ZENATOR SYSTEMS Commissioning Guidelines & Notes Introduction The purpose of this document is to provide COMPANY Projects with a detailed procedure for use during the implementation and recording of Mechanical Completion, Pre-Commissioning and Commissioning of all COMPANY Projects. The Completions phase commences with the testing, inspection and validation of discrete Construction packages with concurrent Handover to the Commissioning Group (for commencement of Pre Commissioning) and continues until all packages forming the whole Facility have been completed and accepted. Dynamic Commissioning of each system shall then be carried out in accordance with approved System specific procedures. This provides an overview of the various aspects of the Completions process, systems and certification, documentation required to implement record and validate Completions activities. 1.0 Abbreviations ZEN Completions Management System FAT Factory Acceptance Test F&G Fire & Gas ITR-A Inspection Test Record (Mechanical Completion) ITR–B Inspection Test Record (Pre-Commissioning) CONTRACTOR Kastroy Services Construction Group MC Mechanical Completion MCSSAC Mechanical Completion Sub System Acceptance Certificate NOSE Notice of System En-ergization OWR Outstanding Work Register P&ID Piping & Instrument Diagram PC Pre-commissioning PCSSAC Pre-commissioning Sub System Acceptance Certificate PTW Permit to Work RFCC Ready For Commissioning Certificate SAC System Acceptance Certificate SLD Single Line Diagram LOSH Limits of System Handover Commissioning Guidelines - 20130419 Page 1 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes 1.10 Definition of Mechanical Completion Mechanical Completion (MC) as a term means bringing the equipment, packages and Hull systems, to a state of installed completion, whereby single discipline pre-commissioning can commence in accordance with project specifications. The fabrication yard and where applicable, vendor representatives will demonstrate MC by inspection, verification and testing of the installation and presentation of the information in check sheet format (ITR ‘A’ Check sheets) so as to confirm the design specification Typical work, which may be specified on the relevant Mechanical Completion Records will include, but not be limited to, the checks and verification of completion of the following: Fabrication, assembly and finishing of all structural steelwork. Installation of platforms, including stairways, safety grills, etc. Surface preparation, painting or galvanising of all steelwork, pipe work, equipment and facilities support steelwork. Installation of all equipment described in the contract and designated for installation together with its associated piping, electrical components, instrumentation and other services. Fabrication, installation, connection and hydrostatic testing of all pipe work including flushing cleaning and drying activities. Installation of all cable support systems, cable glands, penetrations, junction boxes, outlets, light fittings and grounding. Installation, securing, terminating, marking, continuity and tightness checking, of all electrical, telecommunications and instrumentation cabling and wiring. Installation of all switchgear, transformers etc., power supply and control panels. Installation of HVAC ducting complete with all support steel, equipment, accessories, filters, instrumentation and controls. Carrying out an integrity test of the ducting and mechanical function tests of equipment. Checking free rotation and proper orientation of all rotating equipment. Installation of all, floor coverings, partitions, wall linings and associated insulation, furniture, fittings and service systems. Installation of all, instruments, instrument control panels, associated piping, tubing and cabling. Tightness testing of piping, tubing and continuity checking of cable. Installation of all, fire protection / detection and gas detection equipment, accessories including associated piping and wiring. Installation of, insulation and insulation fixing materials. Installation of safety equipment including platform safety and hazardous area signs. Installation and testing of lifting equipment. 1.20 The Mechanical Completion Process In order to achieve a proper and correctly documented handover from CONTRACTOR to COMPANY Commissioning Group and from COMPANY Commissioning group to Operations & Maintenance all Systems shall be divided to form Sub Systems. Commissioning Guidelines - 20130419 Page 2 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes A sub-system is the boundary of equipment, which can conveniently be grouped for the purposes of dividing a larger system into more manageable sections for mechanical completion and when all the subsystems are agreed as mechanically complete, the larger system can in turn become mechanically complete. Each Sub System shall be allocated an alpha numeric code by the COMPANY Commissioning Group, Every item of equipment within each Sub System e.g., piping, cables instruments etc. shall be referenced by its assigned Sub System number. The boundary limits of Sub Systems shall initially be identified by COMPANY Commissioning