Solar farm: siting, design and land footprint analysis .............................................................................................................................................................. ............................................................................................................................................. Abstract Solar farms are becoming a crucial part of the renewable energy mix. Yet, the literature has not reported a generalized approach to its design. In this regard, this paper attempts to provide a detailed plan of a 5MW grid-connected solar farm. In addition, the procedure to analyze the land footprint of the solar plant is also developed. At first, the main components of the solar farm are selected qualitatively. Then, using an excel spreadsheet, the sizing of photovoltaic (PV) array, inverters, combiner boxes, transformers, cables and protection devices is carried out. Finally, the land footprint analysis of the proposed solar farm was carried out mathematically. The proposed solar PV power plant comprises 13 490 numbers of PV modules with a 365-W rating. Nineteen numbers of PV modules will constitute a string. One hundred forty-two numbers of strings will be connected to an inverter of 1 MW rating. The energy output from five such inverters will be fed to the nearest electric substation using a transformer of 1 MVA capacity. The DC and AC cables having a voltage drop of less than 1% are selected. The inter-row distance and ground coverage ratio (GCR) are estimated as 1 and 0.78 m, respectively. The required number of mounting module structures is found to be 710. The proposed solar farm’s total land use requirement is ∼43768.41 m2 (around 3 acres). It was observed that the sizing of solar plant components mainly depends on the electrical parameters of the PV module and inverter selected by the designer. Similarly, the land use requirement is influenced by the inter-row distance and PV site layout. This research is expected to streamline the different approaches of solar farm design, which will be beneficial to energy professionals and policymakers. Keywords: solar farm; photovoltaic; land footprint; green energy; design * Corresponding authors: sudhakar@ump.edu.my; erdem.cuce@erdogan.edu.tr Received 18 June 2022; revised 22 August 2022; accepted 7 September 2022 ................................................................................................................................................................................. International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 © The Author(s) 2022. Published by Oxford University Press. This is an Open Access article distributed under the terms of the Creative Commons Attribution License (https://creativecommons.org/licenses/by/4.0/), which permits unrestricted reuse, distribution, and reproduction in any medium, provided the original work is properly cited. https://doi.org/10.1093/ijlct/ctac107 Advance Access publication 31 December 2022 1478 Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Sreenath Sukumaran1,2 , Kumarasamy Sudhakar3,4,5 , Ahmad Fitri Yusop2,3 , Irina Kirpichnikova4 and Erdem Cuce6,7, * 1 Centre of Excellence for Advancement Research Fluid Flow (CARIFF), Universiti Malaysia Pahang, 26300 Kuantan, Pahang, Malaysia; 2 Automotive Engineering Centre, Universiti Malaysia Pahang, 26600 Pekan, Pahang, Malaysia; 3 Faculty of Mechanical and Automotive Engineering Technology, Universiti Malaysia Pahang, 26600 Pekan, Pahang, Malaysia; 4 Department of Electric Power Stations, Network and Supply Systems, South Ural State University (National Research University), 76 Prospekt Lenina, 454080 Chelyabinsk, Russian Federation; 5 Energy Centre, Maulana Azad National Institute of Technology Bhopal, 462003, Madhya Pradesh, India; 6 Low/Zero Carbon Energy Technologies Laboratory, Faculty of Engineering and Architecture, Recep Tayyip Erdogan University, Zihni Derin Campus, 53100 Rize, Turkey; 7 Department of Mechanical Engineering, Faculty of Engineering and Architecture, Recep Tayyip Erdogan University, Zihni Derin Campus, 53100 Rize, Turkey Solar farm: siting, design and land footprint analysis 1 INTRODUCTION 1. to design and size the main components of a 5-MW gridconnected solar farm, 2. to develop a site layout for the above-mentioned solar farm and 3. to analyze the land use and footprint of the solar farm. 2 GENERAL DESCRIPTION AND OVERVIEW OF THE GRID-CONNECTED SOLAR FARM A typical grid-connected utility-scale SPV power plant consists of PV modules, combiner boxes, inverters, transformers, DC and AC cables, protection and monitoring equipment. Of these components, the power ratings and specifications of the PV module, inverter and transformers are selected first. This selection may be based on a qualitative study on the SPV market, reasonable assumptions or operational SPV projects. These components and their specifications are needed to size the SPV array and other balance of components. In addition, mounting racks or module mounting structures (MMSs) are the main non-electrical component of the SPV power plant. A pictorial representation of an SPV power plant is provided in Figure 1. SPV module: The selection of PV technology is usually based on its conversion efficiency, commercial availability, cost per watt and scale of application (MW range in this study) [16]. The firstgeneration PV technology (which includes monocrystalline and International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 1479 Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Renewable energy (RE) technology is getting attention in many countries across the world. The capacity addition of RE systems was over 260 GW in 2020 [1]. This addition is ∼50% more than the previous value. This record-breaking capacity addition occurred despite an economic slowdown from the COVID-19 pandemic. Solar energy continued to lead this RE capacity addition in 2020 [2]. This lead can be attributed to its most negligible carbon footprint, versatile applications and competitive cost. Hence, solar photovoltaic (PV) systems are expected to be seen everywhere soon [3]. A typical megawatt (MW) scale solar PV (SPV) power plant consists of PV modules, combiner boxes, inverters, transformers, DC and AC cables, mounting racks, protection and monitoring equipment [4]. Many scholars carried out the performance analysis of SPV power plants. For example, Ajithgopi et al. [5] investigated the operational performance of a 2-MW SPV power plant in India and reported a performance ratio of 73.39% and a capacity utilization factor of 15.41%, respectively. Aoun [6] carried out an energy analysis for a 20-MW grid-connected SPV power plant in Adrar, Algeria, and estimated that the average value of performance ratio, system efficiency and capacity factor was 71.71%, 10.82% and 20.76%, respectively. The detailed steps in the design and sizing of SPV are reported in some literature. Most of these documents