THE HYDRAULIC MACHINERY OF OBERVERMUNTWERK II P. Meusburger, L. Werle Abstract: In the course of the development work for the new large scale hydro power plant of Illwerke, some different machinery types and sizes were analysed. Both pumpturbines as well as ternary units were investigated in detail. The final machinery design ended up in two ternary units each consisting of a pump with hydraulic torque converter, a motorgenerator and a separate turbine with a shifting clutch. Apart from the maximum energy storage efficiency this variant also offers the maximum operational flexibility with the shortest switching times. Furthermore the operation mode of controllable pump in hydraulic short circuit secures that the machine sets of the Obervermuntwerk II can cover the full control band from 100% to +100% power and therefore can be used as a full backup for the Kopswerk II units. 1 Introduction The first design layout for the new pumped storage project was carried out in 2006, two years before Kops II started in operation. At that time, the prevailing circumstances of a supposedly limited energy transport system using the existing 110-kV high voltage transmission line, restricted the general layout with a maximum capacity of 160 [MW]. In addition, the opinion prevailed that with the additional capacity of 525 [MW] of Kops II, the volume of the market for balancing power and frequency control could be well covered. Thus a shaft powerhouse with reversible pumpturbines and a maximum capacity of 160 [MW] fulfilled the requirements at that time. In November 2008 Kops II started into full operation with all three machine sets. The flexible concept of providing balancing energy of this power plant for the whole power plant group of Illwerke has been fully confirmed by the experience since start of operation. However, the suspected shift of retention of balancing energy from the former largest pumped storage power plant of Illwerke “HPP Lünersee” to the new Kops II has not occurred. The operation of the power plant Lünersee is largely unaffected by Kops II and an expansion of the preserved balancing energy through the power plant group “Obere Ill – Lünersee” took place. It was found that the further development of renewable energy especially in Germany requires more storage capacity and balancing energy for an efficient integration of wind power and photovoltaics. To meet this demand it was decided to significantly enlarge the design capacity of Obervermuntwerk II to at least 320 [MW]. Therefore the capacity of the transmission line also had to be increased. The new powerhouse will consequently be connected to the switchyard with a new 220-kV underground cable. 2 Machinery Types The Obervermuntwerk II uses the head of 243 – 311 [m] by connecting the two existing reservoirs Silvretta and Vermunt with a new headrace system, a new underground powerhouse and a new tailrace tunnel. In addition, the already existing Obervermuntwerk I will be supplied from the headrace system by a new water conduit. To meet the demands of today’s electricity markets, the utmost operational flexibility for the machinery is required. Beside phase shifting operation, both pump and turbine mode as well as controllable pump mode in hydraulic short circuit or at least in mixed operation was planned. The new power plant is designed for rapid switching times of about 60-70 [s] from turbine to pump mode and vice versa. The regulation time of the turbine guide vane will be around 30 [s]. 2.1 Pumpturbines At the very beginning of the project design the main aim was to increase the storage capacity in the power plant group “Obere Ill – Lünersee”. Because of the lower investment costs for the machinery different variants with pumpturbines were analysed. A selection of the examined hydraulics is given in table 1. Variant no. HPU,opt [m] QPU,opt [m³/s] PPU [MW] nPU [upm] nq,opt,PU [upm] kPU 1 286 92,3 280 272,7 37,67 637,08 2 286 50 151 375 38,13 644,80 3 286 49 147 428,57 43,14 729,51 4 286 45 140 428,57 41,34 699,10 5 286 43 133 500 47,14 797,28 6 286 41 125 500 46,03 778,52 7 286 35 110 500 42,53 719,30 8 286 25 76 500 35,95 607,92 9 286 24 73 600 42,27 714,77 HTU,rated [m] QTU,rated [m³/s] PTU [MW] nTU [upm] nq,rated,TU [upm] kTU 280 123 310 272,7 44,18 739,35 280 65 162 375 44,17 739,09 280 65 163 428,57 50,48 844,67 280 61 152 428,57 48,90 818,27 280 56,5 140 500 54,91 918,77 280 51,8 129 500 52,57 879,72 280 47,5 120 500 50,34 842,42 280 33 83 500 41,96 702,16 280 33 82 600 50,35 842,59 D1 [m] 4,46 3,9 3,481 3,51 3,07 3,04 3,02 2,903 2,482 Table 1: Different pumpturbine layouts Even though with higher speed one can cover the given net head with smaller impeller diameters and thus smaller machinery resulting in remarkable cost savings for the whole powerhouse, the mechanical stress expressed by the k-factor is limiting the maximum power. As the minimum power of the machinery for Obervermuntwerk II was given with 160 [MW] each, the rotational speed was therefore fixed with 428.57 [rpm]. The big disadvantage of all these machines is that the part load behaviour of pumpturbines is very poor. Due to the hydraulic stimulation because of the wrong incident flow at part load, the machines tend to have a strong vibration if the load drops below approx. 