DESIGN, BUILD AND OPERATION OF THE NHIEU LOC THI NGHE WASTEWATER TREATMENT PLANT, HO CHI MINH CITY (NLTN WWTP) Leader REPORT GENERAL MECHANICAL DESIGN CRITERIA A V J - A Comments: Reviewed/ Approved by: 0 0 0 - M E - R P T - 1 0 0 1 - A EMPLOYER’S APPROVAL Code 0: Recommended for approval by EPMR Code 1: Approved by EPM Code 2: Approved with comments Code 3: Amend and resubmit Code 4: Rejected Code 5: For information only (Name, Signature, Date and Stamp) A 2020-07-31 PS JBL SBG Technical Design First Issue Rev. Date Preparation Review Approval Changes/Comments REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 2 / 32 TABLE OF CONTENTS 1 SCOPE 5 2 DOCUMENTS OF REFERENCE 5 3 DESIGN 5 3.1 UNITS 5 3.2 STANDARD AND CODES 6 3.3 INTERNATIONAL STANDARDS 3.3.1 MECHANICAL 3.3.2 PIPEWORK 7 7 7 3.4 GEOGRAPHICAL LOCATION 8 3.5 ENVIRONMENTAL CONDITIONS 3.5.1 GENERAL CLIMATE 3.5.2 TEMPERATURE, RAINFALL AND HUMIDITY 3.5.3 SEISMOLOGICAL DATA 8 8 8 10 3.6 GENERAL MATERIAL REQUIREMENTS 10 3.7 WARRANTY 10 3.8 DESIGN PRESSURE 10 3.9 DESIGN TEMPERATURE 11 3.10 DESIGN LIFE 11 4 11 METALIC WELDING 4.1 GENERAL 11 4.2 STANDARDS 11 4.3 WELDER QUALIFICATIONS 11 4.4 WELDING INSPECTION AND TESTING 11 4.5 PROTECTIVE COATINGS 12 5 12 MECANICAL EQUIPMENT 5.1 DESIGN 12 5.2 VESSELS 5.2.1 PRESSURE VESSELS 5.2.2 TANKS 13 13 13 5.3 ACCESS 13 5.4 ALUMINIUM PLATES AND SECTIONS 13 5.5 STAINLESS STEEL 13 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 3 / 32 5.6 FABRICATION 5.6.1 METAL WORK 5.6.2 STORAGE 14 14 14 6 PIPING 14 6.1 LINE SIZING 14 6.2 ALLOWABLE PRESSURE DROP 14 6.3 PIPING MATERIALS 6.3.1 METALLIC PIPING 6.3.2 NON-METALLIC PIPING 15 15 15 6.4 SAFETY SHOWER AND EYEWASH 16 6.5 PIPING SUPPORTS 6.5.1 SPECIAL PIPE SUPPORTS 16 16 7 16 STRUCTURAL DESIGN FOR EQUIPMENT 7.1 GENERAL 16 7.2 LOADS 7.2.1 7.2.2 7.2.3 PERMANENT LOADS (W) VARIABLE LOADS (W) EARTHQUAKE LOADS (E) 17 17 17 17 8 PROVISIÓN FOR HANDLING EQUIPMENT 17 9 SPECIAL TOOLS 17 10 NOISE AND VIBRATION 17 10.1 SOUND PRESSURE LEVEL 17 10.2 NOISE SURVEY 18 10.3 NOISE CONTROL 18 10.4 THERMAL AND ACOUSTIC INSULATION 10.4.1 GENERAL 10.4.2 INSULATION OF INDIVIDUAL ITEMS 10.4.3 VIBRATION 18 18 18 19 11 LUBRICATION 19 11.1 FIRST FILL & FLUSH 19 11.2 RECOMMENDATION BY SUPPLIER 19 11.3 GREASE LUBRICATION POINTS 19 12 19 PROTECTION OF METAL WORK FROM CORROSION 12.1 GENERAL 19 12.2 SURFACE PREPARATION AND CLEANING OF SURFACES IN THE SHOP 20 12.3 CLEANING OF PRIME AND INTERMEDIATE COATS (IF REQUIRED) 20 12.4 APPLICATION PROCEDURE 20 12.5 GALVANIZING 21 12.6 COATING SYSTEM 22 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 4 / 32 12.7 DESIGN CORROSION CONTROL & DURABILITY 23 13 PRE-SERVICE CLEANING AND PROTECTION OF SYSTEM EQUIPMENT 26 14 SAFETY 26 14.1 PROTECTION OF PERSONNEL 26 14.2 SAFETY OF MACHINERY 26 14.3 INTERLOCKS 26 14.4 INSPECTION OPENINGS 26 14.5 COUPLING GUARDS 27 15 27 FASTENERS 15.1 MECHANICAL FASTENERS 15.1.1 MATERIALS 27 27 15.2 PASSIVATION OF STAINLESS STEEL FASTENERS 27 16 ERECTION MARKS 27 17 LABELS 28 18 PIPELINE IDENTIFICATION 28 19 NAMEPLATES 28 20 INSPECTION AND TESTING 31 20.1 SCOPE 31 20.2 STAGES OF TESTING 31 20.3 INSPECTION POINTS PROGRAM (IPP) 31 20.4 GENERAL REQUIREMENTS FOR TESTING 31 20.5 FACTORY ACCEPTANCE TESTION AND INSPECTION 20.5.1 TEST PLAN AND PROCEDURE 20.5.2 FAT AND INSPECTION REPORT 31 31 32 21 32 PRE-COMMISSIONING 21.1 PRE-COMMISSIONING INSPECTIONS AND TESTS 32 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC 1 GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 5 / 32 SCOPE The aim of this report is to establish the design criteria for all mechanical and chemical equipment, piping and associated items, which form part of THE NHIEU LOC THI NGHE WASTEWATER TREATMENT PLANT, HO CHI MINH CITY (NLTN WWTP). The different equipment that are affected by this design criteria are: pumps, valves, penstocks, mixers, tanks, chemical equipment, pipes, silos, and any other process related equipment. The specific requirements of the equipment, valves, material and other individual specifications and data sheets have precedence over the requirements of this General Mechanical Design Criteria. This design criteria does not apply to Building Services, firefighting or HVAC equipment. This design criteria does also not apply to civil structures and access platforms. 2 DOCUMENTS OF REFERENCE The design shall consider the different documents included by the client as Tender Documents: Title Volume 2 Part 2 – Employer’s Requirements XL-02 Response to the Request of Clarification of Bidders XL-02 Amendments to Bidders 3 DESIGN Mechanical materials and equipment will comply with the technical codes of the International Organization for Standardization (ISO), European codes EN, EN-BS, EN-DIN; American codes ANSI, ASME, ASTM, AWWA, IEEE, API and/or Vietnam code TCVN. The specification and data sheets will reflect the specific standards in each case. If any Vietnamese regulation is contradicting to any standard given in this design criteria, it is the obligation of the Contractor to apply the Code with the highest requirement of quality, functionality and appropriateness. Application of standards shall be consistent for the equipment. In addition, standardisation of equipment (mechanical and electrical) across the Plant is desirable, and compatibility of equipment across the plant is essential. Generally, all internationally recognized Norms and Standards are accepted. Nevertheless, with respect to safety, health and working protection the related standards and laws which are directly linked to local legal provisions, the local law respectively the relevant binding local standards and norms shall be applied. 3.1 UNITS All units shall be expressed in SI (International System of Units). All piping sizes shall be expressed by nominal sizes: DN (diameter nominal) – mm (inches occasionally). VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Parameter Weight Volume Length Temperature Pressure Differential Pressure Mass flow (general) Water / volumetric flow: - large quantities - small quantities Power Energy Consumption Mass Force Time Velocity Quantity Rev. A Date 2020-07-31 Page 6 / 32 Units kg, metric ton (t) cubic metre (m³), litre (l) m, km Degrees Celsius (°C) absolute - Bar(a), gauge - Bar(g), mbar, Pa bar, mbar kg/s, kg/h, t/h m3/s or m3/h l/min MW kW Watt Meg-volt-amp - MVA kWh kg, g; mg N; kN Hour (hr) Minute (min) Second (sec) m/s Milligram per litre - mg/l, Parts per million - ppm, 3.2 STANDARD AND CODES All materials and equipment supplied and all work carried out as well as calculation sheets, drawings, quality and class of goods, methods of inspection, specific design features of equipment and parts and acceptances of partial plants shall comply in every respect with the technical codes of the International Organization for Standardization (ISO) and of the International Electro Technical Commission (IEC). Goods and special guarantees beyond the scope of ISO or IEC shall conform at least to one of the following standards and codes: European American German Japan Vietnam Pipes and accessories VN01C2-ME-RP-1001 EN, EN-BS, EN-DIN ANSI, ASME, ASTM, IEE, NEMA, NFPA, AWWA, IEEE, API, NACE,TEMA VDE, VDEW, DIN Japanese Industrial Standard (JIS) TCVN shall be in accordance with British or American or Japan or European standards if the use of other standards is not specially requested. REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 7 / 32 Other internationally accepted standards which ensure a quality equal to or higher than the standards mentioned above, but only if these are submitted in the English language (it is the obligation of Manufacturer/Contractor to demonstrate this requirement). 3.3 INTERNATIONAL STANDARDS The following list of international codes and standards when applicable shall apply. Where an international code of higher standing exists to another similar international code, then the higher standing code shall take precedence. 