discussed the design steps for rooftop SPV (both grid and off-grid). Shukla et al. [7] presented a detailed design of an off-grid SPV system proposed on the rooftop of a hostel building, including the procedure to size main components. Al-najideen and Alrwashdeh [8] provided an overview of the design of a grid-tied solar photovoltaic power plant for a building roof in Mu’tah University, Jordan. These authors carried out the design based on mathematical equations for specific energy. The differences in design procedures between rooftop and land-based SPV systems can be attributed to two reasons. Firstly, a typical rooftop SPV system’s proposed capacity is tens or hundreds of kWp due to rooftop constraints and characteristics (available area, slope, orientation). Secondly, the design of rooftop SPV systems is often depended on the load demand. Some academic documents or technical reports reported the design and sizing of MW scale SPV power plants. A developer’s guide prepared by International Finance Corporation highlights that the design of an SPV power plant follows some general thumb rules and specific factors of the project location, such as solar insolation, temperature, sun position, etc. [9]. A group of university researchers prepared a design document for a 60-MW gridconnected SPV power plant. This document included the plant layout, substation design and associated balance of the system. Kalita et al. [10] discussed the theoretical design procedure of a 2-MW grid-interactive SPV power plant proposed for different locations in the north-eastern part of India. In a master’s thesis by Fedorov [11], a methodology focusing on SPV market study, component selection, preliminary and detailed sizing for SPV system design proposed for a contaminated area in Falun, Sweden, was described. Since the numerical design aspects of the SPV power plant were not presented in a single source, information available from different academic sources is gathered. For instance, Choudhary et al. [12] reported the design calculations for estimating the minimum inter-row distance between PV arrays. Sreenath et al. [13] designed a PV array, inverters and transformers for a hypothetical SPV power plant in Malaysia. Ong et al. [14] collected land use data of different solar projects and concluded that 5.5 acres per MWac are required for fixed-tilt SPV power plants in the USA. Denholm and Margolis [15] estimated the land area needed to meet electricity uses from SPV in the USA and reported that a solar electric footprint of around 181 m2 area is required per capita in a baseline scenario. Only a few documents (including technical reports) discussed the complete design and sizing of MW scale SPV power plant components. The design of a solar power plant with multiple inverters (say 5 MW SPV plant) is slightly different from those with a single inverter (say 100 kWp SPV plant). None of the authors attempted to report the detailed design of a utility-scale, grid-connected SPV power plant per the author’s knowledge. Also, the area required for SPV systems reported in the literature is often based on simplified assumptions. Though SPV is a landintensive technology, little focus has been given to studying land use requirements in the previous literature. In addition, land footprint analysis of the grid-connected SPV power plant has not been reported anywhere. The main objectives of this paper are the following: S. Sukumaran et al. polycrystalline SPV modules) has good conversion efficiency, is commercially available and has a low cost per watt [17]. Hence, this PV technology is widely used in large-scale SPV installations [18–20]. Inverter: The DC energy produced from the SPV array is transformed to AC energy with the help of inverters. Central inverter and string inverter configuration are the main types. Compared to string configuration, central inverter configuration has a low cost per watt, high reliability, reduced design complexity and ease of installation. Highly efficient inverters (more than 95%) with total harmonic distortion of less than 3% is preferred. These specifications reduce electrical losses and ensure power quality (pure sine wave). The output voltage of the inverter shall be 415 V at 50 Hz (three phases). Typically, the inverter has built-in protective devices in case of an incident such as overvoltage, overcurrent, over/under grid frequency, overtemperature, lightning or surge voltage conditions. These protective features safeguard the inverter as well as the PV array from internal or external sources. String combiner box (SCB): A certain number of PV strings are connected parallel with SCBs. These boxes are covered entirely by insulated materials with an IP54 degree of protection. This is needed to withstand the sunny outdoor climate. In addition, each incoming string is provided protection components such as DC isolators, DC fuses and surge protection devices (SPDs). Step-up transformer: It steps up the inverter’s output voltage and facilitates the electric grid’s interconnection. Transformers with an efficiency of more than 95% have minimum energy losses. Oversized transformer leads to an increase in the cost head and energy losses. Typically, the maximum loading capacity of the transformer is 95%. A trip relay is activated when the rated capacity of the transformer crosses 95%. Similar to the case of the inverters, the protection devices are fixed at the input and 1480 International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 output side of the transformer to safeguard in case of an incident such as overvoltage, overcurrent, over/under grid frequency, overtemperature, lightning and surge voltage conditions. DC and AC cable: The electrical connection between PV modules, PV string and SCBs and SCB and inverter (DC input) are carried out by DC cables. Single-core DC cables with copper strands are typically used since the current flow is comparatively low on the PV array side. Furthermore, due to its exposure to sunlight throughout the day, DC cables with ultraviolet and ozone protection properties are selected [21]. In addition, the cable must withstand maximum DC voltage up to 1500 V and ambient temperature up to 70◦ C. AC cables of appropriate size facilitate energy flow from the inverter to the transformer and transformer to the point of interconnection (switchyard). Typically, Aluminium XLPE insulated cables are selected and are either paved underground or in a cable tray. Also, these cables are expected to have a lifetime of 25 years and are supplied preferably by a reputed manufacturer accredited to ISO 9001. Switchyard: This is the point at which the SPV power plant is physically connected to the electric grid (point of interconnection). Typically, the SPV power plant’s maximum capacity shall be less than 75% of the maximum demand. The main components of the switchyard include power and energy meters, current transformer (CT), potential transformer, bus bar, incoming and outgoing feeders and different AC protection systems such as circuit breakers (CBs) (SF6/Vacuum), DCfuses, isolators and SPDs. Typically, a substation consists of the following: (1) the primary transformer (if present) steps up the input of the feeder bus (say 11 kV) to the desired voltage level (say 132 kV); (2) the CT is used to obtain a suitable current for energy meters and relays (usually between 1 A and 5 A); (3) CBs and relays—when relays detect an overcurrent condition, it commands the CB to break the circuit Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Figure 1. Pictorial representation of a solar photovoltaic power plant. Solar farm: siting, design and land footprint analysis the RTU cubicle, associated cards and SCADA-ready switchgear. In addition, the requirement for wireless monitoring of plant performance through the internet is an added advantage. 