Project No. E1219 NUMALIGARH REFINERY LIMITED NRL REFINERY EXPANSION PROJECT 95 KTPA Hydrogen Generation Unit (HGU) Assam (INDIA) Project Document Title: Electrical System Load Flow Study Project Document Number: E1219-HGU-EL-REP-0001 L&T Energy-Hydrocarbon Contract Reference Number: MTG-LT/01 DATED 08 FEB. 2023 Owner Client MPMC EPC Contractor Licensor 02-May-24 Date 0 Rev. : Numaligarh Refinery Limited : Matheson Hydrogen India Pvt. Ltd. : Technip Energies : Larsen & Toubro Ltd. : Topsoe A/S Issued for Information Description AHC SGP ANS Prepared By Reviewed By Approved By Disclaimer: This document contains confidential and/or proprietary information of LTHE and its affiliated companies. No part of this document, data, or information, issued for the captioned project or purpose, shall be used for other than the purpose for which this has been provided or disclosed to others or reproduced in any manner, except with the prior written permission of LTHE. E1219-HGU-EL-REP-0001 Page 1 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 Rev.0 02-May-24 Issue and Approval Record Issued Category Engineering Approval Code Procurement Construction [Code A or 1] - Approved Consent to proceed [Code B or 2] - Comments As Noted Information Enquiry Construction Work may proceed subject to incorporation of comments [Code C or 3] - Rejected Review Purchase Commissioning Revise and Resubmit. Work shall not proceed [Code D or 4] - Information Only Approval Void As-Built Does issue category require approval? Yes No E1219-HGU-EL-REP-0001 Accepted for information only Code: NA Date: Approver: Note: This approval does not relive the document ORIGINATOR any of his obligations and responsibilities under this Contract. Page 2 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 Rev.0 02-May-24 Revision Record Rev. Date Prepared By Reviewed By Approved By Revision Note / Description 0 25-April-24 AHC SGP ANS Issued for Information Note: A ‘vertical line with revision triangle in the left hand margin plus revised text in Blue colour’ identifies changes in the latest revision of document. Revision description A, B, C..... etc. identifies document during development stage for review, approval and enquiry; Revision description 0,1 ,2…..etc. identifies document if issued for information, or after approval if issued for purchase, construction, commissioning etc. R-X E1219-HGU-EL-REP-0001 Page 3 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 Rev.0 02-May-24 Contents 1.0 PURPOSE 5 2.0 ABBREVIATION 5 3.0 ETAP STUDY SCOPE 6 4.0 CODES, STANDARDS & REFERENCES 6 5.0 SOFTWARE 7 6.0 BASIS AND ASSUMPTIONS 7 7.0 ETAP LOAD FLOW ANALYSIS RESULT SUMMARY 10 8.0 CONCLUSION 10 9.0 ANNEXURES 11 E1219-HGU-EL-REP-0001 Page 4 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 1.0 Rev.0 02-May-24 PURPOSE The objective of carrying out the ETAP Load Flow Analysis for electrical system of Numaligarh Refinery limited Numaligargh Refinery Expansion Project is to know and verify various electrical parameters equipment /switchboard such as Loading, Voltage Profile and Power Factor etc. during different operating conditions of plant. 2.0 ABBREVIATION 1C : Single Core Cable 3C : Three Core Cable A : Ampere AC : Alternating Current BC : Bus Coupler C : Cable CT : Current Transformer DC : Direct Current DLL : Design Margin Lump Load DOL : Direct On Line EMLDB : Emergency Main Lighting Distribution Board EPMCC : Emergency Power cum Motor Control Centre ETAP : Electrical Transient Analysis Program FLC : Full Load Current FLL : Future Growth Lump Load NRL : NUMALIGARH REFINERY LIMITED HV : High Voltage (1000V < V ≤ 33kV) IC : Incomer IEC : International Electrotechnical Commission In : Intermittent JB : Junction Box kA : Kilo Ampere kV : Kilo Volt kVA : Kilo Volt Ampere kW : Kilo Watt LDB : Lighting Distribution Board LF : Load Flow LL : Lump Load LRC : Locked Rotor Current LV : Low Voltage (< 1000V) LTHE : Larsen & Toubro Hydrocarbon Engineering MCC : Motor Control Centre E1219-HGU-EL-REP-0001 Page 5 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 3.0 MLDB : Main Lighting Distribution Board MPDB : Main Power Distribution Board MS : Motor Starting MVA : Mega Volt Ampere MW : Mega Watt OCTC : Off Circuit Tap Changer PCC : Power Control Centre PDB : Power Distribution Board PF : Power Factor S : Standby SB : Switchboard SC : Short Circuit SLD : Single Line Diagram TR : Transformer UPS : Uninterruptible Power Supply W : Working Rev.0 02-May-24 ETAP LOAD FLOW STUDY SCOPE The Scope of Work for ETAP Load Flow Studies is limited to the following; Start Point: End Point: 4.0 Cable from 33kV Feeder of Upstream Substation No.10.