Syed Aamir MSc (Eng) Process Safety and Loss Prevention MANAGING AN ONSHORE OIL & GAS PRODUCTIOON FACILITY MSc Process Safety & Loss Prevention 0 Dissertation Project A study on the comparison of different preventive maintenance strategies using PESTEL technique Submitted by:Syed Aamir Abbas Shah Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Table of Contents List of Figures ............................................................................................................................................. 1 Abbreviations .............................................................................................................................................. 2 1.0 Executive Summary .............................................................................................................................. 3 2.0 Introduction ........................................................................................................................................ 5 3.0 Literature Review .............................................................................................................................. 7 3.1 What is ageing plant ......................................................................................................................... 7 3.2 Ageing Mechanism........................................................................................................................... 7 3.2.1 Material degradation............................................................................................................................... 7 3.2.1 Obsolescence ......................................................................................................................................... 8 3.2.1 Organizational Issues ............................................................................................................................ 8 3.3 Current Work .................................................................................................................................... 8 3.4 Evolution of maintenance strategies ................................................................................................. 9 4.0 Maintenance Strategies, Challenges & Performance measurement .................................... 12 4.1 Remaining Useful Life (RUL) prediction in oil & gas industry .................................................... 13 4.2 Risk-Based Maintenance Strategy .................................................................................................. 15 4.3 Reliability-Centered Maintenance Strategy.................................................................................... 17 4.4 Condition-Based Maintenance Strategy ......................................................................................... 21 4.5 Planned-Preventive Maintenance Strategy ..................................................................................... 24 4.6 Importance of maintenance planning ............................................................................................ 26 4.7 Challenges in maintenance for an oil and gas production facility ................................................. 31 4.8 Maintenance Performance Measurement and Indicators ............................................................... 33 5.0 Comparison of maintenance strategies using PESTEL ......................................................... 37 5.1 PESTEL Technique ....................................................................................................................... 37 5.2 RBM strategy analysis using PESTEL framework ........................................................................ 39 5.3 RCM strategy analysis using PESTEL framework ........................................................................ 42 5.4 CBM strategy analysis using PESTEL framework ........................................................................ 46 5.5 PPM strategy analysis using PESTEL framework ......................................................................... 50 6.0 Conclusion & Future Work .......................................................................................................... 55 6.1 Conclusion ...................................................................................................................................... 55 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 6.2 Future Work .................................................................................................................................. 58 References ............................................................................................................................................... 60 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project List of Figures: Figure 1: Development of maintenance philosophies…………………………………………10 Figure 2: Development of consequence scenario……………………………………………...11 Figure 3: Possibility of life extension via performing inspection. ……………………....…….11 Figure 4: Systematic approach for managing plant aging……………………………………...12 Figure 5: Typical decision framework of the CCEB method…………………………………. 22 Figure 6: Bathtub curve……………………………………...…………………………………24 Figure 7: Maintenance-related accident scenario for the Texas City Refinery……………...…28 1 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Abbreviations: RUL-Remaining useful life RBI-Risk-based inspection RBM-Risk-based maintenance O&G- Oil ang gas CBM-Condition-based maintenance PPM-Planned preventive maintenance RCM-Reliability-centered maintenance I&M-Inspection & maintenance PM-preventive maintenance NDT-Nondestructive testing MPIs- Maintenance performance indicators PI-Performance indicators TBM-Time based maintenance PESTEL-Political, Economic, Technological, Environmental and Legal 2 Dissertation Project Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 1. Executive Summary Managing an ageing oil and gas production facility is very challenging task due to various factors like cost of maintenance, degradation and wear and tear in machinery/equipment, risk of sudden failure due to ageing and other factors that are explained in section 4.7. Numerous preventive maintenance strategies have been developed over the past few decades, like PPM, CBM, RCM and RBM to effectively counter these issues and successfully run an ageing oil and gas production facilities. Remaining useful life estimation (RUL) is a quite helpful in condition monitoring and it is very effective for cost-effective operations and developing maintenance requirement for an aged plant. This study compares different maintenance strategies being used in oil and gas industries based on PESTEL and two other factors (section 5). PESTEL technique has never been used before to analyze or compare the maintenance strategies. This paper considers all the factors of PESTEL (Political, economic, social, technological, environmental and legal) for the comparison of the maintenance strategies. There is very less to no information related to political, social and legal aspects of the different maintenance strategies. However, economic, technological and environmental aspects provide sound basis for the comparison. This paper reviews the different aspect of preventive maintenance strategies in relation to their effectiveness to an ageing oil and gas production facility. Maintenance requirement for static and rotatory equipment installed in an oil and gas production facility are different. One single strategy is not sufficient to deal with the issues of every equipment. In section-5, the study shows that CBM strategy is suitable for rotatory equipment and static vessels but it is unable to predict the hidden faults in protective devices and redundant equipment. Similarly, RCM is more focused on the function of the equipment and machinery and is perfect strategy in providing maximum availability of the equipment and reducing unnecessary maintenance. RBM strategy covers the wide range of issues of an ageing oil and gas production facility (section 4.2 & 5.2). RBM requires to carry out the quantitative risk assessment in addition to the failure mode analysis and prediction/likelihood estimation. This strategy is most effective in quantification of the physical risks, like fire, explosion due to loss of containment. In addition to this, it provides deep insight to the top management in cost cutting related to unnecessary maintenance of low risk equipment and machinery. 3 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Overall one single strategy is not enough to cover all the issue of an ageing oil and gas production facility. PESTEL analysis performed in section 5, brings forward the strengths and weaknesses of these preventive maintenance strategies to decide on which strategy should be used for the concerned problem. This paper looks how each PM strategy influence risk reduction, equipment availability, cost reduction and increasing design life of an ageing oil and gas production facility. 4 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 2. Introduction: Managing an onshore oil & gas aged production facility: Management of ‘an Oil & Gas aged production facility’ is a challenging task. With the passage of time certain factors greatly influence the management of ageing oil and gas plant. This include decrease in oil and gas production, high maintenance cost or breakdowns due to ageing and technological advancement issues. Plant and its installation start deteriorating after some time and this issue escalates when production start decreasing, plant experiences wear and tear and oil prices fall. This is because with low production and high maintenance requirement overall revenue and profit falls greatly and it becomes difficult for the owners and operators to spend more money on maintenance related requirements and running the plant with profit. Owners and operating companies face big challenge of maintaining those aged assets with high risk and low profit. Section 4.7 explains the challenges due to ageing plant. Different strategies are used to reduce the risk arising from ageing of these onshore oil and gas plants and run them with acceptable risk. Preventive maintenance strategies are thoroughly explained in section 4 of this project. Maintenance strategies for new and old oil and gas production facility cannot be same due to various reasons. For example, with time the production starts decreasing as the well pressure drops after couple of years of production, this greatly reduces the revenue and profit of the operating company. Therefore, the same conventional ‘Time based’ maintenance strategy is not adequate to operate the facility with fixed interval of maintenance as it requires significantly high cost. Another important factor related to ageing is the age itself. Wear and tear of all the critical devices and equipment like ESD devices, pressure vessels, storage tanks, rotatory and static equipment at the field increases with the time. After some time, chances of hazardous chemical release and fire and explosion increase. At this stage, operating companies and clients normally perform cost to benefit analysis to check whether the running the plant any further is cost effective or not. Risk analysis and different maintenance strategies are discussed to reduce the risk and keep the plant running. PESTEL framework in section 5 of this dissertation project is used to makes a comparison of the maintenance strategies. 5 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Different companies adopt different strategies to encounter the ageing plant issue. For example, some companies do risk transfer by selling the ageing plant, some outsource their operations, while some work on maintenance strategies to reduce the operational cost and keep the plant running. In this project, the focus will be on the maintenance strategies for managing an ageing onshore oil and gas plant. Maintenance activity is the key to run the plant and control the risk arising from wear and tear of the plant with ageing. At the same time, the cost related to the maintenance is a significant issue, therefore, conventional preventive maintenance strategies are not effective. Moreover, different maintenance strategies focus on different aspects of the plant and equipment, therefore, a thorough comparison will be made to find out which maintenance strategy is best for an old oil and gas production facility. Challenge in the maintenance strategy selection is not only the cost reduction but at the same time risk reduction which is the major concern once the operator or client decides on running the plant. Comparison of maintenance strategies will be based on the main risk reduction with minimum cost and resources. 6 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 3. Literature Review 3.1. What is ageing plant? The term ageing plant is often construed and it is not just about the total age of the plant and its expected life. There are many old plants that are fit for their intended purpose and do not pose high risk. Ageing plant is the one which may or may not be considered fit for the intended purpose due to significant deterioration that had occurred within the plant and could increase the chances of its failure. This has been defined in the following way by HSE UK in “Managing Ageing Plant”. Ageing is not about how old your equipment is; it is about its condition, and how that is changing over time. Ageing is the effect whereby a component suffers some form of material deterioration and damage (usually, but not necessarily, associated with time in service) with an increasing likelihood of failure over the lifetime. 3.2. Ageing Mechanism Plants and equipment can suffer deterioration, degradation and wear and tear due to various potential reasons. Once the equipment is installed or manufactured various factors may contribute to their ageing that are: 3.2.1. Material degradation: Material degradation or physical ageing is dependent on the properties of the plant and equipment and the environment in which it is operated. It is also caused by the operational condition of the plant and equipment and installation. All type of materials rotating parts and machinery suffer from ageing due to the following factors that cause material degradation (Håbrekke, 2011). 