Project No.: PD.19.09 NHON HOI WIND FARM PROJECT – PHASE I TECHNICAL DESIGN VOLUME 1 DESCRIPTION VOLUME 1.1 DESCRIPTION OF POWER PLANT (Version 03) Khanh Hoa, January, 2021 VIETNAM ELECTRICITY POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 4 Project No.: PD.19.09 NHON HOI WIND FARM PROJECT – PHASE I TECHNICAL DESIGN VOLUME 1 DESCRIPTION VOLUME 1.1 DESCRIPTION OF POWER PLANT (Version 02) Deputy Director : Ly Dinh Huy Project Manager : Nguyen Khanh Hoa Khanh Hoa, January EMPLOYER BINH DINH FICO ENERGY JOINT STOCK COMPANY EPC CONTRACTOR POWERCHINA VIETNAM LIMITED COMPANY , 2021 CONSULTANT POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 4 ON BEHALF OF PECC4 Le Cao Quyen Deputy General Director Nhon Hoi Wind farm project – Phase I Technical Design CONTRIBUTORS No. Full Name 1. Nguyen Tan Quang Electrical design leader 2. Vu Ha Linh Civil design leader 3. Duong Dinh Dieu Road design leader 4. Le Thanh Tri Civil designer Contributors Responsibility Signature i Nhon Hoi Wind farm project – Phase I Technical Design CONTENTS Technical Design report of “Nhon Hoi Wind farm project – Phase I” is established as following: Volume 1 Volume 1.1 Volume 1.1A Volume 1.2 Volume 1.3 Volume 2 Volume 2.1 Volume 2.1A Volume 2.2 Volume 2.3 Volume 3 Volume 3.1 Volume 3.2 Volume 3.3 Volume 4 Volume 4.1 Volume 4.1A Volume 4.2 Volume 4.3 Volume 5 Volume 5.1 Volume 5.1A Volume 5.2 Volume 5.3 Volume 6 Volume 6.1 Volume 6.2 Volume 6.3 Volume 7 DESCRIPTION Description of Power plant Description of Turbine foundation Description of Substation Description of Transmission line DRAWINGS Drawings of Power plant Drawing of Turbine foundation Drawings of Substation Drawings of Transmission line CONSTRUCTION EXECUTION Construction execution of Power plant Construction execution of Substation Construction execution of Transmission line CALCULATION Calculation of Power plant Calculation of Turbine foundation Calculation of Substation Calculation of Transmission line TECHNICAL SPECIFICATION Technical specification of Power plant Technical specification of Turbine foundation Technical specification of Substation Technical specification of Transmission line CONSTRUCTION MAINTENANCE PROCEDURE Construction maintenance procedure of Power plant Construction maintenance procedure of Substation Construction maintenance procedure of Transmission line FIRE FIGHTING SYSTEM This is the “Volume 1.1: Description of Power plant” (Version 03). Version 03 is finalized according to Document no. 98/BQL-QLQHXD dated January 20, 2021 of Binh Dinh Economic Zone Management Board announcing the appraisal result of Technical Design of Nhon Hoi Wind Power Plant – Phase I. This version is replaced for version 02 issued in December 2020 by Power Engineering Consulting JS Company 4. Contents ii Nhon Hoi Wind farm project – Phase I Technical Design INDEX CHAPTER 1: OVERVIEW ................................................................................................. 1-1 1.1. LEGAL BASIS .....................................................................................................................1-1 1.2. MAIN PROJECT INFORMATION .....................................................................................1-4 1.3. INPUT FOR TECHNICAL DESGIN .................................................................................1-11 CHAPTER 2: SPECIFICATION OF PROJECT AREA ................................................. 2-1 2.1. PROJECT LOCATION ........................................................................................................2-1 2.2. SITE CONDITIONS OF PROJECT AREA .........................................................................2-3 CHAPTER 3: SOLUTIONS FOR ELECTRICAL – TECHNOLOGY OF POWER PLANT ....................................................................................................................... 3-1 3.1. GENERAL LAYOUT SOLUTION ......................................................................................3-1 3.2. TECHNICAL CHARACTERISTICS OF MAIN EQUIPMENT .........................................3-4 3.3. LIGHTNING PROTECTION .............................................................................................3-27 3.4. FIRE FIGHTING SYSTEM ...............................................................................................3-29 3.5. AUXILIARY TRANSFORMER ........................................................................................3-32 CHAPTER 4: CONSTRUCTION SOLUTIONS FOR PLANT PART ........................... 4-1 4.1. SELECTION OF CONSTRUCTION SITES/ITEM ELEVATION .....................................4-1 4.2. IMPACT LOADS AND EARTHQUAKE-RESISTANT DESIGN REQUIREMENT .......4-1 4.3. WIND TURBINE FOUNDATION ......................................................................................4-3 4.4. TECHINCAL REQUIREMENT FOR HARDSTANDS ......................................................4-4 4.5. O&M BUILDING AREA .....................................................................................................4-7 4.6. TECHINCAL INFRASTRUCTURE ..................................................................................4-10 4.7. SOLUTIONS FOR ROAD PART ......................................................................................4-10 4.8. CIVIL SOLUTION FOR CABLE TRENCH .....................................................................4-15 APPENDIX: LIST OF EQUIPMENT AND MATERIAL Index iii Nhon Hoi Wind farm project – Phase I Technical Design LIST OF TABLE Table 1.1: Summary of land uasge demands of project ...............................................1-4 Table 2.1: Project coordinates ......................................................................................2-1 Table 2.2: Geological layer within the project scope...................................................2-7 Table 2.3: Results of standard penetration test SPT ....................................................2-8 Table 2.4: Physical mechanical properties of rock, soil layers ..................................2-12 Table 2.5: Recommended standard values and calculation of geological layer 1 .....2-13 Table 2.6: Recommended standard values and calculation of geological layer 2 .....2-13 Table 2.7: Recommended standard values and calculation of geological layer 3 .....2-14 Table 2.8: Calculation results according to Hoek – Brown Layer 3 ..........................2-14 Table 2.9: Calculation results according to Hoek – Brown Layer 3 ..........................2-14 Table 2.10: Recommended standard values and calculation of geological layer 4 ...2-15 Table 2.11: Calculation results according to Hoek – Brown Layer 4 ........................2-15 Table 2.12: Calculation results according to Hoek – Brown Layer 4 ........................2-15 Table 2.13: Recommended standard values and calculation of geological layer 5 ...2-16 Table 2.14: Calculation results according to Hoek – Brown Layer 5 ........................2-16 Table 2.15: Calculation results according to Hoek – Brown Layer 5 ........................2-16 Table 2.16: Table of converting ground acceleration to earthquake grade according to TCVN 9386:2012 .......................................................................................................2-18 Table 2.17: Measured results of resistivity of rock and soil ......................................2-20 Table 2.18: Recommendations for grades of excavated soil and rock ......................2-24 Table 2.19: Characteristics of ambient temperature at Quy Nhon meteor station .....2-26 Table 2.20: Characteristics of ambient humidity at Quy Nhon meteor station .........2-27 Table 2.21: Ambient pressure at Quy Nhon meteor station .......................................2-27 Table 2.22: Frequency of wind occurrence at 8 directions in a year at Quy Nhon meteor station .............................................................................................................2-28 Table 2.23: Frequency of wind occurrence at 8 directions at months of rainy season (from September to December) - Quy Nhon meteor station ......................................2-28 Table 2.24: Frequency of wind occurrence at 8 directions at months of dry season (from Jan – August) - Quy Nhon meteor station .......................................................2-28 List of Table iv Nhon Hoi Wind farm project – Phase I Technical Design Table 2.25: Average wind speed of months in a year at Quy Nhon meteor station ..2-30 Table 2.26:Frequency of average wind speed levels at Quy Nhon meteor station ....2-30 Table 2.27: Maximum wind speed of months in a year at Quy Nhon meteor station ...231 Table 2.28: Maximum wind speed correspond to frequencies at 8 directions and nondirection at Quy Nhon meteor station .......................................................................2-31 Table 2.29: Standard wind pressure with repeated cycle of wind 1 time in 10 years and 1 time in 20 years .......................................................................................................2-32 Table 2.30: Precipitation and number of rainy days at Quy Nhon and Phu Cat stations ....................................................................................................................................2-33 Table 2.31: Rainfall volume corresponding to frequencies at Quy Nhon and Phu Cat stations ........................................................................................................................2-35 Table 2.32: Maximum daily precipitation at Quy Nhơn and Phù Cát stations ..........2-36 Table 2.33: Maximum rainfall volume at Quy Nhơn and Phù Cát stations...............2-37 Table 2.34: Maximum daily precipitation corresponding to frequencies at Quy Nhơn and Phù Cát stations ...................................................................................................2-37 Table 2.35: Maximum rainfall volume at design period ............................................2-38 Table 2.36: Annual average evaporation volume at Quy Nhon meteor station ........2-38 Table 2.37: The average number of sunshine hours in many years recorded at Quy Nhon meteor station ...................................................................................................2-39 Table 2.38: Number of days having thunderstorms in average month and year .......2-39 Table 2.39: Number of days having biggest thunderstorms in months and year at Quy Nhon meteor station ...................................................................................................2-40 Table 2.40: Statistic results of storms hitting Binh Dinh-Ninh Thuan area during the period of 1964 to 2017 ...............................................................................................2-41 Table 3.1: Coordinates of some main items of project ................................................3-1 Table 3.2: The operating frequency range of wind turbine........................................3-11 Table 3.3: Main specifications of wind turbines ........................................................3-12 Table 3.4: Specifications of the 0.69/22kV-5500kVA MV substation ......................3-15 Table 3.5: Specification of PPC device .....................................................................3-25 Table 4.1: Summary table of internal road lengths ....................................................4-12 List of Table v Nhon Hoi Wind farm project – Phase I Technical Design LIST OF FIGURE Figure 2.1: Project boundary ........................................................................................2-2 Figure 2.2: Some pictures of project area ....................................................................2-3 Figure 2.3: Topography map scale 1:500 of project, used for Technical Design ........2-5 Figure 2.4: Geological and Mineral resources map of Viet Nam on 1:200000 ...........2-6 Figure 2.5: Earthquake zoning map of Vietnam territory ..........................................2-18 Figure 2.6: Temperature variation progress at Quy Nhon station .............................2-26 Figure 2.7: Wind rose of months and year in Quy Nhon station ...............................2-29 Figure 2.8: Rainfall variation progress at Quy Nhon station .....................................2-35 Figure 2.9: Rainfall variation progress of months in a year at Phu Cat station .........2-36 Figure 3.1: Project General layout ...............................................................................3-3 Figure 3.2: The main components of wind turbines ....................................................3-5 Figure 3.3: Principle of the control of blades angle (pitch) .........................................3-8 Figure 3.4: Typical SLD of turbine ............................................................................3-14 Figure 3.5: RMU configuration..................................................................................3-16 Figure 3.6: Typical SCADA single line diagram .......................................................3-21 Figure 3.7: Typical fiber optic connection of WTG ..................................................3-21 Figure 3.8: Typical fiber optic connection of WTG’s switch ....................................3-21 Figure 3.9: Typical control system of wind power plant ...........................................3-22 Figure 3.10: Wind SCADA configuration .................................................................3-23 Figure 3.11: Single line diagram of SCADA’s communication ................................3-24 Figure 3.12: Normal Configuration ...........................................................................3-26 Figure 3.13: Quick Configuration ..............................................................................3-26 Figure 3.14: Lightning and grounding system of turbine’s tower .............................3-28 Figure 3.15: Gas automatic fire extinguishing system installed in wind turbines .....3-32 Figure 4.1: Foundation type 1 ......................................................................................4-3 Figure 4.2: Foundation type 2 ......................................................................................4-4 Figure 4.3: Typical laydown for asembly and installation...........................................4-4 List of Figure vi Nhon Hoi Wind farm project – Phase I Technical Design CHAPTER 1: OVERVIEW 1.1. LEGAL BASIS Technical design document of project "Nhon Hoi wind power plant – Phase I" is prepared on the following basis: - Law on Electricity No. 28/2004/QH11 dated December 3, 2004 of the National Assembly; Law amending and supplementing a number of articles of the Electricity Law No. 24/2012/QH13 dated November 20, 2012 of the National Assembly; - Law amending and supplementing a number of articles of 11 laws related to the National Assembly's Planning No. 28/2018/QH14 dated June 15, 2018; - Law on Construction No. 50/2014/QH13 dated June 18, 2014 of the National Assembly; - Law on Environmental Protection No. 55/2014/QH13 dated June 23, 2014 of the National Assembly; - Law on Investment No. 67/2014/QH13 dated November 26, 2014 of the National Assembly; - Law on Planning No. 21/2017/QH14 dated November 24, 2017 of the National Assembly; - Decree No. 46/2015/ND-CP dated May 12, 2015 on quality management and construction maintenance. - Decree No. 59/2015/ND-CP dated June 18, 2015 of the Government on management of construction investment projects. - Decree No. 42/2017/ND-CP dated April 5, 2017 of the Government amending and supplementing a number of articles of the Government's Decree No. 59/2015/ND-CP dated June 18, 2015 on construction investment project management; - Decision No. 37/2011/QD-TTg dated June 29, 2011 of the Prime Minister on the mechanism to support the development of wind power projects in Vietnam; - Decision No. 2068/QD-TTg dated November 25, 2015 of the Prime Minister approving the Strategy for development of renewable energy of Vietnam to 2030, with a vision to 2050; - Decision No. 428/QD-TTg dated March 18, 2016 of the Prime Minister approving the adjustment of National Electricity Development Plan for the period 2011-2020 with a vision to 2030; - Decision No. 39/2018/QD-TTg dated September 10, 2018 of the Prime Minister amending and supplementing a number of articles of Decision No. 37/2011/QD- Volume 1.1 – Chapter 1 1-1 Nhon Hoi Wind farm project – Phase I Technical Design TTg dated June 29, 2011 of Prime Minister on mechanism to support the development of wind power projects in Vietnam; - Circular 02/2019/TT-BCT dated 15/01/2019 of the Ministry of Industry and Trade on Regulations on implementing wind power project development and Power Purchase Agreement for wind power projects; - Circular 03/2016/TT-BXD: Circular Regulating the decentralization of construction works and guiding the application in the management of construction investment activities; - Circular 07/2019/TT-BXD: Amending, supplementing and replacing a number of provisions in Circular No. 03/2016/TT-BXD dated March 10, 2016 of the Minister of Construction on levels of construction works and instructions for application in construction management activities; - Decision No. 428/QD-TTg dated March 18, 2016 of the Prime Minister approving the adjusted national electricity development planning for the period 2011-2020 with a vision to 2030. - Circular No. 39/2015/TT-BCT dated November 18, 2015 of the Ministry of Industry and Trade on regulations on distribution power system. - Circular No. 30/2019/TT-BCT dated November 18, 2019 of the Ministry of Industry and Trade on amending and supplementing a number of articles of the Ministry's Circular No. 25/2016/TT-BCT dated November 30, 2016 The Minister of Industry and Trade regulates the power transmission system and the Circular No. 39/2015/TT-BCT dated November 18, 2015 of the Minister of Industry and Trade regulating the distribution power system; - Decision No. 332/QÐ-BCT dated February 3, 2017 of the Ministry of Industry and Trade approving “Power development planning of Binh Dinh province for the period 2016-2025, with consideration of 2035 Master plan for 110kV electric system "; - Investment policy Decision No. 30/QD-BQL dated February 7, 2020 of the Management Board of Binh Dinh Economic Zone on approving the investment policy for FICO Investment Joint Stock Company to invest in the project Nhon Hoi 1 wind power plant in Nhon Hoi Economic Zone, Binh Dinh province; - Decision No. 76/QD-BQL dated 25/03/2020 of the Management Board of Binh Dinh Economic Zone on adjustment of Decision No. 30/QD-BQL dated February 7, 2020 of the Management Board of provincial economic zones Binh Dinh (renamed the project "Nhon Hoi wind power plant - Phase 1)"; - Document No. 1264/UBND-KT dated 04/3/3020 of the People's Committee of Binh Dinh province agreeing the direction of the 110kV line connected, the Volume 1.1 – Chapter 1 1-2 Nhon Hoi Wind farm project – Phase I Technical Design 22kV power line for construction, self-use of Nhon Hoi 1 and Nhon Hoi wind power plants 2; Document No. 5714/UBND-KT, dated 25/8/2020 on the adjustment of some contents in Document No. 1264/UBND-KT dated 04/3/3020 of the Provincial People's Committee; - Agreement on connecting Nhon Hoi wind power plant - Phase 1 and Nhon Hoi wind power plant - Phase 2 between Central Power Corporation and Fico Binh Dinh Energy Joint Stock Company on June 19, 2020 ; - Agreement on technical design of SCADA Telecommunication system for Nhon Hoi wind power plant project - Phase 1 No. 2435/ĐĐQG-CN dated 27/7/2020 between the National Load Dispatch Center and the Company FICO Binh Dinh Energy Joint Stock Company; - Agreement on technical design of the protective and automatic relay system of Nhon Hoi wind power plant project - phase 1 No. 41/2020/ĐĐQG-TTRL dated August 7, 2020 between the National Load Dispatch Center and Fico Binh Dinh Energy Joint Stock Company; - Agreement on technical design of power metering system and metering data collection system for Nhon Hoi wind power plant - phase 1, Binh Dinh province No. 4706/EPTC-KT & IT-KDBD dated September 14, 2020 between Power Trading Company and Fico Binh Dinh Energy Joint Stock Company; - Document No. 286/TC-QC dated June 25, 2020 of the Department of Warfare Ministry of General Staff approving the static altitude for construction of Nhon Hoi wind power plant project - phase 1; - Decision No. 2025/QD-UBND dated May 26, 2020 of the People's Committee of Binh Dinh province approving the detailed construction planning project of 1/500 scale of Nhon Hoi wind power plant - Phase 1, Nhon Hoi Economic zone; - Document No. 805/BQL-QLQHXD dated 18/6/2020 of Binh Dinh Economic Zone Management Board on notification of results of basic design appraisal of Nhon Hoi wind power plant project - Phase 1; - Document No. 1208/BQL-QLQHXD dated September 1, 2020 of the Management Board of Economic Zone of Binh Dinh province confirming the completion of basic design documents of Nhon Hoi 1 and 2 wind power plants; - Decision No. 11/2020/QD-BDE dated October 1, 2020 of FICO Binh Dinh Energy Joint Stock Company approving the feasibility study report on investment in construction of Nhon Hoi wind power plant project - Phase 1. Volume 1.1 – Chapter 1 1-3 Nhon Hoi Wind farm project – Phase I 1.2. Technical Design MAIN PROJECT INFORMATION 1.2.1. Project scale Nhon Hoi wind power plant - Phase I is invested by Binh Dinh FICO Energy Joint Stock Company with a total installed capacity of 30 MW with the project scale as follows: - Type of project: Industry and energy. - Grade of work: Class II. - Construction group: Group B. - The main items of the project: + Construction of wind power plants using horizontal axis wind turbine technology, including 6 turbines, each with a capacity of 5.0MW. + Construction of internal 22kV power grid within the plant to connect wind turbines, combining underground cable and overhead lines solutions. + Construction of 110kV substation of Nhon Hoi wind power plant, capacity of 2x40MVA to share the same infrastructure connection for Nhon Hoi wind power plant - Phase I and Nhon Hoi wind power plant - Phase II. Each project is connected to 1 22/110kV - 40 MVA transformer. + Construction of dual-circuit 110kV transmission line, ACSR 240 conductor, approximately 0.25km in length from the 110kV Nhon Hoi wind power plant substation to transitional connect to 110kV Nhon Hoi - Dong Da transmission line. + Construction of an O&M Building to serve the general operation of Nhon Hoi wind power plant - Phase I and Nhon Hoi wind power plant - Phase II. + Construction of road infrastructure including access road connecting to existing National Highway 19B and internal road for plant construction and operation 1.2.2. Land usage demand Summary of land usage demand of the project is as follows: Table 1.1: Summary of land uasge demands of project Area (ha) No. Item I 1 Phase 1 Phase 2 Total Long term land usage 10.28 7.43 17.71 Wind turbine and harstand area 1.32 1.38 2.70 Volume 1.1 – Chapter 1 1-4 Nhon Hoi Wind farm project – Phase I Technical Design Area (ha) No. Item Phase 1 Phase 2 Total 2 110kV substation 0.70 - 0.70 3 Internal route (including MV cable) 7.81 6.05 13.86 4 O&M building 0.40 - 0.40 5 110kV transmission line foundation 0.05 - 0.05 6 22kV transmission line foundation 0.10 0.10 0.20 II Temporary land usage 6.23 4.22 10.45 1 Site office 0.20 - 0.20 2 Storage area 1.40 - 1.40 3 Disposal area 4.63 4.22 8.85 Therefore, the land usage area of the project is fully compliant with the provisions of Clause 2, Article 12, Circular 02/2019/TT-BCT: long term land usage of wind power plant shall not exceed 0.35 ha/MW, the temporary land usage of wind power plan shall not exceed 0.3 ha/MW. 1.2.3. Applied standard 1.2.3.1. Wind turbines standard - IEC 61400-1 : Wind Turbines – General design requirements; IEC 61400-4 : Wind Turbines – Design requirements for wind turbine gearboxes; IEC 61400-11 : Wind Turbines – Acoustic noise measurement techniques; IEC 61400-12-1 : Wind Turbines – Wind energy efficiency measurements; IEC 61400-13 : Wind Turbines – Measurement of mechanical loads; IEC 61400-21 : Wind Turbines – Measurement and assessment of power quality characteristics of grid connected wind turbines; IEC 61400-22 : Wind Turbines – Conformity testing and certification; IEC 61400-23 : Wind Turbines – Full-scale structural testing of rotor blades; IEC 61400-25 : Wind Turbines – Communications for monitoring and control of wind power plants; IEC 61400-27-1 : Wind Turbines – Electrical simulation models – Generic models Volume 1.1 – Chapter 1 1-5 Nhon Hoi Wind farm project – Phase I Technical Design 1.2.3.2. Wind turbine generator - IEC 60034-1 to 60034-11 – Rotating electrical machines ANSI B 49.1/IEEE Std 810-1987 – Shaft Couplings NEMA ANSI/IEEE Std 810-1987 – Shaft Alignment ISO 10816 – Mechanical vibration — Evaluation of machine vibration by measurements on non-rotating ISO 10816-3 1998-05 Part 3 Industrial machine with capacity of over 15kW, speed from 120 rpm to 15000 rpm when measured in the field. 