-33kV Switchboard feeding 33kV Switchboard SS12-GIS-ICOG-401& SS12-GIS-ICOG-402 (Upstream substation to NRL Substation- SS12) Equipment within NRL CODES, STANDARDS & REFERENCES Standard / Document No. Description E1219-HGU-EL-ELL-0001 Electrical Load List E1219-HGU-EL-BOD-0001 Electrical Design Basis E1219-HGU-EL-SLD-0001 Overall Key Single Line Diagram E1219-HGU-EL-SLD-0003 Single Line Diagram for HV (6.6kV) Switchgear E1219-HGU-EL-SLD-0004 Single Line Diagram for PMCC-01 E1219-HGU-EL-SLD-0005 Single Line Diagram for Emergency EPMCC-01 E1219-HGU-EL-SLD-0006 Single Line Diagram for MCC-01 E1219-HGU-EL-REP-0001 Page 6 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 Standard / Document No. E1219-HGU-EL-SLD-0007 E1219-HGU-EL-SLD-0008 5.0 02-May-24 Description Single Line Diagram for ASB-01 Single Line Diagram for MLDB-01 E1219-HGU-EL-SLD-0009 Single Line Diagram for ELDB-01 E1219-HGU-EL-SCH-0001 HV Power & Control Cable Schedule E1219-HGU-EL-SCH-0002 LV Power & Control Cable Schedule SOFTWARE 6.0 Rev.0 Load Flow Analysis is carried out by using the ETAP Software of Version 20.6 (Operation Technology, Inc, USA) BASIS AND ASSUMPTIONS All equipment is modelled in ETAP based on Design SLDs and Load List. All the Motors have been Modelled for HV System & LV System. Rest of the Loads are modelled as per the Load List with Static/Motor Characteristics for the respective Switchboards. Following is Recommended for transformer in ETAP Load Flow Study Analysis; Power & Distribution Transformer Tap : +2.5% (The tap is increased to limit the over-voltage levels at 6.6kV switchboard & 415V PMCC Lighting Transformer Tap : +2.5% (The tap is decreased for to avoid Overvoltage) Transformer Impedance: Sr. No. 1.a 1.b 2.a E1219-HGU-EL-REP-0001 Transformer Tag % Impedance Make Power Transformer 7.08 % (As per Test Certificate) M/s. Voltamp 9 % (As per Test Certificate) M/s. Voltamp 6.51 % (As per Test Certificate) M/s. Voltamp SS12-TR-401 Power Transformer SS12-TR-402 Distribution Transformer SS12-TR-001 Page 7 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) E1219-HGU-EL-REP-0001 Rev.0 Transformer Tag % Impedance Make Distribution Transformer SS12-TR-002 6.71 % (As per Test Certificate) M/s. Voltamp Normal Lighting Transformer 4% (As per Datasheet) M/s. Automatic Electric LTD 4 % (As per Datasheet) M/s. Automatic Electric LTD Sr. No. 2.b ELECTRICAL SYSTEM LOAD FLOW STUDY 3.a SS12-TR-003 & 004 Emergency Lighting Transformer 3.b SS12-TR-005 & 006 Transformer Rating 02-May-24 : 33/6.9kV,8MVA, ONAN/ONAF : 6.6/0.433kV,2MVA,ONAN : 0.433KV/0.415,125kVA,ONAN :0.433KV/0.415,40kVA,AN DG Impedance : No tolerance on DG impedance Transient Reactance of generator (Xd') : 0.141 (As per Vendor Data; Make : M/S GOEL DG) Sub-Transient Reactance of generator (Xd") :0.113 (As per Vendor Data; Make : M/S GOEL DG) The following load contributions are considered in ETAP Study Analysis; Continuous : 100% Intermittent : 30% Standby : 10% The following Lump Load(Future) contributions are modelled as per Load List data in ETAP Study Analysis; Sr. No. SWB Tag No. Voltage % of Motor Load % of Static Load 1 SS12-SGR-201A 6.6kV 90% 10% 2 SS12-SGR-201B 6.6kV 90% 10% E1219-HGU-EL-REP-0001 Page 8 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 Rev.0 02-May-24 Sr. No. SWB Tag No. Voltage % of Motor Load % of Static Load 3 SS12- PMCC-001A 415V 90% 10% 4 SS12- PMCC-001B 415V 10% 90% 5 SS12-EPMCC-001A 415V 80% 20% 6 SS12-EPMCC-001B 415V 80% 20% 7 SS12- MCC-001A 415V 90% 10% 8 