40% of nominal load. To operate this machinery at deep part load, additional stabilisation measures by blowing air into the housing of the machines are necessary. An adaption of the hydraulic shape of the impeller, as can be done with the turbines of ternary units, seems to be impossible with respect to the utmost efficiency in pump operation. 2.2 Ternary Units Compared to pumpturbines, ternary units offer some essential advantages, which became crucial during the development work of the Obervermuntwerk II project. Variant no. HPU,opt [m] QPU,opt [m³/s] PPU [MW] nPU [upm] nq,opt,PU [upm] kPU 1 HTU,rated [m] QTU,rated [m³/s] PTU [MW] nTU [upm] nq,rated,TU [upm] kTU D1 [m] 2 286 46 139 375 36,57 618,47 280 58 146 375 41,72 698,16 3,949 3 286 45 136 300 28,94 489,37 2,797 280 59 145 300 33,67 563,32 4,768 4 292 48 148 428,57 42,03 718,28 3,377 278 62,5 160 428,57 49,77 829,76 3,529 5 287,7 47 144 500 34,70 588,53 2,528 296 48 150 428,57 41,6 715,8 270 61 150 500 41,46 681,21 3,02 2,25 290 68,3 180 428,57 50,3 856,4 3,425 2,32 Table 2: Ternary unit designs Table 2 shows some different layouts of the machinery for the ternary units of the Obervermuntwerk II. Apart from the higher best point efficiencies of both pump and turbine, resulting in a noteworthy improvement of the overall plant efficiency, especially the part load behaviour of a ternary unit is much more convenient because the turbine impeller can be designed independently from pump operation for this demand. Furthermore ternary units can react much faster than pumpturbines to variable load araising from the volatility in the electrical grid which is due to the integration of windpower and photovoltaics. As Illwerke particularly supply the German electricity market which is dominated by a rapid growth of wind and solar power as pointed out by H. Schmöller (2014), the tremendous increase of windpower and photovoltaics in Germany over the last years has led to a change of requirements on the machinery of Obervermuntwerk II. Fast reaction times and operational flexibility have become much more valuably compared to the first machinery layouts at the very beginning of the project and thus the surplus of investment costs of ternary units compared to pumpturbines can be compensated. With ternary units operating in hydraulic short circuit one can expand the range of the control band to negative power in pump operation. Fig. 1: Power control band of a ternary set Fig. 2: Power control band of a pumpturbines without part-load stabilisation 3 Power Control Band Fig. 1 shows the possible power control range using ternary units for the Obervermuntwerk II project compared to the power control band of pumpturbines depicted in fig. 2. The yellow marked areas show the operating range where the power of the plant can be regulated with respect to the demand of the electrical grid. It is obvious that the control band of the ternary units which covers almost the whole field of net head with just one single small gap (marked red in fig. 1) below net heads of 250 [m] is much more beneficial than the one of pumpturbines showing a gap around zero power over the whole net head range. Furthermore the area between 50% and -100% power (pump operation of both units) is not controllable using pumpturbines otherwise a third unit would be installed. A possibility to enlarge the power control range of pumpturbines is certainly to use a variable speed drive. Indeed, with lower rotational speeds, the minimum load in turbine operation can be reduced significantly but the possible pump power control range strongly depends on the net head of the power plant and becomes smaller the higher the net head. Therefore a solution with pumpturbines and variable speed drives was rejected for the Obervermuntwerk II project as the power control band would still have had unfavourable large gaps. 4 Shifting Time Another essential precondition for the decision to realise ternary units in the Obervermuntwerk II were