INSPECTION & TEST PLAN
CONSTRUCTION OF PETROLEUM INSTITUTE
RESEARCH CENTERAT SAS AL NAKHL
PROJECT NO. 6012 - AGREEMENT NO. 116012C1
ACTIVITY:
INSTALLATION OF AIR HANDLING UNITS & FRESH AIR HANDLING UNITS
AREA/LOCATION:
PI Building Phase 1A
ITP approved by CONTRACTOR's QA/QC:
ITP approved by COMPANY:
Signature:
Signature:
Date:
REF. NO. ITP-6012-0101
REV. NO.
02
DATE :
04.03.2014
PAGE :
1 OF 1
Date:
SERIAL NO.
1
DESCRIPTION
FREQUENCY
Once (Approval
prior to start of
activity)
Specs. DIV 23, Section 237300, Item 1.5. Submittals. (1.5.1 Product Data: As per Approved
MAR Ref. No. M0056 Rev.02: Sumbit manufacturer's technical product for air handling units
showing dimensions, weights, capacities,ratings fan performace with operating pointclearly
indicated, motor electrical characteristics, gages and finishes of materials, and installation
instruction.
CONT.
COMPANY
VERIFICATION
RECORD
H
H
R
Approved MAR
H
H
R
Approved DTF
All forms (MS, QCP, ITP, Check list & Risk Assesstment) as per Annexure "K" of agreement.
H
H
R
Approved DTF
As Per Specs. Book 3 of 4, DIV 23, Section 237300 Item 2 (Products)/ MAR #. M-0056 Rev.02
(AHU & FAHU): Incorporate comments on the Approved MAR.
H
H
H
MVR Approval
As per approved shop drawings.As Per Specs. Book 3 of 4, DIV 23, Clause 237300 Item 3.
(Execution). Clause 3.1. (Installation). Install as shown on the drawings, as detailed, and
according to AHU manufacturer's installation instructions.
H
H
H
ITR, Check List FM 6012-0101 Rev 02
Specs. DIV 23, Section 237300, Item 1.5. 1.5.2 Shop Drawing: Submit assembly type shop
Each Shop Drawing drawing showing unit dimensions, weight, loadings, required clearances, construction details, and
filed connection details.
1.2 Shop Drawing Approval
Once (Approval
prior to start of
activity)
1.3 Method Statement Approval
MATERIAL INSPECTION
2.1 Check the Material as per approved submittal.
3
INSPECTION LEVEL
SUBCON
DOCUMENTATION
1.1 Material Approval
2
SPECIFICATION/CRITERIA
Each Delivery
INSTALLATION INSPECTION
Check the installation as per approved drawing. Check the physical
3.1 Installation of equipment.
LEGEND:
Area Wise or As
instructed by
Company.
H: HOLD
W10: WITNESS 10%
W100: WITNESS 100%
ITP Sign-Off post completion of Works
CONTRACTOR APPROVAL
COMPANY APPROVAL
NAME :
NAME :
SIGN :
SIGN :
DATE:
DATE:
PAGE 1 of 1
S: SURVEILLANCE
R: REVIEW