DEP SPECIFICATION Copyright Shell Group of Companies. No reproduction or networking permitted without license from Shell. Not for resale LINE PIPE FOR CRITICAL SERVICE (AMENDMENTS/SUPPLEMENTS TO ISO 3183:2012 AND API SPEC 5L 45th EDITION) DEP 31.40.20.37-Gen. February 2017 DESIGN AND ENGINEERING PRACTICE DEM1 © 2017 Shell Group of companies All rights reserved. No part of this document may be reproduced, stored in a retrieval system, published or transmitted, in any form or by any means, without the prior written permission of the copyright owner or Shell Global Solutions International BV. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 2 PREFACE DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global Solutions International B.V. (Shell GSI) and, in some cases, of other Shell Companies. These views are based on the experience acquired during involvement with the design, construction, operation and maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference international, regional, national and industry standards. The objective is to set the standard for good design and engineering practice to be applied by Shell companies in oil and gas production, oil refining, gas handling, gasification, chemical processing, or any other such facility, and thereby to help achieve maximum technical and economic benefit from standardization. The information set forth in these publications is provided to Shell companies for their consideration and decision to implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at each locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the information set forth in DEPs to their own environment and requirements. When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the quality of their work and the attainment of the required design and engineering standards. In particular, for those requirements not specifically covered, the Principal will typically expect them to follow those design and engineering practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal. The right to obtain and to use DEPs is restricted, and is typically granted by Shell GSI (and in some cases by other Shell Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three categories of users of DEPs can be distinguished: 1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by these Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement. 2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part of a Service Agreement or otherwise). 3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2) which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said users comply with the relevant standards. Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI disclaims any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination of DEPs or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell Company. The benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies affiliated to these companies, that may issue DEPs or advise or require the use of DEPs. Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and the DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be returned after use, including any copies which shall only be made by users with the express prior written consent of Shell GSI. The copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe custody and Shell GSI may at any time require information satisfactory to them in order to ascertain how users implement this requirement. All administrative queries should be directed to the DEP Administrator in Shell GSI. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 3 TABLE OF CONTENTS PART I 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 INTRODUCTION ....................................................................................................... 6 SCOPE ....................................................................................................................... 6 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS ......... 6 DEFINITIONS ............................................................................................................. 7 CROSS-REFERENCES ............................................................................................. 7 SUMMARY OF MAIN CHANGES ............................................................................... 8 COMMENTS ON THIS DEP ....................................................................................... 8 DUAL UNITS............................................................................................................... 8 NON NORMATIVE TEXT (COMMENTARY) .............................................................. 9 PART II 1.1 1.2 1.3 1.4 1.5 GENERAL REQUIREMENTS .................................................................................. 10 GENERAL ................................................................................................................. 10 APPLICATION .......................................................................................................... 10 PRINCIPAL'S ACCESS AND ACTIVITIES............................................................... 11 PIPE FOR INDUCTION BENDS ............................................................................... 11 SMALL PIPE ORDER QUANTITIES ........................................................................ 12 PART III AMENDMENTS/SUPPLEMENTS TO ISO 3183:2012 and API SPEC 5L 45 EDITION ................................................................................................................... 13 1 Scope ....................................................................................................................... 13 2 2.3 Conformance ........................................................................................................... 13 Compliance to this International Standard ................................................................ 13 3 Normative references ............................................................................................. 13 4 4.18 4.36 Terms and definitions ............................................................................................ 13 EW pipe .................................................................................................................... 13 Manufacturer ............................................................................................................. 13 5 5.2 Symbols and abbreviated terms ........................................................................... 13 Abbreviated terms ..................................................................................................... 13 6 6.1 6.2 Pipe grade, steel grade and delivery condition ................................................... 14 Pipe grade and steel grade ....................................................................................... 14 Delivery condition...................................................................................................... 14 7 7.1 7.2 Information to be supplied by the purchaser ...................................................... 14 General information .................................................................................................. 14 Additional information ............................................................................................... 14 8 8.1 8.3 8.4 8.6 8.7 8.8 8.9 8.10 8.11 8.12 8.13 Manufacturing ......................................................................................................... 15 Process of manufacture ............................................................................................ 15 Starting materials ...................................................................................................... 15 Tack welds ................................................................................................................ 15 Weld seams in SAW pipe ......................................................................................... 15 Weld seams in double-seam pipe............................................................................. 16 Treatment of weld seams in EW and LW pipes ........................................................ 16 Cold sizing and cold expansion ................................................................................ 16 Coil/plate end welds .................................................................................................. 16 Jointers ..................................................................................................................... 16 Heat treatment .......................................................................................................... 16 Traceability................................................................................................................ 16 th This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 4 9 9.1 9.2 9.3 9.4 9.6 9.8 9.9 9.10 9.11 9.12 9.13 9.14 9.15 Acceptance criteria ................................................................................................. 17 General ..................................................................................................................... 17 Chemical composition ............................................................................................... 17 Tensile properties ..................................................................................................... 19 Hydrostatic test ......................................................................................................... 19 Flattening test ........................................................................................................... 19 CVN impact test for PSL2 pipe ................................................................................. 20 DWT test for PSL2 welded pipe................................................................................ 22 Surface conditions, imperfections and defects ......................................................... 22 Dimensions, mass and tolerances ............................................................................ 22 Finish of pipe ends .................................................................................................... 24 Tolerances for the weld seam ................................................................................... 24 Tolerances for mass ................................................................................................. 25 Weldability of PSL2 pipe ........................................................................................... 25 10 10.1 10.2 Inspection ................................................................................................................ 25 Types of inspection and inspection documents ........................................................ 25 Specific inspection .................................................................................................... 26 11 11.1 11.2 11.3 Marking .................................................................................................................... 33 General ..................................................................................................................... 33 Pipe markings ........................................................................................................... 33 Coupling markings .................................................................................................... 34 12 12.2 Coatings and thread protectors ............................................................................ 34 Thread protectors...................................................................................................... 34 14 Pipe loading............................................................................................................. 34 Annex A (normative) Specification for welded jointers ...................................................... 35 Annex B B.1 B.2 B.3 B.4 B.5 B.6 B.7 B.8 (normative) Manufacturing procedure qualification for PSL2 pipe ................... 36 General ..................................................................................................................... 36 Additional information to be supplied by the purchaser ............................................ 36 Characteristics of the manufacturing procedure specification .................................. 36 Characteristics of the inspection and test plan ......................................................... 37 Manufacturing procedure qualification tests ............................................................. 38 Requalification of manufacturing procedure ............................................................. 40 HFW – Parameter envelope ..................................................................................... 40 Surface of seamless pipe ......................................................................................... 41 Annex C C.2 (normative) Treatment of surface imperfections and defects ............................ 42 Treatment of dressable surface defects ................................................................... 42 Annex D D.1 D.2 (normative) Repair welding procedure ................................................................. 43 General ..................................................................................................................... 43 Repair welding procedure qualification ..................................................................... 43 Annex E (normative) Non-destructive inspection for other than sour service or offshore service ...................................................................................................... 44 Qualification of personnel ......................................................................................... 44 Standard practices for inspection ............................................................................. 44 Methods of inspection ............................................................................................... 44 Radiographic inspection of weld seams ................................................................... 47 Ultrasonic and electromagnetic inspection ............................................................... 47 Residual magnetism ................................................................................................. 54 Laminar imperfections in the pipe body of EW, SAW and COW pipes .................... 54 Laminar imperfections along the strip/plate edges or pipe weld seam of EW, SAW and COW pipes ............................................................................................... 54 Laminar imperfections in the pipe body of SMLS pipes ........................................... 55 Thickness measurements for SMLS pipes ............................................................... 55 E.1 E.2 E.3 E.4 E.5 E.7 E.8 E.9 E.11 E.12 This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 5 Annex F (normative) Requirements for couplings (PSL 1 only) ....................................... 56 Annex G G.1 G.6 (normative) PSL 2 pipe with resistance to ductile fracture propagation .......... 57 General ..................................................................................................................... 57 Guidance for determining CVN absorbed energy values in buried onshore gas pipelines .................................................................................................................... 57 EPRG guidelines – Approach 1 ................................................................................ 57 Battelle simplified equation – Approach 2 ................................................................ 57 Battelle two-curve method – Approach 3 .................................................................. 57 AISI method – Approach 4 ........................................................................................ 57 Full-scale burst testing – Approach 5 ....................................................................... 57 G.7 G.8 G.9 G.10 G.11 Annex H H.2 H.3 H.4 H.7 H.9 (normative) PSL 2 pipe ordered for sour service ................................................ 58 Additional information to be supplied by the purchaser ............................................ 58 Manufacturing ........................................................................................................... 58 Acceptance criteria ................................................................................................... 59 INSPECTION ............................................................................................................ 60 PSL 2 pipe ordered for sour service – Additional requirements to comply with Canadian Standard CSA Z662 ................................................................................. 62 Modifications to (PART III AMENDMENTS/SUPPLEMENTS TO ISO 3183:2012) 3 Normative references ............................................................................................. 