Uploaded by Ha Duong

029 SBM Offshore Hot Work

advertisement
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
This Code of Practice is identified as a critical operation.
Critical operations are those, which have a significant risk of
causing major injuries or illness to people, or damage to the
Marine Unit, cargo, other property and/or the environment.
Critical Ops
This COP does not include those work procedures that are not Hot Work, but are developed offshore
for review only by local Shore Base Management and the Production Management Office.
Issue Date
Revision Date
Number of
pages
01/03/ 04
-
30
-
21 March 05
1
Written by
Checked by
Approved by
S. Holtby
HSE Manager
I.Moss
FPSO Ops Manager
D. Montgomery
Production Ops Manager
S. Holtby
HSE Manager
A. Douglass
Safety Engineer
D. Montgomery
Production Ops Manager
REVISION STATUS / SUMMARY OF CHANGES
STATUS
REVISED CHAPTERS
Issue 01
Revision 01
REVISION DESCRIPTION
For implementation
2.9 (a) – page 12
Amended
-1-
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
TABLE OF CONTENTS
GENERAL INTRODUCTION .................................................................................................................. 4
DEFINITIONS.......................................................................................................................................... 4
1.0
PART 1 - HW IN HAZARDOUS AREAS - APPROVAL AUTHORITY LEVELS ................... 5
1.1
INTRODUCTION ................................................................................................................... 5
1.2
CAT 1A HOT WORK ............................................................................................................. 5
1.2.1
1.3
CAT 1B HOT WORK ............................................................................................................. 5
1.3.1
1.4
2.0
APPROVAL .................................................................................................................... 6
CAT 2 HOT WORK................................................................................................................ 6
1.4.1
1.5
APPROVAL .................................................................................................................... 5
APPROVAL .................................................................................................................... 6
DOCUMENTATION............................................................................................................... 6
PART 2 – HOT WORK IN CARGO & BALLAST TANKS ..................................................... 8
2.1
SCOPE AND PURPOSE....................................................................................................... 8
2.2
OBJECTIVES ........................................................................................................................ 8
2.3
GENERAL ............................................................................................................................. 8
2.4
WORK APPROVAL ............................................................................................................... 8
2.5
GENERAL NOTE .................................................................................................................. 9
2.6
ORGANISATION AND RESPONSIBILITIES ........................................................................ 9
2.7
TANK PREPARATION FOR HOT WORK .......................................................................... 10
2.8
WELDING MACHINES / ELECTRICAL EQUIPMENT........................................................ 11
2.9
LIVE BULKHEADS (HYDROCARBONS PRESENT IN THE ADJACENT TANK).............. 12
2.10
TANK HOT WORK SAFETY PROCEDURES................................................................. 12
2.11
FIRE WATCHERS ........................................................................................................... 14
2.12
EMERGENCY PLAN ....................................................................................................... 14
2.13
COMMAND AND CONTROL OF EMERGENCY SITUATIONS ..................................... 15
2.14
SAFETY EQUIPMENT REQUIRED TO COMPLY WITH THIS CODE OF PRACTICE.. 15
-2-
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
3.0
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
PART 3 - GENERAL HOT WORK IN HAZARDOUS AREAS ............................................. 17
3.1
PURPOSE ........................................................................................................................... 17
3.2
INTRODUCTION ................................................................................................................. 17
3.3
RESPONSIBILITIES ........................................................................................................... 18
3.4
3.3.1
O.I.M./UNIT SUPERINTENDENT .................................................................................... 18
3.3.2
AREA AUTHORITY ....................................................................................................... 18
3.3.3
FPSO / FSO SAFETY OFFICER ................................................................................... 18
3.3.4
INDEPENDENT SAFETY CONSULTANT ........................................................................... 18
3.3.5
SHORE BASE UNIT OPERATIONS MANAGER.................................................................. 18
3.3.6
HSE MANAGER .......................................................................................................... 19
3.3.7
DISCIPLINE AUTHORITY ............................................................................................... 19
3.3.8
AREA OPERATIONS MANAGER ..................................................................................... 19
3.3.9
PRODUCTION OPERATIONS MANAGER ......................................................................... 19
HOT WORK PROCEDURE................................................................................................. 19
APPENDIX 1 – HOT WORK PROCEDURE TABLE ........................................................................ 21
APPENDIX 2 - REVIEW AND APPROVAL TABLE ......................................................................... 29
-3-
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
GENERAL INTRODUCTION
This Code of Practice covers:
Part 1 Hot work in Hazardous Areas – Approval Authority Levels
Part 1 clarifies the approval authority levels for hot work taking place in hazardous areas on
board the company fleet of Marine Units. The approval level relates to:
(a)
the type of hot work that can be approved by the O.I.M./Unit Superintendent in
conjunction with the Unit Operations Manager in the local Shore Base, without
approval from the Production Management Office in Monaco, and
(b)
the type of hot work that has to be approved by the Production Management Office in
Monaco, once approved by the O.I.M./Unit Superintendent and the Unit Operations
Manager in the local Shore Base.
Part 2 Hot work in Cargo and Ballast Tanks
Part 2 covers the procedures relating to carrying out hot work in cargo or ballast tanks. Part
2 activities have to be approved by the Production Management Office in Monaco.
Part 3 General Hot work in hazardous Areas
Part 3 covers the general hot work procedures that take place on a Marine Unit; this part
forms an integral element of Part 1 & Part 2 of this Code of Practice.
DEFINITIONS
Area authority:
The person in charge is responsible for a work location on board (see section 3, PTW,
Health & Safety of Environmental Manual).
Hazardous Area
Those areas identified on the Marine Unit Hazardous Area Layout drawing, i.e. Zones 1 & 2.
Hot work
Category 1 - Burning, welding, grinding, any naked flame in hazardous areas. This category
is further defined into types 1A and 1B.
Category 2 - opening junction boxes, using pneumatic chipping hammers, pneumatic wire
brushes, running temporary diesel engines, using impact wrenches, pneumatic drills, using
non I/S equipment in hazardous areas.
