$QJROD%ORFN± $JRJR,QWHJUDWHG:HVW+XE 'HYHORSPHQW3URMHFW $JRJR ,QWHJUDWHG:HVW+XE5)7, PTM YARD - WELDING BOOK FOR PLETS PIPING FABRICATION DESIGNED ASME B31.8 - INCONEL Kilusi Emmauel Kiala cn=Kilusi Emmauel Kiala, o=Saipem, ou=Yard Welding Engineer, email=KilusiEmanuel.Kial a@saipem.com, c=AO 2023.11.21 08:07:34 +01'00' P.P Angelo Carlota Digitally signed by Angelo Carlota DN: cn=Angelo Carlota, o=Petromar, ou=PTM, email=angelo.carlo@pe tromar.co.ao, c=US Date: 2023.11.21 15:42:37 +01'00' (;&2 ,VVXHGIRU&RPPHQWV .(.LDOD 0LJXHO0 $&DUORWD (;&2 ,VVXHGIRU&RPPHQWV .(.LDOD 6DQWKRV. $&DUORWD 'DWH 'HVFULSWLRQ 3UHSDUHG E\ &KHFNHG E\ $SSURYHG E\ 9DOLGLW\ 5HYLVLRQ 6WDWXV 1XPEHU 5HYLVLRQ,QGH[ &RPSDQ\ORJRDQGEXVLQHVVQDPH /&,$FWLYLW\&RGH /&,$2 3URMHFW FRGH Azule Energy Angola S.p.A &RQWUDFWRUORJRDQGEXVLQHVVQDPH &RQWUDFWRU $SSURYHG &RPSDQ\ $SSURYHG &RPSDQ\'RFXPHQW,' &;056 -RE1 &RQWUDFWRU'RFXPHQW,' )6$,:(/%2. 6 &RQWUDFW1 9HQGRU'RFXPHQW,' 9HQGRUORJRDQGEXVLQHVVQDPH 1$ )DFLOLW\ 6XE)DFLOLW\'HVFULSWLRQ $JRJR± ,QWHJUDWHG:HVW+XE5)7, 3URMHFWDQG6R:GHVFULSWLRQ $JRJR,QWHJUDWHG:HVW+XE'HYHORSPHQW 'RFXPHQW7LWOH 1$ 6XSHUVHGHV1 :(/',1*%22.)253/(763,3,1*)$%5,&$7,21 $60(% ,1&21(/ 6RIWZDUH0LFURVRIW:RUG 3XUFKDVH2UGHU1 6FDOH 6KHHWRI6KHHWV 6XSHUVHGHGE\1 3ODQW$UHD )XQFWLRQDO8QLW 1$ )LOH1DPH&;056B(;&2BGRF 7KLVGRFXPHQWLVSURSHUW\RI$]XOH(QHUJ\$QJROD6S$IRUPHUO\(QL$QJROD6S$ ,WVKDOOQHLWKHUEHVKRZQWR7KLUG3DUWLHVQRUXVHGIRUSXUSRVHVRWKHUWKDQWKRVHIRUZKLFKLWKDVEHHQVHQW Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A Validity Status Revision Number EX-CO 01 REVISION LIST EXCO00 Issued for comments EXCO01 Issued for comments HOLD RECORD This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Sheet of Sheets 2 / 13 Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A Validity Status Revision Number EX-CO 01 Sheet of Sheets 3 / 13 TABLE OF CONTENTS 1.0 1.1 1.2 1.3 2.0 2.1 2.2 3.0 3.1 3.2 3.3 INTRODUCTION ................................................................................................................................................ 4 DISCOVERY ........................................................................................................................................................ 4 INTEGRATED DEVELOPMENT CONCEPT ............................................................................................................... 4 SCOPE OF THE DOCUMENT .................................................................................................................................. 6 ABBREVIATIONS & DEFINITIONS ............................................................................................................... 7 ABBREVIATIONS ................................................................................................................................................ 7 DEFINITIONS ...................................................................................................................................................... 8 LIST OF REFERENCED DOCUMENTS ......................................................................................................... 9 COMPANY DOCUMENTS.................................................................................................................................. 9 CONTRACTOR DOCUMENTS........................................................................................................................... 9 INDUSTRY CODES & STANDARDS ...................................................................................................................... 9 4.0 PROJECT BASE MATERIALS ....................................................................................................................... 10 5.0 WELD IDENTIFICATION ............................................................................................................................... 10 6.0 BEVELING ......................................................................................................................................................... 11 7.0 FIT-UP ................................................................................................................................................................. 11 8.0 HI-LO MEASUREMENT .................................................................................................................................. 11 9.0 EQUIPMENT ...................................................................................................................................................... 