ZANZIBAR WATER AUTHORITY, ZANZIBAR, TANZANIA. CRUX CONSULTANT PVT LTD, DELHI, INDIA. LARSEN & TOUBRO LIMITED Project: Rehabilitation and Improvement of Water Supply System in Zanzibar - Lot - III HDPE Pipe Laying – Consideration Pipeline Type HDPE DI Pipe Dia Quantity (Mtr) Excavation (Cu. M) 75mm 49,446 Mtr 18,542 110mm 28,302 Mtr 12,764 160mm & 200mm 22,959 Mtr 14,943 250mm & 315mm 13,641 Mtr 9412 400mm & 450mm 10,565 Mtr 9957 124913 Mtr 65618 Total Length One Unit: One Excavator Operator + Two Fitter + One Butt Fusion Operator (4 Personnel) Standard Bucket capacity (Cu.M) for Excavator : 0.6 Cu. M (Considering the 80% of soil retained) No. of Strokes including swing : 75 strokes / min, Per Hour : 0.6 x 75 = 45 cu.meter Average Excavation / day ( 10 Hrs = 8 Active working hrs & 2 hrs Cushion ) : 360 Cu.M i.e. For 110 mm Pipe – 0.8 Kms stretch can be excavated & Laid in a Working day (10 hours) deploying one unit Inference: More productivity can be achieved by deploying excavator with 1Cu. M capacity bucket and maintaining pile of excavated soil next to trench which reduces the swing and increases the number of stroke. Reducing the idle hours (Cushion Hours). Adjacent activities of lowering HDPE pipes and butt fusion can be coupled with the Working hours in line with the excavation Points to be Considered: HDPE Butt fusion machine to be deployed suiting the various dia’s used at Project i.e. Commonly used Butt Fusion Machines such as Ritmo / Georg Fischer or others confirming to ASTM F2620 Butt fusion machine operator with skills to operate the machine Pipe handling shall be taken care using trolley and shouldn’t be dragged on ground Hydro test as per approved drawings & Method statement Anchor blocks to be constructed wherever necessary as per approved drawings Other Procedures as : LTCD/WET/ZANZIBAR/PQP/MECH/MS02 REV 0 ( HDPE Pipe laying Works ) shall be followed