-4-
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
Safety Consultant
1.0
PART 1 - HW IN HAZARDOUS AREAS - APPROVAL AUTHORITY LEVELS
1.1
INTRODUCTION
When hot work takes place on board a Company Marine Unit within a hazardous area, as
defined on the Marine Unit Hazardous Area drawing, specific procedures will apply. This
Code of Practice defines the procedures.
1.2
CAT 1A HOT WORK
This is open flame work that is less than 5m from any hydrocarbon inventory, or any pipe
work that could contain hydrocarbons either during normal operations, or in an emergency
situation.
This is open flame work that is less than 10m from a flange or fitting associated with
hydrocarbons.
This is open flame work that is a distance of 20m from an operating gas compressor. All
open flame hot work within 20m of an operating gas compressor shall be subject to a Hazid
conducted in Production Management office, reviewed by the HSE Manager.
Includes tank hot work.
1.2.1
Approval
O.I.M./Unit Superintendent, Shore Base Unit Operations Manager, or Shore Base
Manager, Production Management Discipline Authority, Area Operations Manager,
HSE Manager, and Production Operations Manager.
1.3
CAT 1B HOT WORK
This is open flame work that is more than 5m from any hydrocarbon inventory.
This is open flame work that is more than 10m from any flange or fitting associated with
hydrocarbons.
This is open flame work that is more than 20m away from a running gas compressor.
-5-
21/03/05
PART 1 – HW IN HAZAROUS AREAS
An additional Safety Advisor, not the Marine Unit Safety Officer, a person who reports
directly to the O.I.M./Unit Superintendent and has the overall remit of ensuring that the work
is proceeding in accordance with the provisions of the PTW, risk assessments, this COP and
good industrial safe working practices. He will ensure that the approved Hot Work Procedure
is being complied with.
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
1.3.1
07
90
029
ISSUE 01
REV. 01
Approval
O.I.M./Unit Superintendent and the Shore Base Unit Operations Manager, or Shore
Base Manager. Production Management Office will however be notified of the
proposed hot work.
CAT 2 HOT WORK
Where a doubt arises as to whether an activity comes under the definition of Category 1 or 2
hot work, the HSE Manager is to be contacted.
1.4.1
Approval
O.I.M./Unit Superintendent only.
1.5
DOCUMENTATION
The O.I.M./Unit Superintendent will initiate a Risk Assessment for the task, and raise a
normal Hot Work Permit. Gas tests, and where relevant fire watchers (i.e. running diesel
engines) will be in place. Tool Box talks will apply.
-6-
21/03/05
PART 1 – HW IN HAZAROUS AREAS
1.4
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
Hot work Flow Chart
PART 1 – HW IN HAZAROUS AREAS
Open Flame Hot work to
take place in a Hazardous
Area
Less
than 5m from any
hydrocarbon inventory, or
any pipe work that could
contain hydrocarbons either
during normal operations, or
in an emergency situation
YES
Less
than 10m from a
flange or fitting associated
with hydrocarbons
CAT
1A
HW within 20m of
operating compressor
an
NO
CAT
1B
Approval
O.I.M./Unit Supt.
+
Shore Base Unit
Operations
Manager or Shore
Base Manager
+
Production
Management
Office in Monaco
Approval
Tank Hot work involved
-7-
O.I.M./Unit Supt.
+
Shore Base Unit
Operations
Manager or
Shore Base
Manager
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
2.0
PART 2 – HOT WORK IN CARGO & BALLAST TANKS
2.1
SCOPE AND PURPOSE
ISSUE 01
REV. 01
The purpose of this Code of Practice is to ensure that all parties involved in hot work being
carried out on board the Marine Unit cargo/ballast tanks are fully aware of the standards that
must be referred to when producing the onboard fuel procedures. Part 3 of this Code of
Practice is to be referred to.
The responsibility to ensure that the scope and purpose of this CoP is achieved rests with
the O.I.M./ Unit Superintendent, it is to be read and understood by all personnel involved in
the work.
2.2
OBJECTIVES
To perform all work in a manner such as to ensure the safety of all personnel, equipment
and the Marine Unit.
To maintain safe production and/or offloading of oil without interruption whenever possible
throughout the work to the satisfaction of the O.I.M./Unit Superintendent.
2.3
GENERAL
(a)
2.4
All hot work taking place in tanks on the Marine Unit will be clearly defined by the O.I.M./Unit
Superintendent, appropriate senior staff, and the Safety Officer in the form of a written work
scope complemented by detailed attachments, i.e. tank plans, isolations and spading lists,
Risk Assessments, marked up P & ID’s and location drawings to illustrate the work scope
clearly and unambiguously. The description of the hot work, the written work scope,
associated attachments and safety procedures will be submitted to the Production
Management Office in Monaco for approval. A checklist (with signatures) will be used to
complement the preparations/isolations contained within the permits raised for the work.
WORK APPROVAL
(a)
The hot work procedure will be developed on board and reviewed and approved by the
O.I.M./ Unit Superintendent, prior to forwarding to the Shore Base. The Shore Base Unit
Operations Manager will discuss, amend as necessary and agree the content with the
O.I.M./ Unit Superintendent, prior to forwarding to the relevant Area Operations Manager in
the Monaco Production Management Office. The latter will discuss with the FPSO/FSO
Engineer if he considers it necessary.
(b)
The Area Operations Manager and the Marine Superintendent will review the procedure and
when satisfied the Area Operations Manager will send it to the HSE Manager, who will in
turn, review and comment on the content.
-8-
21/03/05
PART 2 - HW IN CARGO AND BALLAST TANKS
To perform hot work in cargo or ballast tanks to the satisfaction of the Certifying Authorities.
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
(c)
07
90
029
ISSUE 01
REV. 01
Any changes considered necessary will be added to the Hot Work Procedure and returned to
the Shore Base Unit Operations Manager who will discuss the modified text with the O.I.M./
Unit Superintendent.
This "loop" between the aforementioned parties will remain until agreement is reached. Once
a definitive Hot Work Procedure is in place and agreed by all, the Production Operations
Manager (or his delegate) will officially issue approval in writing for the work to commence.
The cover sheet for the Hot Work Procedure will contain signatures of the following, i.e.
