Charter Hall 121-127 Harrington Street Fire Engineering Report 221298 Issue | March 2011 Arup Arup Pty Ltd ABN 18 000 966 165 Arup Level 10 201 Kent Street Sydney NSW 2000 www.arup.com This report takes into account the particular instructions and requirements of our client. It is not intended for and should not be relied upon by any third party and no responsibility is undertaken to any third party. Job number 221298-00 Document Verification Job title Job number 121-127 Harrington Street 221298-00 Document title Fire Engineering Report Document ref 221298 Revision Date Filename Issue 01/03/11 Description Name File reference 0001 Fire Engineering Report.docx Issue to Charter Hall for comment Prepared by Checked by Approved by Ted Moyle Marianne Foley Marianne Foley Prepared by Checked by Approved by Prepared by Checked by Approved by Prepared by Checked by Approved by Signature Filename Description Name Signature Filename Description Name Signature Filename Description Name Signature Issue Document Verification with Document 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Charter Hall 121-127 Harrington Street Fire Engineering Report Contents Page 1 Introduction 1 2 Requirements of this report: 1 3 General building description and plans 2 4 Process and approvals pathway 4 5 Fire safety philosophy 5 5.1 6 6 Fire Safety Assessment 6.1 6.2 6.3 6.4 6.5 7 Stair pressurisation Introduction Occupancy Simultaneous evacuation RSET – Comparative Assessment Implications for Fire Brigade Conclusion 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX 7 7 7 8 9 14 15 Charter Hall 1 121 Harrington Street Fire Engineering Report Introduction Arup has been engaged by Charter Hall to determine a fire engineering strategy for 121 Harrington St. The aim is to resolve the current fire stair pressurisation system concerns and to provide an appropriate approvals route in order for a current and certifiable Annual Fire Safety Statement to be achieved. The building has been previously fire engineered, with the strategies and associated fire safety measures required, stated in the following documents: Fire Safety Study Report DLA-1C – Fire Modelling and Computing – March 1999 (This report is the base build fire strategy) Fire Safety Study Report DLA-1D – Fire Modelling and Computing – April 2002 (This report is tenant fit out fire strategy) The requirements of the previous fire engineering reports have been recently reviewed by the author of the reports, via a site visit on the 2nd June 2010. It is understood that any requirements from this site visit can be rectified and that the author will be able to sign off the fire engineering design of the building, with the exception of the stair pressurisation. An Interim Annual Fire Safety Statement was provided by Knight Frank in October 2010 and concluded that the required essential fire safety measures complied, except for the following areas: The café kitchen suppression system, signage and emergency lighting were non compliant. These items can be rectified to meet the required standards and do not form part of this fire engineering report. An exception of the above is that the previous fire engineering report required a stair pressurisation system to be installed in the building. The design of the stair pressurisation and the sealing of the building is such that the current systems do not comply, with air actually being forced into some of the stairs. Because of the heritage nature of the building adding relief air louvers to the building facade is not an option to overcome this issue. Instead, a separate fire engineered solution is to be develop by Arup in regards to this matter and forms the basis of this fire engineering report. 2 Requirements of this report: Based on this fire engineering strategy, in regards to the stair pressurisation system, the following fire safety measures are to be implemented to the building: The 3 fire stairs do not require a smoke pressurisation system as per the analysis and requirements of this fire engineering report. Smoke seals are to be provided to all of the fire stair fire doors. The smoke seal are to be of medium type that can withstand up to 200°C for 30 minutes and be applied to 3 sides of the self closing door i.e. top and sides. The EWIS is to be amended to provide the simultaneous evacuation for the whole building. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 1 Charter Hall 3 121 Harrington Street Fire Engineering Report General building description and plans The Bushells Building at 121-127 Harrington Street is a 7-storey building. The effective height is below 25 m. The ground floor contains a car park (Class 7) and a café (Class 6). Levels 1 to 6 are office use (Class 5). An atrium extends from ground floor up to level 6 and utilises a natural ventilation smoke management strategy. The required type of construction is A, however, its present structural system is approximately related to type B (see previous fire engineering report for details). The 3 fire isolated stairs are provided on the office floor plates. Sprinklers are provided with fast response heads to AS2118. Building detection and alarm are provided to AS1670.1. EWIS is provided to AS2220.2. Hydrants and hose reels are provided to AS2419 and AS2441. The office floors are smoke separated from each other and are also smoke separated from the atrium. The separation of the office floors from the atrium is largely by virtue of the original external brick walls of the building, along with the original (sealed) windows and newer doors to each floor from the bridges across the atrium. Note that the above list is not the full description of building’s fire safety measures, but is shown to place this report into context. Figure 1: Location of the building 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 2 Charter Hall 121 Harrington Street Fire Engineering Report Figure 2: Ground floor plan view Figure 3: Level 1 plan view 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 3 Charter Hall 121 Harrington Street Fire Engineering Report Figure 4: Level 2 to level 6 general plan view 4 Process and approvals pathway The currently installed stair pressurisation system was signed off by the Certifier at the time, even though it had been tested and deemed non compliant (in relation to air flows through the stair doors). Due the unavailable relief paths as described in this report, a compliant stair pressurisation is unachievable. It is recommended that Charter Hall request Council to provide a Fire Order to the building, solely in relation to the stair pressurisation system but requiring the work as described in this report (as all other fire safety aspects can comply with the previous fire engineering reports, and comply with the BCA/ relevant Standards at the time of construction). Arup and Charter Hall are to liaise with the Council and communicate the fire strategy proposed to omit the stair pressurisation system. Ideally the end result would be a Fire Order requiring works to comply with this fire engineering report by Arup. Therefore with the rectification works to the café, a sign off of the original fire engineering design by the previous author, and the alternative design from Arup with deletion of the stair pressurisation system; a compliant Annual Fire Safety Statement for the building should be achievable and a the required level of fire safety for the building will be reached. This approach is considered preferable to simply providing a fire engineering report addressing the deletion of stair pressurisation to meet the performance requirements of the BCA as there is a risk that neither the fire brigade nor a Certifier would agree that the deletion of stair pressurisation met the Performance Requirements for a new building when the base building design required it. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 4 Charter Hall 121 Harrington Street Fire Engineering Report Rather, the fire order approach acknowledges the constraints of the existing heritage building and provides solution to give an acceptable level of fire safety within these constraints. 5 Fire safety philosophy The following discusses the general fire safety philosophy of the building and demonstrates the main principles that provide sufficient safety to occupants and Brigade during a potential fire event. The atrium strategy utilises natural smoke ventilation based on a low fuel load at the base of the atrium. The smoke is generally dilute due to the large volume and roof venting available, with the doors and walls to the office floor plates separated by smoke proof construction. This analysis is quantified in the previous fire engineering reports. The egress routes from the offices do not require occupants to enter the atrium and the risk of fire and smoke conditions affecting office occupants during egress is low. A worse case fire scenario would more likely be a fire in the office than in the atrium. On this basis the risk of fire/smoke spread, occupant evacuation and Brigade Intervention have to be considered below. The offices utilise fast response sprinkler heads throughout to limit and control the fire size. The floors are smoke sealed from each other (they are timber hence not fire separated) and also to the atrium, and a requirement of this report is also to provide smoke seals to the fire stair fire doors. Therefore sprinkler cooled smoke has a low risk of migrating through the building, with the lifts being in the atrium, reducing the risk further. The building has low occupant numbers compared to the generous egress widths provided by the 3 fire stairs, allowing for quick evacuation if occupants are given early warning. The smoke detection system has quick detection due to close spacing of detectors with the AS1670 system. The building also has lower premovement times compared with a BCA DtS complying design, due a pre recorded verbal announcement alarm system (in lieu of just a toned alarm). Brigade intervention is provided by easy access on both sides of the building from the main road and being situated in the city centre (short arrival times). The floor plates are relatively small with generally clear sightlines for fire fighting activities and search and rescue operations. A compliant hydrant system is provided for fire fighting activities and is located outside the choice of fire stairs on each office floor. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 5 Charter Hall 5.1 121 Harrington Street Fire Engineering Report Stair pressurisation As the building is less than 25m in height, the stairs in the office floors are required to be pressurised due to the associated risk with the atrium (as per the BCA). If no atrium were provided then the fire stairs on the office floors would not require stair pressurisation. Stair pressurisation is also a provision of the existing fire engineering report of the building. A stair pressurisation system has been installed into the 3 fire stairs. The stair pressurisation system as it is currently would provide a worse smoke environment when operating in a fire event, as the air velocity coming out of one stair would force smoke into another stair, adversely affecting egress and fire brigade access. The fire stairs do not comply with AS1668.1 as the required airflows of 1m/s through the fire stair doors during testing are not achieved. The issue is that there are insufficient air relief paths through and out of the building, due to a combination of the following factors: the fire engineering report requires all office floors to be smoke sealed from each other and smoke sealed from the atrium. the heritage nature of the building requiring the current non openable façade windows to be maintained and also preventing provision of new openings and penetrations within the heritage fabric. no mechanical relief is provided on the office floors as air handling systems are required to shut down in fire mode. The impact is that smoke can enter the stair in a fire event, spread to non fire floors and also effect egressing occupants and arriving fire brigade. Due to the restrictive elements of the building that do not allow a relief air path for the stair pressurisation system, a fire engineered solution is required to be provided. The fire engineered solution proposed is considered to provide an improved level of safety to that of the originally certified non compliant stair pressurisation system. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 6 Charter Hall 121 Harrington Street Fire Engineering Report 6 Fire Safety Assessment 6.1 Introduction To understand the risk of omitting stair pressurisation and the associated risk of occupants evacuating the building, the following two assessments are provided: 1. For a simultaneous evacuation, the assessment demonstrates that all office occupants can fit into the 3 fire stairs at once. This reduces the risk that they will be queuing on a non-fire floor if smoke or fire spreads to that floor. Occupants can be protected in a fire rated shaft with smoke seals to the fire doors. 2. A comparative assessment to show that the current building design will have a shorter overall evacuation time (RSET) than a building designed in accordance with the current DtS provisions. This is performed by assessing the travel distances and occupant flow times into the 3 existing fire stairs versus a DtS case using compliant travel distances and the associated occupant loading and flows using a DtS scenario that also uses 3 fire stairs. 6.2 Occupancy The net floor area of the offices ranges from 995m2 to 1018m2 (as shown in the Denny Linker floor plans dated 24-11-2000) The occupant load in each storey would be approximately 100 persons based on the occupant load density of 10m2/person as per BCA. Floor Total office NLA Occupant density Occupant load for offices L1~L6 6000m2 10m2/person Total occupant load of 600 people 100 persons per floor 34 persons per floor/per fire stair In terms of occupancy and egress from the other non office floors the following assumptions are made, which exclude their numbers for the evacuation assessment: The carpark is generally a low populated space. Occupants are mostly employees from the offices (taken into consideration for the office populations); however the public is able to use the carpark as well. Occupants in the carpark can egress through into the atrium and then to outside, or through the carpark entrance (which is likely to be open during occupied hours) or into a fire stair that discharges at street level. The café area includes a public seating space, a kitchen and back of house office area. Occupants are likely to egress straight to outside via the main entrance (as that exit is closest and occupants are likely to have entered that way). There is also an alternative egress path through the carpark and into the carpark fire stair. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 7 Charter Hall 121 Harrington Street Fire Engineering Report Occupants in the atrium would likely be transient and employees of the building (taken into consideration for the office populations). They would be able to evacuate through the front entrance or through into the carpark. It is noted that the two assessments below have a margin of safety to allow a scenario where occupants on ground floor utilise the carpark fire stair as well as full capacity office floor evacuation. These include: Additional holding capacity of the fire stair that extends to the carpark, even with all office occupants inside. The building provides half the evacuation time necessary when compared with the DtS case, so a number of additional occupants from ground floor would not affect the conclusion of DtS case being a worse case. 6.3 Simultaneous evacuation If the 3 fire stairs can accommodate all the occupants in the building, the occupants on the other non-fire floors can evacuate into the stairs without waiting on the floor for extended periods of time. This reduces the risk that they will be queuing on a non-fire floor if smoke or fire spreads to that floor. Once all occupants are in to the stairs, then the doors will be closed behind them and the smoke seals will minimise any smoke spread into the stairs. Smoke and fire spread to the other non-fire floors is not likely to result in untenable conditions due to the sprinkler protection and the reduction in smoke spread via the major pathways of the stair (provided with smoke seals), the lifts (smoke separated from the office and located in the atrium) and the smoke sealing of each floor. As the floors are timber, simultaneous evacuation is considered preferable to reduce the risk to occupants in the unlikely case that the sprinklers failed to control the fire. The maximum number of people that can be accommodated in one fire stair at any time is given in Chapter 4, Means of escape and human factors, CIBSE Guide E Nc(max) =pAS = 3.26 x 12 x 6 = 235 person capacity per fire stair in this building Where, ‘Nc(max)’ is the maximum number of occupants that can be accommodated in one stairway at any an time; ‘p’ is the maximum occupant density of the stair, which is approximately 3.26persons/m² based on a high density as per the SFPE handbook and used in the assessment above. Further, CIBSE Guide E recommends the use of 3.5 persons/m² for people in the stairway without suffering extreme discomfort. ‘A’ is the horizontal area of stair and landings per storey (m²) which is approximately 12m²; for a standard 1m wide stair, and ‘S’ is the number of storeys (this includes levels 1 to level 6) Based on this methodology, the capacity of the 3 fire stairs is 235 x 3= 705 occupants. Therefore as the office floors have a maximum population of 600 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 8 Charter Hall 121 Harrington Street Fire Engineering Report occupants (see section 6.2 above for details on occupant numbers), all office occupants are able to fit into the 3 fire stairs simultaneously. It is noted that the fire stairs within the current building are wider than 1m in width. This would allow a much greater holding capacity of occupants than that assessed above. Therefore the assessment is conservative. 6.3.1 Assessment Conclusion With amendments to the EWIS, a fire anywhere in the building would trigger the alarm and simultaneous evacuation would occur. The assessment shows that the all office occupants can utilise the fire stairs at the same time as a place of relative safety as they can all fit in the stair that is provided with smoke seals. This means that they are protected from potential fire and smoke conditions. As they are all able to get into the stair quickly, and in the early stage of a fire, then the stair pressurisation is less crucial than for a DtS case where the queuing times would be longer. A DtS case could allow occupants to queue to enter the fire stair on multiple floors for a simultaneous evacuation (due to larger DtS floor plates and occupant numbers than in the existing building), and hence they would be more vulnerable to fire and smoke conditions on the fire floor or on non fire floors. If the evacuation were simultaneous, the air flows from the stair pressurisation would not meet the 1m/s (due to the amount of doors open simultaneously), hence smoke would not necessarily be kept out of the stair for this extended evacuation time. Alternatively a DtS case could evacuate floor by floor with a phased evacuation, which would allow the air flow of 1m/s to be maintained In this case however, occupants on the non fire floors would be evacuating at a much later stage of the fire and there is greater potential for smoke to have spread between floors. This is particularly of concern in this building due to the timber floors and lack of zone pressurisation on the office floors (required in a new building due to atrium provisions) that could allow smoke to spread up to the floors above the fire floor. Therefore due to the risk of smoke spread through the building when taking into consideration the above factors and the potential impact to occupants if delayed by phasing the building evacuation, utilising a simultaneous evacuation is considered a safer evacuation procedure. As simultaneous evacuation would prevent a stair pressurisation system from working efficiently (due to the number of door open at once), the requirement for it to protect egressing occupants is reduced. 