3.3.1 MECHANICAL EN ISO 9906 ISO 10816-1 BS EN 2516 ISO 3506 ISO 5752 ISO/TR 16880: API std 670 ASME Section VIII, Division 1 PED (97/23/EC) API RP 2000 DIN 2532 ISO 4872 Roto-dynamic Pumps, Hydraulic Acceptance Tests Mechanical Vibration. Evaluation of machine Vibration Passivation of Corrosion Resisting Steels and Decontamination of Nickel Base Alloys Mechanical properties of corrosion-resistant stainless steel fasteners Metal valves for use in flanged pipe systems -- Face-to-face and centre-to-face dimensions Cranes — Bridge and gantry cranes — International Standards for design and manufacturing requirements and recommendations Machinery protection systems Design & Fabrication with Inspections, Repairs, and Alterations of Pressure Vessels European Pressure Equipment regulation (97/23/EC) Venting Atmospheric and Low-Pressure Storage Tanks Cast Iron Flanges; Nominal Pressure 10 Acoustics – Measurement of airborne noise emitted by construction equipment intended for outdoor use – Method for determining compliance with noise limits 3.3.2 PIPEWORK TCVN 9113 TCVN 8492 TCVN 9070 ISO 7005-1 ISO 7005-2 ISO 1127 Reinforced concrete pipes for water draining Spiral winding pipes of unplasticized poly (vinyl chloride) for non-pressure underground drainage and sewerage systems Corrugated pipe HDPE Pipe flanges -- Part 1: Steel flanges for industrial and general service piping systems Metallic flanges -- Part 2: Cast iron flanges Stainless steel tubes. Dimensions, tolerances and conventional masses per unit length. ISO 15493 Plastics Piping Systems for Industrial Applications – ABS, PVC-U and PVC-C – Specifications for Components and the Systems – Metric Series ISO 15494 Plastics Piping Systems for Industrial Applications – PB, PE and PP – Specifications for Components and Systems – Metric Series Plastics piping systems for water supply and for buried and above-ground drainage and sewerage under pressure -Un-plasticized poly (vinyl chloride) (PVC-U) Plastics piping systems -Polyethylene (PE) pipes and fittings for water supply Ductile iron pipes, fittings, accessories and their joints for water applications Cast Iron Flanges; Nominal Pressure 10 Face to face and end dimensions of valves ISO 1452 ISO 4427 ISO 2531 DIN 2532 EN 558 part1, BS 5163. EN10253-2 EN-1092 BS EN 1916 VN01C2-ME-RP-1001 Butt-welding pipe fittings - Part 2: Non alloy and ferritic alloy steels with specific inspection requirements Flanges and their joints. Circular flanges for pipes, valves, fittings and accessories, PN designated. Steel flanges Concrete pipes and fittings, unreinforced, steel fiber and reinforced REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 8 / 32 3.4 GEOGRAPHICAL LOCATION The new Wastewater Treatment Plant (WWTP) shall be developed as a plant for wastewater inflow predominantly of domestic origin and associated facilities, wherein the selected biological technology is MBBR. Detailed design for the NLTN WWTP with a peak flow of 34,000 m³/h. Flows exceeding the max. allowed flow shall be bypassed. Design pollution load is of 52,000 kg/BOD5/d and of 13,000 kg NH3-N/d. Nhieu Loc Thi Nghe WWTP is located in Thanh My Loi Ward of District 2 / Ho Chi Minh City, Vietnam. 3.5 ENVIRONMENTAL CONDITIONS Process and all the equipment provided shall be capable of satisfactory operation within the Vietnamese climate. 3.5.1 GENERAL CLIMATE Vietnam's climate, being located in the tropics and strongly influenced by the South China Sea has a monsooninfluenced tropical climate typical of that of mainland Southeast Asia. In the north, the climate is monsoonal with four distinct seasons (Spring, Summer, Autumn, and Winter) while in the south (areas south of the Hải Vân Pass), the climate is tropical monsoon with two seasons (rainy and dry). The area of Ho Chi Minh City has a tropical climate is a tropical savannah climate, with a two distinct seasons (rainy and dry). 3.5.2 TEMPERATURE, RAINFALL AND HUMIDITY According to QCVN 02:2009/BXD Vietnam Building code Natural Physical & Climatic Data for Construction and Climatic Conditions in the Feasibility Study. Unless otherwise specified the assembly and all the equipment provided shall be capable of satisfactory operation within the temperature limits of -10°C to 50°C and relative humidity of 90 % comply with Vietnamese climate. 3.5.2.1. Temperature The average air temperature is approximately 28.16ºC. The highest temperature is 34.2ºC (2000), the lowest temperature is about 20.8ºC (2000). The average temperature over months from 2005 to 2010 as follows: VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader GENERAL MECHANICAL DESIGN CRITERIA DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC Y\M 2005 2006 2007 2008 2009 I 26.2 27.2 27.3 27.2 25.9 Rev. A Date 2020-07-31 Page 9 / 32 II III IV V VI VII VIII IX X XI 27.7 28.4 29.8 29.7 28.9 27.5 28.4 27.9 27.6 27.5 28.2 28.6 29.5 29.2 28.4 27.9 27.6 27.6 27.7 28.9 27.2 28.8 30.1 28.9 28.7 27.7 27.7 27.7 27.5 26.9 27.3 28.2 29.5 28.2 28.6 28.3 27.7 27.7 28.0 27.2 27.7 29.3 29.4 28.5 29.2 28.0 28.6 27.6 27.7 28.4 Source: Ho Chi Minh City Statistical Yearbook 2010, Tan Son Hoa Station XII 262 27.3 27.6 26.9 27.5 Year 28.0 28.2 28.2 27.9 28.1 The table below reflects the average values of the last year weather conditions register. Max. Ambient Air temperature Min. Ambient Air temperature Humidity +40ºC 20ºC 50-90% 3.5.2.2. Sunshine hours Total sunshine hours per year are 2,073.7 hours. Thereby, April is the month, which has the most hours of sunlight (240.8 hours). The total of average daily radiation in a year is about 110-160 Kcal/cm2. The daylight hours in months from 2005 to 2010 as follows: Y\M 2005 2006 2007 2008 2009 I II III IV V VI VII VIII IX X XI XII 164.8 131.0 113.3 156.3 174.4 215.3 157.7 193.6 135.6 168.1 252.9 221.6 229.5 216.7 236.9 225.6 213.4 213.5 188.3 186.7 200.4 208.7 182.5 165.7 155.9 185.6 161.5 128.0 172.8 191.6 153.1 140.2 147.7 218.7 149.2 178.1 157.2 135.8 161.0 155.7 142.2 141.4 130.8 142.6 116.9 138.8 127.2 147.0 152.4 132.3 124.6 142.1 127.5 145.4 147.7 90.5 121.2 141.8 134.1 187.6 Year 2,071.9 1,923.9 1,891.1 1,989.6 2,003.2 Source: Ho Chi Minh City Statistical Yearbook 2010, Tan Son Hoa Station 3.5.2.3. Rainfall In the city area, the rainfall is uneven, tends to increase along the Southwest – North East. The suburban districts and northern districts are higher rainfall than the rest of regions. Average annual rainfall of the city is high from 1,742.8 to 2,340.2 mm/year. The rainfall concentrates on the rainy months, accounting for 90% of annual rainfall. Thereby, heavy rains usually occur from August to October; especially, there is a little bit the amount of rainfall or no rainfall in January to March. Monitoring data indicates that the average rainfall is 2,016.2 mm in 2010. The average rainfall (in mm) monthly from 2005 to 2010 as follows: Y\M 2005 2006 2007 2008 2009 I 0.4 9.5 0.3 II III IV V VI VII VIII IX X XI 9.6 143.6 273.9 228.0 146.3 182.9 388.6 264.5 72.7 8.6 212.1 299.2 139.4 168.6 349.0 247.7 256.1 16.1 59.3 7.7 327.9 188.8 414.3 301.0 495.4 391.2 147.1 1.5 58.9 127.0 246.9 147.2 331.2 297.8 202.6 165.6 167.1 21.4 57.8 187.0 318.5 83.2 223.0 323.9 325.1 249.0 141.2 Source: Ho Chi Minh City Statistical Yearbook 2010, Tan Son Hoa Station XII 105.4 28.9 7.1 57.8 49.5 Year 1,742.8 1,798.4 2,340.2 1,813.1 1,979.9 3.5.2.4. Humidity The average humidity is 74%, the difference between the highest wet and dry place is about 10 to 12%. The highest humidity in the rainy months is around 83% (September) and the lowest in the dry months is 68% (February). The average humidity monthly from 2005 to 2010 as follows: VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC Y\M 2005 2006 2007 2008 2009 I 69 73 69 71 70 GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 10 / 32 II III IV V VI VII VIII IX X XI 69 67 70 74 77 81 78 80 82 79 68 71 73 75 81 81 82 81 81 75 68 71 69 80 80 83 82 83 82 76 69 71 73 81 78 79 83 83 81 79 73 71 76 81 77 79 80 83 80 73 Source: Ho Chi Minh City Statistical Yearbook 2010, Tan Son Hoa Station XII 77 73 72 73 74 Year 75 76 76 77 76 3.5.3 SEISMOLOGICAL DATA According to QCVN 02:2009/BXD Vietnam Building code Natural Physical & Climatic Data for Construction. 