O.I.M./ Unit Superintendent
Shore Base Unit Operations Manager
Production Management Office Marine Superintendent
Area Operations Manager (review with the FPSO/FSO Engineer)
HSE Manager
Production Operations Manager (final approval)
Any changes in conditions to the approved procedure once work has started, will require the
re approval by the persons listed above. Full documentation will be required to be submitted
as a revision; an appropriate revision number will be applied to the procedure.
GENERAL NOTE
Whenever hot work is required in a hazardous area on a Marine Unit, i.e. pump room, main
deck forward of the accommodation, turret, or at any other location considered to be
hazardous by the O.I.M./ Unit Superintendent, then a procedure must be produced and
approved as described in this CoP.
2.6
ORGANISATION AND RESPONSIBILITIES
(a)
All hot work taking place in cargo or ballast tanks must have an independent Safety
Consultant present in order to monitor and supervise this particular activity; this policy can
only be waived by the Production Operations Manager.
(b)
The Safety Consultant will act as the independent safety authority for the hot work activities
in the tanks. He has the delegated authority to stop the work or to prevent the start of work if
he is not satisfied with the safety of the operation. The Safety Consultant will liaise directly
with the Area Operations Manager and inform him immediately of any breaches to this
procedure, or at any time he has concerns relating to the safety of the ongoing work.
(c)
The Safety Officer and the Area Authority will keep the O.I.M./Unit Superintendent fully
informed. The Safety Consultant shall be party to the daily progress meetings convened for
this purpose. The work programme will normally be carried out in daylight hours. If time
constraints are imposed i.e. a job window is applicable, working at night may be necessary
but this must be assessed and risk assessed in the planning stage.
(d)
The hot work will be continuously supervised by the Safety Consultant who may be relieved
by the Safety Officer, Area Authority, or O.I.M./Unit Superintendent during meal breaks,
handovers etc.
-9-
21/03/05
PART 2 - HW IN CARGO AND BALLAST TANKS
2.5
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
(e)
The organisation and responsibilities of all concerned are to be agreed and clearly defined
before operations are commenced in order to avoid omissions and confusion.
(f)
The agreed work patterns are to be maintained and no work is to be contemplated or
undertaken without full discussion beforehand with all relevant parties. As personnel crew
change, the procedures and plan must be explained to the oncoming staff by means of a
recorded tool box talk so that they are fully familiar with their responsibilities and the required
precautions
(g)
Daily tank atmospheric tests will be carried out by two designated responsible persons in
order for the Entry Certificates and Hot Work Permits to be issued. They will wear 10/15
minute escape sets until the space is found to be gas free.
(h)
Prior to the commencement of work in the tanks, a Tool Box talk will take place at the tank
entry, with a Tool Box talk checklist being completed.
TANK PREPARATION FOR HOT WORK
(a)
For cargo tanks and ballast tanks contaminated with hydrocarbons, the tank atmosphere
must in all cases be purged with inert gas until atmospheric testing indicates the
hydrocarbon content is less than 1% by volume. The inert atmosphere will then be diluted
with air until 21% by volume is obtained without toxic gases being present.
(b)
All adjacent cargo tanks (tanks with a common longitudinal/ transverse or "corner" bulkhead)
should be (1) either clean, gas free and under air, or (2) ballasted to a minimum of 2 metres
higher than the location of the welding, and also clean, gas free and under air.
Note: A relaxation may be applied. This relaxation will clearly explain why section (b)
above cannot be complied with.
(c)
When hot work is taking place on a common bulkhead, the reverse sides of the bulkhead will
also be thoroughly cleaned or clean ballasted to above the hot work area. Other areas that
may be affected by the hot work must be given particular attention, e.g. the area immediately
below the place where the hot work is being undertaken, with consideration being given to
the deck head immediately above the work area if this is relevant due to its proximity to the
hot work.
(d)
Where © above cannot be complied with (with respect to thoroughly cleaning the reverse
side of the bulkhead in conjunction with man entry) due to operational constraints, then the
following can be implemented and incorporated within the HW procedure after discussions
with the Production Operations Manager, HSE Manager, FPSO Engineer, Marine Supt, Unit
Operations Manager, and OIM / Unit Superintendent:
The adjacent tank will be crude oil washed, water washed, and inerted with clean IG.
The IG in the adjacent tank will suppress the 02 content to a level as low as possible,
the level must not rise above 5%. Constant monitoring of the 02 content must be in
place.
Purging the Cargo Tank by IG gas must reduce the hydrocarbon content to 1% or less
by volume.
- 10 -
21/03/05
PART 2 - HW IN CARGO AND BALLAST TANKS
2.7
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
00
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
(e)
All pipe work serving, or passing through the tank, should be flushed with water and left filled
with water where practicable. Heating coils must be flushed prior to blanking.
(f)
All valves in, or leading to the tank will be chain locked closed, or their operating handles
removed, "Do Not Operate" Tags shall be attached. All valve motive driving mechanisms
shall be isolated, and the permits annotated accordingly.
(g)
All pipe work, i.e. cargo, COW, heating coils, and IG/vents in the cargo tank will preferably
be spaded off as close as possible to the termination. If this is not possible, then a two valve
isolation must be in place. If a two valve isolation is not possible, then a R/A must be carried
out and approved by the O.I.M./Unit Superintendent.
(h)
The tank will have been thoroughly crude washed and water washed and drained of all
hydrocarbon deposits, sludge scale and sediment 5m around the hot work location, this 5m
clean zone will extend 10m back from the HW site along the bottom plating, to the
satisfaction of the O.I.M./Unit Superintendent, Area Authority, Safety Officer and the Safety
Consultant. If solid deposits remain, they must be fully removed.
(i)
When considered feasible a water-bottom should be introduced, this being the case, then the
O.I.M./Unit Superintendent will decide if floatation aids for personnel are necessary.
(j)
The tank will be ventilated with air until the space contains 21% oxygen by volume as
measured by an in date calibrated oxygen meter. Ventilation must be continuous. Local
ventilation may be required to combat welding fumes.
(k)
Initial entry atmospheric tests will be carried out by the Safety Officer and the Area Authority
who will wear an approved emergency escape BA set, safety harness, radio, and in date
calibrated portable gas meter whilst in the tank. These tests will have been preceded by
remote sampling of the tank using a gas meter with an extension tube.