1.2.3.3. Semiconductor Converters - IEC 60146-1-1: General requirements and line commutated converters – Part 11: Specification of basic requirements IEC 60146-1-2: General requirements and line commutated converters – Part 12: Application guide IEC 60146-1-3: General requirements and line commutated converters – Part 13: Transformers and Reactors 1.2.3.4. Control, protection and automatic - - IEC 60870 - Telecontrol equipment and systems (WAN network); IEC 61850 - Communication networks and systems for power utility automation (LAN network); IEC 61255 - Protective relays; IEEE 1131/IEC 61131 - Programmable Controllers; IEC 60794-1-31:2018 - Optical fibre cables; IEC 60874 - Fibre optic interconnecting devices and passive components; IEC 61508 – Functional safety of electrical/electronic/programmable electronic safety-related systems; ICCP - Central protocol link control; IEEE 802 - Standards for local area networks; IEC 60870-5-104 - Telecontrol equipment and systems – Part 5-104: Transmission protocols – Network access for IEC 60870-5-101 using standard transport profiles; IEC 61158 - Industrial communication networks – Fieldbus specifications; IEC 61784 - Industrial communication networks; IEC 60870-5-101 - Telecontrol equipment and systems – Part 5-101: Transmission protocols – Companion standard for basic telecontrol tasks; IEC 60870-5-103 - Telecontrol Equipment and Systems - Part 5-103: Transmission Protocols - Companion Standard for the Informative Interface of Protection Equipment; 1.2.3.5. Mechanical structure and components - ISO 2394 General principles of structural reliability Volume 1.1 – Chapter 1 1-6 Nhon Hoi Wind farm project – Phase I - Technical Design ISO 76, Roller Bearing - Static load rating ISO 281:2007, Roller Bearing - Rated dynamic load and rated service life ISO 683 (all components), Heat-resistant steel, alloy steel and free-cut steel ISO 1328-1, Cylindrical gear - ISO precision system - Part 1: Definition and allowable deviation values relative to the rib of the respective gear ISO 6336 (all components), Calculate the load capacity of helical gears ISO 6336-1: 2006, Calculation the load supporting ability of helical gear and volute gear - Part 1: Basic principles, introduction and general influence factors ISO 6336-2: 2006, Calculation the load supporting ability of helical gear and volute gear - Part 2: Calculation of surface strength (pitting) ISO 12925-1, Lubricants, industrial oils and related products (type L). Family C (Gears) - Part 1: Specifications for lubricants for enclosed gear systems DIN 743: 2000: Shaft, calculation of load capacity, Sections 1,2, 3 DIN 3990-4: Calculate the load supporting ability of the cylinder gear: calculate the load supporting ability DIN 6885-2: Parallel keys, deep pattern for machine, dimensions and application 1.2.3.6. Electrical equipment standards - IEC 60076 : Power transformers. IEC 60137 : Insulated bushings for alternating voltages above 1000 V. IEC 60296 : Fluids for electrotechnical applications – Mineral insulating oils for electrical equipment. IEC 60156 : Insulating liquids - Determination of the breakdown voltage at power frequency - Test method. IEC 60085 : Electrical insulation – Thermal evaluation and designation. IEC 60044-1 : Instrument transformers - Part 1: Current transformers; IEC 60044-5 : Instrument transformers . Part 5: Capacitor voltage transformers; IEC 60099-3 : Surge Arresters Part 3: Artificial Pollution Testing of Surge Arresters; IEC 60093-4 : Surge arresters – Part 4: Metal-oxide surge arresters without gaps for a.c. systems; IEC 60099-5 Surge arresters – Part 5: Selection and application recommendations; IEC 60071 : Insulation co-ordination; IEC 60056 : High-voltage alternating-current circuit-breakers IEC 62271-100: High-voltage switchgear and controlgear – Part 100: Alternating-current circuit-breakers; IEC 62271-110: High-voltage switchgear and controlgear - Part 110: Inductive load switching; IEC 60376 : Specification of technical grade sulphur hexafluoride (SF6) and complementary gases to be used in its mixtures for use in electrical equipment; Volume 1.1 – Chapter 1 1-7 Nhon Hoi Wind farm project – Phase I - - - Technical Design IEC 62271-102: High-voltage switchgear and controlgear - Part 102: Alternating current disconnectors and earthing switches; ISA S18.1 : Annunciator Sequences and Specifications; ISA S5.5 : Graphic Symbols for Process Displays; ISA RP60 : Control Center Design Guide and Terminology; ICCP : Central protocol link control; NEMA PB1-197: Panelboards; IEEE 1131 / IEC 61131: Programmable Controllers; IEEE 802 : Standards for local area networks; IEC 61000 : Electromagnetic compatibility (EMC); IEC 61850 : Communication networks and systems for power utility automation; IEC 60870-5-104: Telecontrol equipment and systems – Part 5-104: Transmission protocols – Network access for IEC 60870-5-101 using standard transport profiles; IEC 60870-5-101: Telecontrol equipment and systems – Part 5-101: Transmission protocols – Companion standard for basic telecontrol tasks; IEC 60794 : Optical fibre cables; IEC 61158 : Industrial communication networks – Fieldbus specifications; IEC 61784 : Industrial communication networks; IEC 60255 : Measuring relays and protection equipement; IEC 60870-5-103: Telecontrol Equipment and Systems - Part 5-103: Transmission Protocols - Companion Standard for the Informative Interface of Protection Equipment; IEC 60189 : Low-frequency cables and wires with PVC insulation and PVC sheath; IEC 60227 : Polyvinyl Chloride Insulated Cables of Rated Voltages up to and Including 450/750 V; IEC 60228 : Conductors of Insulated Cables; IEC 60230 : Impulse Tests on Cables and Their Accessories; IEC 60287 : Electric cables – Calculation of the current rating; IEC 60304 : Standard Colours for Insulation for Low-Frequency Cables and Wires; IEC 60331 : Fire-Resisting Characteristics of Electric Cables; IEC 60332 : Tests on electric and optical fibre cables under fire conditions; IEC 60391 : Marking of Insulated Conductors; IEC 60423 : Conduit systems for cable management – Outside diameters of conduits for electrical installations and threads for conduits and fittings; IEC 60502 : Extruded Solid Dielectric Insulated Power Cables for Rated Voltages from 1 kV up to 30 kV; IEC 60793 : Optical fibres; IEC 60794 : Optical fibre cables; Volume 1.1 – Chapter 1 1-8 Nhon Hoi Wind farm project – Phase I - Technical Design IEC 60811 : Electric and optical fibre cables – Test methods for non-metallic materials; IEC 60874 : Fibre optic interconnecting devices and passive components – Connectors for optical fibres and cables; Regulations on electrical equipment 11TCN–18–2006, 11TCN–19–2006, 11TCN–20– 2006, 11TCN–21-2006. 1.2.3.7. Civil standards a. Standards for turbine foundation - EN 1992-1 Eurocode 2 - Design of concrete structures. - CEB-FIB Model Code 2010 - Model code for concrete structures. - EN 1997-1 Eurocode 7 - Geotechnical design. - EN 206-1 Concrete: Specification, performance, production and conformmity - IEC 61400-1 Wind turbines – Part 1: Design requirement b. Others civil standard - TCVN 2682: 2009 Portland cements - Specifications - TCVN 6260: 2009 Portland blended cement - Specifications. - TCVN 6227 :1996 ISO standard sand for determination of cement strength. - TCVN 7570:2006 Aggregates for concrete and mortar - Specifications. - TCVN 7570: 2006 Aggregates for concrete and mortar - Specifications. - TCVN 7572: 2006 Aggregates for concrete and mortar - Test methods. - TCVN 4506: 2012 Water for concrete and mortar - Technical specification. - TCVN 6884:2001 Ceramic tiles with low water absorption – Specification - TCVN 5574:2018 Design of concrete and reinforced concrete structures. - TCVN 9340: 2012 Ready-mixed concrete - Specification and acceptance. TCVN 8828 :2011 Concrete - Requirements for natural moist curing. TCVN 9115:2019 Assembled concrete and reinforced concrete structures Practice for erection and acceptance. TCVN 4453:95 Monlithic concrete and reinforced concrete structures - Codes for construction, check and acceptance TCVN 3118:93 Heavyweight concrete - Method for determinatien of compressive strength TCVN 3106:93 Fresh heavyweight concrete - Method for slump test. TCVN 1651-1: 2018 Steel for the reinforcement of concrete - Part 1: Plain bars. TCVN 1651:2-2018 Steel for the reinforcement of concrete - Part 2: Ribbed bars TCVN 5709: 2009 Hot rolled carbon steel for building - Technical requirements TCVN 197-1:2014 Metallic materials - Tensile testing - Part 1: Method of test at room temperature TCVN 198:2008 Metallic materials - Bend test. TCVN 1765-75 Carbon steel - General structures, Steel grades and specifications Volume 1.1 – Chapter 1 1-9 Nhon Hoi Wind farm project – Phase I - Technical Design TCVN 5847:2016 Spun precast reinforced concrete poles TCVN-134-77 Washers fechnical requirements TCVN 130-77 Lock Washers TCVN 170-2007 Steel structures – Fabrication, assembly, check and acceptance – Technical requerements 1.2.3.8. Firefighting system standards - TCVN 2622: 1995 - Fire prevention and protection for buildings and structures Design requirements. - TCVN 4513 - 1988: Internal water supply – Design standard. - TCVN 5040: 1990 - Fire prevention and protection equipments - Graphical symbols used for protection schemes – Specifications. - TCVN 3890: 2009 Fire protection equipments for construction and building – Providing, installation, inspection, maintenance. - TCVN 7435-1:2004 - Fire protection – Portable and wheeled fire extinguishers Part 1: Selection and Installation. - TCVN 5738 – 2001 Fire detection and alarm system - Technical requirements. - TCVN 6100: 1996 (ISO 5923:1984) Fire protection - Fire extinguishing media – carbon dioxide. - TCVN 6102:1996 ISO 7202:1987 Fireprotection– Fire extinguishingmedia– Powder. - Gas fire extinguishing Novec 1230 system for wind turbines, according to NFPA 2001 standard. - Electrical equipment regulations: 11 TCN 18-2006; 11 TCN 19-2006; 11 TCN 20- 2006; 11 TCN 21- 2006. - TCVN 6160:1996: Fire protection - High rise building - Design requirements; - TCVN 5738: 2001: Automatic fire alarm system; - TCXD 218: 1998. Fire detection system and fire alarm. - TCVN 7568-1:2006. Fire alarm system. Part 1: General rules and definitions. - TCVN 7568-2:2013. Fire alarm system. Part 2: Fire alarm control panel. - TCVN 7568-3:2015. Fire alarm system. Part 3: Sound alarm equipment. - TCVN 7568-4:2013. Fire alarm system. Part 4: Power supply equipment. - TCVN 7568-5:2003. Fire alarm system. Part 5: Point-type fire detectors. - TCVN 7568-6:2013. Fire alarm system. Part 6: Carbon monoxide fire detector use electrochemical battery. - TCVN 7568-7:2015. Fire alarm system. Part 7: Point type smoke detector using light, scattering or ionizing light. Volume 1.1 – Chapter 1 1-10 Nhon Hoi Wind farm project – Phase I Technical Design - TCVN 7568-8:2015. Fire alarm system. Part 8: Point-type fire detectors that use carbon monoxide sensors in combination with heat sensors. - TCVN 7568-9:2015. Fire alarm system. Part 9: Test fires for fire detectors. - TCVN 7568-10:2015. Fire alarm system. Part 10: Point-type fire detectors. - TCVN 7568-11:2015. Fire alarm system. Part 11: Fire alarm button box. - TCVN 7568-12:2015. Fire alarm system. Part 12: Transmission line smoke detector using optical beam. - TCVN 7568-13:2015. Fire alarm system. Part 13: Assessment of compatibility of components in the system. - TCVN 7568-14:2015. Fire alarm system. Part 14: Design, installation, operation and maintenance of fire alarm systems in and around the building. - TCVN 7568-15:2015. Fire alarm system. Part 15: Point-type fire detectors that use smoke and heat sensors - QCVN 06:2020/BXD National technical regulation on fire safety for houses and buildings 1.3. INPUT FOR TECHNICAL DESGIN The input documents serving the Technical design of Nhon Hoi wind power plant - Phase I include: - The legal bases of the project - Basic design documents have been evaluated and approved - Profile of the technical design survey by 23 Construction Consulting Joint Stock Company done in November 2020, including: + Topographic survey report + Construction geological survey report + Meteorological - hydrological survey report - Employer Requirements for EPC Contractor - EPC contractor's technical proposal (Powerchina Vietnam Limited Company) includes the following main contents: + Technical specifications and characteristics of wind turbines proposed for the project + Design requirements and recommendations of the wind turbine manufacturer + Report on wind energy assessment and calculation of annual energy production + Other related documents Volume 1.1 – Chapter 1 1-11 Nhon Hoi Wind farm project – Phase I Technical Design CHAPTER 2: SPECIFICATION OF PROJECT AREA 2.1. PROJECT LOCATION 2.1.1. Project location Nhon Hoi wind power plant - Phase I is located on the western slope of Phuong Mai mountain range, located in the wind power planning area of Nhon Hoi economic zone, in the territory of Nhon Ly and Nhon Hoi communes, Quy Nhon city, Binh Dinh province. The project's geographic coordinates at center of project is 13°51'17.24”, 109°16'48.12”. The total area of about 175 ha which has the following boundaries: - The North borders: Adjacent to QNY - Korea Solar Power project - The South borders: Adjacent to Nhon Hoi wind power project- Phase II. - The East borders: adjacent to the sea and Ky Co tourist area. - The West borders: Adjacent to the 110kV route of Nhon Hoi - Dong Da transmission line. The project boundary has the following coordinates Table 2.1: Project coordinates Point VN2000 coordinates, 3o projection, 108o15' central meridian X (m) Y (m) Boundary of Nhon Hoi WPP – Phase I Volume 1.1 – Chapter 2 M1 1533635.13 610619.67 M2 1532669.79 610677.22 M3 1532543.59 610781.54 M4 1532068.41 610826.06 M5 1531921.56 610922.25 M6 1531665.78 611220.99 M7 1531397.91 611349.07 M8 1531503.90 611550.30 M9 1531745.67 611423.98 M10 1531836.55 611627.93 M11 1531941.12 611581.01 M12 1532278.15 611603.54 2-1 Nhon Hoi Wind farm project – Phase I Point Technical Design VN2000 coordinates, 3o projection, 108o15' central meridian X (m) Y (m) M13 1532437.32 611456.50 M14 1532652.82 611357.23 M15 1532840.22 611397.08 M16 1533022.76 611767.92 M17 1533835.50 611602.17 Area: 175ha Nhon Hoi WPP – Phase I Nhon Hoi WPP – Phase II Figure 2.1: Project boundary Volume 1.1 – Chapter 2 2-2 Nhon Hoi Wind farm project – Phase I Technical Design 2.1.2. Some pictures of project area Figure 2.2: Some pictures of project area 2.2. SITE CONDITIONS OF PROJECT AREA 2.2.1. Topography conditions Nhon Hoi wind power plant - Phase I is located Nhon Hoi economic zone, in the territory of Nhon Ly and Nhon Hoi communes, Quy Nhon city, Binh Dinh province Terrain of the surveyed area is average low mountainous area with natural elevation from hill top from 50m to 360m. The terrain surface is undulated with strongly Volume 1.1 – Chapter 2 2-3 Nhon Hoi Wind farm project – Phase I Technical Design dissected level. Erosion, denudation developed strongly in hill sides. Accumulation process occurs with slow rate at low depression areas and along watersheds. In the project area, the terrain has a steep slope divided by streams and rocks, the road is difficult, the land cover is mainly in the bush and thorn trees. The topographical survey scope in the Basic Design stage measured 1:2000 topography of the project boundary. On that basis, the main items of the project were basically designed. The scope of topographic survey in the stage of Technical design, measuring and drawing topographic maps of 1:500 of project area, which is enough to design the following items: - Turbine foundation - Turbine hardstanding - Access road, site office and storage area - Internal road - MV grid: 22kV underground cable and Overhead line - 110kV substation - O&M Building - 110kV transmission line (particular for 110kV transmission line foundation, surveyed topography map is 1:200) Result of surveyed topography map as in Figure 2.3. The detailed topographical survey results are shown in the topographic survey report of Nhon Hoi wind power plant project - Phase 1 & Phase 2 performed by 23 Construction and Consulting Joint Stock Company implemented in November 2020. Volume 1.1 – Chapter 2 2-4 Nhon Hoi Wind farm project – Phase I Technical Design Figure 2.3: Topography map scale 1:500 of project, used for Technical Design Volume 1.1 – Chapter 2 2-5 Nhon Hoi Wind farm project – Phase I Technical Design 2.2.2. Construction geological conditions 2.2.2.1. General Geological features According the Geological and Mineral resources map of Viet Nam on 1:200000, published by Department of Geological and Mineral of Viet Nam in 1997, locations of the Nhon Hoi Wind Farm are within the distribution of rock, soil of Nha Trang formation and Quaternary sediments. In addition, there is an an extrusive igneous rock of the Deo Ca complex distributed in the east of the project. CRETACEOUS Nha Trang Formation (Knt) The composition mainly includes rhyolite, dacite, andesite and their tuffs. 450600m thick. Nha Trang formation is distributed throughout the scope of the project. QUATERNARY Middle-Upper Holocene (mvQIV2-3) The composition mainly includes yellow grey quartz sand, silt. 10-20m thick. These sediments are mainly distributed in the western and northern extent of the project. EXTRUSIVE IGNEOUS ROCKS Deo Ca Complex - Phase 2 (-Kdc2) The composition mainly includes coarse to medium-grained granite, biotite (hornblende) granosyenite. Deo Ca Complex is distributed in the east, out of the project area. Figure 2.4: Geological and Mineral resources map of Viet Nam on 1:200000 Volume 1.1 – Chapter 2 2-6 Nhon Hoi Wind farm project – Phase I Technical Design 2.2.2.2. Physical mechanical properties of rock, soil within the scope of project construction area 2.2.2.2.1. Engineering geological layer within the project scope Based on the drill core, the results of soil and rock mechanical samples testing and assessment at the site, soil and rock are divided in the project area into 05 layers as follows: Table 2.2: Geological layer within the project scope Lay er 1 2 3 4 5 Layer name mvQIV Layer of marine and wind deposit edQ+IA1 Layer of eluvial deluvial and Zone of complete weathered rock Reddish brown, brownish clay loam, in hard state, mixed with gravel, block stones. Most of them use a shovel to dig Medium Zone of strongly weathered rock Bedrock is gray brown, soft to medium hard, with particularly strong fracture, mixed with some clay loam. More than half of the rock material becomes soft and exists either as monolithic or completely discolored rock cores compared to fresh rock. Using a shovel to dig, although sometimes difficult to dig, using crowds or sometimes mines High Zone of medium weathered rock Bedrock is brownish gray, greenish gray, from medium to hard, very strong fracture. The rock stains or has white streaks, no longer retains its original color. Digging must use mines Very high Zone of fresh rock Bedrock is greenish gray, light gray, the rock is hard to very hard, strongly cracked. The rock is slightly and locally discolored. Weathering on the surface of crevices and other defects, oxidation penetration up to 3mm. Digging must use mines. Very high IA2 IB IIA Description Load bearing capacity Symbols Medium grain sand color is in yellowish grey, tight structured Well Khá 2.2.2.2.2. Results of standard penetration test SPT SPT is carried out in layer 1 and layer 2 of most boreholes, the results are as follows: Volume 1.1 – Chapter 2 2-7 Nhon Hoi Wind farm project – Phase I Technical Design Table 2.3: Results of standard penetration test SPT No. Borehole Location 1 NH-1 WTG 1 2 NH-1A WTG 1 3 NH-2 WTG 2 4 NH-2A WTG 2 5 NH-3 WTG 3 6 NH-3A WTG 3 Volume 1.1 – Chapter 2 Depth (m) Layer 2 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 1 2 3 4 1 2 3 4 5 6 7 8 9 10 1 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 Value SPT N30 47 96 25 21 24 24 27 26 22 23 22 25 26 30 33 32 32 34 34 Rock 23 34 31 Rock 9 11 10 14 16 21 23 21 25 27 25 27 27 2-8 Nhon Hoi Wind farm project – Phase I No. Borehole Location 7 NH-4 WTG 4 8 NH-4A WTG 4 9 NH-5 WTG 5 10 NH-5A WTG 5 11 NH-7 WTG 7 Volume 1.1 – Chapter 2 Technical Design Depth (m) Layer 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 1 2 1 3 4 5 6 7 8 9 10 11 1 2 3 4 5 6 7 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Value SPT N30 29 33 31 37 35 40 43 72 78 32 31 25 36 48 77 84 100 106 37 48 75/5cm 19 21 21 25 43 71 74 38-50/8cm 42-50/5cm 25 28 27 29 28 34 30 26 2-9 Nhon Hoi Wind farm project – Phase I No. Borehole Location 12 NH-7A WTG 7 13 NH-13 WTG 13 14 DVH-1 Road route 15 DVH-2 Road route 16 DVH-3 Road route 17 DVH-4 Road route 18 DVH-5 Road route Volume 1.1 – Chapter 2 Technical Design Depth (m) Layer 2 1 2 2 3 4 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 1 2 3 4 5 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 1 1 1 1 2 2 Value SPT N30 40 27 31 25 31 40 41 45 47 52 40 35 37 40 42 48 23 21 34 15 16 19 23 26 31 34 21 18 30 41 38 39 7 6 11 27 30 34 2-10 Nhon Hoi Wind farm project – Phase I No. Borehole Location 19 DVH-7 Road route 20 DVH-9 Road route 21 DVH-11 Road route 22 DVH-12 Road route 23 DVH-13 Road route 24 TBA-1 Substation 25 TBA-2 Substation 26 TTB-1 Yard equipment 27 28 TTB-2 NQL-1 Yard equipment Management house 29 NQL-2 Management house Volume 1.1 – Chapter 2 Technical Design Depth (m) Layer 1 2 3 3 4 5 6 1 2 1 2 3 4 5 6 7 8 9 10 2 1 2 3 4 1 2 3 1 2 3 4 1 1 1 2 3 4 5 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Value SPT N30 21 30 58 24 27 26 28 30 31 26 26 23 25 29 27 28 25 29 28 Rock 31 37 37 46 30 34 28 31 30 34 31 Rock 33 20 44 58 60 Rock 2-11 Nhon Hoi Wind farm project – Phase I No. Borehole Technical Design Location 30 DZ-1 Transmission line 31 DZ-4 Transmission line Depth (m) Layer 2 3 4 1 2 2 2 2 Value SPT N30 26 30 29 31 Average SPT value by layer (SPT N30): - Layer 1 : 27. - Layer 2 : 35. 