase Order. The “Shipping Drawings” shall show purchase order/tag number, dimensions, and weight of the equipment in the transportation setting, with lifting lugs and/or sling position, size of lugs, the position of the centre of gravity, provisional saddles locations (incl. width, height and weight), SWA Doc No.: SWA-009-SHP-XXXX Date: size and type of spreader-bars, ropes and shackles, and any other information needed to plan the transportation to the job site. CONTRATOR will review the drawings, or will have it reviewed by the appointed Freight forwarder, and will send it back with comments if any. VENDORS or SUB-CONTRACTOR shall send back to CONTRATOR three copies of the final drawings not later than 3 months before the shipping date. The “Shipping Drawings" shall be addressed to the Project Procurement Manager. Saddles shall be designed to avoid any problem during land transportation (weight, height, width, length problems) and shall be suitable for stowage and lashing during sea transportation (apply regulation: 1994/95 IMO publication code of practice IMO295-E). 12. INSURANCE When specified in Purchase Order shipment and delivery by VENDORS or SUB-CONTRACTOR, VENDORS or SUB-CONTRACTOR shall cover insurance against damages or losses in transit. 13. DANGEROUS MATERIAL If the supply includes inflammable, self-igniting, poisonous, corrosive, explosive, radioactive or other dangerous materials, they must be packed according to the instructions of the carrier (EVC, CIM, IMCO, SFO) and noted specially in the packing lists. An official declaration properly identifying the nature of risk shall be provided by VENDORS or SUB-CONTRACTOR and shall be attached to written to the packing list. An official Accident Prevention Sheet written by VENDORS or SUB-CONTRACTOR must be attached to each shipment. The document shall provide information describing: 1) Procedure to properly and safety handle the package(s) 2) Step to be taken in case of accident. (Prepared in the language of the country of destination, at least in English). 14. CUSTOM OPERATIONS All import Customs operations for materials, and payment of relevant duties will be performed by (refer to CONTRACTOR Purchase Order) 15. PACKING SAMPLES TABLE “A” CLASS OF ATERIAL 1. Structural parts, metal or wood SKIDDER OR PLYWOOD TEXTIL BAGS NAILED DRUM OR FIBRE OR FIBRE WOODEN BOX DRUM BOX D,E MULTIWALL SHIPPING SACKS OR METAL DRUM BUNDLE, COIL OR LOOSE D,E SWA Doc No.: SWA-009-SHP-XXXX Date: 2. Major Items a. Large Machinery b. Medium-Small Machinery D,E D,E 3. Tools & Machine Parts D,E D 4. Pipe a. 3" and above b. 2" abd below E 5. Metal rods & sheets D,E 6. Bulk Materials Solids D D D,E 7. Loose article not subject to damage in transit D,E D D,E 8. Hardware & Fittings D, E D D 9. Wire & Cable E D 10.Furniture-Office & Field E D 11.Instruments E D,E D D 12.Liquids – in Bulk D, E 13.Liquids - in containers D, E D 14.Chemicals - in bottles D, E D 15.Chemicals-Inert Granular – in bulk D 16.Chemicals, Inert Granular in container D,E 17. Pressure Valves a. 8' Diameter and above b. 8' Diameter and below E D,E 18. Heat Exchangers D,E 19. Spare Parts D, E Notes relevant to TABLE "A" D,E D D,E D D, E SWA Doc No.: SWA-009-SHP-XXXX Date: 1. 2. "D" designates acceptable for domestic shipment. "E" designates suitable for export or sea shipment. SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: Note: In order to avoid that wooden intermediate layers are torn out, the spacing between threaded bar and board end must be AT LEAST AS WIDE as the space between threaded bar and side of board. - Pipes of carbon steel from DN 150 – Loose Pipes fittings of carbon steel – Case or crate Pipes and pipe fittings of stainless steel – Case Fittings, pipe bends, reducer, flanges – Case SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: SWA Doc No.: SWA-009-SHP-XXXX Date: 16.0 SHIPPING MARK SAMPLE PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICALS METHANOL SDN. BHD., LABUAN, WILAYAH PERSEKUTUAN, MALAYSIA (META) Consignee: PETRONAS CHEMICAL METHANOL SDN BHD (for overseas consignment/import only) Project: PROVISION OF ENGINEERING, CONSTRUCTION AND COMMISSIONING (EPCC) FOR METHANOL EFFLUENT TREATMENT ALLEGIANCE PROJECT AT PETRONAS CHEMICAL METHANOL LABUAN SDN. BHD. Location: LABUAN, FEDERAL TERRITORY, MALAYSIA Contract No: Both COMPANY and CONTRACTOR references COMPANY: RFP-000000059837 CONTRACTOR: as per Purchase Order number PMT Name, Address and Contact Number; To be Advise Item, quantity and unit of measure; Description of MATERIALS or EQUIPMENT; MATERIALS, SUPPLIES, EQUIPMENT or SPARE PART(s) / Tag number; CONTRATOR Inspection Release Notice no. (IRN) Packages number ... of ... Quantity Detailed description of material (as per other documents). Gross and net weight in Kg Type of packing (case, crate, bundle, loose, etc.) Packing dimensions (L x W x H) in cm Shipment n° .... Partial Balance 17.0 PACKING LIST SAMPLE PACKING LIST Consignee: PETRONAS CHEMICAL METHANOS SDN BHD Att.n – Order n° ............................Plant Location: Labuan, Federal Territory, Malaysia - Contract n°…. Purchase Order N.° Item N.° Material description Material Quantity Package n. .... of .... Package Type Dimensions (L x W x H) m Total Packing list n°........... Release notice (IRN)n°………Partial Balance Volume m3 cbm. ........... Net Weight Gross (Kg) Weight (Kg) Kg............................