(l)
Pressurised and secured fire hoses to be run down in the tank to the hot work site area, and
portable powder fire extinguishers to be located adjacent to the work area.
2.8
WELDING MACHINES / ELECTRICAL EQUIPMENT
(a)
Diesel welding sets, diesel air compressors etc. which are to be used in conjunction with the
hot work will be inspected onshore by the Shore Base Unit Operations Manager. The
completed inspection sheet being forwarded to the Marine Unit.
(b)
Daily checks on the equipment when it is on the Marine Unit will be carried out by the I/E
Supervisor, and the Maintenance Superintendent, or their deputies.
(c)
All electrical equipment for use in the tanks and on the deck in the hot work area will be
BASEEFA rated, or of an equivalent standard for use in hazardous areas.
(d)
All electrical and mechanical equipment will undergo a full and comprehensive inspection by
the Maintenance Department prior to its use.
(e)
The diesel welding sets, and air compressors will be subject to a separate Hot Work Permit
when on the Marine Unit, and may not be started without the express approval of the Safety
Consultant after suitable atmosphere and area checks have been completed.
- 11 -
21/03/05
PART 2 - HW IN CARGO AND BALLAST TANKS
PART 1
PART 2
PART 3
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
(f)
2.9
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
Welding equipment should be provided with a "go and return" system utilising two cables
from the welding set.
LIVE BULKHEADS (HYDROCARBONS PRESENT IN THE ADJACENT TANK)
(a)
Hot work is not normally allowed within 500mm of a live bulkhead.
Note: An exceptional relaxation may be applied which permits HW to within 250mm of
a live bulkhead. This relaxation will clearly explain why section 2.9 (a) above cannot
be complied with. This relaxation would only be considered when a full Risk
Assessment has been carried out, and approved by the O.I.M./Unit Superintendent,
the Shore Base Manager, the Production Operations Manager and the HSE Manager.
When hot work comes within 1m of a live bulkhead, the 500mm or 250mm exclusion
zone mentioned in 2.9 (a) above is to be clearly marked on adjacent plating to identify
the prohibited hot work areas.
TANK HOT WORK SAFETY PROCEDURES
(a)
The SBMPC Permit to Work System shall be complied with.
(b)
No diversion of production is permitted other than to approved tanks, and no tank cleaning,
purging, gas freeing or bunkering will be permitted whilst hot work is in progress.
(c)
Hot work is not allowed during offloads to an export tanker.
(d)
The O.I.M./Unit Superintendent retains his normal overall responsibility for the safe
execution of all work being carried out on the unit.
(e)
Calibrated portable gas meters will be located at the hot work sites and will be monitored by
the fire watchers. The meters will be checked daily, at the end of the days work, and prior to
use the following day.
(f)
At the hot work location, a minimum of two gas meters should be employed, one at the
worksite with the Fire Watcher, the other with the Standby Man at the tank entry.
(g)
A Standby Man will be positioned at the tank entry, his main task is to maintain contact with
the work party and to maintain the record of personnel in and out of the tank by recording
their names on an entry check list, or by using a name tag system. He will also periodically
sample the hot work tank from his location at the tank entry. The Safety Consultant will
periodically sample the boundary tankage atmosphere.
(h)
Lifelines and safety harnesses must be available where there is a risk of falling from a height
of more than 2 metres; any staging used must be substantial and fit for purpose.
(i)
Communication will be established, tested and maintained between:
∗
The hot work site, the tank internal Fire Watcher and the Standby Man at the tank
entry.
∗
The Standby Man and the agreed communication centre.
∗
The hot work site and the Safety Consultant
- 12 -
21/03/05
PART 2 - HW IN CARGO AND BALLAST TANKS
2.10
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
90
029
ISSUE 01
REV. 01
The welding machine Fire Watcher and the hot work site Fire Watcher.
(k)
Hot work may normally only be conducted in one cargo/ballast tank at any one time. If HW is
required in more than one tank at the same time a Risk Assessment will be completed under
the authority of the O.I.M./Unit Superintendent and approved by the Shore Base Unit
Operations Manager, for final approval by the Production Operations Manager, and the HSE
Manager.
(l)
HW is allowed in one tank with entry into another tank taking place for mechanical work
under the control of a CW permit. However, a Risk Assessment will be completed for
approval by the O.I.M./Unit Superintendent.
(m)
Notwithstanding the fact that welding, cutting and burning and other hot work may be being
conducted in the tanks, smoking is prohibited in the tanks and on deck.
(n)
Personnel entering the tank will take a 10/15 minute escape set and a portable radio with
them. Rescue BA sets being located at the tank entry for use by the Emergency Response
Team.
(o)
The minimum number of personnel allowed in a tank is two.
(p)
The maximum number allowed in a tank will be decided by the O.I.M./Unit Superintendent,
based on safe working practices and must not exceed the safety equipment available for
each person involved in the tank work.
(q)
Each work party entering the tank will have one person nominated as the "Radio Man". Each
person entering the tank will carry an approved ELSA escape set, (this set need not be worn
continually, but shall be kept immediately available in the work area). In addition to the
normal company required personal protective equipment (PPE), welding PPE will be
required to be worn by the welders or those using burning gear.
(r)
No one may enter the tank in which the hot work is to take place before the Area Authority
has issued an Entry Certificate
(s)
Following this, no person may enter the cargo/ballast tank without the permission of the
Work Force Supervisor or Safety Officer, they will verify that the necessary tests have been
completed and that the Entry Certificate and the Hot work permit have been raised. The Area
Authority and Safety Officer will also visit the work site area in the tank prior to the
commencement of the work, and at regular intervals during the work. These visits are in
addition to the visits carried out by the Safety Consultant.
(t)
Subject to a satisfactory daily inspection in which the following conditions exist, the Entry
Certificate can be raised for personnel entry, (no hot work must take place without a valid
Hot Work Permit complementing the Entry Certificate).
