Example - Quantities taking off - Jan 2023

advertisement
EXAMPLE
1
2
4.5m
C
3
4
6m
7m
F2
F2
F1
F2
F2
F1
7.6m
v1
F2
B
5.5m
FOOTING PLAN
v2
F2
A
F2
W
L
(Grid line at beam c/c)
Lapse 450mm
Existing GL
Beam 250x460mm
min 2.5m
50mm lean concrete
250mm hardcore
Stump size 250 x 250mm
TYPICAL SECTION OF
FOOTING
D
50mm lean concrete
250mm hardcore
Column G30/Beam G25
F1
F2
WxL (mm)
500x600
550x700
Take off quantities of the following items:a. Clearing & top soil scrapping
b. Excavation for footing
c. Excavation for ground beam
d. Formwork & Concreting
D (mm)
500
1000