3 RESEARCH METHODOLOGY 3.1 Geographical site information This study showcases a detailed procedure for designing an MW scale solar power plant. The location and plant capacity are the main prerequisites for applying the developed methodology. It is worth noting that this design procedure can be used to any location. A 5-MW capacity was chosen in this study for the ease of doing calculations. A vacant site in Madurai, India, is selected to apply the proposed methodology. This site has latitude and longitude of 9.9◦ N and 78.1◦ E. The altitude of the selected area is ∼200 m from sea level. Approximately 50 acres of vacant land is earmarked based on the Google Earth’s visual inspection. This site’s solar irradiation, temperature and wind speed are 5.10 kWh/m2 /day, 27.3◦ C and 3.5 m/s, respectively (based on satellite weather data). An overview of the main design steps developed for the SPV power plant is shown in Figure 2. The study hypothesized that an SPV power plant constitutes a fixed-tilt array installed on shadefree land with a DC capacity of ∼5 MW. Also, a Microsoft Excel spreadsheet was created to perform the calculations and design steps of the SPV power plant. 3.2 Sizing of the system The sizing and selection process of the MW-scale SPV power plant is divided into the following steps. Step 1—Selection of correction factors and DC to AC ratio: In the wake of safety concerns, the following factors are used during the sizing of the SPV system. 1. Temperature Correction Factor (FTC ): The ambient temperature slightly influences the open-circuit voltage of the PV module. The temperature coefficient of open-circuit voltage is negative for crystalline-based PV modules. Therefore, the open-circuit voltage increases with a decrease in ambient temperature. To accommodate this variation, 125% of open-circuit voltage is considered for all design calculations. This factor is mainly used for components on the DC side of the SPV system. 2. Irradiance Correction Factor (FIC ): The short-circuit current of the PV module increases rapidly with increased solar irradiation. A safety factor is needed to protect the equipment from this possible current spike at the time of exceptionally high solar insolation. All electrical components are designed with the application of an irradiance correction factor of 1.25. 3. Over Current Multiplier (FOC ): A safety multiplier of 125% is provided for all current calculations. This multiplier is added along with the irradiance correction factor. International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 1481 Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 till the normal level is averted (saving the plant from breakdown); (4) capacitor banks are installed to stabilize harmonics associated with three-phase currents to maintain above 0.90 power factor; and (5) surge arresters are needed to protect the four terminals connected to each feeder transmission line. Protection devices: These are needed to avoid casualties at times of short circuits and lightning. SPDs are employed in SCBs, inverters, transformers, switchyards, etc., to protect the equipment from high voltage surges. An SPD is required when there is no SPD in the inverter or if the distance between SCB and the inverter exceeds 10 m. In SCBs and switchyards, fuses are installed to break the circuit when overcurrent flow occurs during faulty conditions. High rupturing capacity fuses manufactured from ceramic components are typically used due to their durability and quick action. Also, CBs of different ratings are employed to protect the SPV power plant components. The widely used gas in circuit breakers is SF6 (sulfur hexafluoride). Due to its high dielectric strength, it has a high arc interrupting ability for 3–765 kV class. DC and AC isolators are also used to isolate a part of the circuit as and when needed. Earthing system: The excess current generated at faulty events such as short circuits or lightning events provides a low resistance pathway through earthing. It helps to safeguard the life and assets from electric shock, fire hazards or lightning. All the SPV power plant’s electrical components and mounting frames are protected via the earthing system. For MW scale SPV power plants, the type A and type B earthing systems are commonly used. Earth rods are the most common type A electrodes. A minimum of two rods with a length of at least 1.5 m is required per down-conductor. Also, the distance between the earth rods must be two times its length. The commonly used type B electrodes are strip conductors. It consists of a standard mesh that spans over 20 × 20 m. A combination of type A and type B conductors can be used in some instances [22]. Lightning arrester (LA) system: Lightning protection is required to protect the staff, plant components, other equipment and buildings in case of lightning strikes. Also, the initial investment for MW scale SPV power plant is significant. Furthermore, the practical difficulties associated with the repairs or component replacements are also substantial [22]. Hence, the implementation of external lightning protection systems of the large-scale PV systems is a desirable precautionary measure. The air termination system is the commonly applied lightning protection technique in SPV applications. It typically consists of a free-standing rod, isolated support and concrete basement. The basements are connected to the respective earthing pit. This system can be configured as isolated or non-isolated from the PV arrays. The isolated lightning system is typically chosen as it can resist high-risk damage from the lightning strike. Data monitoring system: A reliable method for monitoring and logging the operational data (1- or 5-min interval) is selected for MW scale SPV power plant. It consists of hardware (such as pyranometer and temperature sensor) and software components (SCADA). The weather parameters (such as solar irradiance, the temperature at different points) and electrical parameters at DC and AC sides are recorded. The provision of SCADA also includes S. Sukumaran et al. 4. DC to AC Ratio (RDCtoAC ): An essential factor is the ratio between the plant’s DC capacity and the inverter’s AC output. This ratio can vary from 0.8 to 1.2. As a trade-off, a DC to AC ratio equal to 1 is considered in the present study. In other words, all inverters’ rated AC output power is assumed to be similar to the cumulative DC power capacity of all PV modules at STC conditions. a series (Nms) to form a string. The maximum and the minimum numbers of PV modules possible in a string are calculated using equations 1 and 2, respectively: Step 2—SPV sizing and selection: The PV technology selected for the proposed SPV power plant is monocrystalline. Compared to polycrystalline technology, monocrystalline PV modules have higher conversion efficiency with a slightly higher cost per watt due to pure silicon. A PV module of the selected technology with a power output rating of 300 W or above is chosen, which aids in a more straightforward installation process and effective space utilization. A certain number of modules are connected in (2) 1482 International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 V1 Nmsmax = V3 ∗ FTC V2 Nmsmin = V3 ∗ FTC (1) V1 is the maximum value of the maximum power point tracking (MPPT) voltage of the inverter, V2 represents the minimum value of MPPT voltage of the inverter and V3 denotes MPPT voltage of the PV module. A set of PV strings is connected to the inverter’s input terminals simultaneously [7]. The maximum Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Figure 2. Flow chart for the proposed methodology. Solar farm: siting, design and land footprint analysis number of strings attached in parallel to an inverter depends on the inverter’s input current and short-circuit current of the PV module. In equation 3, the short-circuit DC current of the inverter is denoted by Iininv (SC) and the short-circuit current of the PV module is denoted by Ipv(SC). Nstrperinv(MAX) = Iininv(SC) Ipv(SC) × FOC × FIC Nstrtot = Nstrperinv × Ninv (10) Npv = Nms × Nstrtot (11) NstrperSCB = Nstrperinv NDCinpINV (12) NSCBperINV = Nstrperinv NstrperSCB (13) (3) (4) NSCBtot = NSCBperINV × Ninv The open-circuit voltage and short-circuit current of the string is calculated using equations 5 and 6. In addition, the string voltage must be less than the maximum value of system voltage. In the present study, the maximum value of system voltage is taken as 1000 V. Vstr = (VOC × Nms ) (5) Istr = Ipv(sc) (6) Vstrmax = (Vstr ) (7) Step 4—Inverter’s design and selection: It is assumed that central inverter configuration is desirable due to low cost per watt, high reliability, reduced design complexity and ease of installation. Choosing an inverter with 500 kWac or above power rating for MW scale SPV power plant is reasonable. Since RDCtoAC = 1, the collective power of the individual inverters (Pinv ) must be equal to the SPV power plant’s capacity. The number of inverters (Ninv ) required for an SPV system can be found using equation 8. The plant capacity is denoted by Pc : Ninv = Pc RDCtoAC × Pinv (8) Step 4—Transformer design and selection: Transformers with more than 95% efficiency are chosen to minimize energy losses. The transformer’s primary voltage and the inverter’s output voltage have to be equal. The required number of transformers (Ntrf ) is calculated using equation 9. Ptrf denotes the power rating of the transformer. Pc Ntrf = (9) RDCtoAC × Ptrf Step 5—SCB sizing and selection: At first, the total number of strings (Nstrtot ) needed for the SPV power plant is calculated using equation 10. The total number of PV modules (Npv ) is the product of the modules per string and number of strings. The ratio between strings per inverter and DC inputs of inverter gives (14) A certain number of strings are connected to the input terminals of SCB. The cumulative current of strings must be less than the SCB’s short-circuit current. The voltage and current at the output terminals of SCB are estimated using equations 15 and 16. Then, using equation 17, the number of PV modules connected per SCB is calculated. VoutSCB = Vstr (15) IoutSCB = Istr × NstrperSCB NpvperSCB = NstrperSCB × Nms NpvperINV = NpvperSCB × NSCBperINV (16) VinINV = VoutSCB (19) IinINV = IoutSCB × NSCBperINV (20) (17) (18) Step 6—DC and AC cables sizing and selection: Proper sizing of cables in the SPV power plant is important to ensure safety and minimize the DC side and AC side losses. The DC cable or AC cable is sized to carry the maximum current (expected) value with minimum voltage drop. The maximum value (Imax) is taken as 1.56 times the actual current for DC cable sizing. While for AC cable sizing, the cable is oversized by 25% above the continuous current than it might handle (as safety practice). Based on the maximum value of current to be carried, a cable is selected from the datasheet at first, and its cross-section in mm2 , resistance and reactance are noted (usually ohm/m). Since the DC system has positive and negative pathways, a length cable factor, n = 2, is considered. The length of the cable (Lcable ) corresponds to the distance between the start point (say component A) and the endpoint (say component B) in meters (m). Since the circuit for the AC side of the SPV power plant is not purely resistive, the power factor is taken as 0.9 in this study. It is to be noted that cos ϕ = 1 and hence sin ϕ = 0 for DC circuit. Nr denotes the number of runs in AC cable. The voltage drop (Vd ) is calculated at first. International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 1483 Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 The best value of Nms is chosen so that power input to the inverter (Pininv ) closely matches the inverter’s DC power. Pininv = Nms × Nstrperinv(MAX) the strings per SCB. Similarly, the number of SCB per inverter is estimated using equation 13. S. Sukumaran et al. Then, the percentage change in Vd is estimated with respect to actual voltage (Va ). The actual voltage (Va) for the DC systems depends on the Voc of PV modules and the number of modules in the string. The phase–phase voltage is considered as the actual voltage for a three-phase AC system. A voltage drop of less than 1% is desirable. However, a voltage drop up to 3% is acceptable. ImaxDC = IDC × FOC × FIC Pout × FOC 1.732 × VL (22) Iccc > Imax (23) VdDC = ImaxDC × Rcable × Lcable × n (24) VdAC = ImaxAC × (Rcable × cos ∅ + Xcable × sin ∅) × %Vd = Vd × 100 Va Lcable Nr (25) (26) Step 7—Protection devices sizing and selection: The proper rating of protection devices is estimated based on the system voltage and maximum current value. In SCB, DC fuses are provided for each input string of SCB for protection against over-current. Typically, DC isolators in SCBs are double-pole type, rated for DC operation, and capable of breaking under full load current. For most protection devices, the sizing depends on the maximum value of current flowing through it. Based on this value, the nearest available model is chosen. The voltage across its