12 10.0 REPAIR METHODOLOGY ............................................................................................................................. 12 11.0 REPAIR SEQUENCE ........................................................................................................................................ 12 12.0 WELDING MONITORING .............................................................................................................................. 12 13.0 WELDING QUALIFICTAION ......................................................................................................................... 12 14.0 NDT ...................................................................................................................................................................... 12 15.0 APPENDIX A – WPS ......................................................................................................................................... 13 16.0 APPENDIX B – WPQR ...................................................................................................................................... 13 This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A 1.0 INTRODUCTION 1.1 Discovery Validity Status Revision Number EX-CO 01 Sheet of Sheets 4 / 13 Agogo discovery is located into the West Hub part of the block 15-06, approximately 180 kilometres off the coast and about 20 kilometres west from the Ngoma FPSO (West Hub), which is in operation since November 2014. Water depth of the field is ranging from about 1650 to 1750 m. Ndungu field is located in the same block and approximately 10 km from Ngoma FPSO (West Hub) and close to the subsea systems of Mpungi Field, in a water depth of approximately 1100 m. Figure 1 - Agogo field location in Block 15/06 1.2 Integrated development concept Agogo Integrated West Hub development concept has been defined in order to maximize the exploitation of the reserves associated to the following fields: • Agogo Field; • Ndungu Fields; • All other WH area Fields. Agogo Field started its development and production with the Agogo Early Production Project (produced through Ngoma FPSO) subdivided into two phases: This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A Validity Status Revision Number EX-CO 01 Sheet of Sheets 5 / 13 • Phase 1 (i.e. Agogo EP Ph 1): Conversion of exploration well, Agogo-1, controlled from a semi-sub control vessel and connected to the existing West Hub network; • Phase 2 (i.e. Agogo EP Ph 2): Development of 3 wells (1OP + 1WI + 1GI) tied-back to the existing West Hub network. Ndungu Field started its development and production with the Ndungu Early Production Project (produced through Ngoma FPSO) subdivided into two phases: • • Phase 1 (i.e. Ndungu EP): Development of 2 wells (1OP + 1WI) tied-back to the existing West Hub network; Phase 2 (i.e. Ndungu Phase 2): Development of 2 wells (1OP + 1WI) tied-back to the existing West Hub network. The Agogo Integrated West Hub project will be instead developed through the following 3 main phases: Figure 2 - Agogo Integrated West Hub Phase 1 Figure 3 - Agogo Integrated West Hub Phase 2 Figure 4 - Agogo Integrated West Hub Phase 3 Each project phase will have different main steps and events that will mark the overall project targets: Phase 1 (production gathered by Ngoma FPSO) This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A • Validity Status Revision Number EX-CO 01 Sheet of Sheets 6 / 13 Ndungu Field development phase: the new Ndungu Field consist of the development of 9 production wells and 5 injection wells tied-back to Ngoma FPSO. Phase 2 (production gathered by Ngoma FPSO and Agogo FPSO) • Agogo Field development phase: the new Agogo Field development will be based on a long-term solution with a new FPSO and consists in the development of 12 production wells and 9 injection wells; • Agogo EP production will be diverted to Agogo FPSO as soon as possible, releasing Ngoma topside load, with the aim to accommodate Ndungu Field production; • Ndungu Field wells will continue production through Ngoma FPSO, along with the other West Hub fields wells, till the end of Ngoma FPSO life. Phase 3 (production gathered by Agogo FPSO) • West Hub tails phase: after the Ngoma FPSO disconnection, all production tails of West Hub area (Ndungu, Mpungi and Vandumbu) will be tied-in to Agogo FPSO in order to maximize the related production. 