(u)
∗ Hydrocarbon gas
Virtual Zero
∗ Toxic gases
(H2S & CO) Zero
The Hot Work Permit and the Entry Certificate will be valid for 12 hours with gas tests carried
- 13 -
21/03/05
PART 2 - HW IN CARGO AND BALLAST TANKS
∗
07
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
out before entry and after breaks. If the hot work is suspended for any reason for more than
60 minutes then the Entry Certificate will be re-validated.
(v)
The Entry Certificate immediately becomes invalid if any valve, pipe or joint is opened or
broken, or if any other event occurs in the tank or adjacent tanks which in the opinion of the
Safety Consultant would present a hazard to the on-site personnel.
(w)
In the event of hot work being stopped because of the above, the Safety Consultant will
discuss the situation with the Area Authority in order for remedial steps to be put in place so
that the work can safely recommence.
(x)
If, during the course of the hot work activity it is considered necessary to break into any lines
that may contain hydrocarbons in the tank, then all hot work shall stop. Prior to hot work
recommencing, a new Hot Work Permit, and Entry Certificate must be raised.
FIRE WATCHERS
(a)
During open flame hot work operations, a minimum of two Fire Watchers (in radio contact
with each other and the hot work party) are required. One to be stationed continuously in the
tank, and one at the welding machine. They will be totally independent of the ongoing work,
i.e. they are there to observe and monitor the area, should a fire, or other hazardous
situation develop, they will notify the Work Force Supervisor and Area Authority immediately
and if safe to do so, attempt to fight the fire.
(b)
The O.I.M./Unit Superintendent will however assess the Fire Watcher requirements over and
above this minimum number.
(c)
When hot work is stopped for the day, breaks, or completion, the Fire Watcher
(accompanied by one other person if the tank is empty of personnel) will observe the hot
work location for a period of at least 30 minutes. The Standby Man at the tank entry will stay
in position until all personnel have left the tank.
(d)
The Fire Watchers must not leave their station without the strict approval of the Area
Authority. They will report directly to the Area Authority and must be fully conversant in the
English language.
(e)
The Marine Unit Safety officer will brief the Fire Watchers on their duties, and a record will be
kept in the Marine Unit Safety office listing those personnel trained in fire watching
procedures.
(f)
The Fire Watchers at the hot work site should be provided with dark glasses to avoid "arc
eye".
2.12
(a)
EMERGENCY PLAN
An emergency plan shall be produced by the O.I.M./Unit Superintendent, Area Authority and
Safety Officer and reviewed by the Safety Consultant and tested prior to the start of any hot
- 14 -
21/03/05
PART 2 - HW IN CARGO AND BALLAST TANKS
2.11
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
(b)
The Emergency Plan will be tested prior to work commencing in the tanks with the Safety
Consultant present. Emergency response capability is to be kept under review with refresher
exercises taking place.
(c)
Sufficient rescue equipment must be provided at the tank entry in order to provide effective
cover, this equipment will remain on location throughout the duration of the work. This
equipment should be dedicated to this type of work and not normally drawn from the Marine
Unit fixed inventory (see equipment list).
(d)
Additional rescue ELSA, O2 resuscitator, rescue line and stretcher will be available at the
tank entrance together with sufficient manpower available to effect rescue. The Marine Unit
Safety Officer will check the equipment on a daily basis.
(e)
A rescue tripod to be set up over a suitable tank opening and shall remain in place
throughout the tank hot work. All involved personnel must be familiar with the rescue plan,
they must also be familiar with all the routes to the escape ladders when in the tank
(f)
All personnel involved in the cargo/ballast tank hot work will be given an induction course on
the Marine Unit emergency procedures prior to initial tank entry to ensure that they
understand how to don, use and wear the escape sets.
2.13
COMMAND AND CONTROL OF EMERGENCY SITUATIONS
(a)
The O.I.M./Unit Superintendent will retain his overall responsibility for control of any
emergency or developing emergency.
(b)
Contingency plans must be in place to cover the required procedures for the Fire Watchers
should a Marine Unit emergency occur and personnel have to report to their Muster Stations.
All Permits and Entry Certificates will be automatically withdrawn in the event of an alarm.
(c)
All personnel must evacuate from the hot work site (after making safe) to their designated
emergency muster stations.
(d)
All diesel driven machinery must be shut down and power isolated.
2.14
SAFETY EQUIPMENT REQUIRED TO COMPLY WITH THIS CODE OF PRACTICE
The following list represents guidance on the recommended Safety Equipment requirements
necessary to comply with this Code of Practice. The list does not include the Company
mandatory PPE requirements, i.e. hard hats, overalls etc.
BA Sets (30 minute) - sufficient for the agreed rescue team number
BA spare cylinders
BA Trolley Set
BA Escape Sets (10 minute) - for all personnel entering the tank
Emergency lifting apparatus
- 15 -
21/03/05
PART 2 - HW IN CARGO AND BALLAST TANKS
work activity within the tank. All personnel will be fully familiar with the emergency
procedures and what their duties are.
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
Explosion proof torches - for all personnel entering the tank
Fall arrestors
Fire extinguishers
Fire hoses and branches
Full harness
Gas meters (Triple Function), Minigas/Crowcon Triple Plus
Hand held radios - Fire watchers, Safety consultant, Standby man
Inflatable tank boat
Lifting lines
Plastic wallets to protect the permit displayed on the permit board
PTW Board for displaying permits at the tank entry
Resuscitator plus spare cylinder
Riken OX-1/Servomex 262
SAFE-T-CUBE
Stretcher
Tankscope
Victor Pyrate water driven fans with flexible trunking
Welding fume respirators
PART 2 - HW IN CARGO AND BALLAST TANKS
Wolf Lamps
Work vests - for all personnel entering the tank with a water bottom
Dark glasses for the fire watchers
Fire blankets
- 16 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
3.0
PART 3 - GENERAL HOT WORK IN HAZARDOUS AREAS
3.1
PURPOSE
REV. 01
This Code of Practice describes the procedures that are to be followed when Hot work that
will result in a naked flame i.e. welding, burning and grinding, has to take place in a location
classed as hazardous on a FPSO or FSO.
To be read in conjunction with the general guidelines contained within paragraph 9.3 HOT
WORK, Section 9, Working Safely, Health, Safety and Environmental Manual (or Chapter 2 Section 4 – 1.5 of the HSEP Shipboard Manual)
This type of Hot work is classed a Category 1.