3.6 GENERAL MATERIAL REQUIREMENTS The material selection shall take into account the generally aggressive environment within which the equipment operates. Regardless of whether a material of manufacture or minimum material requirement is specified, all material selections shall be suitable and proven for use in the proposed application. All materials shall be new and of the best quality for use in the conditions and the variations in temperature, pressure and media that will be encountered in service without undue distortion or deterioration or the setting up of undue strains in any part that might affect the efficiency and reliability of the plant. All materials shall correspond either to the approved standards and the respective code number or to exact analysis data, and full information concerning properties and applied heat, chemical and mechanical treatment shall be submitted. Special attention must be paid to eliminating the possibility of corrosion resulting from galvanic effects. Design, selection of materials and all methods of erection shall be such as to keep these effects to a minimum. All materials used shall be resistant to the media handled and to the environmental conditions. Consideration shall also be given to conditions prevailing during transportation, storage and erection. Amongst other things, following conditions and aspects shall be considered: Corrosive environment with high ambient temperatures and high humidity; Corrosive soil; Corrosive and shallow ground water quality; Solar radiation; Design for the severe corrosion conditions; and Consider ambient conditions as specified for the construction site; 3.7 WARRANTY The equipment and installation shall be guaranteed for a period of at least one (1) year trouble free operation. Effectively date of the warranty shall start on the same day the units have been accepted. The supplier shall guarantee the availability of replacement parts and after sales service for a period of five (5) years for each piece of equipment supplied. 3.8 DESIGN PRESSURE Design pressure of the system shall never be less than the maximum pressure expected in service. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 11 / 32 3.9 DESIGN TEMPERATURE Maximum design temperature shall not be less than the Maximum Operating Temperature expected in service. Design margins shall be applicable according to ambient conditions and working requirements, as well as startup/shutdown conditions. The design temperature shall be used to determine the design allowable stresses for the selected material in accordance with the design code. 3.10 DESIGN LIFE The work shall be designed for the following lifetime: Mechanical Equipment shall be designed for long life and continuous 24 hour operation for prolonged periods with a minimum of maintenance. The minimum design life shall be 15 years. The requirements for design life shall govern the selection of materials. 4 METALIC WELDING 4.1 GENERAL All welding, in general, shall be carried out to ISO standards or equivalent ASME. The strength of all welded connections shall not be less than the strength of the parts being joined. 4.2 STANDARDS The work shall be carried out in accordance with the relevant international standards. 4.3 WELDER QUALIFICATIONS Skilled personnel appropriately qualified to relevant standards shall carry out welding. Alternatively, welders shall be qualified by approved international equivalent standard. Copies of welder qualification certificates of the personnel employed on the welding operations shall be provided. All weld preparations, welding heat treatments, weld examination, welding equipment, filler wire, electrodes, welding symbols, terms and definitions shall conform to international Standards. All welded components that require machining and those where dimensional stability is important, shall be stress relieved. Where required, stress relieving shall be carried out before final machining. 4.4 WELDING INSPECTION AND TESTING All joints marked as potentially required for inspection, including welds, are to be left uninsulated, unpainted and exposed for examination during testing. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 12 / 32 4.5 PROTECTIVE COATINGS All equipment shall be coated in compliance with the working conditions to which it is exposed. For further details, refer to section 12. 5 MECANICAL EQUIPMENT 5.1 DESIGN The equipment to be supplied shall be new and clean, and it shall be manufactured and arranged under a functional design and shall provide a pleasant appearance. All equipment of the WWTP shall be arranged in such a manner that surveillance by the operator is easy, as well as maintenance, operation and control. The equipment to be provided shall be state of the art supplied from well known manufacturers with high quality competitive standard. The mechanical equipment shall be designed with operability, constructability, durability and safety considerations. The equipment which is flanged shall conform to ISO 7005 PN10 or higher PN class if higher pressure is functionally required. The Contractor’s design shall show all required components of the WWTP and shall include complete process dimensioning and hydraulic dimensioning and shall clearly indicate how to achieve environmental protection as required by Vietnamese law and regulations. The Equipment to be supplied shall be arranged so that they can be easily inspected, cleaned, erected and dismantled without necessitating large scale dismantling of other parts of the Systems. The Equipment shall be manufactured, mounted and put into operation in accordance with the latest recognized rules of workmanship, modern engineering practice and with good standard of prudence applicable to the international standards and codes which would have been expected to accomplish the desired result at the lowest reasonable cost consistent with reliability, safety and expedition. All applicable laws and governmental decrees, regulations, orders, the regulations as well as common international standards and guidelines shall be observed in the design, calculation, manufacture, erection, installation, testing, commissioning and start up of all parts of the Systems. The following shall be considered in the engineering and construction of the facilities: All parts of the Systems shall be suitable in every respect for continuous operation at maximum load, as well as part loads and expected transient operating conditions peculiar to the site and shall be able to safely withstand the stresses arising from the operating conditions without any reduction in its planned life, which shall be at least equal to the design life time defined. The Contractor shall familiarize himself with the conditions on site. Switchover to stand by units shall be automatic, as far as required for continuous operation of the systems. Minor equipment, which, in case of failure would cause a failure of a pumping station and/or the entire System, is to be provided with a standby facility in order to ensure further operation of the facilities. All live, moving and rotating parts shall be provided with appropriate effective protection in order to avoid danger to the operating staff. All metal parts shall be electrically grounded. The following characteristics are also to be considered: The plant equipment is to be designed with the ergonomics considerations in mind; good safe access is to be provided for all elements that require usual operation or inspections. All materials regardless of size or importance shall comply with durability and material selection criteria to ensure fit for purpose. The main equipment, which could be damaged in case of seism or due to the operation cycle, shall be mounted with expansion joints to ease the assembly and provide security against vibrations. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 13 / 32 5.2 VESSELS All tanks, vessels, chambers and manholes shall be suitably protected to prevent water ingress. 5.2.1 PRESSURE VESSELS Pressure vessels shall be designed fabricated with non-corroding materials, with side entry feed and concentrate ports and connections. The pressure vessels shall have all necessary adaptors, shims, spacers, or other fittings, for a complete and functional system. Pressure Vessels are to be designed under ASME section VIII Division 1 or under PED, European Pressure Equipment regulation. A certified copy of the production test data for each pressure vessel shall be provided. The pressure vessels shall be compatible with the membrane elements, and all necessary internal and external components shall be provided for a fully operational system. For a vessel protected by an upstream relief valve, DP shall be at least equal to the set pressure of that relief valve. 