2.2.2.2.3. Physical mechanical properties of rock, soil layers Determination of physical and mechanical properties of soil and rock was conducted by sampling in boreholes and then transferred to the laboratory department for analysing at LAS XD-641 Testing Center of Construction and Consulting Joint Stock Company 23. Each geological layer was carried out to take experimental samples. The data of experimental samples at each WTG are shown in the "Summary of physical and mechanical properties of soil and rock samples". The samples were collected by layers, statistics and excluded raw errors according to TCVN 9153: 2012 Statistics quantity of samples taken and tested by layer: Table 2.4: Physical mechanical properties of rock, soil layers Layer Quantity of sample Notes 1 33 Disturbed soil samples 2 122 Undisturbed & Disturbed soil samples 3 0 Can not taken samples. All physical and mechanical indicators referenced in the project are similar and the proposed by experience 4 13 Rock samples 5 60 Rock samples Recommended that standard values and calculation of geological layers within the project scope are as follows: Volume 1.1 – Chapter 2 2-12 Nhon Hoi Wind farm project – Phase I Technical Design a. Layer 1: Table 2.5: Recommended standard values and calculation of geological layer 1 Parameters Symbol Unit Values Sand Graine (ASTM D422) - % 43.2 Humidity W % 41.3 Natural density (*) w g/cm3 1.68 Density g/cm3 2.76 Viscosity (*) e - 0.623 Inner friction angle (*) độ 33000’ Cohesion force (*) C kG/cm2 0.024 Total transformation module (*) E0 kG/cm2 155.5 Conventional load capacity R0 kG/cm2 3.0 (*) Recommended value b. Layer 2: Table 2.6: Recommended standard values and calculation of geological layer 2 Parameters Symbol Unit Values Clay Graine (ASTM D422) - % 18.7 Humidity W % 18.6 Natural density w g/cm3 1.76 Saturated state density (recommended value) bh g/cm3 1.85 Dry density k g/cm3 1.46 Density g/cm3 2.71 Elasticity (ASTM D4318) Ip % 35.6 Viscosity B - -0.18 Viscosity e - 0.857 độ 22003’ 21006’ Natural inner friction angle (*) Saturated state inner friction angle (recommended value) bh độ 20031’ 18040’ Natural cohesion force (*) C kG/cm2 0.290 0.276 Volume 1.1 – Chapter 2 2-13 Nhon Hoi Wind farm project – Phase I Technical Design Parameters Symbol Unit Values Saturated state cohesion force (recommended value) Cbh kG/cm2 0.236 0.206 Compression coefficient a1-2 cm2/kG 0.022 Total transformation module E0 kG/cm2 166.2 Conventional load capacity R0 kG/cm2 2.24 Standard value Calculated value (*) c. Layer 3: Table 2.7: Recommended standard values and calculation of geological layer 3 Parameters Recommended Symbol Unit Density g/cm3 2.64 Natural density O g/cm3 2.49 Saturate density H g/cm3 2.54 Dry humidity W0 % 0.49 Saturate humidity WH % 2.38 Porosity n % 6.06 Natural compressive strength Rn kG/cm2 110 Natural tensile strength Rk kG/cm2 8 values Calculation results according to Hoek - Brown standard according to the following tables Table 2.8: Calculation results according to Hoek – Brown Layer 3 Uniaxial compressive GSI strength (Mpa) Rock stype Layer Bedrock (Volcanic) Layer 3 10 20 mi D MR Ei (Mpa) 25 0.5 400 8000 Stress 3max (Mpa) 1.0 Table 2.9: Calculation results according to Hoek – Brown Layer 3 Targets of rock The criteria index/calculated index according to Hoek & (According to Mohr- Coulumb) Brown Hoek & Brown Model constant mb s a mb s a mb s 0.554 0.00002 0.544 0.554 0.00002 0.544 0.554 0.00002 Volume 1.1 – Chapter 2 2-14 Nhon Hoi Wind farm project – Phase I Technical Design Recommended value d. Layer 4: Table 2.10: Recommended standard values and calculation of geological layer 4 Parameters Symbol Unit Values Density g/cm3 2.70 Natural density O g/cm3 2.65 Saturate density H g/cm3 2.67 Dry humidity W0 % 0.26 Saturate humidity/ WH % 0.81 Porosity n % 2.16 Natural compressive strength (*) Rn kG/cm2 335 270 Natural tensile strength (*) Rk kG/cm2 33 26 Standard value Calculated value Calculation results according to Hoek - Brown standard according to the following tables (*) Table 2.11: Calculation results according to Hoek – Brown Layer 4 Rock stype Bedrock (Volcanic) Layer Uniaxial compressive GSI strength (Mpa) mi D Layer 33.5 (*) 27.0 25 0.4 30 MR Ei (Mpa) Stress 3max (Mpa) 400 13400 (*) 10800 1.0 Table 2.12: Calculation results according to Hoek – Brown Layer 4 Targets of rock according to Hoek & Brown Hoek & Brown Model constant mb s a 1.098 0.0001 0.522 (*) The criteria index/calculated index (According to Mohr- Coulumb) mb s a 1.098 0.0001 0.522 mb 1.098 s 0.0001 Standard value Calculated value Volume 1.1 – Chapter 2 2-15 Nhon Hoi Wind farm project – Phase I Technical Design e. Layer 5: Table 2.13: Recommended standard values and calculation of geological layer 5 Parameters Symbol Unit Values Density g/cm3 2.72 Natural density O g/cm3 2.70 Saturate density H g/cm3 2.71 Dry humidity W0 % 0.12 Saturate humidity WH % 0.30 Porosity n % 0.78 Natural compressive strength (*) Rn kG/cm2 879 837 Natural tensile strength (*) Rk kG/cm2 88 83 Calculation results according to Hoek - Brown standard according to the following tables Table 2.14: Calculation results according to Hoek – Brown Layer 5 Rock stype Bedrock (Volcanic) Layer Uniaxial compressive GSI strength (Mpa) mi D Layer 87.9 (*) 83.7 25 0.3 75 MR Ei (Mpa) Stress 3max (Mpa) 400 35160 (*) 33480 1.0 Table 2.15: Calculation results according to Hoek – Brown Layer 5 Targets of rock according to Hoek & Brown Hoek & Brown Model constant mb s a 8.745 0.0457 0.501 (*) The criteria index/calculated index (According to Mohr- Coulumb) mb s a 8.745 0.0457 0.501 mb 8.745 s 0.0457 Standard value Calculated value 2.2.2.3. Engineering geological kinetic phenomenon 2.2.2.3.1. Weathering phenomenon The weathering process is depended on many factors such as: topographic, geomorphological characteristics, climate, fractured level of bedrock... The weathering process of forming weathering crust has different thickness causing the surface of Volume 1.1 – Chapter 2 2-16 Nhon Hoi Wind farm project – Phase I Technical Design weathered cover is in undulated, serrated. The surveyed area in general and the scope of the survey in particular, the weathering process developed strongly. Data of boreholes show that the thickness of weathered cover is 1.0-18.0m. It’s expected that the weathered cover to be much deeper compared to the depth mentioned above. 2.2.2.3.2. Sliding phenomenon No natural sliding points have been detected within the project scope. At locations where the turbine foundations are located on steep hillsides and placed on top of the soil cover (layer 2), measures to protect the slope and foundation bottom should be taken to avoid sliding. 2.2.2.3.3. Earthquake The project is located between Quy Nhon city and Tuy Phuoc district. - According to the document "Earthquake zoning map of Vietnam territory" of the Institute of Geophysics (picture below), the project area has tremor level VII, maximum expected tremor level VII according to the MSK-64 scale. - According to the QCVN 02:2009/BXD Vietnam Building Code - Natural Physical & Climatic Data for Construction, the construction area is located in Quy Nhon city, Binh Dinh province with has peak ground acceleration of agR = 0.9228m/s2 corresponding to earthquake intensity of VII grade according to the MSK-64 scale. - According to the standard for designing earthquake-resistant works: TCVN 9386: 2012, the construction area is located in Quy Nhon city, Binh Dinh province with peak ground acceleration of (g) ag = 0.0941 (Appendix H) corresponding to earthquake intensity of VII grade (Appendix I) according to the MSK-64 scale. It is recommended to use earthquake level VII (scale MSK-64) for design. Volume 1.1 – Chapter 2 2-17 Nhon Hoi Wind farm project – Phase I Technical Design Figure 2.5: Earthquake zoning map of Vietnam territory Table 2.16: Table of converting ground acceleration to earthquake grade according to TCVN 9386:2012 Scale MSK-64 Scale NM Earthquake level Peak ground acceleration (a) g Earthquake level Peak ground acceleration (a) g V 0,012-0,03 V 0,03 - 0,04 VI > 0,03 - 0,06 VI 0,06 - 0,07 VII > 0,06 - 0,12 VII 0,10 - 0,15 VIII > 0,12 - 0,24 VIII 0,25 - 0,30 IX > 0,24 - 0,48 IX 0,50 - 0,55 X > 0,48 X > 0,60 Volume 1.1 – Chapter 2 2-18 Nhon Hoi Wind farm project – Phase I Technical Design In addition, there is no engineering kinetic geological phenomenon that affects to construction work. 2.2.2.4. Hydrological geological features The project's terrain is hilly and mountainous, so water is poor, the water table is deep and fluctuates greatly according to seasons. At the time of the survey, only a few boreholes with groundwater appeared quite deep, most of which did not have groundwater. Surface water only appears when it rains. In the study area, there are 2 following geotechnical stratigraphic unit of hydrogeology as follow: a. The aquifer in the cover: The composition contains water in the cover layers 1 and 2. Water is contained in the empty slot between rock particles. The source is rain water and surface water. The drainage area is the rivers, sea and the aquifers below. b. The aquifer in the bedrock: Water contains and mobilizes mainly in the fissure of the rock. The applying source is rain water, the aquifer above. Drainage areas are springs and sea. 04 water sample was taken at the borehole NH-1A, NH-5, NH-14A, TBA-2. The result of water sample analysis is as follows: HCO3- 69 Cl-23 pH 6.8 Ca2+ 58 Mg2+ 34 According to the standard TCVN 12041: 2017: Water is not corrosive. Water is used for concrete use. M 0.096 General, the underground water level is deep. Groundwater does not affect the foundation. The turbine foundations are not corrosive. 2.2.2.5. Resistivity measurement of rock and soil Resistivity was measured at 20 points at the borehole locations (12 points at WTGs, 04 points at the transmission line, 02 points at the substaion, 02 points at the yard equipment) The C.A 6470N machine of France has been used to measure under the Wenner pole system method, it is arranged in 4 symmetrical poles. Measuring distance a = 2, 4, 8, 16, 30m. Resistivity measurement of rock and soil was conducted on 12nd to 19th of October, 2020. Measurement season: Rain season. The resistivity of rock and soil is calculated by the following formula: Volume 1.1 – Chapter 2 2-19 Nhon Hoi Wind farm project – Phase I Technical Design = 2Ra (m) Where: : resistivity of rock and soil (m) a: measured distance (m) R: readings in machine () Measured results of resistivity of rock and soil see on after table: Table 2.17: Measured results of resistivity of rock and soil No. Borehole 1 NH-1A 2 NH-2A 3 NH-3A 4 NH-4A 5 NH-5A Volume 1.1 – Chapter 2 Distance a (m) 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 Read Resistivity R () 13.20 5.52 4.17 5.91 2.03 440.00 161.00 25.30 9.81 19.60 23.10 9.61 4.11 2.88 2.18 28.30 12.70 8.12 4.79 2.33 29.10 8.78 3.66 1.14 0.75 53.00 29.50 20.80 11.60 (m) 165.8 138.7 209.5 593.8 382.5 5526.4 4044.3 1271.1 985.7 3692.6 290.1 241.4 206.5 289.4 410.7 355.4 319.0 407.9 481.3 439.0 365.5 220.6 183.9 114.5 141.3 665.7 741.0 1045.0 1165.6 Season Weather Rainy season Sunny Rainy season Sunny Rainy season Sunny Rainy season Sunny Rainy season Sunny 2-20 Nhon Hoi Wind farm project – Phase I No. Borehole 6 NH-7A 7 NH-8 8 NH-9 9 NH-10 10 NH-12 11 NH-13 12 NH-14A Volume 1.1 – Chapter 2 Distance a (m) 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 Technical Design Read Resistivity R () 7.01 23.30 10.90 7.36 5.45 3.72 31.10 15.20 10.10 7.81 10.30 46.00 32.40 22.20 11.60 6.06 23.80 13.80 8.81 5.90 3.12 33.60 18.50 7.92 4.60 2.80 79.20 32.50 14.50 6.69 5.35 13.20 5.52 4.17 5.91 2.03 440.00 161.00 (m) 1320.7 292.6 273.8 369.8 547.6 700.8 390.6 381.8 507.4 784.7 1940.5 577.8 813.9 1115.3 1165.6 1141.7 298.9 346.7 442.6 592.8 587.8 422.0 464.7 397.9 462.2 527.5 994.8 816.4 728.5 672.2 1007.9 165.8 138.7 209.5 593.8 382.5 5526.4 4044.3 Season Weather Rainy season Sunny Rainy season Sunny Rainy season Sunny Rainy season Sunny Rain season Sunny Rainy season Sunny Sunny 2-21 Nhon Hoi Wind farm project – Phase I No. Borehole 13 DZ-1 14 DZ-2 15 DZ-3 16 DZ-4 17 TBA-1 18 TBA-2 Volume 1.1 – Chapter 2 Distance a (m) 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 2 4 6 Technical Design Read Resistivity R () 25.30 9.81 19.60 23.10 9.61 27.90 6.97 3.55 1.84 1.01 240.00 116.00 59.30 29.80 14.70 119.00 71.70 38.10 22.70 13.90 27.90 6.97 3.55 45.60 30.70 18.40 9.52 4.14 45.60 20.40 6.67 2.13 1.47 0.97 19.70 9.71 3.32 1.65 (m) 1271.1 985.7 3692.6 290.1 241.4 350.4 175.1 178.4 184.9 190.3 3014.4 2913.9 2979.2 2994.3 2769.5 1494.6 1801.1 1914.1 2280.9 2618.8 350.4 175.1 178.4 572.7 771.2 924.4 956.6 780.0 572.7 256.2 167.6 107.0 147.7 182.7 247.4 243.9 166.8 165.8 Season Weather Rainy season Rainy season Sunny Rainy season Sunny Rainy season Sunny Rainy season Sunny Rainy season Sunny Rainy season Sunny 2-22 Nhon Hoi Wind farm project – Phase I No. Borehole 19 TTB-1 20 TTB-2 Distance a (m) 8 16 30 2 4 6 8 16 30 2 4 6 8 16 30 Technical Design Read Resistivity R () 1.24 22.60 8.79 20.40 6.67 2.13 1.47 0.97 19.70 9.71 3.32 1.65 1.24 20.40 6.67 (m) 233.6 283.9 220.8 256.2 167.6 107.0 147.7 182.7 247.4 243.9 166.8 165.8 233.6 256.2 167.6 Season Weather Rainy season Sunny Rainy season Sunny Note: The resistivity value of rock depends on many different factors such as weather, rock composition, groundwater level... Therefore, during the construction process, it is necessary to conduct tests. check back to suit the actual conditions. 2.2.2.6. Grade of excavated rock, soil for construction Soil grade is classified basing on Vietnamese standard: TCVN 4447: 2012 - Soil work - Construction and test & acceptance and content of boulder masses mixed in the soil. The grade of excavated rock is classified according to Vietnamese standard: TCVN 11676: 2016 - Construction works - Classification of rock in construction, on the basis of uniaxial compressive strength of rock samples, fracturing grade (RQD, Modulus of joint). 73 rock samples for mechanic properties have been taken and synthesized (of which 13 samples are in layer 4, 60 samples are in layer 5). - Compressive strength of layer 4 at saturated state: 117-510kG/cm2. - Compressive strength of layer 5 at saturated state: 487-1339kG/cm2. Based on compressive strength of rock samples, combined with fracturing degree of rock mass (through the criteria RQD, Modulus of joint etc.,), table for recommendation of grades of excavated rock and soil corresponding to weathered zones has been proposed. Volume 1.1 – Chapter 2 2-23 Nhon Hoi Wind farm project – Phase I Technical Design This recommendation table is intended for orientation, serving for calculation of the excavation quantity of soil and rock in the design stage. In construction stage, it is necessary to describe geology of the foundation pit to make accuracy matching with the reality. The grades of excavated soil and rock for construction are proposed as follows: Table 2.18: Recommendations for grades of excavated soil and rock Layer Description Layer 1 Medium grain sand color is in yellowish grey, tight structured. Layer 2 Reddish brown, brownish clay loam, in hard state, mixed with gravel, block stones Layer 3 Bed rock is gray brown, soft to medium hard, with particularly strong fracture, mixed with some clay loam Layer 4 Bed rock is brownish gray, greenish gray, from medium to hard, very strong fracture Layer 5 Bed rock is greenish gray, light gray, the rock is hard to very hard, strongly cracked Rock/soil grade Percent (%) Soil grade II 100% Soil grade III 20% Soil grade IV 60% Rock grade 4 20% Soil grade IV 60% Rock grade 4 40% Rock grade 4 100% Rock grade 4 10% Rock grade 3 20% Rock grade 2 50% Rock grade 1 20% 2.2.2.7. Natural Materials Natural construction materials include soil for making the foundation, aggregates and sand used for concrete. The survey process does not include exploration and searching for borrow pits. We make recommendations. 2.2.2.7.1. Earthfill materials Within the scope of the project area, earthfill is quite rare. The soil cover layer is mixed with many blocks, boulders. However, there are many locations where the covered layer is quite thick and the excavated soil could be used to make road routines to make road base. If the demand for earthfill materials is large, it is necessary to search, explore more soil borrow areas or buy soil from available adjacent soil borrow areas. 2.2.2.7.2. Aggregates, sand materials Aggregates and sand are used as materials for concrete. It is recommended to buy fresh concrete from the available concrete plants which are nearby the project site. Volume 1.1 – Chapter 2 2-24 Nhon Hoi Wind farm project – Phase I Technical Design The detailed Geological survey results are shown in the Construction geological survey report of Nhon Hoi wind power plant project - Phase 1 & Phase 2 performed by 23 Construction and Consulting Joint Stock Company implemented in November 2020. 2.2.3. Basic meteorological characteristics Near the studied area, there is Quy Nhon meteorological station that fully monitoring factors such as precipitation, wind, ambient temperature, ambient humidity, number of rainy days, sunshine days, etc. The monitored data series at Quy Nhon meteorological station used in the project is managed and measured by Vietnam Meteorological and Hydrological Administration, with good quality, reliable assurance for the calculation of design meteorological characteristics. Meteorological characteristics of the Nhon Hoi Wind Power Plant (WPP) project are calculated by statistical method according to actual recorded data of Quy Nhon meteorological station from 1976 to 2018. Particularly, rain characteristics (precipitation, number of rainy days and intensity of rainfall) are taken according to synthesized data of rainfall gauging stations in the basin. In addition, data from the following standards, regulations and norms are also adopted in the report: - QCVN 02:2009/BXD: National technical regulation on data of Natural Physical and Climatic Data for Construction, issued under Circular No. 29/2009/TTBXD dated August 14, 2009. - QP.TL. C-6-77:Norm on calculation of designed hydrological characteristics. - Hydro-meteorology Atlas of Vietnam. 2.2.3.1. Ambient temperature at the project area This is the area with relatively high ambient temperature, the annual average value of about 27.10C, the maximum ambient temperature measured at Quy Nhon Meteorological Station was 40.70C (May 4, 1994), the lowest value measured at this station is 13.00C (October 27, 1995). There is not much difference in heat regime amongvarious months. The average temperature difference value between the lowest month and the highest month is about 6,70C. The characteristics of the average, maximum and minimum ambient temperature at Quy Nhon station are presented in the table below. Please refer to appendices for more details. Volume 1.1 – Chapter 2 2-25 Nhon Hoi Wind farm project – Phase I Technical Design Table 2.19: Characteristics of ambient temperature at Quy Nhon meteor station Characteristics Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Annual mean TmeanoC 23.4 24.1 25.7 27.7 29.3 30.1 30.1 30.0 28.7 27.0 25.6 24.0 27.1 TmaxoC 33.3 34.9 34.9 38.1 40.7 39.9 39.6 39.0 38.8 36.6 33.7 32.9 40.7 TminoC 16.6 16.8 15.8 21.3 23.0 22.7 23.1 22.8 22.6 13.0 19.0 15.5 13.0 Figure 2.6: Temperature variation progress at Quy Nhon station 2.2.3.2. Ambient humidity The relative humidity in the project area according to Quy Nhon meteorological station ranges from 70.6% to 83.3%, with the annual average value of 79%. From June to September, the relative humidity of the ambient is low. The relative humidity of the ambient increased in the rainy season’ months. The lowest ambient relative humidity also varies as the average value does. The annual variation of the relative humidity is similar to that of precipitation. During the rainy season (from October to December), humidity in months varied from 81% -83.3%, the highest values in October and November are 82.3%-83.3%. During dry season, the monthly humidity varied from 70% -77.7%. At the end of the rainy season, humidity decreases continuously and reaches the minimum value in July and August and then gradually increases until October. Characteristics of average and minimum ambient humidity recorded at Quy Nhon station are presented in the table below. Please refer to appendices for more details. Volume 1.1 – Chapter 2 2-26 Nhon Hoi Wind farm project – Phase I Technical Design Table 2.20: Characteristics of ambient humidity at Quy Nhon meteor station Month/characteristics Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Year Ubp % 81.0 81.4 82.5 82.1 78.9 73.0 71.5 70.6 77.7 82.3 83.3 81.8 78.8 Umin % 42.0 36.0 45.0 45.0 34.0 33.0 34.0 37.0 39.0 46.0 46.0 38.0 33.0 2.2.3.3. Ambient pressure The annual average value of ambient pressure reaches 1010 mbar. In general, the mean value as well as the maximum and minimum values among months are slightly different with minor amplitude of variation. The ambient pressure characteristics of Quy Nhon meteorological station are given in the table below. Table 2.21: Ambient pressure at Quy Nhon meteor station Characteristic Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Annual mean Mean 1015 1012 1012 1009 1007 1004 1005 1005 1006 1010 1011 1014 1009 Max 1004 1003 1003 1001 997 994 997 993 984 995 991 1005 984 Min 1023 1022 1026 1018 1014 1012 1012 1013 1015 1018 1021 1021 1026 2.2.3.4. Wind In winter monsoon period, Binh Dinh province is influenced by the eastern Trade Wind with the prevailing air mass of the Tropical Marine. This air mass affects Binh Dinh and normally moves from the Southern edge of the Pacific subtropical high pressure or the sea region at the Eastern of China, while from the latitude 16 onward, the desaturated tropical polar air mass becomes prevailing in this period. However, whenever the Asian Continental High Pressure strongly operates and spreads to the Southward, over the mainland of China or across the Japanese ocean, the Yellow Sea and the Eastern China Sea to our country, then the tropical marine air mass is often interrupted. The polar air mass can reach Binh Dinh along the eastern side of the Truong Son range or in the direction of East off-course across the ocean, but when it affects Binh Dinh, it has changed its original properties a lot compared with that of original characteristics. 