Category 1 Hot work APPROVAL LEVELS, i.e. which tasks have to be approved by the
Production Management Office in Monaco, and those that can be approved by the Shore
Base Unit Operations Manager, plus the O.I.M./Unit Superintendent are detailed in Part 1 of
this Code Of Practice.
The procedures described within Part 3 of the Code of Practice refer to those hot work
activities that have to be approved in the Production Management Office in Monaco.
However the safety principles as described in Part 3 have equal relevance in those hot work
procedures approved locally in the Shore Base.
3.2
INTRODUCTION
Work that has to take place in a hazardous area that may involve hot work must in the first
instance be reviewed to determine if hot work is really necessary, i.e. could the task be
effectively carried out using cold work?
There may be locations onboard or conditions where live hot work is not a suitable option
without recourse to specific additional safety precautions. In these circumstances
pressurised habitats could be used in extreme circumstances with the use of a separate
check sheet to cover the integrity of the habitat.
If it is considered by any of the signatories to the Review and Approval Table that the
appliance of all the mitigating precautions and procedures does not reduce the risk level to
an acceptable level (as per the Risk Assessment) then the decision will be taken to isolate
equipment as appropriate, and if necessary to shutdown the FPSO/FSO if it is essential that
the hot work has to take place.
If hot work is the only solution then a clear method of work must be developed, reviewed,
and approved, in order that the work is carried out, monitored and completed in a safe
manner.
- 17 -
21/03/05
PART 3 – GENERAL HOT WORK IN HAZARDOUS AREAS
PART 1
PART 2
PART 3
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
3.3
RESPONSIBILITIES
3.3.1
O.I.M./Unit Superintendent
90
029
ISSUE 01
REV. 01
The O.I.M./Unit Superintendent will review the pending work that will entail hot work. In
conjunction with the relevant Area Authority, and the Safety Officer he will develop and
approve, the Risk Assessment (R/A) for the hot work. Once the R/A is completed, he will
approve the hot work procedure, prior to forwarding to the Shore Base Unit Operations
Manager for his review. The Shore Base Unit Operations Manager will determine, in
conjunction with the Area Operations Manager and HSE Manager, the requirement for an
independent Safety Consultant.
(The Review and Approval Table is attached as Appendix 1, this form will be faxed from
party to party in order to include the review and approval signatures). The actual hot work
procedure can be transmitted by e-mail.
3.3.2
Area Authority
The Area Authority will approve the R/A, and will ensure that his personnel who are to be
involved in the pending work are fully familiar with the contents and required precautions.
(He will ensure that the Tool Box talk takes place).
3.3.3
FPSO / FSO Safety Officer
The FPSO / FSO incumbent or additional hot work Safety Officer will develop the R/A in
conjunction with the O.I.M. / Unit Superintendent. He will monitor the progress of the hot
work, should he consider that the work is not progressing in accordance with the hot work
procedure, or he considers that an unsafe condition or situation has developed; he will stop
the work and notify the Area Authority.
3.3.4
Independent Safety Consultant
Should the hot work that is due to take place be considered to be such that an Independent
Safety Consultant is required, then an experienced person will be included as part of the task
force in order to effectively fulfill this duty.
He will report directly to the Area Authority. Large hot work repair work, major construction
type work will trigger this extra safety supervision requirement.
He will monitor the safety of the hot work, should he consider that the work is not
progressing in accordance with the Hot Work Procedure, or he considers that an unsafe
condition or situation has developed; he will stop the work and notify the Area Authority.
3.3.5
Shore Base Unit Operations Manager
The Shore Base Unit Operations Manager will review the hot work procedure, and when
satisfied he will sign the Review and Approval Table.
- 18 -
21/03/05
PART 3 – GENERAL HOT WORK IN HAZARDOUS AREAS
PART 1
PART 2
PART 3
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
If the hot work is such that it can be approved by the Shore Base Unit Operations Manager
and the O.I.M./Unit Superintendent he will proceed with the approval. He will still however
advise the Production Management Office of the impending hot work.
3.3.6
HSE Manager
The HSE Manager will review the Hot Work Procedure in conjunction with the relevant
Disciple Authority and the Area Operations Manager and amend if considered ncessary. This
may entail returning the Hot Work Procedure to the Shore Base Unit Operations Manager.
Once satisfied that the procedure contains the necessary safety precautions, he will forward
the procedure to the Production Operations Manager for his review and approval.
The Hot Work Procedure will have the faxed Review and Approval Table attached complete
with the signatures of the O.I.M./Unit Superintendent, Shore Base Unit Operations Manager,
Area Operations Manager, the HSE Manager and the Production Operations Manager.
3.3.7
Discipline Authority
The Discipline Authority will review the procedure against his requirements for the hot work.
Once satisfied he will sign the table.
3.3.8
Area Operations Manager
The Area Operations Manager will review the procedure against his requirements for the hot
work. Once satisfied he will sign the table. (He will, if necessary, discuss with the relevant
FPSO/FSO Engineer).
3.3.9
Production Operations Manager
The Production Operations Manager will review the Hot Work Procedure. Once satisfied, he
will sign to indicate his approval.
3.4
HOT WORK PROCEDURE
The Hot work Procedure Table will include:
•
•
•
•
•
•
•
•
•
Reference Number and Date
Hot work Procedure
Cargo Tank / Ballast Tank Status
Spading List
Daily Marked-up P&ID showing all relevant equipment, lines and isolations Check List
Fire Watcher Duties
Photographs of the work location
Risk Assessment
Any other relevant documentation
- 19 -
21/03/05
PART 3 – GENERAL HOT WORK IN HAZARDOUS AREAS
He will refer to Part 1 of this Code Of Practice, and if the procedure requires approval from
the Production Management Office, he will fax the table and e-mail the hot work procedure to
the Area Operations Manager.
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
APPENDIX 1
APPENDIX 1 – HOT WORK PROCEDURE TABLE
HOT WORK PROCEDURE TABLE
- 20 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
APPENDIX 1 – HOT WORK PROCEDURE TABLE
Marine Unit:
Revision No.:
Reference Number: xxx
Date xx/xx/xx
Description of the Hot work:…………………………..