6.4 RSET – Comparative Assessment Egress of the occupants from the building can also be compared with a deemed to satisfy building, with the maximum number of occupants catered for by the width of fire stairs, to further assess the necessity for stair pressurisation. 6.4.1 Methodology The required safe egress time (RSET) from a point on a floor is the time needed for all occupants to evacuate to an exit in an emergency scenario. RSET can be 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 9 Charter Hall 121 Harrington Street Fire Engineering Report expressed by the following equation: RSET = talarm + tp-m + ttravel + tmove Where: talarm is the detection and alarm time tp-m is the pre-movement time ttravel is the occupant movement time to reach an exit tmove is the time for occupants to queue and flow through the exit The existing building has 3 fire stairs and 100 people per floor (due to the small floor plate area). A DtS design that has 3 fire stairs is able to hold 320 people per office floor. The following assessment will quantify the difference between the DtS RSET and the existing building RSET, showing that the existing building can evacuate its occupants quicker than a comparative DtS case. The nature of the comparative assessment means that the alarm time, premovement time and travel speeds will be the same for both the DtS design and the building design 6.4.2 Assessment of Detection/Alarm time The building is provided with a detection system to AS1670, as the building contains an atrium. The following assesses the time taken for the alarm system to activate with various fire growth rates. Considering a generally open plan office and modelling a range of fire growth rates, the detection/alarm time for the existing AS1670 system is calculated using the program FPETool. The calculation uses a nominal 2.75m ceiling height and assumes the fire is midway between detector heads (as the worst case fire location i.e. 7.2m horizontally from the detector). The following table compares the detection times for different fire growth rates. Times are calculated using a temperature rise of 13°C and an RTI of 1 for smoke detectors. Activation time, Sec Fire growth rate Slow Medium Fast AS1670 (10.2m Spacing) 210 106 54 An alarm time of 106s is taken for both the DtS building case and for the existing building case for input into the RSET timeline, as it is expected that an office fire would produced medium fire growth rate. This is shown in the figure below which depicts tests carried out by NIST for work station fires. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 10 Charter Hall 121 Harrington Street Fire Engineering Report It is noted that travel distances in the existing building and current fitout are assumed to be DtS (no fit out plans have been provided to Arup and there is no discussion of extended travel distances in the base building fire engineering report), so no additional analysis is required for extended travel distances. 6.4.3 Pre-movement time The comparative nature of the assessment means that the pre-movement time for the DtS design and the building design will be the same. For completeness, it is anticipated based on data from Section Table 3-13.1 of the SFPE Handbook; that the pre-movement time for occupants in the small space who can clearly see the smoke will be approximately 30 seconds. For occupants remote from the fire with a non-directive alarm a pre-movement time of up to 3 minutes may be expected. Therefore it is considered that as the building has a directive alarm as part of the previous fire engineering strategy, the pre-movement time would be less than 3 minutes (more in the range of 2 minutes). However for the total evacuation time of occupants 3 minutes has been used to be conservative. 6.4.4 Movement time to the stair exits The movement time, to and through an exit, consists of travel time, which is the time required to reach the exit, and flow time to pass through an exit into a place of safety, which could be the fire stair or could be taken to the final exit, usually a road or open space. Depending on the distance of travel and the numbers of people, the limiting factor may be travel distance or flow through an exit, which can be determined and used in the RSET assessment. Furthermore, it may be the flow through a door or the flow in a stair that limits the overall evacuation time. The following section investigates the dominating flow. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 11 Charter Hall 6.4.4.1 121 Harrington Street Fire Engineering Report Travel Time For the comparative assessment a typical occupant walking speed of 1.2m/s (taken from Chapter 4.7.1, CIBSE Guide E) has been used. Time (at 1.2m/s) DtS ( up to 40m) Design Case (up to 40m) 33 sec 33 sec The analysis is conservative as it uses 40m for the existing building design, whereas with the ability for office occupants to use 3 fire stairs on a relatively small floor plate (to a DtS design), can provide occupants with much shorter travel distances. 6.4.4.2 Flow Time The queuing time in front of a doorway to stairs depends on the flow rate of the doorway and the flow rate in the stairs, should the stairs be full. The following flow rates given in Table 3-13.5, Chapter 3-13, Section 3, SFPE Handbook Edition 3rd can be used to predict queuing. 2 Crowd condition in front of doorway Density (persons/m ) Flow rate (persons/min/m) Moderate 1.09 55.94 Optimum 2.39 85.48 Crush 3.26 49.34 Table 1: Flow rates and Densities for Doorways from SFPE handbook 2 Crowd condition in stairs Density (persons/m ) Flow rate (persons/min/m) Minimum 0.54 16.45 Moderate 1.09 45.90 Optimum 2.07 59.19 Crush 3.26 39.50 Table 2: Flow rates and Densities for Stairs from SFPE handbook Using the worst case scenario of crush conditions for a fire affected floor (as this provide a slower flow rate for evacuation) and would be consistent for a simultaneous evacuation strategy, Table 4 provides the following results. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 12 Charter Hall 121 Harrington Street Fire Engineering Report Elements DtS (3 x 0.8m doors and 3 x 1m stairs)) Existing Building - (3 x 0.8m door and 3 x 1m stair) Occupant load in each floor 320 persons (maximum capacity for the three stairs) 100 persons Doorway capacity 118 persons/min (49.34 x 2.4m) 118 persons/min (49.34 x 2.4m) Stair Capacity 118 persons/min (39.50 x 3m) 118 persons/min (39.50 x 3m) Table 4: Flow time comparison through doors The table above illustrates that both the flow rate into the stair door and down the stairs is equivalent considering the associated flows and widths available. Elements DtS (3 x 1m stairs) Existing Building - (3x1m stair) Total population of building 1920 persons (6 floors x 320 persons) 600 persons (6 floors x 100 persons) Flow rate (see above) 118 per/min 118 per/min Flow time down stairs assuming total population (worst case) 16.3 minutes (978 sec) 5.1minutes (305 sec) Table 5: Comparison of whole building evacuation time in DtS building and in the existing building Under the worst case scenario of crush condition, the total flow time down the stairs would be 5.1 minutes, approximately 3 times less than a DtS complying building with up to 320 people on a floor and three fire stairs. Comparison of overall evacuation time for DtS and existing designs The building features a small floor plate. In order to assess the relationship between the floor plate and the building design, Table 6 below lists the egress time for a building meeting the DtS provisions compared with that in the current building using the 3 fire stairs provided. Elements DtS building Exiting building Number of exits 3 stairs with each width of 1m 3 stairs with width of 1m 3 doorways with width of 0.8m each 3 doorway with width of 0.8m 320persons 100persons Occupant load in each floor 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 13 Charter Hall 121 Harrington Street Fire Engineering Report Elements DtS building Exiting building Detection time 106sec (AS1670) med growth 106sec (AS1670) med growth Pre-movement time 180 sec 180 sec Movement time to reach the fire stairs 33 sec 33sec Flow time in Stairs 978 sec 305 sec RSET (sec) 1297 seconds (22 mins) 624 seconds (11 mins) Table 6: Total Evacuation times comparison 6.4.5 Assessment Conclusion It can be seen from the RSET comparison that the current building design achieves half the evacuation time when compared with the DtS case being assessed. Therefore it is considered that occupants would be exposed to fire and smoke conditions for a shorter period of time in this building than in a compliant DtS design, reducing the importance of the stair pressurisation for maintaining smoke free stairs during egress. Also as, the egress time is much lower, egress is occurring at an earlier stage of the fire hence less smoke is being produced, and it is not as hot It is noted that previous fire engineering reports for the building utilised an ASET/RSET methodology on the office floors to show that occupants could evacuate to the fire stair before untenable conditions occurred. Therefore a similar assessment is not performed in this report as it has already been included in the base build and fit out reports. The assessments in this report do not adversely affect or contradicts the previous analysis and conclusions. 