2.2.3.4.1. Wind direction The project area is located close to Quy Nhon meteorological station, so this station should be used as the basis to determine the annually wind direction in the area. According to wind monitoring data at Quy Nhon station, the most appearing is North direction, then NW direction. The frequency of occurrence of wind directions in the year is shown in the following table, wind rose of months and combined with wind rose are given in the appendix. Volume 1.1 – Chapter 2 2-27 Nhon Hoi Wind farm project – Phase I Technical Design Table 2.22: Frequency of wind occurrence at 8 directions in a year at Quy Nhon meteor station Wind direction N NE E SE S SW W NW Windless Frequency % 26.6 11.3 3.4 19.3 7.2 1.6 9.1 21.6 27.6 Like the whole year, wind directions in the rainy season’ months (September – December) of the region that appear mostly are still the North and NW. The occurrence frequency of wind directions in months of rainy season is stated in the table below. Table 2.23: Frequency of wind occurrence at 8 directions at months of rainy season (from September to December) - Quy Nhon meteor station Wind direction N NE E SE S SW W NW Windless Frequency % 36.8 17.0 3.0 7.3 2.6 0.9 5.6 26.8 21.6 Unlike the rainy season, wind directions in the dry season’ months (January – August) of the region that appear mostly are the Southeast and North directions. The occurrence frequency of wind directions in months of the dry season is provided in the table below. Table 2.24: Frequency of wind occurrence at 8 directions at months of dry season (from Jan – August) - Quy Nhon meteor station Wind direction N NE E SE S SW W NW Windless Frequency % 21.5 8.4 3.6 25.2 9.5 1.9 10.9 19.0 30.6 Thus, it can be said that the wind regime in Binh Dinh shows two distinct seasons clearly. The North wind direction prevails in Winter. The North and NW wind directions prevail in summer. Wind roses illustrating wind direction in months of the year and summarized wind rose for the whole year. N N 50.00 NW 40.00 January 40.00 NW NE 30.00 30.00 N Feb 30.00 NE NW 20.00 20.00 10.00 10.00 E 0.00 W 5.00 E 0.00 SW SW SE SE S S Volume 1.1 – Chapter 2 March NE 20.00 15.00 10.00 W 25.00 W E 0.00 SW SE S 2-28 Nhon Hoi Wind farm project – Phase I Technical Design N N April NE 40.00 NW NW 30.00 20.00 20.00 W E NE 5.00 E SW W SW SE S N 30.00 N July 30.00 25.00 25.00 NW NE 20.00 15.00 10.00 10.00 5.00 5.00 W E 0.00 SW N August 25.00 NW NE 20.00 5.00 E W Octorber SE SW SE NW 30.00 S N November N 50.00 NE 20.00 40.00 50.00 NW NE W 40.00 30.00 30.00 20.00 20.00 December NE 10.00 10.00 10.00 E 0.00 S 40.00 NE 10.00 SW S Sept. 15.00 0.00 SE N S 20.00 15.00 E 0.00 SE S W June 20.00 15.00 0.00 SE NW NW 10.00 SW W 25.00 10.00 0.00 NW 30.00 May NE 40.00 30.00 10.00 W N 50.00 50.00 W E 0.00 E 0.00 E 0.00 SW SW SE SW SE S S S N NW W SE 30.00 25.00 20.00 15.00 10.00 5.00 0.00 Year NE E SW SE S Figure 2.7: Wind rose of months and year in Quy Nhon station 2.2.3.4.2. Wind velocity a. Average wind velocity In Binh Dinh province in general and Quy Nhon station in particular, the annual average wind velocity is quite small, from 1.5-1.8m/s, the monthly average value ranges Volume 1.1 – Chapter 2 2-29 Nhon Hoi Wind farm project – Phase I Technical Design from 1.44-2.5m/s. The month with the highest and lowest average wind velocity are 2.5m/s and 1.44m/s, respectively. In the coastal area, the average wind velocity in the winter monsoon period is higher than that in the summer monsoon period and reaches the highest value. Below is the average wind velocity table recorded at the Quy Nhon meteorological station which is close to the project area. Table 2.25: Average wind speed of months in a year at Quy Nhon meteor station Unit: m/s Features /month Vtb Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Annual mean 2.50 1.83 1.93 1.79 1.44 1.67 1.61 1.64 1.29 1.85 2.40 2.49 1.87 The monthly average wind velocity is shown in Table 2.7, reflecting only the most relative average of wind strength in the region. Therefore, if it only cares at the monthly average wind velocity, the usage of these data for calculating and evaluating the wind potential as well as the harm in order to exploit smoothly and limit negative impacts will face with many difficulties. More descriptions such as frequency of each wind grade, wind velocity and prevailing direction shall be discussed. Wind velocity in Quy Nhon from April to September from 0 to 1m/s usually accounts for the highest frequency. From October to March, the velocity is higher than 2-5m/s, reaching the highest frequency in the year, accounting for 52-72%. Below is a table of average wind velocity frequencies and grades recorded at Quy Nhon meteorological station. Table 2.26:Frequency of average wind speed levels at Quy Nhon meteor station Unit: % Speed/month 0-1 (m/s) >1-5 (m/s) Jan 34.0 63.7 2.3 Feb 43.7 54.6 1.6 Mar 45.5 53.2 1.3 Apr 50.5 49.1 0.4 May 65.1 34.7 0.2 Jun 57.1 40.8 2.0 Jul 51.8 47.6 0.6 Aug 51.6 47.0 1.3 0.1 Sept. 65.5 34.0 0.4 0.1 Oct. 44.8 51.8 3.3 Nov. 22.8 69.6 7.3 Volume 1.1 – Chapter 2 >5-10 (m/s) >10-15 (m/s) >15 (m/s) 0.1 0.1 0.2 2-30 Nhon Hoi Wind farm project – Phase I Technical Design Speed/month 0-1 (m/s) >1-5 (m/s) XII 21.3 72.2 >5-10 (m/s) >10-15 (m/s) >15 (m/s) 6.2 0.2 Wind velocity from higher than 5 to 10m/s accounts for only 0.2-7.3%. In the winter monsoon period, where the leeward is recorded, the wind velocity from higher than 5 m/s to 10m/s only reaches the frequency of 0.1-5%. The velocity of over 10m/s rarely happens with very low frequency, not more than 1% and usually occurs in strong monsoons, or occurs with dangerous weather phenomena such as storms, whirlwind turbulence, tropical depressions. b. Maximum wind velocity According to data recorded from 1976 to 2019, the strongest wind velocity in Quy Nhon measured was 40m/s (grade 14), but according to available data, there was a strong wind of 59m/s in September 1972. Strong winds usually occur during thunderstorms, the influence of storms, tropical depressions, strong northeast or Southwest monsoons, but generally the strongest wind velocity occurs in case of direct-influenced strong storms. Below is a table of the monthly maximum wind velocity in a year at Quy Nhon meteorological station. Table 2.27: Maximum wind speed of months in a year at Quy Nhon meteor station Unit: m/s Features /month Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Annual mean Vmax 15.0 15.0 15.0 14.0 20.0 28.0 40.0 20.0 20.0 40.0 40.0 24.0 40.0 To determine the maximum wind velocity in 8 directions and non-direction corresponding to frequencies, data from 1976 to 2019 are collected for calculation. The results are shown in the table below: Table 2.28: Maximum wind speed correspond to frequencies at 8 directions and non-direction at Quy Nhon meteor station Unit: m/s P%/direction N NE E SE S SW W NW Nondirection 1 44.1 44.0 39.2 35.8 27.8 19.9 42.0 44.5 51.8 2 36.9 37.0 32.6 30.5 23.7 18.4 35.3 37.5 44.5 3 31.8 32.2 28.1 26.9 20.9 17.6 30.8 32.6 39.8 4 29.8 30.2 26.2 25.4 19.7 16.7 28.9 30.5 37.3 5 27.0 27.5 23.7 23.5 18.1 16.2 26.4 27.9 34.5 Volume 1.1 – Chapter 2 2-31 Nhon Hoi Wind farm project – Phase I Technical Design 10 21.4 22.1 18.7 19.3 14.9 14.5 21.2 22.4 28.4 20 16.4 17.1 14.2 15.5 11.7 12.8 16.5 17.4 22.4 25 15.0 15.6 12.9 14.3 10.8 12.1 15.1 15.9 20.5 50 10.3 11.0 8.8 10.5 7.8 9.8 10.7 11.2 14.6 2.2.3.4.3. Wind pressure According to the National technical regulation on data of Natural Physical and Climatic Data for Construction, QCVN 02:2009/BXD and Vietnamese electrical code 11 TCN-19-2006, the wind pressure applied to the project area is as follows: Table 2.29: Standard wind pressure with repeated cycle of wind 1 time in 10 years and 1 time in 20 years District, city Quy Nhơn Region Wo (kN/m2) Wo (kN/m2) Pressure 3 seconds, 10 years 3 seconds, 20 years III,B 1.09 1.25 2.2.3.4.4. Land wind and sea wind Another basic feature of the wind regime in a coastal area like Binh Dinh province is that, in addition to the change in wind direction over seasons according to annual cycle, there also appears a type of wind alternating with the night and day cycle, it is the land wind and sea wind. The primary cause of this wind is the heterogeneity in the heat absorption and emission of the buffer surface. During the daytime, the ground absorbs solar radiation stronger than the ocean surface, so the ground is heated up faster and the air above the ground rises, the pressure decreases and a barometric gradient appears from the sea. towards the mainland, producing the wind blowing from the ocean to the mainland. At night time, the above process is reversed, the ground emits heat strongly and cools faster than the ocean surface, there appears a barometric gradient from the mainland to the ocean, so wind blows from the mainland to the sea. The sea wind blowing to the mainland occurs after sunrise, gradually stronger and reaches its peak at over noon time. At the sunset, the sea wind becomes weaker and it is gradually replaced by the land wind (the wind blowing from the mainland to the sea). The land wind maintains throughout the night and gets its maximum level in the early morning until sunrise. After that, it becomes weak and is replaced by the sea wind. The range of the sea wind blowing to the mainland in mountainous areas like Binh Dinh is about 10-20km, while the land wind blowing to the ocean is about 20-30km and its thickness is usually less than 1.5km. The sea wind- land wind is clearly found during periods of relatively weak monsoon circulation and a less cloudy sky. In the case of the strong monsoon circulation, Volume 1.1 – Chapter 2 2-32 Nhon Hoi Wind farm project – Phase I Technical Design either the land wind or sea wind will be overwhelmed. At that time, the land wind and sea wind only play the role of increasing or decreasing the direction and velocity of monsoon wind. Land wind – sea wind partly contributes to climate regulation in coastal areas. For example, in summer during the daytime, the hot weather is relieved by the sea wind that brings cooler and moist air. On the other hand, the sea wind blows to the mainland due to friction, so the wind velocity is reduced. According to the law of conservation, this area is easy to form turbulent flow, sometimes combined with favorable thermodynamic conditions, sea wind also can create precipitation in the form of showers. 2.2.3.5. Precipitation Precipitation distribution in Binh Dinh is extremely uneven. The mountainous region of Vinh Son and the northern mountainous region of the province are the two regions with the highest precipitation in the province, with the total annual average precipitation from 2200 to 3200mm, of which the highest precipitation center is in An Lao mountainous district. The second heavy rain area is Vinh Kim mountain area in the middle of Kon river, Van Canh district, upstream of Ha Thanh river and the northern coastal districts of 2000 ÷ 2200mm. The remaining areas such as the Southern coastal area of the province, Tay Son district, the East of Vinh Thanh mountainous district and the downstream basin of Kon river, the annual average precipitation is 1600 ÷ 1900mm, of which the lowest precipitation is in Tan An and communes in the East of Tuy Phuoc district with annual precipitation more or less of 1600mm. The rainy season in this area lasts only 4 months, from September to December, the maximum precipitation is in October. The dry season is from January to August. In the 4 months of the rainy season, precipitation accounts for about 70-78% of the annual precipitation. The dry season is quite long but only accounts for 22-30% of the annual precipitation. The number of rainy days in a year is about 120-140 days. The distribution of precipitation and average number of rainy days in many years recorded by stations near the project area are given in the table below: Table 2.30: Precipitation and number of rainy days at Quy Nhon and Phu Cat stations Month Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Year Quy Nhơn station Rainfall volume (mm) 70.2 25.6 30.5 30.2 90.3 65.7 45.2 80.3 239.1 522.0 488.6 203.6 1891 Number of 13 rainy days 6 Volume 1.1 – Chapter 2 5 4 9 7 7 10 16 21 21 19 138 2-33 Nhon Hoi Wind farm project – Phase I Month Technical Design Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Year Phù Cát station L Rainfall volume 48.4 16.7 28.7 39.0 96.3 75.1 63.7 91.8 224.4 557.5 512.5 162.6 1917 (mm) Number of rainy days 4 1 2 3 5 5 4 5 11 15 15 11 79 As shown in the table above, the precipitation is distributed in the studied area in months as follows: From January to April, the period between the Northeast monsoon to the transition period of two monsoons, is a stable period and has the lowest precipitation in a year. The average precipitation in the months is from 17-70mm. However, there is also an unusual year, for example, January 2008, 2019 due to the influence of strong cold air, the whole province had moderate rain to heavy rain, some places with extreme heavy rain, total precipitation in January 2008 at Phu Cat station reached 183.7mm; Quy Nhon station reached 258.3mm. In January 2019, Quy Nhon station had precipitation of 303.8mm. From May to June, the Southwest monsoon begins to take its effect, the lower equatorial strip elevates the north axis to operate in the South and South Central, making the precipitation increase steadily. The monthly average precipitation ranges from 66–96 mm in coastal areas, this is the period of Xiaoman (premature or minor) precipitation in Binh Dinh. In July and August, the precipitation slightly decreases compared to the previous two months, with the total monthly average precipitation from 45 to 92mm. In the middle of September, the Northeast monsoon affects the South, combined with the activity of tropical convergence band as well as disturbances such as storms, tropical depressions, the rainy season officially begins. Precipitation in the beginning and ending months of the rainy season (September and December) is 160-557mm on average. In October and November, the 2 months in the middle of the rainy season, average precipitation is from 488 – nearly 600mm and is the two main rainy months of the year. Below is the plot of the average precipitation variation in months of the year at Quy Nhon and Phu Cat stations. From the series of annual precipitation data from 1976 to 2019 at Quy Nhon Meteorological Station and the series from 1976 to 2017 at Phu Cat rain gauging station, the annual precipitation calculation corresponds to the frequencies as table below: Volume 1.1 – Chapter 2 2-34 Nhon Hoi Wind farm project – Phase I Technical Design Table 2.31: Rainfall volume corresponding to frequencies at Quy Nhon and Phu Cat stations Unit: mm Station/month Xtb Cv Cs Rainfall corresponds to frequencies p% 1 5 10 20 25 50 75 85 90 95 Quy Nhơn 1981 0.25 0.5 3164 2731 2517 2273 2184 1851 1553 1407 1314 1183 Phù cát 1917 0.3 0.59 3502 2949 2679 2374 2265 1858 1501 1330 1221 1071 Please refer to the appendices for the results of annual precipitation frequency curve. Figure 2.8: Rainfall variation progress at Quy Nhon station Volume 1.1 – Chapter 2 2-35 Nhon Hoi Wind farm project – Phase I Technical Design Figure 2.9: Rainfall variation progress of months in a year at Phu Cat station To serve the calculation of water drainage and design floods for the project, rainy value is usually taken with a daily period (24 hours). Below is the statistics of the maximum daily precipitation at the two stations, Quy Nhon and Phu Cat. Table 2.32: Maximum daily precipitation at Quy Nhơn and Phù Cát stations Unit: mm Năm Xmax_Quy Xmax_Phù Nhơn Cát Năm Xmax_Quy Xmax_Phù Nhơn Cát 1976 95.8 143.7 1998 224.4 211.2 1977 127.4 205.5 1999 169.1 264.9 1978 150.7 200.4 2000 93.6 92 1979 217.4 165.2 2001 106.7 107.8 1980 136.4 153.2 2002 127.7 186 1981 293.2 257.9 2003 174.3 198.5 1982 180.9 58.5 2004 288.2 130.1 1983 150.2 232 2005 153.4 238 1984 232.3 188.7 2006 139.5 84.9 1985 206.9 325 2007 193.8 154.8 Volume 1.1 – Chapter 2 2-36 Nhon Hoi Wind farm project – Phase I Năm Technical Design Xmax_Quy Xmax_Phù Nhơn Cát Xmax_Quy Xmax_Phù Nhơn Cát Năm 1986 164.5 154 2008 209.5 127.7 1987 231.7 213 2009 231.9 297.6 1988 337.8 239 2010 256.7 228.6 1989 76 98 2011 129.4 157.7 1990 234.5 191.2 2012 107.9 72.2 1991 274.1 137 2013 143.9 1992 208.2 275 2014 142.2 1993 327.4 185 2015 114.5 1994 82.4 75 2016 191.1 1995 136.6 130 2017 238.8 1996 151 390 2018 153.2 1997 181.7 161.5 2019 151.3 198.4 The highest precipitation recorded at Quy Nhon and Phu Cat are shown in the table below: Table 2.33: Maximum rainfall volume at Quy Nhơn and Phù Cát stations Unit: mm Station Rainfall volume in 1 Rainfall volume in 1 Rainfall volume in 1 day month year Rainfall Rainfall Rainfall Occurrence Occurrence Occurrence volume volume volume Quy Nhơn 337.8 15-X-1988 1511.2 XI-2010 2990 1998 Phù Cát 390 17-XI-1996 1352.9 XI-1996 3176 1996 From the series of maximum daily precipitation data at Quy Nhon Meteorological Station and Phu Cat rain gauging station, the designed daily precipitation with frequencies in the below table is calculated: Table 2.34: Maximum daily precipitation corresponding to frequencies at Quy Nhơn and Phù Cát stations Unit: mm station/month Xmaxtb Cv Cs Rainfall volume corresponding to frequencies p% 0.1 0.2 0.3 0.5 1 3 5 10 20 50 Quy Nhơn 180.4 0.416 4.5Cv 640 576 535 493 438 355 320 274 228 165 Phù cát 182.3 0.46 4.0Cv 700 628 583 532 474 379 339 286 235 164 Volume 1.1 – Chapter 2 2-37 Nhon Hoi Wind farm project – Phase I Technical Design Table 2.35: Maximum rainfall volume at design period Unit: mm Frequency P(%) Period 1 2 4 5 10 20 50 15 minutes 48.1 45.5 41.2 39.6 35.9 31.9 25.1 30 minutes 84.7 77.7 67.9 65.2 57.1 49.8 38.2 60 minutes 122 112 98.2 94.2 83.2 72.2 57.0 120 minutes 157 146 130 124 110 96.0 73.6 1440 minutes 450 416 367 351 306 261 190 (According to the data of the report on hydro-meteorological investigation at FS stage of Nhon Hoi 1 Wind Power plant prepared by Power Engineering Consulting Joint Stock Company 4) 2.2.3.6. Evaporation The total Piche possible evaporation volume in Binh Dinh is relatively stable, the total possible annual amount of evaporation is likely to reach 789 ÷ 1317mm, unevenly distributed in months. Evaporation variation progress are contrary to the rain variation progress. In the dry season, the evaporation is significant and vice versa. According to data recorded at Quy Nhon meteorological station, the monthly average evaporation reaches 73 ÷ 150mm from January to August, the total monthly average evaporation reaches 74 ÷ 100mm from September to December. The annual average evaporation volume at Quy Nhon station is as follows: Table 2.36: Annual average evaporation volume at Quy Nhon meteor station Unit: mm Month Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Year Zpiche 81.7 73.1 79.6 77.8 93.0 127.2 144.8 150.1 99.6 78.6 73.8 78.4 1158 2.2.3.7. Sunshine As located at low latitudes, with a long daytime length around all year, and a very long time dry season with 5-6 months of clear sky, Binh Dinh is also one among provinces having many sunny times. Total mean annual sunny hours ranges from 2,350 to 2,500 hours. During 6 months from March to August, the average number of sunshine hours per month ranges from 240-250 hours, with an average of 8 hours per day. April and May are the two months with the highest sunshine time, with an average of 250-270 hours per month. The months with low sunshine hours are those in rainy season; the average number of sunshine hours every month is also about 100-200 hours, with an average of 5-6 hours per day. December, the month that has the lowest sunshine hours has an Volume 1.1 – Chapter 2 2-38 Nhon Hoi Wind farm project – Phase I Technical Design average of 100-115 hours of sunshine. Thus, the number of sunshine hours of the lowest sunshine month is only approximately half of the number of sunshine hours of the highest sunshine month. This difference in sunshine hours also clearly reflects the contrast between the two seasons: dry season and wet rainy season. The number of sunshine hours at Quy Nhon Meteorological Station is 2455 hours per year in average. The month with the highest sunshine hours in the year is May with 272 hours, the month with the lowest sunshine hours is December with 109 hours. The number of sunshine hours in the dry season is higher than that in the rainy season, 160269 hours in average, 7-9 sunshine hours per day. Months in the rainy season have 110193 hours of sunshine, 5-6 hours sunshine hours per day. The average number of sunshine hours in many years recorded at Quy Nhon station is measured as below: Table 2.37: The average number of sunshine hours in many years recorded at Quy Nhon meteor station Unit: hour Month Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Year Average 153 193 242 264 272 245 248 233 199 168 128 109 2455 The maximum number of sunshine hours observed at Quy Nhon station reaches 12.5 hours/day 2.2.3.8. Special weather phenomena 2.2.3.8.1. Thunderstorm Thunderstorms start from March and end in November, mainly from May to October. According to observed data in Binh Dinh province, the Southern delta of the province has 30-52 thunderstorm days in average; while in the mountains, valleys and the North of the province, the number of thunderstorm day is more than 70 days. Although the time of thunderstorms is not long, the intensity of rain is heavy, sometimes thunderstorms develop violently, causing tornadoes and lightning, resulting to house fires, trees and electric poles falling down and human damage. Table 2.38: Number of days having thunderstorms in average month and year at Quy Nhon meteor station Unit: day Month Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Year Average 0.05 0.00 0.30 1.95 6.32 4.32 3.91 4.00 7.59 4.57 0.91 0.07 33.98 Volume 1.1 – Chapter 2 2-39 Nhon Hoi Wind farm project – Phase I Technical Design Table 2.39: Number of days having biggest thunderstorms in months and year at Quy Nhon meteor station Unit: day Month Jan Feb. Mar. Ap. May Jun. Jul Au. Sept Oct Nov Dec Average 11 12 2 0 5 9 16 12 18 17 7 2 Lightning density at the project area: 8.2 times/km2/year. 2.2.3.8.2. Fog Fog usually occurs in winter. Highland has more fog than lowland. In Quy Nhon, there is very little fog, mainly radiation fog that appearing in the first months in the dry season. The number of foggy days is only about 1-2 days. 2.2.3.8.3. Storms and tropical depressions Especially in the Central provinces in general and Binh Dinh in particular, the storm season occurs coincide with the operating period of the winter monsoon and the tropical convergence band following the natural climate cycle also operates at this latitude. Therefore, the combination of effects among storms, tropical depression and other weather patterns such as cold air, tropical convergence band or tropical disturbances are the cause of heavy rain and big floods. In Binh Dinh area, the real storm season starts from September to December. In average, there are 1-2 storms or tropical depressions annually affecting Binh Dinh. Storms and tropical depressions mostly occur in October and November. Due to unusual changes in weather, unseasonal storms and tropical depressions occur in some years which may affect the area from very early time in June (Storm No. 2 on June 12, 2004, Storm No. 2 on June 30, 1978 all landed in Binh Dinh). These storms and tropical depressions often damage people and properties of the State and of the local people. According to documents before 1975, the strongest storm velocity in Quy Nhon was 59.0 m/s in 1972. In Binh Dinh, it was not a storm that directly hit the province that caused extreme weather phenomena, but many storms and tropical depressions landed in the neighboring provinces also caused dangerous weather. For example, the storm No. 10 (Kyle) on November 23, 1993 landed in Tuy Hoa, the strongest wind velocity was measured at Qui Nhon 34m/s, An Nhon 40m/s and the whole province of Binh Dinh had heavy rain to extremely heavy rain. Or the storm No. 7 on October 8, 1988 that hit the mainland of Quang Ngai also caused heavy rain to extremely heavy rain in the whole province. Storms and tropical depressions hitting Binh Dinh most were in the 1984, 1988, 1990, 1992, 1995 but all of them did not exceed 2 storms and there were also no storms