5.2.2 TANKS All tanks shall be designed with best industry practices in terms of drainage, accessibility. Tanks shall be provided at least with overflow, vent (if required), access manhole and low point drain. 5.3 ACCESS The general layout of equipment shall ensure adequate accessibility to allow regular operating and maintenance tasks to be performed. Access platforms shall be provided for major plant components, which cannot be operated or maintained from floor level. Stairways shall be provided for access. Access routes shall be provided for the removal of large plant components on trolleys or similar handling appliances. All process equipment shall be provided with a suitable quantity and distribution of isolatable drains, vents and connections to service water to allow thorough flushing and draining in preparation for maintenance. For equipment over 25 kg, jack screws, lifting lug or equivalent shall be provided. Drains and vents shall be routed to the side of the package and will be properly isolated. 5.4 ALUMINIUM PLATES AND SECTIONS All aluminium plates and sections shall be aggressive corrosion resistant. manufactures according to EN 573 - DIN 2642 The aluminium Slip-On will be 5.5 STAINLESS STEEL All items fabricated from stainless steel shall be manufactured according to AISI 304 or AISI 316, according to the design to assure the corrosion resistant in each case. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 14 / 32 5.6 FABRICATION 5.6.1 METAL WORK This Section applies to all fabricated carbon steel and aluminium process equipment metalwork which is incorporated into the Works. Fabrication of metalwork items shall be carried out in accordance with EN1993-1-1 Eurocode 3 or international equivalent. Metalwork shall be fitted accurately. Where appropriate, measurements shall be confirmed on site, prior to fabrication. All welding shall be continuous full penetration butt welds or fillet welds. All fillet welds shall be full seal welds. Spot welding or stitch welding shall not be utilised. Machined, cut or sheared edges shall be filed or ground and shall be smooth and free of burrs and sharp edges. Welds in carbon or low alloy shall be chipped and brushed free of slag before surface preparation for painting or galvanizing occurs. 5.6.2 STORAGE All materials stored at the fabrication plant, and all fabricated metalwork, shall be supported above the ground so as not to cause overstressing, properly protected from tarnishing or corrosion, and kept free of dirt, oil, grease, and other foreign material. 6 PIPING 6.1 LINE SIZING Lines shall be designed to convey the designated quantity of fluid (liquid or gas) at a velocity for the best performance considering the back pressure. If there is not a specific requirement, the following typical velocities shall be considered: Water: Material GRP/HDPE Stainless steel Velocity (m/s) 3 2-4 Air: Material Velocity (m/s) Stainless steel 12 (1) Note 1: Maximum velocity in main air collectors shall be 20 m/s. Lines shall be selected with consideration of the pipe relative roughness in order to absorb the minimum pumping energy. 6.2 ALLOWABLE PRESSURE DROP Process critical piping systems shall be fully analyzed (and sizes confirmed) for pressure losses resulting from friction, elevation and pipe fittings. The actual pressure drop, and hence line size, shall be confirmed with detailed calculations of process critical lines. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 15 / 32 6.3 PIPING MATERIALS 6.3.1 METALLIC PIPING 6.3.1.1. General Selection and specification of material shall take account of the following: - Fluid conditions (e.g., % solids, pH levels, chloride levels, erosiveness). - Phenomena such as galvanic and other forms of localized corrosion. - Environmental and Stress Corrosion Cracking. - Intergranular Corrosion. - Final material selection shall be specified in particular specifications and data sheets. 6.3.1.2. Flanges Flange Standards All pipework associated with the pumping unit and associated fittings shall be flanged to PN10 or greater in accordance with ISO 7005-2 (CI or DI) and ISO 7005-1 (Steel). Flange Types Flanges should normally be slip on or weld neck type up to PN10. Weld neck flanges are only to be used where welding directly to butt weld fittings such as an elbow or tee. Pipe flange bolting patterns shall straddle pipe centrelines. 6.3.1.3. Fittings Fittings shall conform to the requirements of the relevant Piping Material Class. Fabricated branch connections shall be permitted, where supporting calculations are provided, as defined in the branch connection table for each Piping Material Class. The branch table nominates the type of branch for every combination of header and branch size for each material type. 6.3.1.4. Joints Butt welded joints shall be used generally for stainless steels. These materials joints are in services susceptible to crevice corrosion. For stainless steel piping in a service not prone to crevice corrosion, socket weld joints shall be used in sizes DN 50 and smaller due to high cost and limited availability of socket weld fittings in larger sizes. 6.3.2 NON-METALLIC PIPING 6.3.2.1. General Selection and specification of material shall take account of the following conditions: - Increase in temperature due to solar radiation. - Reaction with strong acids and alkalis. - Compatibility with service fluid. - Support availability and the facility to absorb the increased thermal expansion of the pipe. - Effects of ultra violet radiation and fire. - Creep. - Cost. - Surge potential. - Corrosion and erosion. - Fatigue. - Shear Stress. - Local buckling. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 16 / 32 6.3.2.2. Flange Backing Ring All pipework associated with the pumping unit and associated fittings shall be flanged to PN10 or greater in accordance with ISO 7005-2 (CI or DI) and ISO 7005-1 (Steel). Backing rings for non-metallic flanged joints shall be made from polypropylene, coated carbon steel, 316 stainless steel, hot dip galvanize (HDG) or plastic and shall be suitable for the plant environment. 6.3.2.3. Fittings Fittings shall be injection moulded from the PVC, PE100, PP, ABS or PVDF. Fittings shall be rated to at least the pipe rating. 6.4 SAFETY SHOWER AND EYEWASH A safety shower and eyewash shall be installed adjacent to any acid, caustic or dangerous material handling equipment in accordance with the relevant international safety standards. The safety shower and eyewash stations are piped to potable water supply. Locations of safety showers shall be decided based on operational requirements. Stations in finished areas shall be supplied with floor drains; stations in process areas shall be curbed with drainage directed to a safe location. Safety shower layout shall provide a clear and unobstructed path from the hazard location to the station. 6.5 PIPING SUPPORTS Pipe Supports location shall be detailed on plans, elevations and support detail drawings. Standard support drawings shall be produced where required. The stresses in small piping connections shall be reduced to a minimum by adequate supporting. Extra supports and bracing shall be designed to minimize vibration. Piping around control valves and in-line instrumentation shall be adequately supported to minimize vibration and stress at these devices. Piping sections requiring frequent dismantling for maintenance, such as for the installation of blinds, shall be provided with permanent supports for the dismantled condition. Pipe supports shall be made of carbon steel coated. Pipe supports will be provided with neoprene band between the pipe and the support in order to avoid corrosion. 6.5.1 SPECIAL PIPE SUPPORTS Special pipe supports shall be numbered, listed, indicated on drawings and controlled by area. Each special pipe support shall be allocated an individual reference and sequentially numbered. The use of unique reference numbers is to assist in the control of the supports during design and construction. 7 STRUCTURAL DESIGN FOR EQUIPMENT 7.1 GENERAL Structural supporting steel work shall comply with EN 1993-1-1 Eurocode 3 or international equivalent. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 17 / 32 7.2 LOADS 7.2.1 PERMANENT LOADS (W) Permanent structures of equipment, shall be designed to resist expected permanent loads as specified in EN 1993-11 Eurocode 3 or an international equivalent. 7.2.2 VARIABLE LOADS (W) Permanent structures of equipment, shall be designed to resist expected variable loads as specified in EN 1993-1-1 Eurocode 3 or an international equivalent. 7.2.3 EARTHQUAKE LOADS (E) The seismic parameters shall be in accordance with TCVN 9386:2012. 8 PROVISIÓN FOR HANDLING EQUIPMENT Equipment/plant shall be designed to enable operational maintenance to be carried out by the plant operators rather than specialised sub-contractors or trades people wherever possible. Lifting equipment with appropriate safe working load capacity shall be provided where health and safety requirements preclude manual handling. The maximum weight of manually-removable covers and grating panels shall be 25 kg. Buildings in which lifting equipment is provided shall be of an adequate height to allow lifting above other items of equipment and onto vehicles. All parts of the plant with a mass greater than 25 kg shall have provision for lifting, slinging and handling during erection and overhaul or maintenance. Lifting procedures shall be supplied for all equipment weighting more than 2 Tonne or larger than 3 m³. 9 SPECIAL TOOLS Any special tools which may be necessary to enable the maintenance dismantling and attention to all parts requiring periodic maintenance or replacement to be carried out expeditiously shall be supplied with the equipment. The use of any special tools shall be clearly identified in the Operation and Maintenance manuals provided by suppliers. 10 NOISE AND VIBRATION The equipment and room design shall comply with the QCVN 26:2010/BTNMT National Technical Regulation on noise and vibration. 10.1 SOUND PRESSURE LEVEL The equipment noise level during operation shall not exceed an overall weighted sound pressure LAeq, 8 h of 85 dB(A) (8 hour exposure average of 85 dB(A)) when measured no further than 1 meter from the wall of the equipment. Where this requirement cannot be met, this shall specifically be indicated. A noise attenuating enclosure or other sound insulating material should be provided to bring the sound pressure level down to stated limits necessary for the protection of workers and the public. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader GENERAL MECHANICAL DESIGN CRITERIA DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC Rev. A Date 2020-07-31 Page 18 / 32 10.2 NOISE SURVEY A noise survey shall be performed prior to commencing construction to determine the current noise level at the site, and demonstrate that the completed WWTP at its full operation shall not increase DENR standards for Noise Levels in General Areas included in table below above 3 dB(A). Table 1 – Permissible noise limits (in decibel), dB(A) (QCVN 26:2010/BTNMT) Nº 1 2 Area Special areas Usual areas From 6:00 to 21:00 55 70 From 21:00 to 6:00 45 55 10.3 NOISE CONTROL Noise levels shall be contained by appropriate equipment design. Acoustic enclosures shall form an integral part of the equipment, and shall not adversely affect the safety or function of equipment. The soundproofing enclosures shall not impede the flow of cooling air when fully installed. The acoustic enclosure shall be constructed so that it can be easily removed for maintenance purposes. The enclosure shall have locks/latches to keep the enclosure closed when it is over the equipment. Normal operation shall be possible without opening or removing enclosure. Hinged access doors shall be provided for easy access for routine inspection and maintenance or lifting lugs where overhead gantry is available. The material used shall not be vulnerable to the high temperature inside the enclosure. 10.4 THERMAL AND ACOUSTIC INSULATION 10.4.1 GENERAL Insulation shall be provided for personnel protection, for reduction of noise emission and for process requirements. All insulated equipment shall be provided with corrosion resistant aluminum sheath. Insulation for outdoor installations shall be rain and dustproof. Tank and duct tops shall be provided with insulation strong enough to support a man's weight. The sheets shall be secured and connected at the longitudinal seams with self tapping screws (five screws per meter). At the longitudinal and circumferential joints, the sheets shall overlap by at least 50 mm so that water will run off and not soak into the insulation material. The overlap shall be in the same direction of possible water flow, so that penetration of water is avoided. The seams and penetrations of any sheet metal insulating jacket installed outdoors shall be sealed against water by means of suitable insulating tape. 10.4.2 INSULATION OF INDIVIDUAL ITEMS All flanges, valves and fittings shall be provided with two piece or multi part combination caps made of sheet metal of the specified thickness and a steel plate galvanized on both sides of at least 275 g/m². The shaped caps of the fittings shall be made longer by approximately twice the insulation thickness so that the welding seams will be exposed after removal of the cap. Where possible, these caps shall be fitted with a clamping strip or lever hook to facilitate assembly. Tanks and equipment shall be insulated in the same way as pipes, except that the insulating material may not be attached by wire but by using strong galvanized steel bands. The tank manufacturer shall furnish insulating supports. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 19 / 32 Expansion joints shall be insulated with detachable, two piece or multi part combination caps. The insulation mats are to be secured in the sheet metal caps by means of hooks and clips. 10.4.3 VIBRATION Impermissible transmission of vibrations shall be prevented, or at least reduced, by mounting equipment on vibration isolators and, as far as possible, by decoupling pipelines to and from the equipment. Moreover, all plant components shall be so designed that impermissible flowing media cannot cause high vibrations. 11 LUBRICATION The equipment design shall ensure cross contamination of lubricants into the process fluid is not possible. 11.1 FIRST FILL & FLUSH Flushing and first fill of lubricating oil or grease for all parts of the work shall be provided with the equipment. 11.2 RECOMMENDATION BY SUPPLIER A list of recommended oils and greases, frequency and method of lubrication for the equipment shall be provided and included in the equipment Manual. 11.3 GREASE LUBRICATION POINTS Grease lubrication points shall be fitted with covered nipples. Greasing points shall be in an accessible position at operator level. Grease lubricator shall be fitted nipples complying with BS 1486 or an equivalent standard. Lubrication units shall be supplied clean and flushed and with all openings sealed for long storage and to be removed just before first filling. 12 PROTECTION OF METAL WORK FROM CORROSION 12.1 GENERAL The local environmental conditions at Nhieu Loc Thi Nghe Wastewater Treatment plant project site are potentially corrosive. Mechanical equipment that is not manufactured from corrosive resistant material shall be supplied with a protective coating under specifications of ISO or equivalent British / American/ Japanese Standards. Suppliers shall provide details of the external coatings provided including: - Surface preparation prior to coating: type, standard etc. The type of coating(s) and dry film thickness (microns). Repair and maintenance procedures. Manufacturers with international experience shall only supply coating material and their products can be obtained internationally. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 20 / 32 Regarding maintenance work (storage), application and supervision of coating work, choice of coating suppliers should be minimized. At any rate, similar parts of structures/components (such as structural steel containers, piping, etc.) shall only be coated with products of one individual manufacturer. The materials and equipment used, the methods of application and the quality of work shall at all times be subject to the inspection and approval of the Employer or his Representative. 