Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 Efficient Power Flow on Direct Current Transmission Lines Using the Load and Component Sizing Technique Igbogidi, O. N., *Amadi, H. N. Department of Electrical Engineering, Rivers State University, Port Harcourt, Nigeria Corresponding Author E-Mail Id: hachimenum.amadi@ust.edu.ng ABSTRACT Due to losses, hazards and cost implications inherent in the use of alternating current systems, the benefits surrounding the use of direct current are so large that it is imperative to explore the technology of direct current, especially on transmission lines. The use of direct current has become so attractive with its attendant benefits and that is the reason a 132kV direct current transmission line from Afam power station to Port Harcourt Mains was proposed. A bipolar direct current link was designed between Afam and Port Harcourt Mains with full utilization of load and component sizing mathematical approach embedded in Electrical Transient Analyzer Program (ETAP) 19.0.1 software. Load flow analysis was conducted on the network after design where buses 1, 2, 3 and 4 maintained total loads of 31.557MW, 31.401MW, 31.341MW and 31.123MW with a total generation of 31.431MW and a total load demand of 31.123MW, the line still having the capacity to evacuate more energy. The design has proven to be valid and is sufficiently adequate. Furthermore, it encourages migration from alternating current mode to direct current mode at some point as no significant losses are observed. Keywords: Direct current, bipolar direct current link, Power flow, load and component sizing technique, power quality INTRODUCTION The transmission and distribution of electricity in the form of direct current electricity are historically linked to the late 19th century [1], though with less efficiency because the possibility of stepping up the already generated low voltage was not easy. It became very obvious that alternating current was accepted after all, less power loss occurred and generated low voltage could as well be transformed to higher voltages. Based on the said advantages, the generation, transmission and distribution of electricity have been based on alternating current technology. All over the world electricity has been seen as a very important driver of the economy in all areas and therefore, the power system has been developed vastly over the years. HBRP Publication Page 1-9 2024. All Rights Reserved Nowadays, electricity in large quantities can always be transmitted to distant areas i.e. from remote power stations to urban load centres. The disadvantage of relying solely on alternating current electricity is the problem of voltage instability and voltage regulation constraints. The first commercial or large size of high voltage direct current transmission link was of a monopolar configuration with sea return connecting the Swedish mainland and the Island of Gotland with ratings as 20 MW, 200 A and 100 kV. The link came into being in 1954 [2] Electricity is vital to socioeconomic and technological advancements as acknowledged by the Millennium Development Goals and the World Summit on Sustainable Development [3]. Page 1 Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 For a nation to advance technologically, electricity must be sufficiently available to satisfy all loads connected to it or planned to be connected to it. Several commitments depend on the power systems to drive the economy for the benefit of mankind without which the nation will be behind the time technologically. Such that depend on electricity to function may include water, education, charging of mobile phones and computers, entertainment, sanitation, lighting, healthcare, communication, etc. [4]. In any case, electricity can be in the form of alternating current or direct current. Each of the systems has a standardized order or specifications to follow to produce the most reliable power system. Generally, high-voltage direct current systems are preferred over alternating current systems when long distances are considered [5]. Transmission and distribution lines connect generation stations to the consumers. For economic reasons, power is usually transmitted from generating stations at high voltages over a long distance to high-load centres and after that distributed to various substations at various locations through distribution lines [6]. The construction of the various substations depends largely on available resources. Based on the attendant advantages of direct current systems over alternating current systems, a 10 km high voltage direct current link from Afam power station to Port Harcourt mains transmission station was proposed. The proposed HVDC line is rated 132kV. The intention is to design a system that will allow for an efficient flow of power irrespective of the fact that generation and distribution are alternating current systems. RELATED WORKS The operation or implementation of a direct current 132 kV transmission line HBRP Publication Page 1-9 2024. All Rights Reserved usually requires the involvement of high voltage power cables usually installed underground or suspended on tall or high transmission towers. Towers designed for direct current transmission lines are always taller and smaller in number than the ones found on alternating current transmission lines. Direct current systems can be used over a long distance without intermediate transformation points. HVDC transmission lines stand very tall in modern power transmission systems as efficient and reliable transfer of bulk power