7 • Corrosion • Weathering • Stress Corrosion Cracking • Physical damage • Fatigue • Instrument drift • Embrittlement • Dry joint development • Erosion • Detector • Subsidence • Contraction & expansion poisoning Syed Aamir Dissertation Project MSc (Eng) Process Safety and Loss Prevention 3.2.2. Obsolescence: Obsolescence means when equipment is outdated, replaced by new technology, equipment or system. The older technology is no longer used for the certain activities and processes and pose big challenges to meet certain demands. Obsolescence also include certain needs like extraction of oil and gas from wells that require specific equipment and technology (Håbrekke, • Equipment out of date • New technology • New needs • New 2011). requirement 3.2.3. Organizational Issues: This deals with the need of clear cut responsibilities for the operation and maintenance of the equipment and transferring of knowledge and skills from the retiring personnel to the new young stuff. Competency of young operator and engineer is critical. Factors that can contribute are (Håbrekke, 2011): • Reorganization • Ageing of personnel • Transfer of knowledge 3.3. Current Work: There is currently a lot of published material and work available about the strategies and techniques for the life extension of the oil and gas installations. Over the past few years lots of researcher and veterans have tried to assess the viability of an aged plant and scope of its life extension. Mahmood Shafiee published a paper “Life extension decision making of safety critical systems: An overview”, that comprehensively gives an insight in decision making of life extension of an existing aged facility. In this paper author compares the existing strategies that are currently being used to manage different hazardous industries plant’s and how the best strategy could be applied in to extend the useful life of the ageing facility. Isaac Animah published a paper “Condition assessment, remaining useful life prediction and life extension decision making for offshore oil and gas assets”. In this 8 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project paper, author lists different techniques that are currently being used for the offshore plant condition assessment, predicting remaining useful life and how life extension decision could be made. Inspection and maintenance is one of the key element in oil and gas plant operations and these processes also play instrumental role in the decision making of plant useful life extension. In this key area, numerous studies have been carried out optimize the processes and increased the critical devices life. ‘Journals of Loss Prevention in the Process Industries’ has published many articles on risk based inspection and maintenance strategies to give insight into the ways of increasing reliability and availability of the plant. Khan and Sadiq (2004), published a paper on risk-based maintenance and its economic viability. Khan & Mahmoud (2004) published another paper on RBM. This paper details how the RBM can be implemented in process plant through risk estimation and defining optimum maintenance interval that reduces the unnecessary maintenance cost. Shiao (2005), wrote a paper on RBM optimization using probabilistic algorithm. This paper is quite useful in accurate estimation of the probability and likelihood of failure. With the growing complexity and advancement in the technology, it has become difficult for operators and clients to decide about the most suitable maintenance strategy. (Ahmad 2012) gives an overview of the TBM and CBM strategies and their application in the industry. This paper gives deep insight in decision making about how these strategies could be implemented in process industries. Endrenyi (2001) also presented a paper on the comparison of the existing maintenance strategies. In this paper author also explains the advantage of RCM as it gives insight to the management to decide on maintenance interval rather than following fixed planned interval. 3.4. Evolution of Maintenance Strategies: Initially the corrective or break down maintenance was the main form of maintenance. But with the passage of time other strategies were developed that include, preventive maintenance, condition based maintenance, reliability centered maintenance and risk based inspection and maintenance. Below picture show the evolution of the maintenance strategies with the 9 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project time. In 1940s, there was conceptive of corrective maintenance only. But within few decades preventive maintenance gained huge importance and many strategies like PPM, CBM and RBM have developed to cater the issues of economic and safety (Ratnayake, 2012). Figure 3:Development of maintenance philosophies. (Ratnayake, 2012) Preventive maintenance is an effective tool to reduce the unexpected failures, downtime cost and possibility of catastrophic failures. RBM is the latest of the maintenance strategies and has been affectively applied in offshore oil and gas (O&G) industry. This technique as described in detail is quite useful in process industry in predicting the likelihood of the failure and its possible consequence. Therefore, gives great insight to the owners and management to decide on the optimum time interval for the maintenance of critical equipment. Around 80 percent of the total risk in process industry are caused by 20 percent of the equipment. Therefore, RBI and RBM can effectively be used to prioritize the maintenance activities for the equipment and installation based on the calculated quantified risk. There is a little difference between the RBI and RBM strategies in terms of implementation. In general, these strategies require dividing the 10 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project system into sub system then calculating risk using consequence modeling and in the end planning maintenance. Below pictures clearly explains this (Ratnayake, 2012). Figure 4: Development of consequence scenario. (Ratnayake, 2012) Ageing is not only about the equipment but also the changes that have occurred in the equipment over time. Therefore, life extension of an ageing equipment is the process of continuous inspection and maintenance of the right equipment, on the right time based on the accurate data and information. Below picture explain the life extension through inspection and maintenance. This shows that with adequate inspection failure can be predicted and with proper maintenance design life could be extended (Ratnayake, 2012). Figure 3: Possibility of life extension via performing inspection. (Ratnayake, 2012) 11 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 4. Preventive Maintenance Strategies, Challenges & Performance Measurement: Since the oil & gas facility ageing is a big challenge for the operators and stake-holders, its maintenance and continual operation require rigorous review of the strategies and techniques being used for the life extension and operating ageing plant. Various factors are involved while deciding on whether to continue operating the current facility equipment or installation or to abandon it. These factors include, high cost, low profitability, increased risk, increased maintenance and inspection intervals, technological advancement, increased downtime and oil and gas prices (Ramírez, 2011). There are several existing maintenance strategies to assist operators and stake-holders to extend the useful life of existing plant and operate it with controlled risk. The aim of this dissertation is to elaborate various such strategies that are currently being used to manage the aged oil and gas facility and make a comparison of them based on their advantages and disadvantages (Ramírez, 2011). Figure 5 (Ramírez, 2011) Figure 4: Systematic approach for managing plant aging. ( Ramírez, 2011) 12 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project The above picture explains the management of an aged plant in a flow chart. This shows that a huge data is required for managing the aging plant. Then this data and information is interpreted to focus on the critical equipment. Ageing monitoring for the critical equipment is carried out in the later phase and in the end decision is made for the maintenance or replacement. This circle is repeated for the aged plant. The focus of this dissertation project will be on the maintenance strategies for an aged oil and gas facility. These techniques include monitoring, inspection and maintenance strategies that could be developed for the ageing plant. First a brief description of different maintenance strategies will be given to give understanding of the procedure of carrying out them, what is their focus and application. 4.1. Remaining Useful Life RUL prediction in oil & gas industry: It is the estimation of the life of the equipment installation during which it could be operated safely at acceptable level. There is various critical equipment in an onshore oil and gas facility that require a life estimation near their end of useful life. These equipment for example includes, safety critical devices, separators, oil & gas pipelines, generators and compressors. RUL is a quite helpful in condition monitoring and it is very effective for cost-effective operations and developing maintenance requirement for an aged plant. For an aged oil and gas plant, where there is big challenge of low production, high operational cost and increased risk, this technique is quite useful in giving insight to the management in decision making. There are different ways of estimating useful life, that are physics based approach, data-driven and fusion which is hybrid of both physics based and data driven (Animah, 2017) Physics based approach: In this approach, theoretical mathematical model is built to estimate the degradation and damage to the equipment over time. Corrosion, wear and crack propagation and their rate can be predicted by using this approach. This model requires using partial differential equation and can be useful when access to data is limited or not available. Various studies have been carried out for offshore and onshore 13 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project plants to estimate corrosion, cracks and erosion issues. This technique is quite useful for critical equipment’s life estimation once they are aged enough and require a decision to be replaced or be used further (Animah, 2017). Data-driven approach: This approach relies on the historical data of safety related of the equipment to establish the connection and develop the future trend of failure and useful life. However, in some cases, there may not be sufficient data available or the data may not be very reliable to be used to predict the further trend, therefore, this one of the big limitation of this approach. If the data is accurate and available this technique can be used for measuring the current condition, cause and condition of the issues with the equipment and predicting its useful life. Data accusation is done through sensors signal using artificial networking and other models (Animah, 2017). Fusion: In this technique both the physics based approach and data-driven are combined in a way to use their strengths and reduce the effect of their weaknesses. This technique uses the principles behind the physics of failure approach to select the system for data-driven technique for diagnosis and prognosis. Therefore, the eventual RUL model is based on both the techniques fusion (Shafiee, 2017). 14 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 4.2. Risk based Maintenance RBM Strategy: Risk based maintenance methodology is aims to reduce the overall risk of the plant. In high and medium risks situations, focused inspection and maintenance is required whereas in low risk scenarios, less effort is needed. RBM suggests sets number or recommendation to for preventive action and tasks required. Quantitative risks are normally calculated and sets the basis for prioritization of inspection and maintenance. In RBM the whole system is divided in to small units and for each unit risk is calculated and compared with the tolerable risk. If the risks accede the acceptable risk, the hazardous scenarios are re-evaluated for optimal inspection/maintenance duration that would bring it down to the tolerable risk. The results obtained for all the units are then combined to develop an overall maintenance plan for the system (Khan 2004). Risk estimation: risk estimation is the first step in the RBM. It includes, development of failure scenario, consequence assessment, probabilistic failure analysis and finally risk estimation. In development of failure scenario, a typical failure situation is described. It describes what could happen, so that a preventive strategy could be developed. Failure scenarios depend upon the physical condition, operating environment and characteristics of the system and inputs. In consequence assessment, quantification of the consequence is carried out. Consequence are quantified in terms of damage radii, damage to property, environment and people. In consequence assessment, wide range of models are used. For example, in source model, rate of release, flashpoint and evaporations are calculated. Models for fire and explosion are used to calculate the characteristics of the fire and explosion. In total four different categories of consequences are combined in consequence assessment, that are system performance loss, financial loss, human health loss and environment and ecological loss. After completion of consequence assessment, probabilistic failure analysis is carried out. This is done by using fault tree. It’s an analytical tool to determine the occurrence of a hazardous undesired event. This can be done by using equipment failure data and human reliability data to determine the probability and frequency of the hazardous event. In this step of RBM, many fault tree analyses are carried out for different initiating events that 15 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project may lead to the final event of the hazardous scenario. In the end, risk estimation is performed based on the results of consequence analysis and probability/frequency estimates. The risk estimation includes factors of fatality, environment, economics and system/production losses. This risk is the total risk of the system and it is compared with the tolerable risk (khan,2004). Risk Evaluation: In risk evaluation first thing is to set up an acceptable risk criterion and then comparing the risk against acceptable risk. Setting up an acceptable risk is different from company to company. There is no strict rule for that. In this step company sets up the acceptable risk for its system or hazard. Some of the common risk criteria is ALARP (as low as reasonably practicable). In risk comparison, the computed risk is compared with the set tolerable risk. The risk for any component/unit if exceeds than the tolerable risk is marked for further analysis to reduce it further (Khan, 2004). Maintenance Planning: Once the risk evaluation is completed, maintenance plan is developed. The first step in developing maintenance plan is estimation of optimal maintenance duration. In it, those equipment and units having increased risks are subject to detail investigation. This investigation includes details analysis of the basic causes of failures and their functions. A detailed reverse fault tree is constructed using this information to achieve the targeted failure probability. This study gives optimal maintenance time for the equipment under study. A maintenance plan then could be organized based on the maintenance time that comes out in first place. Re-estimation and re-evaluation of the risk is performed for the equipment and systems to check that the proposed maintenance plan has decreased the risk to the sufficient level or not. This gives a kind of validation and verification of the planned maintenance program (Khan, 2004). 