terminals determines the SPD and LA rating. A bidirectional energy meter consists of CT (connected parallel to load) and PT (connected across the load). As a safety measure, an overvoltage factor (1.25) is multiplied with voltage calculations. DC Fuse rating = ISC × FIC × FOC Orientation of PV modules: The orientation of PV modules for a fixed-tilt system is chosen to maximize annual energy generation (theoretical). In this regard, the PV array is fixed at an angle from the horizontal (tilt angle (θ t )), which aids in maximizing the solar collector area. Based on a review of several large SPV installations, a tilt angle equal to the site’s latitude is chosen [20]. The azimuth angle of the SPV array located in the northern hemisphere is taken as true south (or vice versa) [23]. In addition, the tilt angle can be adjusted according to weather patterns. However, it is neglected as the proposed SPV system is not seasonally tilted. The inclination of the site’s terrain is to be considered along with the tilt angle. MMS: The PV modules are mounted at a specific orientation based on the predetermined design in a fixed-tilt system. PV modules can be arranged in landscape or portrait position in MMS (or racking frame). Also, PV modules can be single-stacked, double-stacked or multi-stacked. In this study, single-stacked and portrait-fixed configuration is chosen. Since these structures are installed in the outdoor environment, it must be robust and corrosion-resistant. In addition, it must be accredited to the IP67 rating. Inter-row distance (Dr ): It is defined as the distance between two adjacent rows of PV array, which is depicted in Figure 2. The height of the PV module depends on the module length (Lm ) and tilt angle (θ t ). The length of the shadow (Lsh) at a particular time can be estimated using equation 37. The azimuth angle and altitude angle (sun’s position) of a location can be obtained from its sun path diagram. Typically, the altitude and azimuth angle of the sun on 21 December at 9 am are considered (possibility for longest shadow). The minimum value of the inter-row distance (Drmin ) is calculated [12]. The distance between the ground and lower edge of the PV module (Ho) is typically around 50 cm. H = Ho + (Lm × sin θt ) Lsh = (27) H tan θalt Dmin = Lsh × cos θaz IDCISO = ISC × FIC × FOC (28) VratingSPD = Max.system voltage (29) AC Fuse rating = Iouttrf × FIC × FOC (30) IACISO = Iouttrf × FIC × FOC (31) VratingLA = Vouttrf × FOV (32) IprimaryBE,IsecondaryBE = Iouttrf × FOC , 5A (33) VprimaryBE , VsecondaryBE = Vouttrf × FOV , 110V (34) 1484 International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 (35) (36) (37) GCR: It is the ratio of total PV module area and the ground area of the SPV array. This surface coverage index provides an insight into the land utilization of the SPV system. GCR is always below 1, typically between 0.3 and 0.7. In equation 38, Lpva is the length of PV array and Lpitch is the inter-row pitch. GCR = Lpva Lpitch 38 3.4 Land footprint analysis The land requirement of the SPV power plant can be classified as direct-impact area and total-impact area. The area needed for SPV arrays, inter-row spacing, walkway, access roads, inverter Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 ImaxAC = (21) 3.3 Site design and layout Solar farm: siting, design and land footprint analysis Table 1. Assumptions of land use requirement for SPV power plant. Values Remarks Distance between adjacent PV Modules Type of module position Number of modules per MMS Type of stacking in MMS Number of PV modules in arranged vertically in MMS Gap between adjacent MMS Road width Number of strings in a section Number of MMS lengthwise Number of MMS width-wise Area covered by inverter building Area for control room building 10 mm Portrait -s Double stacked 2 0.5 m 3m 25–60 3–10 5–10 500 m2 1000 m2 Accommodate expansion of module frame Typical configuration in SPV installations Designed as per site conditions To reduce the length of racking frame Assumption Space for walkway Aids movement of service vehicles Assumption Assumption Assumption Assumption Assumption Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Particulars rooms and other built areas is considered the direct-impact area. The entire area enclosed inside the SPV power plant site (typically protected by fencing) corresponds to the total impact area [14]. Although the land requirement varies with site conditions, an attempt is based on generalized site layout and reasonable assumptions. Table 1 provides a list of assumptions considered to assess land footprint for SPV power plants. The area calculation varies with PV technology and type of mounting (fixed or tracking). So, this area calculation is suitable for crystalline silicon PV technology-based fixed-tilt groundmounted SPV system. It is assumed that PV modules are arranged in portrait versions (Figure 3). The length of MMS, Lr (including PV modules), and width of MMS, Wr (including PV modules), are calculated using equations 39 and 40: Lr = (Wm × Nmrh ) + Dmm × (Nmrh − 1) (39) Wr = (Lm × Nmrv ) + Dmm × (Nmrv − 1) (40) Several PV arrays on the MMS are grouped to form a section (Figure 4). Nrsl denotes the number of modules mounting structure lengthwise; Nrsw denotes the number of modules mounting structure width-wise. The length (Ls) and width of a section (Ws) can be calculated using equations 41 and 42. Each row of PV array is separated by inter-row distance (Dr). Between adjacent MMSs, a gap distance is provided as a walkway (Dw). This arrangement is intended to make the maintenance activities and clean PV modules easier without disturbing the energy generation. Ls = (Lr × Nrsl) + Dw × (Nrsl − 1) (41) Ws = (Wr × Nrsw ) + Dr × (Nrsw − 1) (42) Asec = Ls × Ws (43) In the direct-impact area of the SPV plant, a number of individual sections of the PV array are arranged together. The number Figure 3. Simplified representation of shading scenario in SPV array (sample). of sections can be calculated using equation 44. It is suggested to have an equal number of modules mounting structure width-wise and length-wise. Nsec = Nstr Nrsl × Nrsw International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 (44) 1485 S. Sukumaran et al. Table 2. Bill of materials for the proposed solar farm. Parameter Value PV module Technology Peak power Configuration AC power output Number of inputs Open circuit voltage (Max) Power Primary voltage Secondary voltage Number of cores Conductor material Number of cores Conductor material Monocrystalline 365 Watts Central 1000 kWac 16 1000 V 1000 kVA 410 V 11 kV Single core Copper Multicore Aluminum Inverter SCB Figure 4. Sample representation of PV module arrangement. Transformer If Ns Number of sections, Wroad width of the road, Area covered by road infrastructure (Aroad) in PV plant area is estimated using equation 45. In a study by Fu et al. [24], the width of a typical service road in an SPV site is reported as 3 m. The overlap of