6.5 Implications for Fire Brigade With regard to fire fighting intervention the faster building clearance means that once the fire brigade arrive and set up it is more likely in this building than in a DtS designed building that the stair will be clear of occupants allowing for faster fire brigade response to attack the fire. The provision of three stairs also gives them more options for fire attack. A sprinkler system with fast response sprinkler heads has been provided throughout to reduce the risk to life safety of occupants and NSWFB and allowing additional property protection. The sprinklers will aid to control or suppress the fire before and during fire brigade intervention. The building has a compliant hydrant and hose reel system (at the time of installation). As there are 3 fire stairs, there is a choice of hydrant and hose reels to utilise in a fire event. With a much smaller floor plate than that allowed by DtS, 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 14 Charter Hall 121 Harrington Street Fire Engineering Report the likely fuel load is lower and also provides better sightlines for fire fighting and less area for search and rescue. If the fire is on an office level, the smoke seals to the fire doors will help minimise smoke spread into the stairs and the sprinklers will help keep fire sizes, and hence smoke production, low. It is acknowledged that after occupants have evacuated the building, a compliant stair pressurisation system would be beneficial for brigade intervention and would also be efficient (as the number of doors open at one time would be limited, allowing the required airflows to be maintained). However as the stairs are required to be pressurised due to the risk created by the provisions of the atrium, it is considered that the office floors where the fire stairs are located do not provide conditions worse than a DtS office building under 25m in height, that has no atrium, and also no requirement for stair pressurisation. The base building fire engineering design naturally vents the atrium smoke to outside and the intrinsic nature of the atrium reduces the risk of smoke spread on multiple office floors due to the external wall and separation of offices by predominantly masonry construction with fixed glazing. The fire engineering report also required limiting the fuel load in the atrium to help minimise potential fire sizes. Therefore the risk of smoke spread to multiple office levels from the atrium and then into the fire stairs (with smoke seals) is considered low. 7 Conclusion Based on the fire engineering assessments above and the required fire safety measures of this report, it is considered that omission of the stair pressurisation does not significantly impact on the life safety of occupants and the Fire Brigade, such that it would need to be retrofitted to comply. In summary, the main points are as follows: The heritage and restrictive nature of the building fabric restricts the penetrations required for relief air to ensure a stair pressurisation system would work. Therefore a solution is required, as the current stair pressurisation conditions are hazardous to occupants and brigade. Occupant numbers are low, on small floor plates and are provided with generous stair capacity that enables all occupants to fit in the fire stairs simultaneously and allows for quick building evacuation. The timber floors, lack of zone pressurisation and separation from the atrium on office floors; concludes that simultaneous evacuation of the building is the safer approach than phased evacuation Simultaneous evacuation would prevent the stair pressurisation from working efficiently due to the amount of doors open at once The quick occupant evacuation and close proximity of Brigade Stations allows the Brigade to enter and fight a fire in a short period of time. The stairs require pressurisation as per the DtS provisions only due to the atrium, however smoke and fire spread from the atrium is seen as a low risk. As such it is considered that potential smoke and fire conditions during Brigade intervention on office floors would be no worse than a DtS complying building, less than 25m in height and without an atrium (and 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 15 Charter Hall 121 Harrington Street Fire Engineering Report indeed is better with the sprinkler protection an AS1670 smoke detection, plus three stairs). Considering the above, the recommendation is to decommission the stair pressurisation systems, retrofit smoke seals and amend the EWIS for simultaneous evacuation. A fire order is considered the best way to gain approval for the works as they are being done to address an existing system that cannot perform as required by the building design and BCA. 221298 | Issue | 1 March 2011 | Arup J:\221298-00 121 HARRINGTON STREET\05 REPORTS\0001 FIRE ENGINEERING REPORT.DOCX Page 16