16 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 4.3. Reliability Centered Maintenance (RCM) Strategy: Reliability-CenteredMaintenance is method of maintenance planning development in aircraft, oil & gas, nuclear and several other industries. Main objective of the RCM is to reduce the cost of maintenance by focusing on the key performance related function of the system and avoiding maintenance programs that not very important. If there already exist a preventive maintenance plan then RCM analysis helps to eliminate or reduce insignificant maintenance (Rausand, 1998). Cost is a big issue in aged oil and gas production facility. With increased risk and less production qualitative preventive maintenance techniques are not very effective. Therefore, to find an alternate quantitative preventive maintenance strategy are considered to extend the life of the plant and controlling the risk at the same time. RCM technique is therefore, a useful tool to manage the old oil and gas production facility. RCM analysis is carried out in a sequence of steps that are; Study preparation: The first thing in RCM is to set the objective and defined the scope of the analysis. Requirements, policies, procedures and acceptance criteria with respect to the safety aspects should be set to define the boundaries. All the resources should be available including human resource, data, unfractured and process and equipment detail (Rausand, 1998). System Selection & Definition: In this step, a decision is normally taken about the plant, system or equipment on which RCM analysis is to be carried out. And on what system the RCM analysis could be beneficial as compared to the traditional maintenance techniques. Principally, RCM benefits all system, but due to limited resources as in ageing plant, priorities are set to limit the cost. Similarly, the system or the plant which is normally comprises of several equipment and installation is broken down into small sub-systems and units. This is done to pick the safety critical equipment for the RCM analysis (Rausand, 1998). Function failure analysis FFA: In this step, the systems required functions and criteria are defined, input interfaces for the system operation are defined and ways in which system can be failed. System usually have many different functions. In this step, all the necessary functions are identified. These functions include, essential functions which are instrumental to 17 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project fulfill the intended purpose of the equipment, auxiliary function which are required to support essential function, protective function which are required to protect people, environment and equipment, information function which are required for condition monitoring like gauges and alarms, interface function which are required for interface between the item in question and other, online functions which are required to update the user about the status of the system, off-line functions which are used infrequently and its availability is not known unless tested this include emergency shut down valves and other emergency instruments (Rausand, 1998). Failure fraction analysis is to identify the different failure modes of the system. Failure mode include, sudden failure which cannot be predicted in advance by any testing or examination, gradual failure which can be predicted by inspection and testing. An important failure is the ageing failure, which likelihood increases with the time and wear out. Ageing failures are sometime termed as the gradual failures. In other cases, these failures can be termed as sudden failure, as with the passage of time the systems inherent resistance and capability reduces and failures occur (Rausand, 1998). Critical item selection: In this step those items in the system are identified which have critical functions. These items are termed as functional significant items. In complex system, there is a need of formal approach to identify the functional significant items. This can be done by using fault tree, event tree or reliability block diagram. In addition to this, equipment and machinery with high maintenance cos, long repair time, low maintainability and items that require external maintenance are identified (Rausand, 1998). Data collection and analysis. Input data is required at various step of the RCM analysis strategy. This data includes, design parameters, drawings, reliability and operational data. Reliability data is important to describe the criticality of the function of the system and optimize the preventive maintenance for it. This include mean time to failure MTTF, mean time to repair MTTR and failure rate. In ageing facilities, failure rate increases with the time indicating that the equipment or item is deteriorating with the time. This reliability data is collected from the monitoring of the existing equipment and from the external sources where similar equipment and installations are used (Rausand, 1998). 18 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Failure Modes, effect and criticality analysis (FMECA): Objective of this step is to identify the dominant failure modes of the maintenance significant items MSI. FMECA is a detailed analysis in which critical items are selected, there functions are described, failure mode is explained, effect of failure is outlined and failure cause is explained. This gives the pretty good idea of the possible failure ways and criticality of the equipment or item. For each failure mode, maintenance action is proposed, which is explained in the next step (Rausand, 1998). Selection of Maintenance Action: This step is a bit novel as compared to the other maintenance program. RCM logic input is used to assist the analyst through FMECA described failure modes. The main idea of this step is to decide whether preventive maintenance is applicable and effective or let the failure occur and corrective actions is sufficient afterwards. The basic maintenance task that are decide in this step are, scheduled on-condition task, scheduled overhaul, scheduled replacement, scheduled function test and run to fail. Preventive maintenance does not prevent all failures. If there is a failure that cannot be addressed through this technique then for sure the modification or redesigning is inevitable. The selection of different preventive maintenance task depends upon criteria and need. For example, for ageing oil and gas production facility, in a situation of hidden function with ageing failure, both function test and scheduled replacement are required (Rausand, 1998). Determination of maintenance interval. Optimal interval determination for the maintenance is a challenging task and it must be based on the failure rate of function, cost involved in the consequence and maintenance. Since with the ageing equipment and unit manufacturer proposed interval is less reliable, therefore, based on the failure rate data, picking the periodicity that seems optimal. Later, based on the characteristics of the equipment periodicity can be increased or decreased (Rausand, 1998). Preventive maintenance comparison analysis: The criteria for selecting RCM is based on the two things, that are, applicability and cost-effectiveness. Applicability means the preventive maintenance task should be applicable in terms of reliability knowledge and failure mode. PM task is applicable if it can eliminate the failure mode or at least it should be able to reduce the probability of its occurrence. The PM cost include the cost of failures related to maintenance, risk of exposure to the personnel, risk and 19 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project cost of failures of another component and the cost of physical resources. Cost of failures include the loss of production, violation of laws and regulations, plant and personnel safety reduction, increased premiums, emergency repairs and high replacement repair (Rausand, 1998). Treatment of non-maintenance significant items: Non-critical items are not analyzed in RCM. Brief cost analysis need to be carried out for the existing maintenance program for these items. If the cost is insignificant then this program should be run as it is. Implementation: Implementation of the results of the RCM requires that the organizational and technical maintenance support functions are available. Many of the accidents happen during or after the maintenance, therefore, it is extremely important to carry out human behavior risk assessment and task risk analysis. This will greatly reduce the chances of failures resulting from human error (Rausand, 1998). In service data collection and updating: One of the major advantage of the technique is that the data we collect during operation after the RCM analysis can be incorporated into the RCM analysis. For example, if some failures occur and it is not covered in the FMECA, it can be included into it with little revision. This revision does not require significant resources as the basis of the analysis has already been done. It does not require to consider all the steps in the analysis. During revision, it is not sufficient to consider only plant being analyzed, it is mandatory to consider all the factors like, contractual requirements and development in the legislation while performing review and update (Rausand, 1998). 20 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 4.4. Condition-based Maintenance (CBM): Condition based maintenance is one of the most advance maintenance techniques. It is a management philosophy in which the decision of repair and replacement are based on the current and future condition of the asset. Changes in the condition and performance of the assets are observed and the decision of the maintenance is based on them. Optimum time for the CBM is determined through actual monitoring of the equipment/unit and its subparts. This condition monitoring varies from the simple visual inspection to the automated tools for the condition monitoring (Ellis, 2008). The heart of the CBM is the condition monitoring, where the condition is continuously monitored through the certain sensor and other appropriate devices. Monitoring parameters include, vibration, noise, lubrication oil, contaminants and temperature. Maintenance is performed only when there is need for it or there is likelihood of failure. Main objective of the CBM is to assess the real-time condition of the equipment/system, to decide about the maintenance to reduce the time and unnecessary cost related to the maintenance. In general, the purpose of the monitoring is twofold. First thing is to identify the condition of the equipment and second thing is to identify the causes of the failure and increase knowledge about the deterioration due to ageing and usage (Ahmad, 2012). Condition monitoring (CM) can be performed in two ways: on-line and off-line. On line monitoring is performed while the equipment is running condition. While in off-line monitoring equipment is required to stop running. CM can also be done either by continuously or at certain specified intervals (Ahmad, 2012). Maintenance decision in CBM strategy can be categorized into two ways: diagnosis and prognosis. Diagnosis is the process of finding the source of faults in the unit/equipment, while in prognosis probability or likelihood of failure is estimated. The aim of prognosis is to find the early warnings and signs of failure and its likelihood in the equipment and system. If the equipment is run in abnormal condition it does not mean the equipment has failed, it may run for certain period. Therefore, prognosis is compulsory to perform (Ahmad, 2012). 21 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Prognosis is better than diagnosis from maintenance point of view in a way that it can prevent unexpected faults and failures hence, saving cost of unplanned maintenance. In CBM, decision can be made using prognosis for equipment deteriorating modeling. This model as shown in the below picture gives insight of the current equipment condition and can predict future deterioration. Current condition data is collected for modeling purpose, then modeling is carried out to estimate the equipment condition at present. Then this is compared with predefined failure limit. If the condition of the equipment is over or exceed the limit, the equipment maintenance will be mandatory at this point. Otherwise it is assumed the condition is good and does not require any further maintenance for certain period (Ahmad, 2012). Figure 5: Typical decision framework of the CCEB method. (Ahmad, 2012). 22 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Vibration Monitoring: most popular technique of rotating equipment is vibration monitoring. In oil and gas industry like generator and compressors condition can be monitored using this technique. It requires certain sensor to be installed on the equipment to measure the vibration and the changes or increase pattern of the vibration over time. This can be done either using continuous monitoring strategy or at specific intervals (Ahmad, 2012). Sound or acoustic monitoring: This has a strong relation with the vibration monitoring technique of CM but there is a fundamental difference between them. Vibration monitoring sensor are mounted on the equipment and measure the motion while in sound monitoring, sensors measures the sound of the equipment. Again, this technique is quite useful in measuring the difference in the sound with the time and usage of the equipment and help the maintenance team in deciding on the maintenance time and interval (Ahmad, 2012). Oil analysis or lubrication monitoring: This is another important CM technique used for the rotatory equipment. In this technique condition of the lubricating oil is tested regularly to measure weather the oil is effective to be used further or should be discarded. This also gives the insight of the internal condition of the oil wetted parts of the equipment. This technique has two general purpose, one to check the quality of oil and other to safeguard the component involved (Ahmad, 2012). Other CM technique: Apart from above, there are few other CM techniques that include electrical, temperature and physical condition monitoring. Electrical monitoring involves monitoring changes in certain properties, like electrical resistance and conductivity. This technique helps in identifying faults related to insulation and motor rotor bars. Temperature monitoring is also applied on the condition monitoring of electric and electronic parts of the equipment. Physical condition monitoring is used to 23 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project monitor the physical deterioration of the equipment and material like cracks propagation, corrosion and erosion. This technique is useful for ageing pipelines, structures and pressure vessels (Ahmad, 2012). 