Group on marked up, colour coded P&IDs, Layout Drawings and Electrical Single Line Drawings. The boundary limits shall be reviewed and agreed with COMPANY Commissioning Group prior to final approval. Sub Systems are defined as mechanical completion sections in which priorities for completion shall be agreed and established by COMPANY Commissioning Group, and CONTRACTOR. On completion of approved System/Sub System boundaries, all equipment within the established Sub System limits shall be listed including in line and remote instruments and associated power and control cables by type and number. The listing of equipment shall be further broken down into individual Mechanical Completion Records (ITR-As) which identify test and inspection requirements for each item of equipment. This listing of ITR-As shall be entered into the Mechanical Completion Database by ITR-A type no., Discipline, System, Sub System and Tag number. The blank ITR-A forms by type are already held in the database. CONTRACTOR shall be issued with ITR-As in Discipline and Sub System packs by the Zenator Power Users direct from the database. CONTRACTOR shall then proceed to carry out the checks as required by the ITR-A sheets. Flow Chart; Production / Commissioning Flow of ITRs A and B Check Sheets (Appendix A) Demonstrates the flow of ITR Check Sheets from issue by the Zenator Power User right through the MC process until the Check Sheets are returned, signed, verified and ready for scanning into Zenator. 1.21 Mechanical Completion Record ITR-A The Project Mechanical Completion Record ITR-A is a standard form tailored to suit a particular item or type of equipment which identifies the specific checks and tests to be done and records to be kept to achieve the verification of compliance with design, specification, regulations, quality control and certification of the installation as being Mechanically Complete. The ITR-A pro forma shall be prepared by COMPANY Commissioning Group and assigned a unique barcode within the Zenator Completions System data base. Commissioning Guidelines - 20130419 Page 3 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes Any future additions, deletions or amendments to ITR-As shall require approval by the Zenator Power Users who shall maintain responsibility for issuing and recording ITR-As and Handover documentation. Each ITR-A contains facilities for approval by Authorised signatories and shall not be deemed complete until approval signatures have been obtained. An Authorised Signature Matrix (see Appendix E) shall be implemented and maintained by Zenator Power Users and Commissioning groups. Where Commissioning group’s review reveals that the requirements of the ITR-As, Design Specifications or Drawings have not been achieved, CONTRACTOR shall rectify the work and shall resubmit the item of work / ITR-A for approval. The ITR-A for specific items of equipment shall list the checks which are normally performed upon that type of equipment but may not be specifically written for each particular item of equipment. In this case the check box NA can be selected It should be noted that although ITR-As are necessary evidence of work completion, they are not intended to supersede, modify or vary contractual agreements. All MC inspections/tests shall be performed with equipment un-energized. All inspection and test equipment used for measurement shall be calibrated to a national standard. A list of test equipment and current calibration details shall be maintained and submitted to COMPANY Commissioning group. It is necessary that each inspection item is addressed and each item shall require either a "yes or "no" or "not applicable" comment. Any item necessitating a "no" must be then identified on a punch list. ITR-As are divided into the following disciplines. 1.22 DISCIPLINE Architectural Electrical Fire and Gas HVAC Instrumentation Mechanical Piping Telecommunications Structural Group Printing of ITR-As Commissioning Guidelines - 20130419 CODE A E F H I M P T ST Page 4 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes In a Sub System where there is a requirement to print numerous ITR-As. of a specific type and the checks are mainly generic, a facility to group print these check sheets has been created called a Bulk Check Sheet. This involves the printing of a master check sheet and an attached computer generated list of all relevant tags. These tags are then checked / inspected against the master check sheet and any unique information recorded on the attached sheet. This facility is generally available at the discretion of the Zenator Power Users, for the following check sheets. 