62 9.9 DWT test for PSL2 welded pipe................................................................................ 62 H.5 Surface conditions, imperfections and defects ......................................................... 63 H.7 Inspection .................................................................................................................. 63 Annex I (normative) Pipe ordered as “Through the Flowline" (TFL) pipe....................... 65 Annex J J.2 J.3 J.6 J.7 J.8 (normative) PSL 2 pipe ordered for offshore service.......................................... 66 Additional information to be supplied by the purchaser ............................................ 66 Manufacturing ........................................................................................................... 66 Tolerances for diameter, wall thickness, length and straightness ............................ 68 Tolerances for the weld seam ................................................................................... 68 Inspection .................................................................................................................. 68 Annex K (normative) Non-destructive inspection for pipe ordered for sour and/or offshore service ...................................................................................................... 70 General non-destructive inspection requirements and acceptance criteria.............. 70 Non-destructive inspection of SMLS pipe ................................................................. 70 Non-destructive inspection of HFW pipe .................................................................. 71 Non-destructive inspection of SAW pipe .................................................................. 72 K.2 K.3 K.4 K.5 Annex M (normative) Pipe ordered for European onshore natural gas transmission lines .......................................................................................................................... 75 PART IV REFERENCES ......................................................................................................... 76 APPENDICES APPENDIX 1 LINE PIPE SUBJECTED TO HIGH STRAIN .................................................. 79 APPENDIX 2 APPENDIX 3 WELDABILITY OF PSL2 PIPE ....................................................................... 82 LINE PIPE FOR DEEPWATER PROJECTS, INCLUDING STEEL CATENARY RISERS ...................................................................................... 85 APPENDIX 4 PROCEDURE REQUIREMENTS FOR NDT ................................................... 88 APPENDIX 5 LINE PIPE ORDER FORM .............................................................................. 89 This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 6 PART I 1.1 INTRODUCTION SCOPE This DEP specifies requirements and gives recommendations for the manufacture and supply of carbon and low-alloy steel line pipe for use in pipelines in critical service. Guidance on the evaluation of pipeline service criticality and line pipe selection is given in DEP 31.40.00.10-Gen. See (Part II 1.2) for applications of this DEP. This DEP is applicable only to grades L245 up to L555 (X80) as designated in th ISO 3183:2012 and API SPEC 5L 45 Edition. th This DEP is based on ISO 3183 Third Edition 2012 and API SPEC 5L 45 Edition. Part III of this DEP amends, supplements and deletes various clauses of ISO 3183 and API SPEC 5L (PSL2). Part III follows the clause numbering of ISO 3183 and API SPEC 5L (PSL2) for easy reference. th The amendments and supplements in this DEP apply equally to API SPEC 5L, 45 edition (PSL2), which contains the identical section numbers and content, with the exception of minor deviations listed in Annex M, N and O. This DEP contains mandatory requirements to mitigate process safety risks in accordance with Design Engineering Manual (DEM) 1 – Application of Technical Standards. This is a revision of the DEP of the same number dated February 2013; see (1.5) regarding the changes. 1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS Unless otherwise authorised by Shell GSI, the distribution of this DEP is confined to Shell companies and, where necessary, to Contractors and Manufacturers/Suppliers nominated by them. Any authorised access to DEPs does not for that reason constitute an authorisation to any documents, data or information to which the DEPs may refer. This DEP is intended for use in facilities related to oil and gas production, gas handling, oil refining, chemical processing, gasification, distribution and supply/marketing. This DEP may also be applied in other similar facilities. When DEPs are applied, a Management of Change (MOC) process shall be implemented; this is of particular importance when existing facilities are to be modified. If national and/or local regulations exist in which some of the requirements could be more stringent than in this DEP, the Contractor shall determine by careful scrutiny which of the requirements are the more stringent and which combination of requirements will be acceptable with regards to the safety, environmental, economic and legal aspects. In all cases, the Contractor shall inform the Principal of any deviation from the requirements of this DEP which is considered to be necessary in order to comply with national and/or local regulations. The Principal may then negotiate with the Authorities concerned, the objective being to obtain agreement to follow this DEP as closely as possible. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 7 1.3 DEFINITIONS 1.3.1 General definitions The Contractor is the party that carries out all or part of the design, engineering, procurement, construction, commissioning or management of a project or operation of a facility. The Principal may undertake all or part of the duties of the Contractor. The Manufacturer/Supplier is the party that manufactures or supplies equipment and services to perform the duties specified by the Contractor. In ISO 3183:2012 and API th SPEC 5L 45 Edition the term Manufacturer is used. In this DEP, the term Manufacturer/Supplier is considered to be equivalent to Manufacturer. The Principal is the party that initiates the project and ultimately pays for it. The Principal may also include an agent or consultant authorised to act for, and on behalf of, the th Principal. In ISO 3183:2012 and API SPEC 5L 45 Edition the term Purchaser is used. In this DEP, the term Purchaser is considered to be equivalent to Principal. The word shall indicates a requirement. The capitalised term SHALL [PS] indicates a process safety requirement. The word should indicates a recommendation. The word may indicates a permitted option. 1.3.2 1.3.3 1.4 Specific definitions Term Definition Critical Line Pipe Line pipe that meets any of the criteria of (Part II 1.2) Not Very Toxic Refer to Part III of DEP 01.00.01.30-GEN. Non-Critical Line Pipe Line pipe that does not meet any of the criteria of (Part II 1.2) Rich Gas (Need a definition for section 9.8.3) Abbreviations Term Definition MPQ Manufacturing Procedure Qualification CROSS-REFERENCES Where cross-references to other parts of this DEP are made, the referenced section or clause number is shown in brackets ( ). Other documents referenced by this DEP are listed in (Part IV). This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 8 1.5 SUMMARY OF MAIN CHANGES This DEP is a revision of the DEP of the same number dated February 2013. The changes followed a requirements quality review and were not a full technical updated. The following are the main, non-editorial changes. 1.6 Section/Clause Change All Restructured and clarified requirements, enforced use of shall/should/may for normative statements. Part II 1.2 Application List of DEP applications demoted from Shall [PS] to “shall” in line with DEP 31.40.00.18 (8.2.1) and since intent is only to list application of the DEP. Individual Shall [PS] statements stand alone later in the DEP. Part III 2 Conformance Quality Assurance System demoted from Shall [PS] to “shall” which aligns with other DEPs. Part III 10.2.5.3 Magnification requirement for metallographic examination of HFW pipe has been separated from the parent Shall [PS] requirement and stated as a “shall” requirement. COMMENTS ON THIS DEP Comments on this DEP may be submitted to the Administrator using one of the following options: Shell DEPs Online (Users with access to Shell DEPs Online) Enter the Shell DEPs Online system at https://www.shelldeps.com Select a DEP and then go to the details screen for that DEP. Click on the “Give feedback” link, fill in the online form and submit. DEP Feedback System (Users with access to Shell Wide Web) DEP Standard Form (other users) Enter comments directly in the DEP Feedback System which is accessible from the Technical Standards Portal http://sww.shell.com/standards. Select “Submit DEP Feedback”, fill in the online form and submit. Use DEP Standard Form 00.00.05.80-Gen. to record feedback and email the form to the Administrator at standards@shell.com. Feedback that has been registered in the DEP Feedback System by using one of the above options will be reviewed by the DEP Custodian for potential improvements to the DEP. 1.7 DUAL UNITS This DEP contains both the International System (SI) units, as well as the corresponding US Customary (USC) units, which are given following the SI units in brackets. When agreed by the Principal, the indicated USC values/units may be used. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 9 1.8 NON NORMATIVE TEXT (COMMENTARY) Text shown in italic style in this DEP indicates text that is non-normative and is provided as explanation or background information only. Non-normative text is normally indented slightly to the right of the relevant DEP clause. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 10 PART II GENERAL REQUIREMENTS 1.1 GENERAL Part III of this DEP is written as amendments and supplements to ISO 3183:2012 and th API SPEC 5L 45 edition. Wherever reference is made to ISO 3183:2012 and/or th API SPEC 5L 45 edition, it shall be understood to mean ISO 3183:2012 and/or th API SPEC 5L 45 edition as amended/supplemented by this DEP. For ease of reference, the clause numbering of ISO 3183:2012 and th API SPEC 5L 45 edition have been used throughout Part III of this DEP. th Clauses in ISO 3183:2012 and API SPEC 5L 45 edition which are not mentioned in this DEP shall remain valid as written. Tables and figures in this DEP not replacing the corresponding item in ISO 3183:2012 and th API SPEC 5L 45 edition are numbered related to the DEP section they are contained in (e.g., Figure 10.2.5.3). 1.2 APPLICATION 1. Carbon steel and low alloy line pipe shall be ordered using this DEP for any of the following applications: a. all offshore pipelines; b. all pipelines designed for sour service; c. all pipelines subject to high strain above normal elastic design limits (more than 0.5%) in installation or service; d. all line pipe ordered with resistance to ductile fracture propagation; e. all line pipe with a maximum design pressure greater than 40 barg (580 psig); f. all pipelines that have been designed with a design factor higher than 0.5; g. all pipelines designed for the transportation of category D or category E fluids, as defined per ISO 13623 Section 5, Table 1; h. all pipelines of a diameter greater than NB 10 inch (273 mm), unless in only Category A service; i. all pipelines forming a part of a main transportation infrastructure; j. the minimum pipeline design temperature is less than 0 °C (32 °F). 2. Line pipe not meeting any of the requirements listed in (Part II 1.2, item 1) may be ordered in accordance with ISO 3183 or API SPEC 5L PSL2 without amendment. 3. Line pipe for Category A fluids (e.g., water) with a maximum design pressure of 20 Barg (2900 psig) and a minimum design temperature greater than 0 °C (32 °F) and a NB of 20 inch (508 mm) or less may be ordered in accordance with ISO 3183:2012 or API SPEC 5L 45th edition PSL1. 4. Line pipe for Category A fluids meeting the requirements of (Part II 1.2 item 2) but is above NB 20 inch (508 mm) shall be ordered to PSL2. 5. SAWH line pipe should be used for onshore applications where the outer diameter and wall thickness requirements are within the manufacturing range for SAWH line pipe (above 610 mm (24 in)). Below this size HFW is generally used. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 11 6. SAWH line pipe shall not be used for any of the following applications: a. where OD of the seam welds are at risk of corrosion due to water drop out; SAWH pipe may be considered but requires analysis of the service conditions and potential for corrosion on a helical weld seam. 7. 1.3 b. where the use of reliability-based limit state design principles is required to confirm design or operational integrity; c. in sour service. Prior to order placement, the pipe mill and all sources of coil shall be subject to approval by the Principal. PRINCIPAL'S ACCESS AND ACTIVITIES 1. Principal’s representatives shall be permitted to witness all chemical testing, mechanical testing, and equipment calibration, and to inspect all pipe. 2. Sufficient notice (at least 14 days) shall be given of the time at which the production run is to begin. 3. The Principal’s representatives shall have free entry at all times to all parts of the Manufacturer’s works that will concern the manufacture, testing, inspection, quality control and shipping of the pipe ordered. This includes the steel mill and the pipe mill. 4. The Manufacturer shall make available to the Principal all reasonable facilities to inspect, measure, and test the pipe in all stages of production. For example, this includes ultrasonic equipment for wall thickness confirmation. 1.4 5. The Principal shall have the option to examine all materials rejected for any reason. 6. The Principal’s representative shall be informed of any pipe fractures occurring during hydrostatic testing and of any test specimen that fails to meet the requirements for any reason. 7. All failed materials shall be retained until examined by the Principal’s representative. 8. The Manufacturer shall allow the Principal to inspect each length of pipe after manufacture and testing are completed but prior to loading for shipment. PIPE FOR INDUCTION BENDS 1. This DEP shall apply to mother pipe intended for induction bending. 2. The composition, mechanical properties and dimensions of mother pipe intended for induction bending shall be dictated by the dimensions and delivery condition of the completed bends. 3. Refer to DEP 31.40.20.33-Gen for requirements for completed bends. 4. The composition, mechanical properties and dimensions of the mother pipe shall be by agreement between the Manufacturer and the Principal. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 12 1.5 SMALL PIPE ORDER QUANTITIES Where small quantities of pipe are required (less than a normal pipe mill order, e.g., for spools induction bend mother pipe, or risers), options to consider are: • place an order with small volume pipe mills. A number of pipe mills, using bending roll or press forming, mainly SAWL can often provide small quantities of pipe; • consider pipe in stock. 1. Small pipe orders and those from stock shall be produced by a steel mill and pipe mill technically approved by the Principal. 2. Pipe from stock shall be evaluated and a gap analysis undertaken from actual production data and the requirements of this DEP. 3. Supplemental tests (e.g., NDT, mechanical, dimensional) deemed necessary from the gap analysis shall be performed to ensure compliance to this DEP. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 13 th PART III AMENDMENTS/SUPPLEMENTS TO ISO 3183:2012 and API SPEC 5L 45 EDITION 1 Scope Replace the first paragraph with the following: 1. Refer to (Part I, Section 1.1). 2 Conformance 2.3 Compliance to this International Standard Replace this clause with the following: 1. 3 The Manufacturer/Supplier shall maintain and operate a quality assurance system in accordance with ISO 9001 or an alternative standard approved by the Principal. Normative references Add the following: 1. See also (Part IV) of this DEP. 4 Terms and definitions 4.18 EW pipe th This section is 4.18 in ISO 3183:2012 and 4.17 in API SPEC 5L 45 edition. Replace this clause with the following: 1. 4.36 Tubular pipe having one longitudinal weld seam produced by high frequency electric current with a frequency equal to or greater than 100 kHz. Manufacturer Add the following: 1. Where pipe manufacturing and/or heat treatment are subcontracted, the pipe mill and/or the processor shall also be considered to be the Manufacturer/Supplier. 5 Symbols and abbreviated terms 5.2 Abbreviated terms Add the following: This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 14 6 Pipe grade, steel grade and delivery condition 6.1 Pipe grade and steel grade 6.1.1 Delete this clause. 