4.5. Planned-Preventive Maintenance(PPM): It is a tradition maintenance strategy which is also known as Time-based Maintenance (TBM). In this strategy failure time/rate is estimated to determine the optimum maintenance interval. In PPM, it is assumed that the failure rate is predictable and this assumption is based on the failure rate trend of the equipment known as bath tub curve. Figure 6: Bathtub curve. (Ahmed, 2012) Age of the equipment or unit is estimated based on the failure time. Failure rate or trends are divided into three sections: burn in, useful life and wear out. In burn in equipment experiences decreasing trend in failure rate, useful life phase experience near constant failure rate. In wear out phase, failure rate increases as shown in the above picture. (Ahmad, 2012). 24 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Once the structure of the equipment is identified then suitable maintenance planning is developed. Non-repairable items require replacement policy. This replacement policy is age-related. Once the age of equipment is reached or first failure occurs, equipment is replaced. After replacement equipment is consider as good as new (Ahmad, 2012). For repairable items, repairing policy is used. In this policy, optimum interval is selected for the maintenance or repairing of the equipment/machinery. In this strategy, the interval for the maintenance is selected based on the failure time and likelihood. This selection is based on the expected run time of the equipment machinery and its possible failure time. Vendors or suppliers recommends the client this information to carry out maintenance. (Ahmad, 2012). Planned preventive maintenance is normally vendor or supplier specified. Interval selection is usually based on the parameters like hours of operation/use. Repairing and maintenance cost for the time-based maintenance is normally high due to overmaintenance. Sometime the parts and equipment is still can be used further but due to schedule time and interval maintenance must be carried out and certain parts, although usable but must be replaced as given by vendor. It has view advantages over CBM and other maintenance strategies in a way that it does not require any formal condition monitoring for defining the maintenance interval. In fact, PPM is planned according to the vendor recommendations or legislation requirements. In PPM, the cost more evenly distributed as the interval for maintenance are pre-defined and does not require any analysis and does not require and further equipment or devices for supervision. PPM, however, has great disadvantage of over maintenance that incurred due to already planned intervals. With the ageing plant planned and schedule maintenance is more often difficult to carryout due to cost implications. According to (Ahmad, 2012) 20% to 42% operational cost of the plant is related to the maintenance. Reliability is another issue associated with PPM strategy as there is no condition monitoring and failure likelihood prediction using analytical tools as in CBM and RCM. 25 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 4.6. Importance of Maintenance Planning: In Oil & gas industry equipment and installation undergo very harsh processes and conditions. In addition to it, many ageing factors and erosion, corrosion and wear further deteriorate the condition of the equipment. This sometime results in unpredicted failures of the plants and equipment that causes huge financial losses, health and safety implications and catastrophic damage to the environment. To address this issue, improvement in equipment reliability and availability can be done using inspection and maintenance. Normally the cost associated with inspection and maintenance is very high and is around 20 to 30 percent of the total operating cost (Ratnayake, 2012). A detailed analysis of aviation industry from 1959 to 1983 revealed that 12 percent of the incident happened due lack of adequate inspection and maintenance. Similarly, in 20110, Deepwater horizon, drilling rig suffer major blowout in the Gulf of Mexico. Later investigation revealed that this rig had not been sent to dry dock for shorerepairing for nine years. Due to this, blowout preventer certification could not be renewed. These investigation shows the importance of the mandatory and cost-effective inspection and maintenance of the equipment and installations in the plant (Ratnayake, 2012). I&M management requires the understanding of ageing plant. It is not about how old equipment is, in fact it is related to the condition of the plant and the factors that influence it. Ageing is the process of continuous degradation which results from the time and the usage of the equipment. Important thing is to understand and reveal the factors and symptoms of ageing that can be detected through inspection. Once these factors are determined, decision can be made on how to proceed with the maintenance plan to increase availability (life extension) and reduce chances of unexpected failure (Ratnayake, 2012). Maintenance & some major accidents: Despite numerous efforts and technology advancement to control and minimize the risks and major accidents, the number of accidents in the past has shown that the control is not sufficient. Examples of such accidents in the oil and gas and chemical industry includes, Bhopal Disaster, Phillips 66 26 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Disaster, Sodegaura Refinery Disaster, Flixborough Disaster and Texas City Refinery Explosion (Okoh, 2013). To control and minimize the risk, safety barriers are put in place but these barriers may fail due to vulnerabilities or the deficiencies in maintenance or because of postponing the maintenance. After each incident, lessons are learnt and efforts are made to control the risk and avoid recurrence of the same incident with the same cause. However, major accident rate has not shown positive trend, despite these efforts. In Norwegian oil and gas industry the number of major hydrocarbons leaks has increased from 2008 to 2010. Major accidents do not happen just because of one cause, but often it involves many combined factors. Advance technology and innovation and complexity is a common element of the oil and gas and chemical industry with high potential of major accident. Due to this reason, many independent barriers are installed to control and mitigate consequences of major hazards. In oil and gas industry these barriers are referred as layers of protection and can be categorized as mechanical, physical and electrical/electronics (Okoh, 2013). The integrity of these barriers requires certain maintenance at specific intervals. Maintenance is therefore, key aspect of preventing major accidents in oil and gas industry. However, maintenance may result in negative effect on the integrity of the system if it is performed in incorrect, delayed, insufficient or excessive. Maintenance can also be initiating event of a major accident, for example, operating the equipment wrongly. Maintenance also put people on the risk, therefore, it should be minimized as much as possible. Many authors, like (Khan, 1999), (Kletz, 2001), (Lees 2005) and (CSB 2007) have investigated the major accidents with the view of maintenance involvement as one of the main reasons. Some authors have explained the factors related to maintenance management and involvement of maintenance in the major accidents in the oil and gas industry. Few of the examples are poor communication between the maintenance staff and operators (Sanders, 2005), lack of mandatory maintenance (Hale et al 1998), maintenance management cyclee (Smith and Harris 1992) and maintainability (Hale et al 1998). Few of the major accidents are explained in relation to the accident process and maintenance management structure. 27 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Texas City Refinery Explosion (March 23, 2005): In Texas City Refinery on March 23, 3005, raffinate tower of the isomerization unit was overfilled. This led to overheating of the raffinate tower and eventually all the pressure relief devices were open. This resulted in eruption of hot flammable liquid from the blowdown stack which was not equipped with flare stack. A huge fire and explosion occurred that killed 15 workers and injuring several others (Okoh, 2013). The factors related to maintenance that resulted in this disaster include (CSB, 2007) failure to correctly calibrate level transmitter (maintenance fault), Sight glass was not cleaned (no maintenance) and failure of high level alarm (no maintenance). This shows the maintenance plan was not sufficient to deal with the critical equipment, business targets and maintenance cost were not balanced and the mechanical integrity program was ineffective. Below picture illustrates this explosion and the maintenance failure (Okoh, 2013). Figure 7: Maintenance-related accident scenario for the Texas City Refinery. (Okoh, 2013). 28 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Stockline Plastics Explosion (May 11, 2014): On May 11, 2014, in Stockline Plastics industry, an ageing liquified petroleum gas (LPG), a pipe was buried underground without any corrosion protection, leaked due to rapid corrosion and flammable gas released which caught fire and explosion occurred. The whole building was razed to ground, nine workers were killed and several got injured. One of the main maintenance factor which contributed to this incident is failure to inspect and maintain the pipe of LPG (OSHA, 2012). Other failure factors include, inadequate risk assessment of the plant and very weak and ineffective procedures and standards of health and safety (Okoh, 2013). DSM Chemical Plant Explosion (April 1, 2013): In DSM Chemical plant on April 1, 2013, an explosion occurred, when maintenance crew tried to start the oven. Oven cover at the top imploded and all the three workers standing on the top, fell into the oven and died. The main issue was the flammable gasses and other dangerous gasses from the plant. These gasses caught up by a stray spark and huge explosion resulted. Normal procedure for the restart requires filtering all the gasses and plant has to be shut down, which requires a lot of time. To avoid this, delay a quick procedure was adopted without taking appropriate measures. Maintenance factors that causes this accident are difficult maintenance, flammable mixture development due to failure of testing and adopting new quick procedure. Management failures include business goals and cost control on maintenance. Poor safety culture and failure to develop the plan for the critical maintenance (Okoh, 2013). Sodegaura Refinery Disaster (October 16, 1992): In Sodegaura Refinery in Japan an explosion occurred on October 16, 1992, which killed ten people injured seven. The lock ring of the channel was broken, it was used to cover the heat exchanger cover. This result in blowing-off the ring and other parts including the channel (Okoh, 2013). In this incident, the major hazard was hydrogen which is highly flammable gas. The main factors causing this incident include multiple ratcheting, which wore out the diameter of the gasket which was used to keep the heat exchanger airtight, incorrect 29 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project positioning of the of gasket which resulted in leakage of the hydrogen gas, insolation removal which caused temperature variation and it introduced new hazard of thermal deformation of the inner parts, internal flange set bolts were inadequately replaced, causing their failure and putting more load on the channel cover. Management failure include failure of the user and manufacturer on the information of the parts replacement, poor safety management, inadequate maintenance planning and poor execution (Okoh, 2013). The Phillips 66 Disaster (October 23, 1989): In polyethylene unit of Phillips 66 in Pasadena USA, an explosion occurred, that killed 23 people and injured over 150. A flammable chemical was released, which ignited later and lead to this incident. This incident happened while a scheduled maintenance was carried out on a reactor to clear the settling legs. The chemical was released due to wrong maintenance. The major maintenance factors that caused this incident are, failure to include double isolation using flange or other means in the maintenance procedure, the only isolation valve was kept open and connected to the wrong air supply hose. Management failure include failure to comply with industry isolation procedure, inadequate permit to work system, failure of company’s own maintenance procedures and standards. It was also observed that the maintenance planning and execution was wrong and inadequate to handle the emergency (Okoh, 2013). 30 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 4.7. Challenges in Maintenance for an oil and gas production facility: Many of the oil and gas production facilities have exceeded their design life. Static equipment like storage tanks, valves, pipelines, separators and vessels undergo degradation due to ageing, corrosion and erosion. Operators and plant management usually have database containing historical data of corrosion, erosion and wear. This data with expert knowledge is used to identify the critical equipment of the system to develop maintenance plan for the plant. However, development of the inspection and maintenance plan is very challenging due to uncertainties because of human involvement and difficult decision making. Due to this reason, ineffective inspection and maintenance strategy could lead to escalated degradation that could cause catastrophic failure. In ageing facility where the design life has passed and the production is decreasing rapidly, it is very difficult to maintain the performance and reliability of the plant while reducing the cost. Here are some of the challenges related to the ageing oil and gas production facility (Ratnayake, 2012). • The time for the preventive maintenance is very limited due to tight schedule of production and limited budged. Therefore, it is not possible to carry out all the maintenance in the given time. • There are normally high number of parts of static equipment on the field that have not been inspected since the date of their installation. • Many times, the wall thickness data is not reliable due to the poor interpretation of the NDT data. • Personal and individuals involve in inspection and maintenance planning frequently changes jobs, this ends up in new people taking the jobs of inspection and planning. This makes problems severe because of the ineffective knowledge transfer and experience. • Quality and effectiveness of the inspection and maintenance planning of newly recruited employee is considerably lower than the experience employee. • The decision and views of the inexperienced persons in performing inspection is also seemed to be narrow. This is because of lack of the information and overview of the equipment problem and inclination to depend on the given current information. 