School of Chemical and Process Engineering CAPE3000 DESIGN PROJECT (2023-24) PART-1 (Group) REPORT, Semester 1 Carbon Capture Plant GROUP NUMBER: CEE2 GROUP MEMBERS: Faisal Kamal, Abdelrahman Abouelela, Ahmed Aldhalei, Bryn Barker, and Sari Miari Company Name: FAABS Writing to the board of Australian Energy (AE) Engineering Ltd SUPERVISOR: Timothy Cockerill SUBMISSION DATE: 14 December 2023 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari DECLARATION OF INDIVIDUAL CONTRIBUTIONS Chapter Lead author(s) [% contribution] Signature(s) Sari Miari (85%) Sari Sari Miari (70%) Sari Chapter 2: Process Route Evaluation & Selection [10%] Chapter 3: Design of Selected Process [15%] Chapter 4: Raw Materials & Products [5%] Chapter 5: Safety, Health & Environmental [15%] Chapter 6: Mass & Energy Balances and PI [50%] Other parts of the report (executive summary, introduction, conclusions, nomenclature, references) [5%] Other members contributed to this chapter. [% contribution] All members are required to contribute to this chapter Abdelrahman Abouelela (5%) Faisal Kamal (5%) Bryn Barker (5%) All members are required to contribute to this chapter Signatures Abdelrahman Faisal Bryn Faisal Bryn Faisal Kamal (25%) Bryn Barker (5%) Abdelrahman Abouelela (90%) Abdelrahman Sari Faisal Kamal (70%) Faisal Bryn Barker (30%) Faisal Bryn Plant Calculations – Bryn Barker (80%) DCC – Sari Miari (100%) Absorber – Bryn Barker (95%) Stripper – Faisal Kamal (95%) HEX – Bryn Barker (98%) Compressor Train – Abdelrahman Abouelela (100%) Pinch Point – Bryn Barker (100%) Abdelrahman Abouelela (75%) Bryn Abdelrahman Faisal Sari All members are required to contribute to this chapter Bryn Abdelrahman Faisal Sari Sari Miari (5%) Ahmed Aldhalei (5%) Plant Calculations – Abdelrahman Abouelela (20%) Absorber – Faisal Kamal(5%) Stripper – Bryn Barker(5%) HEX – Ahmed Aldhalei (2%) Abdelrahman ii Sari Miari (25%) Sari Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari EXECUTIVE SUMMARY Following an extensive process route selection and evaluation, post-combustion carbon capture, coupled with MEA as the amine solution for absorption, has emerged as the most optimal strategy for this project. MEA's increased absorption capabilities, stemming from its reactivity, makes it optimal for our objectives. To maximise cost-effectiveness, we propose sourcing construction raw materials from Chinese suppliers, while also securing coal bed methane from China. Conversely, due to market stability and supplier flexibility, MEA from a local source is recommended. Operational safety is paramount, given the potential hazards of certain chemicals used in operation. Rigorous measures, including exposure controls and proper storage and disposal protocols, are put in place to mitigate potential catastrophe, such as wastewater undergoing treatment to avoid adverse environmental impacts. The operational units in the process have consistently met benchmarks, with the absorber column achieving over 90% CO2 absorption from the flue gas and the stripper generating a CO2 stream exceeding 95 wt% purity. Following compression and being liquefied, the CO2 stream is sent to an underground pipeline to be stored. Calculations project ≈13 kg/s of CO2 to be stored at full operational capacity. The strategic decision to store rather than sell the captured CO2 to collect Australian Carbon Credit Units (ACCUs) is heavily advised. The project's anticipated capture and storage of 370,000 tons of CO2 annually, valued at over $4.5 million, not only ensures economic viability but also exhibits our commitment to positively impact the environment by reducing CO2 emissions. iii Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari ACKNOWLEDGEMENTS Thank you to Tariq Mahmud, Timothy Cockerill and Manoj Ravi for all help and advice provided to the group regarding the production of this report. This report contains Abdelrahman Abouelela, Bryn Barker, Faisal Kamal, Sari Miari and Ahmed Aldhalei’s own unaided efforts. Signatures: Abdelrahman Faisal Bryn Sari iv Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Table of Contents 1. INTRODUCTION ........................................................................................................................................................................ 1 2. PROCESS ROUTE EVALUATION AND SELECTION ........................................................................................ 2 2.1 Processes Route Evaluation ...................................................................................................................................... 2 2.2 Process Selection ................................................................................................................................................................. 3 2.2.1 Technological Methods for Capturing CO2 ..................................................................................................... 3 2.2.2 Choice of Absorbent ............................................................................................................................................. 4 2.2.3 MEA Degradation Products............................................................................................................................... 6 2.2.4 Chemicals physical properties ......................................................................................................................... 7 2.2.5 Simplified Process Pathway including Main Process Units .............................................................. 7 2.3 Plant Location .................................................................................................................................................................... 7 2.4 Environmental Impact .................................................................................................................................................... 9 3. Design OF Selected Process ......................................................................................................................................... 10 3.1 Process Description & Flowsheet Design ........................................................................................................ 10 3.1.1 Pre-treatment Units ............................................................................................................................................ 10 3.1.2 Direct Contact Cooler (DCC-101) ............................................................................................................... 11 3.1.3 Absorber Column (A-101) ............................................................................................................................... 11 3.1.4 Heat Exchanger and Cooler (H-101) ......................................................................................................... 12 3.1.4 Stripper Column (S-101) .................................................................................................................................. 13 3.1.5 Compressor Train (COM-101 TO C-105) ............................................................................................... 13 3.1.6 Process Flow Diagram...................................................................................................................................... 15 3.2 Process Chemistry & Thermodynamics ............................................................................................................ 16 3.2.1 Absorption of CO2 by water ............................................................................................................................ 16 3.2.2 Absorption of CO2 by MEA Kinetics & Mechanisms .......................................................................... 17 3.2.3 Whitman Two-Film Mass Transfer Theory ............................................................................................. 18 3.2.4 Vapor-Liquid Equilibrium (VLE) Data ....................................................................................................... 19 3.2.5 Side Reactions Kinetics and Mechanisms.............................................................................................. 22 4. RAW MATERIALS AND PRODUCTS ....................................................................................................................... 24 4.1 Raw Materials ................................................................................................................................................................. 24 4.1.1 Raw Materials for Construction: ................................................................................................................... 24 4.1.2 Raw Materials for Operation: ......................................................................................................................... 24 4.1.3 Coal bed methane supplier: ........................................................................................................................... 25 4.2 Product and By-products .......................................................................................................................................... 26 5. SAFETY, HEALTH, AND ENVIRONMENT ............................................................................................................. 26 5.1 Process Safety ............................................................................................................................................................... 26 5.2 Health ................................................................................................................................................................................. 28 5.3 Environmental Impact ................................................................................................................................................. 31 6. MASS & ENERGY BALANCES and Process Integration ................................................................................ 32 6.1 Mass Balance PBD ...................................................................................................................................................... 32 6.1.1 Flue Gas................................................................................................................................................................... 32 v Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.1.2 Direct Contact Cooler (DCC-101) .................................................................................................................... 35 6.1.5 S-101 .................................................................................................................................................................................... 40 6.1.5.1 Condenser mass balance: ............................................................................................................................... 41 6.1.5.1.1 Stream 6: ......................................................................................................................................................... 41 6.1.5.1.2 Stream 7: ......................................................................................................................................................... 42 6.1.5.1.3 Stream 8: ......................................................................................................................................................... 43 6.1.5.1.4 Flowrates around condenser:................................................................................................................ 44 6.1.5.2 Mass Balance around Reboiler and column: .......................................................................................... 45 6.1.5.2.1 Stream 11 ........................................................................................................................................................ 45 6.1.5.2.2 Stream 10 ........................................................................................................................................................ 46 6.1.5.2.3 Stream 9 .......................................................................................................................................................... 46 6.1.5.2.4 Flow rates around the reboiler and column. .................................................................................. 47 6.1.5.3 Mass balance summary table......................................................................................................................... 48 6.1.6 Compressor train (COM-1 to COM-4, C-102 to C-105, D-101&D-102) ............................................ 49 6.2 Energy Balance ................................................................................................................................................................ 50 6.2.1 Direct Contact Cooler (DCC-101) .................................................................................................................... 50 6.2.2 Packed Bed Absorption Column (A-101)..................................................................................................... 51 6.2.3 - E-101: ....................................................................................................................................................................... 53 6.2.4 Cooler (C-102)......................................................................................................................................................... 54 6.2.5 S-101 Energy balance ................................................................................................................................................. 55 6.2.5.1 Condenser Duty .................................................................................................................................................... 55 6.2.5.2 Energy balance around the column............................................................................................................. 56 6.2.5.3 Reboiler Duty .......................................................................................................................................................... 57 6.2.6 Compressor train (COM-1 to COM-4, C-102 to C-105, D-101&D-102) ............................................ 58 6.3 Process Integration ........................................................................................................................................................ 62 6.3.1 Hot and cold utility requirements .................................................................................................................. 62 6.3.2 Selection of streams for PI ................................................................................................................................. 62 6.3.3 Minimum approach temperature ................................................................................................................... 62 6.3.4 Application of PI and design of HEN .............................................................................................................. 63 ....................................................................................................................................................................................................... 65 6.4 Final Process Flow Diagr ............................................................................................................................................. 65 6.5 Auxiliary unit power requirement calculations ................................................................................................ 66 7. CONCLUSIONS .................................................................................................................................................................... 67 8. References ................................................................................................................................................................................. 68 APPENDIX B - Raw Materials and Products appendices: .............................................................................................. 79 APPENDIX C - Mass and Energy Balance appendices ......................................................................................... 81 APPENDIX D - MINUTES OF MEETINGS WITH SUPERVISOR: ........................................................................ 86 vi Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari NOMENCLATURE Symbol CP Quantity Specific heat capacity SI Unit j/mol Tc Pc Critical temperature Critical pressure K bar W Work Density Enhancement factor Enthalpy Henrys Law Constant for species i Molar Flow Rate Molar Gas constant Quantity of heat J = kg m2 s-2 Kg m-3 ρ E ̂ 𝐻 ki 𝑛̇ R Q J = kg m2 s-1 Mol/L.bar Mol s-1 J mol-1 K-1 J = kg m2 s-1 Greek letters Symbol Quantity γ Specific heat ratio SI Unit J/Kg K Dimensionless Groups Notation xi yi zi Ki Name Formula Liquid molar fraction of component i Vapour fraction of component i Inlet molar fraction of component i Equilibrium constant of component i vii Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari ABBREVIATIONS Coal Seam Gas – CSG Coal Bed Methane – CBM Carbon Dioxide – CO2 Monoethanolamine - MEA Greenhouse gas - GHG viii Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 1. INTRODUCTION This report aims to explain the process of collecting and storing CO2 from the flue-gas of a 100 MWe gas-fired power station, based in Queensland, Australia. The power station utilises Coal Seam Gas as its chosen fuel source, which is mainly composed of alkanes (99.5 vol%), with the majority of the fuel being composed of methane (95 vol%). The building, design and optimisation of the process has been discussed in detail, along with the appropriate uses for the captured CO2. A rigorous process route evaluation and selection process was conducted to determine the most suitable combustion process and absorbent used in operation for the most effective method of carbon capture. In this process, details stretching from the absorbent’s physical properties to the chosen plant location have been scrutinised in an effort to function as efficiently as possible while mitigating environmental impacts that could arise from the carbon capture project. Furthermore, a thorough description of the entire process has been provided, explaining the function of every unit in detail, along with relevant data on any chemicals and theories that contribute to the function of the units. The suppliers for the raw materials required for the whole carbon capture process, from building the carbon capture unit to when it is fully operational, are examined and the most suitable supplier is chosen, whether it is a local or international supplier. The potential uses of the captured CO2 are discussed and the most appropriate use is chosen based on economic impacts to FAABS as well as environmental impacts. The potential health and safety issues that come along with building and operate the unit along with how to mitigate them have been discussed in this report, to ensure all involved are safe throughout the entire process. Moreover, a rigorous mass and energy balance has been conducted on every operational unit as well as the entire process to understand the chemical and physical side of carbon capture. Process integration was considered throughout to allow for maximum efficiency while also minimising expenses to make the project as economically feasible as possible. After designing the carbon capture plant and ensuring plant operation is feasible, the individual components are to be designed. FAABS has compiled recommendations to the process to be used based on the research and calculations conducted, which will be displayed in this report in an attempt to establish the economic viability of the carbon capture project. 1 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 2. PROCESS ROUTE EVALUATION AND SELECTION 2.1 Processes Route Evaluation As Coal Seam Gas (CSG) is fed into a gas turbine along with air, the CSG combusts to generate electricity resulting in the release of a flue gas which contains CO2 which is a greenhouse gas that has a negative impact on the environment due to its contribution to global warming. There are three primary routes for capturing CO2 from flue gas emissions. These are oxy-fuel combustion, precombustion, and post-combustion. Oxy-Fuel combustion carbon capture is a process wherein the bulk nitrogen in the air feed is removed prior to combustion, yielding a stream that composes of ~95% O2; CSG combusts at a higher temperature in this condition compared to air-fired combustion, increasing the efficiency of the combustion process (Oxy-combustion, 2023). Moreover, the flue gas produced primarily composes of CO2 and water vapour, which reduces the volume of the flue gas by approximately 75% compared to other methods, which leads to less heat lost in the exhaust, making the system more energy efficient (Pronobis, 2020). Moreover, the concentration of CO2 in the flue gas is significantly higher compared to using other methods, which simplifies the CO2 capturing process in the carbon capture unit, as there are fewer other gases to separate it from, because the energy required for CO2 separation is proportional to its concentration in the flue gas, and higher concentrations of CO2 reduce the energy needed for its capture (Karimi et al, 2023). This process has a potential for 100% CO2 capture (Basile et al, 2019). Moreover, the formation of NOx will be avoided to a certain extent due to the lack of nitrogen in the gas turbine. However, an NOx treatment unit might still be needed, as the air separation unit cannot achieve 100% oxygen purity and the CSG may contain small impurities of nitrogen. Thus, little amounts of NOx will inevitably form. Therefore, FAABS does not recommend that AE uses oxy-fuel combustion because purifying the air stream to achieve an O2 rich stream is extremely expensive and energy intensive, and yet the system could still require an NOx treatment unit. Furthermore, the increase of combustion and capturing efficiencies do not overturn the increase of costs caused by purifying the air stream. Figure 2.1: Simple process block diagram showing oxy-fuel Combustion CO2 Capture (Drawn by author). Moving on, in pre-combustion capture, CO2 is captured prior to the fuel combustion. This multi-stage process begins with gasification, where the CSG and steam at 750°C are fed along with an oxygen rich stream into a gasifier (Paul, 2004), which transforms the CSG into syngas which consists of carbon monoxide (CO) and hydrogen (H2) (Persons, 2019). Then the syngas along with steam enter a Water-Gas Shift Reactor which converts the CO into CO2 (Persons, 2019), the CO2 is then captured in a carbon capture unit. This separates the H2 from the CO2, so finally the purified H2 is 2 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari directed into the gas turbine where it is burned as a fuel to generate electricity (Persons, 2019). The Pre-Combustion Carbon Capture method captures 90-95% of CO2 in flue gas (Basile et al, 2019). This is because the stream that enters the carbon capture only contains CO2 and H2, which means that the CO2 concentration in the stream is high which makes the capturing process more efficient. However, FAABS does not recommend AE to use pre-combustion due to its high capital cost, and due to the complexity of the process and the need for specialised equipment. Figure 2.2: Simple process block diagram of Pre-Combustion CO2 Capture (Drawn by author). Finally, in post-combustion capture, CO2 is captured from the flue gas simply after the fuel combusts with air in the gas turbine. The post-combustion capture method captures around 90% of CO2 in flue gas. Currently, post-combustion is the most established and commonly used approach due to having the highest technology maturity and cost-effectiveness, and most importantly due to having the lowest capital cost and indirect costs compared to the other methods (Theo et al, 2016). Furthermore, post-combustion can be retrofitted onto existing power plants and industrial facilities easily. This plays a major role in reducing the cost of adopting a carbon capture method into an existing plant, it also allows the carbon capture unit to be replaced or upgraded with minimum to no impact on the retrofit plant (Carbon capture, 2022). Therefore, FAABs advocates the adoption of this method by AE on the grounds of its simplicity, cost-effectiveness, and low capital costs. Figure 2.3. Simple Process Block Diagram of Post-Combustion CO2 Capture (Drawn by author). 2.2 Process Selection 2.2.1 Technological Methods for Capturing CO2 Having chosen to capture the CO2 from the flue gas after combustion with air has taken place, it is important to consider the technology that shall be used to capture the CO2. The methods which have been considered for the Plant in Queensland can be found in the table below: 3 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Table 2.1: Different possible technologies to use in capturing CO2. CO2 Capture Technology Description Advantages Disadvantages Absorption A gas stream is contacted with a liquid absorbent (solvent), absorbing CO2 either chemically (e.g. Amines) or physically (e.g. Organic molecules). Then heat and/or pressure are applied to release the CO2 and the absorbent is recycled in the system (Co, 2019). Involves the intermolecular forces between the CO 2 and the surface of the adsorbent, resulting in CO 2 adhering to the surface. Heat, electricity, or pressure is then applied to release CO2 (Co, 2019). The most used adsorbent materials are activated carbon, zeolites, and silica (Dziejarski et al, 2023). A selective semi-membrane is used to separate the flue gas components through various mechanisms such as diffusion, molecular sieve, and ionic transport. The partial pressure difference across the membrane provides the driving force for separation (IEAGHG, 2019). The flue gas is cooled by an external refrigerant loop. Flue gas is initially cooled to remove water. Then further cooling is achieved via direct contact with a cryogenic fluid, forming a slurry with solid CO2. The solid CO2 is then removed via filtration and warmed to turn into liquid CO2 (Sayre et al, 2017). Most mature technology (Leung et al, 2014). High energy intensity and solvent might degrade over time. It also requires a significant amount of water (Tuinier et al, 2011). Achieves 9095% CO2 capture (IEAGHG, 2019). High energy intensity. Moreover, the adsorbent can degrade or become fouled, reducing efficiency. The process is slow and can’t maintain rapid CO2 capture (Hudson & Thomson, 2019). Removal of CO2 from flue gas is difficult due to low CO2 partial pressure and precise of water vapour, achieving around 80% carbon capture (Mohammed et al, 2020). Adsorption Membrane Cryogenic Low energy requirements (Abanades et al, 2015). Can achieve CO2 capture between 95 and 99% (Baxter et al, 2018). High energy intensity, with a very high capital cost and many technical difficulties. It is still under development to improve the technology and make it more economically viable (Aneesh & Sam, 2023). AE’s carbon capture plant in Queensland requires to remove 90% of the CO2, which excludes the option of using the membrane technology as it only achieves around 80%. Moreover, the cryogenic technology can achieve a greater carbon capture rate than what is required. However, the technology is still under development as it is not economically viable yet. Therefore, the choice lies on either absorption or adsorption, as both techniques can achieve the required carbon capture rate, but both techniques are highly energy intensive. However, currently absorption is shown to be more effective from an economic and operational point of view; with a larger processing capacity on the industrial scale, with a better return and a better long-term performance (Castro et al, 2021). 