1.3 Scope of the document The purpose of this document is to identify the Welding Procedure Specifications to be applied at Petromar Ambriz Yard for the fabrication of: • Production PLET This welding book covers only ASME B31.8 welds qualified as per ASME IX. This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A 2.0 ABBREVIATIONS & DEFINITIONS 2.1 Abbreviations Validity Status Revision Number EX-CO 01 Sheet of Sheets 7 / 13 ASME American Society of Mechanical Engineers BM Base Metal (or Base Material) CRI Company Representative Inspector GTAW Gas Tungten Arc Welding MC Material controller NDT Non-Destructive Testing PLET Pipe-Line End Termination QC Quality Control Department RT Radiographic Testing RTP Recognize Third Party SMAW Shielded Metal Arc Welding SOW Scope Of Work VT Visual Testing WE Welding Engineer WOP Welding operative personnel (welders, tack welders and welding operators) WI Welding Inspector WPQR or PQR Welding Procedure Qualification Record WPS Welding Procedure Specification WQT Welder qualification tests WS Welding Supervisor WT Wall Thickness CJ Complete Joint Penetration BW Butt Weld ASME American Society of Mechanical Engineers BM Base Metal (or Base Material) HAZ Heat Affected Zone NDT Non-Destructive Testing PLET Pipeline End Termination This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A WPQ (WPQT/WPQR) Welding Procedure Qualification (Test/Report) PT Penetrant Testing RT Radiographic Testing SMAW Shielded Metal Arc Welding SOW Scope Of Work VT Visual Testing WI Welding Inspector WPS Welding Procedure Specification WT Wall Thickness 2.2 Validity Status Revision Number EX-CO 01 Sheet of Sheets 8 / 13 Definitions COMPANY CONTRACTOR PROJECT SUPPLIER SUPPLY SUBCONTRACTOR VENDOR WORK Azule Energy Angola S.p.A Consortium between Saipem SA, Saipem Luxembourg branch and Petromar Lda led by Saipem SA. means Angola Block 15/06 – Agogo Integrated West Hub Development Project. means SUBCONTRACTOR. means the GOODS and relevant SUPPLIER DOCUMENTS, together with the delivery thereof, the performance of the SERVICE and any tangible or intangible thing which arises out of or in connection with the performance of the SERVICES by SUPPLIER GROUP, to be provided by SUPPLIER/VENDOR in accordance with the provision of the corresponding PRUCHASE ORDER DOCUMENTS (which correspond to a part of the WORK subcontracted by CONTRACTOR to VENDOR). means any person, including any vendor or supplier, with whom CONTRACTOR has entered into any contract to provide any part of the scope of work, including any person at any tier with whom any SUBCONTRACTOR has further contracted any part of the scope of work, and their legal successor and assigns. means SUBCONTRACTOR. means all of the works and services to be performed by CONTRACTOR under the PROJECT as are more fully described in the CONTRACT including but not limited to the provision of all labour, facilities, equipment, services and works as may be reasonably inferred therefrom, as necessary for the stability, completion and safe, reliable and efficient operation of the FACILITY. This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A 3.0 LIST OF REFERENCED DOCUMENTS 3.1 COMPANY Documents Ref CPY Document No. [1] 18046.ENG.SSE.STD [2] 363010BXSH01264 3.2 Validity Status Revision Number EX-CO 01 Sheet of Sheets 9 / 13 Document Title API RP 17P RECOMMENDED PRACTICE FOR SUBSEA STRUCTURES AND MANIFOLDS SPECIFICATION FOR WELDING OF CARBON STEEL PIPE AND CRA CLAD OR LINED PIPE FOR PIPE-INPIPE SUBSEA FLOWLINE Revision 01 01 CONTRACTOR Documents Ref CTR Document No. CPY Document No. Document Title [3] 363009DXPTS3113 F10395-SAI-WEL-PROS3113 [4] 363009CXSTS3220 F10395-SAI-WEL-PROS3220 [5] 363009DXPTS3089 [6] 363009DXPTS3094 [7] 363009DXPTS3095 [8] 363009CBQBS3214 [9] 363009CBQBS3206 [10] 363009CXMRS3221 [11] 363009CXSTS3222 WELDING CONSUMABLE CONTROL PROCEDURE ALL SCOPE PTM YARD - WELDER QUALIFICATION PROCEDURE FOR PLET PIPING UNDER ASME IX VT (VISUAL TESTING) PROCEDURE - CRA SOW PT (PENETRANT TESTING) PROCEDURE – CRA SOW PTM YARD – RT (RADIOGRAPHIC TESTING) -CRA/CS SOW PTM YARD - QUALITY CONTROL PLAN WELDING OF PIPING CRA & CS PTM YARD - QUALITY CONTROL PLANPIPING (PLETS) PTM YARD - LIST OF WELDING OPERATORS PTM YARD -MANAGEMENT OF WELDING REGISTER (FMS) 3.3 F10395-SAI-NDT-PROS3089 F10395-SAI-NDT-PROS3094 F10395-SAI-NDT-PROS3095 F10395-SAI-WEL-ITPS3214 F10395-SAI-QUA-ITPS3206 F10395-SAI-WEL-LSTS3221 F10395-SAI-WEL-PROS3222 Revision 04 00 02 02 00 00 00 00 00 Industry Codes & Standards Ref CPY Document No. [12] ASME IV [13] ASME B31.8 [14] DNV RP B204 Document