31 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project • Time availability and state of mind of the person performing inspection and maintenance planning equally effects the procedure. Knowledge and judgement of the condition and deterioration is depended on the person performing this task which could be limited in stress condition. • Wastage of resources is frequent when the planned maintenance of some of the equipment is not carried out during the shutdown maintenance. In addition to these above challenges there are certain other issue related to the ageing factor of the plant which are given below (Ratnayake, 2012). • There is a need of establishing a system and procedure to collect the data and information related to ageing of the plant and critical equipment. Most of the time there is no sufficient data available for the equipment age and deterioration. • Developing a model and predicting the useful life of the equipment is another challenging task. Skills and expertise of the individual is the main factor that upon which the reliability of the model depends. • Old and new equipment compatibility is a challenging task. With ageing equipment and addition of new technology is difficult to manage. • Investigation of the factors that causes ageing and searching for appropriate measures required to mitigate the effects of ageing. • Review and investigation of the existing maintenance strategy for the ageing oil and gas plant and analyzing its effectiveness in relation to the ageing plant (Ratnayake, 2012). 32 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 4.8. Maintenance Performance Measurement and Indicators: Maintenance performance measurement is very important to justify the cost and resources used for the preventive maintenance program. This can be done by implementing a performance measurement system. The quantitative criteria for the maintenance measurement includes downtime, accidents, injuries, output, short and long stops, risks and costs. Qualitatively it includes, employee satisfaction, working environment, humidity and noise. Measurement is very important because it gives the data to be compared and on the basis or results suitable corrective/preventive action can be taken (Parida, 2007). Decision making in maintenance involved various tier in the organization structure. At the strategic level, it is decided that weather the maintenance program should be centralized or decentralized, policy for in-house maintenance or it should be outsourced. At the plant level, decision is taken about the budget, machinery, skill, experience, inventories and time-based maintenance or any other advanced maintenance strategy. Maintenance performance indicators MPIs are very important as they are related to wastes, expenditures and downtime. MPIs give an analysis of the enhancement of quality, productivity, utilization, safety and health. Therefore, they are used to compare set parameters to give management deep insight on the cost, benefit and risk reduction (Parida, 2007). Maintenance performance indicators are used to measure the impact on the process performance. MPIs can be used for many purposes, for example, financial reports, health and safety assessment, environment monitoring, system performance as well as for many other applications. PIs can be differentiated into two types, leading indicators and lagging indicators. A leading indicator gives early warning and is performance driven. For example, downtime and number of stops gives indication of the less availability of the plant and equipment. This in-turn gives indication of the less plant utilization. Therefore, leading indicator is performance driver and it compares the status of the equipment/plant performance with the reference point. From maintenance point of view, condition monitoring indicator, for example, noise, vibration, temperature, contamination in oil can be performance indicator. These indicators help to assess the condition of the equipment and can be used an early warning. Therefore, these indicators are typically 33 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project used for the effectiveness of the maintenance. Lagging indicators on the other hand, are the outcome measures that are normally used to analyze the deviation once the maintenance activity is completed. Expense of the maintenance and the time gap between the breakdown are the typical examples of the lagging indicators. These lagging indicators are effective in measuring the current performance status and the need for further actions, for example equipment parts replacement, to meet planned target. These are helpful in further decision for the replacement of the parts or future maintenance based on the previous history and status (Parida, 2007). Maintenance cost per equipment/part or the total return on the capital are the typical paradigm of the lagging indicators. Both leading and lagging indicators are used together to control and monitor the effectiveness the maintenance strategy. These indicators need to be in line with the applied maintenance strategy. Lagging indicators without leading indicators cannot help how the outcomes should be materialized (Parida, 2007). Maintenance performance indicators (MPIs) are categorized into seven types based on the requirements and internal organization capability and capacity and the different strategy. Here are some of the key MPIs including both leading and lagging; (Parida, 2007). Equipment related indicators: • Availability: It is the percentage of time of the equipment/machinery available for the intended purpose. This can be calculated by taking the ratio of mean time to failure to the total time. • Performance rate: this rate gives the indication of the production speed. Maintenance activity affects the performance rate and is used for calculation • Number of small and big stoppages: this is used to count the number of stoppages either big or small. These can be calculated in terms of time (hours). • Downtime for small and big stoppages: This gives the indication of the availability and is calculated in terms of time (hours). 34 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Maintenance Task Related Indicators: • Quality for maintenance task: This MPI indicates the efficiency of the maintenance task performed. This depends on the certain factors, for example, time taken for the maintenance to meet operational requirements. Quality of the maintenance is the conformance with the process. Maintenance can be a minimal or major overhaul. The quality of the plant or equipment maintenance depend on the type of parts being used like, used parts, genuine or clone. Maintenance operator skill and expertise are the other factors that influence the quality of the maintenance. • Change over time: It indicates the time required for change-over. It is calculated in hours. • Planned Maintenance Task (preventive maintenance): Planned maintenance task are calculated in terms of number planned maintenance or the cost/expenditure required for carryout preventive/scheduled maintenance. • Unplanned Maintenance Tasks (corrective maintenance): This indicates the number of unplanned maintenance tasks performed or the costs/expense incurred on these tasks. • Response time for maintenance: This indicates the time taken in hours for the maintenance activity. Cost-Related Indicators • Maintenance cost/unit: It is the common indicator of the performance measurement and it distributes the total maintenance cost by the volume of production. • Return on Maintenance Investment: This indicator is used to compare the return gained because of high maintenance cost against the past record/target. This performance indicator is a bit complex to calculate but accurate analysis exactly pinpoints the shortcomings in planned maintenance strategy. 35 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Learning & growth • Number of new Ideas generated: For continuous improvement of the organization, it is essential to measure the knowledge. Number of new ideas produced can be served as the way of innovation and development. This PI is very essential for the management. • Skill & Competency development/training: Training and competency development is very important for the company growth and this indicator gives insight to the management of its employees’ strengths and weaknesses. Number of trainings given, amount spent on trainings, number of employees educated/trained are all good indicators of the human development. These indicators are subjective and are a good measure of the competency and skill development. Health, Safety, Security & Environment (HSSE): Indicators of HSSE include accidents, incidents, injuries, security breaches, near misses and environmental issues. Accidents and incidents results in injuries that causes man hours to loss. Criteria for these kinds of incidents could be the cost incurred and time loss. Some of the performance indicators related to HSSE are as follows: • Number of accidents/incidents: This indicates the safety factors needed and provided by the injuries, losses, accidents and fatalities. This is a very critical PI for the management to decide on further measures requirements. • Number of legal cases: Number of legal cases is another important PI which clearly gives insight about the safety factors in an organization structure. • Number of compensation cases/amount of compensation paid: This indicator shows the negligence from the client/company that lead to the incident and eventually company had to pay compensation. 36 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 5. Comparison of maintenance strategies using PESTEL: In above section, a detail description and overview of four major maintenance strategies is given. In this section, the data will be analyzed based on various factors to come up with the best maintenance strategy for the onshore oil and gas production facility. Since due to strengths and weaknesses of each strategy it is not compulsory that one maintenance strategy itself is enough to fulfill the requirement on an ageing oil and gas production facility. Many techniques and tools are used to analyze the effectiveness of maintenance strategies with respect to their use in oil and gas industry. Here we are using PESTEL (Political, Economic, Social, Technological, Environment and Legal) technique for the analysis of the each of the maintenance strategy. In addition to the PESTEL factors, few more factors will be incorporated for analysis. These factors are, risk reduction, safety culture, 5.1. PESTEL Technique: It is a simple technique to be used to analyze the macroexternal factors that affect the organization. The PESTEL framework consist of political, economic, social, technological, environmental and legal factors. PESTEL framework uses macro-indicators for analysis to give big picture to the strategists for decision making. This gives deep insight to take advantage from the opportunities and reduce the risk factors faced by the organization (Issa, 2010). Political: Political factor is directly related to the government laws and regulations that an organization is compelled to adhere with. From this perspective organization is bound to implement the laws of the country in which it is operating. Since maintenance strategies are directly related to the reliability and risk of the organization, different countries have different set of laws and regulations for the maintenance of the high-risk industries that include oil and gas industries (Issa, 2010). Economic: Economic factors are related to the cost and the amount of financial benefit an organization can gain. While adopting any maintenance strategy there are certain financial implications on the company. Experts analyze the total cost incurred on the specific maintenance strategy and the cost it saves in comparison to the other related maintenance strategies (Issa, 2010). Social: Social factor is the changes to the organization by adopting certain strategy. Social aspects include, customer awareness, public attitude and individual response to the strategy 37 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project adopted. It is the moral duty of the organization to adhere to the set of ethics and be aware of the critical information of the strategy and its implications (Issa, 2010). Technological: Technological aspects include the advancement in the technology and the compatibility of the maintenance strategies with them. And how certain techniques have additive advantage over other in that aspect (Issa, 2010). Environmental: With growing concern over environment globally, it has gain equally high importance in the industries specially in oil and gas industry. In the past, certain incident has shown that if sufficient measures are not taken big disaster can occur which could have catastrophic environmental implications. This factor holds equally high importance in evaluating the maintenance strategy with respect to its effectiveness (Issa, 2010). Legal: for each industry, there are legal implications for its operations and maintenance. These days goal setting legislation practices are common worldwide to cope up with risk arising and taking advantage of the technological advancements (Issa, 2010). Before adoption to any maintenance strategy it is legal responsibility of the company to show that the adoption of this strategy is certainly helpful and robust enough to minimize the risk to the ALARP region. Risk reduction & Availability of the plant/machinery: In addition to the factors mentioned in PESTEL framework, I also included two other factors for the analysis of the preventive maintenance strategies that are “risk reduction & availability of the equipment/machinery”. Preventive maintenance strategies that are described in earlier section have direct relation to the risk reduction to the plant, people environment and reputation of the company. In onshore oil and gas production facility the biggest hazard is the crude oil and gas release. With the aging production plant, the chances of these releases can become bigger as the wear and tear of the plant is high. Maintenance of these plants highly critical with respect to the risk reduction and smooth operation of the plant. Availability at the same time is very important in oil and gas organization. Maintenance strategies equally influence the availability of the plant/machinery at the same time. Since in ageing oil and gas production facility usually with the depleting oil and gas reservoir, availability for continuous and maximum production is very important. Therefore, maintenance strategies 38 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project hold huge importance in keeping the plant running and reducing or eliminating the breakdowns due to faults and malfunction in the equipment/machinery. 