This procedure applies to all SBM and contract staff involved in this repair.
When an Independent Safety Officer has been elected to monitor the safety of the Hot Work, the
FPSO/FSO Safety Officer will not be directly involved in the hot work, the latter will however be
available for advice / consultation for the Independent Safety Consultant.
Description
Objective
To carry out all work in a manner which will ensure the
Safety of all personnel, equipment and the FPSO /FSO
itself while following the Company SEP Policy and
procedures
Personnel
Staff carrying out the work will be monitored by the Area
Authority and the Safety Officer
Independent
Safety Officer
Independent Safety Officer required (Y), (N).
O.I.M. / Unit Superintendent + Shore Base Unit Operations
Manager joint decision – to be confirmed by the
Production Operations Manager and HSE Manager.
Confirmation that during the work there will be no
offloading, venting, sampling, gas freeing, bunkering etc.
Plant Status
Work scope
Detailed description of the hot work activity attached.
Live Bulkheads
Confirmation that no hot work will take place within 500mm
of a live bulkhead
Adjacent Tanks
Confirm that if burning or welding on a common bulkhead
that the tank on the other side is gas free and clean and
that the area directly opposite on the reverse side of the
bulkhead to where the hot work is taking place has been
verified as suitably cleaned.
- 21 -
Area Authority
acknowledgement
(tick)
APPENDIX 1 – HOT WORK PROCEDURE TABLE
Item
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
00
Item
Preparations
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
Description
REV. 01
Area Authority
acknowledgement
(tick)
Prepare Hot Work Permit for the area where the hot work
is to be carried out. Raise Cold Work Permit for any
preparatory work. All permits will be raised in accordance
with the SBM Permit to Work System.
Prior to hot work starting a Tool Box Talk will be held and
the check list completed by the Supervisor.
Communication will be established, tested and maintained
between:
1. The Fire-Watcher and the Safety Officer and
Cargo Supt.
2. The Safety Officer and Cargo Supt and the Radio
Room.
3. The welding set Fire-Watcher and Safety Officer
and Cargo Supt.
There shall be a charged fire hose and extinguisher at the
work site.
Emergency Response Team to be briefed in the hot work
and to hold an emergency exercise covering an incident at
the work site.
No hot work during diesel, diesel bunkering, offloading,
venting of gas or transferring chemicals.
All gas cylinders are to be properly secured. Igniters are
restricted to the hot work area and are to be moved to and
from the work site only by the work force supervisor
APPENDIX 1 – HOT WORK PROCEDURE TABLE
PART 1
PART 2
PART 3
The O.I.M./Unit Superintendent and the Cargo Supt. shall
monitor the weather conditions prior to and during the
operation. If any heavy rolling occurs then the work must
stop.
If habitat is to be used, a specific check list will be drawn
up to cover the necessary pre-checks and daily checks,
i.e.
• check integrity of the habitat material,
• ensure positive air pressure exists in the habitat,
• ensure practicable air lock facility is in place,
• ensure respiratory protection is available for welding
fumes.
- 22 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
Item
Fire-Watchers
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
Description
REV. 01
Area Authority
acknowledgement
(tick)
The Fire-Watcher will be briefed and informed of the
actions required by him in the event of a fire.
The Fire-Watcher shall continually monitor a portable gas
detector. In addition to this a Safe-T-Cube, Crowcon
Detective, or similar gas monitor will be strategically
placed to monitor the surrounding area.
A second Fire-Watcher in radio contact with the work site
will be located at the welding machine.
The location of the welding machine to be approved by the
O.I.M./Unit Superintendent
Fire-Watchers must be in attendance at all times during
hot work.
If a fire occurs the Fire-Watcher will raise the alarm and
notify the Radio Room immediately and if safe to do so
attempt to fight the fire.
In the event of an alarm from a portable gas meter the
Fire-Watcher will inform the Safety Officer of the alarm and
the work team will stop work immediately, make the work
site safe and vacate the area. He must also inform the
CCR who will advise the Area Authority. The alarm will be
investigated and no work will restart until the Safety Officer
has given the all clear.
APPENDIX 1 – HOT WORK PROCEDURE TABLE
All portable gas meters to be calibrated / checked daily
and placed on charge overnight.
If the gas detector “flat battery alarm” sounds then the hot
work will be stopped until the battery is changed or a
replacement gas meter is on site.
Breaks Stoppages
& Shift End
Breaks Stoppages
& Shift End Contd.
Gas tests will be carried out by the Safety Officer and FireWatcher at and around the work site at the start of each
shift and after breaks and stoppages.
At the end of each shift the work site is to be cleared of all
waste material and left in a clean and tidy condition.
- 23 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
Item
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
Description
REV. 01
Area Authority
acknowledgement
(tick)
When hot work is stopped for meal /breaks or end of shift
all oxy – acetylene cylinders must be turned off and hoses
drained. The Fire-Watcher must remain in the work for at
least 30 minutes in order to monitor for any post work hot
spots.
Daily Checks
Gas detectors are to be checked and calibrated before
use.
Morning briefing prior to commencing work to remind
personnel of permit conditions and toolbox talk
precautions.
Gas tests will be carried out prior to work commencing and
continually thereafter; the area to be monitored
continuously by the Safety Officer and/or the FireWatchers using portable gas meters and Safe-T-Cubes.
All oxygen – acetylene burning equipment must be
checked daily for flame arrestor at the torch, non-return
valves at the cylinders, damage to hoses, leaks at
connections and damage to the torch itself. If any defects
are found the equipment must be removed from service
immediately and replaced with new or undamaged
equipment.
Welding sets to be checked by Electrical Supervisor.
The O.I.M./Unit Superintendent or his deputy will retain
overall responsibility for control of any emergency.
APPENDIX 1 – HOT WORK PROCEDURE TABLE
In the Event of An
Emergency
In the event of a fire and or gas alarm all personnel are to
stop hot work, switch off and isolate all equipment and
ensure work site is left in a safe condition then proceed to
their emergency or muster stations.
The Safety Officer and Fire-Watchers are to check that the
equipment is isolated before proceeding to their
emergency or muster stations.