1.30 Power / Control Cable Installation & Test Junction Box Installation Field Instrument Installation Fire & Gas Detection Device Installation Mechanical Completion Handover Upon completion of each ITR-A Check Sheet and approval by the authorised signatory of all ITR-A’s within a Sub System, Zenator Power Users will generate an MCSSAC for CONTRACTOR to offer the Mechanically Complete Sub System to COMPANY Commissioning Group for approval, complete with a computer printed status index (list) detailing completed ITR-A’s and any outstanding punch-list items and modified ‘As built’ drawings. COMPANY Commissioning Group shall carry out a physical review of the offered Sub System, documentation and accept or return the Sub System to CONTRACTOR for completion. Upon acceptance of a Sub System by Zenator Power User they shall enter details of completion of the ITR-As and Handover documentation into the database. Any part of an ITR-A which is unable to be completed, shall be entered into the database and Zenator Power User shall generate these items Sub System Punch List Registers. Only when all Sub System ITR-As have been completed shall a Sub System, be considered 'mechanicallycomplete'. If a shortage of materials or outstanding design changes prevent completion of certain ITR-As then a punch-list shall be raised and agreed between CONTRACTOR and COMPANY Commissioning Group. In general and as a matter of principle Sub System Acceptance Punch Lists shall contain only ‘B’ items. In exceptional circumstances the Commissioning group can agree to accept a Sub System with ‘A’ Punch List Items, if these items can be effectively isolated from the System on a temporary basis so as to allow the commencement of Pre-Commissioning in an efficient and safe manner. Acceptance of a Sub System by COMPANY Commissioning signifies the formal Handover of ownership of all equipment defined (with exceptions) in the transmission. This means CONTRACTOR requires COMPANY Commissioning authorisation via the Permit to Work System to carry out any activities on equipment within the Sub System. e.g. clear Punch List items. Commissioning Guidelines - 20130419 Page 5 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes Note: Upon Commissioning Group signing, MC System Acceptance certificates, carrying Punch List items, then clearing these remain the responsibility of CONTRACTOR as applicable. MC Handover is as per Handover Documentation Flow Chart (Appendix C). 1.40 Definition of Pre-Commissioning and Commissioning Pre Commissioning is the execution of single discipline checks carried out on individual items of equipment by authorized Commissioning personnel, required to demonstrate unit or component functionality by introduction of energy, operation under loaded conditions, and prior to the dynamic operation and testing of the system in which the components reside. Presentation of information is in check sheet format (ITR‘B’ Check sheets). Tests shall: Verify MC documentation is in place. Be carried out on a single discipline basis. Require individual items of equipment to be energized Validate the design functionality of equipment Generally not require process fluids Record any outstanding Punch List items. Verify equipment Functionality Commissioning is the activities undertaken to ensure the dynamic verification of the functioning units or components and facilities forming a discrete operational system, sub system or commissioning package by demonstrating and recording its accordance with design parameters, regulations and specified operational requirements. Operation may be simulated, prior to introduction of normal operating conditions. This activity is carried out and presented and recorded in accordance with individual detailed procedures developed specifically for the activity. Typically; dynamic commissioning activities undertaken after the completion of Commissioning Completion Records will: Be carried out on a System or Sub System containing more than one piece of equipment. Be carried out by a multi-disciplined team of Engineers. Be executed with the assistance of, or witnessed by, Operations personnel. Be executed as a series of steps set out in a procedure and signed off on completion of each step. Be executed using permanent utilities. Be executed using simulated conditions and confirmed when process fluids are available. Be witnessed by the Certifying Authority where applicable. Commissioning Guidelines - 20130419 Page 6 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes The Commissioning Process The commissioning process is the overall process by which equipment and systems which have not been operated before are brought into operation. The process begins prior to the commencement of Mechanical Completion whereby, the Power Users identify commissionable packages of Systems and Sub Systems. The boundary limits of Sub Systems will be identified on marked up P&ID’s, Electrical Single Line Drawings F&G, Telecom plans and Block Diagrams. Each Sub System is allocated an alpha numeric code and every item of equipment, piping, cables is referenced by a unique Sub Systems no. Sub Systems will fall into commissioning sections where all equipment will be further broken down into individual Pre-Commissioning Completion Records (ITR-B) requirements. This information will be entered into the Zenator System (Zenator) database by ITR type no., discipline, System, Sub System and tag number. The Zenator Completions System will provide the documentation for recording the interim stages of progress and outstanding work of Discipline, System, and Sub System completion from Mechanical Completion to Final Handover to Operations. This definition