6.2 Delivery condition 6.2.1 Table 1 Pipe Grades, steel grades and delivery conditions Add the following note: Pipes fabricated from thermomechanical rolled material may not be suitable for hot (induction) bending unless chemistry/strength is increased and/or specific post bend heat treatments are undertaken. 7 Information to be supplied by the purchaser Add the following: 1. 7.1 A standard line pipe order form is attached in (Appendix 5) which shall be used for initial technical enquiries with pipe mills. General information b. Delete PSL1 Add the following: 9. Minimum and maximum design and operating temperature (for determination of CVN, DWT and CTOD test temperature) 10. Intended service and installing method (e.g., reel installed gas or oil or dual phase for determination of need for resistance to ductile fracture propagation, sour service, high strain, and deep water) 7.2 Additional information Add the following: a)10) . Diameter and out-of-roundness for pipes with D/t> 75 Information not applicable to this DEP: a)9) b)3), b)5), b)8), b)14) c)2), c)5), c)7), c)13), c)14), c)18), c)19, c)25), c)31), c)44), c)45), c)53). This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 15 8 Manufacturing 8.1 Process of manufacture Table 2 – Acceptable processes of manufacture and product specification levels Delete, “Double-seam SAWL and Double-seam COWL” Delete Note c. Delete Note d and substitute: SAWH is applicable for 610 mm OD (24 inch) and above when specifically approved by the Principal. Add Note g: HFW pipe with a wall thickness greater than 20.6 mm (0.8 in) shall be subject to approval by the Principal. Add Note h: The welding processes used for COW pipe shall be subject to approval by the Principal. 8.3 Starting materials 8.3.10 Add new clause: 1. The abutting edges of strip or plate to be HFW welded shall be milled or machined. 2. Rotary shearing shall not be considered as machining. 3. Where approved by the Principal, rotary shearing may be used only for pipe of 8 mm (0.315 in) wall thickness or less, with a diameter of pipe of 273 mm (10 in) or less, and with a pipeline design temperature of not less than -10 °C. Add new clause: 8.3.11 Centerline segregation of slabs, plate and coil. 1. 8.4 The procedure for evaluation of centerline segregation, including quality evaluation method and acceptance limits, shall be subject to approval of the Principal. Tack welds 8.4.2 Replace this clause with the following: 1. 8.6 Tack welds shall be: a. made using a continuous single pass; b. melted and coalesced into the final weld seam; and c. removed by machining or treated in accordance with Clause C.2. Weld seams in SAW pipe Add the following: 1. The seam welding of SAWH pipe shall be carried out as a separate process from the forming operation (e.g., a 2 step mill where the welding speed is independent of the forming speed). This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 16 8.7 Weld seams in double-seam pipe Delete this clause. 8.8 Treatment of weld seams in EW and LW pipes 8.8.1 PSL 1 EW Pipe Delete this clause. 8.9 Cold sizing and cold expansion 8.9.2 Replace this clause with the following: 8.10 1. Cold expansion shall be performed by mechanical means only. 2. The sizing ratio for cold-expanded pipe shall not be less than 0.008 or more than 0.015. Coil/plate end welds Replace this clause with the following: 1. 8.11 Pipe containing strip end welds shall not be supplied. Jointers Replace this clause with the following: 1. 8.12 Jointers shall not be supplied. Heat treatment Add the following: 1. 8.13 The Manufacture shall supply the following information concerning the heat treatment facility, subject to approval by the Principal: a. type of furnace (e.g., batch, walking beam); b. method of heating and fuel (if applicable); c. number, position of thermocouples and controlled heating zones; d. calibration frequency of the thermocouples; e. arrangement of pipes with furnace; f. identification and control of individual pipes throughout the heat treatment cycle. Traceability 8.13.1 Delete this clause. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 17 9 Acceptance criteria 9.1 General 9.1.2 Replace this clause with the following: 1. 9.2 Pipe manufactured to a specific grade shall not be substituted for pipe ordered as a lower grade. Chemical composition 9.2.1 Delete this clause. 9.2.2 Replace this clause with the following: 1. Annex J Table J1 shall apply for all pipe grades and for pipe with t ≤ 35 mm (1.38 in) other than for sour service. 2. (Annex H Table H.1) shall apply for pipe with sour service. 3. Review ISO 3183 composition limits in Annex M. 9.2.3 Replace this clause by: 1. The composition limits of pipe with t > 35 mm (1.38 in) shall be by agreement or as stated in the purchase order. Delete this table: Table 4 Chemical composition for PSL 1 pipe with t ≤ 25.0 mm (0.984 in) Replace this table with Annex J Table J1: Table 5 Chemical composition for PSL 2 pipe with t ≤ 25.0 mm (0.984 in) This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 18 Add this clause: 9.2.6 Chemical Composition Tolerances 1. The Manufacturer/Supplier’s target product analysis shall be shown in the Manufacturing Procedure Specification. 2. A single value target of CEiiw or CEpcm shall be stated. 3. The range of elements shall be such that the variation in the single value target CEiiw does not exceed ± 0.03 units or CEpcm does not exceed ± 0.02 units with the additional restrictions of Table 9.2.6.3: Table 9.2.6.3 Element Restrictions The figures of Table 9.2.6.3 represent the total range and not a plus or minus tolerance. 4. There shall be no changes in the chemical composition (within the tolerances listed above) from the approved MPS composition. a. 5. No intentionally added elements shall be increased beyond the limits above or removed. The chemical composition recorded for the pipes used in first-day production testing shall set the reference CE. a. Where any of the elements in Table 9.2.6.3 is not intentionally added, the manufacturer may propose maximum values, subject to approval by the Principal. 6. If any part of any specific order is manufacturered outside this range then additional MPQT, including weldability tests when applicable, shall be performed on three selected pipes from the heat. 7. The chemical analysis and reporting in inspection documents shall include all elements covered by the requirements of Annex J Table J1. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 19 9.3 Tensile properties 9.3.1 Delete this clause. Delete this table. Table 6 Requirements for the results of tensile tests for PSL 1 pipe 9.3.1 Replace this clause with: 1. For PSL 2 pipe, the tensile properties shall be as given in Annex J Table J2. Use Annex J Table J2 in leu of Table 7. Review if J2 should be applied with max tolerances. 9.4 Hydrostatic test 9.4.2 Delete this clause. 9.6 Flattening test Replace this clause with the following: 1. No cracks or breaks shall occur in either weld or parent metal during flattening of the test specimen to 50% of the original OD. 2. The specimen shall be further flattened to 1/3 of original OD without cracks or breaks other than in the weld. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 20 9.8 CVN impact test for PSL2 pipe 9.8.1.1 Consider the DNV criteria for sub sized specimen. 9.8.2 Pipe body tests 9.8.2.1 Replace this clause with the following: 1. The minimum average (of a set of three test pieces) absorbed energy for each pipe body test shall be as given in Table 8, based upon full-size test pieces. 2. The test temperature shall be lower than or equal to that specified in Table 9.8.2.1. Table 9.8.2.1 Test temperature Tmin is the minimum design temperature This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 21 9.8.2.2 Add to this clause: 1. Shear requirements on charpy specimen shall apply to base material only. Replace Table 8 with the following: 1. No individual specimen shall be less than 60% of the specified value. Table 8 9.8.3 CVN absorbed energy requirements for PSL2 pipe Pipe weld and HAZ tests Replace this clause with the following: 1. The absorbed energy requirements for weld and HAZ tests SHALL [PS] be as specified in Table 8 of this DEP. 2. If any specimen displays a value less than 60% of the value in Table 8, the Manufacturer shall fully investigate the cause and advise the Principal. 3. For pipelines in rich gas or CO2 service and pipelines subjected to high strain, the values in Table 8 may be increased on a project-by-project basis, 4. The test temperature shall be as specified for the pipe body. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 22 9.9 DWT test for PSL2 welded pipe 9.9.1 Replace this clause with the following: 1. For each test (a set of two test pieces), the average shear fracture shall be ≥ 85% with no individual specimen less than 50% shear area. 2. The test shall be performed at the minimum design temperature specified in the order form (Appendix 5). 3. Where it is not possible to test a full thickness specimen, the test temperature shall be adjusted in accordance with API RP3. 9.10 Surface conditions, imperfections and defects 9.10.5 Geometric deviations 9.10.5.2 Replace this clause with the following: 1. For dents, the length in any direction shall not exceed 25% of the pipe diameter. 2. All sharp gouges (with or without dent) of 1 mm (0.04 in) or greater depth shall be considered a defect. 3. Cold formed dents without sharp bottom gouges are acceptable to a maximum depth of 3.2 mm (0.125 in). Add new clause: 9.10.5.3 Surface condition – seamless pipe 9.11 1. The external surface of all seamless pipes shall be free from scabs, laps, shells, slivers, burrs, metallurgical tears and sharp edged discontinuities that may interfere with the application of thin film (e.g., FBE) coatings and multi-layer coatings where FBE forms the first layer. 2. Prior to manufacturing procedure qualification, the manufacturer shall submit, for approval by the Principal, acceptance criteria for the surface condition of all seamless pipe, together with historic evidence of the successful FBE coating of such pipe without excessive remedial work. 3. In the absence of historic data, seamless pipe shall undergo blast cleaning and examination of three pipes during manufacturing procedure qualification and one pipe per 10 test units during production. 4. The pipes shall be selected at random and heated to a minimum of 70 °C (160 °F). 5. The outside surface of the pipe shall be blast cleaned to a surface finish of SA2½ and the pipe then re-heated to 270 °C (520 °F). 6. Each pipe shall be examined visually over its entire surface for imperfections that could interfere with the FBE coating process. 7. If a seamless pipe(s) is rejected, the remaining pipes from the test unit, and one pipe from each subsequent test unit, shall be blast cleaned and examined. Dimensions, mass and tolerances 9.11.3.1 Replace this clause with the following: 1. The diameter and out of roundness tolerances of Annex J Table J3, as amended by this DEP, shall apply to all pipe ordered for onshore service. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 23 Replace this table with Annex J Table J3: Table 10 Tolerances for diameter and out-of-roundness 9.11.3.2 Replace this clause with the following: 1. The tolerances for wall thickness shall be as given in Annex J Table J4. 9.11.3.3 Replace Table 12 with the following: 1. Length tolerance shall take into account the transportation and installation methods. Table 12 Tolerance for random length pipe 9.11.3.4 Amend this clause as follows: a. The total deviation from a straight line, over the entire pipe length, shall be ≤ 0.15% of the pipe length, as shown in Figure 1. b. The local deviation from a straight line at each end of 1 m (4 ft) section shall be ≤ 3.0 mm (0.12 in) as shown in Figure 2. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 24 9.12 Finish of pipe ends 9.12.1 General 9.12.1.1 Delete this clause. 9.12.2 Threaded ends (PSL1 only) Delete this clause. 9.12.3 Belled ends (PSL1 only) Delete this clause. 9.12.4 Belled ends (PSL1 only) Delete this clause. 9.12.5.4 Replace this clause with: 1. Internal machining or grinding shall not be done unless approved by the principal. a. The specific procedure shall be subject to approval by the principal. b. Machining or grinding for end dimensional tolerance shall be parallel with a 4:1 taper transistion. 9.12.5.5 Add to this clause: 1. Outside and inside at pipe ends shall be deburred within 2mm. 9.13 Tolerances for the weld seam 9.13.1 Radial offset of strip/plate edges Replace Table 14 with the following: Table 14 Maximum permissible radial offset for SAW and COW pipes This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 25 9.13.2.2 Add the following: b. i. For SAWH weld beads, the weld cap profile shall exhibit minimal or no concavity. ii. For SAW and COW, the cap profile shall be subject to approval by the Principal at MPS stage. iii. For SAWH, a sample acceptable weld cross section macro shall be retained as a standard sample of acceptable cap profile. Selection item e) i. 9.14 The outside weld bead shall be removed by grinding for a distance of at least 150 mm (6 in) from pipe end for all pipe ordered. Tolerances for mass 9.14.1 Replace items a), b) and c) with the following: For all pipes: +10.0%, -3.5% 9.14.3 Replace items a) and b) with the following: For all grades: 9.15 -1.75% Weldability of PSL2 pipe Add the following: 1. For all offshore pipelines and for other pipelines where specified in the order form, weldability trials shall be carried out. 2. The material shall be as qualified in the manufacturing procedure qualification (Annex B), within the limits specified in (B.5). The requirements for weldability testing are given in (Appendix 2). 10 Inspection 10.1 Types of inspection and inspection documents 10.1.1.2 Replace this clause with the following: 10.1.2 1. Final inspection reports shall be supplied in both hard copy and searchable electronic versions (e.g., PDF). 2. Testing in which data curves are developed (e.g., Tensile, Compressive StressStrain, CTOD) shall be supplied as raw data formats such as can be imported into a spreadsheet file. Inspection documents for PSL1 pipe Delete this clause. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 26 10.2 Specific inspection 10.2.1 Inspection frequency 10.2.1.1 Delete this clause and Table 17. Replace Table 18 with the following: This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 27 Table 18 Inspection frequency for PSL 2 pipe This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 28 Delete this table: Table 19 Number, orientation and location of test pieces per sample for mechanical tests for PSL 1 pipe Replace Table 20 with the following: Table 20 Number, orientation and locations of test pieces per sample for mechanical tests This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 29 10.2.3 Samples and test pieces for mechanical tests 10.2.3.3 Test pieces for the CVN impact test Amend fourth paragraph as follows: 1. For test pieces taken in the HAZ of SAW pipes, the axis of the notch shall be positioned at the fusion line, fusion line + 2 mm (0.08 in) and fusion line + 5 mm (0.2 in). 2. The upper surface of the specimens shall be within 2 mm (0.08 in) of the outer surface of the pipe. See Figure 7. 3. SAW pipe of wall thickness greater than 25.4 mm (1 in) shall have four additional sets of impact specimens, from weld centre line, fusion line, fusion line +2 mm (0.08 in) and fusion line +5 mm (0.2 in), as shown in Figure 7 but with the lower surface of the specimen within 2 mm (0.08 in) of the inner surface of the pipe. In the fifth paragraph replace “as close as practicable” with “within 0.25 mm”. Add the following: 4. For test pieces taken from seamless pipes the specimens axis shall be aligned with the mid-thickness of the pipe. 5. The impact testing of seamless pipe with wall thickness equal to or greater than 25.4 mm (1 in) shall be as specified in the order form. 6. Coupons/specimens shall not be flattened. Amend Figure 7 as follows: Figure 7 Location of Charpy test specimens for weld and HAZ tests This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 30 Add new clause: 10.2.3.8 Test pieces for CTOD test 10.2.4 1. Test pieces shall be taken from the weld metal, the HAZ, and the parent metal. 2. Test pieces shall be prepared in accordance with ISO 12135. 3. Test specimens shall be Bx2B through thickness notched specimens. 4. For weld metal test, the notch axis shall be located on the weld centre line. 5. For HAZ specimens, the notch axis shal be located so as to sample the fusion line. 6. The central 50% portion of the specimen shall sample the HAZ. 7. The outer portions of the specimen shall sample weld metal. Test methods 10.2.4.8 Hardness test Add the following: 1. For all pipe ordered for non- sour service, hardness surveys (Vickers) shall be carried out as detailed in J.8.3.2 with the acceptance criteria specified in J.4.3. 2. The frequency of testing shall be as required for impact testing by Table J.7. 3. The requirements of (Annex H) shall apply to all pipe ordered for sour service. Add new clause: 10.2.4.9 CTOD test 1. CTOD testing shall be performed in accordance with ISO 12135. 