2.2.2 Choice of Absorbent As mentioned in table 2.1, absorption of CO2 from a flue gas can be done either chemically (e.g. Amines) or physically (e.g. Organic molecules). Current data and research suggest that chemical absorption is the most efficient option if the composition of CO2 in the flue gas is below 30.4% (Zhang et al, 2020). This is because chemical absorption favours low CO2 partial pressures in the flue gas, (Mumford et al, 2015). Based on calculations in section 6.1.1, AE’s proposed plant flue gas will compose of 8.5 mol% CO2. Therefore, FAABS advocates the use of an amine solvent for chemical absorption as it would be the most cost & energy-efficient option. 4 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari The most widely used amines in the absorption of CO2 are monoethanolamine (MEA) and diethanolamine (DEA) (Varbanov et al, 2017). MEA & DEA similarly react with CO2 in an aqueous solution. Firstly, the carbon atom of CO2 binds with the nitrogen atom of MEA via a nucleophilic attack, forming a Zwitterionic intermediate (MEA+COO-) (Holmes, 2018). Then H2O molecules cause the deprotonation of MEA+COO-, forming a stable carbamate ion (MEACOO-) and a solvated proton (H3O+) (Hwang, 2015). The H3O+ reacts with another MEA molecule to form MEAH+ and H2O, which means that theoretically 2 moles of MEA absorb 1 mole of CO2 (Hwang, 2015). The mechanisms of all these reactions are shown in figure 10 in section 3.2.2. The loaded solvent, saturated with CO2 is then regenerated by applying heat to it as this reaction is reversible, the carbamate turns back into the Zwitterion molecule which then dissociates into MEA and CO2, releasing the CO2 from the solvent as a gas to be captured (Lv et al, 2015), while the regenerated solvent can be reused in the absorption step. MEA & DEA absorb CO2 optimally at 40-50 °C because the reaction is exothermic (Bravo et al, 2021). MEA is regenerated optimally at 110-130 °C (Bravo et al., 2021) and DEA is regenerated optimally at 95-105 °C (Zhou et al, 2017). Furthermore, the heat of reaction of MEA is 85.6 kJ/molCO2 which is greater than needed for DEA 76.3 kJ/molCO2 (Galindo et al., 2012). Both of these factors lead to a much higher energy requirement for stripping for MEA than DEA. Moreover, DEA is less reactive than MEA, meaning that it has a lower chance of degrading/reacting with impurities present in the flue gas (Xue et al, 2018), which means that DEA is less likely to degrade overtime compared to MEA, and thus DEA is less likely to cause the corrosion of equipment. However, a major disadvantage of DEA is that it exhibits slow kinetics; making MEA a better choice as it can remove CO2 from the gas stream much more rapidly (Galindo et al, 2012). The faster kinetics of MEA can be observed from comparing figures 4 and 5, as MEA takes noticeably much less time to reach the equilibrium. This leads to a higher CO2 loading rate by MEA, meaning that MEA can capture more CO2 per unit of solvent in a short period of time (Xue et al, 2018). This is particularly beneficial in industrial processes, because the equipment used for the absorption process can potentially be smaller. This leads to cost savings in terms of equipment size, installation, and operational costs. Figures 2.4 & 2.5: Equilibrium loading curve for MEA & DEA (Galindo et al, 2012). 5 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari In Australia, MEA costs $1596/t, nearly the same as DEA $1546/t (Redox, 2023). Therefore, after careful consideration of all factors, FAABS recommends the use of MEA as the absorbing solvent. Furthermore, 30 wt% MEA in water is optimal for CO2 capture when the composition of CO2 (8.5 mol%) in the flue gas is low, this is due to the amine’s reactivity and absorption characteristics (Zhang et al, 2020), which is discussed in section 3.2.4.3. Moreover, this balances the cost of MEA with the increase in driving force for mass transfer for the absorption of CO2. 2.2.3 MEA Degradation Products MEA can degrade overtime due to oxidative or thermal degradation, resulting in solvent loss and production of harmful by-products which can cause equipment corrosion. Oxidative degradation occurs when MEA reacts with O2, SO2 or NOx in the flue gas. The degradation of MEA by SO2 ultimately causes the formation of Bicine which can reduce the efficiency and performance of the absorbing system, and cause equipment corrosion and environmental issues (Fytianos et al, 2015). Furthermore, presence of NOx can cause the degradation of MEA by photo-oxidation to form nitrosamines and nitramines, which can cause equipment corrosion and have also been identified as carcinogenic and highly hazardous for human health and the environment (Vega et al, 2014). Finally, oxidative degradation can also occur in the absorber if the flue gas O2 composition is around 3% or higher (Vega et al, 2014). The main products of MEA oxidative degradation are ammonia, formic acid, acetic acid, HEF, HEI, and HEPO (Vega et al, 2014). These can reduce the efficiency and performance of the absorbing system, and cause equipment corrosion. Thermal degradation also inevitably occurs in the stripper in the presence of CO2 at temperatures between (100 and 150 ºC) (Vega et al, 2014). More thermal degradation occurs as temperature increases. At 100 ºC around 2% of MEA degrades, but 90% of MEA degrades at 150 ºC (Novitsky et al, 2023). Thus, it is crucial to carefully control and maintain the stripper’s temperature. Thermal degradation products mainly include OZD, HEEDA, HEIA, UREA and oligomers (Novitsky et al, 2023), these also cause corrosion of equipment and decrease MEA’s capacity and efficiency. All thermal and oxidative degradation mechanisms of MEA are shown in section 3.2.5. Since the products of oxidative and thermal degradation can cause equipment corrosion, it becomes crucial to purge the degraded MEA. This can be done by removing a small fraction of the MEA solution from the stripper unit and replace it with fresh MEA fed into the absorber. The purged MEA can be either reclaimed or discarded, depending on the economics and environmental regulations. The purging process can be controlled by monitoring the concentration of the degradation products in the MEA solution. The degraded MEA can be distinguished from the normal MEA by measuring the pH, conductivity, density, viscosity, and CO2 loading of the MEA solution. These parameters can indicate the degree of degradation and the presence of degradation products (Braakhuis & Knuutila, 2023). 6 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 2.2.4 Chemicals physical properties Table 2.2: physical properties of gases and chemicals involved in Carbon Capture. (Engineering toolbox) Component Molecular Weight (g/mol) Boiling Melting Density at Density at Solubility in water at point point 40 °C 120 °C 40 °C (g of gas/ kg of (°C) (°C) (kg/m3) (kg/m3) H2O) CO2 44.01 -78.55 -56.6 1.721 1.367 1 H2O 100 100 0 992.3 0.5627 - O2 32 -183 -218.8 1.246 0.9921 0.031 N2 28.01 -195.8 -210 1.091 0.8682 0.014 SO2 64.06 -9.95 -72 2.525 1.999 55 MEA 61.08 170.3 10.3 1001 935.4 Miscible 2.2.5 Simplified Process Pathway including Main Process Units The flue gas exits the gas turbine at 140 °C and enters a direct contact cooler (DCC) which brings the flue gas into direct contact with cooling water to be cooled down to 40 °C. Then, the cooled flue gas & MEA enter an absorption column at 40 °C where MEA absorbs the CO2. This loaded solvent, saturated with CO2 is then regenerated in a stripping column. During this phase, steam (heat) at 120°C is applied to the solvent using a reboiler, which releases the captured CO 2 from the solvent, so the solvent is returned to its original state. The lean solvent is then recycled back to the absorber, but it is passed through a heat exchanger where heat is exchanged between the lean solvent and the rich solvent. While the released CO2 leaves the stripper and is then cooled down and compressed to a high pressure to reduce its volume using a train of coolers and compressors, and the CO2 is then transported to a pipeline network which stores the captured CO2 in depleted oil/gas fields and saline aquifers in the region. (A PBD showing all units can be seen in figure 3.1 in section 3.1). 2.3 Plant Location It is important to consider the plant's proximity to the coal seam gas. The plant should be located reasonably near CSG wells, and the loading centres for the generated electricity, this is to reduce the cost of transportation and minimise the emissions of CO2 caused by transportation. However, the plant must also be situated at a safe distance from the CSG wells in case of any unfortunate incidents that may occur in the power station or in the CSG wells. In Queensland, most of the coal seam gas wells are in the Surat Basin fields located in the southeast of the state between Dalby and Miles as can be seen in figure 6. Furthermore, leading distributors of chemicals such as Redox and Brenntag Australia which supply MEA are located in Brisbane which is only 120 miles away from Dalby. Therefore, FAABS recommends West Dalby as the optimal location for the proposed plant, as the area boasts close proximity to abundant coal seam gas reserves and MEA suppliers, minimising transportation costs and logistical complexities. 7 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Figure 2.6: A map of Queensland showing the location of CSG wells. (Department of natural resources & mines, 2017). Furthermore, an assessment of Queensland’s CO2 geological storage capacity of depleted oil and gas fields was carried out in 2008. Results showed that the depleted fields of Bowen and Surat basins can capacitate 106 Megatons of CO2; the study also estimated the maximum potential storage capacity of Bowen and Surat fields to be 3242 Megatons (Queensland Government, 2008). Based on calculation in section 6.1.1, 0.367 Mt of CO2 will be captured yearly, which means that these depleted oil and gas fields will be able accommodate our captured CO2 for the long-term. Furthermore, West Dalby’s proximity to those depleted fields is ideal to cut down the cost of the piping network that would be needed to transport the captured CO2. Furthermore, West Dalby provides favourable geological conditions, ensuring stability for the construction and operation of the power station (Mond, 1973). The existing infrastructure in the region, including well-established roads and railways, enhances accessibility for the transportation of materials and facilitates efficient connectivity to the electricity grid (Gov.au, 2021). Finally, due to favourable thermodynamic conditions, most gas turbines operate at their peak efficiency when the ambient temperature is around 15 °C (Rahman et al, 2010). This temperature optimises the behaviour of air as an ideal gas, which enhances air density for higher mass flow rates, and improves the efficiency of the compression process (Rahman et al, 2010). The lower ambient temperature also supports more efficient combustion, allowing for better control of the air-fuel mixture and combustion temperature. As can be seen from figure 7, Dalby’s average temperature is ideal for the operation of the proposed power plant for approximately half of the year. Figure 2.7: Climate data for Dalby taken from 1991 to 2021 (Dalby Climate, 2023). 8 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 2.4 Environmental Impact Carbon Capture and Storage (CCS) is a significant technology in reducing greenhouse gas emissions from power plants, thus mitigating climate change impacts. However, its implementation has environmental and energy efficiency implications. The CCS process requires water for chemical and physical processes to capture and separate CO2, potentially leading to water stresses. There’s also a risk of groundwater contamination due to potential CO2 leakage during geologic sequestration. If CO2 escapes into water sources, it can form carbonic acid, leading to the acidification of groundwater, the acidification process may result in the release of dissolved metals, impacting groundwater quality and posing risks to both environmental and human health (Gustin, 2010), especially if the groundwater serves as a drinking water source. The corrosion of underground infrastructure, such as pipes and wells, is another consequence, potentially leading to the release of contaminants. To mitigate these potential effects, it is imperative to implement preventive measures during carbon capture and storage activities, including careful site selection, robust monitoring systems, and effective well-sealing techniques. Regular monitoring and prompt detection of any leaks are essential to enable timely remedial actions and uphold the integrity of groundwater resources. The establishment of stringent regulatory frameworks is vital to guide the safe implementation of carbon capture technologies and minimise risks associated with CO2 leakage into groundwater. On the energy efficiency front, the increase in energy demand associated with CCS can increase operating costs. The process requires energy in the form of steam and electricity, which reduces a power plant’s electric power output and/or increases its fuel input. This creates an energy penalty for power plants, causing the price of electricity sold to the consumer to increase. Finally, as mentioned in section 2.2.3, Some degradation products MEA, such as nitrosamines and nitramines, raise health concerns due to their carcinogenic properties. Modifying process conditions becomes crucial to prevent or minimise the production and emission of these harmful compounds. It is crucial to control nitrosamine concentration within the range of 13.7 to 14 mM to prevent health hazards (Badr et al., 2017). To ensure compliance with regulatory occupational exposure limits, it is recommended to conduct exposure analyses, monitoring chemical concentrations at the plant. Solvent losses due to oxidative degradation are significant, whereas losses from thermal degradation are minimal. The impact of degradation on the Life Cycle Analysis (LCA) is noteworthy, as continuous compensation for the solvent is required to maintain steady-state functionality. It’s crucial to carefully consider these environmental and efficiency factors in the planning and operation of carbon capture plants for power plants, aiming to balance significant reductions in greenhouse gas emissions with minimising the environmental impact and energy costs associated with the process. 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 3. Design OF Selected Process 3.1 Process Description & Flowsheet Design Figure 3.1: A detailed Process Block Diagram of the process route (Drawn by author). 3.1.1 Pre-treatment Units The first step considered in the process of capturing CO2 is the pre-treatment of the flue gas. As mentioned in section 2.2.3, SO2 can cause the degradation of MEA and form bicine. However, SO2 concentrations that causes the formation of bicine is about 10 ppm for 30 wt% MEA solution (Zhou et al, 2013), but some studies show that SO2 at 5 ppm can actually inhibit the oxidative degradation of MEA by O2 by scavenging oxidative radicals (Zhou et al, 2013). The removal of SOx can be achieved by implementing desulphurisation units that utilise limestone-based scrubbers. However, based on calculations in section 6, only 0.3 ppm of SO2 is present in the flue gas leaving the gas turbine which means that it is very unlikely for MEA to degrade due to the presence of SO 2 in this proposed plant. Thus, a desulphurisation unit will not be needed. Moreover, as mentioned in section 2.2.3, MEA can also degrade by the presence of NOx to form nitrosamines and nitramines. However, MEA is a primary amine which is unable to form a stable nitrosamine, but experiments show that under the influence of NOx, MEA degrades to the secondary amine DEA which is then nitrosated (Fostås et al, 2011). Different techniques are used for the removal of nitramines and nitrosamines, such as sorption through activated carbon, precursor pre-oxidation, UV irradiation, bio-treatment, & polymerisation (Krasner et al, 2013). However, it is better to prevent/minimise the formation of nitrosamines and nitramines by implementing a DeNOx pre-treatment unit to separate the NOx from the flue gas before it enters the absorber. NO2 is of particular concern, it has been suggested that concentration of NO2 in flue gas should be restricted to approximately 20 ppm (Gibbins, 2022). Without being given the furnace conditions for the specific gas turbine that will be used by AE for the proposed plant, FAABS cannot assess the amount of NOx that would form in the accurately. 10 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari However, in general when combusting CSG in a gas turbine, 2-20 ppm of NO2 and 20-220 ppm of NO form (Pavri & Moore, 2013). Therefore, FAABS believes that a DeNOx pre-treatment unit will not be needed but recommends leaving space for a DeNOx pre-treatment retrofit in case if the NO2 emissions from the gas turbine get close to 20 ppm. 3.1.2 Direct Contact Cooler (DCC-101) In the absence of any beneficial pre-treatment units. The flue gas exits the gas turbine at 140 °C and 1.2 bar with a H2O composition of 16.52 mol%, the flue gas is directly fed into the DCC from the bottom, while the cooling water stream at 23 °C and 3 bar is fed into the DCC from the top as illustrated in figure 3.1. This configuration exploits the upward movement of the hot flue gas due to its lower density. As the flue gas rises upwards through the DCC, it comes into direct contact with the downward-flowing cooling water. This counter current flow setup ensures a significant temperature gradient between the ascending flue gas and the descending cooling water, promoting effective heat transfer. The flue gas then leaves the DCC from the top at 40 °C with a H2O composition of 15.68 mol%, the decrease in the molar composition of H2O is due to the condensation of some water vapour from the flue gas. Furthermore, ~2 mol/s of CO2 get absorbed by the cooling water due to Henry’s Law. The condensed water from the flue gas and the absorbed CO2 exit the DCC along with the cooling water from the bottom of the DCC at 40 °C. This cooling water will operate in a closed-circuit system, meaning that the water that leaves the DCC will be properly treated then cooled using a cooling tower which is the most efficient and cost-effective cooler to use alongside a pump to transport the water back into the DCC (Brandl et al, 2016). The cost savings associated with decreased water supply and disposal contribute to the economic viability of the system. Moreover, recycling also aligns with sustainable practices by reducing resource consumption and waste generation. Finally the water that condenses must be purged in order to prevent the accumulation of water in the system. After proper treatment this water can be used in the power plant or externally (Magneschi et al, 2017). Finally, the DCC causes a pressure drop of 0.1 bar (Pourahmad et al, 2021), causing the flue gas to exit the DCC at 1.1 bar. Thus, the flue gas is sent to a blower to get slightly compressed, this is to ensure that the flue gas can enter the absorber column and flow through its packed tower structure (Mishra, 2014). 3.1.3 Absorber Column (A-101) At this stage, the flue gas stream is ready to enter the packed bed absorption column, where the CO2 will be captured, and the cleaned flue gas will be released to the atmosphere. In the absorber, MEA concentration in the absorption liquid (water) is at 30 wt%, this composition is used to ensure the specified CO2 removal of 90% and to give the optimal working conditions for MEA (Bravo et al., 2021) (Oko et al., 2018). The cooled flue gas and the recycled lean solvent streams are both supplied to the absorber at 40°C as it is the optimal temperature for CO2 absorption by MEA (Bravo et al., 2021). Furthermore, the cooled flue gas stream enters the absorber column at 1.2 bar and the pressure drop is assumed to be 0.1 bar (Tikrit University, 2023). The cooled flue gas enters at the 11 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari bottom of the absorber, while the CO2 lean MEA stream enters from the top of the absorber column. The CO2 lean stream containing MEA and water has a lean loading value of 0.25 mol CO2/ mol MEA (Prasad Mishra, 2014), and a CO2 rich MEA stream leaves the absorber from the bottom as rich amine with a loading of 0.5 mol CO2/ mol MEA (Prasad Mishra, 2014). The MEA absorbs 90% of the CO2 in the flue gas in this process. But before the lean stream enters the absorber, it is enriched with make-up water and periodically dosed with make-up MEA as shown in figure 3.1, this is to resupply the system in order to counter for any vaporisation and degradation losses of water and MEA in the stripper and absorber. As the flue gas stream rises through the absorption column the MEA stream descends through the packed beds. The absorber is designed with packed column beds as they provide higher contact area over the plate columns for a more efficient absorption of CO2 by MEA (Ustadi et al., 2017). When the MEA reaches the bottom of the absorber column it is pumped into the rich/lean heat exchanger. Meanwhile, the treated flue gas goes through a demister pad and then into a water wash. This is to prevent any significant losses of MEA from the absorber. A demister pad sits at the top of the absorption column. As the lean flue gas containing some absorbed MEA rises through the column, the demister pad, composed of structured fibres or mesh, intercepts and captures liquid droplets carried by the gas (Demisterpads.com, n.d.). Through impact and coalescence on the pad's surfaces, larger droplets form and drain down the pad due to gravity (Mokhatab et al, 2006). This collected liquid, which includes the absorbed MEA, is directed back into the absorption column, ensuring that the absorbent is retained within the system for continued use. The demister's efficiency relies on its design features, optimising liquid removal while minimising pressure drop and preventing re-entrainment of separated droplets (Purchas et al, 2002). The flue gas then enters a water wash column where the majority of the residual MEA that may still be present in the flue gas is recovered to be reused. In the water wash, the flue gas is brought into contact with water to dissolve any residual MEA, which preferentially dissolves the MEA, allowing it to be separated from the flue gas. The recovered MEA can then be returned to the absorption process, reducing the overall loss of MEA. The water wash reduces MEA concentrations in the cleaned flue gas from 99ppm down to an acceptable 1.7ppm. Liu et al., 2021 (These steps taken to prevent the release of MEA into the environment are imperative for environmental protection, regulatory compliance, and resource conservation. Releasing MEA into the environment can potentially contaminate water sources, soil, and air, which can harm ecosystems and wildlife. Furthermore, resource recovery contributes to the economic efficiency of the plant. Having passed all MEA retainment filters, the treated flue gas finally leaves absorber and at the top of the washer into the atmosphere. 3.1.4 Heat Exchanger and Cooler (H-101) To heat the CO2 rich MEA stream up to the desired temperature for the stripper column, a shell and tube heat exchanger is used. The CO2 rich MEA stream leaves the absorption unit at a temperature of 63°C and flows through a centrifugal pump that increases the streams pressure from 1.1 to 2.3 bar, and enters the tube side of the heat exchanger, here the CO2 rich MEA is heated by the CO2 12 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari lean MEA stream and leaves the heat exchanger at 102°C this stream then flows into the stripper unit. The CO2 lean MEA stream leaves the stripper at a temperature of 120°C, from here it enters the shell side of the heat exchanger and is cooled to a temperature of 82.5°C. The pressure drop across the heat exchanger on both the shell and tube side streams is assumed to be 0.5 bar (Mukherjee, R, 1998.). Notably the pressure of the CO2 lean MEA stream is 1.7 bar, this means that there is no required pressure increase via pump since the absorber operates at 1.2 bar. Because the CO2 lean MEA stream is only cooled to 82.5°C, further cooling is required to cool the stream down to the required 40°C. For this a cooler is utilised to cool the stream down as shown in figure 3.2 in section 3.1.6, after cooling the CO2 lean MEA stream re-enters the absorber. 3.1.4 Stripper Column (S-101) In the stripper, the CO2 rich MEA stream enters the unit from the top left of the unit where it makes its way through to the reboiler inlet at the right side of lower half of the stripper. The stripper’s temperature is set to 120°C, this is done regenerate the solvent. The temperature is not raised further to avoid solvent degradation and corrosion problems. In the reboiler, high amounts of steam at a temperature of 120°C are fed to evaporate the solvent, the evaporated solvent travels into the boil up stream and into the column where, due to heat transfer, it evaporates more of the liquid solvent as it goes down the column. The vapour is then accumulated at the top of the stripper column where it exits to the condenser (Oko et al., 2018). The overhead partial condenser splits the vapour into liquid and vapour fractions and is maintained at 40°C to help the condensation process of MEA and water. The liquid fraction, containing mostly water and MEA, is pumped back into the stripper (Oko et al., 2018). While the vapour fractions, containing mostly CO2 and small amounts of water and MEA leaves the system into the next step of the process. Meanwhile the lean solvent is pumped back into the heat exchanger to start the cycle again. It should be noted that the average pressure in stripper and the condenser should be 1.8-1.9 bar, while the pressure in the reboiler is 2 bar. This is done to ensure best performance out of the unit and the highest rate of solvent regeneration (Bravo et al., 2021) (Prasad Mishra, 2014). The loading of the inlet lean amine is around 0.25 and its leaves with CO2 as rich amine with a loading of 0.5, the difference between these two values is the amount of CO2 regenerated in the stripper. Furthermore, the pressure drop in the stripped is assumed to be at the average of 0.1 bar (Prasad Mishra, 2014) (García et al, 2022). Notably, the most energy intensive part of the process is the solvent regeneration in the reboiler. 