5.2. RBM Strategy analysis using PESTEL framework: Risk based maintenance strategy which is now very common in many highly hazardous industries will be analyzed using PESTEL technique. How this technique influences the macro-environment level in onshore oil and gas production facility. Each PESTEL factors will be analyzed with respect to RBM. PESTAL Factors Description and example in relation to the RBM strategy • Political stability and likely changes: RBM strategy does not directly deals with this element of the political factor. However, during risk calculation which is the main aspect of the RBM strategy these factors are analyzed in highly Political volatile political environment. • Environment Law: RBM strategy thoroughly addresses environmental issues related to the maintenance of the oil and gas production facility • Health and Safety Law: During risk calculation and estimation legal requirements are addressed. • Significant cost reduction: RBM strategy often results in significant cost reduction. RBM prioritize the maintenance of item that require frequent maintenance and reduces the frequency of low risk items. Economic • Life extension of the plant: RBM strategy by rigorous maintenance planning and risk assessment aids to increase the design life of the plant and expensive equipment hence saving a lot of money. • Cost cutting of unnecessary maintenance: RBM strategy 39 Syed Aamir Dissertation Project MSc (Eng) Process Safety and Loss Prevention another monetary benefit is the removal of all unnecessary periodic maintenance. Maintenance of low risks are reduced and minimized. • Emphasis on Safety: RBM strategy itself is based on safety aspects of the plant and maintenance. RBM stresses on safety more than all other maintenance strategy. • Lifestyle & work attitude: workers lifestyle and working attitude is greatly influenced by RBM strategy. Risk-based Social maintenance strategy gives awareness to the workers of the potential hazards and catastrophic consequence. This consciousness changes their lifestyle and work attitude more positive, safe and responsible. • Impact on public: Adjacent community and public gets more satisfied with the management of the production facility once they know how much plant management is working on risk reduction and reducing chances of high consequence events. • Basic infrastructure level: RBM is relative new maintenance strategy. It requires skilled engineers and staff to carryout quantitative risk assessment. With new technology and software, it has become easier to perform quantified risk assessment. • Technology changes & Compatibility. Technological changes in oil and gas industries are very rapid over the past Technological factors few decades. RBM strategy in this regard is quite flexible, for example, the development of new software for quantified risk assessment and frequency calculation software and models could generate near real events and these developments assist the RBM in its effectiveness. • Access to new Technology: RBM strategy encourages 40 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project adoption of new technology when comes to development and planning for the maintenance plan using RBM technique. For example, Fault tree analysis and consequence modeling software have made it easy for the engineers to carryout quantified risk assessment for criticality analysis of the process or equipment. • Laws regulating environment pollution: With the growing concern over global warming, countries have made their laws strict for oil and gas companies regarding environmental pollution. Since RBM strategy is based on risk estimation before for maintenance planning, therefore, this strategy Environmental factors considers all kind of risks including environmental pollution and damage while estimating risk. • Air & water pollution: this factor is related to the legal requirements. These factors are considered during the development of the maintenance interval t • Health & safety Law: When it comes to maintenance of the Legal ageing oil and gas facility, operators and clients must satisfy the government bodies about the risk arising from ageing facility. This require aggressive risk assessment and maintenance strategy that could show that the current risk is within the ALARP (as low as reasonably practicable) region. • Ageing oil and gas production facility poses big risk to the environment, people, asset and reputation of the company. In section 2 and 3, it is explained thoroughly how ageing plant poses threat. To overcome these risks and to extend the life of an oil and gas production facility RBM is a very useful Risk reduction strategy. In section 4.2 it is comprehensively explained that adoption of RBM strategy purely works on the risk estimation through probability/frequency calculation and consequence estimation. 41 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project • At the same time, any misleading result or calculation could lead to non-essential maintenance. This could also lead to no decrease in the risk, if the results are not properly calculated or based on incorrect data, as explained in the section 4.2. • Maximum availability of the plant and equipment is the major reason for any maintenance. In RBM frequency estimation of the equipment plant failure is carried out to get Availability an idea of the expected equipment failure or malfunction. Different techniques are used for the failure frequency estimation as discussed in section 4.2. this gives the management an idea to decide on the interval frequency to avoid sudden break downs and increase the availability of the plant. 5.3. Reliability centered maintenance RCM analysis using PESTEL framework: In section 4.3 RCM strategy has been explained thoroughly. Now in this section an analysis will be carried out to assist in judgement for the adoption, feasibility of the RCM maintenance technique for the ageing oil and gas production facility, based on the PESTEL factors. PESTAL Factors Description and example in relation to the RCM strategy • Political stability and likely changes: RCM strategy is purely based on technical aspects of the maintenance and does not deals with the political stability of the region. • Health and Safety Law: Government bodies restrict the oil Political and gas production facilities using HSE laws and set legal boundaries for them for health and safety of the employees 42 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project and the other stack holders. • Significant cost reduction: RCM aims at cost reduction in addition to the maintenance of the plant and equipment. This strategy focuses on the selection of critical equipment for maintenance and avoiding unnecessary maintenance of noncritical equipment by reducing the frequency of the planned/schedule maintenance. This way a lot cost could be saved. Section 4.3 explained this in detail. • Life extension of the plant: Another important benefit of the RCM strategy is the life extension of the plant. FFA & FMECA, the two-important elements of this strategy, explained in section 4.3, focus on the possible failure modes Economic and their analysis. This analysis is directly related to the ageing of the plant. Prevention of the failures in the equipment and timely decision for the preventive maintenance could eventually reduce the wear and tear in the plant and in-turn increase the expected life of the equipment/plant. • Cost cutting of unnecessary maintenance: One of the main point in RCM strategy is the selection of critical equipment for the maintenance and reducing scheduled maintenance for non-critical equipment has direct impact in reducing maintenance cost. This element has already been explained above • Emphasis on Safety: FFA & FMECA analyze the failure modes and their impact. These two elements are focused on the availability of the equipment (section 4.3) but in these analysis safety features are also studied, for example the failure analysis of any safety critical equipment. Social • Lifestyle & work attitude: RCM strategy gives insight to the maintenance personnel about the possible failure modes 43 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project and their impact on the plant/equipment. It brings about the positive change in the workers attitude toward the criticality of the equipment. Those involved directly in maintenance could also be the source of bringing awareness to the other employees on the reliability and safety of the equipment. • Impact on public: Since RCM is reliability focused maintenance strategy, it has direct impact on the public where the onshore ageing production facilities are built close the public. This is because RCM can greatly influence in reduction of the predicted failures which could cause catastrophic incident like fire and explosion by carrying out timely and accurate maintenance. In that way, it could develop a sense of safety in the public about their safety. • Basic infrastructure level: RCM strategy as discussed in section 4.3 require reliable monitoring data of the equipment/machinery for the FFA and FMECA, therefore, it require basic monitoring equipment like sensors for temperature, pressure flow, vibration and so on for the analysis and prediction of the failure mode and likelihood. • Technology Technological factors changes & Compatibility. With the advancement in technology, RCM is compatible with these development as new digital data storage devices and monitoring equipment could make the equipment history data more reliable. This could help in development of more effective and reliable maintenance planning. • Access to new Technology: RCM strategy could be benefitted from the new advanced monitoring equipment and software. • Laws regulating environment pollution: RCM does not directly relate to the laws and legal obligations related to the environment. However, during the failure mode analysis for 44 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project the different equipment, it indirectly ensures that preventive Environmental factors maintenance would take place and any potential failure could be avoided which could result any catastrophic release of the chemicals which damage environment. • Air & water pollution: one of the drawback of RCM is that it completely focuses on the function of the critical equipment and their continuous safe performance and does not account for the air or water pollution factors. • Health & safety Law: Government and legal bodies governing the operation of onshore oil and gas production facilities, has made certain laws regarding the maintenance of Legal the running and static equipment. RCM strategy conforms to the requirement in a way that its focus is equally on the safe plant operation and avoidance of any potential breakdown that could cause catastrophic failure (section 4.3) • RCM is an advanced maintenance strategy and its key objective is the increase functional reliability of the equipment/machinery. It plays important role in decreasing the risk arising from the ageing of the plant. This is because Risk reduction with the ageing the risk increases as described in the bathtub curve in section 4.5. Therefore, at this stage planned preventive maintenance is not sufficient to avoid increased frequency of equipment function failure that result in catastrophic failure. But as explained in section 4.3, RCM predicts equipment functional failure to decide the optimum maintenance interval, therefore, RCM is effective in reducing the risk arising from the ageing of the onshore oil and gas production facilities. • However, one of the drawback of this strategy is, it does not require any formal risk assessment which is key part of the RBM strategy. 45 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project • Risk reduction in RCM is dependent on the accurate maintenance. And this rely on the reliable data analysis and accurate use of FMECA for prediction of the likelihood of the failure rate of equipment/machinery. • RCM is the best strategy in assuring availability of the plant. As described in section 4.3, the objective of this strategy is Availability functional reliability of the plant/equipment. Due to this factor, it can be fairly argued that RCM is most effective in assuring smooth running and functionality of the plant’s key equipment and machinery 5.4. Condition-Based Maintenance analysis using PESTEL framework: CBM is one of the advance maintenance strategy, as explained in section 4.4. The key focus of this strategy is on the condition monitoring of the equipment that is continuously deteriorating with the time. This analysis helps management to analyze it and decide on the maintenance interval for equipment machinery (section 4.4). Here in this section, analysis of CBM will be performed using PESTEL factors to evaluate its effectiveness in an ageing oil and gas production facility. PESTAL Factors Description and example in relation to the CBM strategy • Political stability and likely changes: Like RCM, CBM is purely a technical element of the organization and does not have any direct relation with the political situation of the organization/company following this strategy Political • Health and Safety Law: CBM is not mandatory technique in any legislation that govern the operations of the oil and gas industry. However, this strategy could be said as a factor in 46 Syed Aamir Dissertation Project MSc (Eng) Process Safety and Loss Prevention risk reduction, since in an ageing oil and gas production facility, condition monitoring of the plant equipment is very important to avoid any hazardous incident caused by failures in equipment/machinery. • Significant cost reduction: CBM is another very effective technique in cost reduction in a way that it predicts the likelihood of failure of any equipment machinery before it fails. In that way that failure could be avoided before it happens by replacing the damage or worn out part (Ellis, Byron, 2008). • Life extension of the plant: With that strategy of continuous monitoring management can focus on the just in time (JIT) replacement. Just in time replacement can maximize the life Economic of plant (Ellis, Byron, 2008). • Cost cutting of unnecessary maintenance: Like RBM and RCM, CBM is also focused on avoiding unnecessary planned schedule maintenance. It monitors the condition using sensors and when alarms give a signal for the maintenance/repairing, maintenance is performed (Ellis, Byron, 2008). • False alarms needed to be avoided or detected for the successful implementation of the CBM strategy (Ellis, Byron, 2008). • Emphasis on Safety: CBM strategy uses certain analytical tools for the prediction and analysis of the failure modes. This include FMEA and FMECA, to know the likelihood of failure and how it would occur (Ellis, Byron, 2008). This information is quite useful in early detection of the fault Social that could eventually result in the catastrophic disaster. • Lifestyle & work attitude: CBM strategy is based on the 47 Syed Aamir Dissertation Project MSc (Eng) Process Safety and Loss Prevention condition monitoring through sensor for vibration, temperature, lubricating oil and similar other factors. This in a way gives early warning for the certain failures in the equipment and makes the maintenance vigilant of the