Project Loca on: Industriestraße 12, 67304 Eisenberg (Pfalz), Germany Request you to provide Labor es mate for the below work. Please find the below SOW requested for Labor, Rental hire, and Fire stopping works. Fiber Backbone cabling – 9 links. Provide and install single run (1) 8-strand OS2 tight buffered single-mode fibre cable from MDF cabinet in building-31 on the first floor to IDF-1 in building-31 on the first floor. Provide and install single run (1) 8-strand OS2 ght buffered single-mode fibre cable from the MDF cabinet in building-31 on the first floor to IDF-2 in building-31. Provide and install single run (1) 8-strand OS2 ght buffered single-mode fibre cable from the MDF cabinet in building-31 on the first floor to IDF-3 in the building-31 on Ground floor. Provide and install single run (1) 8-strand OS2 ght buffered single-mode fibre cable from MDF cabinet in building-31 on the first floor to IDF-4 in the building-31 on first floor. Provide and install single run (1) 8-strand OS2 ght buffered single-mode fibre cable from MDF cabinet in building-31 on the first floor to cabinet V4 in the building-11. Provide and install single run (1) 8-strand OS2 ght buffered single-mode fibre cable from MDF cabinet in building-31 on the first floor to cabinet V7 in building 12. Provide and install single run (1) 8-strand OS2 ght buffered single-mode fibre cable from the MDF in the building-31 on the first floor to the new produc on switch in the control room of building-10, 20m of coiled cable will be le coiled at the switch end in building 10 for future reloca on. Provide and install single run (1) 8-strand OS2 ght buffered single-mode fibre cable from the MDF cabinet in the building-31 on the first floor to the New switch in the Wasserglastanklage in building 30m of coiled cable will be le coiled at the switch end in building 10 for future reloca on. Provide and install single run (1) 8-strand OS2 ght buffered single-mode fibre cable from MDF cabinet in building-31 on the first floor to cabinet V6 Gienanth ground floor. Patch panels and Termina ons Provide and install (7) 1U, 6way loaded with 12 LC connectors SM OS2 Fibre panel for the termina on of the fibre cables into remote cabinet loca ons IDF1, IDF2, IDF3, IDF4, V4, V6 Gienanth ground floor, and V7. Provide and install (2) wall-mounted fibre enclosures for the new switch loca ons one in the produc on office in Building 10 and one in the Wasserglastanklage in Building 3. o A 12u wall-mounted data cabinet can be supplied and installed at each of these loca ons to house the new switch and fiber patch panel. Provide and install (36) OS2 Fibre Op c Patch Lead LC-LC Single mode 9/125 Duplex LS0H Yellow 2m to allow 2 fibre backbone links per IDF loca on. Provide and install (18) 8-strand 1m OS2 Fibre Op c LC pigtails for cable termina ons. Data and voice outlets 88- Outlets Provide and install (16) 4-pair, Category 7 LSZH orange cable runs for (8) dual data drops as iden fied on the basement floor plan from the IDF SA-14 on the ground floor, terminated into the 2-port faceplate and Cat6A data jacks. The other side of the cables is patched into the patch panel. Provide and install (62) 4-pair, Category 7 LSZH orange cable runs for (31) dual data drops as iden fied on the ground floor plan from the IDF SA-14 and IDF-3 ground floor, terminated into the 2-port faceplate and Cat6A data jacks. The other side of the cables is patched into the patch panel. Provide and install (2) 4-pair, Category 7 LSZH orange cable runs for (1) dual voice outlet for phone connec ng to building 10 produc on control room. Provide and install (2) 4-pair, Category 7 LSZH orange cable runs for (1) dual data outlet for addi onal outlet needed in Building 31 - ground floor – plan. Provide and install (2) 4-pair, Category 7 LSZH orange cable runs for (1) dual data outlet connec ng to building 10 produc on control room. Provide and install (2) 4-pair, Category 7 LSZH orange cable runs for (1) dual data outlet connec ng to building 11 Wasserglastanklager from the IDF-V3 to the produc on control room. Provide and install (2) 4-pair, Category 7 LSZH orange cable runs for (1) dual data outlet connec ng to building 31 Ground floor from the IDF-V6 Gienanth to the close to ARC office. Patch panels and Termina ons. Provide and install (7) 1U, 24-port Category 6A Patch panels in the communica on cabinets with 1U horizontal cable manager for the cable termina on across the cabinets IDF1, IDF2, IDF3, IDF4, V4, V6 Gienanth and V7. WAP Outlets 8-outlets Provide and install (6) 4-pair, Category 7 UTP LSZH orange cable runs for Addi onal WAP drops as iden fied on the first floor as per the predic ve site survey, terminated into a surface-mount box and Cat6A data jacks. The other side of the cables is patched into the new patch panel. Provide and install (2) 4-pair, Category 7 UTP LSZH orange cable runs for Addi onal WAP drops as iden fied on the second floor as per the predic ve site survey, terminated into a surface-mount box and Cat6A data jacks. The other side of the cables is patched into the new patch panel. WAP Outlets Reloca on 4-outlets Provide and install (3) 4-pair, Category 7 patch lead for reloca ng the WAP drops as iden fied on the Basment floor as per the predic ve site survey. Provide and install (1) 4-pair, Category 7 patch lead for reloca ng the WAP drops as iden fied on the second floor as per the predic ve site survey. Exis ng WAP. Mount (25) exis ng access points horizontally on the ceiling at least 1m away from walls or obstruc ons. o Exis ng/swap out APs should align with the AP Placement d floor plan. This may require extending the cable via patch lead. When hard ceilings are in play and extensive work is required to comply with this direc ve. Cable Tray and Accessories. Provide and install approx. 120mtrs 100mm wide perforated cable tray in the ground floor as per the floor plan. Provide and install approx. 55mtrs 100mm wide perforated cable tray in the first floor as per the floor plan. Provide and install approx. 100mtrs external tube in the basement floor as per the floor plan. Provide and install 2 packs of 2inch J-hooks and flexible conduit for cable rou ng inside the building on basement, first floor and second floor. Provide and install support brackets uni-strut, stud, g-clamps, nuts, bolts, and washers. Access equipment-Rental 2 x 12 tread step ladders for office areas 2 x 4m pop up for office and produc on areas. 2 x 10m electric scissor li /boom li for produc on and outside areas Scaffold for use in stairwell between buildings 31 and 41 for install of fibre and copper cable. Cutover/migra on of ac ve equipment Permi ed for a total of 6 man days (2 man days for pre-staging and prepara on); planned ahead with co-ordina on with end customer IT team to minimize down me and delays. It is assumed that most of the ac ve device movement will occur a er working hours. Decommission and removal of old data cabinets and cables Permi ed a total of 10 men for the decommission and removal of data cabinets in building 31 IDF V5 ground floor, IDF Vi ground floor, IDF V6 on the second floor, and Building-2 IDF V1 first floor, along with exis ng cables days planned to minimize down me and delays. Building -3 IDF V3 first floor along with exis ng cables days planned to minimize down me and delays, only a er the COLT line relocated to MDF. Removed equipment and cables will be handed over to the customer. Fire stopping Client has at this stage allowed to temporarily fire stop all new wall penetra ons and any exis ng penetra ons that need to be reopened. Client will provide marked-up floor plans of penetra ons made so permanent fire-stopping can be installed by others a er the cable installa on has been completed. Client can supply a qualified 3rd party company to install all permanent fire-stopping a er the cable installa on has been completed.