INSPECTION & TEST PLAN CONSTRUCTION OF PETROLEUM INSTITUTE RESEARCH CENTERAT SAS AL NAKHL PROJECT NO. 6012 - AGREEMENT NO. 116012C1 ACTIVITY: INSTALLATION OF AIR HANDLING UNITS & FRESH AIR HANDLING UNITS AREA/LOCATION: PI Building Phase 1A ITP approved by CONTRACTOR's QA/QC: ITP approved by COMPANY: Signature: Signature: Date: REF. NO. ITP-6012-0101 REV. NO. 02 DATE : 04.03.2014 PAGE : 1 OF 1 Date: SERIAL NO. 1 DESCRIPTION FREQUENCY Once (Approval prior to start of activity) Specs. DIV 23, Section 237300, Item 1.5. Submittals. (1.5.1 Product Data: As per Approved MAR Ref. No. M0056 Rev.02: Sumbit manufacturer's technical product for air handling units showing dimensions, weights, capacities,ratings fan performace with operating pointclearly indicated, motor electrical characteristics, gages and finishes of materials, and installation instruction. CONT. COMPANY VERIFICATION RECORD H H R Approved MAR H H R Approved DTF All forms (MS, QCP, ITP, Check list & Risk Assesstment) as per Annexure "K" of agreement. H H R Approved DTF As Per Specs. Book 3 of 4, DIV 23, Section 237300 Item 2 (Products)/ MAR #. M-0056 Rev.02 (AHU & FAHU): Incorporate comments on the Approved MAR. H H H MVR Approval As per approved shop drawings.As Per Specs. Book 3 of 4, DIV 23, Clause 237300 Item 3. (Execution). Clause 3.1. (Installation). Install as shown on the drawings, as detailed, and according to AHU manufacturer's installation instructions. H H H ITR, Check List FM 6012-0101 Rev 02 Specs. DIV 23, Section 237300, Item 1.5. 1.5.2 Shop Drawing: Submit assembly type shop Each Shop Drawing drawing showing unit dimensions, weight, loadings, required clearances, construction details, and filed connection details. 1.2 Shop Drawing Approval Once (Approval prior to start of activity) 1.3 Method Statement Approval MATERIAL INSPECTION 2.1 Check the Material as per approved submittal. 3 INSPECTION LEVEL SUBCON DOCUMENTATION 1.1 Material Approval 2 SPECIFICATION/CRITERIA Each Delivery INSTALLATION INSPECTION Check the installation as per approved drawing. Check the physical 3.1 Installation of equipment. LEGEND: Area Wise or As instructed by Company. H: HOLD W10: WITNESS 10% W100: WITNESS 100% ITP Sign-Off post completion of Works CONTRACTOR APPROVAL COMPANY APPROVAL NAME : NAME : SIGN : SIGN : DATE: DATE: PAGE 1 of 1 S: SURVEILLANCE R: REVIEW