3.1.5 Compressor Train (COM-101 TO C-105) After the separated CO2 leaves the stripper, it heads into the last step of the process which is to be cooled and compressed to 25 °C and 50 bar in preparation to be put in storage. However, due to some water being present in the stream, the water content in the separated CO2 flow must first be removed through the use of a dryer. This is because water and CO2 are corrosive when mixed (Onyebuchi et al., 2018) . After the water has been removed from the stream, the concentrated CO2 enters the first of four compressors at 1.7 bar and 40°C. Four compressors are used instead of three 13 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari to lower the interstage pressure between each compressor, which decreases the temperature rise that the stream experiences and lowers the individual duty of each compressor and cooler, at the cost of an extra compressor and cooler. The stream is then compressed to 14 bar and experiences a sharp rise in temperature, so it is then sent to the first cooler to decrease the temperature. Cooling water at 23°C absorbs heat from the CO2 stream, due to a temperature difference. This process is repeated three more times, with each compressor increasing the pressure of the stream by 12 bar, until the stream is at 50 bar. The stream finally enters the fourth cooler, where it is cooled to the desired temperature of 25°C where it is then ready to be sent to the pipeline for storage. 14 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 3.1.6 Process Flow Diagram Figure 3.2: PFD of the process with streams conditions 15 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 3.2 Process Chemistry & Thermodynamics 3.2.1 Absorption of CO2 by water As mentioned in section 3.1.2, some CO2 is absorbed by the cooling water used in the DCC to cool down the flue gas. The process of CO2 absorption by water involves a series of chemical reactions and is influenced by thermodynamic principles. When CO2 comes into contact with H2O, it can dissolve to form carbonic acid (H2CO3). This reaction occurs when the pH is in the range of 3-8, but the reaction has slow kinetics (Britannica, 2023). Moreover, this is a reversible reaction, meaning the carbonic acid can decompose back into water and carbon dioxide. The reaction can be represented as shown below: CO2 + H2O ⇌ H2CO3 (3.1) Furthermore, carbonic acid is a weak acid and can dissociate in water to form bicarbonate (HCO3-) and a hydrogen ion (H+) (Britannica, 2023). The HCO3- is more stable than and less likely to release the CO2 back into the gas phase (Britannica, 2023). Furthermore this reaction occurs when the pH is in the range of 3-8, and the reaction has fast kinetics (Britannica, 2023). This reaction can be represented as shown below: H2CO3 ⇌ HCO3− + H+ (3.2) Moreover, Bicarbonate can further dissociate to form carbonate ions (CO32-) and another hydrogen ion (Britannica, 2023). This reactions has fast kinetics but this reaction is not likely to occur as it requires a pH higher than 10. This reaction can be represented as shown below: HCO3− ⇌ CO32−+H+ (3.3) These reactions are equilibrium reactions, meaning they can proceed in both directions. The position of the equilibrium (how much of the reactants convert into products) is influenced by factors such as temperature, pressure, and the concentration of the reactants and products. In terms of thermodynamics, the absorption of CO2 in water is an exothermic process, meaning it releases heat. The solubility of gases in water typically decreases with increasing temperature, so more CO2 will dissolve in cold water compared to warm water. Furthermore, the absorption of CO2 by water is significantly influenced by pressure. According to Henry’s Law, the solubility of a gas in a liquid is directly proportional to the partial pressure of the gas above the liquid. This means that as the partial pressure of the CO2 increases, more CO2 will dissolve in the water. Henry’s law was used in section 6 to calculate the amount of CO2 that gets absorbed by the cooling water stream: 𝐶 = 𝑘𝐻 × 𝑃𝐶𝑂2 (3.4) Henry’s constant (kH) was taken at 23 °C (0.034 mol/atm) from literature (NIST, 2023). This is because Henry's law is typically applied to the temperature of the liquid phase, which, in this case, would be the water at 23 °C. 16 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Furthermore, the O2 and N2 present in the flue gas can also be absorbed by the cooling water. However, as can be seen from table 2 in section 2.3.1, the solubility of O 2 and N2 are very low compared to CO2. Thus, their absorption by water is neglected. 3.2.2 Absorption of CO2 by MEA Kinetics & Mechanisms The main reaction in the absorption column involves absorption of CO2 by the aqueous MEA. As mentioned in section 2.2.2, the carbon atom of CO2 binds with the nitrogen atom of MEA via a nucleophilic attack, forming a Zwitterionic intermediate (MEA+COO-) (Holmes, 2018). The reaction can be represented as follows: k2 C2H4OHNH2 + CO2 ⇌ C2H4OHNH2+COO- (3.5) k-1 Furthermore, the Zwitterionic intermediate then gets deprotonated by water molecules, forming a stable carbamate ion and a solvated proton. The reaction can be represented as follows: 𝑘𝑏 C2H4OHNH2+COO- + H2O → C2H4OHNHCOO- + H3O+ (3.6) Then another MEA reacts with the solvated proton as mentioned in section 2.2.2. The mechanisms of these reaction are all shown in figure 3.3. Figure 3.3: Mechanisms involved during CO2 capture in aqueous MEA (Hwang et al.,2015). The rate of reaction can be expressed as shown below: −rCO2, C2H4OHNH2 = k2 [CO2 ][C2 H4 OHNH2 ] (1+∑ k−1 ) kB [H2 O] (3.7) For the CO2 absorption by MEA system, the overall reaction rate is second order, being first order with respect to both CO2 and MEA (Sakwattanapong et al., 2009). Therefore, equation 3.7 can be rewritten as show below: −rCO2 , C2 H4 OHNH2 = k 2 [CO2 ][C2 H4 OHNH2 ] (3.8) 17 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Finally, based on experiments, researchers determined a value for k2. According to Hikita et al. (1977), the kinetic data can be characterised by the equation shown below: log(k 2 ) = 10.99 − 2152 T (3.9) 3.2.3 Whitman Two-Film Mass Transfer Theory In an absorber packed column in a post-combustion CO2 capture plant, the efficiency of CO2 absorption by MEA is influenced by factors such as the gas-liquid contact degree, physicochemical properties, hydrodynamics of the absorber column, amine reactivity degree, and operating parameters related to the gas and amine solution (Khan et al., 2011). The chemical absorption of CO2 into an amine solution is often described by Whitman’s two-film theory, which proposes the existence of two thin films near the gas and liquid phase interfaces. These films, separating the phases from their respective bulk phases, assume that the bulk phases are in equilibrium and that all mass and heat transfer resistances exist within the two films (Ghadiri, 2023). When CO2 moves from the gas to the liquid phase, a chemical reaction between CO2 and the amine solution can take place in the liquid film or liquid bulk, fast reactions occur in a narrow zone within the film, while slow reactions spread through the film and liquid bulk (Afkhamipour, 2017). This is dependent on the relative values of the reaction rate constants, mass transfer coefficients of gas and liquid phases, concentration ratio of reactants and CO2 equilibrium solubility (Afkhamipour, 2017). 3.4: schematic diagram for Whitman’s two-film model, showing the location of the chemical reaction between CO2 and the amine (Afkhamipour, 2017) Figure Furthermore, the reaction between CO2 and MEA is assumed to be infinitely fast, the reaction is fast enough so that this reaction zone remains totally within the liquid film (Levenspiel, 1999). Thus, no CO2 enters the main body of liquid amine to react there. Therefore, the overall rate of absorption of CO2 in an aqueous solution of MEA considering the mass transfer and chemical reaction rates can be expressed based on the two-film model for a fast second-order reaction as shown below: −rCO2 = pCO2 (k HCO 2 ) + CO2 g 𝑎 kCO2 l a E 1 (3.10) (Levenspiel, 1999) In the CO2 absorption system, Henry’s constant is very large (Ghadiri, 2023), which means that: 1 k CO2 g 𝑎 ≪ HCO2 k CO2 l a E 18 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Therefore, it could be considered that the resistance to mass transfer resides in the liquid film, neglecting the mass transfer resistance by the gas film (Ghadiri, 2023). 3.2.4 Vapor-Liquid Equilibrium (VLE) Data 3.2.4.1 Optimum temperature for absorption VLE Data is a fundamental aspect of understanding the behaviour of CO2 in MEA solutions. This data provides insights into the phase behaviour of the CO2-MEA-H2O system under various conditions of temperature and pressure. It is crucial for the accurate simulation and design of CO2 absorption processes; it allows for the prediction of the system’s performance under different operating conditions. 3.5: CO2 partial pressure as a function of loading for 30 wt% MEA at different temperatures. (○=40 °C), (◊=60 °C), (□=80 °C), (Δ=100°C), (∇=120°C) (Aronu et al.,2011). Figure Figure 3.5 shows that, at a temperature of 40 °C, the absorption of CO2 by 30 wt% MEA exhibits the lowest CO2 partial pressure requirement to attain a specific CO2 loading value at any given point. This suggests that 40 °C is the optimum temperature for CO2 absorption by 30 wt% MEA. This is because when a lower CO2 partial pressure is required for the same loading, it suggests a heightened sensitivity to capture CO2 from flue gas streams which is beneficial for streams with a low CO2 concentration (mol%), facilitating more effective capture (Khan et al., 2023). Moreover, a lower CO2 partial pressure requirement means that the absorber column requires a lower total pressure (Ravi, 2023). This reduces the need for compressing gases to high pressures, leading to energy savings and decreasing operational costs. Furthermore, it also allows for the use of less expensive and more readily available equipment, as well as materials with lower pressure ratings (King, 2020). 19 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 3.2.4.2 Optimum pressure for absorption Table 3.1: VLE date from literature for 30 wt % aqueous MEA at 40 °C (Jayarathna et al., 2013). This table can be further illustrated as a graph as shown in figure 3.6: Figure 3.6: A graph of the VLE data shown in table 3.1. As shown in table 3.1 and figure 3.26, a higher CO2 loading requires a higher partial pressure of CO2. Increasing the partial pressure of CO2 approximately from 0.01 to 10 kPa increases the CO2 loading approximately from 0.2 to 0.5 mol CO2/mol MEA. However, a further small increase of the CO2 loading from 0.49 to 0.58 requires a huge increase in CO2 partial pressure from 10.75 to 82.7 kPa (Lee et al., 1974). This is mainly because as mentioned on section 2.2.2, two moles of MEA are needed to absorb one mole of CO2 theoretically, meaning that the loading value is 0.5 mol CO2/mol MEA. However, with enough high partial pressure, a strong driving for more CO2 absorption by MEA can be created, allowing for the loading value to exceed 0.5 mol CO2/mol MEA (Zhang et al., 2017). While increasing the partial pressure of CO2 to high pressures can enhance its loading value in MEA absorption, industries typically avoid doing so due to several reasons. Firstly, raising the CO2 partial pressure significantly increases energy consumption, leading to higher operational costs. Secondly, equipment designed to withstand high pressures tend to be more robust and expensive, increasing the capital costs (King, 2020). Lastly, safety concerns also arise with high pressures, including the 20 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari risk of equipment failure or leaks that could lead to the release of CO2 and other gases (Cusco, 2007). Based on the VLE data, the optimal partial pressure of CO2 is identified at 10 kPa. This choice is a compromise, maximising absorption efficiency while managing the associated costs, considering factors such as energy requirements, operational costs and expensive robust equipment requirements. Based on calculations in section 6, the cooled flue gas entering the absorber column has a composition of 0.0855 mol%. The optimal total pressure inside the absorber column is calculated using the equation below: 𝑃𝐶𝑂2 𝑃𝑇𝑜𝑡𝑎𝑙 = 𝑋 𝐶𝑂2 𝐴𝑏𝑠𝑜𝑟𝑏𝑒𝑟 𝑂𝑝𝑡𝑖𝑚𝑢𝑚 𝑃𝑇𝑜𝑡𝑎𝑙 = (3.11) 10 ≈ 120 𝑘𝑃𝑎 = 1.2 𝑏𝑎𝑟 0.0855 3.2.4.3 Optimum MEA wt% Figure 3.7. A graph of the VLE data at 40 °C for MEA with different concentrations (wt%) (Aronu et al.,2011). As shown in figure 3.7, the absorption of CO2 by very low wt% MEA exhibits the lowest CO2 partial pressure requirement to attain a specific CO2 loading value at any given point. However, using a very low wt% of MEA causes a significant need to increase the solvent flow rate (Wang et al., 2023). This is because despite the potential for higher CO2 loading values with lower MEA concentrations, each unit of solvent has a diminished capacity for CO2 absorption (Ravi, 2023). Therefore, this limitation necessitates a larger volume of solvent circulation to capture equivalent amounts of CO 2. Higher flow rate requirements in industrial processes lead to increased costs due to the need for larger equipment, elevated energy consumption for pumping, higher infrastructure and maintenance expenses, and potential compliance-related expenditures (King, 2020). Furthermore, the mass transfer rate also decreases at lower MEA concentrations (Wu et al., 2017), which necessitates a greater time of contact between the solvent and the flue gas, which means that an absorber column with a greater column height would be required, increasing the capital costs. Additionally, the regeneration of the solvent for reuse after CO2 capture often requires more extensive processing at lower MEA concentrations, this is due to the higher flow rate used with low wt% MEA (Wang et al., 2023). This higher flow rate requirement not only impacts energy consumption but also poses operational and economic considerations. 21 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari On the other hand, using a very high wt% of MEA in CO2 absorption processes offers a higher CO2 absorption capacity per unit of solvent (Akram et al., 2020), resulting in increased efficiency and potential reductions in solvent flow rates and operational costs. However, challenges arise as higher MEA concentrations may lead to increased viscosity (Amundsen et al., 2009), impacting fluid dynamics within the absorption column and requiring more pumping power, increasing the costs for pumping. Moreover, high MEA concentrations can elevate the corrosivity of the solvent (Akram et al., 2020), necessitating corrosion control measures and the use of corrosion-resistant materials which increases the costs. Furthermore, the cost of MEA is a significant factor in the overall economics of the absorption process and using higher a wt% of MEA directly increases the costs of the absorption process. A 30 wt% of MEA in CO2 absorption is considered optimal as it is a compromise between optimising absorption performance within the constraints of operational and economic considerations (Zhang et al, 2020). 3.2.5 Side Reactions Kinetics and Mechanisms 3.2.5.1 Oxidative degradation of MEA by SO2 As mentioned in section 3.1.1, oxidative degradation of MEA by SO2 can occur to form bicine. However, this requires at least 10 ppm of SO2 for 30 wt% MEA solution to be present in the flue gas (Zhou et al, 2013). As shown in section 6, the proposed plant only has 0.3 ppm present in the flue gas, making the formation of bicine highly unlikely. The rate of reaction for the degradation of MEA by SO2 can be expressed as shown below (Supap et al., 2008): 𝐸𝑎 −rC2H4 OHNH2 = − k0 𝑒 𝑅𝑇 [C2 H4 OHNH2 ]𝑎 [O2 ]𝑏 [SO2 ]𝑐 1 + kB [CO2 ]𝑑 (3.12) Based on experimental results obtained by Uyanga et al. (2007), equation 3.12 can be rewritten as shown below: 20752 −rC2H4 OHNH2 = − 0.7189𝑒 8.314𝑇 [C2 H4 OHNH2 ]1.359 [O2 ]0.03 [SO2 ]2 [CO2 ]0.033 (3.13) 3.2.5.2 Oxidative degradation of MEA by NOx Furthermore, as mentioned in section 3.1.1, photo-oxidative degradation of MEA by NOx can occur to form nitrosamines and nitramines when NO2 concentrations are around 20 ppm in the flue gas. However, MEA is a primary amine which is unable to form a stable nitrosamine, but under the influence of NOx, MEA degrades to the secondary amine DEA which is then nitrosated (Fostås et al, 2011). The mechanisms of the MEA degradation by NOx are shown in figure 3.8. 3.2.5.3 Oxidative degradation of MEA by O2 Moreover, as mentioned in section 2.2.3, oxidative degradation by O2 can also occur in the absorber if the flue gas O2 composition is around 3% or higher (Vega et al, 2014). The main products of MEA oxidative degradation are ammonia, formic acid, acetic acid, HEF, HEI, and HEPO. The different MEA degradation reactions are shown in figure 3.9. 22 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Figure 3.8. MEA degradation by NOx mechanisms (Vevelstad et al, 2011) Figure 3.9. MEA oxidative degradation reactions (Vevelstad et al, 2011). 3.2.5.3 Thermal degradation of MEA Finally, thermal degradation also inevitably occurs in the stripper in the presence of CO2 at temperatures between (100 and 150 ºC) (Vega et al, 2014). More thermal degradation occurs as temperature increases. At 100 ºC around 2% of MEA degrades, but 90% of MEA degrades at 150 ºC (Novitsky et al, 2023). Thermal degradation products mainly include OZD, HEEDA, HEIA, UREA and oligomers (Novitsky et al, 2023). The mechanisms of thermal degradation reactions are shown in figure 3.10. Figure 3.10. MEA thermal degradation pathways (Jens, 2013). 23 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 4. RAW MATERIALS AND PRODUCTS 4.1 Raw Materials 4.1.1 Raw Materials for Construction: Table B.1 in Appendix B provides a list of international and local steel and concrete suppliers for the construction of the carbon capture plant. Both international and local suppliers are considered as they both have their separate advantages and disadvantages. International steel and concrete suppliers should be used as the company can benefit economically from the reduced prices and advanced technology they offer, due to them being much larger corporations. Both steel and concrete should be supplied from China. From China, Baowu Steel Group and China National Building Material Group respectively. Table 4.1: Advantages and disadvantages of local and international suppliers Local suppliers Advantages: Disadvantages: - - Increased flexibility and decreased leadtime when purchasing raw materials from a local supplier. It is likely going to be an easier process dealing with a local supplier compared to an international supplier (e.g. language barriers, time-zone differences) International suppliers Advantages: - - - Likely to be smaller suppliers that can’t match international supplier’s prices or quality. Specific raw materials may not be available from a local supplier. Disadvantages: - Can offer lower prices and better-quality products due to the company being larger in size. There are a greater number of international suppliers compared to local suppliers that can meet the specific requirements for the raw materials. - Increased transportation cost of raw materials. Political and economic issues in the country or region of the supplier can impact the supply of raw materials. 4.1.2 Raw Materials for Operation: Referring to Figure B.1 in Appendix B, it is illuminated that the price of MEA is expected to decrease over the coming years. This means that it is likely economically beneficial to not enter a long-term contract with any MEA suppliers and rather consider signing yearlong contracts to leverage the decreasing market price of MEA. Furthermore, the market price of MEA in SE Asia is currently and is projected to be the lowest out of all other areas so if an international supplier is to be chosen, it should be from the SE Asia region. Furthermore, this would decrease the transportation costs of the MEA from the supplier to the carbon capture plants due to the geographical location of SE Asia. However, due to current political factors in the SE Asia region, such as border disputes and conflicts as well as high levels of corruption, it may be more beneficial in the long-term to opt for a supplier in a more politically stable region (Heng, 2020). A suitable choice is SABIC, an international MEA supplier based in the Middle East, which has the second lowest MEA market price according to figure appendix B.3. 24 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari As the price for MEA is similar for both local and international suppliers, it is more economically advantageous to opt for a local supplier due to the decreased transport costs and for ease of communication. A suitable local MEA supplier would be Redox Pty Ltd., which operates a short distance away from the carbon capture plant. This would also allow for more flexibility when it comes to acquiring the MEA and a shorter lead-time, as well as the potential for a good relationship with Redox Pty Ltd. as a long-term MEA supplier. 4.1.3 Coal bed methane supplier: A local supplier for coal bed methane could be beneficial as this avoids any global events that might affect the supply chain, such as COVID-19, which impacted global trade. Due to the creation of new policies and laws during the lockdown period, this significantly affected shipping networks and ports which resulted in challenges regarding international trade (World Bank, 2022). Similarly, events such the Russia-Ukraine war, have affected the European and Australian imported fuel market heavily. Australia has long imported gas from Russia in the past due to the cheap prices offered however on the 25th of April 2022, the Ministry of Foreign Affairs in Australia issued a ban on the acquisition and transportation of Russian-based oil, gas, petroleum derivatives and coal (Department of Foreign Affairs and Trade, 2023). As global political climates are constantly changing, it could be beneficial to acquire coal bed methane from a local supplier, such as Woodside Energy which is one of the largest oil and gas suppliers in Australia, making them a low risk and potential long-term supplier (Bellantuono et al, 2023). Although, it would be very beneficial to have a local supplier for coal bed methane economically, this is not feasible. Due to an initiative from the Australian fracking industry to build new fracking fields, it costs between 3.65 - 6.40 Australian dollars to produce one gigajoule of energy from coal seam gas which is much higher than the expected price of 2.20 - 2.70 Australian dollars per gigajoule. As gas price is an essential player in the Australian electricity market, electricity prices in Australia, specifically in Queensland where the plant is located, have skyrocketed after the fracking initiative with domestic gas prices rising to a peak of 21 Australian dollars per gigajoule in 2017 (Robertson, 2019). It is much more economically favourable to have a coal bed methane supplier from China where it costs 0.2 American dollars per metre cubed (Yihe, 2021). All things considered; it is best to use China United coalbed Methane Corp. Ltd. as the coal bed methane supplier. For coal bed methane, it is best to obtain a long-term contract as the price of coal bed methane is currently increasing as the coal bed methane market is emerging, with prices likely to rise as the global coal bed methane market expecting to grow by 4.9% during 2023-2028, from US$ 18.9 Billion in 2022 to US$ 25.4 Billion by 2028 (imarcgroup, 2023). In addition to this, new legislations or policy changes could lower the product prices, such as Australia aiming to have a zero net emission of carbon by 2050 could lead to an increase in the price of coal bed methane due to a potential increase in carbon tax in Australia, which would see organisations moving away from traditional oil as a fuel. 25 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 4.2 Product and By-products After capturing of the carbon dioxide, it is then transported through pipelines to be stored underground. The utilisation of the captured carbon dioxide is referred to as CCUS (carbon capture, utilisation, and storage), which has a global market value of $1.9 billion in 2020 and is projected to reach $7 billion by 2030 (alliedmarketresearch, 2020). CO2 is used in industries such as the food & beverages, fire extinguishers, refrigeration and polymers industries to be sold as a product (Co, 2021). The food & beverage industry is stable and is projected to be worth $250 billion in 2030, making them a large consumer of CO2 (CSIRO, 2019). Diverting captured CO2 for commercial use in the food and beverage sector may contribute to increased competition for a finite resource, possibly impacting other crucial industrial applications and exacerbating market dynamics (Mackey et al, 2013). One of the major applications of CCUS is enhancing oil recovery which is done by injecting carbon dioxide into oil reservoirs to increase the amount of oil that is capable of being extracted. However, most of the injected carbon dioxide enters the atmosphere once again (McGlade, 2019). The captured carbon dioxide can also be converted into cement through the process of mineralisation (Ralston, 2021). This does not release the carbon dioxide back into the atmosphere. However, not much carbon dioxide will be needed for this process. The price of CO2 varies on its purity; the captured CO2 would have a market price of 85$ per ton or 60$ per ton if used in enhancing oil recovery (MIT, 2023). Referring to figure B.2 in Appendix B, the demand for carbon dioxide is likely to increase in the coming decades. This is due to increased efforts in enhancing oil recovery and the very stable agriculture sector, specifically the fertiliser industry, which requires carbon dioxide to produce urea . However, in 2021, the amount of carbon dioxide captured globally was estimated to be around 40 million tonnes per year, across 26 operational CCS facilities (Brogan, 2022). Moreover, the increased efforts in implementing CCUS units should increase the amount of carbon dioxide captured in the coming decades. To maximise use of the captured carbon, it should be stored to obtain carbon credits as Australia has a government-run carbon credit scheme which gives Australian Carbon Credit Units (ACCUs). One ACCU is earned for each tonne of CO 2 stored by a project. This project is projected to capture and store 370,000 tons of CO2 per year, worth more than $4.5 million (Starr, 2023). Furthermore, this approach aligns with the imperative of achieving climate targets. As there are emerging applications for carbon dioxide, the CCUS market is competitive with many corporations starting to build units to meet the increasing demand for carbon dioxide. This should increase efficiency and advance technological operations to maximise the amount of carbon captured (MIT, 2023). 