2. The test temperature shall be at the minimum design temperature as stated in the order form This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 31 10.2.5 Macrographic and metallographic tests 10.2.5.2 Delete this clause. 10.2.5.3 Replace this clause with the following: 1. For HFW pipe, a metallographic examination of the weld seam SHALL [PS] be carried out. 2. The metallographic examination shall be carried out at a magnification of at least 200 times. 3. The frequency of a metallographic examination of the weld seam shall be as follows: a. Manufacturing Qualification Test: i. One specimen shall be taken from each qualification pipe ii. The manufacturer shall record the following information: 1). Width of heat treated zone (unless full body heat treatment carried out); 2). Grain size and microstructure of heat treated weld area; 3). Deformation angle (i.e., the angle by which the material adjacent to the weld is displaced from the horizontal) or other means of assessment of deformation or squeeze pressure during welding, as agreed with Principal. (See Figure 10.2.5.3). b. iii. The manufacturer shall produce acceptance criteria, subject to approval by the Principal, based on the results of the manufacturing qualification test. iv. These acceptance criteria shall be applied in production and shall demonstrate that the entire weld heat affected zone has been heat treated over the full wall thickness and is free of defects. v. The acceptance criteria shall include assessment of the grain size, and general microstructure. vi. Metallographic examination shall include an assessment of the level of deformation achieved during the welding operation (e.g., deformation angle). Production i. Metallographic examination shall be carried out at each of the following frequencies to confirm full fusion and the criteria as stated in (10.2.5.3, item 3.a): 1). one per five coils; 2). at least once per shift; 3). whenever the wall thickness or diameter changes; and 4). where there are excursions outside of the parameters agreed in the MPS for the heat treatment time or temperature. ii. All measurements made against the criteria in (10.2.5.3, item 3.b.i) shall be recorded. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 32 Figure 10.2.5.3 Deformation angle – HFW pipe 10.2.6.1 Replace this clause with the following: 1. Test pressures for all pipe shall be held for not less than 10 seconds. 10.2.6.3 Delete this clause. 10.2.6.4 Delete this clause. 10.2.6.5 Replace the first sentence of this clause with the following: 1. Except as allowed by 10.2.6.6 and 10.2.6.7, the hydrostatic test pressure, P, expressed in megapascals (pounds per square inch), for plain-end pipe shall be determined using Equation (6), with the results rounded to the nearest 0.1 MPa (10 psi): Delete this table: Table 24 — Test pressures for light-wall threaded pipe Delete this table: Table 25 — Test pressures for heavy-wall threaded pipe Delete this table: Table 26 — Percentage of specified minimum yield strength for determination of S 10.2.6.7 1. The test pressure for all types and sizes of pipe shall be such that the hoop stress, calculated on the basis of the minimum specified wall thickness (minimum wall thickness to include deduction of thickness for mill tolerance) including stresses from the end loading, is at least 95% of the specified minimum yield strength. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 33 10.2.7 Visual inspection 10.2.7.1 Add the following: 10.2.8 1. For HFW and SAW pipes, the inspection shall include the internal weld profile. 2. The entire internal surface of SAW pipes of outside diameter greater than 610 mm (24 in) shall be visually inspected. Dimensional testing 10.2.8.1 Replace this clause with the following: 1. The diameter of the first 10 pipes shall be measured. 2. After the first 10 pipes, the diameter shall be measured once every 20 pipes but not less than once per 4 hour shift. 3. Unless a specific method is specified in the order form, diameter measurements shall be made with a circumferential tape, ring gauge, snap gauge, calliper or optical measuring device. 10.2.8.2 Replace this clause with the following: 1. The out of roundness of the first 10 pipes shall be measured. 2. After the first 10 pipes, the diameter shall be measured once every 20 pipes but not less than once per 4 hour shift. 3. The out of roundness shall be determined as the difference between the largest inside diameter and the smallest inside diameter, as measured in the same cross-sectional plane. 10.2.8.3 Delete this clause. 11 Marking 11.1 General 11.1.2 Delete this clause. 11.2 Pipe markings 11.2.1 Add the following: k). i. Each pipe shall be uniquely indentified. Add the following: l). i. The applicable DEP number and project name shall be added. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 34 11.2.3 Replace this clause with the following: a). a. Low stress die stamping or vibro etch marking is required only if specified in the order forms. i. Low stress die stamping shall only be applied to the bevel face or plain end. ii. Vibro etch marking may be applied within 150 mm (5.9 in) from the pipe end. Add new clause: d). Die stampings shall be coated with a clear lacquer to prevent corrosion at the location of the markings. 11.3 Coupling markings Delete this clause. 12 Coatings and thread protectors 12.2 Thread protectors Delete this clause. 14 Pipe loading Add the following: 1. If required by the order form, each end of each length of pipe shall be provided with a suitable end protector designed to prevent damage to the weld prepared or plain end. 2. End protectors shall not be attached to the pipe using tape or other connectors. 3. The end protector design shall be submitted to the Principal. 4. The end protector design shall be conducive for using crane hooks for lifting. Refer to the order form for protector requirements. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 35 Annex A (normative) Specification for welded jointers Delete this annex. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 36 Annex B (normative) Manufacturing procedure qualification for PSL2 pipe B.1 General Replace this clause with the following: 1. Manufacturing procedure qualification shall be required for all PSL2 pipe. 2. Qualification shall be carried out on each combination of diameter and wall thickness supplied. 3. The qualified manufacturing procedure shall form the basis for pipe acceptance. 4. Deviation from the qualified manufacturing procedure shall require full requalification in accordance with the requirements of (B.5). 5. The Manufacturer shall inform the Principal within 48 hours of any intentional or unintentional manufacturing deviations from the agreed procedures, dimensional tolerances, or composition. 6. The Manufacturer shall communicate manufacturing deviations even if the finished line pipe meets the requirements of this DEP and ISO 3183:2012 and th API SPEC 5L 45 edition. 7. The manufacturing procedure shall be qualified by selecting at random three of the completely finished pipes of the first day’s production. 8. If more than one heat is used in the first-day production pipes, at least two heats shall be represented by the test pipes. 9. All testing shall be performed on each test pipe. 10. For HFW pipe, the test pipes shall include the pipes made from each end of the first coil of strip. 11. For orders less than 200 tonnes (220 tons), use of data from a previous order shall be subject to approval by the Principal provided the pipe grade, size, and manufacturing method are similar. 12. With Principal approval, part or all of the manufacturing procedure qualification may be carried out prior to first day production, but shall use plate or coil ordered for production and the same welding machines and procedure and NDT equipment as proposed in production. B.2 Additional information to be supplied by the purchaser Delete list items a) and b) and replace by: 1. B.3 Unless otherwise specified on the order form, qualification shall be in accordance with (B.3, B.4 and B.5). Characteristics of the manufacturing procedure specification a. steel making and casting — for all pipe Add the following: 9. b. Quality plan detailing all inspection points and tests performed in accordance with ISO 10005. pipe manufacturing — for all pipe: Replace this clause with the following: 1. e. Strip/plate manufacturing method including details of rolling conditions, accelerated cooling conditions (if applied) and heat treatment method (N or Q) if applicable. pipe manufacture – for welded pipe: This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 37 Add the following: 3. a. For HFW pipe, the seam welding procedure shall include details of the following: III. Methods to be used for heating strip edges and for the control and monitoring of power input in relation to the temperature of the pipe surface and the speed of the pipe; IV. Frequency (in kHz) of the welding power supply; V. Welding speed VI. Welding Temperature (or Principal approved alternative method of monitoring weld quality). VII. Welding power VIII. Compressive force or displacement used in welding. IX. Temperature of in-line normalising or normalizing and tempering (if applied) X. Details of any protective atmosphere used for welding; XI. Methods used to accomplish and control the upset welding of the heated pipe edges; XII. Methods used for trimming of the weld bead. 4. for SAW and COW pipes: Add the following a. For SAW pipe, the seam welding procedure shall include details of the following: V. brand name, classification, size and grade of filler metal and flux; VI. speed of welding; VII. number of electrodes and polarity for each electrode; VIII. stickout for each wire; IX. welding current for each wire; X. welding voltage for each wire. Add new clause: g. B.4 For sour service pipe, the hydrogen-induced cracking test procedure shall include full details of the exposure test method required by NACE TM0284 and DEP 30.10.02.16-Gen. and full details of the procedure used for metallographic preparation of the exposed test pieces. Characteristics of the inspection and test plan Add the following to the first paragraph j. Quality plan detailing all inspection points and tests performed in accordance with ISO 10005. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 38 B.5 Manufacturing procedure qualification tests B.5.2 Add the following: The following additional tests apply: B.5.2.1 Tensile tests – General 1. Parent material and all weld metal tensile tests (at ambient and elevated temperature) shall be conducted so as to record the full stress strain curve up to maximum load. This applies to manufacturing procedure qualification testing only. 2. B.5.2.2 B.5.2.3 B.5.2.4 Data shall be provided electronically in spreadsheet format. Elevated temperature tensile tests 1. Where required in the order form, elevated temperature tensile tests shall be taken in both the longitudinal and, for pipes of outside diameter ≥ 219.1 mm (8.63 in), the transverse direction. 2. Testing shall be in accordance with a nationally recognized standard. 3. The testing temperature and acceptance criteria shall be stated in the order form. All weld tensile tests (SAW only) 1. All weld tensile tests shall be performed on each of the first-day production test pipes. 2. The tests results shall meet the minimum specified requirements of the plate with regard to yield, tensile strength and achieve a minimum elongation value of 18%. 3. The test method shall be in accordance with a nationally recognized standard. 4. Where required in the order form, all weld tensile tests shall also be performed at elevated temperature. Impact tests 1. 2. For each of the first-day production pipes, a full impact transition curve shall be determined for all location specified in (10.2.3.3). a. Seamless shall be performed within the pipe body. b. HFW shall be performed within the parent material along weld centre line (within 0.25 mm from FL). c. SAW shall be performed within theparent material along weld centre line, fusion line, fusion line +2 mm (0.08 in), and fusion line +5 mm (0.2 in). At least 12 specimens shall be tested at each position at a temperature range wide enough to obtain upper and lower shelf toughness impact energy values. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 39 B.5.2.6 B.5.2.7 CTOD testing (SAW only) 1. CTOD testing shall be performed in accordance with ISO 12135. 2. The test temperature shall be the minimum design temperature as stated in the order form. 3. Test pieces shall be taken from both the weld and HAZ. 4. Test pieces shall be SENB type prepared in accordance with ISO 12135. 5. Weld test specimens shall be through thickness notched with the notch being located at the weld centreline. 6. HAZ specimens shall be surface notched from the outside surface so that the fatigue crack tip samples the HAZ within 0.5 mm (0.02 in) of the fusion line. 7. The location of the fatigue crack tip shall be verified by post test sectioning and metallography. 8. Through thickness notched specimens shall be Bx2B and surface notched specimens BxB. 9. The minimum CTOD value (from a set of three specimens) taken from each of the pipe, weld and HAZ locations, shall be as stated in the order form. Strain aged testing 1. B.5.2.8 Drop weight tear tests 1. B.5.2.9 Where required by the order form, tensile Charpy impact, fracture toughness testing and hardness testing shall be carried out in the strain aged condition according to (Appendix 1). In addition to the normal DWTT requirements, a full transition curve shall be established for the parent material on each of the test pipes. Radiography 1. The weld seams of all SAW pipes shall be radiographically examined throughout their full length. B.5.2.10 PT or MT 1. The weld seam shall be subjected to liquid penetrant or magnetic particle testing to check for surface defects in the weld and adjacent HAZ. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 40 Add new clause: B.6 Requalification of manufacturing procedure 1. The following changes to the manufacturing procedure shall require full requalification of the manufacturing procedure: a. Any change to the steel chemistry which produces a change in the CE of more than +0.03 (see (9.2.2); b. Any change to the steel de-oxidation practice; c. A change from ingot casting to continuous casting or vice versa; d. Any change to the plate or pipe reduction ratio; e. A change in the finishing temperature during plate or strip rolling outside the approved range; f. A change in the accelerated cooling start temperature outside the approved range; g. A change in the finishing temperature outside the approved range, for pipe not subject to further heat treatment; h. A change in the pipe heat treatment soaking temperature and soaking time; i. Any change to the welding procedure outside the essential variable limits of ISO 9956-3. In addition for SAW pipe, a change in flux brand name and an increase of more than 20 mm (0.8 in) in the wire stick-out. Add new clause: B.7 HFW – Parameter envelope 1. 2. In addition to the essential variables stated in clause B.5, the Manufacturer shall submit, subject to approval by the Principal, the maximum ranges of each of the following parameters for each pipe diameter, thickness and material grade: a. Welding speed; b. Welding temperature (or Principal approved alternative method of monitoring weld quality); c. Welding power; d. Compressive force or displacement. The Manufacturer shall provide details, subject to approval by the Principal, on how the parameters in (B.7, item 1) are to be monitored and recorded. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 41 Add new clause: B.8 Surface of seamless pipe 1. The Manufacturer shall provide historical evidence that the surface finish of previous production was suitable for the application of FBE coatings. 2. In the absence of the data in (B.8, item 1), three pipes from the first day's production shall be selected at random and heated to a minimum of 70 °C (160 °F). 3. The outside surface of the pipes shall be blast cleaned to a surface finish of SA2.5 and the pipe re-heated to 270 °C (520 °F) 4. Each pipe shall be examined visually over its entire surface for scabs, slivers, tears and similar surface defects which may interfere with the application of FBE and other coatings. 5. Should the pipe fail to meet the required standard of surface finish, the Manufacturer shall submit procedures for remedial action and subsequent testing of the production material to guarantee suitability of the production material for FBE coating, for approval by the Principal. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 42 Annex C (normative) Treatment of surface imperfections and defects C.2 Treatment of dressable surface defects C.2.2 Add the following: 1. All ground areas shall be smoothly contoured at a minimum 3 to 1 slope. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 43 Annex D (normative) Repair welding procedure D.1 General D.1.2 1. Repair welds shall be made by one or more of the following methods: Delete this clause: b). b) D.2 Repair welding procedure qualification D.2.3 Mechanical testing D.2.3.4 Charpy (CVN) impact test D.2.3.4.4 Add the following: 1. The test temperature shall be the same as that required for the unrepaired production pipe weld metal and HAZ. Add new clause: D.2.5 CTOD test 1. The qualification of repaired weld shall be subject to the same CTOD testing as required by (Annex B clause B.5.2). 2. In the case of (D.2.5, item 1) surface notched specimens shall be used to sample the weld metal and both HAZs (repair/parent material and repair weld/original weld). This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 44 Annex E (normative) Non-destructive inspection for other than sour service or offshore service E.1 Qualification of personnel Add the following: 1. The qualifications of personnel shall be subject to approval by the Principal. E.1.3 Add the following: E.2 1. The Manufacturer/Supplier shall have a NDT UT Level 3 available on call during manufacture. 2. All of the Manufacturer/Supplier NDT specifications and procedures shall clearly state the approval of the NDT Level 3 showing approval date and qualification number and the expiry date of the NDT Level 3 individual. Standard practices for inspection Add the following: 1. A procedure shall be written for every technique describing the inspection process, with as a minimum the essential variables stated in (Appendix 4 Table 4.1). E.3 Methods of inspection E.3.1 General E.3.1.1 Replace this clause with the following: 1. The weld seams of welded pipe shall be inspected using the ultrasonic angle beam shear wave method in accordance with ISO 10893-11:2011, over the full length (100%) for the entire thickness, as given in Table E.1. Acceptance levels: ISO Reference reflectors as shown in Table E.8. 2. Inspection procedures including the use of ToFD shall only be used with the approval of the Principal. 3. Advanced ultrasonic techniques (e.g., phased array, EMAT) may only be permitted by the approval of the Principal on the basis of a specific qualification program approved by the Principal. E.3.1.2 Replace this clause with the following: 1. All SMLS pipe shall be non-destructively inspected full length (100%), as given in Table E.2. Applicable code: ISO 10893-10:2011 (longitudinal and transverse imperfections). E.3.1.3 Replace this clause with the following: b). Welded pipe shall have final acceptance inspection after hydrostatic test. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 45 Replace Table E.1 with the following: Table E.1 Pipe weld seam non-destructive inspection Replace Table E.2 with the following: Table E.2 SMLS pipe body non-destructive inspection E.3.2 Pipe end inspection — Welded pipe E.3.2.1 Replace this clause with the following: 1. Pipe end weld seam: If an automated ultrasonic or electromagnetic inspection system is applied to meet the requirements of (E.3.1.1), welds at any pipe ends that are not covered by the automated inspection system shall be inspected for defects by a manual or semi-automatic ultrasonic angle beam method, using the same inspection sensitivity and inspection parameters as specified in (E.3.1.1). 2. Alternatively, non-inspected pipe ends in (E.3.2.1, item 1) may be cut off. 3. The non-AUT inspected pipe end shall not be longer than 355 mm (14 in). E.3.2.2 Replace this clause with the following: 1. For SAW and COW pipe, the weld at each pipe end for a minimum distance of 200 mm (8.0 in) shall be inspected by the radiographic method. 2. For SAW and COW pipe, the results of radiographic inspection shall be recorded on either film or another imaging medium (See also E.4). 3. The radiographic inspected area shall be inspected by the ultrasonic method. 4. The ultrasonic method shall be considered the prime inspection method. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 46 E.3.2.3 Replace this clause with the following: 1. Ultrasonic inspection in accordance with the method described in ISO 10893-8:2011 shall be used to verify that the circumference of the pipe ends over a length of 25 mm (1 in) or 2t (whichever is the greater, with a maximum of 50 mm (in) from the point where the outside surface meets the face or bevel) is free from laminar imperfections ≥ 6.4 mm (0.25 in) in the axial and circumferential directions. 2. The ultrasonic inspection may be undertaken from the outside surface if the pipe end is inspected before weld beveling, 3. If ultrasonic inspection is undertaken after weld beveling inspection shall be from the pipe internal surface. Add new clause: E.3.2.4 E.3.3 SAW & COW pipe end circumference: 1. Ultrasonic inspection using 45° angle beam shear wave probes and scanning in two circumferential directions shall be used to verify that the 25 mm (1 in) wide zone at each pipe end is free of axially aligned through thickness cracking. 2. An axially aligned N5 notch shall be the reference and acceptance level. Pipe end inspection — SMLS pipe E.3.3.1 Replace this clause with the following: 1. Pipe end – not tested portion: If an automated ultrasonic system (i.e., combined equipment, operating procedures and personnel) is applied to meet the requirements of (E.3.1.2), the end of the pipe that is not covered by the automated inspection system shall be inspected for defects by the semiautomatic ultrasonic angle beam method using the same inspection sensitivity and inspection parameters as specified in (E.3.1.2). 2. Pipe ends not inspected by automated or semi-automatic ultrasonic angle beam methods shall be cut off. 3. The non AUT inspected pipe end shall not be longer than 324 mm (12 in). 4. Manual ultrasonic inspection may be approved by the Principal as an interim measure. 5. The manufacturer shall install an automatic or semi automatic system within an agreed time frame if manual ultrasonic inspection is used as an interim measure. E.3.3.2 Replace this clause with the following: 1. Ultrasonic inspection in accordance with the method described in ISO 10893-8:2011 shall be used to verify that the circumference of the pipe ends over a length of 25 mm (1 in) or 2t (whichever is the greater, with a maximum of 50 mm (2 in), from the point where the outside surface meets the face or bevel) is free of laminar imperfections ≥ 6.4 mm (0.25 in) in both axial and circumferential direction. 2. The ultrasonic inspection shall be carried out from the inside surface if the pipe is examined after weld bevel cutting. 3. If ultrasonic inspection is before bevel cutting, the examination may be undertaken from the outside surface. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 47 E.4 Radiographic inspection of weld seams E.4.2.3 Replace this clause with the following: 1. E.4.6 The density of the radiograph shall be between 2.0 – 3.0 in the weld seam. Defects found by radiographic inspection Add the following: 1. Where retesting of suspect areas indicated by UT is performed with RT and found to be free of indications, the area shall be subjected to further UT. 2. If an indication is confirmed with the repeat UT and is not caused by geometrical features or acoustic coupling conditions, then the UT indication shall be classed as a crack and the material rejected. Add new clause: E.4.8 Use of filmless radiography or digital radiography 1. The radiographic inspection of the body weld seam and the weld seam at the pipe ends may be replaced by automatic filmless radiography or digital radiography provided that the standard of the automatic filmless radiography is at least equal to the requirements for film radiography. 2. The image quality during digital radiography shall comply to class B (ISO 10893-7). 3. The final disposition of radiography for suspect areas shall be made using UT (see E.4.6 and E.5.5.2). E.5 Ultrasonic and electromagnetic inspection E.5.1 Equipment E.5.1.1 Add the following: 1. Automatic ultrasonic equipment (AUT) SHALL [PS] be used for weld seam and pipe body inspection for detection of indications and identification of defects. 2. The AUT shall have automatic facilities with the following characteristics: a. Registration/ recording of indications shall be carried out without any intervention of the ultrasonic operator and available for review. b. Any indication above 50% (~ 6 dB) of the reference level shall be marked as an indication and registered. c. There shall be a device that monitors the effectiveness of the acoustic coupling. d. Loss of coupling (a deviation in excess of 10 dB from the good coupling situation) shall be recorded. e. Upon loss of coupling, automatic spray paint shall be activated and automatic acoustic warnings sounded. 3. For welded pipe, an automated weld tracking system shall be used for correct positioning of the probes with respect to the weld centerline. 4. Manual ultrasonic inspection (MUT) shall be used to verify the indications rejected by AUT and confirm rejection or acceptance, and to inspect areas not able to be inspected by AUT. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 48 Add new clause: E.5.1.3 Performance test of AUT for mill qualification 1. The performance test shall be carried out during the qualification of the mill to test the AUT system with the pipes as follows: a. For the wall thickness category >11.9 mm (0.469 in) to be qualified: i. b. One test pipe in the highest wall thickness category to be qualified, and For the wall thickness category <= 11.9 mm (0.469 in) to be qualified: i. One test pipe with the lowest wall thickness and diameter to be qualified. 2. The test pipes shall contain the reference reflectors of Table E.7, E.7.1 (HFW), E.7.2 (SAW and COW), E.7.3 (SMLS) and either two notches or through-drilled holes at both pipe ends to mark the border of zones that are not covered by AUT. 3. The stability tests shall be carried out in dynamic mode. This means either moving the pipe under a fixed scanning device or moving the scanning device over the pipe. 4. The stability tests shall also apply to full body AUT. 5. The reference signals shall be set on 80% screen height (± 5%) to be able to see fluctuations in the signal. 6. The signal to noise ratio of the reference signals shall be at least 12 dB and at least 4x the noise level. Figure E.5.1.3 Reference signals 7. A total of 8 test runs for each test pipe shall be made to confirm the stability of the AUT system. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 49 8. 9. E.5.2 The following listed items shall be reported: a. Diameter and wall thickness of the test pipe(s); b. Specification of used probes (angles and frequencies); c. Drawing of the reference reflectors in the test pipe (above view and cross section); d. Layout of the probes in combination with the reading channels; e. Printout (paper or digital) of the screen from the individual scans and reference signals marked on the first scan; f. Actual values of the reference signals; g. Actual values of the signal to noise ratio. For the AUT system, the fluctuation of the reference signal between eight test runs shall be ± 25% of the average signal. Ultrasonic and electromagnetic inspection reference standards E.5.2.2 Replace this clause with the following: 1. Reference standards shall contain as reference indicators one or more notches, radially drilled holes and, if applicable, flat bottom holes as given in Table E.7, E.7.1 (HFW), E.7.2 (SAW) and/or E.7.3 (SMLS). 2. For electromagnetic inspection, the reference standard shall contain OD notches, ID notches and a radially drilled hole. (See E.5.3.4.) Replace Table E.7 with the following: Table E.7 Reference indicators This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 50 Add new table: Table E.7.1 HFW - Number of Probes for zone of weld for different wall thickness/reference reflector 1. A direct irradiation method (pulse echo) may be used if the main axis of the ultrasonic beam hits the corresponding reference reflector perpendicular within ± 30. 2. The flat-bottomed holes shall be located at the mid-thickness of the weld inner zone and be perpendicular to the fusion line of the weld (e.g., at the fusion line 50% or 40 and 60% WT depth). This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 51 Add new table: Table E.7.2a SAW – Number of probes for zone of weld for different wall thickness/reference reflector 1. The angle of the probes for embedded zones shall be perpendicular to the original weld bevel ± 3°. a. If the weld bevel is less than 15° (half aperture) the probes shall be used in the tandem arrangement. 2. For longitudinal imperfection detection, transducer angle shall be between 50° – 70°. 3. Notch type reflectors (N5) at the toes of the weld (ID and OD) may be used to verify start and end of monitoring gates, but not to adjust sensitivity settings. 4. The echo of notch type reflectors shall exceed the recording threshold level or the reference sensitivity level adjusted to above 100% FSH. The reject level remains the original 33% FSH. 5. Alternative numbers and configurations of probes may be used, subject to demonstration of reliable responses from the reference indicators for each zone, and subject to the approval of the Principal. 6. A 1.6 mm (0.063 in) diameter radially drilled hole with an acceptance level of 0 dB (100% of reference level) may be used. 7. There shall not be crack-like indications in any weld beads (weld pass-particularly for SAW welding). a. The gate setting for the weld bevel inspection shall include the weld pass centre line. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 52 Add new table: Table 7.2b SAW Add new figures: Figure E.1(a) Example of transducer set-up and FBH location at 30% and 70% of wall thickness for one side of the weld Figure E1(b) Example of tandem transducer set-up and FBH location at 50% of the pipe wall thickness for one side of the weld (tandem required if the (half) bevel angle is less than 15°) This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 53 Add new table: Table E.7.3 1. E.5.5 SMLS: probes and reference reflector Other probe angles may be approved by the Principal, based on the demonstration of repeatable detection of reference indicators on the calibration pipe. Acceptance limits E.5.5.2 Add new clauses: E.5.7 d. Where retesting of suspect areas indicated by UT is performed with RT, and found to be free of indications, the area shall be subjected to further UT. e. If the indication is confirmed with the repeat UT and is not caused by geometrical features or acoustic coupling conditions, the UT indication shall be classed as a crack and the material rejected. Weld repair Add the following: 1. Repair of HFW pipe weld seams by repair welding is not permitted. 2. Surface repair of external and internal HFW weld seam shall be done only by dressing with grinding and wall thickness checked after grinding. Replace Table E.8 with the following: Table E.8 Acceptance limit 1. The reject threshold (see E.5.3) shall not exceed the applicable acceptance limit. 2. A radially drilled hole of 1.6 mm (0.063 in) with an acceptance limit of 100% (0 dB) may be used. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 54 E.7 Residual magnetism E.7.4 Replace this clause with the following: 1. Measurements shall be made on each end of a pipe, selected at least three times per 4 h per operating shift. E.7.6 Replace this clause with the following: E.8 1. Four readings shall be taken approximately 90° apart around the circumference of each end of the pipe. 2. The average of the four residual magnetism readings shall be ≤ 2.0 mT (20 Gs) with no individual residual magnetism reading greater than 2.5 mT (25 Gs). Laminar imperfections in the pipe body of EW, SAW and COW pipes E.8.1 Replace this clause with the following: 1. For HFW pipe, ultrasonic inspection shall be used to verify that the pipe body is free of laminar imperfections. 2. Ultrasonic inspection of HFW pipe shall be performed in accordance with: a. ISO10893-9:2011, if such inspection is done prior to pipe forming; or b. ISO 10893-8:2011, if such inspection is done after seam welding. 3. Acceptance criteria shall be in accordance with Table K.1 of this DEP. 4. The coverage of the ultrasonic inspection of HFW pipe shall be at least 50% of the total strip/plate or pipe body. E.8.2 Replace this clause with the following: 1. 2. E.9 For SAW and COW pipe, ultrasonic inspection shall be used to verify that the strip/plate or the pipe body is free of laminar imperfections. a. Ultrasonic inspection of SAW and COW pipe shall be in accordance with ISO 10893-9:2011. b. Coverage of the ultrasonic inspection of SAW and COW pipe shall be at least 50% of the total plate/pipe. Acceptance criteria shall be in accordance with Table K.1 of this DEP. Laminar imperfections along the strip/plate edges or pipe weld seam of EW, SAW and COW pipes Replace this clause with the following: 1. For HFW, SAW and COW pipes, ultrasonic inspection shall be used to verify that the 25 mm (1 in) wide zone along each of the strip/plate edges or along each side of the pipe weld seam is free of laminar imperfections. 