SS12-MLDB-001A 415V 10% 90% 9 SS12-MLDB-001A 415V 10% 90% 10 SS12-ASB-001A 415V 20% 80% 11 SS12-ASB-001B 415V 20% 80% Refer Annexure-3.0 for overall load summary. The following data is considered as Source Input at 33kV Switchboard NRL-SS12-GIS-ICOG-401 & SS12-GIS-ICOG-402 Sr. No. Voltage SWB Tag No. Max SC Current Min SC Current 1 33kV UPSTREAM S.S No.10 (Desc.: 33kV Switchboard) 33.5 KA 1915 MVAsc X/R=16.5 6.0 kA 343 MVAsc X/R=25 Remark Values taken from the Case Study 17 Page No.23 Max & Min SC current values are taken from available project data as informed by NRL. Max SC Current Value is used for ETAP SC Study and Min SC Value is used for ETAP LF/MS Studies. Major Equipment Details are summarized in Annexure-1.0 Transformer ratings are found suufficient on peak load as per load list and future load growth. Electrical Load List in Annexure 2.0 Power cable length is taken from Cable Schedule and parameters from Vendor Cable Data (HV Cable From M/S POLYCAB & LV Cable From KEI ). E1219-HGU-EL-REP-0001 Page 9 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 Rev.0 02-May-24 Cable sizes and runs are as per approved cable sizing calculations and changes in cable sizes required for maintaining sufficient voltage during motor starting are incorporated. ETAP configurations considered for load flow are summarized in Annexure-3.0. The following are allowable voltage variations as per Electrical Design Basis (Doc No. E1219-HGU- EL-BOD-0001) 7.0 33kV : ±10% 6.6kV : ±6% 415V : ±6% The following is considered for carrying out ETAP Load Flow Study Analysis in each configuration; Study Case Tag : LF Loading Category : Normal Transformer Impedance Tolerance : Individual Result Allowable Limits Trafo Loading : 100% (Critical) Bus Over Voltage : 110% (Critical) Bus Under Voltage : 90% (Critical) ETAP LOAD FLOW ANALYSIS RESULT SUMMARY 8.0 ETAP Load Flow Analysis Results are summarized in Annexure-4.0 and the following are attached for each configuration results; ETAP Single Line Diagram ETAP Output Report CONCLUSION Refer Annexure-3.0, ETAP Load Flow Study result gives the following conclusion; Switchgears Bus Loadings are normal. No overloading observed. Voltage range at each bus are in within limit. When the capacitors are Switched ON and transformer tap is at normal position, there is overvoltage of approximately 1% at 6.6kV Bus and 415V PMCC-001& Downstream Switchboards. Hence 8 MVA(33/6.9KV) Transformers and 2 MVA(6.6/0.433Kv) Transformers are recommended to be at +2.5% tap & this tap is used for all the system studies like SC & MS. Transformers loading are found to be OK under all conditions. E1219-HGU-EL-REP-0001 Page 10 of 11 95 KTPA Hydrogen Generation Unit (HGU) Numaligarh, Assam (INDIA) ELECTRICAL SYSTEM LOAD FLOW STUDY E1219-HGU-EL-REP-0001 9.0 Rev.0 02-May-24 ANNEXURE 9.1 Annexure-1.0: Major Equipment Details 9.2 Annexure-2.0 : Electrical Load List 9.3 Annexure-3.0 : Overall Configuration Summary 9.4 Annexure-4.0 : ETAP Load Flow Results Summary 9.5 Annexure-5.1a: ETAP Load Flow SLD (Case-1) 9.6 Annexure-5.1b : ETAP Load Flow Report (Case-1) 9.7 Annexure-5.2a : ETAP Load Flow SLD (Case-2) 9.8 Annexure-5.2b : ETAP Load Flow Report (Case-2) 9.9 Annexure-5.3a : ETAP Load Flow SLD (Case-3) 9.10 Annexure-5.3b : ETAP Load Flow Report (Case-3) 9.11 Annexure-5.4a : ETAP Load Flow SLD (Case-4) 9.12 Annexure-5.4b : ETAP Load Flow Report (Case-4) 9.13 Annexure-5.5a : ETAP Load Flow SLD (Case-5) 9.14 Annexure-5.5b : ETAP Load Flow Report (Case-5) 9.15 Annexure-5.6a : ETAP Load Flow SLD (Case-6) 9.16 Annexure-5.6b : ETAP Load Flow Report (Case-6) 9.17 Annexure-5.7a : ETAP Load Flow SLD (Case-7) 9.18 Annexure-5.7b : ETAP Load Flow Report (Case-7) 9.19 Annexure-5.8a : ETAP Load Flow SLD (Case-8) 9.20 Annexure-5.8b : ETAP Load Flow Report (Case-8) 9.21 Annexure-5.9a : ETAP Load Flow SLD (Case-9) 9.22 Annexure-5.9b : ETAP Load Flow Report (Case-9) 9.23 Annexure-5.10a: ETAP Load Flow SLD (Case-10) 9.24 Annexure-5.10b: ETAP Load Flow SLD (Case-10) 9.25 Annexure-6 : Reference Vendor Document E1219-HGU-EL-REP-0001 Page 11 of 11