5. SAFETY, HEALTH, AND ENVIRONMENT 5.1 Process Safety In order to guarantee the safety and integrity of the process, a HAZOP0/1 was carried on the proposed carbon capture plant. The study involves explosion, corrosion, fire, extreme weather, conventional safety and loss of service conditions and their possible consequences. 26 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Table 1. HAZOP0/1 Study Guidewords Hazard Consequences of HAZARD Pipe blockage Buildup of fluid, high pressure, potential equipment damage upstream Injury to workers, release of flue gas stream to atmosphere Pump increases pressure of stream excessively, damage to downstream equipment Potential unwanted exothermic side reactions Massive damage to plant, loss of life or serious injury, release of harmful components to atmosphere Reaction rate and heat release increased. May eventually exceed vessel cooling capacity. leading to overtemperature Injury to workers, release of flue gas stream to atmosphere Contamination of stored product Pipe rupture Pump failure Explosion/overpressure Flue gas impurities Vessel failure Increased flow rate. Pipe rupture Corrosion Storage tanks Fire Electrical spark Damage to equipment. Human error Potential to start fire. 27 Hazard Management strategy Pressure indicators Actions Comments Consider operating conditions. Regular maintenance. & ESD shutdowns on process to be installed Design of control systems for shutdown On-line flue gas monitoring Constant monitoring of process conditions. Independent alarms Perform regular maintenance. Consider operating conditions, Perform regular maintenance. Lining the tank with corrosion resistant material Ground all pumps and compressors Designated smoking areas Perform regular maintenance. Activities with potential to Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari cause fire must not be done on plant premises. Flammable products. i.e. MEA Combustion of hot vapours Lightning Power loss, damage to equipment, fire Flooding A hold back on normal personal operations, Possible damage to equipment. Noise pollution, potential hearing loss of workers Extreme weather Noise Conventional safety Electricity Steam Loss of service Electricity Risk of electrocution, electrical spark causes fire Risk of condensation leading to overflow in stripper column and reboiler outlet. Interruption of process monitoring causing to loss of control over plant. Remove all sources of ignition from areas where flammable products are stored Lightning rod on tall equipment, ground all electrical equipment Consider alleviating equipment susceptible to water damage. Place pumps and coolers away from workstations Ground equipment, regular maintenance ESD of process until issue is resolved. Consider having an electrician. Backup power generators. 5.2 Health The carbon capture plant involves the handling of many dangerous materials if not handled properly. These materials pose risks to human health which must be understood to ensure the safety of operators, employees, and the surrounding public. In order to understand these risks material safety data sheets were utilised to present relevant hazards to the plant proposed. The key elements of the process will be considered in this section, these are deemed to be CO2, MEA, H2O, O2, and N2. At the proposed plant’s conditions, CO2, is a colourless gas. At low concentrations, the gas is odourless. At higher concentrations it has a sharp, acidic odour. As such, the handling of CO2 must 28 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari be done with the utmost care to prevent hazards and risks. In the case of the outlet stream of the plant, when the CO2 gas is compressed & liquefied, it poses no toxicity risk, however if pipes carrying the component are amply heated, the risk of explosion becomes apparent, possibly endangering the lives of close-by personal. In case of high concentrations care should be taken as CO2 is considered an Asphyxiant. With regards to MEA, it is the most harmful material to human life in the plant. Contact with the skin causes severe burns, irritation to the eyes could cause serious eye injury, and exposure is likely to cause respiratory irritation. If not handled correctly, MEA can cause serious damage to personal or employees. Furthermore, MEA is susceptible to combustion at high temperatures (2). O2 and N2 at this plant are do not pose any toxicological or ecological threats, however, both components are considered and Asphyxiants. Oxygen might intensify fires, both nitrogen and oxygen may explode if heated (Air Liquide, 2021). Water has no adverse health effects, no toxicological or ecological effects if handled properly. In order to fully understand the possible health effects and the way of mitigating the chances of such risks from occurring, a materials safety data sheet was created for the proposed plant. And so, further details around the process and all considered components including prober storage and disposal conditions alongside accidental release measures and all other relevant information can be seen in Table (5.2) Below. All information was taken from individual component data sheets (Air liquid, 2022. Honeywell. 2017 CHEM supply Australia. 2020. LAB CHEM, 2020). 29 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Table 5.2: Material safety data sheet for all key components involved in the process COMPONENT CO2 MEA H2O O2 N2 IDENTIFIER Carbon dioxide CAS-No.: 124-38-9 MONOETHANOLAMINE CAS-No.: 7727-37-9 Water CAS-No.: 7732-18-5 Oxygen CAS-No.: 7782-44-7 Nitrogen CAS-No:7727-37-9 N.A. N.A. N.A. None May cause or intensify fire, oxidiser. May explode if heated. May explode if heated. No adverse health effects No adverse health effects. considered Asphyxiant No toxicological or ecological damage caused by this product. considered Asphyxiant Material can create slippery conditions. Use non-slip safety shoes in areas where spills or leaks can occur. Ventilate area. In case of fire: Stop leak if safe to do so. Prevent from entering sewers, basements and workpits, or any place where its accumulation can be dangerous. Remove victim to uncontaminated area. Skin and eye contact have no Adverse effects expected. Adverse effects not expected from this product General room ventilation No special precautions are normally required when handling this product Avoid inhalation. Use in wellventilated areas. Where an inhalation risk exists, mechanical extraction ventilation is recommended. Wear PPE. Permitted disposal of water. No special protective measures required Ensure no corrosive conditions. Keep container below 50°C in a well-ventilated place. Segregate from flammable gases and other flammable materials in store. Protect from sunlight. Store in a well-ventilated place. May be vented to atmosphere in a well ventilated place. Do not discharge into any place where its accumulation could be dangerous. COSHH PICTOGRAM N.A. STEL EXPOSURE LIMIT 30,000ppm, 54000 𝑚 𝑔3 HAZARDS May displace oxygen and cause rapid suffocation. May increase respiration and heart rate. HEALTH EFFECTS ACCIDENTAL RELEASE MEASURES FIRST AID MEASURES 𝑚 No known significant effects or critical hazards.. considered Asphyxiant. Evacuate. Avoid breathing gas. Provide adequate ventilation. Wear appropriate respirator when ventilation is inadequate. Put PPE. Remove victim to uncontaminated area. Wash skin and eyes if in contact. 15 𝑚𝑔 , 6 𝑝𝑝𝑚 𝑚3 Harmful in contact with skin. Causes severe skin burns and eye damage. Harmful if inhaled. May cause irritation to nose, throat and lungs in high concentrations. May cause redness, pain and blistering. Danger of skin absorption can cause severe eye irritation and burns with redness, pain. and blurred vision. Use personal protective equipment. Wear respiratory protection. Ensure adequate ventilation If breathed in Take individual outside into fresh air. In case of skin contact: remove the infected shoes and clothing right away. in case of eye contact: Rinse well. EXPSOURE CONTORLS Good general ventilation should be sufficient to control worker exposure to airborne contaminants. Effective exhaust ventilation system Ensure that eyewash stations and safety showers are close to the workstation location. STORAGE AND DISPOSAL Protect from sunlight. Store in a well-ventilated place. Dispose of surplus and nonrecyclable products via a licensed waste disposal contractor. Waste should not be disposed of untreated to the sewer unless fully compliant with the requirements of all authorities with jurisdiction The product should not be allowed to enter drains, water courses or the soil. No smoking. Keep container tightly closed in a dry and well-ventilated place. Reacts with copper, aluminium, zinc, and their alloys 30 No hazards which require special first aid measures. Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 5.3 Environmental Impact Globally, over 40% of energy-related carbon dioxide emissions are due to the burning of fossil fuels for electricity generation, in Australia, the situation is worse where, in 2021, there were four tonnes of carbon dioxide released for every Australian (World Nuclear Association, 2022). The average person in the world only produces 1.1 tonnes of carbon dioxide per year to generate electricity (Broadbent, 2023). The ability to retrofit a plant with post-combustion carbon capture, is forecasted to greatly reduce the carbon emissions in Australia (Geoscience Australia, 2023). However, it is important to note that carbon capture is not completely free of the risk of emissions. Under normal circumstances, it is important to continuously monitor the process, the primary goal of process monitoring is to demonstrate that the process's emissions, mostly to the air, do not pose a threat to the environment (UK EA, 2022). In normal operations adequate safety measures and containment protocols must be in place to prevent accidental spills or releases, all units were optimised to minimise MEA release or degradation (see chapter 3?). However, in the case of leaks in the process, whether they be CO2 and MEA related or not, they need to be identified and rectified. Notably, in process dealing with similar amounts of carbon, fugitive emissions from the natural gas industry (which encompasses both conventional and CSG gas) were estimated to be 9.3 million tonnes of carbon dioxide in 2008–09 (DCCEEW, 2012). In the case of accidents or failure of the operation, the hazards have a far more immediate impact. Firstly, in the case of accidental release of the MEA can pose risks to the environment. For example. For example, harming the aquatic life if in contact with any water streams, in cases such as this, these spillages can be contained and then collected with non-combustible absorbent material such as sand, earth, diatomaceous earth and vermiculite (Air liquid, 2022). The most pronounced issue is the rerelease of CO2 into the atmosphere, this could occur in a number of ways. Firstly, if CO2 was released in significant quantities at the plant site or in the surrounding area. Secondly, if there are issues with underground storage, it could lead to immense environmental concerns that would affect the surrounding water and ecosystem, agricultural land, the rerelease of great amounts of CO 2 into the atmosphere (St John, 2013). In terms of transporting materials, CSG deposits in Australia are frequently found near areas of prime agricultural land, such as Queensland's Darling Downs and New South Wales Liverpool Plains (St John, 2013). According to academic findings and media reports, there may occasionally be a conflict between agricultural practices, the development of CSG, and the movement of martials into and out of plants (St John, 2013). Naturally, the carbon capture plant is located within premises close to the CSG plants where materials are typically transported by truck or rail, which can contribute to damaging and polluting the nearby agriculture land. Furthermore, in the transportation CO2 form the carbon capture plant to the storage site, the most unwanted impurity in the stream is considered to be water. If not properly removed, it causes hydrate formation in the transport pipeline. Therefore, in a similar transportation conditions used in this plant, the presence of water is likely to lead to 31 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari corrosion and leaks or even raptures in the pipes, realising CO2 into the atmosphere (Onyebuchi et al., 2018). Furthermore, the process involves wastewater containing contaminants that must be treated before discharge to prevent negative impacts on aquatic surroundings (St John, 2013). Damage through release of untreated production water could also lead to damage to wildlife habitat in sensitive areas and contamination of surface water resources in drinking water catchment (St John, 2013). Modelling undertaken by the former Queensland Water Commission suggested that CSG, activities might affect a small proportion of agricultural aquifers in the Surat basin if contaminates are not disposed of correctly if wastewater is not disposed of properly, it would only further disrupt the local aquifers and environment (St John, 2013). Therefore, wastewater in the plant must be disposed of properly, one method of doing this is treating the purge water using water treatment units before purging or by hiring waste contractors. Notably, all other by-products of this specific flue gas coming out of the absorber are clean and within safe limits, these by-products have no effect on the personal or the environment. In the proposed carbon capture plant, there is 1.44 Kg/s of carbon emitted as reported in chapter 6.1.3. These emissions are safely stored underground. As this process is related to carbon capturing, minimal CO2 emissions are released. This value is well under the legal limits of release in legislated in Australia (Parliament, 2013). 6. MASS & ENERGY BALANCES and Process Integration 6.1 Mass Balance PBD 6.1.1 Flue Gas Lead author: Bryn Barker Contributing author(s): Abdelrahman Abouelela Table 6.1.1.1: Shows the composition of the CSG being combusted in the power plant Component Vol % 𝑥𝑐𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 Methane (CH4) 95.0 0.95 Ethane (C2H6) 3.5 0.035 Propane (C3H6) 1.0 0.01 Carbon dioxide (CO2) 0.3 0.003 Nitrogen (N2) 0.19964 0.0019964 Hydrogen Sulphide (H2S) 0.00036 0.0000036 32 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Assumptions: • • • • Efficiency of the gas turbine is assumed to be 35%. (Brighthub Engineering, 2022) 15% excess air is fed to the turbine N2 and CO2 are assumed to be inert (Mahmud T, 2023) All combustion is complete combustion. Stoichiometric calculations: 𝐶𝐻4 + 2𝑂2 → 𝐶𝑂2 + 2𝐻2 𝑂 (6.1.1.1) 𝐶2 𝐻6 + 3.5𝑂2 → 2𝐶𝑂2 + 3𝐻2 𝑂 (6.1.1.2) 𝐶3 𝐻8 + 5𝑂2 → 3𝐶𝑂2 + 4𝐻2 𝑂 (6.1.1.3) 𝐻2 𝑆 + 1.5𝑂2 → 𝐻2 𝑂 + 𝑆𝑂2 (6.1.1.4) Table 6.1.1.2.HHV and density values (engineering ToolBox, 2003) Component HHV (kJ/m3) Density (kg/m3) Methane 37769 0.67 Ethane 66433 1.36 Propane 95830 1.88 Carbon dioxide - 1.98 Nitrogen - 1.21 Hydrogen sulphide - 1.54 To determine the density of the coal seam gas the individual component densities shown in table 6.1.1.2 were multiplied by their respective molar fractions as shown in table 6.1.1.1. The fuel’s HHV was calculated using the equation below: 𝐹𝑢𝑒𝑙 𝐻𝐻𝑉 = (𝑥𝐶𝐻4 × 𝐻𝐻𝑉𝐶𝐻4 ) + (𝑥𝐶2 𝐻6 × 𝐻𝐻𝑉𝐶2 𝐻6 ) + (𝑥𝐶3 𝐻8 × 𝐻𝐻𝑉𝐶3 𝐻8 ) (6.1.5) 𝐹𝑢𝑒𝑙 𝜌 = (𝑥𝐶𝐻4 × 𝜌𝐶𝐻4 ) + (𝑥𝐶2𝐻6 × 𝜌𝐶2𝐻6 ) + (𝑥𝐶3 𝐻8 × 𝜌𝐶3 𝐻8 ) + (𝑥𝐶𝑂2 × 𝜌𝐶𝑂2 ) + (𝑥𝑁2 × 𝜌𝑁2 ) + (𝑥𝐻2𝑆 × 𝜌𝐻2𝑆 ) (6.1.6) Using equation 6.1.1 to calculate the fuel’s HHV: 𝐹𝑢𝑒𝑙 𝐻𝐻𝑉 = (0.95 × 37.669) + (0.035 × 66.433) + (0.01 × 95.830) = 39.07 𝑀𝐽/𝑚3 Equation 6.1.2 is used similarly to calculate fuel’s density. Fuel ρ= 0.717 kg/m3 The fuel HHV is the calculated in MJ/kg using the equation shown below: 𝐻𝐻𝑉(𝑀𝐽/𝑘𝑔) = 𝐻𝐻𝑉 (𝑀𝐽/𝑚3 ) 𝜌 (𝑘𝑔/𝑚3 ) 39.07 = 0.717 = 54.49 𝑀𝐽/𝑘𝑔 (6.1.7) The proposed power plant wants to generate 100 MJ/s using a gas turbine. Gas turbines have an efficiency of 0.35 (Pashchenko et al., 2022). Therefore, the thermal power is calculated using the equation below: 𝑇ℎ𝑒𝑟𝑚𝑎𝑙 𝑝𝑜𝑤𝑒𝑟 = 𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑎𝑙 𝑝𝑜𝑤𝑒𝑟 η 100 = 0.35 = 285.71 𝑀𝐽/𝑠 (6.1.8) The mass flow of fuel needed to be combusted to give off the required thermal power is calculated using the equation below: 33 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 𝑅𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝐹𝑢𝑒𝑙 𝑖𝑛𝑙𝑒𝑡 𝑚𝑎𝑠𝑠 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒 = 𝑇ℎ𝑒𝑟𝑚𝑎𝑙 𝑝𝑜𝑤𝑒𝑟 𝐻𝐻𝑉 = 285.71 54.49 = 5.243 𝑘𝑔/𝑠 (6.1.9) To determine the mass of each component in the flue, a 100 moles basis was used to determine the mass fractions of each component. To determine the mass of each component the formula below was used: 𝑚𝑎𝑠𝑠 = 𝑚𝑜𝑙 × 𝑀𝑅 (6.1.10) 95 × 16 = 1520 𝑔 After the masses of each component were found, the total mass was determined for the 100 moles basis, then the mass of each component was divided by this total mass to determine their individual mass fractions, the results of this are shown in table 6.1.1.3: Table 6.1.1.3. Calculated mass of each component in the fuel These mass fractions were then multiplied by the determined flue gas mass of 5.2435 kg/s to determine the mass flowrates of the flue gas components, these masses were then used find the molar flowrates of the flue gas components based on the actual mass flowrate. Table 6.1.1.4. mass and molar flowrates of fuel components fuel mass frac Mass flow rate Molar flow rate (mol/s) (kg/s) CH4 0.900579485 4.722161217 295.1351 C2H6 0.062211083 0.326201926 10.8734 C3H8 0.026069406 0.136694141 3.106685 CO2 0.007820822 0.041008242 0.932006 N2 0.003311952 0.017366121 0.620219 H2S 7.25203E-06 3.80258E-05 0.001118 using the individual flue gas molar flowrates in table 6.1.1.4 and substituting them into the stoichiometric combustion equations the flue gas compositions were calculated, a sample calculation is shown below for this: 295𝐶𝐻4 + 590𝑂2 → 295𝐶𝑂2 + 590𝐻2 𝑂 after the stoichiometric calculations were carried out the excess air was calculated, the sum of the stoichiometric oxygen was first calculated before this was then multiplied up to find the excess air. these calculations are shown below. 1.15 × ∑ 𝑠𝑡𝑜𝑖𝑐ℎ𝑖𝑜𝑚𝑒𝑡𝑟𝑖𝑐 𝑂2 = 𝑠𝑢𝑝𝑝𝑙𝑖𝑒𝑠 𝑂2 (6.1.1) 𝑠𝑢𝑝𝑝𝑙𝑖𝑒𝑑 𝑂2 ÷ 0.21 = 𝑡𝑜𝑡𝑎𝑙 𝑎𝑖𝑟 𝑓𝑒𝑒𝑑 (6.1.12) 𝑡𝑜𝑡 𝑎𝑖𝑟 𝑓𝑒𝑒𝑑 × 0.79 = 𝑁2 𝑓𝑒𝑒𝑑 (6.1.13) 𝑠𝑢𝑝𝑝𝑙𝑖𝑒𝑑 𝑂2 − ∑ 𝑠𝑡𝑜𝑖𝑐ℎ𝑖𝑜𝑚𝑒𝑡𝑟𝑖𝑐 𝑂2 = 𝑂2 𝑖𝑛 𝑓𝑙𝑢𝑒 𝑔𝑎𝑠 (6.1.14) 𝑁2 𝑓𝑒𝑒𝑑 + 𝑁2 𝑖𝑛 𝑓𝑢𝑒𝑙 = 𝑁2 𝑓𝑙𝑢𝑒 𝑔𝑎𝑠 (6.1.15) These calculations alongside the calculations for flue gas composition were used to calculate the values shown in table 6.1.1.5: 34 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Table 6.1.1.5. flue gas compositions flue gas CO2 H2O O2 N2 SO2 total Molar flow rate (mol/s) 327.13 635.32 96.58 2786.09 0.0011 3845.1206 Composition (%) 8.51 16.52 2.51 72.46 0.29ppm 100 Mass flow rate (kg/s) 14.394 11.436 3.091 78.011 0.000071616 106.931 Composition (%) 13.46 10.69 67 ppm 2.89 72.95 100 6.1.2 Direct Contact Cooler (DCC-101) All streams highlighted with yellow are streams which were unknown and calculated. Lead author: Sari Miari 3 2 2B 2B D-101 2 1 Table Stream table for unit DCC-101 Stream No. 1 Component (kg/s) CO2 14.394 H2O 11.436 O2 3.091 N2 78.011 Total flow (kg/s) 106.931 Temperature (°C) 140 Pressure (bar) 1.2 Phase V 2B 2 3 0 574.203 0 0 574.203 23 3 L 0.089 574.901 0 0 574.990 40 1.1 L 14.305 10.738 3.091 78.011 106.144 40 2.9 V Assumptions: • • • SO2 mass flow rate is very small. Thus it is neglected and considered as 0 for the calculations. Pressure drop is 0.1 bar only and is assumed to not affect calculations. Only CO2 is absorbed by the cooling water, N2 and O2 absorption are neglected due to being too small. Firstly, the required mass flow rate of inlet cooling water was calculated using an integrated mass & energy balance equation which is explained in section 6.2.2. The cooling water inlet flow rate was calculated to be 31,900.182 mol/s = 574.203 kg/s. Secondly, the amount of water vapour in the flue that condenses due to cooling of the flue gas was calculated using the water vapour partial pressure and saturated pressure. This is shown below: 𝑝𝐻2 𝑂 = 𝑃𝑇𝑜𝑡𝑎𝑙 × 𝑥𝐻2 𝑂 = 1.2 × 0.1652 = 0.1983 𝑏𝑎𝑟 (6.1.2.1) The value of 𝑥𝐻2 𝑂 was obtained from table 6.1.1.5 from section 6.1.1. 35 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari The Antoine’s equation was then used to calculate the saturated pressure of water vapour at 40 ºC (313 K), which is the temperature of the flue gas outlet stream. The parameters for Antoine’s equation were at 313 K were obtained from NIST, 2023. 𝐵 1733.926 log10 𝑃𝑠𝑎𝑡 = 𝐴 − (𝑇+𝐶 ) = 5.20389 − (313+(−39.485)) = −1.1355 (6.1.2.2) 𝑃𝑠𝑎𝑡 = 101.1355 = 0.0732 (6.1.2.3) The mole fraction of the flue gas’ water vapour which will condense was calculated using the equation shown below: 𝑃𝑠𝑎𝑡 𝑥𝐻2 𝑂𝑐𝑜𝑛𝑑𝑒𝑛𝑠𝑖𝑛𝑔 = 𝑃 𝑇𝑜𝑡𝑎𝑙 = 0.0732 1.2 = 0.061 (6.1.2.4) The amount of water vapour in the flue gas which condenses due to cooling was finally calculated using the equation shown below: 𝑛̇ 𝐻2 𝑂𝑐𝑜𝑛𝑑𝑒𝑛𝑠𝑖𝑛𝑔 = 𝑛̇ 𝐻2 𝑂 × 𝑥𝐻2 𝑂𝑐𝑜𝑛𝑑𝑒𝑛𝑠𝑖𝑛𝑔 = 635.318 × 0.061 = 38.751 𝑚𝑜𝑙/𝑠 (6.1.2.5) Finally, the amount of CO2 which gets absorbed from the flue gas onto the cooling water was calculated using Henry’s Law as shown in the equation below: 𝑝𝐶𝑂2 = 𝑥𝐶𝑂2 × 𝑃𝑇𝑜𝑡𝑎𝑙 = 0.0851 × 1.2 = 0.102 𝑏𝑎𝑟 (6.1.2.6) 𝐶 = 𝑘𝐻 × 𝑝𝐶𝑂2 = 0.03445 × 0.102 = 0.003517 𝑚𝑜𝑙/𝐿 (6.1.2.7) The kH value for CO2 at 23 ºC was obtained from NIST, 2023. This is because Henry's law is typically applied to the temperature of the liquid phase, which, in this case, would be the cooling water inlet stream which is at 23 °C. The obtained value of 0.003517 mol/L means that every litre of water in the cooling stream absorbs 0.003517 moles of CO2, which is equivalent to 0.155 grams of CO2. Based on the calculation in 6.2.2, the molar flow rate of the cooling water is 31,900.182 mol/s = 574.203 kg/s. the specific volume of water at 23 °C is 1.00246 L/kg (ref), this is used to calculate the volumetric flow rate of the cooling water stream: 𝑉̇ 𝐻2 𝑂𝑐𝑜𝑜𝑙𝑖𝑛𝑔 𝑖𝑛𝑙𝑒𝑡 = 𝑚̇𝐻2 𝑂𝑐𝑜𝑜𝑙𝑖𝑛𝑔 𝑖𝑛𝑙𝑒𝑡 × 𝑣𝑎𝑡 23 °C = 547.203 × 1.00246 = 575.616 𝐿/𝑠 (6.1.2.8) The volumetric flow rate of water is then multiplied by absorption concentration as shown below: 𝑛̇ 𝐶𝑂2,𝐴𝑏𝑠𝑜𝑟𝑏𝑒𝑑 𝑏𝑦 𝑐𝑜𝑜𝑙𝑖𝑛𝑔 𝑤𝑎𝑡𝑒𝑟 = 𝐶 × 𝑉̇ 𝐻2 𝑂𝑐𝑜𝑜𝑙𝑖𝑛𝑔 𝑖𝑛𝑙𝑒𝑡 = 0.0003517 × 575.616 = 2.025 𝑚𝑜𝑙/𝑠 (6.1.2.8) 2.025 mol/s of CO2 is equivalent to 0.089 kg/s. 6.1.3 Packed Bed Absorption Column (A-101) Lead author: Bryn Barker Contributing author(s): Faisal Kamal 36 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Stream table for unit A-101 Stream No. 3A Component flow (kg/s) 14.39 CO2 H2O 10.74 3.09 O2 N2 78.01 MEA 0 106.23 Total flow (kg/s) Temperature (°C) 40 1.2 Pressure (bar) Phase V 5 4 12 25.91 167.62 0 0 71.84 265.37 ? 1.1 L 1.44 10.74 3.09 78.01 Trace 93.28 40 1.1 V 12.95 167.62 0 0 71.84 252.42 40 1.2 L *Yellow values are those determined by mass balance Assumptions: Only carbon dioxide is absorbed by the lean MEA stream, stream 12. (Mahmud T, 2023) 90% of the CO2 from 3A is absorbed by 12 as per the briefing document For the mass balance the vaporisation of MEA in stream 4 is negligible From the assumption that only CO2 is absorbed by the lean MEA stream (stream 12) all of the N2, H2O and O2 present in the flue gas from the DCC in stream 3A will leave the absorption column in stream 4. Since 90% of the CO2 is absorbed by stream 12 then the CO2 present in stream 4 was given by equation 6.1.3.1 shown below, 14.39𝑚̇ × 0.1 = 1.44𝑚̇𝐶𝑂2 (6.1.3.1) From this calculation the composition of stream 4 was fully determined. From the mass of CO2 present in the flue gas stream the mass of CO2 absorbed by the MEA stream inside the absorption unit was determined, this calculation is shown in equation 6.1.3.2 below. 14.39𝑚̇ × 0.9 = 12.95𝑚̇𝐶𝑂2 (6.1.3.2) eq 6.1.3.2 the loading values of the lean and rich MEA streams were set as 0.25 moles CO2/mole MEA and 0.5 moles CO2/mole MEA respectively. From these loading values the MEA required for the absorption of the calculated CO2 was calculated . the equations used in these calculations were as follows: 37 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 0.5 𝑚𝑜𝑙 𝐶𝑂2 𝑚𝑜𝑙 𝑀𝐸𝐴 − 0.25 𝑚𝑜𝑙 𝐶𝑂2 𝑚𝑜𝑙 𝑀𝐸𝐴 = 0.25 𝑚𝑜𝑙 𝐶𝑂2 𝑜𝑓 𝑚𝑜𝑙 𝑀𝐸𝐴 𝑎𝑑𝑑𝑖𝑡𝑖𝑜𝑛𝑎𝑙 𝑙𝑜𝑎𝑑𝑖𝑛𝑔 (6.1.3.3) this additional loading is equal to the molar amount of CO2 that is required to be absorbed in the absorber, this molar amount is calculated from the mass flowrate determined in equation 6.1.3.2. consequently the number of moles of CO2 per second can be multiplied by the additional loading value calculated in equation 6.1.3.3 to determine the number of moles present in both streams 12 and 5. This calculation is shown in equation 6.1.3.4 below 294.32𝑛̇ 𝐶𝑂2 × 4 = 1177.28𝑛̇ 𝑀𝐸𝐴 (6.1.3.4) eq 6.1.3.4 From these calculations the moles of CO2 present in streams 12 and 5 can be calculated from the molar flowrate of MEA and the pre-determined loading values, the calculations are shown in equations 6.1.3.5 and 6.1.3.6 below. 0.25 × 1177.28 = 294.32𝑛̇ 𝐶𝑂2 𝑖𝑛 𝑠𝑡𝑟𝑒𝑎𝑚 4 (6.1.3.5) 0.5 × 1177.28 = 588.64𝑛̇ 𝐶𝑂2 𝑖𝑛 𝑠𝑡𝑟𝑒𝑎𝑚 2 (6.1.3.6) The process selection determined that the optimum concentration of MEA in an MEA water solution was 30wt%. From this the molar flowrate of MEA calculated in equation 6.1.3.4 was converted into a mass flowrate and this was used to calculate the mass flowrate of water required in streams 5 and 12. This was determined to be 167.62 KG/s of water 6.1.4 Water wash (w-101) Lead author: Bryn Barker Stream table for unit w-101 Stream No. Component flow (kg/s) CO2 H2O O2 N2 MEA Total flow (kg/s) Temperature (°C) 4 4A wwin wwout 1.44 10.74 3.09 78.01 0.0093 93.37 40 1.44 10.74 3.09 78.01 0.00016 93.28 40 0 1.35 0 0 0 1.35 23 0 1.35 0 0 0.0091 1.36 23 38 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Pressure (bar) Phase 1.1 V 1.1 V 1.1 L 1.1 L *Note yellow values are those calculated by mass balance Assumptions: The water wash is capable of reducing the MEA emissions in the flue gas to 1.7 ppm (Liu et al., 2021) The MEA Concentration in the water wash water after absorption is 0.2 mol% (Liu et al., 2021) only MEA is absorbed by the water wash water Stream 4 is the cleaned flue gas from the absorber as calculated in mass balance 6.1.3. The vapour pressure of the liquid MEA was first determined by the following equation using 313K (40°C) for T as this was the temperature of the absorption column tops. (Nguyen et al., 2010) −1.04×104 )− 𝑇 0 𝑃𝑀𝐸𝐴 = 𝐸𝑋𝑃 [92.6 + ( (9.47𝐿𝑛𝑇) + (1.9 × 10−18 𝑇 6 )] (6.1.4.1) this gave an MEA vapour pressure of 0.1424KPa. This calculated vapour pressure was substituted into equation 6.1.4.2 . (Nguyen et al., 2010) 𝛾𝑎𝑚𝑖𝑛𝑒 = 𝑃𝑎𝑚𝑖𝑛𝑒 0 𝑥𝑎𝑚𝑖𝑛𝑒 ×𝑃𝑎𝑚𝑖𝑛𝑒 (6.1.4.2) for this equation 𝛾𝑎𝑚𝑖𝑛𝑒 , the activity coefficient of the MEA, was taken to be 1, and 𝑥𝑎𝑚𝑖𝑛𝑒 was the mole fraction of MEA in stream 4. Rearranging equation x a gave a partial pressure of the MEA, 𝑃𝑎𝑚𝑖𝑛𝑒 , in stream 4 of 0.0048KPa. (Nguyen et al., 2010) Because the partial pressure of the MEA vapour was determined Dalton’s law was then used to work out the number of moles of MEA present in stream 4, Dalton’s law is shown in equation 6.1.4.3 below 𝑃𝑡𝑜𝑡𝑎𝑙 𝑛𝑡𝑜𝑡𝑎𝑙 𝑃 = 𝑛𝑎𝑚𝑖𝑛𝑒 (6.1.4.3) 𝑎𝑚𝑖𝑛𝑒 for the Dalton’s law equation 𝑃𝑡𝑜𝑡𝑎𝑙 was taken to be 110Kpa, this was determined from the pressure drop in the absorber, from this goal seek was used to determine the moles of amine present in stream 4. The equation used to calculate 𝑛𝑎𝑚𝑖𝑛𝑒 is shown in equation 6.1.4.4. 