2. Acceptance criteria for ultrasonic inspection of HFW, SAW, and COW pipes shall be as follows: a. ISO 10893-9:2011 acceptance level U2, if such inspection is done prior to pipe forming; or b. ISO 10893-8:2011 acceptance level U2 if such inspection is done after seam welding. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 55 Add new clause: E.11 Laminar imperfections in the pipe body of SMLS pipes 1. For SMLS pipe, ultrasonic inspection shall be used to verify that the pipe body is free of laminar imperfections greater than those permitted by ISO 10893-8, acceptance level U1. 2. The coverage shall be sufficient to detect the minimum defect size as specified in ISO 10893-8 level U1 but not less than 50%. Add new clause: E.12 Thickness measurements for SMLS pipes 1. For SMLS pipe, ultrasonic thickness measurements shall be carried out. 2. Coverage of ultrasonic thickness measurements for SMLS pipe shall be at least 25% of pipe surface. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 56 Annex F (normative) Requirements for couplings (PSL 1 only) Delete this annex. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 57 Annex G (normative) PSL 2 pipe with resistance to ductile fracture propagation G.1 General Add new clause: G.1.3 The Charpy test requirements given in (9.8) are based on crack initiation principles. 1. For rich gas transmission and two phase pipe lines, higher absorbed energy requirements may be specified to avoid the risk of running fractures. In this case, the Battelle Two Curve method would be used to determine the required absorbed energy. 2. The calculation of the Battelle Two Curve method shall be performed by the Purchaser and the requirements included in the order form. DEP 31.40.00.10-Gen., section 8.1.6 provides design information and requirements. 3. When specified, additional Charpy impact testing shall be performed on the pipe body and, for welded pipe, also on the weld and heat affected zone. a. The additional Charpy impast testing shall be conducted at the minimum design temperature provided in the order form and as specified in (9.8). If the required absorbed energy values are obtained at the test temperature prescribed for fracture initiation, (9.8.2.1) the additional tests need not be performed, unless higher values are stated in individual Order forms. G.6 Guidance for determining CVN absorbed energy values in buried onshore gas pipelines Replace this clause with the following: 1. Absorbed energy values shall be as specified in (9.8.2.1) or as stated in individual order forms. Delete these clauses: G.7 EPRG guidelines – Approach 1 G.8 Battelle simplified equation – Approach 2 G.9 Battelle two-curve method – Approach 3 G.10 AISI method – Approach 4 G.11 Full-scale burst testing – Approach 5 This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 58 Annex H (normative) PSL 2 pipe ordered for sour service H.2 Additional information to be supplied by the purchaser Delete the following items: Information included in this DEP b) f) g) h) i) j) k) l) m) n) Information not applicable to this DEP c) H.3 Manufacturing H.3.1 Manufacturing procedure Remove the word “possibly.” H.3.3 Pipe manufacturing H.3.3.2 Welded pipe H.3.3.2.4 Replace this clause with the following: 1. Strip and plate shall be inspected ultrasonically for laminar imperfections or mechanical damage in accordance with (Annex K), either before or after cutting the strip or plate. 2. Alternatively, the completed pipe may be subjected to full-body inspection, including ultrasonic inspection. H.3.3.2.5 Delete this clause. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 59 H.4 Acceptance criteria H.4.1 Chemical composition H.4.1.1 Replace this clause with the following: 1. Table H.1 shall apply for all pipe grades and for pipe with t ≤ 35 mm (1.38 in), with the additional requirement that Boron (B) shall not exceed 0.001%. 2. The Manufacturer/Supplier’s target product analysis shall be shown in the Manufacturing Procedure Specification. 3. A single value target CEiiw or CEpcm, shall be stated. 4. The range of elements shall be such that the variation in the single value target CEiiw does not exceed ± 0.03 units or CEpcm does not exceed ± 0.02 units with the following additional restrictions: Table H.4.1.1 Pipe grade restrictions The figures in Table H.4.1.1 represent the total range and not a plus or minus tolerance. 5. There shall be no changes in the chemical composition (within the tolerances listed in Table H.4.1.1) from the approved MPS composition. 6. No intentionally added elements shall be increased beyond the limits in Table H.4.1.1 or removed. 7. The chemical composition recorded for the pipes used in first-day production testing shall set the datum CE. 8. Where any of the elements in Table H.4.1.1 are not intentionally added, the manufacturer may propose maximum values for approval by the Principal. 9. All elements listed in Table H.1 shall be reported. H.4.1.2 Replace this clause with the following. 1. For pipe with t > 35 mm (1.38 in), the chemical composition shall be agreed with the Principal, with the requirements given in Table H.1 being amended. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 60 H.4.4 Hardness test Amend this clause as follows: 1. The maximum hardness of the pipe body shall not exceed 240 HV10 at the inner surface, centerline and outer surface. 2. For specific orders the hardness limits may be reduced from that specified above in (H.4.4, item 1). First paragraph: Delete (22 HRC) Second paragraph: Delete (26 HRC) H.7 INSPECTION Table H.3 Inspection frequency Delete references to SAWH in table: Note that SAWH is not permitted for sour service per previous clauses in this DEP. Table H.4 Number, orientation and location of test pieces per sample for hardness tests Delete reference to strip/plate end weld. Delete note c. H.7.3 Test Methods H.7.3.1 HIC/SWC test H.7.3.1.1 Replace this clause with the following: 1. Refer to NACE TM0284 and DEP 30.10.02.16-Gen requirements for HIC/SWC tests. H.7.3.1.4 Replace second sentence with the following: 1. Photographs of any reportable crack shall be provided with the report. Add the following: 2. For tests on HFW pipe, sections containing the weld seam shall be metallographically examined at magnifications of at least 100X for any evidence of cracking at the weld line in the through-thickness direction and all such indications reported. 3. Indications on the weld line shall not have an aggregate length greater than 0.5 mm (0.02 in) through thickness. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 61 H.7.3.2 SSC test H.7.3.2.1 Replace this clause with the following: 1. Sulphide stress cracking tests are required for manufacturing procedure qualification of each pipe thickness. 2. A four-point bend test piece in accordance with ISO 7539-2 or ASTM G39 shall be used. 3. The SSC test duration shall be 720 h. 4. SSC testing shall be carried out at 90% of the actual yield of the parent material using the 4 point bend method (internal surface in tension) as described in Table B1 of ISO 15156-2, with reference to Appendix 2 of EFC 16. 5. The applied strain of the SSC test shall be verified by the direct application of strain gauges. 6. Test solution A of TM0177 (the same as test solution A, EFC 16 Annex A3), shall be used adjusted to a starting pH of 3.5. 1 bara (pure). 7. For welded pipe three four-point bent test specimens shall be taken transverse to the weld. 8. The distance between the inner supports shall be equal to, or greater than, the width of the weld plus 50 mm (2 in) (25 mm (1 in) on each side of the weld). 9. The specimen thickness shall be t or 15 mm (0.6 in), whichever is the less, unless otherwise agreed with the Principal. 10. The specimen width shall be ≥ 20 mm (0.8 in), unless otherwise agreed with the Principal. 11. All SSC test specimens shall meet the acceptance criteria of ISO 15156-2. 12. All SCC test specimens shall be evaluated for resistance to SOHIC in accordance with ISO 15156-2, clause B.4.2.3. 13. Two longitudinal metallographic sections shall be taken from each SSC specimen. 14. There shall be no ladder-like HIC features or cracks exceeding a length of 0.5 mm (0.02 in) in the through thickness direction. H.7.3.3 Hardness test H.7.3.3.1 Replace the first two paragraphs with the following: 1. Hardness testing shall be performed using the Vickers test in accordance with ISO 6507-1 or ASTM E384. Figure H.1 – Location of hardness tests Amend note b) as follows: 0.50 mm (0.02 in) from fusion line Modify drawings a, b and c with: 2. Surface hardness indentation shall be on a line not greater than 1.5 mm (0.06 in) from the inside and outside surfaces. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 62 Add new clause: H.7.3.4 Root guided bend test for HFW pipe H.7.3.4.1 1. Root guided-bend test specimens shall be undertaken in accordance with 10.2.4.6 on pipe of 219 mm (8 in) OD and greater. 1. One root guided-bend test shall be conducted for each pipe on MPS qualification (first day production test) at both ends of each pipe, and in production on one end per pipe per 100 pipes. 1. Root guided bend test specimens shall not fracture completely. 2. No opening longer than 3 mm (1/8 in) shall occur during the root guided bend test. H.7.3.4.2 H.7.3.4.3 Add new section: H.9 PSL 2 pipe ordered for sour service – Additional requirements to comply with Canadian Standard CSA Z662 H.9.1 Scope This section, which continues through the remainder of Annex H, contains additional requirements for sour service pipe when the requirements of Canadian Standards CSA Z245.1 and CSA Z662 for line pipe are specified in the order form. Modifications to (PART III AMENDMENTS/SUPPLEMENTS TO ISO 3183:2012) 3 Normative references Add: CSA Z662, Oil and Gas Pipeline Systems; CSA Z245.1 Steel Pipe; ERCB directive 56; Alberta Pipeline Act and Regulations; British Columbia Oil and Gas Activities Act; B.C. Reg. 281/2010 Pipeline and Liquefied Natural Gas Facilities Regulation; Shell STD. 3-1.12, Pipe, Valves and Fittings - Piping Classes, (Upstream Field Facilities). 9.9 DWT test for PSL2 welded pipe 9.9.1 Replace this clause with the following: 1. Refer to CSA Z245.1 Clause 8.4.4.1.3 for the requirements of DWT test for PSL2 welded pipe. 2. Drop-weight tear tests or Charpy V-notch impact tests shall be performed at the minimum design temperature specified in the order form. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 63 H.4.2 Tensile properties Replace this clause with CSA Z245.1 Clause 16.8. H.4.4 Hardness test Delete second paragraph: Add, based on CSA Z245.1 Clause 16.5: 1. The microhardness at any location in the weld zone of HFW pipe and in the deposited weld metal and heat-affected zones of other welds shall not exceed 248 HV 500 gf. 2. The welding procedure qualification test for the pipe weld shall be microhardness tested at the hardest-appearing microstructure. a. The microhardness at any location therein shall not exceed 248 HV 500 gf. Add new clause H.4.6 Root-Guided Bend Test 1. H.5 Refer to CSA Z245.1 Clause 16.6 for requirements for root-guided bend test. Surface conditions, imperfections and defects Delete this clause. H.7 Inspection H.7.1 Specific inspection Replace Table H.3 with the following: Table H.3 Inspection frequency Replace line 5 with: This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 64 H.7.3 Test Methods H.7.3.3 Hardness test Add new clause, based on CSA Z245.1 clause 16.5: H.7.3.3.4 Microhardness 1. The welding procedure qualification test weld for longitudinal seam of SAW and COW pipe shall be microhardness tested at the hardest-appearing microstructure. 2. The microhardness at any location therein shall not exceed 248 HV 500 gf. 3. The microhardness at any location in the weld zone of electric welded pipe and in the deposited weld metal and heat-affected zones of other welds shall not exceed 248 HV 500 gf. Add new clause, based on CSA Z245.1 Clause 16.6 and 7.5.2: H.7.3.4 Root guided bend test for HFW pipe 1. Root guided-bend test specimens shall be in accordance with Clause 10.2.4.6. 2. For electric welded pipe produced in single lengths, when specified, one root guided-bend test shall be conducted at each end of electric-welded pipe. 3. For electric-welded pipe produced from coiled skelp in multiple lengths and subsequently cut into single lengths, two test rings for each multiple length from the leading end of the first pipe and two test rings from the trailing end of the last pipe, shall be tested with the weld altemately at 0° and 90° to the applied force. 4. The 0° tests are not required for pipe subjected to root guided-bend testing in accordance with the requirements of 10.2.3.6. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 65 Annex I (normative) Pipe ordered as “Through the Flowline" (TFL) pipe Delete this annex. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 66 Annex J (normative) PSL 2 pipe ordered for offshore service J.2 Additional information to be supplied by the purchaser Delete the following items: Information included in this DEP b), e), g), m), n), p) Information not applicable to this DEP c) Add: dd) more stringent tolerances on pipe end out-of-roundness and internal diameter. ee) recording pipe end out of roundness and internal diameter for each pipe end. J.3 Manufacturing J.3.3 Pipe manufacturing J.3.3.2 Welded pipe J.3.3.2.4 Replace this clause with the following: 1. Strip or plate shall be inspected ultrasonically for laminar imperfections or mechanical damage in accordance with Annex K. a. The ultrasonic testing shall be done: i. before or after cutting the strip or plate; or ii. as part of full-body inspection completed on the formed pipe. J.3.3.2.5 Delete this clause. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 67 J.4.1 Chemical Composition J.4.1.1 Replace the first sentence with the following: 1. Table J.1 (non sour service) shall apply for all pipe grades and for pipe with t ≤ 35 mm (1.38 in). 2. The Manufacturer/Supplier’s target product analysis shall be shown in the Manufacturing Procedure Specification. 3. A single value target of CEiiw or CEpcm shall be stated. 4. The range of elements shall be such that the variation in the single value target CEiiw does not exceed ± 0.03 units or CEpcm does not exceed ± 0.02 units with the following additional restrictions: Table J.4 Elements Tolerances The figures in Table J.4 represent the total range and not a plus or minus tolerance. 5. There shall be no changes in the chemical composition (within the tolerances listed in Table J.4) from the approved WPS composition. 6. No intentionally added elements shall be removed or increased beyond the limits in Table J.4. 7. The chemical composition recorded for the pipes used in first-day production testing shall set the datum CE. 8. All elements listed in Table H.1 shall be reported. J.4.1.2 Replace this clause with the following. 1. For pipe with t > 35 mm (1.38 in) the chemical composition shall be subject to approval of the Principal, with the requirements given in Table J.1 being amended as applicable. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 68 J.6 Tolerances for diameter, wall thickness, length and straightness Table J.3 – Tolerances for diameter and out-of-roundnessModify Table J.3 as follows: 1. The pipe end out-of-roundness for pipe > 610 mm (24 in) diameter and with D/t < 75 shall be 0.0075D with a maximum of 6 mm (0.25 in). Where required by the order form, tighter tolerances on pipe end out-of-roundness and internal diameter might apply. Replace Note c) with the following: 1. For pipe with D ≥ 219.1 mm (8.63 in), the diameter tolerance and out of roundness shall be determined using the measured inside diameter. 2. The OD OOR requirements shall be maintained. 3. Pipe end rectification may be applied to achieve diameter and OOR tolerance, subject to review and approval of the rectification procedure by the Principal. Add new clause: J.6.5 Surface condition of pipe ends 1. The outer surface of the pipe, for a distance of 200 mm (8 in) from each pipe end, shall permit the use of AUT examination of circumferential joints during pipeline installation. 2. There shall be no pitting in the outer surface of the pipe, for a distance of 200 mm (8 in) from each pipe end greater than 0.25 mm (0.001 in) in depth. 3. The surface finish of the pipe measured during the MPQ shall be the agreed surface finish for all production pipes. J.7 Tolerances for the weld seam J.7.1 Radial offset of strip/plate edges Delete clause and replace with the following: 1. The radial offset of strip/plate edges shall be in accordance with (9.13.1). J.8 Inspection J.8.1 Specific inspection Table J.6 – Inspection frequency Add note: 1. Higher frequencies of inspection for pipe end internal diameter and out-of roundness may be specified in the order form. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 69 J.8.2 Samples and test pieces for mechanical and technological tests J.8.2.2 Test pieces for CTOD test Replace this clause and with the following. 