over a long distance is possible. Several substations and power components that are capable to transform and maintain the different voltage levels are usually installed between the generation stations and the power supply users [8]. Electricity is always generated at low voltages and not at high voltages. Due to losses inherent in the transmission of power, it is comparatively better and more economical to transmit power at high voltages. Consumers are supplied with power at low voltages [7]. It is possible to choose between high voltage direct current and high voltage alternating current for transmission of power. In any case, several reasons and intentions play major roles under different conditions in deciding which one to adopt or to use a hybrid system. Every high voltage direct current transmission system has its peculiar reasons why it is intended. Some of the reasons are technical which may include: asynchronous connection, increased system reliability, high controllability, inadequate short circuit current, small corona loss and radio interference, small potential stress, small reactive power need, fast change of power flow, etc. Economic reasons for the choice of HVDC are less investment cost, simplicity and cheap, reduced losses, stage construction and Page 2 Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 environment friendly, etc. with little constraints such as converters being relatively high in price, high converter reactive power needs, converters generation of harmonics by converters, etc. Specifically speaking, loss levels increase with distance in a high-voltage AC system than in a DC system. High voltage direct current transmission line design anchors on several factors such as transmission voltage, sag and tension, location of the line, conductor type and size, line supports and cross-arms, span, configuration of conductor, spacing and clearance, insulation, etc. Mechanical strength and electrical properties are important factors in the design of the HVDC system when selecting insulators [9]. The grid or earth mat is placed in the earth at each terminal for the protection of the equipment from over voltages and for the safety of personnel by connecting the equipment’s earth terminals and the neutral of the converter transformers to the earth mat without a known metallic link between ground electrodes and earth grid. Comparatively, a high-voltage direct current system is cheaper than its corresponding alternating current system when used over a long distance referred to as the break-even distance [10]. MATERIALS AND METHOD Materials Several data paramount and helpful in the design of a hitch-free power flow were made available. The design is a proposal of a 132kV direct current transmission line radiating from Afam to Port Harcourt mains transmission station. All materials connected to the design completion of an operatable DC link were considered for the design proposal. Method A trending mathematical formulation known as the load and component sizing method was utilized to accomplish the design of the proposed 132kV direct current transmission network from Afam to Port Harcourt mains. A line measuring about 10km and proposed to be of Aluminium Conductors Steel Reinforced (ACSR). Existing equipment capacities and proposed equipment capacities are all captured accordingly. Table 1: Data Considered for the HVDC Line Design [11]. S/No Parameter Dimensions/UNITS 1 132kV Transmission line route length (Afam to PH) 10km 2 Afam Power Station Transformer T1 150MVA 3 Port Harcourt Mains Transformer T1 60MVA 4 132kV Line Peak Load 80MW 5 Type of Conductor ACSR 6 Size of Conductor 350mm² 7 Resistivity of Conductor at 20°C 8 132kV Line spacing on 132kV Line 9 PF 10 Base MVA Source: Transmission Company of Nigeria (TCN). 2.83x 0.8 100 - Table 1 shows the materials for the proposed Afam/Port Harcourt Mains 132kV direct current transmission line and is diagrammatically presented in Figure 1. HBRP Publication Page 1-9 2024. All Rights Reserved Page 3 Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 Fig. 1: Single Line Diagram of the Proposed Afam/Port Harcourt Mains 132kV Direct Current Transmission Line [11]. 3.3 Proposed Afam/Port Harcourt Mains 132kV Direct Current Transmission Line According to Igbogidi et al. [11], for a cylindrical conductor with DC flowing round it, the DC resistance is: l (1) Where, is conductor resistivity at a given temperature in is conductor length in m A is a conductor cross-sectional area in m² Assuming cross-sectional area, A is Diameter, d Also d d r /m (2) (3) r (4) From eqn. 3, the radius can be calculated thus: r d (5) Per kilometre reactance of one phase can be realized with: log r HBRP Publication Page 1-9 2024. All Rights Reserved (6) Page 4 Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 where is the geometric mean distance between the line conductors r is considered as the radius of conductors Line reactance X, is evaluated thus: (7) The distributed series impedance is: = j (8) The equivalent admittance may be realised thus: j (9) The following may be realized from equation (9) as: (10) and j j (11) Where Base MVA and source impedance are already established, then ource mpedance ase (12) ault If the line constants for the entire length of line are established, then transmission line constants with reference to base MVA in p.u can be realized thus: (13) ase If is the voltage at the sending end and current may be taken as: is the voltage at the receiving end the line (14) where R is the resistance of the complete transmission