Week 05-2024 JDL Activity Report

advertisement
Initial
JDL
Week No.
5
Date Cut-In
29-Jan-24
WEEK 05 - 2024
Date Cut-Off
4-Feb-24
Date Prepared
3-Feb-24
ENGINEERING DEPARTMENT
JHUN MICHAEL D. LOCUS
Checked by
ASS
CAVITE PHILIPPINES OFFICE
PROJECT ENGINEER
Submitted To
RDE
DAILY ACTIVITY REPORT
Specific Job
Notes & Remarks
Date
Project
29-Jan-24
22024
Size Press Kitchen Tanks & Stand
8:00 AM. - 5:00 PM
Continue
30-Jan-24
22024
Size Press Kitchen Tanks & Stand
8:00 AM. - 5:00 PM
Continue
20021
PM2 Vaccum Chamber Hole Cover Fabication - Conceptualize
31-Jan-24
20021
PM2 Vaccum Chamber Hole Cover Fabication layout
8:00 AM. - 5:00 PM
Checked
1-Feb-24
22024
Size Press Kitchen Tanks & Stand
8:00 AM. - 5:00 PM
Continue
2-Feb-24
22024
PM4 Vacuum Pumps Requirements
8:00 AM. - 5:00 PM
Submitted
-
Submitted
8:00 AM. - 5:00 PM
For checking
Worked Time
Done
PM4 Vacuum Pumps Requisition Update
3-Feb-24
20021
4-Feb-24
-
Prepared By: Jhun Michael D. Locus
Date: February 03, 2024
Checked By: Arnold S. Sapanta
Date: February 03, 2024
Week 05-2024 JDL Activity Report
Size Press Kitchen Tanks & Stand
Rest Day
Submitted To: PPI Office
Date: February 03, 2024
Evaluation and Remarks:
12-
Page 1 of 1