the area between two adjacent PV array sections is smaller and hence neglected. DC cable Aroad = Ns × (Ls × Wroad + Ws × Wroad ) (45) The components of SPV power plants such as inverters, transformers and switchgear protection requires isolation from the external environment. Hence, separate buildings (mostly prefabricated) are erected in different locations of SPV sites. In addition, a control room is also constructed to perform SCADA monitoring, office space and battery bank. Actrl denotes the area required for the control room. It is assumed that an inverter room is provided for each section of the PV string. Ainvr denotes the area needed for the inverter room. Both of these areas include the set off from SPV array to eliminate the shading. So, the total area needed for buildings (ABA ) of SPV power plants is given by equation 46: ABA = Actrl + (Ainvr × Ninv ) (46) Considering all sections of PV array, roadway and building, the direct-impact area (ADI ) of the proposed SPV plant is estimated using equation 47. It assumed that 5% of the direct-impact area (A1 ) is needed for setback from the site boundary fencing in the wake of possible shading. Since the site landscape affects the SPV array installation, an additional 30% land area is added as a contingency. ADI = (Asec × Nsec + Aroad × ABA ) (47) AOA = 5%of ADI (48) Acon = 30% (ADI + AOA ) (49) The total impact area (ATI ) of the proposed SPV plant is calculated using equation 50. ATI = (ADI + AOA + Acon ) 1486 (50) International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 AC cable 4 RESULTS AND DISCUSSIONS At first, the design of PV array, inverters, combiner boxes, DC and AC cables and protection devices is presented. A single-line diagram and site layout of the proposed SPV power plant is also provided in this section. Finally, the results of the land footprint analysis are described. 4.1 Components sizing and bill of materials Each step-up transformer has a capacity of 1 MVA with a primary voltage of 410 V and a secondary voltage of 11 kV. A summary of selected components for the solar farm is given in Table 2. The specification of the main features is also provided in Appendix 1. 4.2 Component selection and detailed plant design The proposed 5 MW SPV power plant consist of monocrystalline SPV modules with power ratings of 365 Wp is selected for. The power conversion efficiency of this PV module is 18.4% at standard test conditions. The maximum and the minimum number of PV modules in a string are calculated to be 15 and 20, respectively. The maximum number of strings that can be connected to the selected inverter is estimated as 142. From Table 3, a string consisting of 19 PV modules is desirable for the proposed 5 MW SPV power plant because of the close match with the DC power of the inverter (1000 kW). Also, the open-circuit string voltage is below the system voltage (1000 VDC) in this configuration. The total number of strings is estimated to be 710. Hence, the number of PV modules required for the SPV power plant is approximately 13 490. A 1000-kW central inverter from a renowned manufacturer is selected as a power conditioning unit. It has an efficiency of 98%. It can operate continuously at climatic conditions between −40◦ C and 62◦ C. This inverter is capable of unity power factor at rated power. Nine DC inputs are present. The MPP voltage at 40◦ C varies from 625 to 850 V. Considering a 1000-kWac central inverter, five inverters are needed for the proper operation of the Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Component Solar farm: siting, design and land footprint analysis Table 3. Possible arrangement of PV module connection to the selected inverter. Number of PV modules in a string Max number of strings per inverter Power at inverter’s input (kW) Voltage it Inverter’s input(V) Current at inverter’s input(A) 15 16 17 18 19 20 142 777.45 829.28 881.11 932.94 984.77 1036.6 616.5 657.6 698.7 739.8 780.9 822 1601.76 Is this configuration acceptable Cable start point Cable end point Length (m) C.S.A (mm2 ) Voltage drop (%) String conductor SCB output Inverter output Transformer output SCB input Inverter input Trans input Switch yard 25 25 5 5 4 35 300 25 0.61 0.94 0.0356 0.0032 Table 5. Rating of selected protection devices for the proposed SPV system. Location Component Specification SCB DC Isolator DC SPD DC Fuse AC Fuse AC isolator LA Energy meter 1000 Vdc , 15 A, 2 poles 1000 Vdc , 40 kA 15 A 80 A 11 kV, 100 A 33 kV CT: 60/5 A, Class 1 PT: 11 kV/110 V, Class 1 Switch yard proposed SPV power plant. Each step-up transformer has a capacity of 1 MVA with a primary voltage of 410 V and a secondary voltage of 11 kV. A total of five transformers are required to step up the output voltage of the inverter. An extra 250 kVA transformer can also be considered for accommodating the variation in power factor. The energy generated will be injected to the nearest substation at 11 kV voltage level through the transmission line. Also, 16 strings are connected to an SCB whose output voltage and current are 780.90 V and 180 A, respectively. Hence, the total number of SCBs needed for SPV power plants accounts for 45. With less than 1% voltage drop, 4 mm2 DC cables are used as string conductors. From the output of SCB and input of the inverter, 35 mm2 copper cable is used. The main features of DC and AC cables for the proposed SPV system are shown in Table 4. A 300 mm2 × 7 run AC cable was selected to carry current from inverter output to transformer input. A 25 mm2 cable is sufficient to withstand the current flow between transformer output and switchyard. Selected protection devices for the proposed SPV power plant are depicted in Table 5. The single line diagram of the proposed SPV system is shown in Figure 5. The sample arrangement of MMS in a PV array section and the single line diagram of the proposed SPV system is shown in Figures 5 and 6. Figure 5. Sample representation of the arrangement of MMS in a PV array section. International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 1487 Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Table 4. Main features of DC and AC cables for the proposed SPV system. S. Sukumaran et al. 4.3 Site layout and GCR value The tilt angle for the PV array in Madurai is selected as 10◦ . The inclination of the MMS is taken as the tilt angle based on the assumption that the ground surface is flat. Double-stacked and portrait configuration is selected for PV arrays. This arrangement is typical for land-based SPV projects. All the 19 PV modules of the string are accommodated into a single MMS. Therefore, 710 numbers of MMS are required for the entire SPV power plant. For this scenario, the minimum inter-row distance to avoid selfshading is 0.93 m. Based on these conditions, the GCR for the 1488 International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 proposed configuration is 0.78. The top view and side view of the proposed PV array is shown in Figures 7 and 8, respectively. 