or tropical depressions landed such as 1976, 1981, 1982, 1989, 1991, 1994, 1997, 2000, 2002, 2003. Considering the influence of storms and tropical depressions, 1990 has the Volume 1.1 – Chapter 2 2-40 Nhon Hoi Wind farm project – Phase I Technical Design most storms, up to 4 storms. In addition, there are two storms landed in the same province, 5-12 days apart from each other, causing great damage to people and properties of the State and people in 1984, 1992, 1995. Below is a statistic table of storms hitting Binh Dinh and Ninh Thuan provinces. Table 2.40: Statistic results of storms hitting Binh Dinh-Ninh Thuan area during the period of 1964 to 2017 Coastal area Time of occurrence Storm names Storm grade Binh Dinh - Ninh Thuan 11/6/1964 JOAN (No.14) Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 11/12/1964 KATE (No. 15) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 11/7/1967 FREDA (No. 10) Grade 9 (75-88 km/h) Binh Dinh - Ninh Thuan 11/15/1968 MAMIE (No. 9) Grade 10 (89-102 km/h) Binh Dinh - Ninh Thuan 10/18/1970 KATE (No. 5) Grade 9 (75-88 km/h) Binh Dinh - Ninh Thuan 10/26/1970 LOUISE (No. 6) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 4/23/1971 WANDA (No. 1) Grade 9 (75-88 km/h) Binh Dinh - Ninh Thuan 12/4/1972 THERESE (No. 10) Grade 10 (89-102 km/h) Binh Dinh - Ninh Thuan 10/4/1973 OPAL (No. 10) Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 11/9/1973 SARAH (No. 13) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 11/13/1974 HESTER (No. 14) Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 11/2/1975 HELLEN (No. 7) Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 6/28/1978 SHIRLEY (No. 2) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 10/31/1978 NONAME (No. 10) Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 10/4/1979 SARAH (No. 8) Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 10/29/1980 CARY (No. 7) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 10/12/1981 FABIAN (No. 7) Grade 9 (75-88 km/h) Binh Dinh - Ninh Thuan 3/17/1982 MAMIE (No. 1) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 10/6/1983 HERBERT (No.8) Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 10/15/1983 KIM (No.10) Grade 9 (75-88 km/h) Binh Dinh - Ninh Thuan 10/11/1984 SUSAN (No.8) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 10/23/1984 WARREN (No.9) Grade 7 (50-61 km/h) Volume 1.1 – Chapter 2 2-41 Nhon Hoi Wind farm project – Phase I Coastal area Time of occurrence Technical Design Storm names Storm grade Binh Dinh - Ninh Thuan 11/20/1985 GORDON (No.11) Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 11/6/1986 HERBERT (No.9) Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 11/14/1987 MAURY (No.6) Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 10/7/1988 NONAME (No.7) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 10/1/1990 IRA (No.7) Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 10/16/1990 LOLA (No.8) Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 11/10/1990 NELL (No.3) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 10/15/1992 ANGELA (No.6) Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 10/18/1992 COLLEEN (No.7) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 11/19/1993 KYLE (No.10) Grade 13 (>133 km/h) Binh Dinh - Ninh Thuan 12/2/1993 LOLA (No.11) Grade 10 (89-102 km/h) Binh Dinh - Ninh Thuan 10/17/1994 TERRESA (No.9) Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 10/24/1995 YVETTE (No.10) Grade 10 (89-102 km/h) Binh Dinh - Ninh Thuan 11/1/1996 Tropical depression Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 11/17/1998 DAWN (No.5) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 11/23/1998 ELVIS (No.6) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 12/9/1998 FAITH (No.8) Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 11/4/1999 Tropical depression Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 12/14/1999 NONAME (No.10) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 11/7/2001 LINGLING (No.8) Grade 11 (103-117km/h) Binh Dinh - Ninh Thuan 6/9/2004 CHANTHU (No.2) Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 9/11/2005 Tropical depression Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 10/26/2006 Cimaron Grade 13 (>133 km/h) Binh Dinh - Ninh Thuan 8/2/2007 Tropical depression Grade 8 (62-74 km/h) Binh Dinh - Ninh Thuan 10/29/2007 Tropical depression Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 11/22/2007 Hagibis Grade 12 (118-133 km/h) Binh Dinh - Ninh Thuan 11/11/2008 Tropical depression Grade 6 (39-49 km/h) Volume 1.1 – Chapter 2 2-42 Nhon Hoi Wind farm project – Phase I Coastal area Time of occurrence Technical Design Storm names Storm grade Binh Dinh - Ninh Thuan 11/15/2008 Noul Grade 7 (50-61 km/h) Binh Dinh - Ninh Thuan 9/3/2009 Tropical depression Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 10/25/2009 MARINAE Grade 6 (39-49 km/h) Binh Dinh - Ninh Thuan 7/18/2010 Chan Thu Grade 7 (50-61 km/h) Binh Dinh - Phu Yen 10/2012 GAEMI Grade 6 (39-49 km/h) Da Nang - Quang Nam 10/2013 NARI Grade 10 (89-117 km/h) Khanh Hoa-Ninh Thuan 11/2013 PODUL Grade 8 (62-74 km/h) Binh Dinh - Phu Yen 11/2014 SINLAKU Grade 9 (75-88 km/h) Quang Nam-Quang Ngai 9/2015 Vamco Grade 8 (62-74 km/h) Quang Nam-Quang Ngai 9/2016 Rai Grade 8 (62-74 km/h) Quang Tri-Thua Thien Hue 10/2016 Tropical depression Grade 6 (39-49 km/h) Phu Yen - Khanh Hoa 11/2017 Damrey Grade 9 (75-88 km/h) Ninh Thuan-Binh Thuan 11/2017 Kirogi Grade 6 (39-49 km/h) Toraji (No. 8) Cấp 8 (62-74 km/h) Matmo (No. 5) Grade 9 (75-88 km/h) Ninh Thuan-Binh Thuan 17-18/11/2018 Binh Dinh-Phu Yen 28-30/10/2019 Phu Yen - Khanh Hoa 5-10/11/2019 Tropical depression Grade 6 (39-49 km/h) 2.2.3.8.4. Dry and hot western wind The main source of the dry and hot west wind in Binh Dinh is during the Southwest monsoon period with the nature of the hot and moist air flowing from Bengan Bay through the vast continent to Vietnam was blocked by the Truong Son range. As it crosses the mountain range, the air mass leaves most of the moisture in the form of rain on the West slope, then continues to slide down the eastern slope toward valleys and coastal plains. By this time, the air mass becomes hotter and drier than the original nature, which is often called the hot and dry west wind. The property of dry and hot west wind weather is absolute daily maximum temperature ≥ 350C, combined with the daily minimum relative humidity ≤ 50%. Every year in Binh Dinh at the later weeks of April, hot and dry west wind appears in the low valleys of the province. In the middle and end of May, it appears in most of the rest of the province. However, dry and hot weather may appear so early in some years in the middle of March in the North of the province and at the later weeks of April Volume 1.1 – Chapter 2 2-43 Nhon Hoi Wind farm project – Phase I Technical Design in the South of the province, but it is not the Southwest monsoon mentioned above, but the southern circulation of the South China continent's depression suffered from the puffeffect of the Truong Son range. Usually this is the prerequisite for the Southward invasion of the cold air wave. The end date of this pattern of weather is also quite different from year to year, normally in the later weeks of August in the North and the coastal plain and early weeks of September in the South of the province. There was no more dry and hot west wind phenomenon from the middle of August in some years but in some other years dry and hot west wind phenomenon lasted until early October (October 1st, 1976). The dry and hot west wind does not happen continuously but is interrupted in many times. From May to August, each month has 2 hot and dry west winds in average. The month that has the most dry and hot west wind is 4-5 winds. Most of the dry and hot west winds last for 2-3 days, accounting for 60%, 4-6 days accounting for about 2025%, the rest are those lasting for more than 6 days. From July to August, dry and hot west wind phenomenon may last 10-15 days. The hot and dry west wind may last over half of a month in year (in Quy Nhon, one time of 16 days in July, 1963; and 1 time of 25 days in August, 1982). Hot and dry west wind days in Binh Dinh have the daily average temperatures of 27-300C, average wind velocity of 2-8m/s (Grade 2 to Grade 4). 2.2.3.8.5. Northeast monsoon Every year, Binh Dinh, like the central provinces, is influenced by Northeast monsoon. The first period is around October, November or until December in some years, at this time the monsoon brings dry weather for the northern provinces, but the moving process towards the South causes wet weather in the Central coastal provinces. The later period,about from January to April or sometimes until May in some years, the Northeast monsoon only brings a little and irregular precipitation and causes dry weather pattern for the Central region in general and Binh Dinh in particular. Weather characteristics under the effect of the Northeast monsoon is cloudy usually resulted in precipitation, the wind direction changes North and getting stronger to Grade 3, Grade 4, breeze Grade 5, 6 or above Grade 6 in coastal areas; in particular, there are strong winds of Grade 6, Grade 7, above Grade 7 in offshore area. In the early winter months, the Northeast monsoon arrives, sometimes combined with other weather system leading to heavy to extremely heavy rain, causing floods. In the last months of winter, the impact of Northeast monsoon often causes thunderstorms, sometimes accompanied by cyclones. In addition, in February and March, the Northeast monsoon comes, the daily average temperature may drops below 200C and lasts for a few days. The Northeast monsoon during the process of moving to the South has been altered its characteristics quite a lot, so when it affects Binh Dinh, the Northeast monsoon Volume 1.1 – Chapter 2 2-44 Nhon Hoi Wind farm project – Phase I Technical Design standard is no longer clear. According to statistic data, under the influence of the Northeast monsoon, it’s only wind to change its direction towards the North and getting stronger to Grade 3, Grade 4, gales of grade 5, Grade 6 in the coastal area, barometric pressure increases, most of daily average temperatures reduce only about 10C. In average, every year, there are nearly 10 Northeast monsoon times affecting Binh Dinh, accounting for 30% of the monsoon time arriving to Hanoi and 68% of the monsoon times to Da Nang. The first Northeast monsoon time to Binh Dinh normally from October, but there is also a year that the first Northeast monsoon time appears in Binh Dinh in September or until November. The end time usually ends in April, but sometimes till May in some years. In general, in the winter months from November to March of the following year, on average, there is more than one monsoon affecting Binh Dinh. Monsoon occurs in December accounts for about 20% of the number of monsoons in a year. 2.2.3.8.6. Atmospherecontamination Nhon Hoi wind power plant project is expected to be built in Nhon Hoi economic zone, Nhon Hoi and Nhon Ly communes, Quy Nhon city, Binh Dinh province. The project is on Den mountainous area where there is a lot of boulders, 5km far from the sea. According to the electrical equipment code 11 TCN-19-2006, it is recommended to design the insulation for heavily polluted environment, corresponding to the leakage line standard of 31mm/kV. The detailed meteo-hydrological survey results are shown in the meteohydrological survey report of Nhon Hoi wind power plant project - Phase 1 & Phase 2 performed by 23 Construction and Consulting Joint Stock Company implemented in November 2020. Volume 1.1 – Chapter 2 2-45 Nhon Hoi Wind farm project – Phase I Technical Design CHAPTER 3: SOLUTIONS FOR ELECTRICAL – TECHNOLOGY OF POWER PLANT 3.1. GENERAL LAYOUT SOLUTION The General layout was basicaly considered for implementation in the Basic Design stage. Due to the project is located in hilly and steep terrain, the optimal locations for the arrangement of wind turbines do not vary much between calculated scenarios, mainly in areas of hilltop or top of watershed. On the basis of the researches in the Basic Design stage, combined with the detailed 1:500 topographic map in the Technical Design stage, the wind turbines are micro sitting to fit with the construction conditions, as well as ensuring the optimum in terms of energy production. Accordingly, the positions will be adjusted about 15 ÷ 30m compared to the Basic Design stage. The General layout solution for other items is as follows: - 110kV substation and 110kV transmission line: the position is maintained according to Basic Design stage; - Access road and internal road: inheriting the results of basic design phase, combined with detailed 1:500 topography map, the Technical design adjusts some parts of road sections to facilitate road slope, intersections to suit transportation and installation of wind turbines; - 22kV underground cable and overhead line: adjusted to fit with internal routes and topographic conditions (for the 22kV overhead line); - The O&M Building: The position of the O&M Building is shifted about 170m from the Basic Design, located on the same main road leading to the project; - Disposal area: on the basis of locations of main disposal area in the Basic Design stage, the Technical design readjust the area to suit the terrain conditions; - Temporary items such as construction offices, storage areas are arranged near the access road to the project, on flat terrain. The coordinates of some main items are as follows:. Table 3.1: Coordinates of some main items of project VN2000 coordinates, 3o projection, 108o15' central meridian Point X (m) Y (m) Turbine location – Phase I NH1 1533584.51 610753.35 NH2 1533355.48 610894.33 NH3 1533210.33 611143.02 Volume 1.1 – Chapter 3 3-1 Nhon Hoi Wind farm project – Phase I Point NH4 NH5 NH7 Q1 Q2 Q3 Q4 Volume 1.1 – Chapter 3 Technical Design VN2000 coordinates, 3o projection, 108o15' central meridian X (m) Y (m) 1533094.29 611401.38 1533056.61 611663.47 1532228.71 611472.61 O&M Building Location 1532854.51 610841.51 1532791.17 610822.95 1532804.11 610778.81 1532867.45 610797.37 3-2 Nhon Hoi Wind farm project – Phase I Technical Design Figure 3.1: Project General layout Volume 1.1 – Chapter 3 3-3 Nhon Hoi Wind farm project – Phase I 3.2. Technical Design TECHNICAL CHARACTERISTICS OF MAIN EQUIPMENT 3.2.1.1. Wind turbines 3.2.1.2. Applied standard The wind turbine standard specifies requirements and considerations when designing a wind turbine, as well as other related components, systems, and technologies that affect the reliable functioning of wind turbines. The extended IEC 61400 covers related issues such as overall inspection of the structure and acoustical noise metering, as well as a 6-part information model for communication for monitoring and control. wind power plants, the standardization of wind turbines is complemented by efforts from ISO, ANSI, and other national standards. Together, these standards help ensure the design and manufacture of wind turbines reliably and are conducive to ensuring the long service life of wind turbines and both environment and economy. The typical standards that are widely used when designing wind turbines as well as specific wind power plants are: - IEC 61400 for requirements in wind turbine design, from pre-construction conditions to inspection of installation and commissioning; - IEC 60050-415 Wind turbine generator systems; - ANSI/AGMA/AWEA 6006-A03 (R2010) Design And Specification Of Gearboxes For Wind Turbines; - IEC 60076 (All part) Power transformers in wind turbines; - EC 62305: 2006 and the GL standard for lightning protection; - IEC 62271 High-voltage switchgear and controlgear - IEC 60376 Specification of technical grade sulfur hexafluoride (SF6) and complementary gases to be used in its mixtures for use in electrical equipment; - IEC 60815 Selection and dimensioning of high-voltage insulators intended for use in polluted conditions; - IEC 60364-6 Low-voltage electrical installations - Part 6: Verification; - IEC 60364-1 (all parts) Low-voltage electrical installations - IEC 60502 ower cables with extruded insulation and their accessories for rated voltages from 1kV (Um = 1,2kV) up to 30kV (Um = 36kV) - IEC 60044 Current transformers - IEC-60099 Surge arresters 3.2.1.3. Main equipment specifications of wind turbines Wind turbines are composed of the main components as shown below: Volume 1.1 – Chapter 3 3-4 Nhon Hoi Wind farm project – Phase I Technical Design Figure 3.2: The main components of wind turbines a. General requirements: Wind turbines are constructed with safety grade not less than class III according to IEC 61400-11 standard at wind speed at height. Wind turbines are equipped with automatic control, monitoring and protection system to meet the requirement of no operator. b. Nacelle The Nacelle is the place where most of the regulating equipment of wind turbines such as control space, heat exchange system, cylinder rotation system, generator, power converter ..., outside the shell is equipped with sensors wind. The Nacelle is made of fiberglass, highly durable, lightweight. The turbine shell has space (operating floor) for maintenance personnel. c. Base Plate The base plate is located in the turbine housing compartment, for the installation of a driven train, gearbox, generator, transmitting wind turbine power to the tower and foundation. Base plate is made from cold rolled steel. Volume 1.1 – Chapter 3 3-5 Nhon Hoi Wind farm project – Phase I Technical Design d. Rotor Blade: The turbine uses 3 upwind type blades. Each wing has an independent pitch control system. The wing is equipped with a lightning protection system, which conducts lightning through the tower to the ground. The blades material uses epoxy-reinforced fiberglass. Lightning protectors and lightning arresters installed on the top of the blade, wire cross-section and the temperature rise for the maximum lightning discharge current of 100kA does not exceed 250°C Blades and turbines are certified according to IEC 61400-23, the surface roughness is tested to comply with DNVGL-ST-0376 quality certification or equivalent. Root Bulkhead is connected to the turbine bulb by planting a bolt. The structure allows copper / electro-hydraulic transmission equipment to be arranged for the blades angle adjustment system. e. Cooling system The wind turbine unit compartment is equipped with an indirect water cooling system with blower and circulating water pump, heat dissipation for the bearing oil parts, generators, and inverters. Radiator fins made of copper or stainless steel. f. Generator Generator type DFIG is intended. Main components include stator, rotor, stator shaft, rotor shaft and other auxiliary parts. + Type : DFIG asynchronous + Rated power : 5.000kW + Maximum capacity : 5.150kW + Range of power factor : 0.9 leading to 0.9 lagging + Rated speed : 1120 rpm-6p (50Hz) 1344 rpm-6p (60Hz) + Insulation level : Stator F/H Rotor F/H + Cooling system : Liquid cooling + Ventilation inside : Air + Adjusted parameters : Coil, liquid, bearing temperature + Rated frequency : 50 or 60Hz + Minimum voltage : 90% Rated + Maximum voltage : 112% Rated + Minimum frequency : 94% Rated Volume 1.1 – Chapter 3 3-6 Nhon Hoi Wind farm project – Phase I + Maximum frequency Technical Design : 106% Rated With the 3-phase, 6-pole squirrel cage asynchronous generator type connected to the 22kV transformer via a full-power inverter. The inverter power is determined by the manufacturer in accordance with the range of slip rates between the rotor frequency and the grid frequency. g. Inverter The 3-phase inverter meets the grid connection requirements specified in Circular 39/2017 / TT-BCT. The inverter is equipped with frequency-based shedding protection and is capable of maintaining grid-clinging operation within the specified frequency range. The inverter capacity is determined by the manufacturer according to the wind turbine generator configuration/type. h. raking system The wind turbine includes 2 brake systems: aerodynamic brake and mechanical brake. The aerodynamic brake system is operated through 3 independent pitch angle control systems of 3 blades. Thanks to that, the braking of wind turbines can be operated flexibly without being affected even in the event of a system failure. The mechanical brake system is often used to lock the generator rotor during maintenance. This system works independently of the control and protection system of a wind turbine. 3.2.1.4. Monitoring control system a. Yawin This system works to rotate the entire nacelle to direct wind turbines to the main wind direction, thereby achieving the highest wind energy collection. Uses multiple motors to rotate the shaft with its smooth torque property to optimize rotation speed thereby minimizing the effects of fluctuating operating conditions. The system uses hydraulic brakes to lock the nacelle when the wind turbine is not operating. In addition, the yawing system also uses an electromagnetically operated safety brake at the motor shaft in case of serious damage. b. Pitch control The pitch motor uses a two-way acting hydraulic system that adjusts the wing angle according to the wind speed signal installed above the wind turbine compartment: - High charging current, short charging time. - No required charge/discharge circuit. - Long service life. - Compact … Volume 1.1 – Chapter 3 3-7 Nhon Hoi Wind farm project – Phase I Technical Design The blades adjustment system is arranged for each blade independently, the adjustment angle is not set to 90 degrees. The turbine is capable of adjusting maximum power as well as the speed of output power change through the pitch control system. The plant system not only controls the capacity of each wind turbine but also has the function of controlling the capacity of the whole wind farm to ensure that it is consistent with the resource mobilization plan and stable operation on the regional power grid. The control of the power increase rate of the turbine is achieved by controlling the pitch angle change rate of the impeller to minimize the effects of sudden increases in wind speed resulting in large fluctuations (pulses) wind turbine output power. Figure 3.3: Principle of the control of blades angle (pitch) c. Wind gauge Each wind turbine is equipped with a device that measures the wind speed and direction above the turbine compartment, directly connected to the Pitch and Yaw control.. d. The system for continuous monitoring of wind turbines The control system consists of the following main parts: - Main control cabinet; - Sensor signal reception box; - Inverter; - The controller pitch; - Yaw regulator; - Generator cooling system; - Water cooling system control; Volume 1.1 – Chapter 3 3-8 Nhon Hoi Wind farm project – Phase I Technical Design - Operational control; - Monitoring system (voltage, frequency, current, power and power factor of generators, wind speed ...). The wind turbine generator control system together with the electrical system can completely protect the turbine generator's electromechanical equipment from malfunctions and failures, and together with ensuring the power generated when wind maximum speed. This control system must be automated, operating unattended under regional conditions. The main control board can be individually designed for each generator and installed at each generator. The system should at least be able to shut down, display, and signal under the following conditions: - Activate emergency stop - Grid breakdown: frequency breakdown, voltage breakdown, over current, phase order breakdown, ground fault, phase loss symmetry - Rotor over speed - Generator over speed - Transient overload Pt (Pr + 25%) is exceeded - The maximum overload level, Pa (Pr + 50%), is exceeded. - Over wind speed - Overheating (generator, transmission oil, control panel, frequency converter Overheating (generator, transmission oil, control panel, frequency inverter) - Brake system failure - Nacelle vibration - The Yaw incident - Twisted cable - Control failure - Grid breakdown - Hydraulic system breakdown - Transformer overheating (phase 1: warning, phase 2: disconnect the circuit breaker and cut off the load - transfer load MV) The system can display and signal in case of wind sensor failure. The control system can automatically restart the WTG after being turned off due to a mesh malfunction, after the cable is untwisted, after the wind speed returns to normal after the overheating in the system is caused by overheating transient and temporary overloads after disappearing. The WTG must be manually restored in the event of all shutdowns and failures unevaluated. Volume 1.1 – Chapter 3 3-9 Nhon Hoi Wind farm project – Phase I Technical Design Emergency shut-off switches are required for manual operation at least at the nacelle, ground control, top control, spindle and yaw ring. Surveillance system that is part of the WTG control system should at least display the following: - Status of each WTG - The state of the wind farm - State of the wind farm substation - Status of the meteorological station - Power generated by WTG (kWh) - All phase voltages and phase currents - Harmonic output of each WTG - Wind speed (m/s) and wind direction - All incidents including wind farm grid failures (status messages, times and total times, dates and or accumulated memory to provide more than 14 months of storage) - Active capacity (kW) - Reactive power (kVAR) - Power factor - Rotor speed (rpm) - Generator speed (rpm of high speed shaft) - Temperatures at nacelle, gearbox, generator, bearing, control panel and environment. If a certain value cannot be measured directly, the contractor has to offer an alternative to obtain data at the central monitoring computer. Central monitoring software monitoring system has the function of monitoring, controlling alarms, reporting ..., remote monitoring system. The intranet is flexibly designed according to network forms such as ring circuit configuration, tree shape, star shape, and special forms depending on the wind turbine layout. 