12.2 SURFACE PREPARATION AND CLEANING OF SURFACES IN THE SHOP Prior to blasting, areas have to be cleaned from: oil, grease, paint residues, splatters, mill scale, welding splashes and, welding slag. Sharp edges have to be rounded off. Contamination caused by salts, acids and alkali solutions shall be eliminated by rinsing with water up to a pH value of 6-8. The preparation of substrates shall be carried out on the basis of the specifications of ISO 12944 part 4 and ISO 8501 or equivalent British / American/ Japanese Standards. After blasting, an anchor profile of 25-50 μ shall be achieved. Blasted surfaces have to be provided with a prime coat of the considered coating system immediately after blasting. Steel work protected by shop primer after arrival on site must be cleaned of salt, sand, oil, etc. before the first coat of paint is applied on site. Shop primer damaged during transport must be rectified by blast cleaning and coating before application of the site coats. Wood surfaces shall be sanded clean. All nail holes shall be puttied and sanded before priming. If a protective coating of concrete is required, concrete shall be allowed to cure before painting. Transport and erection damages, as well as damages which result out of additional welding have to be repaired as soon as possible. The damaged areas have to be de rusted with rotating or steel brushes, abrasive wheels, abrasive blasting according to ISO 8501-1, or equivalent International Standards. 12.3 CLEANING OF PRIME AND INTERMEDIATE COATS (IF REQUIRED) To prevent contamination by mineral oil products, areas with prime and intermediate coat have to be treated with suitable cleaning agent. Cleaning has to be done free of residues, e.g. with alkaline detergents and thorough washing done with fresh water. Rusty spots have to be removed according to required purity. Metallic areas, which are provided with temporary corrosion protection, have to be cleaned. No oxidation products shall remain on the surface. Furthermore, care should be given that on hot components no destructive nor reaction products will be released when heating which could injure insulation. 12.4 APPLICATION PROCEDURE When using the provided coating material, strict adherence to all application instructions given in product data of coating manufacturer is necessary. To obtain the maximum performance, technical data as well as application instructions for the individual coating material have to be strictly followed. For a multi layer coating system, each layer has to have a different color shade in order to clearly identify number of coats applied. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 21 / 32 The last finish coat has to be applied in the specified color shade. The interval between applying the different coats has to follow the supplier's instructions. Each layer has to be cleaned and released from spray dust before the next layer will be applied. Prior to applying a further layer, the last one has to be repaired. All coatings have to be applied without retarding. Following application procedures are allowed: Prime coats by airless spray: areas like disconnection, angles, corners, etc., which are difficult to be reached, can be applied by brush or roller; Repair of prime coat by brush; Finish coats; - at works: by airless pray, roller or brush; at site: by roller or brush or airless spray. When applying coating systems by roller, rollers have to be of the kind and quality that makes an appropriate application possible. Control areas in accordance with the coating supplier's instructions have to be applied. For this procedure, a schedule for control areas has to be prepared by the Contractor and coating supplier which corresponds with the requirements of the warranty agreement. Number and performance of the control areas have to be done in accordance with ISO 12944 part 7 or equivalent British/American/Japan Standards, and have to be documented in writing. All specified dry film thickness (DFT) are minimum thickness. Checkered plates, snap plates, etc. do not have to be covered with adhesive tape, but have to be coated with stripping coat in a dry film thickness of at least 150 μm. Edging lines on steel structure have to be taped prior to application and after blasting in sufficient width or have to be protected with varnish before application. Thickness of prime coat may be 50μm max. During repairing works at site on shop primed structures, it is important that different coats will have different color shades. Number of layers have to be the same as the original coating system to be used. Application of temporary primer on structures which have to be insulated has to be in accordance with a sufficient corrosion protection for the period of storage depending on the erection time. 12.5 GALVANIZING Galvanizing work shall conform in all respects to ISO 1461 or BS 729, BS 3083 and BSCP 2008 and shall be performed by the hot dip process unless otherwise specified. It is essential that details of steel assemblies which are to be hot dip galvanized should be designed to suit the requirements of the process. They should be in accordance with BS 4479and ISO 12944. Vent holes and drain holes shall be provided to avoid high internal pressures and air locks during immersion and to ensure that molten zinc is not retained in pockets during withdrawal. Careful cleaning of welds is necessary before welded assemblies are dipped. All defects of the steel surface including cracks, surface laminations, and laps and folds shall be removed in accordance with BS 4360. All drilling, VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 22 / 32 cutting, welding, forming and final fabrication of unit members and assemblies shall be completed, where feasible, before the structures are galvanized. The minimum average coating weight shall be as specified in Table 1 of BS 729. Structural steel items shall be first grit blasted to BS 4232, second quality, (Sa 2½) or pickled in a bath, and the minimum average coating weight on steel sections 5 mm thick and over shall be 900 g/m², on steel sections 2 5 mm thick 600 g/m². Galvanized contact surfaces to be joined by high tensile friction grip bolts shall be roughened before assembly so that the required slip factor (defined in BS 3294 part 1 and BS 4604 part 1) is achieved. Care shall be taken to ensure that the roughening is confined to the area of the mating faces. Protected slings must be used for off loading and erection. Galvanized work which is to be stored at the works or on site shall be stacked so as to provide adequate ventilation of all surfaces to avoid wet storage staining (white rust). Small areas of the galvanized coating damaged in any way shall be restored by: Cleaning the area of any weld slag and thorough wire brushing to give a clean surface. The application of two coats of zinc rich paint, or the application of a low melting point zinc alloy repair rod or powder to the damaged area, which is heated to 300°C. Connections between galvanized surfaces and copper, copper alloy or aluminum surfaces shall be protected by suitable tape wrapping. 12.6 COATING SYSTEM The protecting coating shall comply at least with the table below. Coating Systems System No. 1 2 3 4 Structural steel works, piping, vessel, tanks INDOOR Structural steel works, piping, vessel, tanks OUTDOOR Up to 120 SA 2.5 Primer Finish 1 1 Zinc-Epoxy Epoxy high solid Up to 120 SA 2.5 Primer Intermediate Finish 1 1 -2 1 80 160 80 80 160 80 290 Piping, tanks etc. INDOOR and OUTDOOR, Insulated Pumps, motors, other equipment OUTDOOR Up to 120 SA 2.5 Primer 1 Zinc-Epoxy Epoxy high solid 2-Comp. Polyurethane Zinc-Epoxy 50 50 Up to 120 or according manufacture standards SA 2.5 Primer Intermediate Finish 1 1 1 Zinc-Epoxy Epoxy high solid 2-Comp. Polyurethane 80 110 50 80 110 50 240 Zinc-Epoxy Epoxy high solid 80 50 80 50 130 Zinc-Epoxy 75 75 Zinc Ethysilicate Silicone Acrylic 75 50 75 100 175 Pumps, motors, other equipment INDOOR Up to 120 6 Piping, reactors OUTDOOR Insulated Stacks OUTDOOR >120 7 Dry film thickness (DFT) per coat μm 80 80 Surface preparation 5 VN01C2-ME-RP-1001 <120 <200 Coating system No. of coats Temperature (°C) Surface location Or according manufacture standards SA 2.5 Primer 1 Finish 1 Or according manufacture standards SA 2.5 Primer 1 SA 2.5 Primer Finish 1 2 Generic type Total DFT μm 80 80 160 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 