110 3511.86+𝑛𝑎𝑚𝑖𝑛𝑒 0.0048 =𝑛 𝑎𝑚𝑖𝑛𝑒 (6.1.4.4) the number of moles of MEA in stream 4 was determined to be 0.15mol/s. This was calculated to be 99.6ppm. From this calculation as stated in the assumptions the concentration had to be reduced to 1.7ppm. From these calculations it was determined that 9.13g/s of MEA would have to be removed from the flue gas by the water wash. From the assumption that the water wash should contain 0.2 39 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari mol% MEA it was calculated that the water wash would require a water flowrate of 1.35kg/s to remove the MEA. 6.1.5 S-101 Lead author: Faisal Kamal Contributing author(s): Faisal Kamal Due to lack of initial information and the “delaying” of the calculation of the column stages, it is assumed that the stream 6 is in equilibrium with the stream 5B, for the same reasons, a “stripping split” was assumed between the column itself and the reboiler, The Ratio is 70% of CO2 Stripping is done in the column while 30% occurs in the reboiler. It is also assumed that both the top and bottom product streams are in equilibrium with the Reflux and Boil up streams respectively. The pressure in the system is also assumed to be constant. 6 CON-101 5B 8 7 S-101 10 REB-101 9 11 Table 6.1.5.1: Stream Stream No. CO2 flow (Kg/s) MEA flow (Kg/s) H2O Flow (Kg/s) Total flow (Kg/s) Temperature (°C) Pressure (bar) Phase 5B 25.91 71.83 167.71 265.47 102.78 1.2 L 6 ? ? ? ? 102.78 1.8 V table for unit S-101 7 8 9 ? 12.95 ? ? ? ? ? ? ? ? ? ? 40 40 ? 1.8 1.8 2 L V L 10 ? ? ? ? 120 2 V 11 12.95 ? ? ? 120 2 L The aim of this mass balance is to determine the flow rates of each stream, the ultimate aim is to determine the purity of the of the top product, stream 8. The temperature of stream 6 is known from the assumption of equilibrium with the Rich MEA stream inlet, therefore thermal equilibrium is an extension of that assumption. Furthermore, the pressure and temperature of all units are set in accordance with literature as set in chapter 3, these pressure are chosen with the best performance of the solvent used and loading values in mind. The temperatures of streams 7 and 8 are set to the temperature of the condenser, while streams 10 and 11 are set to the temperature of the reboiler. The amount of CO2 leaving at stream 8 is a set value as it is the difference of the lean and rich loading values of 0.25 and 0.5 mol/ mol MEA. 40 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.1.5.1 Condenser mass balance: 6.1.5.1.1 Stream 6: The first step of the mass balance is to calculate the concentrations of Stream 6. Since equilibrium with stream 5B was assumed. The calculation would follow simple bubble point, dew point, flash calculations (Coulson and Richardson, 2005). Therefore, to calculate the concentrations of stream 6 we employ the following equation: 𝑦𝑖 = 𝐾𝑖 𝑥𝑖 (6.1.5.1) In this case, yi would be the concentration of a component in stream 6, while the xi value would signify the molar concentration of a stream 5B component. The Ki value would be the equilibrium constant of said component at the specific temperature that both streams share. This constant is acquired by dividing the Antione’s equation of a component by the unit’s pressure and is done at the temperature of the of the stream. This equilibrium constant is key to determining the concentrations of the components in Stream 6. The equation for Ki is: 𝐾𝑖 = 10 𝐵 𝐴− 𝑇+𝐶 𝑃 (6.1.5.2) For Example, in determining vapour concentration of H2O, we must first define xH2O which would be: 𝑥𝐻2𝑂 = 𝑚𝑜𝑙 ) 𝑠 𝑚𝑜𝑙 𝑟𝑎𝑡𝑒 (11078.93 ) 𝑠 𝑀𝑜𝑙𝑎𝑟 𝑓𝑙𝑜𝑤 𝑟𝑎𝑡𝑒 𝑜𝑓 𝐻2 𝑂 (9312.41 𝑇𝑜𝑡𝑎𝑙 𝑀𝑜𝑙𝑎𝑟 𝑓𝑙𝑜𝑤 = 0.8405 (6.1.5.3) The equation was repeated to attain other concentrations where 𝑥𝐶𝑂2 =0.053 and 𝑥𝑀𝐸𝐴 = 0.106. Finally, to determine the equilibrium constant KH2O, Antoine’s coefficients for H2O must be used at the appropriate temperature, these can be seen in table 1 below: Table 6.1.5.2: Antoine's coefficients of MEA and H2O, where the pressure is in (Bar) and the temperature in (Kelvin) MEA H2O TEMPERATURE (K) 338.6-444.1 344 - 373 RANGE A B C 4.29252 5.08354 1408.873 1663.125 -116.093 -45.622 With these parameters, KH2O value can be calculated as follows: 1663.125 𝐾𝐻2𝑂 105.08354−375.78−45.622 = = 0.617 1.8 The equations 6.1.5.2 and 6.1.5.3 are repeated again for MEA with the stream 5B’s liquid concentration and the MEA Antoine’s coefficients respectively, this yields 𝐾𝑀𝐸𝐴 = 0.0409. Equation 6.1.5.3 is repeated for CO2 This allows the calculation of the vapour concentrations of these two components using Equation (6.1.5.1). For example, in the case of H2O, the vapour concentration would be as follows: 41 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 𝑦𝐻20 = 0.617 ∗ 0.8405 = 0.519 The repetition of the previous three equations to determine the value the vapour concentration of MEA in stream 6 yields the value of yMEA = 0.0021. This value is considerably smaller than the water value due to MEA having the lowest volatility of all the components. Having obtained both these values, we can calculate the concentration CO2 in stream 6 to be yCO2 = 0.478. This is done as the summation of all concentrations in a compound is equal to 1: 𝛴𝑥𝑖 𝑜𝑟 𝛴𝑦𝑖 = 1 Equation (6.1.5.4) Notably, KCO2 calculations has not been conducted in stream 6. This is because the mass balance calculation does not require the specific calculation of the equilibrium constant of CO 2 at this stage. The second rationale is that CO2 has a critical temperature of 31°C. Consequently, at temperatures higher than that, Antoine's equations are unavailable and are less accurate. This will be covered in more detail in the stream 7 calculations. 6.1.5.1.2 Stream 7: Stream 3 is the reflux stream of the condenser; this stream can be calculated using the information acquired from the calculations of stream 6 above. The concentrations of stream 7 can be obtained by: 𝑥𝑖 = 𝑧𝑖 1 − 𝑉(𝐾𝑖 − 1) Equation (6.1.5.5) In this equation the 𝑧𝑖 is the inlet concentration, in this case this is the vapour concentrations 𝑦𝑖 from stream 6. V is the vapour fraction in the condenser, i.e., how much of stream 6 vaporises. This value was assumed at 0.5 to achieve initial results. However, through goal seeking a value of the vapour fraction was attained that would satisfy equation (6.1.5.4), where the vapour fraction value attines sum of 𝑥𝑖 to equal 1. Notably, 𝐾𝑖 must be calculated again for stream as its temperature is lower (40°C), this would require new Antoine’s coefficient, these, and all other coefficients are taken from national institute of standers and technologies (NIST, 2023). These can be seen in table 2 below: Table 6.1.5.3: Antione's equations at the range of 40°C, temperature and pressure of CO2 and MEA are in Celsius and mmHg. H2O temperature and pressure are at kelvin and Bar MEA H2O CO2 TEMPERATURE RANGE (K) 283-637 303-334 216-304 A B 8.36214 5.20389 7.8101 2117.92 1733.926 987.44 C 215.389 -39.485 290.9 In the case of CO2 and MEA, to perform the calculations correctly, the temperature in to be used Antoine’s equation was converted into Celsius, the pressure value from Antoine’s equations was 42 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari turned into bar by dividing it by 750.1 before being dived by the unit’s pressure to attain the equilibrium constant. For example, in the case of MEA the calculation would be: 2117.92 108.36214−40+215.389 ( ) 750.1 𝑘𝑀𝐸𝐴 = = 0. 000868621 1.8 This method is repeated again to calculate the KCO2 Values. It’s important to note that the temperature range for CO2 in the above table is the highest range possible for CO2 as mentioned before 31°C is the critical temperature for CO2. This was done in accordance with advice form consultants, the optimum way of attaining the KCO2 at these conditions would be software such as Aspen Plus. As access to Aspen is not granted at this stage of the calculations, and as the temperature difference between the condenser and the temperature limit of Antoine’s coefficients is relatively small at 9 °C. A decision was made to use the coefficients at the critical temperature of CO2. As Antione’s parameters for H2O were in the units Kelvin and Bar, no conversion was needed before or during the calculations. This information is all that is required to calculate the concentrations in stream 7. For instance, as per equation (6.1.5.5), in the case of MEA: 𝑥𝑀𝐸𝐴 = 0.0021 = 0.004244 1 − 0.487924927(0. 000868621 − 1) This equation was repeated two additional times with the values of H2O and CO2 to calculate their liquid molar concentrations in stream 7. Where it was found that 𝑥𝐶𝑂2 = 0.01935 and 𝑥𝐻2𝑂 = 0.9764. It should be noted that the vapour fraction used in the equation above and in the calculations for the 𝑥𝑖 values is the vapour fraction value that was obtained using goal seeking to ensure that the sum of 𝑥𝑖 is equal to 1. The results of the 𝑥𝑖 values summed can be used to confirm the success and accuracy of the vapour fraction value used: 0.019355276 + 0.0042448 + 0.9764 = 1 6.1.5.1.3 Stream 8: In stream 8 the flow rate of CO2 is already specified; this means that calculating all the concentrations in the stream will provide the rest of the flow rates in the stream. In order to calculate the concentration, equation 6.5.1.1 is repeated here, where 𝑥𝑖 is equal to the previously calculated liquid concentrations in stream 7. The Ki are also the same as the temperature and pressure are the same in both streams. Therefore, for example, in the case of stream 8’s MEA: 𝑦𝑀𝐸𝐴 = 0.000868621 ∗ 0.0042448 = 0.0008481 As mentioned before, small concentrations of MEA are expected in all vapour phases due to MEA’s low volatility relative to other components in the system. This can be seen with the rest of the calculation of the concentrations as 𝑦𝐻2𝑂 = 0.0397 and 𝑦𝐶𝑂2 = 0.95944. The value of 𝑦𝐶𝑂2 signifies 43 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari that Stream 8 has a CO2 purity of 95.94%, this is deemed to be appropriate and is consistent with literature (Goto et al., 2013) 6.1.5.1.4 Flowrates around condenser: Having made all preliminary calculations, the flow rates in the above streams can know be calculated. Firstly, in stream 8, the flow rate of CO2 is known, therefore the flowrate of the two other components in the stream can be calculated. However, to start, the overall flow rate in stream 8 must be calculated first using: 𝑂𝑣𝑒𝑟𝑎𝑙𝑙 𝑀𝑜𝑙𝑎𝑟 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒 𝑛̇ = 𝑛̇ 𝑖 𝑦𝑖 Equation (6.1.5.6) In this case, 𝑛̇ 𝑖 is the CO2 molar flowrate which is already to be 294.45 mol/s (Table 1). Similarly, 𝑦𝑖 is the molar fraction of CO2 in the composition previously calculated at 0.95944. Therefore, applying equation (6.1.5.6) on these values yields and overall molar flow of 306.86 mol/s. Having calculated the overall flow rate in the stream, it is possible now to define the flowrates of the two other components: 𝑛̇ 𝑖 = 𝑛̇ ∗ 𝑦𝑖 Equation (6.1.5.7) Notably, in both pervious equations, 𝑦𝑖 or 𝑥𝑖 can be used depending on the state of the stream in question. Using the equation (6.1.5.7), the molar flow rates of both H2O and MEA were calculated at 12.18 mol/s and 0.26 mol/s respectively. In converting these flowrate values, CO2 = 12.95 Kg/s, H2O = 0.21 Kg/s, and MEA= 0.0158 Kg/s. The calculation of these values were the last remaining unknowns in stream 8. Having these values allows for the calculation of the flowrates of the other two streams before it. Consequently, the values from stream 8 alongside the vapour fraction used in equation (6.5.1.3) can be used to calculate the amount of CO2 in the inlet to the condenser Stream 6. The vapour fraction is an indication of split into vapour or liquid in the condenser. For example, in the case of CO2, V = 0.487924927 is equal to 12.95 Kg/s, this is because 48.79% of the CO2 vaporised, or in this case did not condense and stayed in the vapour phase, and from that value, the amount of overall CO2 coming in from the inlet cane be calculated. Therefore, equation (6.1.5.6) can be used here to determine the flowrate of CO2 in stream 6: 𝑚𝑜𝑙 294.42 ( 𝑠 ) 𝑚𝑜𝑙 𝑆𝑡𝑟𝑒𝑎𝑚 2 𝐶𝑂2 𝑀𝑜𝑙𝑎𝑟 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒 = = 603.41 ( ) 0.487924927 𝑠 With this value obtained, alongside the 𝑦𝑖 values from Stream 6 Calculations, the overall molar flowrate of Stream 6 can be calculated using the same equation. Thus, the overall molar flowrate in stream 6 is 1261.15 mol/s. Using equation (6.1.5.7), the rest of the molar flowrates of the individual 44 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari components are calculated at; 654.99 mol/s for H2O, and 2.743 mol/s for MEA. In converting these values, in stream 6: MEA = 0.167 Kg/s, H2O= 11.79 Kg/s, and CO2= 26.55 Kg/s. Finally, stream 7 cane be calculated using simple mass balance, where it would be equal to the difference between stream 6 and stream 8: Equation (6.1.5.8) 𝑆𝑡𝑟𝑒𝑎𝑚 7 = 𝑆𝑡𝑟𝑒𝑎𝑚 6 − 𝑆𝑡𝑟𝑒𝑎𝑚 8 And so, the streams around the condenser are equal to: Table 6.1.5.4: Table showing flowrates of streams 6 to 8. Stream No. 6 7 8 CO2 flow (Kg/s) 26.55623271 13.59878481 12.9574479 MEA flow (Kg/s) 0.167329041 11.57704016 0.01587577 H2O Flow (Kg/s) 11.79646581 0.151453271 0.219425647 Total flow (Kg/s) 38.52002756 25.32727825 13.19274932 Temperature (°C) 102.78 40 40 Pressure (bar) 1.8 1.8 1.8 Phase V L V 6.1.5.2 Mass Balance around Reboiler and column: 6.1.5.2.1 Stream 11 Stream 11 is the outlet stream from the reboiler, this stream is known as the Lean solvent stream. As this is one of the only two outlets around the entire system, the other being stream 8. The compositions and flowrates of the stream can easily be determined using simple in = out mass balance, and therefore: 𝑆𝑡𝑟𝑒𝑎𝑚 11 = 𝑆𝑡𝑟𝑒𝑎𝑚 5𝐵 − 𝑆𝑡𝑟𝑒𝑎𝑚 8 Equation (6.1.5.9) Subtracting the flow rates of the pure CO2 stream, stream 8, and the Rich solvent inlet stream, stream 5B, yields the following values for each component: 𝑆𝑡𝑟𝑒𝑎𝑚 11 𝐶𝑂2 = 25.91 − 12.95 = 12.96 𝐾𝑔 𝑠 𝑆𝑡𝑟𝑒𝑎𝑚 11 𝑀𝐸𝐴 = 71.83 − 0.015 = 71.78 𝐾𝑔 𝑠 𝑆𝑡𝑟𝑒𝑎𝑚 11 𝐻2 𝑂 = 167.71 − 0.21 = 167.50 𝐾𝑔 𝑠 The total flowrate in stream 11 is 252.24 Kg/s. Notably, as the values of stream 8 are the difference between the Rich and lean solvents, the lean solvent must be fed these differences as “make up Water/MEA”. This compensation of lost material has been further discussed in Chapter 3. 45 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.1.5.2.2 Stream 10 Stream 10 contains the vapour produced in the reboiler, hence it is known as the boil up stream. Based on the aforementioned assumption that 30% of CO2 stripping occurs in the reboiler, the CO2 in stream 10 is 30% of that in stream 6. Thus, stream 6 contains 7.96 Kg/s or 181 mol/s of CO2. Furthermore, since stream 10 is in equilibrium with stream 11, equations (6.1.5.1-6.5.1.4) can be used in this case to calculate the vapour concentrations in stream 10 using the 𝑥𝑖 concentrations of stream 11 and the 𝐾𝑖 values at the temperature of the reboiler, 120 °C. Notably, Because MEA in both streams 10 and 6 is in the appropriate temperature range, the Antione's coefficients used for MEA are the same as those in Table 1. But since H2O is outside of Table 1's temperature range, new Antione's coefficients must be applied. Table X below shows the new H2O coefficients. Additionally, the reboiler's pressure is 2 Bar, so the 𝐾𝑀𝐸𝐴 value will still differ. Table 6.1.5.5: Antone's coefficients of MEA at 120 °C, Pressure in Bar, Temperature in °C. TEMPERATURE RANG (K) A B C H2O 379-573 3.55959 643.748 -198.043 From this, the 𝐾𝑖 values of two of the components can be attained. Where 𝐾𝐻2𝑂 = 0.9048 and, 𝐾𝑀𝐸𝐴 = 0.0800. 𝐾𝐶𝑂2 is not calculated for the same reasons mentioned in previously. Having calculated the 𝐾𝑖 values, the 𝑥𝑖 values can be obtained from Stream 11 using equation (6.1.5.3), where it can be found that, 𝑥𝑀𝐸𝐴 = 0.1093 , 𝑥𝐻2𝑂 = 0.8633 , and 𝑥𝐶𝑂2 = 0.0273 . In acquiring both the equilibrium constant and the liquid concentration, the vapour concentrations in stream 10 can be calculated using equation (6.1.5.1), where it can be found that 𝑦𝐻2𝑂 = 0.7811 and 𝑦𝑀𝐸𝐴 = 0.0087, and, using equation (6.1.5.4) 𝑦𝐶𝑂2 = 0.2102. With the concentrations calculated in stream 10, the flowrates can be easily calculated as the flowrate of CO2 is known. Therefore, using equation (6.1.5.6), the overall flowrate in stream 6 is: 𝑚𝑜𝑙 181 ( ) 𝑠 = 861.776 𝑚𝑜𝑙 𝑜𝑟 20.52 𝐾𝑔 𝑆𝑡𝑟𝑒𝑎𝑚 10 𝑂𝑣𝑒𝑟𝑎𝑙𝑙 𝑀𝑜𝑙𝑎𝑟 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒 = 0.2102 𝑠 𝑠 From this, using equation (6.1.5.7), the rest of the flowrates can be calculated: 𝑆𝑡𝑟𝑒𝑎𝑚 10 𝑛𝐻20 = 0.7811 ∗ 861.776 = 673.20 𝑚𝑜𝑙 𝐾𝑔 𝑜𝑟 12.12 𝑠 𝑠 𝑆𝑡𝑟𝑒𝑎𝑚 10 𝑛𝑀𝐸𝐴 = 0.0087 ∗ 861.776 = 7.544 𝑚𝑜𝑙 𝐾𝑔 𝑜𝑟 0.46 𝑠 𝑠 6.1.5.2.3 Stream 9 The calculations in stream 9 are a simple mass balance similar to that of stream 11, where we can take IN = OUT around the reboiler, where out is streams 11 and 10, and IN is stream 9 itself. Therefore, to calculate stream 9: 46 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 𝑆𝑡𝑟𝑒𝑎𝑚 9 = 𝑆𝑡𝑟𝑒𝑎𝑚 11 + 𝑆𝑡𝑟𝑒𝑎𝑚 10 Equation (6.1.5.10) And so, the flowrates for each component in stream 9 can be calculated using equation (6.1.5.7) and are as follows: 𝑛𝑐𝑜2 = 475.44 𝑚𝑜𝑙 𝐾𝑔 𝑜𝑟 20.92 𝑠 𝑠 𝑛𝑀𝐸𝐴 = 1184.96 𝑛𝐻2𝑂 = 9973.43 𝑚𝑜𝑙 𝑠 𝑜𝑟 179.62 𝑚𝑜𝑙 𝐾𝑔 𝑜𝑟 72.28 𝑠 𝑠 𝐾𝑔 . 𝑠 6.1.5.2.4 Flow rates around the reboiler and column. All stream flowrates have already been calculated, and therefore this section will be a calculation of the changes in the column and a confirmation of the rest of the streams. Firstly, in the column, there is an amount of CO2 vaporised as per the assumption of 70% of CO2 stripping happening in the column. This amount can be known by getting 70% of the CO2 value in stream 6. Thus, in the column itself, there is 422.38 mol/s or 18.59 Kg/s. This is not the only reaction in the column however, as it is expected that H2O and MEA undergo changes in the column. It is simple to calculate these changes with the knowledge of the rest of the streams in the system. The change happening in the column can be calculated as the difference between the inlet to the condenser and the boil up stream, streams 6 and 10 respectively. Taking out that difference resulted from subtracting stream 10 to stream 6 gives the amount of the specific material vaporised/condensed in the column: Column 𝑚𝑎𝑠𝑠 𝑏𝑎𝑙𝑎𝑛𝑐𝑒 = 𝑆𝑡𝑟𝑒𝑎𝑚 6 − 𝑆𝑡𝑟𝑒𝑎𝑚 10 Equation (6.1.5.11) If the difference is positive, it indicates the vaporisation of a component (i.e. CO2 vaporisation in the column), if negative it indicated condensation for instance, in the case of H2O: 𝐾𝑔 𝐾𝑔 𝐾𝑔 − 12.12 = −0.33 𝑠 𝑠 𝑠 This shows that there are 0.33 Kg/s of H2O condensing in the column, doing the same calculation 11.79 for MEA, yields a value of -0.29 Kg/s. This means both MEA and water condense in the column while only CO2 evaporates. This discrepancy between the MEA and H2O condensation and the CO2 vaporisation, is again due to the volatility of each component, where CO2 has the lowest. Furthermore, the condensation and vaporisation occur in the column due to the heat transfer happening between the stream 7, the reflux stream, and stream 10, the boil up stream. As the hot vapour proceeds to the top of the column, it is cooled down by the colder reflux stream. Meanwhile stream 7 and the inlet stream 5B are heated up by the high temperature of the boil up, stream 10, coming out of the reboiler, this heating vaporises the CO2 in streams 5B and 7. These values could help further corporate the values of stream 9. This can be done by subtracting vaporisation of a component or adding the condensation of a component to stream 5B + stream 7. Thus, for each component in stream 9: Equation (6.1.5.11) 47 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 𝑆𝑡𝑟𝑒𝑎𝑚 9 = 𝑆𝑡𝑟𝑒𝑎𝑚 5𝐵 + 𝑆𝑡𝑟𝑒𝑎𝑚 7 + 𝐶𝑜𝑛𝑑𝑒𝑛𝑠𝑎𝑡𝑖𝑜𝑛 𝑖𝑛 𝑐𝑜𝑙𝑢𝑚𝑛 (𝑜𝑟 − Vaporisation in colmn ) Running this calculation with the above values provided of vaporisation and condensation yields the same values previously calculated in stream 9. This is done as a way of confirming both calculations. Therefore, the final values of all flowrates around the reboiler are as follows: Table 6.1.5.6: mass balance around reboiler. Stream No. 9 10 11 CO2 flow (Kg/s) 20.92431771 7.966869814 12.9574479 MEA flow (Kg/s) 72.28294379 0.460208161 71.82273563 H2O Flow (Kg/s) 179.6215949 12.12446984 167.4971251 Total flow (Kg/s) 272.8288564 20.55154782 252.2773086 Temperature (°C) ? 120 120 Pressure (bar) 2 2 2 Phase L V L 6.1.5.3 Mass balance summary table Table X below shows the final and complete mass balance around the stripper system. The table contains the flowrates, phases, temperatures, and pressures of each stream. Furthermore, the table contains the vaporisation and condensation flowrates occurring inside the column. Table 6.1.5.7: Final mass balance summary table Stream No. CO2 flow (Kg/s) MEA flow (Kg/s) H2O Flow (Kg/s) Total flow (Kg/s) Temperature (°C) Pressure (bar) Phase 5B 25.910 71.830 167.717 265.470 102.780 1.200 L 6 26.556 0.167 11.796 38.520 102.780 1.800 V 7 13.599 0.151 11.577 25.327 40.000 1.800 L 8 12.957 0.016 0.219 13.193 40.000 1.700 V 9 10 20.924 7.967 72.283 0.460 179.622 12.124 272.829 20.552 110.500 120.000 1.800 2.000 L V 11 Vap in collumn Cond in column 12.957 18.589 --------------71.823 --------------1.111 167.497 --------------0.328 252.277 18.589 1.439 120.000 ----------------------------1.900 1.800 1.800 L V L With these mass balance finished, the reflux and boil up rations can be calculated as, calculated as 0.32 and 0.08 respectively. These values were found to be constant with literature (Gilliland, 1940). The mass balance is based in the assumptions made, most of the assumptions made are practically realistic (Coulson and Richardson, 2005), however, the assumption of stream 6 being in equilibrium with stream 5B is not entirely based in reality. The actual temperatures will differ in these streams and thus, the mass balance calculations. Notably, without this assumption and without knowledge on the design of the column, such as column diameter, and column height, calculating the mass balance across the systems is not feasible. Furthermore, the assumption regarding the amount of stripping occurring in the column or reboiler are an estimation of reality and are not to be taken as a fact. The precision of these calculations is likely to be affected should the design parameters of the column be known (Coulson and Richardson, 2005). The number of stages in particular would lead to more precise and closer to reality calculations. This method followed is the typical method used when the design parameters of the column are not known, therefore, it provides a good intimal estimation despite not being entirely accurate. 48 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.1.6 Compressor train (COM-1 to COM-4, C-102 to C-105, D-101&D-102) Lead author: Abdelrahman Abouelela Contributing author(s): N/A Mass Balance: Assumptions: - All Water and MEA is removed by the dryer. The mass balance for the compressor train is very straightforward as a concentrated stream of CO2 is only compressed and cooled, with no actual reaction taking place. However, there is some water and trace amounts of MEA in the stream, which are removed through the use of an adsorption dryer before they enter the compressor train. The following is the mass balance for the entire process: Table 6.1.6.1: Stream table for compressor train Stream No. 8 13 14 12.95 12.95 12.95 0.22 0 0 0.02 0 0 13.19 12.95 12.95 Temperature (°C) 40 40 270 Pressure (bar) 1.7 1.7 14 Phase V V L CO2 flow (kg/s) H2O flow (kg/s) MEA flow (kg/s) Total flow (kg/s) *Streams 14-21 are the same, except for temperature and pressure 49 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.2 Energy Balance 6.2.1 Direct Contact Cooler (DCC-101) Lead author: Sari Miari Contributing author(s): N/A Stream table for unit D-101 1 Stream No. 106.931 Total flow (kg/s) 140 Temperature (°C) 1.2 Pressure (bar) V Phase For the energy balance: 2B 574.203 23 3 L 2 574.990 40 2.9 L 3 106.144 40 1.1 V ̂1 + 𝑛2𝐵 ̂2𝐵 = ∑ 𝑛̇ 3 𝐻 ̂3 + 𝑛̇ 2 𝐻 ̂2 ∑ 𝑛̇1 𝐻 ̇ 𝐻 ṅ in (mol/s) substance ̂ in (kJ/mol) H ̂ 1,1 + H ̂ 1,2B H H2O ṅ 1 +ṅ 2b CO2 ṅ 1 ̂2 H O2 ṅ 1 N2 ṅ 1 ̂3 H ̂4 H ṅ 3 + ṅ 2 ̂ out (kJ/mol) H ̂ 5,3 + H ̂ 5,2 H ṅ 3 + ṅ 2 ̂ 6,3 + H ̂ 6,2 H ṅ out (mol/s) ̂7 H ̂8 H ṅ 3 ṅ 3 Table 6.2.2.1. cp a + bT + cT2 + dT3 kJ/mol °C substance H2O (g) H2O (l) CO2 (g) O2 (g) N2 (g) a x 103 33.46 75.4 36.11 29.1 29.0 b x 105 0.688 0 4.233 1.158 0.2199 c x 108 0.7604 0 -2.887 -0.6076 0.5723 d x 1012 -3.593 0 7.464 1.311 -2.871 Heat of Vaporisation = 40.656 kJ/mol, and Heat of Condensation = -40.656 Stream 1 T= 140 °C. Stream 2B T= 23 °C. Stream 3 T=40 °C. Stream 2 T=40 °C. Tref = 25 °C ̂ 1,1 = ∫100 𝑐𝑝,𝐻 𝑂(𝑙) 𝑑𝑇 + ∆H ̂ V (100) + ∫140 𝑐𝑝,𝐻 𝑂(𝑔) 𝑑𝑇 (6.2.1.1) H 2 2 25 100 ̂ 1,1 = (75.4 × 10−3 × (100 − 25)) + 40.656 + (33.46 × 10−3 × (140 − 100)) + (1 × 0.688 × 10−5 × H 1 1 2 (1402 − 1002 )) + ( × 0.7604 × 10−8 × (1403 − 1003 )) + ( × −3.593 × 10−12 × (1404 − 1004 )) = 3 4 47.687 𝑘𝐽/𝑚𝑜𝑙 50 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Equations 6.2.2.2 to 6.2.2.10 are all used in the same way that equation 6.2.2.1 has been used. ̂ 1,2B = ∫23 𝑐𝑝,𝐻 𝑂(𝑙) 𝑑𝑇 = −0.151 𝑘𝐽/𝑚𝑜𝑙 H 2 25 (6.2.1.2) ̂ 5,2 = −∆H ̂ V (100) + ∫40 𝑐𝑝,𝐻 𝑂(𝑙) 𝑑𝑇 = H 2 25 −39.525 𝑘𝐽/𝑚𝑜𝑙 (6.2.1.7) ̂ 2 = ∫140 𝑐𝑝,𝐶𝑂 (𝑔) 𝑑𝑇 = 4.528 𝑘𝐽/𝑚𝑜𝑙 (6.2.1.3) H 2 25 ̂ 6,3 + H ̂ 6,2 = ∫40 𝑐𝑝,𝐶𝑂 (𝑔) 𝑑𝑇 = 0.562 𝑘𝐽/𝑚𝑜𝑙 H 2 25 (6.2.1.8) ̂ 3 = ∫140 𝑐𝑝,𝑂 (𝑔) 𝑑𝑇 = 3.451 𝑘𝐽/𝑚𝑜𝑙 (6.2.1.4) H 2 25 ̂4 = H 140 ∫25 𝑐𝑝,𝑁2 (𝑔) 𝑑𝑇 = 3.361 𝑘𝐽/𝑚𝑜𝑙 (6.2.1.5) 40 ∫25 𝑐𝑝,𝐻2 𝑂(𝑙) 𝑑𝑇 ̂ 5,3 = H (6.2.1.6) ̂ 7 = ∫40 𝑐𝑝,𝑂 (𝑔) 𝑑𝑇 = 0.442 𝑘𝐽/𝑚𝑜𝑙 (6.2.1.9) H 2 25 ̂ 8 = ∫40 𝑐𝑝,𝑁 (𝑔) 𝑑𝑇 = 0.436 𝑘𝐽/𝑚𝑜𝑙 (6.2.1.10) H 2 25 = 1.131 𝑘𝐽/𝑚𝑜𝑙 Table 6.2.2.2: Shows the enthalpy substance H2O CO2 O2 N2 ̂ 𝐼𝑛 nIn,flue ̇ gas × H (kJ/s) 30296.1582 1481.49665 333.291875 9363.47177 total Q1= 36663.8701 n𝐼𝑛,𝑐𝑜𝑜𝑙𝑖𝑛𝑔 ̇ 𝑤𝑎𝑡𝑒𝑟 ,× ̂ H𝐼𝑛 (kJ/s) -4810.5483 ̂ 𝑂𝑢𝑡 n𝑂𝑢𝑡, ̇ ×H (kJ/s) 36753.83 183.791823 42.6926947 1215.18886 ̂ 𝑂𝑢𝑡 n𝑂𝑢𝑡,𝑐𝑜𝑛𝑑𝑒𝑛𝑠𝑒𝑑 ̇ ×H (kJ/s) -1531.6333 total Q2= 36663.8701 Since the cooling water inlet flow rate was unknown, then the total molar flow rate of the water exiting the unit was also unknown. However, using an energy balance where a goal seek method was possible to use. The goal seek method was used to estimate the molar flow rate of the inlet cooling water stream. Since n1 is known to be 635.318 mol/s, then n2B can be estimated while also knowing that n1+n2B=n2+n3. ̂ 1,2B ) was multiplied by the unknown inlet molar flowrate of the cooling water, while H ̂ 1,1 was (H multiplied by the known molar flowrate of water in the flue gas (635.318 mol/s). Furthermore, the ̂ 5,2 . Finally, (the total molar flowrate of the water that condenses (38.751 mol/s) was multiplied by H outlet molar flowrate of water – the molar flowrate of the water that condensed) was multiplied by ̂ 5,3 . The total inlet kJ/s (Q1) is then subtracted from the total outlet kJ/s (Q2). The goal seek was H utilised to guess the value of the inlet molar flowrate of cooling water until Q1 was equal to Q2. 