1. Test pieces shall be taken in accordance with (10.2.3.8). Table J.7 – Number, orientation and location of test pieces per sample for mechanical tests Modify this table as follows: 1. For pipe of D ≥ 219.1 mm (8.63 in), longitudinal and transverse pipe body tensile tests are required at the frequency of testing given for transverse pipe body tests (as modified by J8.1). 2. The acceptance criteria for longitudinal pipe body tensile tests shall be as for the transverse tests. J.8.3 Test methods J.8.3.1 CTOD test Replace this clause with the following: J.8.3.2 1. CTOD testing shall be performed in accordance with ISO 12135. 2. The CTOD test temperature shall be the minimum design temperature as stated in the order form. 3. The minimum CTOD value (from a set of three specimens) taken from each of the pipe, weld and HAZ locations, shall be 0.25 mm (0.0098 in), tested at the minimum design temperature given in the order form. Hardness test J.8.3.2.1 Replace the first two paragraphs with the following: 1. Hardness testing shall be performed using the Vickers test in accordance with ISO 6507-1 or ASTM E384, Figure J1 Location of hardness tests Amend note b) as follows: 0.50 mm (0.02 in) from fusion line Modify drawings a, b and c with: 2. Surface hardness indentation shall be on a line not greater than 1.5 mm (0.06 in) from the inside and outside surfaces. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 70 Annex K (normative) Non-destructive inspection for pipe ordered for sour and/or offshore service K.2 General non-destructive inspection requirements and acceptance criteria K.2.1 Laminar imperfections at the pipe ends K.2.1.2 Delete this clause. K.2.1.3 Remove words “If agreed” Add the following: 1. This may be undertaken from the outside surface if the pipe end is inspected before weld beveling. 2. If inspection is after weld beveling, this shall be undertaken from the pipe internal surface. K.2.1.4 Add the following: 1. K.2.2 When specified in the order form, the end face/bevel at each pipe end shall be magnetic particle inspected for the detection of laminar imperfections. Suspect pipe K.2.2.4 Replace this clause with the following: 1. Where dressing is carried out, complete removal of defects and the remaining wall thickness shall be verified by local visual inspection and by aNDT method. K.3 Non-destructive inspection of SMLS pipe K.3.1 Ultrasonic inspection for longitudinal imperfections Replace this clause and with the following: 1. All SMLS pipe shall be non-destructively inspected full length (100%) per ISO 10893-10 (longitudinal and transverse imperfections), as given in Table E.2. 2. Acceptance limits shall be as per Table E.8 of this DEP. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 71 K.3.2 Laminar imperfections in the pipe body K.3.2.1 Replace this clause with the following: 1. For sour service, individual laminations and/or lamination densities exceeding the acceptance limits for sour service given in Table K.1 shall be classified as defects. 2. Compliance with (K.3.2.1, item 1) shall be verified by ultrasonic inspection in accordance with ISO 10893-8:2011 (except 5.2). 3. The coverage during automatic inspection shall be 100% of the pipe surface. K.3.2.2 Replace this clause with the following: K.3.4 1. For offshore service, individual laminations and/or lamination densities exceeding the acceptance limits for offshore service given in Table K.1 shall be classified as defects. 2. Compliance with (K.3.2.2, item 1) shall be verified by ultrasonic inspection in accordance with ISO 10893-8 2011 (except 5.2). 3. The coverage during automatic inspection shall be ≥ 50% of the pipe surface. Supplementary non-destructive inspection Table K.1 Acceptance criteria for laminar imperfections 1. In Table K.1 under Service Condition column “Sour, if agreed” delete “if agreed” (i.e., this applies for all sour service pipe). K.4 Non-destructive inspection of HFW pipe K.4.1 Non-destructive inspection of the weld seam Replace this clause with the following: K.4.2 1. The full length of the weld seam shall be ultrasonically inspected for the detection of longitudinal imperfections, with the acceptance limits being in accordance with Table E.8 of this DEP. 2. The probe per weld distribution shall be in accordance with Table E.7.1 of this DEP. Laminar imperfections in the pipe body Replace this clause with the following: K.4.2.1 General 1. K.4.2.2 For sour surface applications 1. K.4.2.3 The pipe or strip/plate body shall be ultrasonically inspected for the detection of laminar imperfections in accordance with ISO 10893-8:2011 (except 5.2) or ISO 10893-9:2011 (except 5.2), respectively, to acceptance limits for the relevant application as given in Table K.1. For strip/plate and pipe examination, the coverage during automatic inspection shall be 100% of the pipe surface. For offshore, non sour, applications 1. The level of coverage shall be ≥ 50% of the pipe or plate/strip surface. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 72 K.4.3 Laminar imperfections on the strip/plate edges or areas adjacent to the weld seam Replace this clause with the following: K.4.4 1. The strip/plate edges or the areas adjacent to the weld seam shall be ultrasonically inspected over a width of 25 mm (1 in) for the detection of laminar imperfections, in accordance with ISO 10893-8:2011 or ISO 10893-9. 2. The acceptance limits of the ultrasonic inspection shall be as given in Table K.1. Supplementary non-destructive inspection Delete this clause. K.5 Non-destructive inspection of SAW pipe K.5.1 Ultrasonic inspection for longitudinal and transverse imperfections in seam welds K.5.1.1 Replace this clause with the following: 1. 2. The full length of the weld seams of SAW pipe shall be ultrasonically inspected for the detection of longitudinal and transverse imperfections in accordance with ISO 10893-11:2011 acceptance level U2, with the following modifications: a. The notch depth shall be ≤ 2.0 mm (0.080 in). b. Internal and external longitudinal notches located on the centre of the weld seam shall not be used for equipment standardization purposes. c. The sensitivity of the longitudinal imperfection detection probes shall be adjusted on the radially drilled hole, as per Table E.7.2. d. As an alternative to the use of the reference hole for equipment calibration for the detection of transverse imperfections, acceptance level U2 internal and external notches lying at right angles to, and centered over, the weld seam may be used. e. In the case of (K.5.1.1 item 1d), the Manufacturer may grind both the internal and external weld reinforcements to match the pipe contour in the immediate area and on both sides of the reference notches. f. The refernce notches shall be sufficiently separated from each other in the longitudinal direction and (if ground flush) from any remaining reinforcement, to give clearly identifiable separate ultrasonic signal responses. g. The full signal amplitude from each notch shall be used to set the trigger/alarm level of the equipment. h. The manufacturer may apply the provisions of (K.5.3) to retest the suspect areas. The probe per weld zone distribution shall be in line with Table E.7.2 of this DEP. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 73 K.5.1.2 Delete this clause. K.5.1.3 Delete this clause. K.5.2 Laminar imperfections in the pipe body and on the strip/plate edges K.5.2.1 Replace this clause with the following: K.5.2.1.1 General 1. K.5.2.1.2 The pipe or strip/plate body shall be ultrasonically inspected for the detection of laminar imperfections in accordance with ISO10983-9:2011 (except 5.2) to acceptance limits given in Table K.1 with the following coverage requirements: For sour surface applications: 1. K.5.2.1.3 For strip/plate and pipe examination, the coverage during automatic inspection shall be 100% of the pipe surface. For offshore, non-sour applications: 1. The required levels of coverage for plate/strip and pipe shall be ≥ 50% of the pipe surface. K.5.2.2 Replace this clause with the following: K.5.3 1. The strip/plate edges or the areas adjacent to the weld seam shall be ultrasonically inspected over a width of 25 mm (1 in) for the detection of laminar imperfections, in accordance with ISO 10893-8:2011 or ISO 10893-9:2011. 2. The acceptance limits of ultrasonic inspection shall be as given in Table K.1. Non-destructive inspection of the weld seam at the pipe ends/repaired areas Replace this clause with the following: 1. 2. The length of weld seam at pipe ends that cannot be inspected by the automatic ultrasonic equipment and repaired areas of the weld seam (see Clause C.4) shall be subjected to the following: a. For the detection of longitudinal imperfections, semi-automatic or manual ultrasonic inspection using the same inspection sensitivity and inspection parameters as is specified in (K.5.1.1) and radiographic inspection in accordance with Clause E.4. b. Manual ultrasonic inspection may be approved by the Principal as an interim measure if the manufacturer installs an automatic or semi automatic system within an agreed time frame. c. For the detection of transverse imperfections, automatic or semi-automatic ultrasonic inspection using the same inspection sensitivity and parameters as is specified in (K.5.1.1) and radiographic inspection in accordance with (E.4). For manual ultrasonic inspection, the maximum scanning speed shall be 150 mm/s (6 in/s). This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 74 K.5.4 Supplementary non-destructive inspection operation Add the following: 1. Each pipe shall be tested over the final 25 mm (1 in) at each end with UT using a 45° shear wave probe to disclose axially aligned, through-thickness cracks. 2. The manufacturer may perform the examination in (K.5.4, item 1) on the ends of the plate ends prior to forming/welding. 3. There shall be no cracks a. Any cracked areas shall be cut-off and the pipe end re-tested. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 75 Annex M (normative) Pipe ordered for European onshore natural gas transmission lines Delete this annex. This Appendix is not applicable for Shell pipelines in Europe unless specified in individual order forms. th This Appendix is blank in API SPEC 5L 45 Edition. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 76 PART IV REFERENCES In this DEP, reference is made to the following publications: NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used, together with any amendments/supplements/revisions thereto. 2. The DEPs and most referenced external standards are available to Shell staff on the SWW (Shell Wide Web) at http://sww.shell.com/standards/. SHELL STANDARDS DEP feedback form DEP 00.00.05.80-Gen. Definition of temperature, pressure, and toxicity levels DEP 01.00.01.30-Gen Evaluation of pipeline and pressure vessel steels for resistance to hydrogen-induced cracking (amendments/supplements to NACE TM0284) DEP 30.10.02.16-Gen. Pipeline engineering (amendments/supplements to ISO 13623) DEP 31.40.00.10-Gen. Line pipe induction bends (amendments/supplements to ISO 15590-1) DEP 31.40.20.33-Gen. Welding of deepwater pipelines, flowlines, and steel catenary risers (amendments and supplements to API 1104) DEP 37.81.40.31-Gen. Welding of pipelines and related facilities (amendments/supplements ISO 13847:2000) DEP 61.40.20.30-Gen. Project quality assurance DEP 82.00.10.10-Gen. Shell HSSE & SP Control Framework, Design Engineering Manual (DEM) 1 – Application of Technical Standards https://eu001sp.shell.com/sites/AAAAA8432/CF/Web/Design Engineering Manual 1 DEM1.aspx DEM 1 Pipe, Valves and Fittings - Piping Classes, (Upstream Field Facilities) Shell STD. 3-1.12 AMERICAN STANDARDS Standard test methods and definitions for mechanical testing of steel products ASTM A370 Standard test method for knoop and vickers hardness of materials ASTM E384 Standard test method for crack-tip opening displacement (CTOD) fracture toughness measurement ASTM E1290 Standard practice for preparation and use of bent-beam stresscorrosion test specimens ASTM G39 Recommended practice for care and use of cable drilling and fishing tools API RP3 th Specification for Line Pipe – 45 Edition; Effective Date: July 1, 2013 API SPEC 5L This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 77 CANADIAN STANDARDS Steel Pipe - Eighth Edition CSA Z245.1-07 Oil and gas pipeline systems - Sixth Edition CSA Z662-11 ERCB directive 56 Alberta Pipeline Act and Regulations British Columbia Oil and Gas Activities Act B.C. Reg. 281/2010 Pipeline and Liquefied Natural Gas Facilities Regulation EUROPEAN STANDARDS Guidelines on materials requirements for carbon and low alloy steels for H2S-containing environments in oil and gas productionIssued by: European Federation of Corrosion EFC 16 INTERNATIONAL STANDARDS Petroleum and natural gas industries — Steel pipe for pipeline transportation systems ISO 3183 Metallic materials Vickers hardness test Part 1: Test method ISO 6507-1 Metallic materials – Tensile testing at ambient temperature ISO 6892 Corrosion of metals and alloys - Stress corrosion testing – Part 2: Preparation and use of bent-beam specimens ISO 7539-2 Specification and approval of welding procedures for metallic materials – Part 3: Welding procedure tests for the arc welding of steels ISO 9956-3 Quality management systems — Requirements ISO 9001 Quality management systems – Guidelines for quality plans ISO 10005 Non-destructive testing of steel tubes - Part 7: Digital radiographic testing of the weld seam of welded steel tubes for the detection of imperfections ISO 10893-7 Non-destructive testing of steel tubes - Part 8: Automated ultrasonic testing of seamless and welded steel tubes for the detection of laminar imperfections ISO 10893-8 Non-destructive testing of steel tubes - Part 9: Automated ultrasonic testing for the detection of laminar imperfections in strip/plate used for the manufacture of welded steel tubes ISO 10893-9 Non-destructive testing of steel tubes - Part 10: Automated full peripheral ultrasonic testing of seamless and welded (except submerged arc welded) steel tubes for the detection of longitudinal and/or transverse imperfections ISO 10893-10 Non-destructive testing of steel tubes - Part 11: Automated ultrasonic testing of the weld seam of welded steel tubes for the detection of longitudinal and/or transverse imperfections ISO 10893-11 Metallic materials Unified method of test for the determination of quasistatic fracture toughness ISO 12135 Petroleum and natural gas industries – Pipeline transpiration systems ISO13623 Petroleum and natural gas industries — Materials for use in H2Scontaining environments in oil and gas production — Part 2: Cracking- ISO 15156-2 This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 78 resistant carbon and low-alloy steels, and the use of cast irons Metallic materials — Method of test for the determination of quasistatic fracture toughness of welds BSI BS EN ISO 15653 Petroleum and natural gas industries – Induction bends, fittings and flanges for pipeline transportation systems – Part 1, Induction bends ISO 15590-1 NORWEGIAN STANDARDS Offshore standard, Submarine pipeline systems DNV OS-F101 This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 79 APPENDIX 1 1.1 LINE PIPE SUBJECTED TO HIGH STRAIN GENERAL The following requirements are additional to those specified for PSL2 pipe ordered for th offshore service by ISO 3183:2012 and API SPEC 5L 45 Edition (Annex J) and this DEP. The requirements in this Appendix apply for pipe or pipelines for use in the following applications: • Deepwater applications • Reeled installations • Pipe for pipelines subject to a single high strain event, where (elastic + plastic) in any direction is > 1.0% or accumulated strain is > 2%, during installation or operation. These conditions apply to all pipelines subjected to high strain, whether onshore or offshore, at pipe grades up to and including L450. 1. For pipe proposed for installation by reeling, reelability data shall be provided for the pipe proposed and include previous data for pipe in terms of the same pipe grade, dimensions, manufacturing process, chemical composition, and heat treatment. 2. The reelability data shall be provided before and after reeling trials/simulations including but not limited to stress/strain curves, fatigue, toughness, hardness, yield, tensile, and yield/tensile ratios. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 80 1.2 MECHANICAL PROPERTIES 1. The results of all longitudinal tensile tests shall conform to the requirements of Table J.2 with the following modifications: a. Non proportional tensile specimens with 50 mm (2 in) gauge length should be used. b. Where specified in order forms, the proportional type shall be used in accordance with ISO 6892. i. 2. 