Uploaded by ojdenzel

SUBMISSION TEMPLATE (PSCC1) 003

advertisement
Originating Company
OZPERAX LIMITED
Project Title
PROCUREMENT, SUPPLY, CONSTRUCTION AND
COMMISSIONING (PSCC1)
Client CLUSTER TIE IN WORKS
CONTRACT FOR OZPAX PROJECT
[
Client
J
Document Title
PROJECT EXECUTION PLAN
Document Number
0
IFB
REVISION
STATUS
DESCRIPTION
DATE OF
ISSUE
PREPARED
BY
REVIEWED
BY
APPROVED
BY
This document contains proprietary information and may not be partly or wholly reproduced without prior written permission from OZPAX Limited
PROCUREMENT, SUPPLY, CONSTRUCTION AND COMMISSIONING (PSCC1)
CLUSTER TIE IN WORKS CONTRACT FOR OZPAX PROJECT
[OZPAX/-PSCC1-C0001-CFT]
DETAILED PROJECT EXECUTION PLAN
OOL/PSCC1/PLN/2023/0001
TABLE OF CONTENTS
1.0 INTRODUCTION ........................................................................................................................ 2
1.1 PROJECT OVERVIEW ............................................................................................................... 2
1.2 PROJECT OBJECTIVES ............................................................................................................. 3
1.3 DESIGN LIFE .............................................................................................................................. 3
1.4 SCOPE OF WORK ....................................................................................................................... 3
1.4.1 SUMMARY SCOPE OF WORK AND BASIC ENGINEERING CLARIFICATION ............ 3
1
PROCUREMENT, SUPPLY, CONSTRUCTION AND COMMISSIONING (PSCC1)
CLUSTER TIE IN WORKS CONTRACT FOR OZPAX PROJECT
[OZPAX/-PSCC1-C0001-CFT]
DETAILED PROJECT EXECUTION PLAN
OOL/PSCC1/PLN/2023/0001
1.0 INTRODUCTION
1.1 PROJECT OVERVIEW
OZPAX Main Development Project (UMDP) involves the development of a discovered and
appraised field to the south-west of the (OML 180) producing fields Onshore Nigeria. The
OML 180 Block is located onshore Nigeria, approximately 85 km North-West.
The existing OML 180 facilities consist mainly of:

OZPAX FS (Flow Station).

OZPAX TC (Treatment Centre);

OZPAX PC (Production Centre).

Various clusters and oil and gas wells.

Oil and gas gathering flow lines, from wells and well clusters to plants.

Inter-field pipelines and power cables.
The facilities are operated by NG (E&P Nigeria Limited) on behalf of a joint venture between
NG and NNPC (Nigerian National Petroleum Company).
The scope of this project is to:
 Design, Construct, and Commission OZPAX Production Cluster Facilities (PSCC1)
 Design, Construct, and Commission the Pipeline to transport produced multiphase
fluid to OZPAX for processing and treatment. (EPSCC2)

Drill & Complete OZPAX Main Wells.

Make provision for Deep Exploration and Production Facilities.
A fully rated unmanned Well Pad, the OZPAX PC Facilities comprises, but is not limited to,
the following:

6 Production Wellheads and 6 x 8’’ Flowlines from wellheads to production manifold

One MPFM per producing well flowline (plus a spare) for production monitoring and
well testing.

A production manifold which gathers the produce fluid prior being exported.

A pig launcher for export pipeline pigging purpose and an open drain system

A maintenance flare (for manual depressurization and maintenance activities)
2
PROCUREMENT, SUPPLY, CONSTRUCTION AND COMMISSIONING (PSCC1)
CLUSTER TIE IN WORKS CONTRACT FOR OZPAX PROJECT
[OZPAX/-PSCC1-C0001-CFT]
DETAILED PROJECT EXECUTION PLAN
OOL/PSCC1/PLN/2023/0001

Chemical injection packages (Corrosion inhibitor and Methanol) and nitrogen
package for pig barrel purging and inerting, as well as purging of the flare systems.
At OZPAX PC, the gas from each well is measured by a multiphase flowmeter, before being
commingled at the cluster manifold then transported by one 16” multiphase pipeline to the
Obite TC where the gas is fully processed to specifications.
1.2 PROJECT OBJECTIVES
The objective of this project is to prepare the place (well pad) for drilling operative and to
evacuate the gas and make production of tie in to 16’’ multiphase pipeline. At OZPAX PC,
the gas from each well is measured by a multiphase flowmeter, before being commingled at
the cluster manifold then transported by one 16” multiphase pipeline to the Obite TC where
the gas is fully processed to specifications.
1.3 DESIGN LIFE
The design life of the PLANT is 20 years.
The PLANT shall be capable of performing according to the minimum operating life without
the need for major repairs (subject to operations being carried out in accordance with
operating and maintenance procedures established during engineering and in accordance with
good industry practice) with guarantees and warranties as specified in the CONTRACT. The
PLANT shall be capable of being safely decommissioned and dismantled at expiry of the
operating life
1.4 SCOPE OF WORK
1.4.1 SUMMARY SCOPE OF WORK AND BASIC ENGINEERING CLARIFICATION
The WORK includes Engineering, Procurement, Supply, Transportation, Fabrication,
Construction, Pre-commissioning, and Commissioning of the WELLPAD, OZPAX
PRODUCTION CLUSTER and Tie-ins to Obite Treatment Center and assistance with startup of the PLANT, and completion of performance testing of the PLANT.
CONTRACTOR’S scope of WORK, in brief, shall include:
a) Project Management, Controls, Coordination and Administration
3
PROCUREMENT, SUPPLY, CONSTRUCTION AND COMMISSIONING (PSCC1)
CLUSTER TIE IN WORKS CONTRACT FOR OZPAX PROJECT
[OZPAX/-PSCC1-C0001-CFT]
DETAILED PROJECT EXECUTION PLAN
OOL/PSCC1/PLN/2023/0001
b) Engineering
c) Procurement, Supply and Transportation
d) Assignment of COMPANY ITEMS
e) PLANT Construction and Tie-in.
f) Shutdown Activities
g) Pre-commissioning, Commissioning, and Assistance to
Start-up
h) Performance Tests
i) Third party Inspection and certification
j) Final Documentation
All the works listed above shall be carried out in the PLANT, up to a complete state of readiness
for start-up, as further detailed in the CONTRACT.
The WORK further includes the provision of such necessary or incidental supplies, consumables,
utilities, tools, labour, facilities, equipment, services and works as may be inferred therefrom,
unless specifically stated in the CONTRACT as excluded.
All as further detailed in the EXHIBITS.
4
Download