6.2.2 Packed Bed Absorption Column (A-101) Lead author: Bryn Barker 51 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Stream table for unit A-101 Stream No. Total flow (kg/s) Temperature (°C) Pressure (bar) Phase 3A 5 4 12 106.23 265.37 93.28 252.42 40 62.92 40 40 1.2 V 1.1 L 1.2 L 1.1 V *Note yellow values are calculate in energy balance Assumptions: streams 3 and 4 are in thermal equilibrium (Ravi, 2023) The energy balance for the absorption column was to determine the temperature of stream 5 (the rich MEA stream), all other streams were pre-defined and had a temperature of 40°C, this was because 40°C was found to be the optimum temperature for CO2 absorption by MEA. The equation for the energy balance is shown in equation 6.2.3.1 below. ∑ Hstream 3A + ∑ Hstream 12 = ∑ Hstream 4 + ∑ Hstream 5 + ∆HRXN eq 6.2.2.1 eq 6.1.3.4 Because the reaction taking place in the absorption column is the absorption of CO2, then the ∆𝐻𝑅𝑋𝑁 term is the enthalpy of absorbtion. The heat of absorption for 30wt% MEA at 40°C with a loading of 0.5mol CO2/ mol MEA was found to be -71.30 Kj/mol CO2 (Kim et al, 2014). This value was multiplied by the number of moles of CO2 absorbed, 294.32 moles, as calculated in 6.1.3, this gave a value of -20992 KJ/s. This exothermic reaction is responsible for the rise in temperature of stream 5. It therefore follows that using a simple 𝑖𝑛 = 𝑜𝑢𝑡 + ∆𝐻𝑅𝑋𝑁 energy balance could be used to determine the enthalpy of stream 5 and therefore its temperature. For all streams the enthalpy calculations used a reference temperature of 25°C. The enthalpy balance calculations are shown in tables 6.2.2.1 to 6.2.2.4 that are located in appendix c. Equation 6.2.2.2 shown below shows the formula used to calculate the enthalpy of stream 5. As in the initial energy balance the individual component enthalpies of the stream were summed to determine the total enthalpy of the stream. This process was repeated for streams 3A, 4 and 12. ∑ 𝐻𝑠𝑡𝑟𝑒𝑎𝑚 3𝐴 + ∑ 𝐻𝑠𝑡𝑟𝑒𝑎𝑚 12 − ∑ 𝐻𝑠𝑡𝑟𝑒𝑎𝑚 4 − ∆𝐻𝑅𝑋𝑁 = ∑ 𝐻𝑠𝑡𝑟𝑒𝑎𝑚 5 eq 6.2.2.2 eq 6.1.3.4 From equation 6.2.2.2 the enthalpy of the rich MEA stream was determined to be 34868 KJ/s. Using goal seek on excel the outlet temperature was determined, this value was determined to be 62.92°C. This was a 23°C temperature increase. 52 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.2.3 - E-101: Lead author: Bryn Contributing author(s): Ahmed Aldhalei Stream table for unit E-101 Stream No. Total flow (kg/s) Temperature (°C) Pressure (bar) Phase 5A 5B 11A 11B 265.37 265.37 252.20 252.20 62.92 102 2.3 1.8 L L 122 2 L 82.46 1.5 L *Note yellow values are those calculated by energy balance Assumptions Because more rigorous design of the heat exchanger is not required, the heat exchanger is assumed to be 100% efficient. The shell and tube heat exchanger exchanges heat between the rich and lean MEA streams, streams 5 and 11. The allocation of fluids to shell side and tube side depends on multiple parameters including fouling, corrosiveness of the fluids, what state the fluids are in and the pressure of the fluids. Because it is cheaper to build thicker tube walls than shell walls. it is advisable to allocate the higher-pressure stream to the shell side. (ENERQUIP, 2018).Because only the pressure differs between the 2 process streams the rich MEA stream (stream 5) was set as the shell side fluid. The temperature of the rich MEA stream was calculated in the energy balance for the packed bed absorber and the desired temperature of the rich stream entering the stripper was 102°C, as such the temperature of the tube side was fully defined. The temperature of the lean stream (stream 11) exiting the stripper was 122°C. Consequently the energy balance calculated the tube side outlet temperature. The enthalpy balance is shown in equation 6.2.4.1 below. 53 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari ∆𝐻𝑠𝑡𝑟𝑒𝑎𝑚 5 = ∆𝐻𝑠𝑡𝑟𝑒𝑎𝑚 11 eq 6.2.3.1 eq 6.1.3.4 The Rich stream enthalpy change was found to be 36115KJ this calculation for this was shown in tables 6.2.4.1 to 6.2.4.2 in appendix c. Using the inlet temperature of the lean stream of 122°C the goal seek function in excel was used to determine the outlet of the of the heat exchanger, this temperature was determined to be 82.46°C. The equation used to calculate this is shown below. 36115 𝑛𝑠𝑡𝑟𝑒𝑎𝑚 11 × 𝐶𝑝̇ × (122 − 𝑇) eq 6.2.3.2 eq 6.1.3.4 6.2.4 Cooler (C-102) Lead author: Bryn Barker Stream table for unit C-102 Stream No. Total flow (kg/s) Temperature (°C) Pressure (bar) Phase 11B 11B 252.20 252.20 82.46 40 1.5 1.2 L L cw cw 542.75 542.75 23 40 3 2.7 L L *Note highlighted values are calculated from the energy balance Assumptions: the cooler is 100% efficient There is no absorption in the cooling water stream For the cooler energy balance the temperatures of all 4 streams were set, the cooling water had a supply temperature of 23°C and a maximum allowable return temperature of 40°C. For the lean MEA stream (11B) the temperature inlet was 82.46°C as determined by the energy balance in section 6.2.4. The outlet of the Lean MEA stream was 40°C, this was because the absorption column required the inlet streams to be at 40°C. Then energy balance carried out determined the mass flowrate of cooling water required to cool the Lean MEA stream. the enthalpy balance equation is shown below in equations 6.2.5.1 & 6.2.5.2. ∆𝐻𝑠𝑡𝑟𝑒𝑎𝑚 11𝐵 = ∆𝐻𝑐𝑜𝑜𝑙𝑖𝑛𝑔 𝑤𝑎𝑡𝑒𝑟 eq 6.2.4.2 eq 6.1.3.4 54 eq 6.2.4.1 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari ∆𝐻𝑠𝑡𝑟𝑒𝑎𝑚 11 = 𝑛𝑐𝑜𝑜𝑙𝑖𝑛𝑔 𝑤𝑎𝑡𝑒𝑟 𝐶𝑃 ∆𝑇𝑐𝑜𝑜𝑙𝑖𝑛𝑔 𝑤𝑎𝑡𝑒𝑟 eq 6.2.5.2 eq 6.1.3.4 From these calculations shown in table 6.2.4.2 in appendix C, the cooling duty waseq calculated 6.2.4.2 to be 38.65MW and the cooling water mass flowrate was determined to be 542.75 Kg/s. 6.2.5 S-101 Energy balance Lead author: Faisal Kamal Contributing author(s): Faisal Kamal • The assumptions made are the same as those of the mass balance calculations, see chapter 6.7 the stream numbers used and the UBD is the same as well. • The enthalpies highlighted in the table below were calculated using the equations in this section, for the sake of space, these enthalpies are included here. Table 6.2.5.1 Stream table for unit S-101 9 10 11 5B 6 7 8 Stream No. 272.82 20.55 252.27 265.47 28.52 25.32 13.19 Total flow (kg/s) 110.5 120 120 102 102 40 40 Temperature (°C) 2 2 1.9 1.2 1.8 1.7 1.8 Pressure (bar) 11257 43246. 86742. 71994.47 Streams calculated 3581.418 912.72 177.52 2 3 9 Enthalpies (Kw) L V L L V L V Phase The main goal of the energy balance calculation is to determine the duties of the reboiler and condenser in the system, alongside that, the temperature of stream 10 will also be calculated. The energy balance will follow simple enthalpy differential calculations to attain the duties of the units mentioned above, the enthalpies will be calculated in the following manner: 𝐻̇ = 𝑛̇ 𝐶𝑝 ∆𝑇 Equation (6.2.5.1) Notably, the molar flow rates are used in the equation, the value of the flowrates in table (6.1.4.7) in the mass balance of the stripper, where used alongside the molar weights in Chapter 3 to convert the values of the table. Moving forward, the difference between the enthalpy sum of the inlet streams and the enthalpy sum of the outlet streams is equal to the duty required in a unit, and therefore: 𝐷𝑢𝑡𝑦 𝑖𝑛 𝑎 𝑢𝑛𝑖𝑡 = ∆𝐻̇ = 𝛴𝐻̇𝑖𝑛 − 𝛴𝐻̇𝑜𝑢𝑡 Equation (6.2.5.2) 6.2.5.1 Condenser Duty With the understanding of the method used for the calculations, streams 6,7 and 8 are the first enthalpies to be calculated, and the duty of the condenser is the first to be attained. the specific heat capacity at the appropriate temperature must be calculated for all 7 streams through. The specific heat coefficients alongside the calculation alongside the rest of the 𝐶𝑝 calculations will ne be provided in appendix C. These values were multiplied by the molar flowrate according to equation (6.2.5.1) to attain the enthalpies. The enthalpy values where then converted to Kj/s. This provides all the values need to calculate the duty required for the condenser where: 𝐷𝑢𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑐𝑜𝑛𝑑𝑒𝑛𝑠𝑜𝑟 = ∆𝐻̇ = 𝐻̇2 − (𝐻̇3 + 𝐻̇4 ) 55 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari And so, 𝐷𝑢𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑐𝑜𝑛𝑑𝑒𝑛𝑠𝑜𝑟 = 3581.41 − (912.72 + 177.52) = 2491.17 𝐾𝑗 𝑜𝑟 2.491 𝑀𝑤 𝑠 The calculation above shows the duty of the condenser is 2.49 Mw, from this calculation, the amount of cooling water required in the condenser can also be calculated. The specific heat of water was calculated, see appendix c, the value attained was 1.28 Kj/mol. This value was divided by the duty requirement to provide the required cooling water flow rate: 𝐾𝑗 𝑠 = 1942.39 𝑚𝑜𝑙 𝑜𝑟 34.98 𝐾𝑔 𝐶𝑜𝑜𝑙𝑖𝑛𝑔 𝑤𝑎𝑡𝑒𝑟 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑: 𝐾𝑗 𝑠 𝑠 1.28 𝑚𝑜𝑙 2491.17 6.2.5.2 Energy balance around the column At this stage of the calculations, all enthalpies can be attained using equation (6.2.5.1) with the exception of stream 9. This is because the temperature of stream 9 is unknown, therefore, the calculating the specific heat capacity, and as an extension, the enthalpy of stream 9 is not possible in accordance with the method used up to this point. Therefore, to calculate the enthalpy of stream 9, a general energy balance is done around the stripper column itself. In this case, the inlets to the column would be streams 5B, 7 and 10. The outlets would be streams 6 and 9. 𝐻̇5𝐵 + 𝐻̇7 + 𝐻̇10 = 𝐻̇6 + 𝐻̇9 Equation (6.2.5.3) And therefore, in order to calculate stream 9, the enthalpies of the rest of the required streams must be calculated first. The enthalpies of streams 6 and 7 were calculated in the condenser duty section, and thus, only streams 5B and 10 must be calculated. And so, the enthalpies of both streams were calculated. Notably, in the case of stream 10, the boil up stream, the value shown does not consider the heats of reaction and vaporisation occurring in the reboiler. These values must be added to the enthalpy of stream 9 before proceeding, in order to calculate these values, the heat of reaction is obtained from the absorber calculations, as it is known that the absorption of CO2 into aqueous amines is an exothermic reaction and therefore in order to strip CO2 from amines the required amount of energy is the same as the amount of energy released during the absorption process (Srisang, 2017).And therefore, if the heat of absorption is -71.3 Kj/mol of CO2, then the heat of desorption is 71.3 Kj/mol of CO2. Furthermore, the heat of water vaporisation was obtained from literature to be 40.65 Kj/mol (Ayala and Rogstad, 2020). Having acquired the heat of reaction and the heat of vaporisation of water, table (6.2.5.7) from the stripper mass balance can be used to obtain the calculated amounts of water vaporisation and CO 2 desorption in the reboiler’s boil up stream, stream 10. The table shows 7.96 Kg/s of CO2 desorbed and 12.12 Kg/s of water vaporised. 56 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari With the amounts of water vaporisation and CO2 reaction known, they are converted to mol/s to calculate the enthalpy of reaction and vaporisation, Thus, the enthalpies of reaction and water vaporisation can be calculated as follows: 𝑚𝑜𝑙 𝐾𝑗 ∗ 71.3 = 12906.7 𝑠 𝑠 𝑚𝑜𝑙 𝐾𝑗 = 673.20 ∗ 40.65 = 27365.89 𝑠 𝑠 𝐻̇𝑟𝑒𝑏 𝑟𝑒𝑐 = 181.02 𝐻̇𝑟𝑒𝑏 𝑣𝑎𝑝 As follows, the enthalpy of stream 9 can now be calculated in addition to the heat of reaction and vaporisation. This yields a value of ∆𝐻̇6 = 43246.3 Kj/s. Finally, the enthalpy of stream 9 can now be calculated in accordance with equation (6.2.5.3): 𝐻̇5 = 71994.47 + 912.72 + 43246.3 − 3581.4 = 112572 𝐾𝑗/𝑠 Notably this enthalpy contains the heat of reaction and water vaporisation in the column, so in removing these values, the calculation of the temperature of the stream is possible. Similarly, to stream 10, the enthalpies of stream 9’s heat of reaction and condensation are calculated using the flowrates in the stream attained from the final mass balance table. These calculations result in: 𝑚𝑜𝑙 𝐾𝑗 ∗ 71.3 = 30116.3 𝑠 𝑠 𝑚𝑜𝑙 𝐾𝑗 = −18.21 ∗ 40.65 = −740.3 𝑠 𝑠 𝐻̇𝑐𝑜𝑙𝑢𝑚𝑛 𝑟𝑒𝑐 = 422.38 𝐻̇𝑐𝑜𝑙𝑢𝑚𝑛 𝑐𝑜𝑛𝑑 And from this, the enthalpy of stream 9 required to calculate the temperature is 83196. Kj/s. Through goal seeking in excel in the table below, for the sum of the enthalpies to be equal to 83196 Kj/s by changing the set temperature, a set temperature of 110.6 degrees is attained. CP values and calculations. STREAM 9 Tref = 25, Tset =110.68 . Phase L Comp cp in j/mol H5 j/s H5 in Kj/s MEA 14557.54311 17250197.88 17250.19788 H2O 6449.930359 64327972.14 64327.97214 CO2 3402.891765 1617886.581 1617.886581 Total 83196.0566 6.2.5.3 Reboiler Duty In order to calculate the reboiler duty, the enthalpies of streams 9,10 and 7 must be known. Therefore, the enthalpy of stream 11 was calculated in accordance with equations (6.2.6.1-2) to be 𝐻̇11 = 86742.89 Kj/s. With this value, the duty of reboiler would be equal to: 𝑅𝑒𝑏𝑜𝑖𝑙𝑒𝑟 𝐷𝑢𝑡𝑦 = 𝐻̇11 + 𝐻̇10 − 𝐻̇9 And so, the reboiler duty is calculated to be 46793.16 Kj/s or 46.79 Mw. Furthermore, the attained reboiler duty can be converted to MJ/Kg by dividing reboiler duty to amount of CO2 generated. This 57 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari yields a value of 3.61 MJ/Kg. This value is corporate by several similar studies from literature under the process conditions similar to those used in this energy balance (Biermann et al., 2022. Mathisen et al., 2013) 6.2.6 Compressor train (COM-1 to COM-4, C-102 to C-105, D-101&D-102) Lead author: Abdelrahman Abouelela Contributing author(s): N/A Compressor Energy Balance: Assumptions: - All Water and MEA is removed by the dryer. - There is no pressure drop from the coolers. After the water and MEA is removed from the stream via the adsorption dryer, the pure CO2 stream enters the compressor train at 40℃ and 1.7 bar and must enter the storage pipeline at 25℃ and 50 bar. The first compressor must compress the stream from 1.7 bar to 14 bar, however, this creates a temperature increase due to the relationship between pressure and temperature. The outlet temperature of the stream must be calculated to know the cooling duty of the interstage cooler. The work done by the compressor must also be calculated. This was done through the use of the following method: Firstly, the polytropic efficiency, EP, of the compressor must be found from figure 6.2.7.1. However, to find the polytropic efficiency from the chart, the compression ratio must first be found. This is calculated through the use of: 𝑃2 𝑃1 14 = 1.7 = 8.24 (3 sf) (equation 6.2.6.1) The polytropic efficiency can then be extrapolated from the chart and it is found to be 86% (0.86) for the first compressor. After that, an initial value for the polytropic temperature exponent, m, is to be calculated through the use of: 𝑚= (𝛾−1) 𝛾𝐸𝑝 (1.29−1) = 1.29∗0.86 = 0.26 (3 sf) (equation 6.2.6.2) Then, the outlet temperature, T2, can be calculated through the use of: 𝑃 𝑚 𝑇2 = 𝑇1 ∗ (𝑃2 ) 1 14 0.26 = 313 ∗ (1.7) = 543K → 270℃ (3 sf) (equation 6.2.6.3) Since the outlet temperature has been calculated, the mean temperature and pressure are calculated through the use of: 𝑇𝑚𝑒𝑎𝑛 = 𝑇1 +𝑇2 2 (equation 6.2.6.4) 58 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 𝑃1 +𝑃2 2 𝑃𝑚𝑒𝑎𝑛 = For the first compressor, 𝑇𝑚𝑒𝑎𝑛 = (equation 6.2.6.5) 318 + 543 2 = 431 K and 𝑃𝑚𝑒𝑎𝑛 = 1.7+14 2 = 7.9 bar The mean temperature and pressure are then used to find the reduced temperature, Tr, and reduced pressure, Pr. 𝑇𝑟 = 𝑇𝑚𝑒𝑎𝑛 𝑇𝑐 = 431 304 = 1.42 (3 sf) (equation 6.2.6.6) 𝑃𝑟 = 𝑃𝑚𝑒𝑎𝑛 𝑃𝑐 = 73.8 = 0.11 (3 sf) (equation 6.2.6.7) 7.9 The reduced temperature and pressure values are then used to find the compressibility factor, Z, and compressibility functions X and Y, from their respective charts. From figures 6.2.7.2, 6.2.7.3 and 6.2.7.4 respectively, Z = 1, X = 0.06, Y = 1.02, for the first compressor. After that, a revised value for the polytropic temperature exponent, m, is to be calculated through the use of: 𝑚= 𝑍𝑅 1 ( 𝐶𝑃 𝐸𝑃 + 𝑋) = 1 ∗ 8.314 1 ( + 37.35 0.86 0.06) = 0.27 (3 sf) (equation 6.2.6.8) Then, the polytropic exponent, n, is to be calculated through the use of: 1 1 𝑛 = 𝛾−𝑚(1+𝑋) = 1.29−0.27(1+0.06) = 1.37 (3 sf) (equation 6.2.6.9) Using the values obtained, the work done by the first compressor can be calculated through the use of: 𝑛−1 𝑊=𝑍 𝑅𝑇1 𝑛 𝑃 𝑛 [( 2 ) 𝑀 𝑛−1 𝑃1 1.37−1 − 1] = 1 8.314 ∗ 318 1.37 1.8 1.37 [( ) 44 1.37−1 1.7 − 1] = 348 j/mol (3 sf) (equation 6.2.6.10) The actual work done is calculated through the formula: 𝑊𝑜𝑟𝑘 𝐷𝑜𝑛𝑒 348 𝐴𝑐𝑡𝑢𝑎𝑙 𝑊𝑜𝑟𝑘 𝐷𝑜𝑛𝑒 (𝑊𝐷0 ) = 𝑃𝑜𝑙𝑦𝑡𝑟𝑜𝑝𝑖𝑐 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 = 0.86 = 405 j/mol (3 sf) (equation 6.2.6.11) To convert the work done from j/mol to kW, the flow rate of CO2, in mol/s, must be converted to kg/s. This is done through the use of: 𝜐= 𝜐0 ∗ 𝑀𝑟 1000 = 294.42 ∗ 44 1000 = 13 kg/s 59 (equation 6.2.6.12) Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari The flowrate in kg/s must then be multiplied by the work done in j/mol and divided by 1000 to obtain the work done on a kW basis: 𝑊𝐷 = 𝜐 ∗ 𝑊𝐷0 1000 = 13 ∗ 403 1000 = 119 kW (3 sf) (equation 6.2.6.13) This process is repeated for the next three compressors, with the calculated outlet temperature and pressure conditions of the CO2 stream from the cooler being the inlet conditions for the next compressor. Cooler EB: To find the outlet temperature of the stream after it has exited the cooler requires equating and rearranging the following equation for work done by the cooler: 𝑄 = 𝑚̇𝐶𝑃 (𝑇𝑖𝑛 − 𝑇𝑜𝑢𝑡 ) (equation 6.2.6.14) 𝑚̇𝐶𝑂2 𝐶𝑃 𝐶𝑂2 (𝑇𝑖𝑛 − 𝑇𝑜𝑢𝑡 )𝐶𝑂2 = 𝑚̇𝑤𝑎𝑡𝑒𝑟 𝐶𝑃 𝑤𝑎𝑡𝑒𝑟 (𝑇𝑖𝑛 − 𝑇𝑜𝑢𝑡 )𝑤𝑎𝑡𝑒𝑟 𝑇𝑜𝑢𝑡 𝐶𝑂2 = [ 𝑚̇𝑤𝑎𝑡𝑒𝑟 𝐶𝑃 𝑤𝑎𝑡𝑒𝑟 (𝑇𝑖𝑛 −𝑇𝑜𝑢𝑡 )𝑤𝑎𝑡𝑒𝑟 𝑚̇𝐶𝑂2 𝐶𝑃 𝐶𝑂2 (equation 6.2.6.15) ] − 𝑇𝑖𝑛 𝐶𝑂2(equation 6.2.6.16) For the first cooler, an initial value for the flow rate of water was chosen (15 kg/s). Furthermore, the cooling water has a summer temperature of 23℃ and a maximum return temperature of 40℃. This gives an outlet stream temperature of: 𝑇𝑜𝑢𝑡 𝐶𝑂2 = [ 15 ∗ 4180 ∗ (313−296) ]− 12.95 ∗ 849 544 = 447K → 174℃ To find the work done by the cooler, equation 6.2.6.14 is utilised: 𝑄 = 15 ∗ 4180 ∗ (313 − 296) = 1066 kW Since the equations are equated, the work done on the water is equal to the work done on the CO2 stream, meaning the work done of 1066 kW is doubled to 2132 kW, giving the total work done by the first compressor. This process is repeated for the next two coolers, with the calculated outlet temperature and pressure conditions of the CO2 stream from the compressor being the inlet conditions for the next cooler. However, for the final cooler, the unknown variable switches from the outlet temperature of the CO2 60 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari stream to the flow rate of water required so equation 6.2.7.15 is rearranged to calculate the unknown flow rate required: 𝑚̇𝑤𝑎𝑡𝑒𝑟 = 𝑚̇𝐶𝑂2 𝐶𝑃 𝐶𝑂2 (𝑇𝑖𝑛 −𝑇𝑜𝑢𝑡 )𝐶𝑂2 𝐶𝑃 𝑤𝑎𝑡𝑒𝑟 (𝑇𝑖𝑛 −𝑇𝑜𝑢𝑡 )𝑤𝑎𝑡𝑒𝑟 (equation 6.2.6.16) For the final cooler, the flow rate of water is: 𝑚̇𝑤𝑎𝑡𝑒𝑟 = 12.95 ∗ 849 ∗ (403−298) 4180 ∗ (313−296) = 16.3 kg/s (3 sf) Table 6.2.6.1: Stream table for compressors in compressor train Unit COM-101 COM-102 COM-103 In/Out In Out In Out In Out In Out Stream No. 13 14 15 16 17 18 19 20 CO2 (kg/s) 12.95 12.95 12.95 12.95 12.95 12.95 12.95 12.95 Temperature (°C) 40 270 173 253 155 199 102 130 Pressure (bar) 1.7 14 14 26 26 38 38 50 Work (kW) 119 flow Done Phase V 91 L L COM-104 74 L L 73 L L L Table 6.2.6.2: Stream table for coolers in compressor train Unit C-102 In/Out In Out In Out In Out In Out Stream No. 14 15 16 17 18 19 20 21 CO2 (kg/s) flow 12.95 12.95 12.95 12.95 12.95 12.95 12.95 12.95 H2O (kg/s) flow 15 15 15 15 15 15 16.4 16.4 Temperature (°C) 270 173 253 155 199 102 130 25 Pressure (bar) 14 14 26 26 38 38 50 50 Work (kW) 2132 Phase Done L C-103 C-104 2132 L L C-105 2132 L L 61 2316 L L L Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari *Highlighted values are calculated 6.3 Process Integration 6.3.1 Hot and cold utility requirements Table 6.3.1.1: hot and cold plant utility requirements Description C-101 C-102 C-103 C-104 C-105 REB Hot Utility (KW) Cold utility (KW) 38500 1065.9 1065.9 1065.9 1158.0 46793 6.3.2 Selection of streams for PI 4 streams were chosen for the pinch point analysis, these being the rich MEA stream, the lean MEA stream the reboiler stream and the condenser stream. The streams between compressors were not selected as the cost of building pipelines to the start of the process would likely be not feasible. For similar reasons the flue gas outlet stream from the power plant was not selected for the pinch analysis as it would be impractical to pump it far downstream of the absorber only to have to pump it back to the absorber. Of the 4 streams selected, the lean MEA and condenser were both hot streams, while the rich MEA and reboiler streams were both cool streams. 6.3.3 Minimum approach temperature A minimum approach temperature of 20°C was selected for the pinch point analysis. Typical minium approach temperatures range from 5°C to 30°C. In general a lower minimum approach temperature decreases the requirement of additional utilities however this comes at the cost of the present utilities needing to be larger in size, hence increasing their capital cost (Towler and Sinnott, 2013). A minimum approach temperature of 20°C would balance these requirements and be a suitable trade off. 62 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.3.4 Application of PI and design of HEN The following diagrams are provided by: (Xu, 2006) Figure 6.3.4.1: input data for pinch point analysis Figure 6.3.4.2: cascade table produced Figure 6.3.4.3: pinch point diagram From the pinch point calculations carried out on the provided spreadsheet using the input data shown in figure 6.3.4.1, the pinch point was determined to be 83°C. From the pinch point diagram shown in figure 6.3.4.3 it was shown that the only streams capable of exchanging heat were the rich and lean 63 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari MEA streams. Because the Reboiler stream doesn’t come close to the other streams in temperature additional hot utility is required for it to function. This was provided by the kettle reboiler in the current plant design. Because the lean MEA stream can only transfer energy to the rich stream above the pinch as shown by figure 6.3.4.3, the lean stream will require additional cooling utility. This was already incorporated into the energy balance via the addition of a cooler after the rich-lean heat exchanger. Since cooling of the condensate stream typically takes place in the condenser it would require considerable redesign to incorporate the condensate stream into a heat exchanger network. The pinch point analysis indicates that the current design set out in the report is optimised and no further redesign is required. 64 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.4 Final Process Flow Diagr Equiptment code Equiptment Name Design Temp. (°C) Design Pressure (bar) DCC-101 Direct contact cooler 140 A-101 Packed bed absorber 40 1.2 1.2 E-101 Shell and tube heat exchanger 63 Rich 122 Lean 2.3 Rich 2.0 Lean C-102 Cooler S-101 Stripping unit COM 1 to 4 Compressor train 82.5 102 1.5 1.8 270, 253, 199, 130 14, 26 ,38, 50 Utility Cooling water Equiptment C-102 23, 3 Tin (°C) pin (bar) Tout (°C) 40, 2.7 Pout (bar) Flow (kg/s) 542.75 Stream NO. Component flow (kg/s) MEA CO2 H2O N2 O2 Total flow (kg/s) Enthalpy (kW) Temperature (°C) Pressure (bar) Phase 1 2B 2 3 3A 5 12 4 4A WWin WWout 5A 5B 11A 11B 0 14.39 11.44 78.011 3.091 0 0 574.203 0 0 0 0.089 574.90 0 0 0 14.305 10.74 78.011 3.091 0 14.39 10.74 78.01 3.09 0 25.91 167.62 0 0 0 12.95 167.62 0 0 0 1.44 10.74 78.01 3.09 0.00016 1.44 10.74 78.01 3.09 0 0 1.35 0 0 0 0 1.35 0 0 71.84 25.91 167.62 0 0 71.84 25.91 167.62 0 0 71.84 12.95 167.40 0 0 71.84 12.95 167.40 0 0 106.93 574.99 574.99 106.23 106.23 265.37 252.42 93.37 93.28 1.35 1.36 265.37 265.37 252.20 252.20 41474.4 2 -4810.55 34548.6 2 2114.12 1747 34869 13706 1578 1578 1578 1578 71994. 47 71994.4 7 86742 38649 140 23 40 40 40 63 40 40 40 23 23 63 102 122 82.5 1.2 V 3 L 1.1 L 2.9 V 1.2 V 1.1 L 1.2 L 1.1 V 40 1.1 3 L 1.9 L 2.3 L 1.8 L 2 L 1.5 L 65 Stream NO. Component flow (kg/s) MEA CO2 H2O N2 O2 Total flow (kg/s) Enthalpy (kW) Temperature (°C) Pressure (bar) Phase Cooling water C-103 Cooling water C-104 Cooling water C-105 Cooling water C-106 23, 3 23, 3 23, 3 23, 3 P-101 63,1.1 P-102 122, 1.7 40, 2.7 40, 2.7 40, 2.7 40, 2.7 63, 2.3 2.0 15 15 15 16.30 265.37 265.18 Pumping power 6 7 8 9 10 11 13 14 15 16 17 18 19 20 21 0.17 26.56 11.80 0 0 11.58 13.60 0.15 0 0 0.016 12.96 0.22 0 0 72.28 20.92 178.62 0.46 7.97 12.12 71.82 12.96 167.50 0 0 0 0 12.96 0 0 0 0 12.96 0 0 0 0 12.96 0 0 0 0 12.96 0 0 0 0 12.96 0 0 0 0 12.96 0 0 0 0 12.96 0 0 0 0 12.96 0 0 0 0 12.96 0 0 0 38.52 25.33 13.19 272.83 20.55 252.28 12.96 12.96 12.66 12.96 12.96 12.96 12.96 12.96 12.96 3581.4 1 912.72 177.5 112572 43246.3 1 86742 177.5 119 2132 91 2132 74 2132 73 2316 102.78 40 40 110.6 120 120 40 270 173 252 155 199 102 120 25 1.8 V 1.8 L 1.8 V 2 L 2 V 2 L 1.7 V 14 L 14 L 26 L 26 L 38 L 38 L 50 L 50 L Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6.5 Auxiliary unit power requirement calculations Pump calculations: P-102 increased the pressure of the lean MEA stream, (stream 5) from 1.1 bar at the exit of the absorption column to 2.3 bar at the exit of the pump. This pressure increase was decided based on the upstream stripper pressure requirement of 1.8 bar. The equations used to calculate pump power are shown below: 𝑞𝜌𝑔ℎ (3 × 106 ) Equation 6.5.1 Pump power calculation (EngineeringToolbox, 2003) The head, denoted h in equation 6.4.1 would typically be calculated more rigorously in a pump design however typical head ranges are given in literature, for centrifugal pumps the typical range of head is between 10-50m. (Coulson & Richardson, 2005). The upper limit was selected as to give an upper estimate to the required pump power. the average fluid density was determined using the sum of the individual component densities. The densities of fluids used are shown in table 6.5.1 below. Table 6.5.1: fluid densities, (EngineeringToolbox, 2003) (cameochemicals, 1999) Component ρ at 63°C ρ at 120°C MEA 979.29 1181 H2O 981.61 943.08 CO2 598 990.36 determine the volume flowrate in 𝑚3 ℎ𝑟 to the formulas below were used. The stream 5A volume flowrates are displayed in table 6.5.2: 𝑀̇ 𝑚3 × 3600 = 𝑣𝑜𝑙𝑢𝑚𝑒𝑡𝑟𝑖𝑐 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒 𝜌 ℎ𝑟 71.84 𝑚3 × 3600 = 264.11 979.29 ℎ𝑟 Equation 6.5.2 Equation 6.5.3 Table 6.5.2: volume flowrates of stream 5A component mol FR mass 𝐾𝑔 𝑠 MEA H2O CO2 1177.682 71.84 9312.413 167.62 588.8411 25.91 FR/ Vol FR / 𝑚3 ℎ𝑟 264.11 614.75 155.97 The sum of the individual volume flowrates shown in table 6.5.2 was found to be 1034.83 𝑚3 ℎ𝑟 using equation 6.4.1 where 𝜌 was the the average density of the fluid the pump power can be found with 66 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 𝐾𝑔 the following equation. for stream 5A this density was calculated to be 852.94𝑚3. The calculation for this is shown in equation 6.4.4 below 1034.83 × 852.94 × 9.81 × 50 = 120.26𝐾𝑤 (3.6 × 106 ) Equation 6.5.4 Using the same calculations, the power needed for pump 102 was calculated at its specific density and flowrate (Appendix C). The power of P-102 was found to be 123.2002 Kw, the pump raises the pressure of the stream to 2 bar in order to take the pressure drop of the heat exchanger and the cooler into account and deliver the stream at 1.2 bar, the optimum pressure in the absorber. 