the considerably lower shifting times between different operation modes. Fig. 3 shows the presumed shifting times of a pumpturbine following G. Penninger and F. Spitzer (2006). Fig. 3: Shifting time of a pumpturbine In contrast to ternary sets, the controlled pump operation mode is not possible with pumpturbines thus depicted with dotted lines in fig. 3. However, a similar operation can be achieved if the plant comprises of at least two units and if the pump power of one unit is balanced with the turbine operation of the other machine. The balancing of the power is then performed on the electrical section whereas with ternary units it can be done at the mechanical level on the same shaft and therefore with higher efficiency. This is because in this case the power losses of the generator can be omitted twice. Mainly when starting into pump direction, the pumpturbines lose much more time compared to ternary units because they must be started with a depressed water level in the draft tube using a start-up frequency converter. Improvements can certainly be obtained using full size converters but they are not yet widely spread and for the power of the Obervermuntwerk II units they are not actually known. Fig. 4: Shifting time of a ternary unit In contrast to pumpturbines, ternary units offer significantly shorter switching times as shown in fig. 4 because the pump rotates in the same direction as the turbine and they can be started using a hydraulic torque converter. For phase shifting mode one just has to decouple the pump as well as the turbine impeller which can be done much faster and easier than aerating the machine. 5 Conclusion The higher efficiency of the machines and the operational flexibility has led to the decision to realise ternary units for the Obervermuntwerk II. The fast switching time between the different operation modes and the possibility to cover the full control range from -100% until +100% load are the main advantages of these machineries with respect to today’s electricity market requirements and additionally allow for the use of the machines as a full back-up for the Kopswerk II units. To avoid the requirement to empty the draft tube of the turbines in case of pump or phase shifting operation mode, a shifting clutch is installed for the turbine. By declutching the turbine impellers, the tailrace system can be simplified because deaeration chambers can be omitted and the ventilation losses in these operation modes are even reduced, which further increases the efficiency of the powerplant. For a fast start-up of the pumps, hydraulic torque converters will be used. Compared to the friction coupling, which was also examined in detail, the wear-free operation and the well-known system of the hydraulic torque converters with numerous comparable references constituted this decision. Fig. 5: Cross section of the ternary machine set (sample picture from Voith) To improve the behaviour of the machinery in part-load operation which is awaited in a huge amount of time over the year in the Obervermuntwerk II, the volutes of both the pump and the turbine will be embedded in concrete as shown in fig. 5. References [1] [2] H. Schmöller: Pumped storage power plant Obervermuntwerk II – economical background. 18th International Seminar on Hydropower Plants. TU Wien 2014. G. Penninger, F. Spitzer: New challenges for modern pump storage units. 14th International Seminar on Hydropower Plants, ISBN 3-9501937-2-3. TU Wien 2006, p. 465 – 472. Authors Dr. Peter MEUSBURGER Vorarlberger Illwerke AG Engineering Services Maschinenbau Anton-Ammann-Strasse 12, A-6773 Vandans, AUSTRIA Phone: +43-5556-701-86260, FAX: +43-5556-701-17086260 E-mail: peter.meusburger@illwerke.at Dr. Peter Meusburger graduated in Mechanical Engineering from the Technical University of Graz, Austria. He then worked as an Assistant Professor at the Department of Hydraulic Fluid Machinery at the Technical University of Graz where he finished his doctoral studies in mechanical engineering in June 2006 with the degree of a doctor of technical sciences. Since 2008 he has worked as an expert for 3D fluid hydraulics and waterhammer calculations at Vorarlberger Illwerke AG. Dipl. Ing. Lucas WERLE Vorarlberger Illwerke AG Engineering Services Maschinenbau Anton-Ammann-Strasse 12, A-6773 Vandans, AUSTRIA Phone: +43-5556-701-86382, FAX: +43-5556-701-17086382 E-mail: lucas.werle@illwerke.at Lucas Werle graduated in Mechanical Engineering from the Technical University of Graz, Austria. Since 2009 he has worked as project engineer with a focus on FEM and waterhammer calculations at Vorarlberger Illwerke AG.