PAM 2018 vs PAM 2006 – Salient Point Description 2018 2006 Remark Limit of retention sum No limit of retention sum 5% of Contract Sum Issuance of Contract document and drawings Within 14days after the award of the contract. Immediately after execution of the contract. Additional V.O. clause Added ground for v.o. in “execution of temporary work” Time frame imposed No mention “execution of temporary work” as a ground for v.o. No time frame imposed It limit the time for v.o.to be deliberated with Employer Architect only need to It is limiting the power of provide reason for the Architect work not practically completed Imposition of time frame in valuation of v.o. When work not practically completed in the opinion of the Architect Reason for rejecting and provide detail for EOT When work not practically completed in the opinion of the Architect need to “specifying the incomplete work and the conditions that have not been complied with” Architect must provide reason when and rejecting EOT and provide detail when issuing EOT within a time frame Architect does not need to provide reason and detail There’s no specified limit in PAM2018, only that retention sum to be specified throughout the Interim Certificate. The default is 5% if not stated otherwise. The Employer will retain less 5% in the Interim Certificate if using PAM2018 while PAM2006 allow retention of 10% for each certificate until a maximum of 5% of contract sum. PAM2018 impose a time frame for the Architect/QS to issue the Contract document& drawings which burden the Architect/QS Risk of additional clause for the Employer It is limiting the power of the Architect and impose additional liability EOT ground for delay in providing contract document and drawings Delay in providing contract document and drawings within the time frame is ground for EOT Not a ground for EOT as no time frame set Risk of time under consultant and Employer Contractor claiming loss and/or expense Contractor may claim loss and/or expense for delay in providing contract document and drawings Contractor’s consent needed for omission and awarding to others of any PC sum item No ground for claim on this matter Risk of cost under consultant and Employer No such provision Clearly specify the rights of the Contractor, while in PAM2006, contractor can only commence legal proceeding on claiming loss due to omission of work in PC Sum Allow part of set-off amount to be disputed and other non-disputed amount set-offed. Architect to certify contractor’s breach is a condition precedence. No provision on part of the set-off amount Omission of PC sum and permission to award to others Part of amount under set-off Calling of Performance Bond Do not need Architect to certify breach Employer’s liberty to call the Performance Bond curtailed, Architect’s liability increase Note: Generally, PAM 2018 imposed time frame and more specific on the operation of the Clauses.