provides a common database and tracking register for all Mechanical Completion, PreCommissioning and Commissioning activities. Commissioning Records (ITR Bs) will be issued in Discipline and Sub System packs by the Zenator Power User direct from the computer database. Flow of ITR B Check Sheets will be as per the ITR Check Sheet Flow Chart, (Appendix A) ITRs are used to prove, validate and record the functioning of individual pieces of equipment during the Pre-Commissioning phase. A detailed step by step Commissioning Procedure will be produced by COMPANY Commissioning for each System which will contain all the information required to dynamically test the System in accordance with Vendor recommendations and design criteria. This procedure will also include an index of all ITRs for individual pieces of equipment within the System. 1.50 Pre Commissioning Completion Record ITR-B The Commissioning Completion Record (ITR-B) identifies the specific checks and tests to be carried out and the records to be kept to prove and validate the functioning of equipment. ITR-B Check Sheets shall be prepared by Zenator Power Users and assigned in the Zenator Completions System (Zenator) data base. Commissioning Guidelines - 20130419 Page 7 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes Any future additions, deletions or amendments to ITR-Bs shall require approval by the Lead Discipline Engineer. Zenator Power User shall maintain responsibility for issuing and recording ITR-B Check Sheets and Acceptance documentation. The ITR is a standard form tailored to suit a particular item or type of equipment on which checks and tests are required to prove functionality. As an example; the ITR B Check Sheet for pumps, motors, vessels etc. will list the checks which are normally performed upon that type of equipment but may not be specifically written for each particular item of equipment. Each ITR-B contains facilities for Approval by Authorised signatories and shall not be deemed complete until Approval signatures have been obtained. It is necessary that each inspection item is addressed and each item will require either a "yes or "no" or "not applicable" comment. Any item necessitating a "no" must be then identified on a punch list. An Authorised Signature Matrix (see Appendix B) will be implemented and maintained by Commissioning. ITR-Bs will be allocated unique numbers denoting each discipline and the System or Sub System within which the equipment is located. The Zenator System (Zenator Power User) will issue indices by Sub System detailing the status of all ITR-Bs within each Sub System by discipline. Status Indices of ITR-Bs will form part of Commissioning Procedures as handover documentation Zenator Power Users shall continuously review the ITR-B indices and System Responsible Discipline Engineers will assess and authorise any necessary additions and deletions required to maintain the integrity of Completion and Commissioning. All inspection and test equipment used for measurement shall be calibrated to a national standard complete with the relevant documentation. ITR-B’s are divided into the following disciplines: DISCIPLINE - Electrical - Fire and Gas - HVAC - Instrumentation - Mechanical - Telecommunications - Dynamic Commissioning Commissioning Guidelines - 20130419 CODE E F H I M T C Page 8 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes Copies of Pre Commissioning Records (ITR-Bs) can be obtained from Zenator Power Users. 1.60 Commissioning Procedures The objective of the System Commissioning Procedure is to set out guidelines and objectives so as to allow Systems to be commissioned safely in a controlled manner and a method of documenting the extent of testing undertaken (and that which remains outstanding), whilst demonstrating system operability to the Operations group at point of Handover. The purpose of the System Commissioning Procedure is to define, describe and record all multidisciplined preparations and activities to be progressed, endorsed and recorded in a logical step by step manner. Commissioning procedures will be developed by the COMPANY Commissioning group in a standard format which will be Subject to COMPANY Management Group approval prior to Rev 0 issues. The technical content of Commissioning Procedures will be developed using all Design drawings, parameters and specifications in addition to Vendor documentation, manuals and equipment performance characteristics in accordance with legislative bodies and statutory regulations. Commissioning procedures will be developed for each System or Sub System to be commissioned by a multi-discipline team of Commissioning Engineers, with a nominated System Responsible Engineer, of the primary discipline, for each procedure. Commissioning procedures shall define agreed safety critical elements within each System for which specific tests and activities shall be witnessed, signed and endorsed by the appointed Certifying Authority (C.A.) on satisfactory completion. The execution and validation of commissioning will be the responsibility of the COMPANY Commissioning group, with assistance and guidance from the Zenator Power Users with nominated System Responsible Engineers maintaining overall responsibility for execution of each of their allocated Systems and procedures. Commissioning Procedures can be recorded in the data base by the allocation of Dynamic Commissioning ITR-Cs (C-01C). 