Letter no. 02 March 12, 2024 Global Officium Limited Inc Engineering Department Malera Construction & Supply Mr. Marsden Lee Ramos Owner Dear Sir, We are writing this letter to your good office to follow up the following submittals that supposedly to be submitted last February 19, 2024 Recommendation with computation of 30HP pumps New plan Design including the relocation of equipment based on findings Water analysis result with solution This is also to remind you that items 1 and 2 are required to submit before the Variation process for new proposal of higher HP pumps. And with item 3, we need the solution based on latest result to meet the required passing value of DENR. Additionally, I would like to remind you that the project has already exceeded the timeline stated in the contract. Liquidated damage will be applied based on the number of days that have passed. Very truly yours, Allan Christian Malocon R&D Engineer Noted by: MNavilla / R&D Manager MJMiguel Engineering Manager