potential failure (Tsang 1995). This influence workers perception and understanding of the potential failures and increases their understanding in understanding the change in these monitoring tools. • Impact on public: As explained above, CBM strategy relies on monitoring of certain factors before giving signal for the maintenance or replacement of any damaged part. Therefore, it is quite useful in avoiding catastrophic failures due machinery/equipment sudden failure. Often bigger fire and explosion effects the public living in the proximity of the oil and gas production facility. But using CBM many potential disasters could be avoided by timely maintenance and replacement of the parts and public can be saved from these risks. • Basic infrastructure level: CBM is one of the advanced maintenance strategy and it require digital sensor for monitoring accurate changes in temperature, flow, pressure, Technological factors vibration and current changes to decide on the maintenance requirement. • Technology changes & Compatibility. Technological changes and advancement has greatly influenced this technique. Since with more precise and accurate condition monitoring sensor, CBM can be more reliable and save strategy for the ageing oil and gas production facilities. • Access to new Technology: CBM strategy could be benefitted from the new advanced monitoring equipment and 48 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project software. • Laws regulating environment pollution: CBM is not directly related to the legislation. Environmental factors • Air & water pollution: CBM equipment monitoring and timely part replacement strategy could be effective in reducing the air pollution in case of pumps and generators used in oil and gas production facility, where wear and tear can increase the emissions if not maintained timely. • Health & safety Law: CBM is not directly related to the health and safety law. Government bodies governing the oil Legal and gas production facilities lay down certain maintenance requirement for the owners and operators of the production facilities. • In ageing oil and gas facility, the corrosion and wear and tear effects are more prominent than the new facility. And the risk of failure of equipment like production pipelines, storage tanks and pressure vessel is high as explained in the bathtub curve in section 4.5. CBM as explained in section 4.4 is totally depended on the accurate condition monitoring of the Risk reduction equipment/machinery, therefore, it is very effective in reducing the risk of loss of containment due to corrosion and wear and tear due to other factors like, temperature, pressure and flow rate. • In addition to it, in rotating equipment like compressor and pumps and generator, factors like monitoring and analysis of vibration, temperature, noise, and change in resistance, gives early warning of the equipment failure and management can take prompt action to avoid any catastrophic failure due to these failures in the rotating equipment (Tsang 1995). • However, the use of CBM is not effective in standby units 49 Syed Aamir Dissertation Project MSc (Eng) Process Safety and Loss Prevention and protective devices like ESD valves because there are hidden faults in this equipment and which only come to know when there is a demand (Tsang 1995). • CBM is effective in assuring maximum availability of the rotating equipment in a way that it could avoid potential Availability failure of the equipment due to monitoring sensors installed on them, which give early warning and just in time replacement/repairing of equipment avoids sudden breakdown (Ellis, Byron, 2008). 5.5. Planned-Preventive Maintenance Strategy (PPM) analysis using PESTEL framework: Time based maintenance is a conventional maintenance technique. In this section, PPM will be analyzed using PESTEL factors to measure its effectiveness for the ageing oil and gas production facility. PESTAL Factors Description and example in relation to the PPM strategy • Political stability and likely changes: PPM is purely related to the maintenance of the plant/equipment and has no direct relation to the political stability and changes in political environment. Political • Health and Safety Law: Maintenance of the plant/equipment is a key part of the operations of an oil and gas industry. Government bodies lay down laws related to health and safety of the employees. These laws restrict oil and gas companies to ensure proper maintenance to reduce the risk and safety of employees, and environment. Accurate 50 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project PPM strategy could help preventing incident related plant. • Significant cost reduction: Planned-preventive maintenance as described in section 4.5 is based on the pre-defined maintenance interval recommended by supplier or vendor. The cost associated with this strategy is evenly distributed as all the repairing and replacement items are already know. However, the cost associated with PPM strategy is high due to over maintenance. Maintenance interval decisions and likelihood prediction analysis are not carried out to reduce maintenance requirement and to predict the failure rate. Economic • Life extension of the plant: life extension of the ageing oil and gas production facility is difficult with PPM strategy. Since PPM is totally dependent on the vendor recommendation and with ageing facility and increased wear and tear failure rate increases and these could result in further deterioration of the plant. Likelihood of failure and failure mode analysis are not carried out in PPM; therefore, this strategy does not predict the sudden failures and brings no help in increasing the design life of the plant. • Cost cutting of unnecessary maintenance: One of the major drawback of this strategy is the cost implications. PPM does not offer any assistance in reducing the unnecessary costs associated with the ageing plant and it completely relies on the vendor/supplier recommendations as explained in section 4.5. • • Emphasis on Safety: PPM does not require any analysis to be performed for the failure rate and mode prediction as required in other maintenance strategies described above. In ageing plant, these analyses are mandatory to be performed 51 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Social Dissertation Project to predict the failure rates and modes because of increase rate of failures due to ageing. Therefore, this strategy does not have very great emphasis on the safety as have other strategies. • Lifestyle & work attitude: In PPM, maintenance team and workers are stick to the vendor/supplier recommendations and do not perform any failure analysis themselves to know the failure trends. Therefore, PPM strategy does not influence the lifestyle and working attitude of the maintenance team and workers and does not bring awareness to the team of the sudden failures and ageing plant risks. • Impact on public: Public is concerned with the safety of environment and safety of resident in proximity of an oil and gas production facility. Since PPM does not reduces the risks associated with the ageing plant, like increased failure rates, therefore, to continue with this strategy could be a concern for the public safety and possible environment disasters due to loss of containment. • Basic infrastructure level: PPM is a simple strategy and it does not require any condition monitoring devices or any other failure analysis. It is the simplest of all the preventive Technological factors maintenance strategies, in terms of the requirement and technical resources needed for it. • Technology changes & Compatibility. Since with the changing and development in technology PPM is rarely relied and most often RCM, CBM and RBM are used due to the cost implications and increased risk associated with the ageing oil and gas production facility. • Access to new Technology: PPM cannot be benefitted from the new technology as it is strictly based on the pre-defined intervals. 52 Syed Aamir Dissertation Project MSc (Eng) Process Safety and Loss Prevention • Laws regulating environment pollution: PPM has no direct relation with the environment regulations. Environmental factors • Air & water pollution: PPM could be helpful in controlling the emissions and effluents. Vendor/suppliers normally define optimum interval for the replacement and maintenance, therefore, for the rotatory equipment when the emissions and effluent start to increase due to wear and tear, maintenance is normally performed according to the predefined interval and hence air and water pollution can be controlled. • Health & safety Law: PPM has no direct relation to the Legal legislation but sometimes it is often stated in the legislation to carry out the maintenance of the equipment as desired by vendor/supplier. • In an ageing oil and gas production facility, risk due to sudden failure and loss of containment is high. PPM as explained in section 4.5 is only based on the maintenance interval recommended by the supplier or vendor and it does not account for the risks arising from the ageing of plant and increased wear and tear. Therefore, this strategy is least Risk reduction effective in controlling risk arising from the ageing of the plant. • In addition to it, condition monitoring and risk assessment are very important in ageing oil and gas production facility as explained in section 4.3 and 4.4. But this strategy does not have any requirement for the risk assessment or condition monitoring of the ageing plant. • PPM strategy is not very effective in maintaining or assuring Availability 53 maximum availability in an aged oil and gas production Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project facility. This is because there is no failure prediction analysis is carried out in this strategy and maintenance interval selection is based on recommendations of the supplier/vendor. Factors like equipment deterioration and wear tear due ageing are not accounted for in this strategy and due to this sudden failure keep on happening that reduces the availability of plant/equipment as explained in section 4.5. 54 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 6. Conclusion & Future Work 6.1. Conclusion In this section, a conclusion will be drawn through the analysis performed in section 5. All the four major maintenance strategies, that are RBM, RCM, CBM and PPM that are now being used in oil and gas industry and other high-risk industries like, aviation, nuclear, transmission lines and marine are analyzed using PESTEL factors and two other factors including risk reduction and availability in previous section. • RBM provides a new approach in asset integrity management. It not only considers the reliability of the system while deciding the time interval of the maintenance but also analyzes the consequences of the risks that arises due to failure. Since in ageing oil and gas production facility the biggest issue is the potential release of the hazardous flammable chemical, therefore, it is more important to carefully examine and carryout risk assessment and make it a part of the maintenance strategy of the plant. RBM is the maintenance strategy as explained in earlier section which is primarily focusing on the risks and consequence of failure. Different installation on the plant like separator, oil and gas pipelines, storage tanks and compressors pose a high risk if loss of containment incident happens. Therefore, loss of containment is nearly unacceptable from such equipment and installation in the oil and gas production facility. Since with the ageing as explained in bath tub curve (section 4.5), failure rate increase in the in these critical equipment and installation, therefore, in addition to the normal failure analysis like Failure mode effect analysis (FMEA) which is a common method for RCM and CBM strategy, quantitative risk assessment is mandatory for the ageing plant. And this is the biggest advantage of the RBM strategy. In literature review section, certain past accidents are briefly explained that they are happened either due to lack of maintenance or poor maintenance strategy/technique. RBM not only analyzes the risk posed by equipment/machinery ageing but also analyzes the risk while carrying out maintenance. Author considers the ageing itself the biggest risk and all the other three maintenance strategy, although focus on the function, availability and possible failure and its likelihood, but they don’t analyze the physical risk like fire, explosion and possible escalation, which is a key part of RBM. Due to these factors RBM could be said to be 55 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project best suited for the many static and rotatory equipment maintenance and for the protective devices and redundant equipment. However, there are certain limitations of RBM strategy. Quantitative risk assessment is a specialized job and need careful analysis to analyze the possible failures that could lead to the catastrophic incident in the oil and gas industry. This require expertise and accurate risk assessment to decide on the optimum interval. Therefore, this strategy completely relies on the quantitative risk analysis and if the information is not sufficient or if the engineer judgement is wrong or lack adequate expertise, could give rise to wrong maintenance planning and the sole purpose of risk reduction fails. At the same time, this require enough time and resources to carryout quantified risk assessment, which in case of ageing plant are very small. Cost to benefit analysis is required for the selection of this strategy. • RCM is more focused on the continuous functions of the critical equipment and reduction of the unnecessary planned maintenance. This strategy has great relative advantage of the cost reduction as it selects the key component failure analysis. With the ageing oil and gas production, functions of the redundant equipment and protective devices become very important as the need of these installation is expected to increase. Other maintenance strategies do not particularly focus on these elements of the plant. However, RCM in that way provides a better edge and could be more useful. Apart from that other rotatory equipment installed on the plant including compressors, generators, and pumps smooth running is equally important to reduce the downtime and increase productivity in ageing plant to maximize the production. Therefore, RCM provides relative better advantage as explained in section 5.3 of the PESTEL analysis. RCM on the other hand is not adequate for the static equipment like pipelines, pressure vessels and storage tanks installed in oil and gas industry. The continuous degradation in these installations may require other monitoring technique to identify their failures like in CBM (section 4.4 and 5.4) where sensors and condition monitoring devices are installed to monitor the condition of the equipment. At the same time, no formal risk 56 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project assessment is carried out