7. CONCLUSIONS A post-combustion carbon capture method has been decided as the most viable process for this project along with MEA as the amine solution due to its increased absorption capabilities stemming from its high reactivity. Raw materials used for construction should be bought from Chinese suppliers to benefit economically from cheaper prices. Likewise, coal bed methane should also be supplied from China for the aforementioned reason. On the other hand, MEA should be bought from a local supplier due to its stable market price and for the flexibility from the supplier to FAABS. Some of the chemicals that are being used in operation can be very dangerous if handled improperly, leading to the implementation of exposure controls, proper storage and disposal guidelines, such as in the case of wastewater where it is treated before disposal to prevent any negative environmental impacts. The units in the operational process have all achieved their desired benchmarks, such as the absorber column absorbing over 90% of the CO2 available from the flue gas and the stripper producing a CO2 stream with a purity over 95 wt%. Once the stream has been compressed and liquified, it was sent to the underground pipeline to be stored. Calculations illustrate that ≈13 kg/s of CO2 will be stored when the plant is fully operational. FAABS opted to store the CO2 rather than sell it to gain Australian Carbon Credit Units (ACCUs). As this project is projected to capture and store 370,000 tons of CO2 per year, worth more than $4.5 million, this makes the project economically viable while simultaneously positively impacting the environment by reducing CO2 emissions. 67 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 8. References • • • • • • • • • Abanades, J.C., Arias, B., Lyngfelt, A., Mattisson, T., Wiley, D.E., Li, H., Ho, M.T., Mangano, E., Brandani, S., 2015, Emerging CO2 capture systems, International Journal of Greenhouse Gas Control 40, 126–166. Adams, D. n.d. Flue gas treatment for CO capture. 2010. Usea.org. [Online]. [Accessed 24 November 2023]. Available from: https://usea.org/sites/default/files/062010_Flue%20gas%20treatment%20for%20co2%20ca pture_ccc169.pdf. Afkhamipour, M. 2017. Review on the mass transfer performance of CO2 absorption by amine-based solvents in low- and high-pressure absorption packed columns. RSC advances. 7(29), pp.17857– 17872. Available from: https://pubs.rsc.org/en/content/articlelanding/2017/RA/C7RA01352C Akram, M., Milkowski, K., Gibbins, J. et al. (1 more author) (2020) Comparative energy and environmental performance of 40% and 30% monoethanolamine at PACT pilot plant. International Journal of Greenhouse Gas Control. Vol 95, pp 102946. Available from: https://eprints.whiterose.ac.uk/155639/1/Comparative%20Performance%20of%2040%25%20and%2 030%25%20MEA.pdf Amundsen, T., Øi, L., & Eimer, D. 2009. Density and Viscosity of Monoethanolamine + Water + Carbon Dioxide from (25 to 80) °C. Journal of Chemical and Engineering Data - J CHEM ENG DATA. Available from: https://www.researchgate.net/publication/244465871_Density_and_Viscosity_of_Monoethanolamin e_Water_Carbon_Dioxide_from_25_to_80_C Aneesh, A.M. and Sam, A.A. 2023. A mini-review on cryogenic carbon capture technology by desublimation: theoretical and modeling aspects. Frontiers in energy research. Available from: https://www.frontiersin.org/articles/10.3389/fenrg.2023.1167099/full Anon 2023. NIST. NIST. [Online]. Available from: https://www.nist.gov/. Anon n.d. Dalby climate: Weather Dalby & temperature by month. Climate-data.org. [Online]. [Accessed 26 November 2023b]. Available from: https://en.climatedata.org/oceania/australia/queensland/dalby-6713/. Aronu, U.E., Ghondal, S., Hessen, E.T., Haug-Warberg, T., Hartono, A., Hoff, K.A. and Svendsen, H.F. 2011. Equilibrium in the HO-MEA-CO system: new data and modeling. Ieaghg.org. [Online]. [Accessed 12 December 2023]. Available from: https://www.ieaghg.org/docs/General_Docs/PCCC1/Abstracts_Final/pccc1Abstract00040.pdf. • Australian Government. N.D. Exposure Standard Documentation. Available from: https://hcis.safeworkaustralia.gov.au/ExposureStandards/Document?exposureStandardID=109. • Ayala, H. and Rogstad, K. 2020. General Biology [Online]. Available from: http://books.google.ie/books?id=f8RowgEACAAJ&dq=General+Biology+(Boundless)&hl=&cd=1 &source=gbs_api. Basile, A., Gugliuzza, A., Iulianelli, A. and Morrone, P. 2011. Membrane technology for carbon dioxide (CO2) capture in power plants In: Angelo Basile and S. P. Nunes, eds. Advanced Membrane Science and Technology for Sustainable Energy and Environmental Applications. Elsevier, pp.113– 159. Available from: https://www.sciencedirect.com/topics/engineering/pre-combustioncapture#:~:text=Pre%2Dcombustion%20capture%20reveals%20to,of%20the%20more%20complex %20installation Baxter, L., Stitt, K., Russell, C., Harmon, D., 2018, Cryogenic carbon capture development, Presentation at: 2018 NETL CO2 Capture Technology Project Review Meeting, August 2018. • • 68 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari • • • • • • • • • • • • Biermann, M., Normann, F., Johnsson, F., Hoballah, R. and Onarheim, K. 2022. Capture of CO2 from Steam Reformer Flue Gases Using Monoethanolamine: Pilot Plant Validation and Process Design for Partial Capture. Industrial & Engineering Chemistry Research. 61(38), pp.14305–14323. Braakhuis, L. and Knuutila, H.K. 2023. Predicting solvent degradation in absorption–based CO2 capture from industrial flue gases. Chemical engineering science. 279(118940), p.118940. https://www.sciencedirect.com/science/article/pii/S0009250923004967 Bravo, J., Drapanauskaitė, D., Sarunac, N., Romero, C. E., Jesikiewicz, T., & Baltrušaitis, J. (2021, January 1). Optimization of energy requirements for CO2 post-combustion capture process through advanced thermal integration. Fuel. https://doi.org/10.1016/j.fuel.2020.118940 Bravo, J., Drapanauskaite, D., Sarunac, N., Romero, C., Jesikiewicz, T. and Baltrusaitis, J. 2021. Optimization of energy requirements for CO2 post-combustion capture process through advanced thermal integration. Fuel (London, England). 283(118940), p.118940. Available from: https://www.sciencedirect.com/science/article/pii/S0016236120319360 Bravo, J., Drapanauskaite, D., Sarunac, N., Romero, C., Jesikiewicz, T., & Baltrusaitis, J. (2021, January). Optimization of energy requirements for CO2 post-combustion capture process through advanced thermal integration. Fuel, 283, 118940. https://doi.org/10.1016/j.fuel.2020.118940 Brighthub Engineering, 2022. The efficiency of power plants of different types. [online]. [accessed on 8th December 2023]. Available from: The Efficiency of Power Plants of Different Types (brighthubengineering.com) Britannica.com. 2023. [Online]. [Accessed 10 December 2023l]. Available from: https://www.britannica.com/science/carbonic-acid. Broadbent, H. 2023. Per Capita Coal Power Emissions, 2022 | Ember. Ember. [Online]. Available from: Https://ember-climate.org/insights/research/per-capita-coal-power-emissions-2022/. CameoChemicals. 1999. MEA. [online]. [date accessed 11/12/2023]. Available from: https://cameochemicals.noaa.gov/chris/MEA.pdf Carapellucci, R., Giordano, L. and Vaccarelli, M. 2015. CO2post-combustion capture in coal-fired power plants integrated with solar systems. Journal of physics. Conference series. Available: https://iopscience.iop.org/article/10.1088/17426596/655/1/012010?gclid=CjwKCAjw1t2pBhAFEiwA_-A-NOncf883YInLWVuREDf3YkRtH79MR7VWgzPOG5uRoKX--o0b8tf1xoChCwQAvD_BwE Carbon capture. Ukccsrc.ac.uk. 2022. [Online]. [Accessed 19 November 2023]. Available from: https://ukccsrc.ac.uk/ccs-explained/carbon-capture/. Castro, M., Gomez-Díaz, ´ D.M., Navaza, J.M., Rumbo, A., 2021. Carbon dioxide capture by chemical solvents based on amino acids: absorption and regeneration. Chem. Eng. Technol. 44, 248– 257. https://doi.org/10.1002/ceat.201900562. • Co, U. and Csiro, U. 2021. Australia’s National Science Agency. Csiro.au. [Online]. [Accessed 20 November 2023]. Available from: https://www.csiro.au/-/media/Services/Futures/21-00285_SERFUT_REPORT_CO2UtilisationRoadmap_WEB_210810.pdf. • CO2: Air Liquide. 2021. CO2 MSDS. Air Liquide Security Filtering. Available from: http://docs.airliquide.com.au/msdsau/AL062.pdf. Coker, A. 2007. Ludwig's Applied Process Design for Chemical and Petrochemical Plants. [online]. 4th edition. Gulf Proffessional Publishing. [accessed 12/12/2023]. Available from: Ludwig's Applied Process Design for Chemical and Petrochemical Plants | ScienceDirect • • Crawley, F., Preston, M. and Tyler, B. 2008. HAZOP : Guide to Best Practice [Online]. IChemE. Available from: 69 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari http://books.google.ie/books?id=dGNJ8FezCXUC&printsec=frontcover&dq=hazop+guide+to+best+ practice&hl=&cd=2&source=gbs_api. 70 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari • • • • • • • • • • • • • • • CSIRO Futures (2019) Growth opportunities for Australian food and agribusiness: Economic analysis and market sizing. Available from: https://www.csiro.au/-/media/DoBusiness/Files/Futures/GrowthOpportunitiesAustralianFoodAgribusiness.pdf Cusco, L. 2007. Hazards from high pressure carbon dioxide releases during carbon dioxide sequestration processes. Icheme.org. [Online]. [Accessed 13 December 2023]. Available from: https://www.icheme.org/media/17864/cusco_connolly_2007_hazards_from_co2.pdf. Demisterpads.com. [Online]. [Accessed 10 December 2023k]. Available from: https://www.demisterpads.com/pdf/demister-pads-brochure.pdf. Department of natural resources & mines. 2017. Queensland’s petroleum and coal seam gas. Gov.au. [Online]. [Accessed 26 November 2023]. Available from: https://www.australiaminerals.gov.au/__data/assets/pdf_file/0003/47622/Queenslands-petroleumand-coal-seam-gas-2017.pdf. Dziejarski, B., Serafin, J., Andersson, K. and Krzyżyńska, R. 2023. CO2 capture materials: a review of current trends and future challenges. Materials Today Sustainability. available from: https://www.sciencedirect.com/science/article/pii/S2589234723001690#:~:text=Generally%2C%20t he%20most%20widely%20used,%2C%20biochar%2C%20and%20hydrochar). ENERQUIP. 2018. tubeside or Shellside: Comparing Fluid Allocation Options for Your Shell and Tube Heat Exchanger. [online]. [acessed 12/12/2023]. Available from: Tubeside or shellside: Comparing fluid allocation options for your shell and tube heat exchanger (enerquip.com) Engineering ToolBox, 2003. Fuels - Higher and Lower Calorific Values. [online]. [accessed on 8th December 2023]. Available from: Fuels - Higher and Lower Calorific Values (engineeringtoolbox.com) Engineering ToolBox, 2003. Gases – Densities. [online]. [accessed on 8th December 2023]. Available from: Gases - Densities (engineeringtoolbox.com) Felder, R, Rousseau, R, Bullard, L. 2018. Elementary Principles of Chemical Processes, 4th Edition. [online]. 4th edition. [accessed 12/12/2023]. available from: BibliU - Reader - Elementary Principles of Chemical Processes Fostås, B., Gangstad, A., Nenseter, B., Pedersen, S., Sjøvoll, M. and Sørensen, A.L. 2011. Effects of NOx in the flue gas degradation of MEA. Energy procedia. 4(C), pp.1566–1573. https://core.ac.uk/download/pdf/82573085.pdf Fytianos, G., Ucar, S., Grimstvedt, A., Hyldbakk, A., Svendsen, H.F. and Knuutila, H.K. 2016. Corrosion and degradation in MEA based post-combustion CO2 capture. International journal of greenhouse gas control. 46, pp.48–56. Available from: https://www.sciencedirect.com/science/article/pii/S1750583615301730 Galindo, P., Schäffer, A., Brechtel, K., Unterberger, S. and Scheffknecht, G. 2012. Experimental research on the performance of CO2-loaded solutions of MEA and DEA at regeneration conditions. Fuel (London, England). 101, pp.2–8. Available from: https://www.sciencedirect.com/science/article/pii/S0016236111000639 García‐Mariaca, A., & Llera‐Sastresa, E. (2022, August 13). Energy and economic analysis feasibility of CO2capture on a natural gas internal combustion engine. Greenhouse Gases: Science and Technology, 13(2), 144–159. https://doi.org/10.1002/ghg.2176 Geoscience Australia, G. 2023. Carbon Capture and Storage (CCS). Geoscience Australia. [Online]. Available from: https://www.ga.gov.au/scientific-topics/energy/resources/carbon-capture-andstorage-ccs. Gibbins, P. by J. and Lucquiaud, M. n.d. BAT review for new-build and retrofit post-combustion carbon dioxide C apture using Amine-based technologies for power and CHP plants fuelled by gas and biomass and for post-combustion capture using Amine-based and hot potassium carbonate 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari technologies on EfW plants as emerging technologies under the IED for the UK. Ukccsrc.ac.uk. [Online]. [Accessed 24 November 2023]. Available from: https://ukccsrc.ac.uk/wpcontent/uploads/2023/01/BAT-for-PCC_v2_EfW_web-1.pdf. • • • • • • • • • • • • • • Gilliland, E. R. (1940, September). Multicomponent Rectification Estimation of the Number of Theoretical Plates as a Function of the Reflux Ratio. Industrial & Engineering Chemistry, 32(9), 1220–1223. https://doi.org/10.1021/ie50369a035 Goto, K., Kazama, S., Furukawa, A., Serizawa, M., Aramaki, S. and Shoji, K. 2013. Effect of CO2 Purity on Energy Requirement of CO2 Capture Processes. Energy Procedia. 37, pp.806–812. Gov.au. 2021.[Online]. [Accessed 11 December 2023m]. Available from: https://www.tmr.qld.gov.au/-/media/aboutus/corpinfo/Publications/regionaltransportplans/RTPSEQ-web.pdf. H2O: LAB CHEM. 2020. H2O MSDS. LABCHEM, INC. Available from: https://www.labchem.com/tools/msds/msds/LC26750.pdf Hikita, H., Asai, S., Ishikawa, H. and Honda, M. 1977. The kinetics of reactions of carbon dioxide with monoethanolamine, diethanolamine and triethanolamine by a rapid mixing method. The chemical engineering journal. Vol 13, pp.7–12. Available from: https://www.sciencedirect.com/science/article/pii/0300946777800026 Holmes. 2018. Carbamate anion formation in CO2 absorption process. [Accessed 23 November 2023]. Available from: https://www.youtube.com/watch?v=wHzIpv00op8. Hwang, G.S., Stowe, H.M., Paek, E. and Manogaran, D. 2015. Reaction mechanisms of aqueous monoethanolamine with carbon dioxide: a combined quantum chemical and molecular dynamics study. Physical chemistry chemical physics: PCCP. 17(2), pp.831–839. Available from: https://pubs.rsc.org/en/content/articlelanding/2015/cp/c4cp04518a IEAGHG document manager. 2019. [Online]. [Accessed 22 November 2023]. Available from: https://documents.ieaghg.org/index.php/s/qTKTVzLPiQVo6Yj. In-Text Citation: (Contact, 2013) Jayarathna, Chameera & Elverhøy, Anita & Ying, Jiru & Eimer, Dag. (2013). Experimentally based evaluation of accuracy of absorption equilibrium measurements. Energy Procedia. 37. 834-843. Available from: https://www.researchgate.net/publication/269836867_Experimentally_based_evaluation_of_accurac y_of_absorption_equilibrium_measurements Jens, K.-J. 2013. Oxidative degradation of aqueous Amine solutions of MEA, AMP, MDEA, pz: A review. Energy procedia. 37, pp.1770–1777. https://www.sciencedirect.com/science/article/pii/S1876610213002968?ref=pdf_download&fr=RR2&rr=82b624ac6c1852de Karimi, M., Shirzad, M., Silva, J.A.C. and Rodrigues, A.E. 2023. Carbon dioxide separation and capture by adsorption: a review. Environmental chemistry letters. 21(4), pp.2041–2084. Available from: Carbon dioxide separation and capture by adsorption: a review | SpringerLink Khan, F.M., Krishnamoorthi, V. and Mahmud, T. 2011. Modelling reactive absorption of CO2 in packed columns for post-combustion carbon capture applications. Chemical engineering research & design: transactions of the Institution of Chemical Engineers. 89(9), pp.1600–1608. Available from: https://www.sciencedirect.com/science/article/pii/S026387621000287X?ref=pdf_download&fr=RR2&rr=8342f7fb3e7c63e7 Khan, U., Ogbaga, C.C., Abiodun, O.-A.O., Adeleke, A.A., Ikubanni, P.P., Okoye, P.U. and Okolie, J.A. 2023. Assessing absorption-based CO2 capture: Research progress and techno-economic assessment overview. Carbon Capture Science & Technology. vol 8, pp. 100125-100150. Available from: https://www.sciencedirect.com/science/article/pii/S2772656823000295?via%3Dihub 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari • • • • • • • • • • • • • • • • • Kim, I, Hoff, K, Mejdell, T. 2014. Heat of Absorbtion of CO2 with aqeous Solutions of MEA: New Experimantial Data. Energry Procedia. Volume 63. pages 1446-1455 King, R. 2020. Hydraulics Vs. Pneumatics - which is better? - rowse. Rowse.co.uk. [Online]. [Accessed 13 December 2023]. Available from: https://www.rowse.co.uk/blog/post/hydraulics-vspneumatics. Krasner, S.W., Mitch, W.A., McCurry, D.L., Hanigan, D. and Westerhoff, P. 2013. Formation, precursors, control, and occurrence of nitrosamines in drinking water: A review. Water research. 47(13), pp.4433–4450. Available from: https://www.sciencedirect.com/science/article/pii/S004313541300393X Leung, D.Y.C., Caramanna, G. and Maroto-Valer, M.M. 2014. An overview of current status of carbon dioxide capture and storage technologies. Renewable and Sustainable Energy Reviews. 39(C), pp.426–443. Available from: An overview of current status of carbon dioxide capture and storage technologies (hw.ac.uk) Levenspiel, O., 1999. Chemical Reaction Engineering, 3rd ed. John Wiley & Sons. Available from: https://www.bau.edu.jo/UserPortal/UserProfile/PostsAttach/57412_6499_1.pdf Liu, F, Qi, Z, Fang, M, Wang, T, Yi, N. 2021. Evaluation on water balance and amine emission in CO2 capture. International Journal of Greenhouse Gas Control. Volume 112. Lv, B., Guo, B., Zhou, Z. and Jing, G. 2015. Mechanisms of CO2 capture into monoethanolamine solution with different CO2 loading during the absorption/desorption processes. Environmental science & technology. 49(17), pp.10728–10735. Available from: https://pubs.acs.org/doi/10.1021/acs.est.5b02356 Mackey, B, Prentice, C, Steffen, W, House, JI, Lindenmayer, D, Keith, H & Berry, S (2013) Untangling the confusion around land carbon science and climate change mitigation policy. Nature Climate Change Magneschi, G., Zhang, T. and Munson, R. 2017. The impact of CO2 capture on water requirements of power plants. Energy procedia. 114, pp.6337–6347. Available from: https://www.sciencedirect.com/science/article/pii/S1876610217319720 Mahmud, T. Personal communication, nk/10/2023. Mahmud, T. Personal communication, nk/11/2023. Mathisen, A., Sørensen, H., Melaaen, M. and Müller, G.-I. 2013. Investigation into Optimal CO2 Concentration for CO2 Capture from Aluminium Production. Energy Procedia. 37, pp.7168–7175. MEA Price in Australia - 2023. Indexbox.io. [Online]. [Accessed 23 November 2023]. Available from: https://www.indexbox.io/search/monoethanolamine-price-australia/. MEA: CHEM supply Australia. 2020. MEA MSDS.CHEM-SUPPLY PTY LTD. Available from: https://shop.chemsupply.com.au/documents/ML0271CHHZ.pdf Mishra, D. 2014. Simulation of carbon dioxide - monoethanolamine - water system using equilibrium approach. Core.ac.uk. [Online]. [Accessed 28 November 2023]. Available from: https://core.ac.uk/download/pdf/53190349.pdf. Mohammad, M., Isaifan, R.J., Weldu, Y.W., Rahman, M.A., Al-Ghamdi, S.G., 2020. Progress on carbon dioxide capture, storage and utilisation. Int. J. Glob. Warming 20. Available form: https://www.researchgate.net/publication/339397675_Progress_on_carbon_dioxide_capture_storage _and_utilisation/link/6307055461e4553b9537de9f/download?_tp=eyJjb250ZXh0Ijp7InBhZ2UiOiJ wdWJsaWNhdGlvbiIsInByZXZpb3VzUGFnZSI6bnVsbH19 Mokhatab, S., Poe, W.A. and Speight, J.G. (eds.). 2006. Phase Separation In: Handbook of Natural Gas Transmission and Processing. Chapter 5, pp.197–246. Available from: https://www.sciencedirect.com/science/article/pii/B9780750677769500105 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari • • • • • • • • • • • • • • • • • • Mond, A. 1973. Dalby 1:250,000 geological series - explanatory notes. Gov.au. [Online]. [Accessed 26 November 2023a]. Available from: https://geoscience.data.qld.gov.au/data/dataset/cr040268/resource/geo-doc1171833-cr040268. Monoethanolamine ingredient & chemical distributor. Redox. 2023 [Online]. [Accessed 24 November 2023]. Available from: https://redox.com/products/monoethanolamine/. Monoethanolamine Price in Australia - 2023. Indexbox.io. [Online]. [Accessed 23 November 2023]. Available from: https://www.indexbox.io/search/monoethanolamine-price-australia/. Mukherjee, R., 1998. Effectively design shell-and-tube heat exchangers. Chemical Engineering Progress, 94(2), pp.21-37. Mundhwa, M, Henni, A. 2007. Molar Heat Capacity of Various Aqueous Alkanolamine Solutions from 303.15 K to 353.15 K. ACS publications. volume 63, issue 2. Pages 491-498 N2: Honeywell. 2017. N2 MSDS. Honeywell Burdick & Johnson. Available from: https://shop.chemsupply.com.au/documents/LC365M.pdf National Nuclear Laboratory. 2023. Hazop 0/1 studies. CAPE 3000. 09/10/2023. School of Chemical & Process engineering, University of Leeds. Nguyen, T, Hilliard, M, Rochelle, T. 2010. Amine volatility in CO2 capture. International Journal of Greenhouse Gas Control. volume 4, issue 5. pages 707-715. NIST Office of Data and Informatics. 2023. Carbon dioxide. [Online] [Accessed 10 December 2023]. Available from: https://webbook.nist.gov/cgi/cbook.cgi?ID=C124389&Mask=10 Novitsky, E.G., Grushevenko, E.A., Borisov, I.L., Anokhina, T.S. and Bazhenov, S.D. 2023. Monoethanolamine (MEA) degradation: Influence on the electrodialysis treatment of MEAabsorbent. Membranes. 13(5), p.491. Available from: https://www.ncbi.nlm.nih.gov/pmc/articles/PMC10224274/#:~:text=The%20authors%20also%20not e%20significant,C%2C%20they%20reach%2090%25. O2: Air Liquide, 2021. O2 MSDS. Air Liquide Security Filtering. Available from: http://docs.airliquide.com.au/msdsau/AL605.pdf. Oko, E., Zacchello, B., Wang, M., & Fethi, A. (2018, April 16). Process analysis and economic evaluation of mixed aqueous ionic liquid and monoethanolamine (MEA) solvent for CO2 capture from a coke oven plant. Greenhouse Gases: Science and Technology, 8(4), 686–700. https://doi.org/10.1002/ghg.1772 Onyebuchi, V.E., Kolios, A., Hanak, D.P., Biliyok, C. and Manovic, V. 2018. A systematic review of key challenges of CO2 transport via pipelines. Renewable and Sustainable Energy Reviews. 81, pp.2563–2583. Oxy-combustion. netl.doe.gov. [Online]. [Accessed 19 November 2023a]. Available from: https://netl.doe.gov/node/7477. Oxyfuel combustion. Linde Engineering. [Online]. [Accessed 19 November 2023]. Available from: https://www.linde-engineering.com/en/process-plants/co2-plants/carbon-capture/oxyfuel/index.html. Parliament H.C., Act, 2600; 2013. Emissions control policies. Available from: https://www.aph.gov.au/About_Parliament/Parliamentary_Departments/Parliamentary_Library/pubs /BriefingBook43p/emissioncontrol. Paul, A.D. 2004. Coal, Fuel and Non-Fuel Uses In: Encyclopedia of Energy. Elsevier, pp.435–444. Available from: https://www.sciencedirect.com/topics/earth-and-planetary-sciences/coalgasification#:~:text=The%20main%20process%20is%20the,4%2C%20depending%20on%20proces s%20conditions Pavri, R & Moore, G. 2013. Gas turbine emissions and control. Www.ge.com. [Online]. [Accessed 24 November 2023]. Available from: https://www.ge.com/content/dam/gepower- 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari new/global/en_US/downloads/gas-new-site/resources/reference/ger-4211-gas-turbine-emissionsand-control.pdf. • • • • • • • • • • Persons, J. 2019. Carbon capture tech update. [Accessed 19 November 2023]. Available from: Available from: https://www.youtube.com/watch?v=Kx00e6qDLn8. Pourahmad, S., Pesteei, S.M., Ravaeei, H. and Khorasani, S. 2021. Experimental study of heat transfer and pressure drop analysis of the air/water two-phase flow in a double tube heat exchanger equipped with dual twisted tape turbulator: Simultaneous usage of active and passive methods. Journal of energy storage. Available from: https://www.sciencedirect.com/science/article/pii/S2352152X2101094X Prasad Mishra. (2014). SIMULATION OF CARBON DIOXIDE - MONOETHANOLAMINE WATER SYSTEM USING EQUILIBRIUM APPROACH. Department Of Chemical Engineering National Institute Of Technology . Retrieved December 10, 2023, from https://core.ac.uk/download/pdf/53190349.pdf Pronobis, M. 2020. Interactions between emission reduction systems In: M. Pronobis, ed. Environmentally Oriented Modernization of Power Boilers. Elsevier, pp.309–315. Available from: Interactions between emission reduction systems - ScienceDirect Purchas, D.B. and Sutherland, K. 2002. Air and Gas Filter Media In: D. B. Purchas and K. Sutherland, eds. Handbook of Filter Media. London. Chapter 5, pp.153–200. Available from: https://www.sciencedirect.com/science/article/pii/B9781856173759500067 Queensland Government. Queensland carbon dioxide geological storage atlas. 2008. GSQ open data portal. Gov.au. [Online]. [Accessed 26 November 2023d]. Available from: https://geoscience.data.qld.gov.au/dataset/ds000035. Rahman, M.M., Taib, M.Y., Ismail, A.R., Yusoff, A.R., Romlay, M.A.M., Pahang, M. and Ibrahim, T.K. 2010. Effects of operation conditions on performance of a gas turbine power plant. Edu.my. [Online]. [Accessed 26 November 2023]. Available from: http://umpir.ump.edu.my/id/eprint/1776/1/EFFECTS_OF_OPERATION_CONDITIONS_ON_PER FORMANCE_OF_A_GAS.pdf. Ravi, M. Personal communication, nk/11/2023. Sakwattanapong, R., Aroonwilas, A. and Veawab, A. 2009. Reaction rate of CO2 in aqueous MEAAMP solution: Experiment and modeling. Energy procedia. Vol 1, pp.217–224. Available from: https://www.sciencedirect.com/science/article/pii/S1876610209000320?ref=cra_js_challenge&fr=R R-1 Sandru, M., Kim, T.-J., Capal, W., Huijbers, M., Hagg, M.-B., 2013, Pilot scale testing of polymeric membranes for CO2 capture from coal fired power plants, Energy Procedia 37, 6473–6480. • Sayre, A., Frankman, D., Baxter, A., Stitt, K., Baxter, L., 2017, Field testing of cryogenic carbon capture, Presentation at Carbon Management Technology Conference, Houston, Texas, 17– 20 July 2017. • Sinnott, R.K. (2005). Coulson & Richardson’s chemical engineering. Vol. 6, Chemical engineering design. 