Title BOILER AND PRESSURE VESSEL CODE SECTION IX – WELDING, BRAZING AND FUSING QUALIFICATIONS GAS TRANSMISSION AND DISTRIBUTION PIPING SYSTEMS – ASME CODE FOR PRESSURE PIPING WELDING OF SUBSEA PRODUCTION SYSTEM EQUIPMENT This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Revision 2019 2019 2019 Vendor logo 4.0 Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A Validity Status Revision Number EX-CO 01 Sheet of Sheets 10 / 13 PROJECT BASE MATERIALS Tables 4.1 describes the material grades that have been selected for the fabrication of Inconel piping scope. Table 4.1: PLET Piping Location Material OD (mm) WT (mm) 2” (73.03) 6.35 Production (Inconel): PLET 5.0 • • • • • Pipe (N06625) Bend (N06625) Hot Stab (ASTM N06625) Gate Valve (ASTM N06625) Reducing Tee (ASTM N06625) WELD IDENTIFICATION Table 5.1: Production Plet Welds to be performed OD x WT (mm) Position Reducing Tee to Pipe 73.03 x 6.35 mm All Pipe to Bend 73.03 x 6.35 mm All Pipe to Pipe 73.03 x 6.35 mm All Pipe to Gate Valve 73.03 x 6.35 mm All Pipe to Hot Stab 73.03 x 6.35 mm All Supporting PQR ERSAI-P-095 Figure 5.1: Production This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A 6.0 Validity Status Revision Number EX-CO 01 Sheet of Sheets 11 / 13 BEVELING Beveling shall be done by machining or grinding. 7.0 FIT-UP Fit-up shall be done by tack welding as follows: Figure 7.1: Fit-Up Tack weld shall be removed progressively during root pass. The material of the tack bullets must be similar to the base metal. 8.0 HI-LO MEASUREMENT Open Gap Tool shall be used for the Internal Hi-Lo measurement. The instrumentation's accuracy shall be of +/- 0.1 mm. Each instrument shall be provided with its calibration certificate. Hi-Lo measurement shall be done after pipe fit-up but prior welding at 4 equidistant locations as indicated in Figure below: Figure 8.1: Measurement Location along the circumference Frequency : • • 100% for first 3 welds. Internal Hi-Lo measurements at the 4 locations indicated in Figure above, shall be recorded on the Internal Hi-Lo Records Report for each pipe joint (see template in Appendix). Then, based on the above measurements (i.e., if no measurements fall outside the acceptable tolerance), recording will be done on a random basis only (Hi-Lo measurements at the 4 locations indicated in Figure 10 on 10% of the joints). However, hi lo verification will be performed for all welds as part of the fit-up step of the ITP (without recording). Maximum internal Hi-Lo shall be as per WPS. This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A 9.0 Validity Status Revision Number EX-CO 01 Sheet of Sheets 12 / 13 EQUIPMENT All tools and equipment used (discs, wire brush, hand tools) shall be free from iron and specific to the material: - Inconel (UNS N06625) 10.0 REPAIR METHODOLOGY Due to the thicknesses on the Inconel 625 pipes, repairs are not allowed. If repairs are required, the weld will be cut and re-bevelled. 11.0 REPAIR SEQUENCE • Localization of the defect area. • Carry out cut-out of weld with removal of HAZ. To ensure the HAZ removal, the weld shall be cut back at least 6 mm into the base material measured from the OD cap weld toe. • VT to be performed after removal of HAZ, VT and PT to be performed after welding. 12.0 WELDING MONITORING Welding parameters will be monitored by means of Ammeter and Voltmeter by the QC Welding Inspectors or the project welding engineer(s). The following welding parameters will be provided in a report: • • Iave, Vave, TS based on actual ROL measured with a tape and recorded welding time. HI based on the above values and k factor based on according to EN1011-1. Volts, amps and travel speed ranges are given for guidance only. Heat-input range shall be fulfilled. 13.0 WELDING QUALIFICTAION Welders shall hold a valid certificate to perform the scope of work. All new welder qualifications will be done in accordance with project welder qualification procedure Ref. [3]. 14.0 NDT All NDT to be done in accordance with NDT Project procedure Ref. [4], [5] and [6]. This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Vendor logo Company Document ID Contractor Document ID Vendor Document ID 363009CXMRS3217 F10395-SAI-WEL-BOK-S3217 N/A Validity Status Revision Number EX-CO 01 15.0 APPENDIX A – WPS - AFF-PIP-AMSE-INCO 16.0 APPENDIX B – WPQR - 84-2021 BAR-PIP-12 This document is property of Azule Energy Angola S.p.A., formerly Eni Angola S.p.A. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent. Sheet of Sheets 13 / 13