1.61 Dynamic Commissioning Completion Record ITR-C The Dynamic Commissioning Completion Record ITR-C (C-01-C) is allocated to each Commissioning Procedure in order to track, control and record progress of dynamic testing of each system within the database. 1.70 Commissioning Handover Commissioning Guidelines - 20130419 Page 9 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes When CONTRACTOR / COMPANY Construction Group have completed the checks as required by the ITR sheets and when all Sub Systems ITRs have been completed for a Sub System, the Zenator Power User will raise a Mechanical Completion Sub System Acceptance Certificate (MCSSAC). This will be endorsed by CONTRACTOR / COMPANY and handed over to the COMPANY Commissioning Team along with a computer printed list detailing completed ITRs and any outstanding punch-list items. CONTRACTOR / COMPANY shall include all modified ‘As built’ drawings in the handover documentation. On acceptance of a Sub System, COMPANY Commissioning shall commence Pre-Commissioning by completing the checks required on the ITR B Check Sheets for all equipment within the Sub System. On completion of all required ITRs for a Sub System, COMPANY Commissioning (assisted by COMPANY Operations & Maintenance) shall carry out dynamic commissioning of the completed Sub System / System in accordance with the specific System Commissioning Procedure. On completion of dynamic commissioning (and re-preservation as applicable) of a System or Sub System COMPANY Commissioning shall accept and take ownership of that System/Sub System. COMPANY Commissioning will raise a System Acceptance Certificate (SAC) for each system on a progressive basis which will be issued to CONTRACTOR for acceptance along with the completed System Commissioning Procedure, ITR Check Sheets, Punch Lists and supporting documentation. Acceptance of the final Handover will require any red line mark-up drawings, lists of outstanding activities and the relevant certification documentation to be identified and made available. Operations will then take over full ownership of the systems and operate in accordance with the operational procedures and maintain the equipment and systems under the Maintenance Strategy. Commissioning Handover is as per Handover Documentation Flow Chart (Appendix C). 1.80 Punch Lists On completion of an ITR, any item which does not meet the required standards should be signified in the” no “column, and the specific check number, description of fault / non conformance and categorisation A or B entered in the comments section of the relevant ITR. Supporting information, attachments or continuation sheets should be clearly referenced in the comments section. Punch list details will be entered in the Zenator database, which will format individual items on a discipline basis for each Sub System. Subsequent clearance of Punch List items will be recorded in the database. a) Outstanding Punch lists compiled by Construction and Commissioning in discipline format will be Submitted to Operations with the completed Sub Systems Completion certificate, and will be mutually agreed and categorized before being issued as a Punch List Completion check record. Commissioning Guidelines - 20130419 Page 10 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes b) All punch list items of both categories are to coincide with the relevant discipline ITR item no's where the "no." column has been utilized. Items will also be supported by relevant material, order no's, damage reports, material shortage reports, photographs etc. Any item considered by Commissioning to be a design change will be raised in the form of a design change proposal with supporting information. c) Punch lists items will be categorized into A or B status. Category “A” Any punch list item that is categorised as 'A' will indicate that the relevant System is considered unsafe to operate or cannot be operated effectively, will be rejected and returned in its entirety to CONTRACTOR or Commissioning as applicable. The returned Sub System shall be accompanied by, the Completion certificate noted, rejected, signed and dated. The Sub System will be re-Submitted to on completion/resolution of punch list 'A' items. In special circumstances Zenator Power Users can sanction handover of Sub Systems with ‘A’ Punch List items included e.g. where punch list item can be rendered safe and can be isolated so as to permit the efficient progress of Pre-Commissioning / Commissioning. Category “B” Activities, which do not affect the safety, operation or Start up of the offered Sub Systems or equipment will be categorised as a “B” item. However the raising of such items for acceptance should be kept to a minimum as a high proportion of Punch List items for an individual Tag or Sub System will result in a rejection of the Submission. In general, acceptance of Sub System Completion certificates will be held until completion of outstanding “A “ punch list items or until outstanding 'B' items are agreed. Zenator Power Users shall, maintain on database an updated status of outstanding punch list items and cleared Punch List items as a permanent record of Sub System status and on final completion shall be entered into the computerised archive together with ITR A / ITR B data associated with the relevant Sub Systems. 