link. The sending end voltage becomes: *( ) + and the receiving end voltage becomes: HBRP Publication Page 1-9 2024. All Rights Reserved (15) Page 5 Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 *( ) + where is the firing angle of rectifier, is the extinction angle of inverter, is the ac side line-to-line rms voltage at the sending end, is the ac side line-to-line (16) rms voltage at the receiving end, is the commutation reactance at the sending end and is the commutation reactance at the receiving end. Then, the power transferred is thus: watts (17) Transformer full load current may be realized thus: (18) A bipolar DC link after modelling was simulated using Electrical Transient Analyzer Program (ETAP) to validate the power flow. This is synonymous with alternating current environment and is shown in Figure 2. Fig. 2: Proposed Afam/Port Harcourt Mains 132kV Direct Current Transmission Line Modelled in ETAP 19.0.1 Software [11]. HBRP Publication Page 1-9 2024. All Rights Reserved Page 6 Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 RESULTS AND DISCUSSION Results The proposed Afam/Port Harcourt Mains 132kV direct current transmission line was modelled using the Electrical Transient Analyzer Program (ETAP) 19.0.1 software. The analysis was conducted to ascertain how seamless power flow could be and implemented in direct current mode as it would have been in alternating current mode without adversely been affected by load and component placement. Proposed Afam/Port Harcourt Mains 132kV Direct Current Transmission Line Power Flow Result Summary The results realized from the proposed Afam/Port Harcourt Mains 132kV direct current transmission line power flow are contained in Table 2 and Table 3. Figure 3 shows bus loading in MW and Figure 4 shows generation and load demand curve validation. Table 2: Summary of Bus Loading. Bus Total Bus Load (MW) 1 31.557 2 31.401 3 31.341 4 31.123 Fig. 3: Graph Showing Bus Loading. Table 3: Summary of Generation and Load Demand. Generation (MW) Static Load (MW) 31.431 31.123 HBRP Publication Page 1-9 2024. All Rights Reserved Page 7 Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 Fig. 4: Graph Showing Generation and Load Relationship. CONCLUSION There is a need to ascertain if load flow is hitch-free in direct current mode, especially on high voltage transmission circuits i.e., the HVDC transmission line being used for the transmission of high voltage direct current. This was domesticated in the Afam/Port Harcourt Mains 132kV transmission line, a line measuring about 10km and can evacuate about 120MW. Most of the data needed for this research were taken from the Transmission Company of Nigeria (TCN). The line was designed based on load and component sizing principles and embedded in the Electrical Transient Analyzer Program (ETAP). After the acquisition of all the needed data, a trending method known as load and component sizing mathematical formulation was used to design a network known as the Afam/Port Harcourt 132kV direct current transmission line. In the design, a bipolar DC link was considered as its solution was embedded in ETAP 19.0.1 software. The network was subjected to a load flow scenario and it was noted that buses 1, 2, 3 and 4 maintained total loads of 31.557MW, 31.401MW, 31.341MW and 31.123MW where the total generation is 31.431MW while load demand is 31.123MW. The HBRP Publication Page 1-9 2024. All Rights Reserved power flow is seamless and without friction. Load demand is worth less than the generation. This depicts a perfect power flow scenario. Such a system will operate without power quality compromise. REFERENCES 1. Direct current. https://en.wikipedia.org/wiki/Direct_cu rrent. 2. HVDC Gotland. https://en.wikipedia.org/wiki/HVDC_ Gotland 3. Amadi, H. N. (2015). Impact of power outages on developing countries: evidence from rural households in Niger Delta, Nigeria. Journal of Energy technologies and Policy, 5(3), 27-38. 4. Debasish, M. (2019). Electricity Key to a Nations Development https://www.livemint.com. 5. Glover, J. D., Sarma, M. S., & Overbye, T. (2012). Power system analysis & design, SI version. Cengage Learning. 6. Gupta, J. B. (2009). A course in power systems. SK Kataria and Sons. 7. Ale, T.O. (2016). Electrical Services Design Lecture Note. Department of Electrical/Electronic Engineering, Page 8 Journal of Research and Advancement in Electrical Engineering Volume 7 Issue 1 DOI: https://doi.org/10.5281/zenodo.10617869 Federal University of Technology Akure, Ondo State. 8. Ale, T.O. (2015). Electrical Services Design Lecture Note. Department of Electrical/Electronic Engineering, Federal University of Technology Akure, Ondo State. 9. Charsles, J. K. (2011). Design of High Voltage Direct Current (HVDC) Line from Ethiopia to Isinya, Kenya. 10. Larruskain, D. M., Zamora, I., Mazón, A. J., Abarrategui, O., & Monasterio, J. (2005, July). Transmission and distribution networks: AC versus DC. In 9th Spanish-Portuguese Congress on Electrical Engineering (pp. 1-6). HBRP Publication Page 1-9 2024. All Rights Reserved 11. Igbogidi, O. N., Amadi, H. N., Ekeriance D. E. (2013). Analysis of High Voltage Direct Current Transmission Lines Bus Voltages Using Load and Component Sizing Method. Journal of Recent Trends in Electrical Power System, 7(1), 1-9. Cite as : Igbogidi, O. N., & Amadi, H. N. (2024). Efficient Power Flow on Direct Current Transmission Lines Using the Load and Component Sizing Technique. Journal of Research and Advancement in Electrical Engineering, 7(1), 1–9. https://doi.org/10.5281/zenodo.10617869 Page 9