3.2.1.5. Converter The procedure for starting and connecting is as follows: - Wind sensor detects the direction of the wind to adjust the nacelle to rotate in that direction; - Generator turbines rotate, excitation current increases with wind speed. - When the wind speed is greater than the operating speed (cut in), the full converter generates voltage equal to the grid voltage as well as frequency synchronous with the frequency on the grid. At the same time, the phase difference between the generator is the voltage at the connection point being measured. When this deviation Volume 1.1 – Chapter 3 3-10 Nhon Hoi Wind farm project – Phase I Technical Design is 0, the generator is connected to the grid through the converter's IGBT power electronics. Table 3.2: The operating frequency range of wind turbine No. Technical requirements System frequency (50Hz –60Hz) 1 Depending on the minimum frequency, the turbine can operate normally < 46Hz 2 The turbine can operate for as little as 0.2 seconds at a time 46-47Hz 3 The turbine can operate for at least 2 seconds at a time 47-47,5Hz 4 Continuous operation 47,5-52,5 Hz 5 The turbine can operate for at least 2 minutes at a time 52,5-53 Hz 6 The turbine can operate for as little as 0.2 seconds at a time 53-54 Hz 7 Depending on the maximum frequency, the turbine can operate normally >54 Hz At high frequencies, the system is either turned off or deflated to 2% to 10% of rated power. The reactive power control system adopts a power converter. 3.2.1.6. Steel tube cylinder Steel tube cylinders for wind turbines are usually divided into sections and connected by flanges and bolts. Steel tube cylinders is made entirely of galvanized steel. Steel tube pillars are installed on a reinforced concrete foundation with the foundation bolts buried in the concrete foundation. Inside the steel tube cylinders are equipped with ladders and landing sites as well as a protection system against falling. The lift can also be fitted inside if applicable. The electrical cabinets are located below the tower. The grade design meets level II for bearing safety. The tower is equipped with a ladder and protected against falling. An elevator is optional. The power cable and control cable are located in the post with anti-twisting protection when rotating the nacelle. After the nacelle rotates in the same direction, the cable is automatically twisted. 3.2.1.7. Main specifications Volume 1.1 – Chapter 3 3-11 Nhon Hoi Wind farm project – Phase I Technical Design The main specifications of wind turbines will include the following: Table 3.3: Main specifications of wind turbines No. Unit Parameter 1.1 Type - 3 blades, horizontal axis 1.2 Orientation - In the wind direction 1.3 Diameter m 145 1.4 Scanning area m2 16.513 1.5 Capacity adjustment - Adjust pitch and torque with variable speed 1.6 Rotor inclination - 6o 2.1 Type - Self-bearing 2.2 Blades length m 71 2.3 Root chord m 2,856 1 2 Part Rotor Blades 2.4 Material 3 Aerodynamic brake 4 Load support item Epoxy reinforced Fiberglass 4.1 Hub - nodular cast iron 4.2 Main shalf - forging steel 4.3 Frame shell - nodular cast iron 6.1 Type - Completely self-contained 6.2 Gloss of surface - Half Gloss, <30/ISO2813 6.3 Color - White, RAL 9018 7 Generator - Asynchronous generator, DFIG 8 Connect (LV) 5 Mechanical brake Nacelle 6 Volume 1.1 – Chapter 3 3-12 Nhon Hoi Wind farm project – Phase I No. Unit Parameter 8.1 Basic rated capacity MW 5.0 8.2 Voltage V 690 8.3 Frequency Hz 50 hoặc 60 9.1 Type - Stell tube 9.2 Hub - 102,5 9.3 Anticorrosion - Paint 9.4 Gloss of surface - Half Gloss, <30/ISO-2813 9.4 Color - White, RAL 9018 9 Part Technical Design Turbine tower 3.2.2. MV switchgear in power plant 3.2.2.1. Voltage level The generators of each wind turbine will generate 3-phase AC with an output voltage of 690V, then through a MV transformer placed in the turbine nacelle to transform the voltage up to 22kV. These turbines will be connected together by 22kV underground cable combined with overhead line 22kV XLPE aluminum core type then connected to the 22kV busbar at the 22/110kV Nhon Hoi WPP substation to transform the voltage up to 110kV, then connected to the National grid via the 110kV Nhon Hoi – Dong Da transmission line. 3.2.2.2. Single line diagram Newly building a 3-phase, 22kV medium voltage system combining underground cables and OHL cables connecting from turbines to 22kV cabinets at 22/110kV Nhon Hoi WPP substation. Volume 1.1 – Chapter 3 3-13 Nhon Hoi Wind farm project – Phase I Technical Design Figure 3.4: Typical SLD of turbine The Nhon Hoi WPP – Phase 1 project has 06 MV substations 0.69/22kV (1 MV substation for each turbine), divided into three 22kV cable routes connected from the 0.69/22kV MV substation to 22/110kV Nhon Hoi WPP substation via 01 single OHL and 01 double OHL, using ACX-240mm² wire. The details are as belows: - Circuit 1: Connecting NH7 turbine to 22/110kV Nhon Hoi WPP substation. + Connecting from NH7 turbine to overhead transmission line using underground cable Al-22kV-3x120mm2, 220m long. + Connecting from the overhead transmission line to 22/110kV Nhon Hoi WPP substation using ACX-240mm², 373m long. - Circuit 2: Connecting the NH1-NH2 turbines one by one 22/110kV Nhon Hoi WPP substation. + Connecting from NH1-NH2 turbine using Al-22kV-3x120mm2 underground cable with length of 400m. + Connecting from NH2 turbine to overhead transmission line using Al22kV-3x240mm2 cable with length of 129m. + Connecting from the overhead transmission line to 22/110kV Nhon Hoi WPP substation using ACX-240mm², 1605m long. - Circuit 3: Connecting the NH5-NH4-NH3 turbines one by one to 22/110kV Nhon Hoi WPP substation. + Connecting from NH5-NH4 turbine using Al-22kV-3x120mm2 underground cable with the length of 513m. Volume 1.1 – Chapter 3 3-14 Nhon Hoi Wind farm project – Phase I Technical Design + Connection from NH4-NH3 turbine using Al-22kV-3x240mm2 underground cable with length of 461m. + Connecting from NH3 turbine to overhead transmission line using underground cable Al-22kV-2x(3x240mm2) with length of 274m. + Connecting from the overhead transmission line to 22/110kV Nhon Hoi WPP substation using ACX-240mm², 1605m long. The OHL 22kV No. 1 has 1 section about 1km length with 3 circuits, of which a 22kV OHL is used to supply electricity for auxiliary power for the O&M building. The 22kV underground cable routes go out from the 0.69/22kV wind turbine’s MV substation to the transited pole between underground cable - overhead line are laid in the cable trench, put inside flexible plastic pipe HDPE with a suitable size, protecting HDPE conduits via a brick tile layer with an underground cable warning tape. Above the cable trench, there are poles signaling the cable line with a distance of 50m/pile. The underground cables cross the road are protected by steel pipe. 3.2.2.3. 0.69/22kV MV substation At each wind turbine tower, 01 MV substation of 0.69/22kV will be arranged. MV substation include MV transformer, medium voltage switchgear and protection system, in which the alternating current will be transformed up to 22kV using 5500kVA transformer. The MV substation will be placed in the nacelle to minimize capacity loss. Specifications of the 0.69/22kV-5500kVA MV substation are as follows: Table 3.4: Specifications of the 0.69/22kV-5500kVA MV substation No. Item Specification Unit 1 Type 3 phases, dry transformer 2 Standard 3 Rated capacity 5500 kVA 4 LV Rated voltage (turbine side) 0.69 kV 5 Connection Dyn11 6 MV Off-load tap changer 7 MV Rated voltage 8 Insulation level (AC/LI) 9 IEC60076 ECO Design Directive ± 2 x 2.5% 22 kV 50/125 kV Frequency 50 Hz 10 Cooling method AF 11 Temperature regulation Volume 1.1 – Chapter 3 Winding, Magnetic core 3-15 Nhon Hoi Wind farm project – Phase I No. Technical Design Item Specification 12 Insulation F 13 Impedance 8.31 Unit % 3.2.2.4. RMU 22kV To protect and operate the 0.69/22kV - 5500kVA transformer for maintenance and repair working, using the RMU switchgear equipped with a MV circuit breaker which has a rated current 630A at the MV side. Beside, the RMU is equipped with LBS - Load breaking switch with the rated current 630A to protect the underground cable line to ensure continuous operation and for isolated cutting the underground cable segment to maintenance and repair. These switches are integrated in the RMU located in the working platform inside wind turbine tower. Two type of RMU shall be used in Nhon Hoi – Phase 1 project: - Type 1: 1 transformer cabinet included circuit breaker and disconnecting switch, 1 feeder cabinet for cables come out (turbine no. NH1, NH5, NH7). - Type 2: 1 transformer cabinet included circuit breaker and disconnecting switch, 1 feeder cabinet included load breaker for cables come in, 1 feeder cabinet for cables come out (turbine no. NH2, NH3, NH4). RMU type 1 RMU type 2 Figure 3.5: RMU configuration Specification of the 22kV medium voltage cabinet are as follows: - Metal-clad/metal-enclosure/Ring main unit 3 phases, SF6/vacumm insulation. - Rated frequency : 50 Hz - Rated voltage : 24 kV - Insulation level : o Lightning impulse : 125 kV (peak) o Industrial frequency impulse : 50 kV (rms) Volume 1.1 – Chapter 3 3-16 Nhon Hoi Wind farm project – Phase I - - Technical Design MV feeder bay : Equip LBS o Rated current : 630 A o Load breaking current : 630 A o Short-circuit breaking current : 20 kA rms (1s) o Transient breaking current : 25 kA (peak) Main transformer bay : Equip ACB o Rated current : 630 A o Short-circuit breaking current : 25 kA rms (1s) o Transient breaking current : 62.5 kA (peak) 3.2.2.5. Measuring diagram - All measuring equipments have input or converter that communicates with SCADA system. - The generator output: Measure A, V, W, Var, Wh, Varh, f, cos φ. - Auxiliary power source: Measure A, V AC and DC. 3.2.2.6. MV switchgear location Medium voltage equipment and control equipment are planned to be located in the foundation base of the wind turbine with the working platform and access ladder. The distance between MV equipment and other equipment at the base of the wind turbine is arranged to ensure a safety distance for the operator and equipment in accordance with the current IEC regulations. The MV equipment and the control device are fixed to the working platform by a solid bolt connection, while allow to detach the damaged part and replace easy the new part when a failure occurs. The electrical equipment is transported through the door at the base of the wind turbine’s tower. 3.2.2.7. Specification of MV underground cable No. 1 Item Type Rated voltage 2 Unit kV Specification YJLY2318/30kV 3*120 YJLY23-18/30kV 3*240 18/30 18/30 Conductor Manufacturer Jiangsu Shangshang Cable Group Co.,Ltd. Material Aluminum Volume 1.1 – Chapter 3 Aluminum 3-17 Nhon Hoi Wind farm project – Phase I No. Item Technical Design Unit Long term operating temperature ℃ 90 90 Short circuit temperature ℃ 250 250 Nominal cross-section area mm2 120 240 Approximate outer diameter mm 13 18.3 Number / diameter of single wire mm 19/2.95 37/2.97 ≤0.9 ≤0.9 957 1924 Compression coefficient Structural consumption 3 kg/km Jiangsu Shangshang Cable Group Co.,Ltd. Insulation Material 4 Specification XLPE XLPE Thickness(nominal value) mm 8.0 8.0 Outer diameter (approximate insulation outer diameter value) mm 30.3 35.6 Structural consumption (approximate weight of insulation) kg/km 1512 1867 inner covering Anhui Kenuo New Material Co., Ltd. Jurong Boyue Cable Material Co., Ltd. Liyang new century electrical materials Co., Ltd Manufacturer filling material PP rope PP rope Thickness(nominal value) mm 2.0 2.2 Outer diameter (approximate outer diameter of inner sheath) mm 75 87 Volume 1.1 – Chapter 3 3-18 Nhon Hoi Wind farm project – Phase I No. Item Structural consumption (indicated by classification) (reference weight of inner sheath) 5 Technical Design Unit kg/km 704 918 Armor layer (if any) Manufacturer Jiangsu Ruixin metal products Technology Co., Ltd. Jiaozuo Haibo metal products Co., Ltd Material Steel ribbon Steel ribbon Specification (nominal value) mm 0.8 0.8 outer diameter mm 78 90 1965 2273 Structural usage (approximate kg/km weight of armor) 6 Specification Serving Manufacturer Jiangsu Shangshang New Material Co. , Ltd.Linhai Yadong special cable material factory Material PE plastic, anti rodent, anti water PE plastic, anti rodent, anti water Thickness(nominal value) mm 3.7 4.1 Outer diameter (approximate outer diameter of outer sheath) mm 86.5 99.4 Structure dosage (outer sheath reference weight) kg/km 888.7 1142 7 Approximate weight of cable kg/km 7902 10644 8 DC resistance of conductor at 20 ℃ Ω/km 0.153 0.0754 9 Resistance of metal screen at 20 ℃ μF/km 0.1760 0.2207 Volume 1.1 – Chapter 3 3-19 Nhon Hoi Wind farm project – Phase I No. Item 10 Capacitance of cable 11 Maximum allowable traction force of cable 12 Allowable bending radius of cable 13 Short circuit current of conductor for 1 second 14 Standard Technical Design Unit mH/km Specification 0.3799 0.3360 14040N 28080N mm 12D 12D kA 11.4 22.6 IEC60502 IEC60502 3.2.3. SCADA system 3.2.3.1. SCADA configuration Control, monitoring and data collection system (SCADA system) is located in the central control room of Nhon Hoi wind power plant with the aim of controlling and monitoring all equipment in the whole plant as well as processing data to create a complete database for operational management. Through the establishment of the Control Center and appropriate Gateway devices and terminals, the tasks are as follows: - Control wind turbines and collect data from wind power plants. - Analyze and report on the operation of the plant. - Simple operation, minimizing the down time of the power plant and the grid. - The power plant SCADA system includes optical switches connected in series between the turbines to the central switch at the control room, through the router and communication equipment equipped in the 22/110kV Nhon Hoi substation’s scope. The SCADA signals are connected to a wide area network WAN. - Use Ethernet network cable to connect the switch of each turbine to the Wind turbine monitoring device (SCADA monitoring device). - Use fiber optic cables in the conduit placed in the cable trench to connect the switches of wind turbines, the optical cables follow the underground cable to the overhead line connecting to the fiber optic terminal box hanging on the steel pole, the fiber optic cable routes overhead wire to control room. - The information on the wind power plant control system in this document is for reference and design coordination of data communication lines to the dispatching center according to the required SCADA signals in the Information - SCADA agreement. Volume 1.1 – Chapter 3 3-20 Nhon Hoi Wind farm project – Phase I - Technical Design SCADA system is equipped in the Nhon Hoi power plant project - Phase 1 and is used for general control and supervision for both phases of the project. It means the total generating capacity of all wind turbines of both phases is controlled through the common PPC - Power Plant Control device, invested in phase 1 of the project. Figure 3.6: Typical SCADA single line diagram Figure 3.7: Typical fiber optic connection of WTG Figure 3.8: Typical fiber optic connection of WTG’s switch Volume 1.1 – Chapter 3 3-21 Nhon Hoi Wind farm project – Phase I Technical Design 3.2.3.2. Control system of wind power plant The power plant control system is equipped with computer control, power controller and working status monitoring of all wind turbines, generators, inverters and MV station equipments. The wind power plant model for control and supervision system is set up with a control loop through two optical switches were invested in 22/110kV Nhon Hoi substation’s scope. Figure 3.9: Typical control system of wind power plant The VOB server operation control computer has the function of controlling and monitoring the operation of the whole plant. The PPC – plant power controller performs the functions of automatically adjusting active power, reactive power of each wind turbine according to the requirements of the power system dispatching centers. All functions of the turbines and 22kV stations are controlled by computer software with remote control using the manufacturer's dedicated integrated control system for each turbine and interconnection to the central SCADA system located in the central control room of the 110/22kV substation. Data is transmitted through the fiber optic communication system, beside, a local control function in the control cabinets shall be equipped too. All equipments are arranged in the turbine tower or in the cabin next to the turbine tower (in the project is being designed the 0.69/22kV substation, RMU and low voltage equipment, protective controller located in the turbine tower). Volume 1.1 – Chapter 3 3-22 Nhon Hoi Wind farm project – Phase I Technical Design The operation of the wind power plant is completely automatic, except when the generator is actively stopped due to problems or due to periodic maintenance. The wind power plant is equipped with WIND SCADA system meeting IEC 61400 standard to control wind turbines. Figure 3.10: Wind SCADA configuration The wind turbines and WIND SCADA server systems are interconnected via an internal fiber optic network (SCADA Network). WIND SCADA server supports connection to other SCADA systems according to IEC 60870-5-104. From the Setpoints value received via the SCADA system at the 22/110kV substation. WIND SCADA server controls the response wind turbines according to the value Setpoints received. Volume 1.1 – Chapter 3 3-23 Nhon Hoi Wind farm project – Phase I Technical Design Figure 3.11: Single line diagram of SCADA’s communication 3.2.3.3. Power generation prediction system SCADA system shall be equipped with equipment, tools or software to predict output power of solar power plant based on meteorological conditions. These data shall be transmitted to National Load Dispatch Center (A0) to ensure grid safety operation. Output power prediction of solar power plant shall meet requirement of precision, time range, to be consistent with load dispatch circle and exchange circle of Vietnam Wholesale Electricity Market (VWEM), with considering to uncertainty of meteorological factor. Detail technical requirements are as following: a. Prediction in operation day (intra day) - Resolution: 15 minutes - Time range: next 3 hours, with total 12 SCADA signals - Update frequency: 15 minute/time, real time operation - Acceptable mismatch: less than ± 7%. This mismatch will be decreased, depended on real time operation requirement. - Connection: measuring SCADA signal from power plant to National Load Dispatch Center (A0). b. Prediction of next day, next week (day ahead and month ahead) - Resolution: 15 minutes - Time range: next 7 days - Update frequency: 1 time/day at 10h00 - Acceptable mismatch: less than ± 10%. This mismatch will be decreased, depended on real time operation requirement. Volume 1.1 – Chapter 3 3-24 Nhon Hoi Wind farm project – Phase I Technical Design - Connection: to website of Hydro-meteorological forecasting system for planing and operation of power system (https://weather.nldc.evn.vn/KTTV). c. Prediction of next month (month ahead) - Resolution: 1 hour (typical daily chart) - Time range: next month - Update frequency: before 15th day of each month - Connection: to website of Hydro-meteorological forecasting system for planing and operation of power system (https://weather.nldc.evn.vn/KTTV). 3.2.3.4. Power plant controller - PPC The power plant controller divides in two configurations: Normal and Quick Configuration, available for installation in the wind farm depending on the reaction time, response time, and accuracy to be achieved. The main difference between both configurations is the reaction time and response time which is summarized in the following table: Table 3.5: Specification of PPC device No. Normal Configuration Quick Configuration Reaction time A-F (Active power – Frequency) 1-2s <200ms 1-2s <200ms Depending on turbine’s transformation ratio Depending on turbine’s transformation ratio 2-3s <1s Solution Yes Yes Hardware requirement No Yes Reaction time Q-V (Reactive power – Voltage) Response time A-F (Active power – Frequency) Response time Q-V (Reactive power – Voltage) Volume 1.1 – Chapter 3 3-25 Nhon Hoi Wind farm project – Phase I Technical Design Figure 3.12: Normal Configuration Figure 3.13: Quick Configuration The power control function can be divided into 3 main components: - Management system: Processes all external signals (regulating commands and external control signals - Control commands and control signals) and forwards these signals to the different internal regulators. - QVi: Module integrates algorithms to adjust reactive power / voltage. - PFi: Module integrates algorithms to adjust active power / frequency. 