1.90 Endorsement of Signatory Authority Zenator Powers Users / COMPANY Commissioning and CONTRACTORs shall agree a list of nominated personnel authorised to sign acceptance of Completions certification. An Authorised Signature Matrix (Ref: Appendix B) shall be established identifying the level of authority for nominated individuals. Zenator Power Users shall be responsible for maintaining and distributing current revisions. Commissioning Guidelines - 20130419 Page 11 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes 2.00 Vendors Representatives CONTRACTOR Construction shall issue a Vendor schedule defining CONTRACTOR requirements and shall co-ordinate Vendor site visits during installation. COMPANY Commissioning Group shall issue a schedule of Commissioning Vendor requirements and shall co-ordinate Vendor site visits during Pre-commissioning and System dynamic Commissioning. The initial issue of CONTRACTOR Construction and COMPANY Commissioning schedules shall be reviewed and where possible rationalised and co-ordinated to avoid duplication of effort or resources. 2.10 Vendor Documentation Zenator Powers Users shall review existing and proposed vendor documentation and procedures to ascertain Commissioning Check Record requirements for each Sub System. Any tests or checks required on an ITR which have previously been carried out by the Seller/ Manufacturer, upon which documentary evidence is available shall be assessed for validity, who shall determine whether such documentation is sufficient in its entirety to fully comply with Project requirements. Upon completion of this review COMPANY Commissioning Group shall implement one of the following options: Issue ITRs for all equipment within a Sub System. This shall apply when no Vendor documentation is available, or that which is available, does not comply with requirements. Issue ITRs with instructions to attach (or reference) Vendor documentation to relevant Records. This shall apply when Vendor documentation only partially complies with requirements. Issue no ITRs This shall apply when Vendor’s complies with all requirements and no further testing is identified. Vendor Commissioning Procedures will also undergo this review process with the same criteria and resolution applied. 2.20 Preservation Preservation and De-Preservation throughout the Mechanical Completion and PreCommissioning/Commissioning phases shall be the responsibility of the CONTRACTOR Construction Commissioning Guidelines - 20130419 Page 12 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes and COMPANY Commissioning groups and should be carried out in accordance with approved Preservation procedures and Vendor recommended preservation requirements. Specific post commissioning acceptance re-preservation requirements shall be identified by CONTRACTOR in the individual commissioning procedures and preparation scope. Implementation of Post commissioning preservation shall be the responsibility of COMPANY Commissioning Group until Handover and Acceptance by Operations group of the individual System or Sub system. The Projects, on completion, will be handed over to COMPANY. As such it will be necessary to preserve certain equipment and systems until so as to prevent corrosion, deterioration of the equipment and maintain all systems in perfect operating condition. Where required Vendor preservation procedures will be strictly applied and followed. 2.30 Safety General The safety objective during the execution of CONTRACTOR Construction, Mechanical Completion and Commissioning activities is to prevent all unsafe actions and working conditions which potentially may cause injuries, health risks and damage to assets. All personnel involved shall comply with Project Safety. Health and Working Environment requirements and also with safety requirements contained in Site Manuals and procedures Ref: Project HSE Plan, Document No- [Hold] CONTRACTOR & COMPANY Commissioning Group shall implement a Permit to Work System which shall remain in force throughout Mechanical Completion, Pre-Commissioning, and Commissioning phases. The PTW System shall include procedures for the Livening Up of equipment and systems, and definition of responsibilities during the MC/ Pre-Commissioning / Commissioning phase. As a minimum all Commissioning activities will be carried out under the approved PTW system with attachments NOSE, MCSSAC, RFCC MC/PC Status indices, PL Reports, Marked up P&ID / SLD, PCSSAC, ZENATOR Status reports as specifically required. Ref: Permit to Work System (PTW). [HOLD] A Task Risk Assessment shall be carried out prior to the commencement of Dynamic Commissioning of all systems undertaken by Commissioning in accordance with the approved Commissioning Procedure. 