3. c. The yield strength shall not exceed the specified minimum value by more than 120 MPa (17,405 psi) or vary more than 100 MPa (14,505 psi) from the agreed MPS value; d. The ratio of yield to tensile strength shall not exceed 90%; e. The elongation shall not be less than 20%. One set of longitudinal Charpy impact specimens shall be taken at a frequency of one set per test unit from the pipe body. a. The Charpy impact specimens shall be through-thickness notched and located at mid-thickness. b. The minimum Charpy impact energy shall be 100 J (75 ft-Ibf) average and 80 J (60 ft-Ibf) individual. c. The testing temperature shall be as given in Table 8, unless otherwise specified on the order form. For the manufacturing procedure qualification test, the longitudinal tensile and Charpy impact tests shall be carried out in both the as-received condition and after a heat treatment simulating thin-film coating. a. 4. For proportional type, the gauge length shall be equal to 5.65S0, where S0 is the original cross-sectional area of the specimen; The heat treatment shall consist of holding at 250 °C (480 °F) for a minimum of 10 minutes, unless otherwise specified on the order form. When required by the the Principal, all production longitudinal tensile and Charpy impact test shall receive the same heat treatment prior to testing. This decision by the Principal is dependent on the results of the manufacturing qualification test. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 81 1.3 STRAIN AGED TESTING 1. The following shall form part of the manufacturing procedure qualification test for each combination of diameter and wall thickness. a. For reeling applications, two samples of pipe shall be subject to a longitudinal plastic strain of 3% per the following cycles: i. Sample 1: Start in tension strain – Finish in compression strain 3 times. ii. Sample 2: Start in compression strain - Finish in tension strain 3 times. b. For single high strain events (see (Appendix 1, Section 1.1)), samples of pipe body shall be subjected to a longitudinal, uni-axial strain of 3.0% (or greater if stated in the order form). c. A sufficient number of strain gauges shall be used to verify even straining. Refer to DNV F101 – Appendix B: A1200. 2. d. Samples of the longitudinal seam weld (SAW and HFW pipe) shall besubjected to uni-axial straining to 3.0% strain (unless otherwise stated in the order form) transverse to the seam. e. After straining, the samples shall be aged at 250 °C (480 °F) for one hour. The following mechanical tests shall be performed: a. b. Pipe body: i. Two longitudinal tensile tests; ii. One set of three longitudinal Charpy impact tests ; iii. One through thickness hardness survey (HV10), per Fig J.1.a). Weld seam: i. One all-weld tensile test (SAW only); ii. Four sets of Charpy impact tests at weld, fusion line, fusion line+2 mm (0.08 in) and fusion line +5 mm (0.2 in) in accordance with 10.2.3.3; iii. One hardness survey (HV10) per Fig J.1 b) or c). 3. The impact test temperature shall be as specified for the unstrained tests. 4. The acceptance criteria for all mechanical tests shall be as specified for the unstrained tests. a. Yield/tensile ratio may be increased by up to 4% points (or higher if approved by the Principal). 5. Where required by the Order Form, SSC testing shall be performed on samples after undergoing straining and aging. 6. HFW pipe intended for reeling shall be subjected to one of the following heat treatments: a. Full body quench and temper; or b. Weld seam online quench followed by full body temper. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 82 APPENDIX 2 2.1 WELDABILITY OF PSL2 PIPE GENERAL 1. Weldability trials on the pipe material shall be carried out for all offshore pipelines, all pipelines greater than 0.5% strain, and where otherwise specified in the Order form. The intent of the weldability tests is to verify adequate properties in the girth weld HAZ. a. Weldability tests shall be performed by the pipe manufacturer. b. Weldability tests may be performed by the installation contractor if agreed by the Principal. Weldability performed by the installation contractor runs the risk of material being received that is not suitable for the project. 2.2 2. The pipe material shall be as qualified in the manufacturing procedure qualification (Annex B) and within the limits specified in (B.5), as modified by this DEP. 3. One trial each shall be carried out at the minimum and maximum heat inputs as detailed below at the minimum and maximum wall thicknesses to be produced, or as agreed with the Principal. 4. Data from previous weldability trials may be accepted by the Principal, in whole or part, in lieu of testing. 5. Where the Principal allows data from previous wedability trials in leu of testing, material used in the previous weldability trials shall be identical in grade and manufacturing procedure to the pipe to be supplied and be of similar diameter, wall thickness and chemical composition (within the limits of Annex H table H.1). WELDING 1. Girth welds shall be carried out in accordance with welding procedure specifications representative of those used by installation contractors and subject to approval by the Principal. However, the pipe is normally roll welded (1G) so as to ensure a consistent and even heat input. 2. A Welding Procedure Specification (WPS) prior to welding and a Procedure Qualification Record (PQR) after welding and testing shall be provided. Guidance on welding procedure and testing requirements is given in DEP 61.40.20.30-Gen. and DEP 37.81.40.31-Gen. For requirements around the production of girth welds, refer to DEP 61.40.20.30-Gen. and DEP 37.81.40.31-Gen. 3. Welds shall be produced by the mechanized/automatic GMAW process or SAW process with arc energies for each weld pass of 0.5 kJ/mm and 2.0 kJ/mm (unless otherwise stated on the order form) so as to cover the lower and upper heat input ranges of typical weld procedures. a. The upper and lower heat inouts should be consistent throughout the weld (i.e., each weld pass should have the same heat input). 4. Welding techniques shall be utilized that results in a straight HAZ on a square edge side of the weld grove (i.e., a bevel with one side square, the other side bevelled). 5. The HAZ shall be considerd sufficiently straight when scribed marks for the machining of fracture toughness specimen notches sample at least 80% of the scribe length in the central 60% of the specimen thickness within 0.5 mm of the fusion line. The 80% need not be continuous. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 83 2.3 6. For the purpose of the criteria in (2.2, item 5), the fusion line shall be considered part of the weld metal and not be included in the determination of % HAZ sampled. 7. Weld bead placement techniques shall be utilized such that within the central 60% of the section thickness, 25% of the weld metal adjacent to the fusion line on the square edge side of the weld grove is unrefined-columnar weld metal. 8. At least one full butt weld shall be produced for each trial. 9. When additional welds are required to be supplied for testing conducted by the Principal, the number and dimensions of these weld test pieces shall be stated in the purchase order. MECHANICAL AND CORROSION TESTING 1. Mechanical testing of the weld and heat affected zone (HAZ) shall be as follows: a. Cross Weld Tensile. i. b. c. d. Fracture shall be in the base material. Cross macro and weld hardness survey. i. The survey shall be performed 1.5 mm (+0 -0.5) below the OD and ID surfaces and mid wall with indentations spaced at 0.5 mm (0.02 in) into the base unaffected material. ii. The initial indentation shall be within one diamond indentation of the fusion line on the straight edge. iii. The maximum shall be 275 HV10 except where sour service is applied. iv. Where sour service is applied, the maximum shall be 250 HV10. Charpy and Charpy transition in both the HAZ within 0.5 mm (0.02 in) of the fusion line and at the edge of the visible HAZ. i. Charpy acceptance criteria shall be as per the base material and (unless otherwise stated in the order form) Charpy test temperature shall be - 20 °C (- 4 °F). ii. There shall be a transition curve for each of the test areas. CTOD in both the HAZ within 0.5 mm (0.02 in) of the fusion line and at the edge of the visible HAZ. i. CTOD shall be performed. ii. Sectioning of CTOD samples should be made following testing to ensure sampling of the required areas. iii. Pre and post macro-graphs should be supplied to show sampling requirements have been met. iv. CTOD acceptance criteria shall be as per the base material and (unless otherwise stated in the order form) CTOD test temperature shall be - 10 °C (14 °F). This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 84 2. Fracture toughness testing shall be carried out for the weld, fusion line and HAZ for each weld heat input as follows: a. b. For elastic design: i. SENB CTOD specimens shall be used. ii. For weld metal specimens, the fatigue crack tip shall sample 100% of the weld metal and be within 1 mm - 2 mm from the fusion line. iii. For HAZ specimens, the fatigue crack tip shall sample at least 50% of the fusion line. iv. A minimum CTOD value of 0.25 mm (0.01 in) shall be achieved in all tests. v. For SCR pipe, the minimum allowable CTOD shall be 0.51 mm (0.02 in). For high strain: i. Testing for high strain design shall be performed following application of straining and ageing per (Appendix 1). 1). CTOD testing may be either single specimen or multiple specimen, as indicated on the order form. 2). For multiple specimen CTOD testing, at least 6 CTOD specimens (SENB or SENT or both, as stated in the Order form) shall be tested, and an R-curve for the HAZ produced. 3). The design temperature relevant to CTOD and impact testing shall be as stated in the order form. ii. Where required by the order form, corrosion (SSC) testing shall be carried out in accordance with section 6.8 of DEP 61.40.20.30-Gen. 1). The specimen thickness shall be t or 15 mm (0.6 in), whichever is less. 2). Specimens not exhibiting surface cracking after testing shall be evaluated for resistance to SOHIC in accordance with ISO 15156-2, clause B.4.2.3: A). Two longitudinal metallographic sections shall be taken from each SSC specimen. 3). There shall be no ladder-like HIC features or cracks exceeding a length of 0.5 mm (0.02 in) in the through thickness direction. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 85 APPENDIX 3 3.1 LINE PIPE FOR DEEPWATER PROJECTS, INCLUDING STEEL CATENARY RISERS SCOPE This appendix, when stated on the order form or project documentation, specifies the requirements for line pipe used on deepwater projects. These requirements are in th addition to those specified in this DEP, ISO 3183:2012 and API SPEC 5L 45 Edition. 3.2 1. The requirements of Annex J and Appendices 1 and 2 shall apply to all pipes for deepwater projects unless specifically stated otherwise on order forms for specific projects. 2. When specified in the order form or project documentation for sour service the requirements of (Annex H), as modified by this DEP, shall also apply. GENERAL 1. The results of all longitudinal tensile tests shall conform to the requirements of Table J.2 with the following modifications: a. Non proportional tensile specimens with 50 mm (2 in) gauge length should be used. b. Where specified in order forms, the proportional type tensile specimens shall be in accordance with ISO 6892. c. For proportional type tensile specimens the gauge length shall be equal to 5.65S0, where S0 is the original cross-sectional area of the specimen; d. The yield strength shall not exceed the specified minimum value by more than 120 MPa (17,405 psi) or vary more than 100 MPa (14,505 psi) from the agreed MPS value; e. For seamless pipe, all billets and slabs shall be scarfed or peeled prior to rolling or forming unless otherwise approved by the Principal after review and evidence of the billet or slab surface quality. f. Continuous cast rounds shall be conditioned to the Manufacturer’s specifications. g. Pipe straightness and length shall be measured and recorded for each pipe. h. Unless otherwise stated by the Principal, 85% of pipe shall be in the range 11.9 m – 12.5 m (39 ft – 41 ft) with the remaining 15% in the range of 11.6 m –12.8 m (38 ft – 42 ft). i. The wall thickness negative tolerance shall be -5%. j. The wall thickness positive tolerance for seamless pipe shall be +15%. k. For welded pipe the tolerance shall be -5% - +10 %. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 86 3.3 3.4 ADDITIONAL TESTING FOR SAW PIPE 1. During first day production, Manufacturer shall perform circumferential compressive stress tests. 2. A compressive stress-strain curve shall be developed. 3. The units used on each axis of each compressive stress-strain curve shall be clearly identified. 4. The compressive stress-strain curves shall cover a range of at least -2.0% strain. 5. During first day production, Manufacturer shall perform ring splitting residual stress tests. 6. If residual stresses are greater than 25% of SMYS, the Principal shall be informed in order to have the pipe collapse tested. WELDABILITY TEST 1. Weldability testing shall be in accordance with (Appendix 2). 2. CTOD requirements are as follows: 3. 3.5 a. For SCR pipe: Minimum allowable CTOD shall be 0.51 mm (0.02 in) b. For flowlines and high strain testing: minimum allowable CTOD shall be 0.25 mm (0.01 in) The Charpy impact test temperature shall be at a minimum of -20 °C (-4 °F) and CTOD at a minimum of 0 °C (32 °F). PIPE ENDS 1. Pipe ends shall be either bevelled or square cut, as required by the order form. 2. When a bevel angle is specified, the plus or minus tolerance shall be 2 1/2°, unless otherwise specified. 3. Root face shall be as described by Clause 9.12.5.2 of ISO 3183:2012 th /API SPEC 5L 45 edition, except the following: a. There shall be no internal bevel resulting from removal of the internal burr. 4. The inside diameter of each end of each pipe for a distance of 102 mm (4 in) from the end shall be as specified in Table J.3, but not be more than 1.6 mm (0.063 in) larger, nor more than 1.6 mm (0.063 in) smaller than specified, as measured with inside calipers, inside micrometers, a rod gauge, or similar device. 5. For SCR applications the inside diameter of each end of each pipe for a distance of 102 mm (4 in) from the end, shall not be more than 1.6 mm (0.063 in) larger, nor more than 1.6 mm (0.063 in) smaller than specified. 6. The inside diameter at the ends may be machinedwith the termination of the machining parallel over 200 mm (8 in) of the pipe, and all wall thickness tolerances maintained. 7. If end machining is required to meet the tolerances in (3.5 item 5), the Manufacturer shall submit a procedure to the Principal for approval. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 87 3.6 3.7 NON-DESTRUCTIVE INSPECTION 1. After all manufacturing and heat treatment procedures have been completed on seamless pipe, the entire steel volume of each length of pipe (100%) shall be inspected by both ultrasonic and electromagnetic methods in accordance with this th DEP and Annexes E and K of ISO 3183:2012/API SPEC 5L 45 edition, and the additional requirements of this section. 2. Prior to edge preparation and forming, all plate (100%) for SAW pipe shall be subjected to an ultrasonic examination in accordance with this DEP and Annexes E th and K of ISO 3183:2012/API SPEC 5L 45 edition to detect discontinuities parallel to the rolled surfaces. 3. The ultrasonic examination may be performed after the pipe fabrication is complete. 4. All weld seams for SAW pipe shall be inspected full length (100%) by ultrasonic examination in accordance with this DEP and Annexes E and K of th ISO 3183:2012/API SPEC 5L 45 edition. 5. For steel catenary riser pipe, the ultrasonic testing equipment shall be qualified and approved in accordance with Shell Quality Services’ TC 11.1 Rev. 1 (16 August 2001) “Quality Services’ Process for Performing UT/EMI System Capability Study”. 6. Each length of pipe shall be measured along the full length for wall thickness. 7. There shall be no laminations within 150 mm (6 in) of the pipe ends. WORKMANSHIP 1. The pipe shall contain no dents that affect both the outside surface and the inside surface. 2. The pipe shall contain no dent on the outside surface with a depth exceeding 1.6 mm (0.063 in) for seamless pipe and 0.8 mm (0.03 in) for SAW pipe. a. 3. For the whole order, there shall be no more than 0.5% of the pipe welds repaired (excluding minor surface indications repaired by grinding only). a. 3.8 Dents shall not be pounded out or jacked out. Individual repair by welding shall not be performed more than once. MARKING AND COATING 1. Refer to the order form for any additional marking requirements, including the requirement for marking in US units and conformance to US anti-dumping regulations. This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 88 APPENDIX 4 PROCEDURE REQUIREMENTS FOR NDT Table 4.1 Inspection process essential variables This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26 DEP 31.40.20.37-Gen. February 2017 Page 89 APPENDIX 5 LINE PIPE ORDER FORM This document has been supplied under license by Shell to: Worley Parsons Oman Engineering LLC altaf.patel@worleyparsons.com 09/10/2018 08:20:26