Report Details Date of Checkpoint Period Covered 8/2/23 + 8 days = 20/2/23 When the tech hub went live, we knew that there were errors that took 8 days to fix; they passed) 9 Jan 2023 – 20 Feb 2023 Cabling delay – Tech hub delay Document details Version Modifications 1 Author Panagiot Mechilli Date 20/2/23 Date of checkpoint report Approvals This document requires the following approvals: Name Imran Hussain COPY FROM PID <<copy from PID>> <<copy from PID>> Role Council leader Signature Date 23/2/23 Next day (check if weekend) Version 1 <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> Distribution This document has been distributed to: Name Role <<copy from PID>> Date of Issue 24/2/23 Version Name 1 Kia Hails Kia Hails Senior Software Engineer Arian Malkine Junior Software Engineer 24/2/23 1 Arian Malkine Emily Newell App Developer 24/2/23 1 Emily Newell Sophia Hurrell Senior Network Engineer 24/2/23 1 Sophia Hurrell <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> <<copy from PID>> Products Product Name Cabling – network infrastructure Work Undertaken Waited until cabling was delivered four days later Date Complete 6 February 2023 Could not install and configure technical hub software 13 February 2023 In the issues No time Say it was just delayed Installing and configuring technical hub software Can assign task to someone else Network immediately shut down and updated the scripts. (Same date as before because someone else could do it) 20 February 2023 Project Management Control (in PID) I will provide confidence to stakeholders that I have adequate control over the project’s outcomes and can respond effectively to change by: Skills: - Time scheduling (Gantt chart) Cost planning (Cost plan) Resourcing (Resources list) Risk management (Risk management plan) Communication planning (Communications plan) Document this in a Project Initiation Document (PID) BECOMES By: - Planning the project scheduling using a Gantt chart Costing the project accurately and to budget using a cost plan Resourcing the tasks efficiently and accurately using a resources list Managing risk with a Risk Management Plan that identifies risks, assesses each risk’s probability and severity, and mitigation methods for each risk. Communication planning to ensure timely and clear communication between stakeholders using a communication plan I will document this in a Project Initiation Document (PID) that will be approved by the client and sponsor and distributed to the project team. Quality Management I provided confidence to stakeholders that I had adequate control over the project’s outcomes and could respond effectively to change by: - Planning the project scheduling using a Gantt chart Costing the project accurately and to budget using a cost plan Resourcing the tasks efficiently and accurately using a resources list Managing risk with a Risk Management Plan that identifies risks, assesses each risk’s probability and severity, and mitigation methods for each risk. Communication planning to ensure timely and clear communication between stakeholders using a communication plan. I documented this in a Project Initiation Document (PID) that was approved by the client and sponsor and distributed to the project team. Just copy the Project Management Control section from PID and make it past tense. Work Package Tolerance Status Time: - 4 days for delay of networking (does not affect schedule) - 10 days for illness - 8 days for additional scripts Due to delays and issues the project has now delayed by 16 days. Cost: Quality: Add up delays in days, only what actually affected the time scheduling Put the actual dates from Gantt Chart Due to the delays, the team members were paid for these extra days at a cost of £5504 Actions were taken to ensure the quality of the deliverables met the client’s requirements. What aktions Issues log Date Raised Raised By 9/1/23 Sarah Bailey – Senior Network Engineer 23/1/23 Absent team member called beforehand 8/2/23 First day of Description Delivery of the cabling was delayed by four days. Panagiot Mehilli Project Manager The Senior Software Engineer became ill and was off during the second and third week of the project. Emily Newell – App developer Security issues arose after the network went live Action Taken Installing network infrastructure had to be delayed for 4 days. [TASK] had to be delayed for [x] days Assigned the installation of technical hub software to XXXX Date Closed 13/1/23 this required an immediate shut down and updating of the 20 February 2023 Can ignore weekend days 24 January 2023 Assigned to someone else, so closed the next day testing Anyone who did the task scripts. Lessons Learned as Project Manager, refer back to Part A ( not needed?) Talk about: (use these words) - Comms planning Risk management Scheduling Cost 2 positives, 2 negatives How do I find the lessons learned: 1) Issues log, how to prevent future issues of the same type from happening Issue 1: cabling delay - I learned that there should be more contingency time in a project schedule (Gantt chart) so that if a project resource is unavailable for any reason, the project completion is not delayed. (Contingency Time) - I learned that I should have backup resources so they can take on the role if something happens to the original resource, should they be unavailable for any reason. - I learned that it is important to have a contract with suppliers in case that the equipment is not delivered on time, that there are consequences for the supplier. For example, compensation. (reference from suppliers, reviews of previous projects) - I learned that the supplier used for the network infrastructure was not reliable, and we will not continue to use them in future projects. - I learned that the resource allocated to security, Arian Malkin, did not have the necessary skills to ensure that the security of the network was adequate. (e.g. meeting security standards of CIA – confidentiality, integrity and availability, access control is correct). And in future projects, I should train resources in advance. - I learned that the resource allocated to security, Arian Malkin, did not have enough time needed to complete the security - tasks to the required standard, and in future projects, I will ensure that Function Point I learned that the resource allocated to security, Arian Malkin, did not have the necessary support during the project needed, and in future projects, I will ensure that my communications plan has more frequent communication opportunities with key resources during vital tasks so that if issues arise, they can be dealt with more promptly. Positive lessons learned – Look at PID, risks that did not come up Scheduling - A lesson that I learned that if I could plan contingency time into my project schedule, then issues that arose that caused delays in the completion of tasks during the project, did not delay the final handover of the project. I will ensure that I plan in contingency time for expected, but also unexpected events. Comms plan - A lesson that I learned was that when communications between stakeholders are planned in advance and occurs at the necessary frequency, as I did in my communications plans, then events such as staff illness are flagged immediately and can be dealt with quickly and effectively. This ensures that the project stays on task. - - A lesson that I learned was that when I accurately and efficiently cost and resource project with a contingency budget (for situations whether the project accrues additional costs due to additional resourcing or equipment costs). Iron triangle