4.4 Land footprint and cost analysis The entire 5 MW SPV farm is composed of 15 sections of PV array. Each section is spread over 2361.82 m2 approximately. It consists of 49 units of MMS arranged into seven rows and seven columns. The direct-impact area required for the solar power plant is estimated as 43768.41 m2 . An additional 30% of the land Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Figure 6. Single-line diagram for the proposed solar farm. Solar farm: siting, design and land footprint analysis Figure 7. Side view of SPV arrays for the proposed SPV layout. area is assigned to accommodate site-related space requirements. The total-impact site is found to be 59743.89 m2 or 14.77 acres. It was observed that the direct impact is located within the boundary of total land area and hence requires lesser land area than totalimpact area. Since the total impact area varies with site conditions, it is difficult to estimate its accurate value. However, the land requirement for the direct-impact area is not much influenced by the site conditions. It can be calculated based on the SPV site layout plan. Economic analysis indicates the profitability of the installed PV system. It gives an idea about the recovery of invested amount and profit gain. For the solar farm as per various databases and authors’ experience in solar farm projects, the overall cost break-up of the solar farm is presented in Figure 9. However, the cost can vary widely in different places, as each country has its policies and prices. Table 6 summarizes the various estimated financial parameters of the solar farm. Although the initial investment in the solar farm is very high, the project will be attractive with the reasonable tariff and carbon credit revenue. Based on cost calculations, the solar farm in Madurai is economically beneficial with a favorable payback period, net present value and internal rate of return. This parameter is also crucial to address the sustainability aspects of the project. 4.5 Discussions The higher power rating PV module is used in some operational SPV power plants. Many SPV installations have PV modules with a rating of 300 Wp or above. For instance, 325 W [18] and 315 W [19]. String inverters can also be employed for MW-scale solar power plants. It offers modularity, which makes maintenance easy 5 CONCLUSIONS In this paper, the detailed design of a 5-MW grid-connected solar farm is carried out. In addition, the inter-row distance and land area requirement is estimated. The following conclusions are drawn: • The proposed solar power plant comprises 13 490 numbers of PV modules with a 365 Wp rating. Nineteen numbers of PV modules will constitute a string. One hundred forty-two numbers of strings will be connected to an inverter of 1 MW rating. International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 1489 Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Figure 8. Top view of SPV arrays for the proposed SPV layout. [18]. Several 60 kW inverters are used in an SPV power plant installed in Irbid, Jordan [25]. The inter-row distance varies with the location of the SPV system. For an SPV power plant located in 32o latitude, an inter-row distance of 2 m was reported. Similarly, the inter-row distance for the SPV power plant in Eastern Turkey is 4.55 m [25]. The 2.5 MW SPV plant in Navrongo has an interrow space of 3 m to minimize the module-to-module shading [26]. A detailed step is presented in this study to estimate the land use requirement of SPV power plants. However, the value varies depending on the landscape conditions of the site on a case-tocase basis. In a study by [25], the area covered by a 5-MW SPV power plant is reported as 58 300 m2 . The 2.5-MW SPV plant in Navrongo is spread over 48562.30 m2 of land [26]. The land required for Uganda’s 10-MW SPV power plant was 34 acres or 3.4acres/MW [27]. This closely matches the area estimated for this study’s proposed 5-MW SPV power plant. Fthenakis and Kim [28] studied the average land requirements during the lifetime of RE sources and concluded that the SPV system needs the least land area. However, it is subjected to variation in regional and technological conditions. Most large-scale SPV power plants are divided into blocks to ease electrical connection. Eight main blocks are in India’s 10-MW SPV power plant [4]. Similarly, a 10-MW SPV power plant in Uganda is assembled into 43 SPV arrays in which each array comprises ten smaller units [27]. For SPV power plants near the equator, a slightly higher tilt angle can be provided to aid the self-cleaning of modules. For example, the latitude of Uganda’s 10-MW SPV power plant is 1◦ 33 N. However, the tilt angle is 10◦ [27]. An improvement in energy output occurs with the periodic cleaning of SPV modules, say twice a month. The cleaning schedule can be adjusted with the rain season. In this respect, self-cleaning thin film PV glazing systems can be considered in further works [29]. Also, a higher cleaning frequency is suggested for SPV systems located in arid/desert regions. In any type of PV//T system design, vacuum medium and vacuum glazing technologies can be utilized to minimize thermal losses [30, 31], and highly thermally dissipative extended surfaces can be preferred to enhance heat transport from surface to heat transfer fluid [33]. The total length of solar cable in a typical MWscale SPV project ranges up to few km [32]. The optimization of cable size and cable length reduces energy loss. This energysaving may be equivalent to energy generation worth a few lakhs per annum. S. Sukumaran et al. Table 6. Summary of the financial parameters. Plant life 25 years Plant capital investment cost Average sunshine hours Annual energy yield Operation and maintenance cost Inflation Discount rate Interest rate Payback period (year) NPV LCOE 2 million USD (0.400 USD/MW) 5.5 hrs 7522 MWh/year 2% 3.5% 10% 11% 4.9 0.803 million USD 8.8 cents/kWh • The energy output from five such inverters will be fed to the nearest electric substation using a transformer of 1 MVA capacity. The DC and AC cables are selected such that the voltage drop is less than 1%. It is observed that the ratings of protection devices mainly depend on current value. • For an SPV array proposed in 10o latitude and 78o longitude, the inter-row distance is estimated as 1 m. The required number of MMSs will be 710. It is observed that the length of MMS mainly depends on the number of PV modules in a string. For the proposed SPV system, this length is estimated as 10.61 m, approximately equal to the width of 10 PV modules. • Based on reasonable assumptions, the total land use requirement of the proposed SPV system is observed to be 43768.41 m2 (around 3 acres). • The design procedure presented in this study is focused on technical and safety factors. With due consideration to the market trends, component cost and availability, there is a scope to improve the developed design methodology. • The practical implication of this study is to streamline the different solar farm design approaches, which will benefit energy professionals and policymakers. In addition, the design and land footprint analysis of tracking SPV systems can be the focus of future works. 