3.2.3.5. SCADA fiber optic cable specification SCADA fiber optic cable has detailed structure as shown below: Volume 1.1 – Chapter 3 3-26 Nhon Hoi Wind farm project – Phase I 3.3. Technical Design - Minimum of 24 optical fibers (12 pairs) for each wind turbine connected to SCADA system; - Fiber optic type Single mode 9/125 OS2; - Non-corrosive, meet IEC60754-2 and EN50267 standards; - Fire retardant, meet standards IEC60332-3-24 and EN50266-2-4; - Has reinforced flame retardant layer, does not generate halogen gas when burning; - No water ingress, meet IEC60794-1-2-F5 standard; - Non-metal fiber optic cable, no need for safe grounding; - Against rodent damage to optical fiber via anti-rodent chemical powder adding in cable’s insulated cover; - Anti-bacteria and anti-UV; - Can be installed in cable conduit or buried directly in the ground; - Meet the regulations of RoHS; - Working temperature: -5°C to 50°C. LIGHTNING PROTECTION 3.3.1. Strike lightning protection Lightning protection system for each wind turbine: the receptors are located on the turbine blades, the lightning arrester is arranged inside the blades to protect overvoltage caused by direct lightning strikes. 3.3.2. Surge lightning protection Protection against atmospheric overvoltage propagating from the strike lightning protection to the wind turbine 22kV switchgear is carried out by lightning wire and surge arresters installed at the both-end terminals of the 22kV underground cable and at the MV side of MV transformer’s cable. Lightning arresters use non-gap metal oxides valve. At the wind turbine nacelle, an anemometer installation area is equipped with a lightning arrester to conduct lightning current through the grounding system to avoid the lightning current spreading in the driven system. Volume 1.1 – Chapter 3 3-27 Nhon Hoi Wind farm project – Phase I Technical Design Figure 3.14: Lightning and grounding system of turbine’s tower 3.3.3. Grounding system Wind turbine grounding grid consists of 02 parts, circular ground grid and additional rod-bar grounding grid with D16 galvanized steel wire combined with D22 galvanized steel rod 2.4m long. Volume 1.1 – Chapter 3 3-28 Nhon Hoi Wind farm project – Phase I Technical Design Arranging a circular ground grid in accordance with the shape of the concrete foundation at the bottom of turbine tower, using bare copper wire with a minimum cross section of 70mm² to perform a ring ground grid. The grounding grid directly placed in the concrete foundation at bottom of the turbine tower. Combined arrangement of equipotential rings in the bottom of reinforced concrete foundation and inside the turbine tower to form a complete grounding grid. The air-termination wire is from the air-termination unit on the top of the turbine blade to the monopile foundation and the grounding system uses bare copper wire with minimum cross section 50mm². Main earthing electrical bonding (MEEB) is located at the back of the RMU mediumvoltage distribution cabinet to ground circuit breakers, load breakers, transformers, electrical panel covers, steel ladders, cable trays, turbine platform, underground cable strip steel cover and grounding for all equipment with metal shells in wind turbines. The selection of the wind turbine grounding resistance value should meet the Vietnam Electrical Equipment Regulation and recommendations of the turbine manufacturer. Specifically, the whole turbine ground resistance should not exceed 5Ω. In accordance with the technical requirements of the Regulation on Grounding for electrical equipment above 1kV of isolated neutral network, Article I.7.46, and at the same time meeting Article I.7.52 on Grounding for electrical equipment below 1kV of directly earthed neutral network (for Wind Turbine Generator), combined with the turbine manufacturer's specifications for lightning arresters for both of the medium and low voltage side that grounding resistance value shall be equivalent and should be less than 10 Ω. Therefore, choosing the design of the whole turbine earthing resistance not exceeding 5Ω is guaranteed in terms of technical criteria and suitable for economic criteria. 3.4. FIRE FIGHTING SYSTEM The wind energy industry is one of the current leading industries in the field of renewable energy, providing cheap and sustainable energy solutions. However, wind power plants are facing the risk of fire and explosion. The elements of combustion are always present in the body of the wind turbine. During a fire, it is difficult to extinguish the fire because the height and location of these turbines are often located far from residential areas, causing considerable damage to the wind industry. Therefore, it is necessary to have an overview of the causes of fire for wind turbines to have an effective fire protection solution. 3.4.1.1. Causes of fire in wind turbines Some of the possible causes of fire in wind turbines are: - Lightning, electrical equipment failure, surface ignition and construction maintenance. Of these reasons, lightning is the most common source of ignition, especially for wind turbines at sea. The risk of fire is higher when wind turbines are Volume 1.1 – Chapter 3 3-29 Nhon Hoi Wind farm project – Phase I Technical Design not equipped with a lightning protection system or a lightning protection system that is not maintained or maintained. - Another common cause of fire is breakdown of electrical / electronic equipment, overload of electrical / electronic equipment. Short circuits, electrical arcs, and improper protection of electrical equipment are also common causes of fires in wind turbines. - “Hot” surfaces such as overheating bearings, actuators, and mechanical brakes can present a high risk of fire if flammable materials come into contact with these components. - In case of emergency, when the aerodynamic brake system fails to stop the turbine, mechanical brake is used, and leads to a high risk of fire if the brake system is too hot (especially if the lubrication is poor ), when very high temperatures are reached, an arc can be ignited that can ignite combustible materials (for brakes without protective covers). The phenomenon of overheating of the brake system can lead to the breakdown and creation of brake disc fragments, which can cause hydraulic hose to break in the engine body, resulting in hydraulic fluids at high pressure which are very flammable in contact with "hot" surface. - Maintenance and repair activities such as cutting, welding, and grinding inside a wind turbine can lead to a high risk of fire, especially in gear drive systems. - Flammable materials at a distance of 10m or more can be easily burned with a spark from grinding, welding, and cutting. 3.4.1.2. Fire protection solutions for wind turbines 3.4.1.2.1. Passive solution Passive fire prevention in wind turbines can be done in many ways, but is primarily focused on flammable components that spread the flame to other components in the turbine body. Passive fire prevention for wind turbines is implemented by several solutions such as: - Installation of lightning protection systems; - Use hydraulic oil and non-flammable lubricating oil; - Using incombustible materials for wind turbine bodies; - Avoid performing maintenance and repair activities related to welding, "hot" cutting inside the turbine body; - Use condition monitoring system (CMS) to monitor the working status of important equipment and perform regular inspection and maintenance. 3.4.1.2.2. Active solution Volume 1.1 – Chapter 3 3-30 Nhon Hoi Wind farm project – Phase I Technical Design a. Smoke detector for wind turbine pillar In the air intake detection system, the air is sampled from the protected area through a network of pipes, actively sucking air towards the detection system using a highpressure suction fan. Advantages of the system: - The sampling pipe used in the air intake system is more resistant to the harsh environment than the standard point smoke detector. - Smoke detector system can typically provide much higher sensitivity than standard smoke detectors, but at the cost of a conventional smoke detector. - This highly sensitive smoke detector is a device quality measuring device that collects laser light scattered from smoke particles in a full 360 degree scan. The result is an astonishing 0.001% obscure/meter sensitivity, 2000 times more sensitive than a conventional smoke detector. b. Fire fighting system in wind turbine pillars Areas within a wind turbine with a high fire risk include: - Electric cabinets area - Converter cabinets area - Transformer room area At the wind turbine pillars installed and equipped with automatic fire extinguishing system NOVECTM 1230 installed fire protection for the areas inside the wind turbine. Combined with the manufacturer's designed smoke detector integrated in the device of the wind turbine. The NOVECTM 1230 automatic gas fire extinguishing system includes: - Smoke detection system (smoke detector); - Control cabinet; - System of gas cylinders NOVECTM 1230; - Pipeline system of gas distribution and spray nozzle; - Push button activates the exhaust (on the cabinet); - Push button by manual action; - Push button to delay fire fighting; - Fire bell; - Horn / lamp; - Accessories included. The number of Novec 1230 cylinders for a wind turbine pillar is 2 Novec 1230 cylinders for 1 wind turbine pillar (01 cylinder 11kg, 01 cylinder 2.7kg) Volume 1.1 – Chapter 3 3-31 Nhon Hoi Wind farm project – Phase I Technical Design Figure 3.15: Gas automatic fire extinguishing system installed in wind turbines 3.5. AUXILIARY TRANSFORMER - Auxiliary power source of wind turbines is taken from a 0.69/0.4kV transformer installed inside the turbine, combined with a UPS power source from a battery used for control and protection systems. - Auxiliary power source of the O&M building is supplied from the 22kV OHL from the 22/110kV substation, installed 01 new 22/0.4kV-200kVA substation near the entrance of the O&M building. - During construction time, using diesel generator for auxiliary power supply. - Specifications of the auxiliary transformer of the O&M building are as follows: + Voltage : 22±2x2.5%/0.4kV. + Capacity : 200 kVA. + Connection : Dyn-11. Volume 1.1 – Chapter 3 3-32 Nhon Hoi Wind farm project – Phase I Technical Design CHAPTER 4: CONSTRUCTION SOLUTIONS FOR PLANT PART 4.1. SELECTION OF CONSTRUCTION SITES/ITEM ELEVATION 4.1.1. Principle of elevation calculation The grading elevation of the plant shall be calculated to ensure conditions of technical and consider the analysis of the economic factors of the project. The selection of reasonable leveling will advance for the exploitation of natural land, reduction of costs and construction time. - In accordance with the planning of infrastructure development and transportation in Nhon Ly and Nhon Hoi communes – Nhon Hoi economic zone, Quy Nhon city, Binh Dinh province. - Balancing cut-fill volume of the construction areas on the principle of ensuring the technical requirements of the project. - In accordance with terrain and geological conditions of the areas. - Ensure surface drainage, avoiding local flooding in the rainy season. - Connecting traffic infrastructure from the plant internal transport system to adjacent works/ items to ensure technical requirements. 4.1.2. Leveling solution The leveling and preparation work of Nhon Hoi Wind power plant project – Phase 1 shall be constructed hardstand area, road, etc. Before leveling, it is necessary to remove the surface organic soil layer with a thickness of about 20cm, dismantle and move the stump, single rocks, etc. on the area surface. Waste soil shall be storaged to reuse for backfilling. The leveling work shall be carried out on the principle of digging at the location of high elevation and filling the position of low elevation, refer to the slope ratio shown in the drawing. Filling work: must remove the organic soil layer and make step on nature surface to increase connection between soil layers, compaction ration requirement is K >0.95 4.2. IMPACT LOADS REQUIREMENT AND EARTHQUAKE-RESISTANT DESIGN 4.2.1. Impact loads Depending on the characteristics, the scale of the structure, the technological characteristics will have different special load types. However, basically the load impacting on the construction includes the following types of loads. 4.2.1.1. Permanent loads (standard or design load) These are the impact loads which do not change during construction and operation stage. The permanent loads include: Volume 1.1 – Chapter 4 4-1 Nhon Hoi Wind farm project – Phase I Technical Design - Weight of components and structures, weight of reinforcing structures and cladding structures. - Weight and pressure of soil (backfilling and filling). 4.2.1.2. Long-term temporary loads include: - Weight of partitions, soil and concrete cushioned under the equipment; - Weight of fixed equipment; - Load applied to the floor by materials and equipment in rooms, warehouses, etc. 4.2.1.3. Short-term temporary loads include: - Weight of person, repaired material; accessories and tools; - Dynamic load by equipment in the stages of turn-on, cut-off, forwarding and testing; - Load due to moving lifting equipment during construction and operation stage; - Load impact on the floor of houses, public houses, manufacturing storages. - Dynamic loads shall be accorded to TCVN 2737:1995. 4.2.1.4. Wind load: The wind load will be determined according to the standard: TCVN 2737-1995 "Loads and Actions norm for design"; The plant is located in the region of medium wind forces (zone III.B according to the wind pressure partition table) with standard wind pressure Wo = 125 daN/m2 W0 is determined from the wind speed v0 - wind speed at a height of 10m compared to the benchmark (the average speed in a period of 3 seconds is exceeded by the average one of once every 20 years) corresponding to the B-type terrain (surface roughness z0 = 0.005). 4.2.1.5. Other loads and forces Other loads and forces considered in the design include, but are not limited to, the following loads and forces: Soil pressure, water pressure, environmental load, influence of temperature change, influence due to shrinkage, settelment, etc. 4.2.2. Earthquake-resistant design requirements The calculation of earthquake-resistant design for project items complies with TCVN 9386: 2012 “Design of structures for earthquake resistances”. According to Appendix H - TCVN 9386: 2012, the coefficient of peak ground acceleration of the zone in Quy Nhon city, Binh Dinh province with the value of peak ground acceleration is agR = 0.0941g, conversion from peak ground acceleration to earthquake grade (Scale MSK-64) in Appendix 1 TCVN 9386:2012, the Nhon Hoi Wind Volume 1.1 – Chapter 4 4-2 Nhon Hoi Wind farm project – Phase I Technical Design farm project shall be calculated for earthquake level VII and must calculate seismic resistance. 4.3. WIND TURBINE FOUNDATION 4.3.1. Design of wind turbine foundation The geotechnical and structural design is based on the principle of limit state design, application of load components and the resistance coefficients in accordance with the following standards: - EN 1992-1 Eurocode 2 - Design of concrete structures. - CEB-FIB Model Code 2010 - Model code for concrete structures. - EN 1997-1 Eurocode 7 - Geotechnical design. - EN 206-1 Concrete: Specification, performance, production and conformmity - IEC 61400-1 Wind turbines – Part 1: Design requirement 4.3.2. Structure of wind turbine foundation Wind turbine foundation structure is a reinforced circular concrete slab structure, in which: - Type 1 – NH1 to NH5: diameter 21.4 m; height of foundation base 2.6m; height of pedestal 0.65m; total height of foundation 3.25m. Figure 4.1: Foundation type 1 - Type 2 – NH7: diameter 26.2 m; height of foundation base 2.6m; height of pedestal 0.65m; total height of foundation 3.25m. Volume 1.1 – Chapter 4 4-3 Nhon Hoi Wind farm project – Phase I Technical Design Figure 4.2: Foundation type 2 Detail description shall be presented in “Volume 1.1A Description of turbine foundation” 4.4. TECHINCAL REQUIREMENT FOR HARDSTANDS 4.4.1. The load-bearing capacity of the internal roads, the crane hardstand and the working ares Figure 4.3: Typical laydown for asembly and installation The crane hardstand areas must have a load capacity of 2 kg / cm², transmitted by the main crane supports. All internal roads shall be constructed with a minimum asphalted width of 4.5 m. The requirements for access routes, internal roads and crane hardstand areas are often intended to ensure that cranes and heavy vehicles can safely access and work at wind turbine foundations. These requirements must be complied with in all weather conditions. 4.4.2. Wind turbine foundation area During installation of the crane boom and WTGS, distance between foundation and crane is more than 24 m, depending on the WTGS and crane configuration. Where Volume 1.1 – Chapter 4 4-4 Nhon Hoi Wind farm project – Phase I Technical Design backfilling is required as part of the foundation design, such backfilling may in some cases only be completed once the WTGS has been installed. A gravel path shall be installed between the crane pad / interal road and the foundation, around the tower in order to ensure safe access of the WTGS without any danger. 4.4.3. Site office area This area shall be leveled and constructed to a maximum slope of 2% and paved with clean, fine gravel or equivalent. Construction contractor and supplier shall place containers, toilets, equipment and parking in this area. This area shall be located outside the crane working area to avoid the risk of falling objects. If this is not possible, special procedures should be considered, such as evacuation during crane lifting. 4.4.4. Crane pad The crane hardstanding areas shall be constructed for both wheel-mounted and crawlermounted cranes can be used. The requirements of the crane hard standing / working areas are different due to tower length and hub heights. Any changes below are only allowed with the approval of the supplier's representative: - The entire length and width of the crane hardstand surfaces shall be constructed with slope 0% - maximum 0.5%. - Crane hardstand are must have loading capacity of 2 kg / cm² over the entire yard area. - The Supplier points out that crane hardstands must be constantly monitored, in particular during adverse weather conditions. Any required repairs must be directly carried out during the installation phase of the project. he crane pads will be required to be re-checked and repaired where necessary. Also the levelness of for the crane pads will be required to be re-checked and re-instated where necessary. - Top Soil and obstacles shall not be deposited around the crane pad and along the site road. This area is required as working area and for assembly of the crane boom. Also any overhanging tree branches or cables are to be removed from the crane construction area. - In order to avoid contaminating the wind turbine equipment, a 2 m wide gravel path must be constructed from the crane pad/site road to the WTGS and around the tower. Volume 1.1 – Chapter 4 4-5 Nhon Hoi Wind farm project – Phase I Technical Design - A working area on the right or left of the crane hard standings shall be used for assembly of WTGS components and storage of the turbine components. - These areas shall be free and clear of obstacles that would prevent cranes movement over them, to stage components and assemble WTGS. - The crane manual for the particular machine actually used on the project must be consulted to verify dimensional and bearing requirements prior to the performance of any move or lift. Compaction requirements must be checked prior to mobilization of the crane. Any additional design requirements such as working area for construction machines; road or hardstand area; Drainage and reinforcement for roads and cranes are added according to specific requirements and topographic situation. 4.4.5. Delivery and storage the turbine components Tower sections: Delivery and storage will take place on the designated open spaces next to the crane hard standing. This area should be prepared so that it is walkable and can be used by an all-terrain forklift. The surface must absorb a surface pressure of at least 2 kg/cm². The Supplier or the assigned assembly company will provide appropriate plates for load distribution. Naccle, hub, etc: Delivery and storage shall take place on the hardstand area next to the interal road. Blades, rotors: Delivery and storage shall take place on the hardstand area next to the interal road. 4.4.6. Crane boom assembly requirements This area needs to be accessible for the assisting crane which will always be required. The assisting crane will also require a plain area beside the site road, or along the direction chosen for the assembly of the main boom. The requirements for crane boom assembly listed below. If the following conditions cannot be met, the other options of the project must be discussed and approval. In general, the followings can be noted about the boom assembly area: - The assembly area must be accessible to all off-road forklifts. - In forestry areas the minimum dimensions must also be considered in the vertical direction to ensure that all trees and cables shall be removed from the crane working area. - All crane hardstand areas: Load capacity of the ground is not less than 2 kg / cm². Volume 1.1 – Chapter 4 4-6 Nhon Hoi Wind farm project – Phase I Technical Design 4.4.7. Crane boom assembly The areas for the auxiliary crane shall be cleared and flat. This needs to be prepared and serviceable by an off-road forklift. Depending on the crane boom length, support surfaces to be used as abutments are required underneath the crane mast. These surfaces and positions differ for each crane mast configuration and can only be provided once the crane technology has been determined. In general, the following does apply: the higher the abutment, the greater the base area. Depending on the crane boom length, there are support surfaces for the boom installation. These surfaces and locations of auxiliary crane differ for each crane configuration and can only be correct once the crane technology has been approved. In general, the following applies: the taller the crane boom, the larger the support area. 4.5. O&M BUILDING AREA 4.5.1. Office house This is one-storey house, plan dimension (17.5x13.7) m2. Office house include the function room as follow: Meeting room, Technology room, Expert room, General room…. Foundation structure shall isolated footing foudations. Columns, beams, roofs shall reinforced concrete grade B20 (M250), aggregate size 1x2cm, casted in place. Wall shall be made of un-burnt brick with cement mortar M75. External wall and internal wall shall be plastered mastic, applied emulsion paint. Ceramic size 400x400 shall be tiled on the floor. The door and window shall made of aluminium frame, glass thickness 5mm. Reinforced concrete roof floor with sheet metal heat resistant. 4.5.2. Canteen house This is one-storey house, plan dimension (9.2x12.0) m2. Foundation structure shall isolated footing foundations. Columns, beams, roofs shall be made of reinforced concrete grade B20, aggregate size 1x2cm, casted in place. Wall shall be made of unburnt brick with cement mortar M75. External wall and internal wall shall be plastered mastic, applied emulsion paint. Ceramic size 400x400 shall be tiled on the floor. The door and window shall be made of aluminium frame, glass thichness 5mm. Reinforced concrete roof floor with sheet metal heat resistant. 