2.40 Planning and Reporting Planning of Mechanical Completion shall be driven by Commissioning Completion Logic which determines the precedence of priority for each System e.g. Utility Systems such as Diesel, Instrument Commissioning Guidelines - 20130419 Page 13 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes Air, Drains and Electrical Power are required to provide services for all other Project Systems and therefore shall be prioritised for Mechanical Completion. Zenator Power Users shall develop Commissioning Logic, which will be over laid against the COMPANY Commissioning Group programme to produce an overall Commissioning Schedule defining Mechanical Completion of each Sub System by Milestone. Mechanical Completion Sub System Milestones shall be determined by: Site testing required following Factory Acceptance Testing. Equipment Delivery dates. Planned duration of CONTRACTOR Construction and MC activities. Definition of work scope. Required MC Handover dates to meet critical start dates of Pre-Commissioning and Dynamic System Commissioning in order to achieve overall Project Completion Milestones. 2.50 Test Equipment COMPANY Commissioning Group shall maintain a comprehensive list of all Test equipment to be used. This list shall prove that all test equipment has a standard of accuracy better than that of the manufacturer's stated accuracy for the instrument / equipment being tested. Acceptable evidence of the satisfactory condition of test equipment (e.g. copies of up to date Test Certification) shall be provided in accordance with Commissioning requirements. All test equipment shall be frequently checked throughout the mechanical completion period for deterioration. Where test equipment requires an electrical or air supply, Commissioning shall ensure accuracy of voltage and frequency/ pressure and quality. 2.60 Check Sheets Completion Rules All ITR A’s & B check sheets need to follow a standard throughout the MC. & PC. commissioning phases and total handover to operations and maintenance groups. These standards maintain traceability and master record compilation in the handover process. The following rules MUST be adhered: All ITR check sheets are completed in BLUE pen No whiteout or correction fluid used on the document All signature boxes are completed, signed and dated Signatures should be completed as per the signature matrix (See Image Below) Commissioning Guidelines - 20130419 Page 14 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes 2.70 As Built Drawings As built drawings play a significant part in the handover process from MC to PC and final handover to Operations and Maintenance, strict guidelines should be maintained when completing ‘As built documentation to ensure transparency throughout total project phases. As built stamp must be used on every document complete in RED accompanied by the issuer’s Signature, Name and Dated. Changes to any information in the document should be clouded and scratched in RED with the new information clearly and visibly shown. These documents should be attached with associated ITR or necessary paperwork and placed in the relevant sub-system or system dossiers and issued on (SAC) completion. Master drawings such as P&ID’s, Isometrics, SLD’s should be stamped with a BLUE Master Stamp and remain in the Zenator Power User Control until new Revisions are issued and documented accordingly and distributed throughout the system process. As constructed drawings should all be stamped and clearly indicate ‘As constructed and be issued to all relevant Groups using the correct distribution process. 2.80 Limits of System Handover (LOSH) A sub-system is the boundary of equipment, which can conveniently be grouped for the purposes of dividing a larger system into more manageable sections for mechanical completion and when all the subsystems are agreed as mechanically complete, the larger system can in turn become mechanically complete. Each Sub System shall be allocated an alpha numeric code. Every item of equipment within each Sub System e.g., piping, cables instruments etc. shall be referenced by its assigned Sub System number. The boundary limits of Sub Systems shall initially be identified by COMPANY Commissioning Group on marked up, colour coded P&ID's, Layout Drawings and Electrical Single Line Drawings. These documents remain custody of the Commissioning Group. The boundary limits should follow simple guide lines in order to ensure a simple handover process throughout the project phases. Commissioning Guidelines - 20130419 Page 15 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes 1. 2. 3. 4. 5. Commissioning Guidelines - 20130419 The separation of process trains into individual systems Boundary limits finish on a flanged connections or skid packages Heat exchanger’s, coolers etc are only defined in a single sub-system * * Page 16 of 17 19 April 2013 ZENATOR SYSTEMS Commissioning Guidelines & Notes 3.0 APPENDICES Appendix A Appendix B Appendix C Appendix D Appendix E - Commissioning Guidelines - 20130419 COMPANY Commissioning Process COMPANY ITR A & B Distribution Flow Chart System Handover Process Handover Flow Chart Authorized Signature Matrix Page 17 of 17 19 April 2013