ID Task Name 1 2 3 8 12 17 24 27 Duration LAUNCH OF 240 days MANCHESTER INTERCONTINENTAL HOTELS Conduct Project 1 day Kicik-Off Meeting Carry out Maintenance 75 days of the Building Create Awareness for the New Hotel Brand Recruit New Staff for Hotel Operation Set Up Each Department in the New Hotel Supply all items needed for the immediate take-off of the Hotel Opening Ceremony Project: MODULE 1 ASSIGNMENT Date: Sun 13/03/22 15 days 20 days 128 days Start Finish Mon 14/03/22 Fri 10/02/23 Mon 14/03/22 Mon 14/03/22 Mon 14/03/22 Fri 24/06/22 Mon 14/03/22 Mon 28/03/22 Mon 27/06/22 Fri 01/04/22 11 October 27/09 13/12 21 March 28/02 16/05 01 September 01/08 17/10 Fri 22/04/22 Wed 21/12/22 32 days Thu 22/12/22 Fri 03/02/23 5 days Mon 06/02/23Fri 10/02/23 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 1 11 February 02/01 20/03