Load Flow Analysis simulation using Power World simulator BAGUMA KEVIN – MEE231025 Faculty of Electrical Engineering Universiti Teknologi Malaysia Johor Bahru, Malaysia bagumakvn20@gmail.com Abstract—This document describes the IEEE fourteen bus power system setup with connected loads, synchronous condensers, transmission lines, generators and capacitor banks. Power World simulator is used to perform the load flow analysis and the per unit bus voltages, real and reactive power flows are determined for the simulated system. Keywords—Load flow analysis, power system, Power World Simulator. I. INTRODUCTION Load Flow Analysis (LFA) is a study that is aimed at determining the power flows, currents and voltages in a power system (PS) under steady state. Every power system consists of at least synchronous generators, transformers, transmission lines and various types of connected loads. A power system is connected to ensure that it supplies reliable power that is within the acceptable voltage and frequency limits to the customer in real time. During normal operation, there is need to determine the steady state system voltages, currents and the real and reactive power flows for the connected system. Unlike traditional circuit analysis, power flow studies use simplified notations such as single-line diagrams and the per unit system, and focuses on the various forms of AC power i.e., real, reactive and apparent rather than voltage and current. The most important use of load flow studies is in the planning for the future expansion of power systems as well as in determining the best operation for the existing systems [1]. This work is based on simulations using the Power World simulator which provides the results of the system parameters under study. II. THEORY In a network, the transmission lines, transformers and reactances are modelled by their linear equivalent circuits but for generation and load demands at the buses, non-linear electrical characteristics are present. For digital simulations, a number of algorithms have been developed for digital power flow solutions and with these, different methods for LFA have been developed and distinguished from each other by the speed and time of computation, storage requirement and the rate of convergence. The common power flow methods used are Gauss-Seidel method, Newton-Raphson method and the Fast Decoupled method [1]. The main points of concern in a LFA are: • Determining the voltage magnitude and phase angle at each bus. • Determining the active and reactive power flows in each line. At each bus, there are always two variables that are defined and the other two are always unknown and need to be determined. The variables are: voltage magnitude, voltage phase angle, real power injection and reactive power injection. In a power flow analysis, three types of network buses are encountered that is [2]; • Slack or swing bus – the voltage magnitude and phase angle are known; real and reactive power injections are unknown. • Generator or voltage-controlled bus – this is also called the PV bus where the real power injection and voltage magnitude are known; voltage phase angle and reactive power injection are to be determined. • Load or PQ bus – the real and reactive power injections are known; voltage magnitude and phase angle are unknown. This document therefore presents details of the IEEE 14 bus one-line diagram setup with connected loads, generators, synchronous condensers, transmission lines and capacitor banks. Power world simulator was used the LFA task as described. III. SIMULATION SETUP In the Power World simulator, the components of the IEEE 14 bus network system were set all set to the initial values. Generator buses were modelled and initialized with their real power injections and voltage phase on a system base apparent power of 100MW. The selected system nominal voltage was 138kV for which the per unit (P.U) voltages at the buses were determined. Table 1: Initial P.U bus voltages and bus loads Table 1 above indicates the initial P.U bus voltages and the different loads that were connected to the load buses. BAGUMA KEVIN – MEE231025 The buses were clearly distinguished from one another by the initial settings. This created the slack bus, PV and PQ buses for the network as shown. Table 4: Transmission line parameters Table 2: Bus types All that information was used to design the IEEE 14 bus system in Power World simulator software as illustrated. For each of the buses, the P.U voltage limit was set so as to help in monitoring the stage when iterations are made with the simulation software. A deviation of ±6% was used to set the limits within 0.94 and 1.06 P.U. Any values within that range are acceptable and the system operation is normal for this scenario. The following table indicates the set limits. Table 3: P.U bus voltage limits Interconnections between the different system equipment was done with transmission lines. The transmission lines were modelled with per unit values of reactances, resistances and line charging. For interconnections where a transmission was introduced, the transformers were well initialised with tap ratios indicated as below. Figure 1: IEEE 14 bus simulation setup BAGUMA KEVIN – MEE231025 IV. RESULTS AND DISCUSSIONS In the run mode of the simulation software, the base case power flow was run. Upon completion, bus bar per unit voltages were determined. Also, the real and reactive power flows in the transmission lines were determined as indicated. With use of the limit monitoring option, it was discovered that all the per unit bus voltages on the system nominal voltage were within the acceptable range for proper system operation. The limits are indicated in the table below. Table 6: P.U bus voltage limit monitoring The real and reactive power flows after running the base case scenario are extracted and shown below. Table 7: Real and reactive power flows Figure 2: P.U bus voltages and line flows The following table clearly indicates the per unit bus voltages after running the base case scenario. Table 5: P.U bus voltages The real and reactive power line flows were extracted into an excel sheet and the required per unit values computed as shown in the table below. BAGUMA KEVIN – MEE231025 Table 8: P.U real and reactive power computations Real and reactive line flows From Name Bus 1 To Name Bus 2 MW From 158.7 Mvar From -24.1 PU MW flow 1.587 PU Mvar flow -0.241 Bus 1 Bus 5 75.6 5.3 0.756 0.053 Bus 2 Bus 3 74.4 -1.5 0.744 -0.015 Bus 2 Bus 4 56.1 1.1 0.561 0.011 Bus 2 Bus 5 41.5 3.7 0.415 0.037 Bus 3 Bus 4 -22.4 12.4 -0.224 0.124 Bus 4 Bus 5 -60.3 14.3 -0.603 0.143 Bus 4 Bus 7 27.8 -2.9 0.278 -0.029 Bus 4 Bus 9 16.0 1.8 0.160 0.018 Bus 5 Bus 6 44.6 12.9 0.446 0.129 Bus 6 Bus 11 7.6 4.9 0.076 0.049 Bus 6 Bus 12 7.9 2.7 0.079 0.027 Bus 6 Bus 13 17.9 8.0 0.179 0.080 Bus 7 Bus 8 0.0 -9.4 0.000 -0.094 Bus 7 Bus 9 27.8 4.8 0.278 0.048 Bus 9 Bus 10 5.0 3.0 0.050 0.030 Bus 9 Bus 14 9.2 2.8 0.092 0.028 Bus 10 Bus 11 -4.0 -2.9 -0.040 -0.029 Bus 12 Bus 13 1.7 0.9 0.017 0.009 Bus 13 Bus 14 5.9 2.6 0.059 0.026 V. CONCLUSION The simulated IEEE 14 Bus system above was operating with the busbar voltages within the acceptable ranges and thus the system was stable. VI. REFERENCES [1] M. W. Mustafa, Power System Analysis, Esktop Publisher, 2023. [2] Corry B., Weedy B.M., Electric Power System, 5th Edition, John Wiley & Sons Ltd, 2012. BAGUMA KEVIN – MEE231025