4.5.3. Tenement house This is one-storey house, plan dimension (13.5x27.5) m2. Foundation structure shall isolated footing foundations. Columns, beams, roofs shall be made of reinforced concrete grade B20, aggregate size 1x2cm, casted in place. Wall shall be made of unburnt brick with cement mortar M75. External wall and internal wall shall be plastered mastic, applied emulsion paint. Ceramic size 400x400 shall be tiled on the floor. The door and window shall be made of aluminium frame, glass thichness 5mm. Reinforced concrete roof floor with sheet metal heat resistant. Volume 1.1 – Chapter 4 4-7 Nhon Hoi Wind farm project – Phase I Technical Design 4.5.4. Storage house This is one-storey house, plan dimension (6.6x23.3) m2. Foundation structure shall isolated footing foundations. Columns, beams, roofs shall be made of reinforced concrete grade B20, aggregate size 1x2cm, casted in place. Wall shall be made of unburnt brick with cement mortar M75. External wall and internal wall shall be plastered mastic, applied emulsion paint. The main door using automatic rolling steel door, width 4.6m and hight 5.0m. Reinforced concrete roof floor with sheet metal heat resistant. Make ground floor slope i=2% to drain oil on both sides, to prevent oil from spreading around when there is an incident. In the storage house, electricity storage room area (3.1x6.2) m2. The room wall shall be built with un-burnt brick cement mortar M75, the wall foundation shall be made of stone, the roof shall be made of reinforced concrete. The floor of the house shall be poured with reinforced concrete grade B25 (M350) aggregate size 2x4, 150cm thick, with air-conditioning. The door and window shall be made of aluminium frame, glass thichness 5mm. 4.5.5. Waste house This is one-storey house, plan dismension (5.0x5.0) m2. Wall foundation and reinforcing concrete bracing grade B20 (M250) agg. 1x2cm, steel columns shall be on the concrete foundation. Cover fences wire B40 with height of 1.5m. Floor shall be mad of concrete B20 (M250) agg. 1x2cm thickness 150mm. Around the floor, wall with height of 100mm shall be built to prevent the soil from spreading, and make slope of i=2% on floor. 4.5.6. Guard house This is one-storey house, plan dimension (2.8x2.8) m2. Foundation structure shall isolated footing foundations. Columns, beams, roofs shall be made of reinforced concrete grade B20, aggregate size 1x2cm, casted in place. Wall shall be made of unburnt brick with cement mortar M75, wall foundation shall be made of stone. Ceramic size 400x400 shall be tiled on the floor. The door and window shall be made of aluminium frame, glass thichness 5mm. 4.5.7. Garage This is one-storey house, plan dimension (4.0x2.8) m2. Foundation structure shall isolated footing foundations casted in-place reinforced concrete with grade B20, agg. 1x2cm. Ground floor shall be made of reinforced concrete grade B25, agg. 2x4cm, casted in place, thickness 150mm. Frame shall be made of galvanized tubular steel, with painting layers include 02 primer layers and 01 finished coat layer, roof slope at on side and using galvanised purlin. Volume 1.1 – Chapter 4 4-8 Nhon Hoi Wind farm project – Phase I Technical Design 4.5.8. Water tank support structure Foundation structure shall isolated reinforcing foundation grade B20 (M250) agg. 1x2cm. Upperstructure shall be made of galvanized steel. Plan dimension (4.0x5.0)m2, height of structure is 8m. 4.5.9. Ground water reservoir The tank shall be made of reinforcing concrete grade B20 (M250) agg. 1x2cm. The capacity of tank is (2.1x2.6x1.1)m3. 4.5.10. Water supply and drainage system - Water supply system: Water for domestic use shall be provided from well underground water. After discharged water from the domestic water system shall be stored in the ground water reservoir and pumped to the inox water tank to serve for the control house and guard house. Before use, water must be tested for physicochemical and microbiological criteria according to QCVN 01 & 02: 2009/BYT. - Drainage system: Rainwater is spilled over the surface of the concrete yard towards the back of the house. - Watsewater: Fertilizer drainage system + primary compartment of the toilet compartment, domestic drainage system inlet to the tank of the toilet, The dishwashing water system before flowing into the tank will be passed through the grease extraction tank. 4.5.11. Gate – fence, internal roads 4.5.11.1. Gate – fences - Gate: The main gate shall be designed as a sliding door on steel rails, the width of 7.5m, driven open and closed by electric motors. Gate shall be made of shape steel and flat steel painted rust layer and color layer. Gate pillar shall be made by reinforced concrete B20 (M250) agg. 1x2. - Fences: Column of fences shall be made by reinforced concrete B20 (M250) agg. 1x2, size 150x150, array 2.5m. Wall of fences shall be made by steel wire B40 thichness 3mm, height 2m. - The total length of the gate and fence: 200m. 4.5.11.2. Yard and internal roads - The structure of the yard and the internal road surface shall be made of concrete B25, agg. 2x4cm, thichness 150mm, make slope i = 2%. Area of Yard and internal road: 1301.26 m2. Volume 1.1 – Chapter 4 4-9 Nhon Hoi Wind farm project – Phase I 4.6. Technical Design TECHINCAL INFRASTRUCTURE The main technical infrastructure of the project includes: 4.7. - The internal road system connects the O&M building area and the Substation for the plant operation and maintenance. Designed to ensure a slope and a curvature radius for the transport of materials and equipment. (i) The road system connects the O&M building area with the local road; (ii) The internal road system connect the O&M building and the turbine towers with the alphalted width of 4.5m, the surface of the road is paved with asphalt concrete. Details are referred to section 4.7. - Electricity supply system for construction and daily activities: Power source for construction shall be taken from local power source and diesel generator of contractor. - Water supply system for the plant: Water for construction and daily activies shall be taken from the local water supply unit and by well underground water in the substation and O&M building area. The water source on the site must meet quality requirements consistent with the technical and hygiene standards. Water for the construction work such as mixing concrete, mixing mortar, washing stone and gravel, casting reinforced concrete structures, building bricks, plastering, must be clean, must not contain grease and acids. Water for living must be pure, clean, free of microorganisms, up to the standards of domestic water prescribed by the Ministry of Health. - Other technical infrastructure includes: Access road to the area of the O&M building and substation: A traffic route connecting from the area of the O&M building and substation to the local traffic works. SOLUTIONS FOR ROAD PART 4.7.1. Overview of the road system 4.7.1.1. Main features of the road system The transport of concrete, wind turbine equipment, as well as the transport of cranes, along with their attached components, need to be carried out by heavy trucks, super-long vehicles, super-heavy vehicles. Therefore, the road system needs to meet the minimum requirements related to the transportation of materials and equipment such as the load of the road, the width of the road, the curve radius of the road, ... transportation and installation work at each wind turbine location as well as operation and maintenance after the plant is put into operation. 4.7.1.2. Standard apply Current design standards for highways in Vietnam. Volume 1.1 – Chapter 4 4-10 Nhon Hoi Wind farm project – Phase I Technical Design - Highway − Specifications for design : TCVN 4054-2005 - Calculation of flood flow characteristics : TCVN 9845:2013 - Flexible pavement - Requirements and guidelines designed - Temporary regulations on the design of regular concrete pavement with joints in : 22 TCN 211-06 the construction of transport works is issued together with Decision No.3230/QĐ-BGTVT dated 14/12/2012 of the Ministry of Transport. - Bridge design standard : 22 TCN 272-05; TCVN 11823:2017 - National Technical Regulation on Traffic Signs and Signals: QCVN 41:2019/BGTVT. 4.7.1.3. Scale of design The internal road system is designed with a scale equivalent to that of the mountainous grade VI road according to the TCVN 4054-2005 standard, with the following main parameters: - Speed of design: V = 20 km/h. - Width of the roadbed: 6.0 m; inside: + Width of pavement: 2 sides x 2. 5 m = 5.00 m (with widening in the curve, ensuring vehicle width requirements as recommended by some equipment suppliers, refer to some projects that have been implementing). + Width of shoulder: 2 sides x 0.5 m = 1.00 m (land shoulder). - Minimum radius Rmin = 30 m (ensure shipping equipment). - Maximum longitudinal gradient of imax = 10%; limited difficulty imax = 15% (due to difficult terrain). - Pavement structure design load: 12T for vehicles with single axle. - Modular elasticity required of the pavement structure: Eyc 100 MPa. - Construction load design: HL93. - Frequency of designing roadbeds and drainage Constructions: 4%. 4.7.2. Design Solutions 4.7.2.1. Design the layout Nhon Hoi Wind Farm Project – Phase 1 is connected to NH19B (at the existing intersection of the planned route to Nhon Ly), the route (Road D1) basically follows the planned route to Nhon Ly. The layout of the route is designed on the principle of ensuring design standards according to the procedures, rules and scale of the project, ensuring the vehicle runs Volume 1.1 – Chapter 4 4-11 Nhon Hoi Wind farm project – Phase I Technical Design safely and smoothly, minimizing the volume of construction and construction on road and secure requests from the equipment carrier and supplier. The roads in service of super-long and super-heavy vehicles for transporting turbine construction equipment should ensure that the route ground must ensure that these vehicles change smoothly at curved positions, following natural terrain to avoid excavation deep and deep embankment, minimize the sections with large longitudinal slope for convenient transportation. Nhon Hoi Wind Farm Project – Phase 1, it is expected to use a vehicle with a Lift truck to transport Blades with length L = 71m, so the internal roads are subject to the minimum radius Rmin = 30 m is guaranteed to be eligible for shipping. 4.7.2.2. Profile design Based on the results of hydrological survey and calculation, the longitudinal design ensures that the shoulder height of the road is at least 0.5m higher than the water level before the culvert (for terrain culverts): - Designing the maximum vertical slope of 15% to meet the transport requirements (it is necessary to ensure the requirements of the type of road surface for the large slope segments as recommended by some equipment suppliers); - Design profile along the terrain to reduce the volume of earthwork; - The connection is consistent with the existing roads; - Ensure convenient transportation; - Ensure design elevation at drainage culverts. Table 4.1: Summary table of internal road lengths road Length of road (km) Width of roadbed (m) Width of pavement (m) 1 Road D1 2.16 6.0 4.5 2 Road D2 1.85 6.0 4.5 Internal road 3 Road D3 2.23 6.0 4.5 Internal road 4 Road D4 0.68 6.0 4.5 Internal road 5 Road D5 0.18 6.0 4.5 Internal road Total 7.10 No. Name of Notes Access road (Road connecting with NH19B) 4.7.2.3. Cross section design Volume 1.1 – Chapter 4 4-12 Nhon Hoi Wind farm project – Phase I Technical Design Scale of cross section are proposed as follows: - Part of vehicle passed: 2 x 2. 5 m = 5.00 m (with superelevation design and expansion in the curves, ensuring the transport of super-long and superweight equipment). - Part of the land shoulder:2 x 0.5 m = 1.00 m. - Total: = 6.00 m. 4.7.2.4. Roadbed design Based on the geological survey data, the roadbed design solution is proposed as follows: - Embankment: + When the natural ground has a horizontal slope <20%, organic layer about 20cm thick must be excavated before embankment. + When the natural ground has a horizontal slope ≥20%, it is required to dig the grade about 2m wide before embankment. + The slope of the soil embankment is 1/1.5 (with turfing to protect the slope); the stone embankment is 1/1.0. + Compacted requires Kyc ≥ 0.95. - Excavation: + The slope of the excavation in layer 1: 1: 1.00. + The slope of the excavation in layers 2, 3, 4: 1: 0.75. + The slope of the excavation in layers 5: 1: 0.50. + Compacted requires Kyc ≥ 0.95. 4.7.2.5. Design of pavement structures Nhon Hoi Wind Farm Project – Phase 1 uses 02 types of pavement structures to meet the requirements of the type of road surface depending on the longitudinal slope the recommendations of some equipment suppliers: A. Structure A1 (applicable to segments with a longitudinal slope on the straight line >10%, and on the curve >7%): top-to-bottom pavement structure is as follows: Concrete pavement is calculated with a design single-shaft load of 10 tons (of which the heaviest shaft is designed to be 15 tons). The structure of the pavement from top to bottom is as follows: - Cement concrete M300, 1x2 stone, thickness 22cm. - Oil paper lining. Volume 1.1 – Chapter 4 4-13 Nhon Hoi Wind farm project – Phase I Technical Design - Graded aggregate of class I, thickness 18cm, Dmax = 25 mm, designed to be 30cm wider than the concrete pavement on each side. - Separation layer made of geotextile, using the type with tensile strength ≥ 25kN/m (separating Graded aggregate of class I layer with sandy base, only for segments passing sand base). - Capping layer K≥ 0.95. B. Structure A2 (applicable to segments with a longitudinal slope on the straight line ≤10%, and on the curve ≤7%): top-to-bottom pavement structure is as follows: The pavement is of Graded aggregate and Bituminous penetration, calculated for single-axle vehicles with axle load of 12T, minimum required elastic modulus: Eyc ≥100 MPa. The structure of the pavement from top to bottom is as follows: - Bituminous penetration 2 layer, standard 4.0kg/m2 (including penetration and stick bituminous standard 1.0 kg/m2). - Graded aggregate of class I (Dmax = 25mm), thickness 17cm (K≥ 0.98). - Graded aggregate of class II (Dmax = 37.5mm), thickness 18cm (K≥ 0.98). - Separation layer made of geotextile, using the type with tensile strength ≥ 25kN/m (separating Graded aggregate of class I layer with sandy base, only for segments passing sand base). - Capping layer K≥ 0.95. 4.7.2.6. Drainage works 4.7.2.6.1. Longitudinal ditch design - At the segments of excavation roads with vertical slope i ≤ 3%: design of trapezoidal longitudinal drainage ditches with dimensions: 0.40m deep; face above 1.20m; the bottom of 0.40m is not reinforced. - At the segments of excavation roads with vertical slope 3% < i ≤ 6% or the segments excavation through the sandy ground: design of trapezoidal longitudinal drainage ditches with dimensions: 0.40m deep; face above 1.20m; the bottom of 0.40m is reinforced with concrete B12.5 (M150), thickness 15cm. - At the sections of excavation roads with vertical slope i > 6%: design of trapezoidal longitudinal drainage ditches with dimensions: 0.40m deep; face above 1.20m; the bottom of 0.40m is reinforced with concrete B12.5 (M150), thickness 15cm. In these ditch segments, there are staggered energy Volume 1.1 – Chapter 4 4-14 Nhon Hoi Wind farm project – Phase I Technical Design dissipation edges 2m / location, energy dissipation edges with a thickness of 20cm. 4.7.2.6.2. Culvert design Design solutions for drainage culvert across roads are as follows: - Culvert is permanently designed with design load HL93. - The culvert aperture is based on hydrological data and area's topography. - Structure of pipe culvert: culverts are made by centrifugal rotation technology combined with vibration, culverts are made of reinforced concrete B22.5 (M300), the length of each culvert segments is from 2-4m. Culvert foundation, head walls is made of concrete B15 (M200); wing walls, reinforced of culvert yard by of mortared stonework B7.5 (M100). - Box culvert structure: culvert body is made of reinforced concrete M300. Culvert heads and foundation are made of concrete B15 (M200); wing walls, reinforced of culvert yard made of mortared stonework B7.5 (M100). 4.7.2.7. Intersection design At these positions, only the design of linked claws connecting the pavement; length, slope and radius of linked claws to ensure technical requirements and traffic safety; pavement structure made with the main road structure. 4.7.2.8. Traffic safety design Picket systems, signs, ... have the effect of guiding traffic and ensuring traffic safety. The shape, specifications, size, color and location of the traffic safety system are designed according to the “National Technical Regulation on Traffic Signs and Signals QCVN 41:2019/BGTVT”. 4.8. CIVIL SOLUTION FOR CABLE TRENCH The 22kV underground cable is connected from the turbine to the poles of 22kV overhead line. 22kV underground cable is arranged along the internal road, under the road shoulder. Underground cable warning pickets are arranged along the cable route and at the road crossings according to regulations. Medium voltage underground cables and communication cables are put in HDPE pipes of suitable cross section for protection. The structure of the cable trench includes sand layer, brick layer, warning tape, compacted soil layer K ≥ 0.95. At cable trenches crossing the road, underground cables and communication cables are put in steel pipes of suitable cross-sections and poured with concrete for mechanical protection outside. Volume 1.1 – Chapter 4 4-15 Nhon Hoi Wind farm project – Phase I Technical Design APPENDIX: LIST OF EQUIPMENT AND MATERIAL NO. ITEM A ELECTRICAL MATERIAL I WTG 1. WTG 5MW and full of accessories: UNIT QUANTITY Set 3 Set 3 NOTE - 0.69/22kV – 5.5MVA transformer; - RMU 22kV type 2 cabinets: 1 transformer cabinet, 1 feeder out; - Auxiliary systems: Controlprotection, communication, SCADA, auxiliary power, fire and fighting system, lightning and grounding system… 2. WTG 5MW and full of accessories: - 0.69/22kV – 5.5MVA transformer; - RMU 22kV type 3 cabinets: 1 transformer cabinet, 1 feeder in, 1 feeder out; - Auxiliary systems: Controlprotection, communication, SCADA, auxiliary power, fire and fighting system, lightning and grounding system… II WTG’s grounding system 1. Annealed bare copper wire 70mm2 m 1020 2. Galvanized steel wire 16 m 2700 3. Copper-plated steel rod Rod 144 4. Exothermic welding Pcs 240 5. Electric welding Pcs 300 6. Connecting steel bar Pcs 300 III Cable and fiber optic system Volume 1.1 – Appendix L=2.4m, D=0.022 PL-1 Nhon Hoi Wind farm project – Phase I Technical Design NO. ITEM UNIT QUANTITY 1. Underground cable – 22kV – Al 3x120mm2 m 1133 2. Underground cable – 22kV – Al 3x240mm2 m 1138 3. 1 phase 22kV terminal cable for 1x120mm2 Pcs 18 Cable termination 4. 1 phase 22kV terminal cable for 1x240mm2 Pcs 24 Cable termination 5. Fiber optic 24 core singlemode m 2000 6. HDPE 260/200 conduit m 1960 for 22kV underground cable 7. HDPE 65/50 conduit m 1960 for fiber optic cable 8. 200 Steel conduit m 40 for 22kV underground cable across road 9. 50 Steel conduit m 40 for fiber optic cable across road IV Power plant’s SCADA system 1. Power plant control - PPC System 01 2. Fiber optic switch System 02 3. SCADA’s computer System 01 4. Power generation prediction system System 01 B EQUIPMENT AND MATERIAL OF CONSTRUCTION PART I Hardstand area part 1. Volume of cutting organic layer m3 7280.09 2. Total volume of soil and rock excavation works: leveling, aggregates, drainages… m3 63593.22 3. Total volume of soil filling work m3 15551.66 Volume 1.1 – Appendix - NOTE Installed in 110kV substation PL-2 Nhon Hoi Wind farm project – Phase I Technical Design NO. ITEM UNIT QUANTITY 4. Gravel size Dmax=2.5cm spread the hardstand area, storage area,… m3 4472.31 5. Cement concrete grade M150 for drainage work m3 112.5 II O&M BUILDING PART (i) Infrastructure work 1. Leveling work: excavation volume m3 1612.8 2. Leveling work: filling volume m3 933.5 3. Reinforcement of slope by stone m3 323.0 4. Drainage work: trench excavation m3 1049.55 5. Drainage work: length of filter pipe PVCD60 m 191.0 6. Drainage work: geotextile m2 546.0 7. Gravel size 1x2 m3 50.0 8. Drainage ditch m3 43.2 (ii) Main structures in O&M building area 9. Office house house 1 10. Canteen house house 1 11. Tenement house house 1 12. Storage house house 1 13. Garage house 1 14. Guard house house 1 15. Water tank support structure set 1 16. Ground water reservoir tank 1 17. Gate, fence system 1 18. Flower parterre set 1 19. Waste house house 1 20. Water supply system system 1 21. Lighting and electrical supply system system 1 C NOTE INTERNAL ROAD Volume 1.1 – Appendix PL-3 Nhon Hoi Wind farm project – Phase I NO. ITEM Technical Design UNIT QUANTITY m 7,063 I LENGTH 1 Length of road II ROADBED 1 Road excavation m3 1.1 Excavation layer 1 m3 46,621 1.2 Excavation layer 2 m3 136,626 1.3 Excavation layer 3 m3 901 1.4 Excavation layer 4 m3 2,737 1.5 Excavation layer 5 m3 504 2 Ditch excavation m3 - 2.1 Excavation layer 1 m3 944 2.2 Excavation layer 2 m3 1,310 2.3 Excavation layer 3 m3 33 2.4 Excavation layer 4 m3 89 2.5 Excavation layer 5 m3 63 3 Road shaping excavation m3 - 3.1 Excavation layer 1 m3 3,891 3.2 Excavation layer 2 m3 6,320 3.3 Excavation layer 3 m3 95 3.4 Excavation layer 4 m3 355 3.5 Excavation layer 5 m3 70 4 Stripping, earth class of 2 m3 2,499 5 Stepped excavation, earth class of 3 m3 2,512 6 Roadbed earthfill; K≥ 0.95 m3 7 Roadbed rockfill; γ≥ 1.9 T/m3 m3 314 8 Compacted subgrade, thickness of 30cm; K≥0.95 m2 28,574 9 Sodding on embankment slope m2 11,110 10 Clearance m2 98,893 III PAVEMENT STRUCTURE Volume 1.1 – Appendix NOTE 28,210 PL-4 Nhon Hoi Wind farm project – Phase I Technical Design NO. ITEM UNIT QUANTITY 1 Concrete M300, 1x2 stone, thickness 22cm m3 4,269 2 Oil paper lining m2 21,540 3 Graded aggregate of class I, thickness 18cm, K≥ 0.98 m3 3,877 4 Bituminous penetration 2 layer, standard 4.0kg/m2 (including penetration and stick bituminous standard 1.0 kg/m2) m2 17,207 5 Graded aggregate of class I, thickness 17cm, K≥ 0.98 m3 2,925 6 Graded aggregate of thickness 18cm, K≥ 0.98 II, m3 3,097 7 Separation layers by Geotextile (on sand base) m2 13,488 IV CULVERT 1 Reinforced concrete pipe culvert Ø0.80m pcs/m 11/137.5 2 Reinforced concrete pipe culvert Ø1.00m pcs/m 4/58 3 Reinforced concrete box culvert 2x2.5x2m pcs/m 1/10 VI LINING DRAINAGE DITCH 1 Shaping excavation of ditch, earth class of 3 m3 2,646 2 Concrete M200 of longitudinal ditch, stone 2x4 m3 2,732 3 Concrete M200 of energy dissipation edge, stone 2x4 m3 27 VII LINING STEPS DITCH 1 Shaping excavation of ditch, earth class of 3 m3 90 2 Concrete M200 of ditch, stone 2x4 m3 98 class - - - VIII WATER STEPS 1 Shaping excavation of steps, earth class of 3 Volume 1.1 – Appendix NOTE m3 198 PL-5 Nhon Hoi Wind farm project – Phase I NO. ITEM Technical Design UNIT QUANTITY 2 Mortared stonework M100 m3 139 4 Blinding stone, thickness 10cm m3 13 IX TRAFFIC SAFETY 1 Picket pcs 1,580 2 Traffic signs (triangle) pcs 54 3 Direction signs pcs 3 4 Auxiliary signs pcs 24 Volume 1.1 – Appendix NOTE PL-6