1490 International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 DATA AVAILABILITY The data and information used in this research study can be shared upon personal request to the authors. ACKNOWLEDGMENTS The authors are grateful for the financial support of the Universiti Malaysia Pahang (www.ump.edu.my) through the Doctoral Research Scheme and PGRS1903172 for the first author to pursue his doctoral research. The authors are also thankful to the Russian Science Foundation grant no. 22-19-20011 support of South Ural state university. REFERENCES [1] IRENA. World Adds Record New Renewable Energy Capacity in 2020. https://www.irena.org/newsroom/pressreleases/2021/Apr/World-A dds-Record-New-Renewable-Energy-Capacity-in-2020 (7 June 2021, date last accessed). [2] IRENA. Renewable Capacity Highlights. https://www.irena.org/-/media/ Files/IRENA/Agency/Publication/2021/Apr/IRENA_-RE_Capacity_Hi ghlights_2021.pdf?la=en&hash=1E133689564BC40C2392E85026F71A0 D7A9C0B91 (28 September 2021, date last accessed). [3] Sreenath S, Sudhakar K, Fitri YA. Airport-based photovoltaic applications. Prog Photovolt Res Appl 2020;28:833–53. [4] Shiva Kumar K, Sudhakar B. Performance evaluation of 10 MW grid connected solar photovoltaic power plant in India. Energy Rep 2015;1: 184–92. [5] Gopi A, Sudhakar K, Ngui WK et al. Energy analysis of utility-scale PV plant in the rain-dominated tropical monsoon climates. Case Stud Therm Eng 2021;26:101123. [6] Aoun N. 2020. Performance analysis of a 20 MW grid-connected photovoltaic installation in Adrar, South of Algeria. In Advanced Statistical Modeling, Forecasting, and Fault Detection in Renewable Energy Systems. Intech Open, 85–94. [7] Shukla AK, Sudhakar K, Baredar P. Design, simulation and economic analysis of standalone roof top solar PV system in India. Sol Energy 2016;136:437–49. [8] Al-najideen MI, Alrwashdeh SS. Design of a solar photovoltaic system to cover the electricity demand for the Faculty of Engineering-Mu’tah University in Jordan. Resource-Efficient Technol 2020;3:440–5. Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 Figure 9. Cost break-up % of solar farm. Solar farm: siting, design and land footprint analysis [21] Polycab. Photovoltaic Cables. https://polycab.com/wp-content/uploa ds/2019/03/SOLAR-DC-CABLES.pdf (05 March 2021, date last accessed). [22] Charalambous CA, Kokkinos ND, Christofides N. External lightning protection and grounding in large-scale photovoltaic applications. IEEE Trans Electromagn Compat 2014;56:427–34. [23] Fu R, Feldman D, Margolis R. 2018. U. S. Solar Photovoltaic System Cost Benchmark: Q1 2018. Golden, CO: National Renewable Energy Laboratory. [24] Alshare A, Tashtoush B, Altarazi S, El-khalil H. Energy and economic analysis of a 5 MW photovoltaic system in northern Jordan. Case Stud Therm Eng 2020;21:100722. [25] Mensah LD, Yamoah JO, Adaramola MS. Performance evaluation of a utility-scale grid-tied solar photovoltaic (PV) installation in Ghana. Energy Sustain Dev 2019;48:82–7. [26] Oloya IT, Jl T, Adaramola MS. Techno-economic assessment of 10 MW centralised grid-tied solar photovoltaic system in Uganda. Case Stud Therm Eng 2021;25:100928. [27] Fthenakis V, Kim HC. Land use and electricity generation: a life-cycle analysis. Renew Sust Energ Rev 2009;13:1465–74. [28] Young CH, Riffat SB, Cuce E. High capacity energy efficiency solar glass. In: The 14th International Conference on Sustainable Energy Technologies, 25–27 August 2015, Nottingham, United Kingdom, World Society of Sustainable Energy Technologies (WSSET). [29] Cuce E, Riffat SB. Vacuum tube window technology for highly insulating building fabric: an experimental and numerical investigation. Vacuum 2015;111:83–91. [30] Cuce E, Riffat SB. Aerogel-assisted support pillars for thermal performance enhancement of vacuum glazing: a CFD research for a commercial product. Arab J Sci Eng 2015;40:2233–8. [31] Cuce E, Cuce PM. Homotopy perturbation method for temperature distribution, fin efficiency and fin effectiveness of convective straight fins with temperature-dependent thermal conductivity. Proc Inst Mech Eng C J Mech Eng Sci 2013;227:1754–60. [32] First Green Consulting Pvt Ltd. Understanding of Selection of Cable and Cable Size for a Solar PV Plant. https://firstgreenconsulting.wordpress. com/2013/05/16/understanding-of-selection-of-cable-and-cable-size-fo r-a-solar-pv-plant/ (13 February 2021, date last accessed). International Journal of Low-Carbon Technologies 2022, 17, 1478–1491 1491 Downloaded from https://academic.oup.com/ijlct/article/doi/10.1093/ijlct/ctac107/6967776 by guest on 15 March 2024 [9] International Finance Corporation. Utility-Scale Solar Photovoltaic Power Plants. https://www.ifc.org/wps/wcm/connect/topics_ext_content/ifc_e xternal_corporate_site/sustainability-at-ifc/publications/publications_u tility-scale+solar+photovoltaic+power+plants (1 January 2022, date last accessed). [10] Kalita P, Das S, Das D et al. Feasibility study of installation of MW level grid connected solar photovoltaic power plant for northeastern region of India. Sādhanā 2019;44:9. [11] Choudhary A, Kumar Saxena B, Mishra S. Making Indian airports sustainable by using solar photovoltaic system: analysis of three airports. Int J Sustain Energy 2021;40:149–74. [12] Choudhary A, Saxena BK, Mishra S. Making Indian airports sustainable by using solar photovoltaic system: analysis of three airports. Int J Sustain Energy 2020;40:1–26. [13] Sreenath S, Sudhakar K, Yusop AF et al. Solar PV energy system in Malaysian airport: glare analysis, general design and performance assessment. Energy Rep 2020;6:698–712. [14] Ong S, Campbell C, Denholm P et al. Land-Use Requirements for Solar Power Plants in the United States, NREL Publications, 2013. [15] Denholm P, Margolis RM. Land-use requirements and the per-capita solar footprint for photovoltaic generation in the United States. Energy Policy 2008;36:3531–43. [16] Kim S, Lee Y, Moon HR. Siting criteria and feasibility analysis for PV power generation projects using road facilities. Renew Sust Energ Rev 2018;81:3061–9. [17] Fraunhofer Institute for Solar Energy Systems. Photovoltaics Report. https://www.ise.fraunhofer.de/content/dam/ise/de/documents/publicatio ns/studies/Photovoltaics-Report.pdf (5 June 2022, date last accessed). [18] Boddapati V, Daniel SA. Performance analysis and investigations of gridconnected solar Power Park in Kurnool, South India. Energy Sustain Dev 2020;55:161–9. [19] Cubukcu M, Gumus H. Performance analysis of a grid-connected photovoltaic plant in eastern Turkey. Sustain Energy Technol Assess 2020;39:100724. [20] Padmavathi K, Daniel SA. Performance analysis of a 3MWp grid connected solar photovoltaic power plant in India. Energy Sustain Dev 2013;17:615–25.