4th ed. Oxford: Elsevier Butterworth-Heinemann. Solubility of gases in water vs. Temperature. Engineeringtoolbox.com. [Online]. [Accessed 25 November 2023d]. Available from: https://www.engineeringtoolbox.com/gases-solubility-waterd_1148.html. • • Srisang, D.W. 2017. Heat Duty Evaluation for Solid Acid Catalyst-Aided CO2 Desorption in AmineBased Post combustion CO2 Capture and Options for Integration of Process with a CoalBased Electricity Generating Power Plant. [Accessed 13 December 2023]. Available from: 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari • • • • • • • • • • • • • • • • https://ourspace.uregina.ca/server/api/core/bitstreams/216916d3-0807-40b0-9cde7cb589915049/content. St John, D.A. Parliament of Australia 2013. The coal seam gas debate. [Accessed 9 December 2023]. Available from: https://www.aph.gov.au/About_Parliament/Parliamentary_Departments/Parliamentary_Library/pubs /BriefingBook44p/GasDebate. Starr, H. 2023. The problem with carbon credits and offsets explained. The Australia Institute. [Online]. [Accessed 20 November 2023]. Available from: https://australiainstitute.org.au/post/carbon-credits-and-offsets-explained/. Supap, T., Idem, R., Tontiwachwuthikul, P. and Saiwan, C. 2009. Kinetics of sulfur dioxide- and oxygen-induced degradation of aqueous monoethanolamine solution during CO2 absorption from power plant flue gas streams. International journal of greenhouse gas control. Vol 3, pp.133–142. Available from: https://www.sciencedirect.com/science/article/pii/S1750583608000625 Texas Commission on Environmental Quality (TCEQ) 2015. FACT SHEET Monoethanolamine [Online]. [Accessed 9 December 2023]. Available from: https://www.tceq.texas.gov/downloads/toxicology/dsd/fact-sheets/monoethanolamine.pdf. The Department of Climate Change and Energy Efficiency (DCCEEW) 2012. COAL SEAM GAS ESTIMATION AND REPORTING OF GREENHOUSE GAS EMISSIONS [Online]. [Accessed 8 December 2023]. Available from: https://www.dcceew.gov.au/sites/default/files/documents/ngacoal-seam-gas-estimating-and-reporting-greenhouse-gas-emissions.pdf. The Engineering ToolBox (2003). Carbon Dioxide - Liquid Properties. [online]. [acessed on 11/12/2023]. https://www.engineeringtoolbox.com/carbon-dioxide-d_1000.html The Engineering ToolBox (2003). Water - Density, Specific Weight and Thermal Expansion Coefficients. [online]. [acessed on 11/12/2023]. Available at: Pump Power Calculator (engineeringtoolbox.com) The Engineering ToolBox. 2003. Pump Power Calculator. [online]. [acessed on 11/12/2023]. available from: Pump Power Calculator (engineeringtoolbox.com) Theo, W.L., Lim, J.S., Hashim, H., et al., 2016. Review of pre-combustion capture and ionic liquid in carbon capture and storage. Appl. Energy 183, 1633-1663. Available from: https://ideas.repec.org/a/eee/appene/v183y2016icp1633-1663.html Tikrit university (2023). كلية الهندس- جامعة تكريتhttps://ceng.tu.edu.iq/ched/images/lectures/chemlec/st4/c1/EQUIPMENT_DESIGN_LECTURE_25%20mass%20transfer%20equipment%203.pdf Towler, Sinnott. 2020. Chemical Engineering Design. [online]. 6th edition. Elsevier. [date acessed 13/12/2023]. Available from: Chemical Engineering Design | ScienceDirect Tuinier, M.J., Hamers, H.P., van Sint Annaland, M., 2011b, Techno-economic evaluation of cryogenic CO2 capture – A comparison with absorption and membrane technology, International Journal of Greenhouse Gas Control 5, 1559–1565. UK EA 2022. Post-combustion carbon dioxide capture: best available techniques (BAT). GOV.UK. [Online]. Available from: https://www.gov.uk/guidance/post-combustion-carbon-dioxide-capturebest-available-techniques-bat. United States Department of Agriculture (USDA) n.d. Carbon Dioxide Health Hazard Information Sheet [Online]. [Accessed 9 December 2023]. Available from: https://www.fsis.usda.gov/sites/default/files/media_file/2020-08/Carbon-Dioxide.pdf. Ustadi, I., Mezher, T., & Abu-Zahra, M. R. (2017, July). Potential for Hybrid-Cooling System for the CO2 Post-Combustion Capture Technology. Energy Procedia, 114, 6348–6357. https://doi.org/10.1016/j.egypro.2017.03.1771 Uyanga, I.J. and Idem, R.O. 2007. Studies of SO 2 - and O 2 -Induced Degradation of Aqueous MEA during CO 2 Capture from power plant flue gas streams. Industrial & engineering chemistry 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari • • • • • • • • • • • • research. Vol 46, pp.2558–2566. Available from: https://www.academia.edu/70558524/Studies_of_SO_2_and_O_2_Induced_Degradation_of_Aqueo us_MEA_during_CO_2_Capture_from_Power_Plant_Flue_Gas_Streams Varbanov, P.S., Su, R., Lam, H.L., Liu, X., Klemeš, J.J., Lang, P., Denes, F. and Hegely, L. 2017. Comparison of different Amine solvents for the absorption of CO2. Chemical engineering transactions. Vega, F., Sanna, A., Navarrete, B., Maroto-Valer, M.M. and Cortés, V.J. 2014. Degradation of amine-based solvents in CO2capture process by chemical absorption: Degradation of amine-based solvents in CO2capture process by chemical absorption. Greenhouse Gases Science and Technology. 4(6), pp.707–733. Available from: https://pure.hw.ac.uk/wves/portalfiles/portal/9277103/Manuscript_revised.pdf Vevelstad, S.J., Eide-Haugmo, I., da Silva, E.F. and Svendsen, H.F. 2011. Degradation of MEA; a theoretical study. Energy procedia. 4, pp.1608–1615. https://www.sciencedirect.com/science/article/pii/S1876610211002281 Wang, N., Wang, D., Krook-Riekkola, A. and Ji, X. 2023. MEA-based CO2 capture: a study focuses on MEA concentrations and process parameters. Frontiers in energy research. 11, p.1230743. available from: https://www.frontiersin.org/articles/10.3389/fenrg.2023.1230743/full#:~:text=3.2.&text=It%20can% 20be%20explained%20that,equipment%20dimension%20and%20higher%20CAPEX. Wang, N., Wang, D., Krook-Riekkola, A. and Ji, X. 2023. MEA-based CO2 capture: a study focuses on MEA concentrations and process parameters. Frontiers in energy research. 11. Available from: https://www.frontiersin.org/articles/10.3389/fenrg.2023.1230743/full Wilday, J, Moonis, M, Wardman, M, Johnson, M. 2009. SAFETY IN CARBON CAPTURE, TRANSPORT AND STORAGE. Buxton: IEA. [date acessed 12/12/2023] available from: Microsoft Word - Report Cover.doc (globalccsinstitute.com) World Nuclear Association 2022. Carbon Dioxide Emissions from Electricity - World Nuclear Association. Available from: https://world-nuclear.org/information-library/energy-and-theenvironment/carbon-dioxide-emissions-from-electricity.aspx. Wu, X., Yu, Y., Qin, Z., & Zhang, Z. 2017. Performance of CO 2 absorption in a diameter-varying spray tower. Chinese Journal of Chemical Engineering. 25. 10.1016/j.cjche.2017.03.013. Available from: https://www.researchgate.net/publication/315918534_Performance_of_CO_2_absorption_in_a_diam eter-varying_spray_tower Xu, Bao. 2006. Pinch Spreadsheet NOV06 FINAL. Leeds University. [online]. [accessed 12/12/2023]. Xue, B., Yu, Y. and Chen, J. 2018. Process simulation and energy consumption analysis for CO2 capture with different solvents In: Exergy for A Better Environment and Improved Sustainability 1. Cham: Springer International Publishing, pp.1413–1434. Available from: https://link.springer.com/chapter/10.1007/978-3-319-62572-0_90 Zhang, W., Chen, J., Luo, X. and Wang, M. 2017. Modelling and process analysis of postcombustion carbon capture with the blend of 2-amino-2-methyl-1-propanol and piperazine. International journal of greenhouse gas control. 63, pp.37–46. Available from: https://eprints.whiterose.ac.uk/118339/1/2017_03_11%20Zhang_Weiyu_XiaoBo_Commented.pdf Zhang, X., Song, Z., Gani, R. and Zhou, T. 2020. Comparative economic analysis of physical, chemical, and hybrid absorption processes for carbon capture. Industrial & engineering chemistry research. 59(5), pp.2005–2012. Available form: https://pubs.acs.org/doi/abs/10.1021/acs.iecr.9b05510#:~:text=It%20is%20found%20that%20for,2% 20content%20(%3E59.3%25). 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari • • • Zhou, S., Wang, S., Sun, C. and Chen, C. 2013. SO2 effect on degradation of MEA and some other amines. Energy procedia. 37, pp.896–904. https://www.sciencedirect.com/science/article/pii/S187661021300194X#:~:text=Higher%20concentr ation%20of%20SO2,catalyst%20of%20SN2reaction Zhou, Y.-L., Zheng, L.-N., Yi-Fan, C.A.O., Huang, L., Shi, H.-C. and Li-feng, C.2017. Amine regeneration tests on MEA, DEA and MMEA with respect to energy efficiency study. Atlantispress.com. [Online]. [Accessed 23 November 2023]. Available from: https://www.atlantispress.com/article/25882700.pdf. Pashchenko, D., Mustafin, R. and Karpilov, I. 2022. Efficiency of chemically recuperated gas turbine fired with methane: Effect of operating parameters. Applied thermal engineering. 212(118578), p.118578. 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 9. Appendices APPENDIX A: PROJECT PLAN Project Planner Select a period to highlight at right. A legend describing the charting follows. Period Highlight: PLAN START PLAN DURATION ACTUAL START ACTUAL DURATION Chapter 2 1 7 1 6 100% Chapter 3 1 7 1 7 100% Chapter 4 7 1 7 1 100% Chapter 5 8 2 9 2 100% Chapter 6 4 4 4 5 100% Formatting + introduction and conclusion 11 1 11 1 100% ACTIVITY PERCENT COMPLETE 1 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan) PERIODS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 APPENDIX B - Raw Materials and Products appendices: Table B.1: potential steel & concrete suppliers Local Suppliers: Blue Scope Steel Limited Sims Limited Bisalloy Steel Limited Equatorial Resources Limited Local Suppliers: Hanson Australia Cement Australia Holcim Australia Brickworks Steel International Suppliers: Park side steel (UK) Nucor corporation (USA) Ezz Steel (Egypt) China Baowu Steel Group (China) Concrete International Suppliers: Foundation Developments (UK) Baker Construction Enterprises Inc. (USA) China National Building Material Group (China) Lafarge Holcim (Switzerland) Appendix B.2 : Potential MEA & coal bed methane suppliers Local Suppliers: MEA International Suppliers: 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Brenntag CSBP Redox Pty Ltd Orica Local Suppliers: Woodside Petroleum Santos Ltd Origin Energy AMPOL Dow Chemical Company (USA) SABIC (Saudi Arabia) BASF (Germany) INEOS (UK) Coal bed methane International Suppliers: Shell (Netherlands) British Petroleum (UK) ExxonMobil (USA) China United coalbed Methane Corp. Ltd. (China) Appendix B.3 –: Market price of MEA in different geographical regions (businessanalytiq, 2023) 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Appendix B.4 : Projections for future global CO2 demand (IEA, 2019) APPENDIX C - Mass and Energy Balance appendices MSDS: O2: Air Liquide, 2021. O2 MSDS. Air Liquide Security Filtering. Available from: http://docs.airliquide.com.au/msdsau/AL605.pdf. N2: Honeywell. 2017. N2 MSDS. Honeywell Burdick & Johnson. Available from: https://shop.chemsupply.com.au/documents/LC365M.pdf MEA: CHEM supply Australia. 2020. MEA MSDS.CHEM-SUPPLY PTY LTD. Available from: https://shop.chemsupply.com.au/documents/ML0271CHHZ.pdf CO2: Air Liquide. 2021. CO2 MSDS. Air Liquide Security Filtering. Available from: http://docs.airliquide.com.au/msdsau/AL062.pdf. H2O: LAB CHEM. 2020. H2O MSDS. LABCHEM, INC. Available from: https://www.labchem.com/tools/msds/msds/LC26750.pdf Exposure limits: Australian Government. N.D. Exposure Standard Documentation. Available from: https://hcis.safeworkaustralia.gov.au/ExposureStandards/Document?exposureStandardID=109. Table 6.2: Table of Cp values used in energy balance, (henni et al 2007), (Coker, 2007), (Felder & Rousseau, 2018) Source ACS publication Felder Ludwig’s Ludwig’s Ludwig’s Ludwig’s Componant MEA (L) CP (J/mol.K) a b 170 H2O (L) H2O (g) CO2 (g) N2 (g) O2 (g) 75.4 33.993 27.437 29.342 29.526 -8.42*10^-3 0.042315 -3.54*10^-3 -8.*10^-3 C d 2.9906*10^-5 1.9555*10^-5 1.0076*10^-5 3.8083*10^-5 -1.7825*10^-8 3.9968*10^-9 -4.312*10^-9 -3.2629*10^-8 Absorbtion column appendices: Table 6.2.2.1: stream 3A Cp enthalpy table Stream (3A) Flue gas from CP (J/mol.K) DCC CO2 (g) 579.7923 H2O (g) 504.6641 O2 (g) 441.46798 N2 (g) 436.17389 Sum of individual componant enthalpies (KJ) H (KJ) 188.4953 301.0661 42.63664 1215.219 1747.417 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Table 6.2.2.2: stream 4 Cp enthalpy table Stream (4) cleaned flue gas to CP (J/mol.K) atmosphere CO2 (g) 579.7923 H2O (g) 504.6641 O2 (g) 441.46798 N2 (g) 436.17389 Sum of individual componant enthalpies (KJ) H (KJ) 18.96697 301.0661 42.63664 1215.219 1577.8889 Table 6.2.2.3: stream 12 Cp enthalpy table Stream (x) L-MEA CP (J/mol.K) MEA (l) 2550 H2O (l) 1131 CO2 (aq) 579.7923 Sum of individual componant enthalpies (KJ) H (KJ) 3003.089 10532.34 170.7028 13706.13 Stream (x) R-MEA CP (J/mol.K) MEA (l) 6446.06 H2O (l) 2859.0172 CO2 (aq) 1109.38197 Sum of individual componant enthalpies (KJ) H (KJ) 7591.4098 26624.348 653.24968 34869 Heat exchanger: Table 6.2.3.1: stream 11 Cp enthalpy table Stream (11A-B) L-MEA MEA (l) H2O (l) CO2 (aq) CP (J/mol.K) H (KJ) 6630 7915.539025 27724.85149 474.59 36115 2904.6 1567.264 Sum of individual componant enthalpies (KJ) Table 6.2.3.2: stream 5 Cp enthalpy table Stream (5A-5B) R-MEA MEA (l) H2O (l) CO2 (aq) CP (J/mol.K) 6630 2940.6 1567.264 Sum of individual componant enthalpies (KJ) H (KJ) 7808.033 27384.08 922.8692 36115 Cooler exchanger: Table 6,.2.4.1: stream 11B Cp enthalpy balance Stream (11B) L-MEA MEA (l) H2O (l) CP (J/mol.K) 7218.2 1271.79 H (KJ) 8500.74532 374.441873 9 Table 6.2.3.4: stream 5 Cp enthalpy table Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari CO2 (aq) 3201.48 Sum of individual componant enthalpies (KJ) 29774.5865 38650 Table 6.2.4.2: stream cw Cp enthalpy balance Stream (x) cool water C-102 H2O (l) CP (J/mol.K) 1281.8 H (KJ) 38650 Stripper energy balance: Comp MEA H2O CO2 Total A Comp MEA H2O CO2 Total A Comp MEA H2O CO2 Total A Comp MEA H2O CO2 Comp MEA H2O CO2 CP values and calculations. STREAM 8 Tref = 25, Tset =40. Phase V C D cp in j/mol H4 j/s 0 0 0 2550 663.6592337 -0.008419 0.000029906 -1.78E-08 5.05E+02 6148.08761 0.042315 -0.000019555 3.9968E-09 579.8197 170710.8221 B 170 33.933 27.437 CP values and calculations. STREAM 7 Tref = 25, Tset =40. Phase L C D cp in j/mol H3 j/s 0 0 0 2550 6331.243302 -0.039953 -0.00021103 5.35E-07 1131.33146 727233.1897 0.042315 -0.000019555 3.9968E-09 579.8196788 179160.26 B 170 92.053 27.437 CP values and calculations. STREAM 6 Tref = 25, Tset =102.78. Phase V C D cp in j/mol H2 j/s 0 0 0 13090 35907.16635 -0.0084186 0.000029906 -1.78E-08 2603.352232 1705183.542 0.042315 -0.000019555 3.9968E-09 3049.861058 1840327.653 B 170 33.933 27.437 CP values and calcuations lean mea B C D cp in j/mol H2 j/s H2 in kj 170 0 0 0 16150 19015363.6 19015.36 92.053 -0.039953 -0.00021103 5.35E-07 7.16E+03 66612143.6 66612.14 27.437 0.042315 -0.000019555 3.9968E-09 3788.424 1115389.7 1115.39 A A B 170 92.053 27.437 C 0 -0.039953 0.042315 Comp MEA H2O CO2 A B 170 33.933 27.437 H4 in Kj/s 0.66365923 6.14808761 170.710822 177.522569 H3 in Kj/s 6.331243302 727.2331897 179.16026 912.724693 H2 in Kj/s 35.90716635 1705.183542 1840.327653 3581.418361 CP values and calcuations boil up C D cp in j/mol H3 in j/s H3 in kj 0 0 0 16150 121841.9966 121.842 -0.0084186 0.000029906 -1.78E-08 3.22E+03 2.17E+06 2165.77 0.042315 -0.000019555 3.9968E-09 3788.423549 685795.8921 685.7959 CP values and calcuations TO REB D cp in j/mol H2 j/mol 0 0 14557.54311 17250197.88 -0.00021103 5.35E-07 6449.930359 64327972.14 -0.000019555 3.9968E-09 3402.891765 1617886.581 Compressor train: Figure 6.2.6.1: Typical efficiencies for reciprocating compressors (Sinnott, 2005) 9 H2 in kj 17250.19788 64327.97214 1617.886581 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Figure 6.2.6.2: Compressibility factors of gases and vapours (Sinnott, 2005) Figure 6.2.6.3: Generalised compressibility function X (Sinnott, 2005) 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Figure 6.2.6.4: Generalised compressibility function Y (Sinnott, 2005) 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Table 6.2.6.3: Known thermophysical properties of CO2 (engineeringtoolbox, 2018): CP (j/mol) 37.35 Specific heat ratio (ɣ) 1.29 Critical Temperature (K) 304 Critical Pressure (bar) 73.8 Table 6.2.6.4: CP values (engineeringtoolbox, 2018): CP of CO2 (j/kg K) 4180 CP of H2O (j/kg K) 849 PUMP: P-103 1.2 bar req'd comp 1.7 bar out of strp MEA H2O CO2 mol FR MW 1177.422 9300.229 294.4205 mass FR KG/s Vol FR m^3/s Vol FR m^3/hr 61 71.82274 0.060815187 218.934673 18 167.4041 0.177507871 639.028335 44 12.9545 0.015294573 55.0604643 tot vol FR m^3/hr 913.023472 Centrifugal selected tot vol FR 857.963 m^3/hr Hysys value ? m^3/hr Pump power123.2002 (Kw) Pump power (MW) 0.1232 APPENDIX D - MINUTES OF MEETINGS WITH SUPERVISOR: Appendix D.1 - Week 1 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 – GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 am on 03/10/2023. 1. Present: Sari Miari, Abdelrahman Abouelela, Ahmad Aldhalei, Bryn Barker, Faisal Kamal 2. Apologies for absence: N/A 3. Absentees: N/A 4. The meeting was chaired, and minutes were taken by Sari Miari 5. Minutes of the previous meeting of the group held on: N/A 6. Matters arising from the previous meeting: Discussed the things we need to research about (post-com, pre-comb, oxyfuel-comb and types of solvents used to absorb CO2) 7. Minutes of items arising from the meeting agenda: Decided who will research about each section 8. Any other business: N/A 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 9. Chairperson for the next meeting: Sari Miari 10. Next meeting to be held at 11:00 am on 10/10/2023 in Prof Tim Cockerill office. Appendix D.2 - Week 2 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 – GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 am on 10/10/2023. 1. Present: Sari Miari, Abdelrahman Abouelela, Ahmad Aldhalei, Bryn Barker, Faisal Kamal 2. Apologies for absence: N/A 3. Absentees: N/A 4. The meeting was chaired, and minutes were taken by Sari Miari 5. Minutes of the previous meeting of the group held on: 03/10/2023 6. Matters arising from the previous meeting: Discussed the gantt chart, and picked the process route which was post-combustion and chose monoethanolamine (MEA) as our solvent for absorption 7. Minutes of items arising from the meeting agenda: Chose who was going to write about each advantage and disadvantage of each solvent and process discussed, also chose who to start the mass balance calculations (which is shown in the gantt chart) 8. Any other business: N/A 9. Chairperson for the next meeting: Sari Miari 10. Next meeting to be held at 11:00 am on 10/10/2023 in Prof Tim Cockerill office. Appendix D.3 - Week 3 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 – GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 am on 17/10/2023. 1. Present: Sari Miari, Abdelrahman Abouelela, Ahmad Aldhalei, Bryn Barker, Faisal Kamal 2. Apologies for absence: N/A 3. Absentees: N/A 4. The meeting was chaired, and minutes were taken by Sari Miari 5. Minutes of the previous meeting of the group held on: 03/10/2023 6. Matters arising from the previous meeting: Discussed the gantt chart, and picked the process route which was post-combustion and also chose monoethanolamine (MEA) as our solvent for absorption 7. Minutes of items arising from the meeting agenda: Chose who was going to write about each advantage and disadvantage of each solvent and process discussed, also chose who to start the mass balance calculations (which is shown in the gantt chart) 8. Any other business: N/A 9. Chairperson for the next meeting: Sari Miari 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 10. Next meeting to be held at 11:00 am on 10/10/2023 in Prof Tim Cockerill office. Appendix D.4 - Week 4 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 - GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 on 24/10 1. Present:- Abdelrahman Abouelela, Sari Miari, Bryn Barker, Faisal Kamal, Ahmed Aldhalei 2. Apologies for absence:- N/A 3. Absentees:- N/A 4. The meeting was chaired and minutes were taken by Abdelrahman Abouelela 5. Minutes of the previous meeting of the group held on 17/10 Chose who was going to write about each advantage and disadvantage of each solvent and process discussed, also chose who to start the mass balance calculations (which is shown in the gantt chart) 6. Matters arising from the previous meeting: - Advantages and disadvantages of solvents to be researched 7. Minutes of items arising from the meeting agenda - Continue with Mass and Energy Balance (everyone involved) - Meet on Wednesday 25/10 to decide the individual equipment design - References to be sorted to Leeds Harvard 8. Any other business N/A 9. Chairperson for the next meeting: Abdelrahman Abouelela 10. Next meeting to be held at 11:00 on 31/10 in SCAPE 3.06 Appendix D.5 - Week 5 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 - GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 on 31/10 1. Present:- Abdelrahman Abouelela, Sari Miari, Bryn Barker, Faisal Kamal 2. Apologies for absence:- Ahmed Aldhalei 3. Absentees:- N/A 4. The meeting was chaired and minutes were taken by Abdelrahman Abouelela 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 5. Minutes of the previous meeting of the group held on 24/10 - Continue with Mass and Energy Balance (everyone involved) - Meet on Wednesday 25/10 to decide the individual equipment design - References to be sorted to Leeds Harvard 6. Matters arising from the previous meeting: - Mass and Energy Balance is the priority for the next three weeks 7. Minutes of items arising from the meeting agenda - Determine flowrate of solvent - Continue to work on mass and energy balance (everyone involved) - Sari works on the direct contact cooler - Research low NOx burners 8. Any other business N/A 9. Chairperson for the next meeting: Ahmed Aldhalei 10. Next meeting to be held at 11:00 on 7/11 in Energy G.1 Appendix D.6 - Week 6 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 - GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 on 7/11 1. Present:- Abdelrahman Abouelela, Bryn Barker, Faisal Kamal, Sari Miari 2. Apologies for absence:- Ahmed Aldhalei 3. Absentees:- N/A 4. The meeting was chaired and minutes were taken by Abdelrahman Abouelela 5. Minutes of the previous meeting of the group held on 31/10 - Determine flowrate of solvent - Continue to work on mass and energy balance (everyone involved) - Sari works on the direct contact cooler - Research low NOx burners 6. Matters arising from the previous meeting: 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari - Mass and Energy balance is the priority for the next two weeks 7. Minutes of items arising from the meeting agenda - Faisal and Bryn work together on absorber and separator M&EB - Abdelrahman starts preliminary work on compressor train M&EB 8. Any other business N/A 9. Chairperson for the next meeting: Ahmed Aldhalei 10. Next meeting to be held at 11:00 on 14/11 in Energy G.13 Appendix D.7 - Week 7 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 - GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 on 14/11 1. Present:- Abdelrahman Abouelela, Bryn Barker, Faisal Kamal, Sari Miari 2. Apologies for absence:- Ahmed Aldhalei 3. Absentees:- N/A 4. The meeting was chaired and minutes were taken by Abdelrahman Abouelela 5. Minutes of the previous meeting of the group held on 7/11 - Faisal and Bryn work together on absorber and separator M&EB - Abdelrahman starts preliminary work on compressor train M&EB 6. Matters arising from the previous meeting: - Mass and Energy balance is the priority for the next week 7. Minutes of items arising from the meeting agenda: - Faisal and Bryn finish absorber and separator M&EB - Abdelrahman finishes mass and energy balance for compressor train 8. Any other business N/A 9. Chairperson for the next meeting: Ahmed Aldhalei 10. Next meeting to be held at 11:00 on 21/11 in Energy G.13 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari Appendix D.8 - Week 8 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 - GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 on 21/11 1. Present:- Abdelrahman Abouelela, Bryn Barker 2. Apologies for absence:- Ahmed Aldhalei, Sari Miari, Faisal Kamal 3. Absentees:- N/A 4. The meeting was chaired and minutes were taken by Abdelrahman Abouelela 5. Minutes of the previous meeting of the group held on 14/10 - Faisal and Bryn finish absorber and separator M&EB - Abdelrahman finishes mass and energy balance for compressor train 6. Matters arising from the previous meeting: - Mass and Energy balance is the priority for the next week 7. Minutes of items arising from the meeting agenda Start write up for mass and energy balance and any uncompleted chapters. 8. Any other business N/A 9. Chairperson for the next meeting: Bryn Barker 10. Next meeting to be held at 11:00 on 28/11 in Energy G.13 Appendix D.9 - Week 9 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 - GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 on 28/11 1. Present:- Abdelrahman Abouelela, Bryn Barker, Faisal Kamal, Sari Miari 2. Apologies for absence:- Ahmed Aldhalei 3. Absentees:- N/A 4. The meeting was chaired and minutes were taken by Abdelrahman Abouelela 5. Minutes of the previous meeting of the group held on 21/11 - Start write up for mass and energy balance and any uncompleted chapters. 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 6. Matters arising from the previous meeting: N/A 7. Minutes of items arising from the meeting agenda - Continue write up of mass and energy balance and uncompleted chapters (chapters 3 & 5). 8. Any other business N/A 9. Chairperson for the next meeting: Bryn Barker 10. Next meeting to be held at 11:00 on 5/12 in Energy G.13 Appendix D.10 - Week 10 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 - GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 on 5/12 1. Present:- Abdelrahman Abouelela, Bryn Barker, Faisal Kamal, Sari Miari 2. Apologies for absence:- Ahmed Aldhalei 3. Absentees:- N/A 4. The meeting was chaired and minutes were taken by Abdelrahman Abouelela 5. Minutes of the previous meeting of the group held on 28/11 - Continue write up of mass and energy balance and uncompleted chapters (chapters 3 & 5) 6. Matters arising from the previous meeting: N/A 7. Minutes of items arising from the meeting agenda - Continue write up of mass and energy balance and chapter 5. 8. Any other business N/A 9. Chairperson for the next meeting: Faisal Kamal 10. Next meeting to be held at 11:00 on 12/12 in Energy G.13 Appendix D.11 - Week 11 meeting minutes: CAPE3000 DESIGN PROJECT, 2023-24 - GROUP CEE2 Minutes of the Semester-1 Group Meeting with Project Supervisor held at 11:00 on 12/12 1. Present:- Abdelrahman Abouelela, Bryn Barker, Sari Miari 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari 2. Apologies for absence:- Ahmed Aldhalei, Faisal Kamal 3. Absentees:- N/A 4. The meeting was chaired and minutes were taken by Abdelrahman Abouelela 5. Minutes of the previous meeting of the group held on 5/12 - Continue write up of mass and energy balance and chapter 5. 6. Matters arising from the previous meeting: N/A 7. Minutes of items arising from the meeting agenda Finish final touches on individual write-ups and collate work to format. 8. Any other business N/A 9. Chairperson for the next meeting: Faisal Kamal 10. Next meeting to be held at N/A on N/A in N/A 9 Group Number: CEE2 Contributing Member(s): Faisal, Abdelrahman, Bryn & Sari B1