23 / 32 Coating Systems System No. Surface location Temperature (°C) Surface preparation 8 Steel surfaces Uninsulated 200 -450 SA 2.5 9 Galvanized surface Up to 120 10 Steel surface permanently in contact with water, also seawater splash zone Medium temperature up to 69 oC Mechanical cleaning from contaminants and zinc salts by means of washing or steam jetting or sweep blasting with fine sand SA 2.5 Coating system No. of coats Primer Finish 1 2 When finish coat is required, such as sea climate with chloride exposure 1 Prime and finish coat in one 1 Generic type Zinc Ethysilicate Silicone Acrylic Epoxy high solid* Glassfake reinforced High solid epoxy Dry film thickness (DFT) per coat μm 75 25 Total DFT μm 75 50 125 125 125 500 500 12.7 DESIGN CORROSION CONTROL & DURABILITY Proper planning and careful attention to corrosion protection at the design stage are essential to minimise corrosion and simplify future maintenance. All design work therefore has to be performed with corrosion prevention in mind by avoiding sharp edges, crevices, rough welds, corners, depression and pockets dead legs and areas subject to stagnation. The detailed design should as far as possible avoid all features which would make it possible for water or foreign matter to accumulate, and therefore accelerate the failure of coatings. Where this is not possible, drainage holes should be provided or flushing methodology proposed. The structure should be designed to facilitate the application of maintenance coatings in the future. Examples of design shortcomings that are to be avoided are as follows: VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 24 / 32 Poor access, back to back angles, sharp corners and profiles should be avoided to ensure adequate surface preparation, access for coating is provided. Figure 1- Effects of design on the painting and cleaning of structures Structural members should allow good drainage i.e. be designed to avoid retention of fluids. Figure -2 - Effects of design on drainage Ensure gaskets are well fitted with no overhang or under-hang which can create crevices and promote crevice corrosion, especially in stainless steels. Figure -3 - Effects of untrimmed gaskets VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 25 / 32 Particularly important for metallic vessels, it is imperative that the design does not allow the accumulation of liquids under the base of the tank. Figure -4 - Effects of poor drainage Similar to fig 12-4 above, tanks should be designed as free draining. Important for coated steel tanks, but equally important for non-metallic and stainless steel tanks, as concentration effects can significantly change the corrosion characteristics of the fluid. Figure-5 - Effects of poor drainage Structural components should be designed to avoid retention of fluids. Figure-6 - Effects of poor drainage VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 26 / 32 13 PRE-SERVICE CLEANING AND PROTECTION OF SYSTEM EQUIPMENT This clause covers mechanical and pre service cleaning and protection of the items and equipment at the Manufacturer's workshop and at site that are not subsequently to be painted. Mechanical cleaning as opposed to alternative chemical cleaning is the preferred method for workshop cleaning except where this is precluded by design or access considerations. Machined surfaces shall be protected during the cleaning operations. For re cleaning, small areas, hand cleaning by wire brushing may be permitted. Wire brushes used on austenitic materials shall have austenitic steel bristles. Austenitic stainless steels, copper and aluminum alloys, cast iron, bimetallic and metallic/plastic items, and components fabricated by spot welding or riveting shall not be chemically cleaned. All weld areas shall be suitably stress relieved before chemical cleaning. 14 SAFETY The consideration of personnel safety during construction, ongoing operation and maintenance, in the design, selection and installation is paramount. It shall assure safe operation and provide adequate access for maintenance activities, minimize consequence due to fire and avoid congestion. 14.1 PROTECTION OF PERSONNEL Emergency showers, eye wash stations and emergency deluge bays shall be designed, specified and located to suit each particular circumstance and to maximize their effectiveness. Water temperature, deluge rate and coverage, supply pressure, accessibility and remote indication of use shall be considered. All piping trenches or drainage trenches shall be covered to minimize accidental fall risk. Openings in the grating shall be enclosed in handrails. 14.2 SAFETY OF MACHINERY All packaged equipment shall fully meet the safety standards of the Socialist Republic of Vietnam. All guards, notices and warning lights necessary to afford protection from electrical apparatus, conductors, moving parts of machinery, hot surfaces etc. shall be provided to prevent risk of injury to personnel. 14.3 INTERLOCKS Inspection doors shall be provided by the Supplier where required for routine inspections. All guards shall be capable of being removed without disturbing other parts of the plant. All inspection doors shall be fitted with interlocks that shall prevent the machines from running when opened if not adequately guarded or other means to prevent injury to personnel. 14.4 INSPECTION OPENINGS Inspection openings shall have warning signs to advise personnel of potential hazards that may be exposed when opened. Where equipment must be isolated, drained, depressurised or any other procedure to make equipment safe for inspection, e.g. confined spaces, this shall be stated on the warning notice at the opening. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 27 / 32 Inspection openings that may expose potential hazards which cannot be adequately controlled by “Basic PPE” shall not be operable by hand without the use of tools or keys. For the purposes of this requirement “Basic PPE” means safety glasses and earplugs. 14.5 COUPLING GUARDS Coupling guards shall be provided and shall be rigidly fixed over the coupling. The coupling guard shall be designed so that it can be readily removed. No body parts shall be able to come in contact with rotating parts. Guards shall be made from materials complying with the durability requirements to provide the asset life. 15 FASTENERS 15.1 MECHANICAL FASTENERS 15.1.1 MATERIALS All fasteners shall be of materials suitable to achieve the durability specified herein. The type of fasteners to be used in plant depends on their location and environment as specified in equipment data sheets. In general fasteners for mechanical plant shall be corrosion resistant stainless steel, except for equipment with type test certificates such as electric motors where surface coating protection is to be provided. Unless stated otherwise the following fasteners shall be used: - Metal fasteners of dissimilar metals from the base structures must be isolated to minimize the possibility of galvanic corrosion. All fasteners including bolts, studs, nuts and washers shall be marked to be able to identify and segregate different grades of stainless steel Where stainless steel fasteners are used in contact with HDG, insulating washers or joints are required. Bolting should comply with AISI316 or a similar recognized international standard. 15.2 PASSIVATION OF STAINLESS STEEL FASTENERS Stainless steel fasteners shall be passivated after manufacture and prior to installation. 16 ERECTION MARKS All apparatus and fittings shall be marked or stamped or otherwise permanently labelled before leaving the site where the equipment has been fabricated. This shall be a distinguishing number and/or letter corresponding to the distinguishing number and/or letter drawings or material list. The identification of component members shall correspond to the distinguishing numbers and/or letters shown on approved drawings and shall be in the location shown on these drawings. The erection marks shall be clearly legible after galvanising or painting and shall be legible from a distance of at least 2 metres. Where stamps are used to identify components the stamping must be ringed with paint to assist location. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 28 / 32 17 LABELS Each installed equipment shall be labelled for permanent identification. All labels, nameplates, instruction, and warning plates shall be securely fixed to items of plant and equipment with stainless steel rivets, plated self-tapping screws or other means except adhesives. All inscriptions shall be in the English and Vietnamese language. For safety signs ISO 3864 (Safety Colours and Safety Signs Information) shall be applied. 18 PIPELINE IDENTIFICATION Pipe Markers in the form of appropriately coloured printed labels shall be affixed on all pipes according to ASM A13.1 or BS 1710 – Specification for Identification of Pipelines and Services . The printed labels shall show words indicating the contents of the pipe and any associated hazardous aspect of the pipe, e.g. high pressure, toxic, strong acidity. The letters shall be in a colour that is clearly visible, identification code for pipeline according to media, with the German colors tone system RAL 840 HR. Arrows shall be provided to show the direction of flow. The outside surfaces of pipes shall not be painted to provide identification of their contents. Painting of pipes can create significant quantity of future maintenance work and is also inappropriate for some applications (stainless steel pipes). Furthermore, when utilising the colour coding, in some cases different services will be given the same identification colour as a large variety of chemicals will be used at this plant. Instead of painted pipe, localized paint marks or colour stickers shall be used. The labels shall be both UV and weather resistant and shall not fade or need replacement more frequently than once every fifteen years. Piping shall be marked on both ends. 19 NAMEPLATES Nameplates for plant and equipment identification and record purposes shall be manufactured from stainless steel or aluminum with a mat or satin finish, and engraved with black lettering of a size which is legible from the working position. Warning plates shall be manufactured from stainless steel or aluminum engraved red white lettering on a white background and sited in the position where they afford maximum safety of personnel. All equipment within panels and desks shall be individually identified by satin or mat finish stainless steel or aluminum labels, or laminated plastic labels to the extent approved by the owner's Project Manager. Nameplates fixings shall be such as to allow ready replacement without damage to the label or the fixing. Adhesive nameplates should avoided unless specific advantages for particular applications. The label shall be affixed to the specific item of equipment so that it may be conveniently read when in the installed position and should be attached to a principal component of the equipment item so that it is not misplaced or inadvertently discarded on a replacement part during overhaul. Pump casing hydrostatic test pressures and serial number shall be stamped on the casings and the direction of rotation of pump shall be clearly indicated by an arrow cast on the castings. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA Rev. A Date 2020-07-31 Page 29 / 32 Each valve shall be fitted with a stainless steel or aluminum nameplate indicating the valve service and reference number. Valve direction of closure should be clearly and permanently marked on the hand wheel. Information shall be provided by the Supplier for the various items as follows: VN01C2-ME-RP-1001 REPORT GENERAL MECHANICAL DESIGN CRITERIA DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC Cranes, davits, other lifting equipment Centrifuges, conveyors and mechanisms Heaters & coolers Mixers 30/32 Compressors, blowers Page: Filters, screens, strainers 2020-07-31 Chemical plant Date: Tanks & other vesselsA A Venturi’s, ejectors, diffusers, flowmeters Rev: Pumps AVJ-A000-ME-RPT-1001 Valves, penstocks Equipment→ Ref: Manufacturer X X X X X X X X X X X Model / Type X X X X X X X X X X X Serial number X X X X X X X X X X X Nominal size / capacity X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X ↓ Parameter X Design standard X X Hydrostatic test pressure X X Flange Specification X X Design Pressure (bar) and temperature (°C) Material X NPSHr (m) at duty point X Relief valve pressure set point X X X X Flow rate (m3/h) X X Discharge head (bar) X X Speed (RPM) X Voltage/Phase/Hz X X X X X X X X X X X X X Duty point power (kW) Year, country of manufacture X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X Impeller diameter (mm) Suction and discharge diameters (mm) Mass (empty/ full) X X X Safe Working Load Note A: Other vessels include receivers, pressure vessels, surge vessels, pulsation dampers and silos. VN01C2-ME-RP-1001 X X X REPORT Ref: AVJ-A000-ME-RPT-1001 Rev. A Date 2020-07-31 Page 31 / 32 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA 20 INSPECTION AND TESTING 20.1 SCOPE The scope of the inspection and testing to validate the design shall be defined in the equipment specifications and or data sheets in the appendix called Inspection Point Program (IPP). Equipment specific inspection and test plans including the proposed workshop, factory acceptance and precommissioning test shall be submitted. This documentation shall define the responsibility matrix. All required workshop tests and factory acceptance tests of the equipment shall be performed. Equipment assemblies shall be tested as a single combined unit. 20.2 STAGES OF TESTING Workshop Tests conducted during the manufacture of the equipment. Factory Acceptance Tests (FAT) conducted at completion of manufacture prior to dispatch. FAT shall include the compilation of all Workshop Test records for the equipment. Pre-commissioning tests of equipment following completion of construction. When identified in the IPP, Acciona - Vinci (AVJ) shall advise for witness test and or witness point release. 20.3 INSPECTION POINTS PROGRAM (IPP) All test plans and procedures for workshop tests, factory acceptance tests, pre-commissioning tests as applicable, and prior to commencement of each stage of work shall be submitted by the AVJ Representative. Any additional tests that may be required to confirm that the equipment complies with the Specifications shall be performed in accordance to the mechanical equipment specific IPP’s as appended in their relevant specification and or data sheet. 20.4 GENERAL REQUIREMENTS FOR TESTING Tests and inspections, unless otherwise specified, shall be in accordance with the relevant design standard. Any deviation to PPI’s specified standards shall be transmitted for approval. All relevant information and experiences gained during tests, including readings such as flow, noise, vibration, power draw, shall be properly documented, and included in an appendix of the Operations and Maintenance Manuals and work-as-executed drawings. 20.5 FACTORY ACCEPTANCE TESTION AND INSPECTION 20.5.1 TEST PLAN AND PROCEDURE An Inspection Points Program (IPP), and procedures for Factory Acceptance Testing (FAT) and inspection covering each type of equipment to be tested are shown in the relevant mechanical equipment Inspection Points Program. VN01C2-ME-RP-1001 REPORT Ref: AVJ-A000-ME-RPT-1001 Rev. A Date 2020-07-31 Page 32 / 32 Leader DESIGN, BUILD AND OPERATION OF THE NLTN WWTP, HCMC GENERAL MECHANICAL DESIGN CRITERIA 20.5.2 FAT AND INSPECTION REPORT All documentation, including IPP’s, material certificates and performance curves shall be included in the Factory Acceptance Testing and Inspection Report. A copy of the final version of this report shall be included as an appendix of the relevant Operation and Maintenance manuals. 21 PRE-COMMISSIONING 21.1 PRE-COMMISSIONING INSPECTIONS AND TESTS A pre-commissioning inspection and test plan for the equipment shall also be provided for the equipment in the commissioning manual. Pre-commissioning entails conducting tests and simulations for the purpose of proving that a particular piece of equipment, part of the plant or a component is complete, fully functioning and ready for operational/performance tests and operation. Pre-commissioning includes dry testing and wet testing, including all aspects of component operation such as hydraulic, electrical, mechanical, instrumentation, software and control systems associated with or linked to the Component. VN01C2-ME-RP-1001