Safety Officer will investigate the alarm and report back to
the O.I.M./Unit Superintendent.
- 24 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
Item
029
ISSUE 01
Description
REV. 01
Area Authority
acknowledgement
(tick)
ATTACHMENTS
Cargo tank/
Ballast Tank
Status
Attach cargo tank/ballast tank status, i.e. crude oil, ballast,
inert gas free, or clean, that will apply during the hot work.
Method Statement
Attach the method statement to be used to safely
accomplish the work
Preparations
Attach Risk Assessment
Attach Spading List
Attach Tank Status for all tanks
Attach Photographs / and or sketches
Attach marked-up P&ID.
APPENDIX 1 – HOT WORK PROCEDURE TABLE
Attach copies of Permit to Work, Isolation Certificates etc
Attach any other relevant documents
Attach sketch showing location of welding sets highlighting
distance from nearest source of hydrocarbons
- 25 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
Item
Daily Work Site
Checklist (to be
verified each day
before the start of
work)
To be attached to
the Hot Work
Permit for the
work.
90
029
Description
ISSUE 01
REV. 01
Area Authority
acknowledgement
(tick)
1) Copies of procedures distributed
to all relevant personnel
2) Oil plant operating normally
with no upsets no other work planned)
3) Cold Work and Hot Work Permits prepared
4) Safety System Isolations on (if applicable)
5) All signs and barriers in place (tannoy
announcements)
6) Access and egress to worksite checked
acceptable. Safety harness to be worn of working
above 2 metres.
7) Adequate provision for tool storage and
material handling.
8) Work faces surrounded by enclosures
fitted with pressurising fans (if applicable)
9) Fire Watchers on location at worksite and
at welding set site.
10) All flammable materials moved away.
11) Fixed F & G detection equipment function
checked. Flame detectors Mos’d as required.
APPENDIX 1 – HOT WORK PROCEDURE TABLE
PART 1
PART 2
PART 3
12) Portable gas detectors function checked.
13) No cargo or fuel transfer or bunkering planned.
14) Cargo tank lids, ullage ports, IG connections
checked for gas leakage.
15) All fire blankets, flame retardant PPE, fire
extinguishers on hand.
16) Standby vessel on close standby.
(if applicable)
17) Main deck wetted down underneath the
hot work area.
blankets.
- 26 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
Item
Daily Work Site
Checklist (to be
verified each day
before the start of
work)
To be attached to
the Hot Work
Permit for the
work.
90
029
Description
ISSUE 01
REV. 01
Area Authority
acknowledgement
(tick)
18) Local electrical cables protected with fire
blankets.
19) Temporary safe lighting provided where
necessary.
20) Welding equipment checked for integrity
by the electrical dept.
21) Radio communications tested.
22) IG pressure between 400 and 700 mm wg.
23) Pre job meetings completed.
24) Arrangements made for CCR to be informed
whenever Hot work ongoing
25) All Fire Watchers completed safety training
with the Safety Officer.
26) All gas monitoring (continuous) being carried
out by competent personnel.
27) Continuous gas test on gas pipe work and
valves adjacent to worksite.
VALIDATION
APPENDIX 1 – HOT WORK PROCEDURE TABLE
PART 1
PART 2
PART 3
Applicable hot work permit number:
Area Authority:
Safety Officer:
Signed:
Date and Time:
- 27 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
00
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
APPENDIX 2 – REVIEW AND APPROVAL TABLE
PART 1
PART 2
PART 3
APPENDIX 2
REVIEW AND APPROVAL TABLE
- 28 -
21/03/05
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
00
07
90
029
ISSUE 01
REV. 01
APPENDIX 2 - REVIEW AND APPROVAL TABLE
Marine Unit:
Reference Number:
Date:
Work Description:
REVIEWED
FPSO / FSO
O.I.M. / Unit Supt.
SHORE BASE
Shore Base Unit Operations
Manager
Name
Signature
This section to be completed if
the hot work is such that it
requires approval of the
O.I.M./Unit Supt. and Shore
Base Unit Operations
Manager and the Production
Management Office in
Monaco
Date
This section only to
be completed if the
hot work is such that
it only requires
approval of the
O.I.M./ Unit Supt.
and Shore Base Unit
Operations Manager
PRODUCTION
MANAGEMENT OFFICE
REVIEWED BY
Discipline Authority
Area Operations Manager
HSE Manager
APPROVED BY
PRODUCTION OPERATIONS
MANAGER
- 29 -
21/03/05
APPENDIX 2 – REVIEW AND APPROVAL TABLE
PART 1
PART 2
PART 3
CODES OF PRACTICE AND OPERATING PROCEDURES MANUAL
PART 1 - GENERIC CODES OF PRACTICE
OFFSHORE HOT WORK PROCEDURES
PART 1
PART 2
PART 3
00
HW IN HAZARDOUS AREAS – APPROVAL AUTHORITY LEVELS
HW IN CARGO & BALLAST TANKS
GENERAL HW IN HAZARDOUS AREAS
07
90
029
ISSUE 01
REV. 01
APPENDIX 2 – REVIEW AND APPROVAL TABLE
REVIEW AND APPROVAL FLOW CHART
O.I.M./Unit Supt. raises the HW procedures in compliance with
the procedures as contained within the CoP. He then signs the
review and approval table and sends the table and the
procedure to the Shore Base Unit Operations Manager
Reviewed by the Shore Base Unit Operations Manager, he
refers to Part 1 of this CoP. If the procedure requires Monaco
approval he forwards the procedure to the Area Operations
Manager. If not, he approves the procedure in conjunction with
the O.I.M./Unit Supt.
If Monaco approval is needed the HSE Manager discusses the
HW procedure with the relevant discipline authority and
relevant Area Operations Manager. When all are satisfied with
the content, the review and approval table is signed and
forwarded to the Production Operations Manager.
When the Production Operations Manager is satisfied with the
contents of the procedure he returns the signed review and
approval table along with the procedure to the HSE Manager.
The HSE Manager sends the review and approval table back to
the Shore Base Unit Operations Manager and the FPSO/FSO
complete with all signatures. The Hot work can then
commence.
- 30 -
21/03/05
Download