in this strategy to evaluate the risk arising due to ageing of the plant. Which author believes, is mandatory to enlighten top management about the potential catastrophic incident scale and their scale. • CBM strategy has distinct advantage with respect to an ageing oil and gas facility as far as ageing is concerned. It has prominent features like continuous monitoring of the condition of static as well as rotatory equipment installed in the oil and gas facility. Through this feature as explained in section 4.4 & 5.4, it gives early warning to the maintenance team of any potential failure and breakdown. Maintenance team and department can take prompt action based on the alarm and signal of the monitoring devices and can swiftly replace/maintain defective part and ensure smooth operation with minimum downtime. This strategy like RCM has great economic advantage in terms of availability and maximum production. Just in time replacement of the parts helps increased design life of the plant and reduced further deterioration of the equipment/machinery as explained in section 5.4. Although it does not require any formal risk assessment but due to continuous condition monitoring of the plant equipment it has additive advantage in foreseeing the hazard due to failure. This indirectly reduces the chances of catastrophic disaster due to the sudden failures and greatly effective in reducing risk arising from the ageing of the plant. At the same time CBM like RCM has advantage in cost cutting and avoiding any unnecessary planned maintenance. This is because maintenance intervals are based on the condition monitoring devices signals and interpretation. When any variation in the temperature, pressure, flow rate or changes in lubricating oils occur, it gives signal to the maintenance team to carryout maintenance/replacement of the equipment. Therefore, maintenance cost related to unnecessary repairing/replacement can be reduced to the maximum (section 5.4). Like other maintenance strategies CBM has also few limitations. Protective devices and redundant equipment has many hidden faults. These faults appear only when these equipment/devices are needed. Monitoring devices has limitation and they cannot predict those hidden failures as explained in PESTEL analysis of section 5.4. Therefore, this strategy of maintenance is not sufficient for the redundant and protective devices. 57 Syed Aamir • MSc (Eng) Process Safety and Loss Prevention Dissertation Project PPM is simple and straight forward methodology of managing asset. It does not require any condition monitoring devices and equipment and failure mode analysis and failure likelihood is not performed. This strategy provides even distribution of cost estimation as the maintenance intervals are already defined. It is easier for the maintenance team to follow and does not require expertise to carryout failure analysis and mode of failure identification. In an ageing oil and gas production facility where the failure rate and mode are very important to foresee the sudden breakdowns and failures, PPM does not provide adequate assistance to prevent these failures. Due to these reasons, this strategy is not reliable in preventing sudden failures. Over-maintenance is another issue in implementing this strategy as explained in section 4.5. This strategy can be effective in new oil and gas production facilities where the cost is not a big issue and equipment and machinery is relatively in better condition without severe degradation. 6.2. Future Work: • This study was used to compare the maintenance strategy using PESTEL factors, but was restricted due to less information available for certain factors. PESTEL technique is never used to compare the advanced and conventional maintenance strategies before. There is no work available on the comparison using PESTEL framework. There is huge scope to relate maintenance strategies with legal, political and social factors. • There is little information available on the fusion technique. In which multiple maintenance strategies could be used at the same time. Static and rotatory equipment may not be effectively maintained by single maintenance strategies. In addition to it, protective devices and redundant equipment has hidden faults which pop up on demand. Therefore, fusion strategy, study should be carried out for RBM, CBM and RCM to enable owners and operators to resolve this problem. • Information of maintenance performance measurement is adequately available. But most of the maintenance performance indicators (MPIs) and the work is general, that is, it could be used for any maintenance strategy. To measure true performance of the specific 58 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project maintenance strategy maintenance strategy, specific performance measurement indicators and information should be available to analyze the actual performance of the maintenance strategy. 59 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project Reference: 1-Horrocks, P., Mansfield, D., Parker, K., Thomson, J., Atkinson, T., Worsley, J., House, W. and Park, B., 2010. Managing Ageing Plant. HSE, Warrington, UK, Tech. Rep, 823. 2-Håbrekke, S., Hokstad, P. and Ersdal, G., 2011. Ageing and life extension for safety systems on offshore facilities. Advances in Safety, Reliability and Risk Management: ESREL 2011, p.247. 3-Rahuma, M.N. and Bobby Kannan, M., 2014. Corrosion in Oil and Gas Industry: A Perspective on Corrosion Inhibitors. J Material Sci Eng, 3, p.e110. 4-Parsi, M., Najmi, K., Najafifard, F., Hassani, S., McLaury, B.S. and Shirazi, S.A., 2014. A comprehensive review of solid particle erosion modeling for oil and gas wells and pipelines applications. Journal of Natural Gas Science and Engineering, 21, pp.850-873. 5-Animah, I. and Shafiee, M., 2017. Condition assessment, remaining useful life prediction and life extension decision making for offshore oil and gas assets. Journal of Loss Prevention in the Process Industries. 6-Khan, F.I. and Haddara, M., 2004. Risk‐based maintenance (RBM): A new approach for process plant inspection and maintenance. Process Safety Progress, 23(4), pp.252-265. 7-Shafiee, M. and Animah, I., 2017. Life extension decision making of safety critical systems: An overview. Journal of Loss Prevention in the Process Industries. 8-Ramírez, P.A.P. and Utne, I.B., 2011. Challenges due to aging plants. Process Safety Progress, 30(2), pp.196-199. 9-Khan, F.I. and Haddara, M., 2004. Risk‐based maintenance (RBM): A new approach for process plant inspection and maintenance. Process Safety Progress, 23(4), pp.252-265. 10-M., 1998. Reliability centered maintenance. Reliability Engineering & System Safety, 60(2), pp.121-132. 11-Ellis, B.A. and Byron, A., 2008. Condition based maintenance. The Jethro Project, 10, pp.15. 60 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 12-R. and Kamaruddin, S., 2012. An overview of time-based and condition-based maintenance in industrial application. Computers & Industrial Engineering, 63(1), pp.135-149. 13- Ratnayake, R.C., 2012, July. Challenges in inspection planning for maintenance of static mechanical equipment on ageing oil and gas production plants: The state of the art. In Proceedings of the ASME 31st international conference on ocean, offshore and Arctic engineering. 14-Parida, A. and Chattopadhyay, G., 2007. Development of a multi-criteria hierarchical framework for maintenance performance measurement (MPM). Journal of Quality in Maintenance Engineering, 13(3), pp.241-258. 15-Okoh, P. and Haugen, S., 2013. The influence of maintenance on some selected major accidents. Cet. Chem. Eng. Trans., 31. 16-Wilson, A., 1994. Asset optimisation strategies for large transformers. In Condition Monitoring and Remanent Life Assessment in Power Transformers, IEE Colloquium on (pp. 11). IET. 17-Niu, G., Yang, B.S. and Pecht, M., 2010. Development of an optimized condition-based maintenance system by data fusion and reliability-centered maintenance. Reliability Engineering & System Safety, 95(7), pp.786-796 18-Schneider, J., Gaul, A.J., Neumann, C., Hogräfer, J., Wellßow, W., Schwan, M. and Schnettler, A., 2006. Asset management techniques. International Journal of Electrical Power & Energy Systems, 28(9), pp.643-654. 19-Mannan, S. ed., 2005. Lees' loss prevention in the process industries. ButterworthHeinemann. 20-Doyle, M.W., Stanley, E.H., Havlick, D.G., Kaiser, M.J., Steinbach, G., Graf, W.L., Galloway, G.E. and Riggsbee, J.A., 2008. Aging infrastructure and ecosystem restoration. Science, 319(5861), pp.286-287. 21-Kletz, T.A., 2001. Learning from accidents. Routledge. 61 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 22-CSB15, U.S., 2007. Investigation Report, Refinery Explosion and Fire, BP-Texas City, Texas, March 23, 2005. 23-Khan, F.I. and Abbasi, S.A., 1999. Major accidents in process industries and an analysis of causes and consequences. Journal of Loss Prevention in the process Industries, 12(5), pp.361378. 25-Parsi, M., Najmi, K., Najafifard, F., Hassani, S., McLaury, B.S. and Shirazi, S.A., 2014. A comprehensive review of solid particle erosion modeling for oil and gas wells and pipelines applications. Journal of Natural Gas Science and Engineering, 21, pp.850-873. 26-Ciaraldi, S.W. and Hedges, B., 2004, January. Restoring Integrity to Aged Petroleum Production Facilities. In ASME 2004 23rd International Conference on Offshore Mechanics and Arctic Engineering (pp. 25-32). American Society of Mechanical Engineers. 27-Selvik, J.T. and Aven, T., 2011. A framework for reliability and risk centered maintenance. Reliability Engineering & System Safety, 96(2), pp.324-331. 28- Parida, A., 2006. Development of a multi-criteria hierarchical framework for maintenance performance measurement: Concepts, issues and challenges (Doctoral dissertation, Luleå tekniska universitet). 29- Parida, A. and Chattopadhyay, G., 2007. Development of a multi-criteria hierarchical framework for maintenance performance measurement (MPM). Journal of Quality in Maintenance Engineering, 13(3), pp.241-258. 30- Animah, I., Shafiee, M., Simms, N. and Tiwari, A., 2017. A multi-stage remanufacturing approach for life extension of safety critical systems. Procedia CIRP, 59, pp.133-138. 31- Fickler, R., Cheim, L. and Lam, B., 2009, March. Application of probabilistic techniques in asset management. In Power Systems Conference and Exposition, 2009. PSCE'09. IEEE/PES (pp. 1-7). IEEE. 32- Ahmad, R. and Kamaruddin, S., 2012. An overview of time-based and condition-based maintenance in industrial application. Computers & Industrial Engineering, 63(1), pp.135-149. 62 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 33- Wintle, J. and Sharp, J., 2008. Requirements for life extension of ageing offshore production installations. Published by TWI, Cambridge, UK, Report, 17554(1), p.08. 34- Issa, T., Chang, V. and Issa, T., 2010. Sustainable business strategies and PESTEL framework. GSTF International Journal on Computing, 1(1), pp.73-80. 35- Tsang, A.H., 1995. Condition-based maintenance: tools and decision making. Journal of Quality in Maintenance Engineering, 1(3), pp.3-17. 36- Crocker, J. and Kumar, U.D., 2000. Age-related maintenance versus reliability centred maintenance: a case study on aero-engines. Reliability Engineering & System Safety, 67(2), pp.113-118. 37- Yüksel, İ., 2012. Developing a multi-criteria decision making model for PESTEL analysis. International Journal of Business and Management, 7(24), p.52. 38- Henderson, P.A., Hopkins, P. and Cosham, A., Extending the Life of Ageing Pipelines. In Offshore Pipeline Technology Conference, USA. 39- Stacey, A., 2011, January. KP4: Ageing & Life Extension Inspection Programme-The First Year. In Offshore Europe. Society of Petroleum Engineers. 40- Hudson, B., 2010, January. Extending the life of an ageing offshore facility. In Abu Dhabi International Petroleum Exhibition and Conference. Society of Petroleum Engineers. 41- Shiao, M., 2005, June. Risk-based maintenance optimization. In Proceedings of the ICOSSAR (pp. 3231-3237). 42- Krishnasamy, L., Khan, F. and Haddara, M., 2005. Development of a risk-based maintenance (RBM) strategy for a power-generating plant. Journal of Loss Prevention in the Process Industries, 18(2), pp.69-81. 43- Dekker, R., 1996. Applications of maintenance optimization models: a review and analysis. Reliability engineering & system safety, 51(3), pp.229-240. 63 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 44- Jiang, Y., Zhong, Z., McCalley, J. and Voorhis, T.V., 2004, February. Risk-based maintenance optimization for transmission equipment. In Proc. of 12th Annual Substations Equipment Diagnostics Conference. 45- Tian, Z. and Liao, H., 2011. Condition based maintenance optimization for multi-component systems using proportional hazards model. Reliability Engineering & System Safety, 96(5), pp.581-589. 46- Khan, F.I. and Haddara, M.M., 2003. Risk-based maintenance (RBM): a quantitative approach for maintenance/inspection scheduling and planning. Journal of loss prevention in the process industries, 16(6), pp.561-573. 47- Tan, Z., Li, J., Wu, Z., Zheng, J. and He, W., 2011. An evaluation of maintenance strategy using risk based inspection. Safety science, 49(6), pp.852-860. 48- Fujiyama, K., Nagai, S., Akikuni, Y., Fujiwara, T., Furuya, K., Matsumoto, S., Takagi, K. and Kawabata, T., 2004. Risk-based inspection and maintenance systems for steam turbines. International Journal of Pressure Vessels and Piping, 81(10), pp.825-835. 49- Kolios, A. and Read, G., 2013. A political, economic, social, technology, legal and environmental (PESTLE) approach for risk identification of the tidal industry in the United Kingdom. Energies, 6(10), pp.5023-5045. 50- Khan, F.I., Sadiq, R. and Haddara, M.M., 2004. Risk-based inspection and maintenance (RBIM): multi-attribute decision-making with aggregative risk analysis. Process safety and environmental protection, 82(6), pp.398-411. 51- Dekker, R., 1996. Applications of maintenance optimization models: a review and analysis. Reliability engineering & system safety, 51(3), pp.229-240. 52- Dey, P.K., Ogunlana, S.O. and Naksuksakul, S., 2004. Risk-based maintenance model for offshore oil and gas pipelines: a case study. Journal of Quality in Maintenance Engineering, 10(3), pp.169-183. 64 Syed Aamir MSc (Eng) Process Safety and Loss Prevention Dissertation Project 53- Mahmood, W.H.W., Rahman, M.N.A., Deros, B.M. and Mazli, H., 2011. Maintenance management system for upstream operations in oil and gas industry: a case study. International Journal of Industrial and Systems Engineering, 9(3), pp.317-329. 54- Parida, A. and Kumar, U., 2009. Maintenance productivity and performance measurement. Handbook of maintenance management and engineering, 1, pp.17-41. 55-Jardine, A.K., Lin, D. and Banjevic, D., 2006. A review on machinery diagnostics and prognostics implementing condition-based maintenance. Mechanical systems and signal processing, 20(7), pp.1483-1510. 56-Ellis, B.A. and Byron, A., 2008. Condition based maintenance. The Jethro Project, 10, pp.1-5 65