CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 1 2 3 NO. DESCRIPTION APPENDIX-XII B MECHANICAL REVISIONS SCOPE OF WORK AND TECHNICAL SPECIFICATIONS Prepared By: MIR FOR Approved By: CONSTRUCTION OF 380/132kV NIC CIRCLE BSP NAO PTS-20WN374 Certified By: FINAL Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 (ATTACHMENT TO SCHEDULE "B" OF CONTRACT NO. ……………/….) THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 1 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D TABLE OF CONTENTS DESCRIPTION SECTION I 03 1.01 GENERAL 03 1.02 CONFLICTS & DEVIATIONS 03 MECHANICAL SCOPE OF WORK 03 2.01 HVAC SYSTEMS 03 2.02 PLUMBING SYSTEMS 06 2.03 WEIGHT HANDLING SYSTEMS 08 III STANDARDS, CODES AND SPECIFICATIONS 09 IV DESIGN CRITERIA 12 HVAC DESIGN PARAMETERS 12 EQUIPMENT/MATERIALS & TECHNICAL SPECIFICATIONS 14 5.01 HVAC SYSTEMS 14 5.02 PLUMBING SYSTEMS 44 5.03 WEIGHT HANDLING SYSTEMS 48 1 2 3 NO. REVISIONS Approved By: 4.01 V NAO VI Certified By: VII Fares Al-Amro Division Manager(A) PAGE INTRODUCTION II Prepared By: MIR TITLE PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS HVAC CONTROL SCHEMATIC DIAGRAMS & HVAC ALARMS LOGIC DIAGRAM 48 49 VIII ANNEXURES 49 IX DATA SCHEDULES 50 ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 2 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D SECTION I - INTRODUCTION 1.01 GENERAL DESCRIPTION This section broadly outlines the PROJECT’S mechanical requirement and shall be read in conjunction with the COMPANY'S Engineering, Construction and Material Standard Specifications and the latest edition of associated international Standards and Codes. For other mechanical WORK requirements, refer to the main Scope of Work and Technical Specification. 1 2 3 NO. 1.02 CONFLICTS AND DEVIATIONS REVISIONS Any conflict between this Specification and other applicable COMPANY Engineering Standards, Material System Specifications, Standard Drawings or Industry Standards, Codes and forms shall be resolved in writing by the COMPANY. SECTION II - MECHANICAL SCOPE OF WORK Prepared By: MIR Approved By: The WORK shall include design, supply of equipment, materials, labor and tools for the installation of new systems. The WORK shall also include equipment start-up, testing and commissioning for the new systems and to execute other related services for the safe, efficient and reliable performance and complete installation of this PROJECT to the satisfaction of the COMPANY in conformance with the requirements as prescribed below. 2.01 HVAC SYSTEMS NAO Certified By: 1. Heating, Ventilation and Air Conditioning (HVAC) System consisting of Direct Expansion (DX) type, Single Packaged Air Conditioning Units (PACU) with identical cooling capacity per system for duty and standby units as per attached HVAC Control schematic diagrams, conforming to the applicable requirement of COMPANY Standard 73-TMSS01. Note: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED -All PACU of 380kV GIS Building shall be installed on roof and Equipment / Ductwork shall be concealed. Requirement of openings in Roof for HVAC Supply, Return and smoke purging fans shall be coordinated with Civil. Also the requirement of duct hangers from roof (if any) shall be coordinated with civil -The Alarm “AIR CONDITIONING FAULTY”, “HIGH TEMPERATURE” and “HIGH HUMIDITY” for all Substation Buildings including Security Building shall be integrated with Substation Automation System (SAS) as per TES-P-107.02R2 2. Electric Duct Heaters (EDH) shall be provided for Reheating and Dehumidification 3. HVAC system design shall be for the ultimate configuration of building considering specified future expansions. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 3 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY DESCRIPTION 4. Ventilation system for continuous operation shall be provided for the cable tunnels / Cable Basements considering minimum Six (6) Air Changes per Hour. Duct Banks / Trenches (if any) converted as Tunnels based on ampacity calculation or such other reasons shall also be considered and provided with Ventilation System. Installation height of ventilation fans shall not be less than 1.2m from finished surrounding level. Exhaust fans shall be listed for use as smoke purge fans, likewise a remote switch outside in an approved location shall also be provided. Note: 1 2 3 NO. -Ventilation Shaft dimensions shall be considered in calculations REVISIONS - Separate ventilation control panels shall be provided for the Basement & Tunnels and the alarm “Ventilation Faulty” for each building Basement / tunnel shall be integrated with Substation Automation System (SAS) as per TES-P-107.02R2 5. HVAC Control system shall be in accordance with PTS per applicable COMPANY Standards Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro 6. HVAC design scheme shall be as per attached HVAC control schematic diagrams WT925440 sheet 1 to 08 for Substation Buildings, attached in PTS/Appendix XIIB based on Tender Layout WT-925438 attached in PTS/Appendix I 7. Alarms of Mechanical / HVAC system shall be integrated with SAS and SCADA (ECC) as per TES-P-107.02R2 and attached tender drawing WT-925441: Mechanical / HVAC Alarms Logic Diagram in Appendix XIIB 8. HVAC system for Security Equipment Building and other security systems/buildings (if any) shall conform to HCIS SEC & SAF directive requirements and shall also comply with applicable SEC/NG Engineering, Material and Construction Standards. The same shall be coordinated with Security Consultant / Contractor 9. Exhaust fans (1-Duty & 1-Standby, 100% capacity each) for 24 hours continuous operation shall be provided for Battery Rooms (12 ACH). Exhaust fan of Battery room shall be listed for use as smoke purge fan, likewise a remote switch outside in an approved location shall also be provided. The exhaust fan motor shall have a corrosion and explosion proof enclosure with Class B insulation Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 10. Exhaust fan shall be provided for Fire Protection Equipment Rooms. Fan sizing shall be done as per Guidelines in International / national standards for Gas Rooms 11. Exhaust system / fan shall be provided for Toilets (10 ACH). HVAC Supply is not required for Toilets. Exhaust fan of toilet will be normally OFF and interlocked with light switch as per Standard TES-P-119.19 12. GIS Buildings store room, Control building store room, Relay test room, conference room, office, archive room or such other room as applicable per Substation layout shall be provided with wall mount split type air conditioning unit (SASO certified). No standby redundancy is required. These units are intended to be normally off for unmanned substation and therefore no interlock with HVAC control panel for PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 4 OF 50 REV. 0 CERT. APP’D CHK’D monitoring / control is required. Normally closed Motorized fire smoke damper with transfer grille in wall opening shall be provided for these rooms for the case of smoke extraction, if any 13. Exhaust Fan shall be provided for Fire Pump House (10 ACH). Fresh Air Intake in Pump House shall be through Sand Trap Louvers, 50 mm thick Aluminium Filters and stainless steel Bird screen. Replacement air shall be considered to enter the pump room through STL Assembly only and is not acceptable through Infiltration. Four (4) percent of floor area shall be considered in sizing of fresh air intake louvers as per ASHRAE 62.1 & International Mechanical Code. 1 2 3 DESCRIPTION NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY REVISIONS Prepared By: MIR Approved By: 14. Smoke purging fans shall be provided as per TES-P-119.21. Fans located near the fresh air intakes shall be centrifugal upblast type with minimum capacity sized at six (6) air changes per hour. Smoke purging shall include spaces for false ceilings / floors. Care shall be taken to completely dissipate hazardous atmospheres and not just move them to other locations, as clean agents are generally heavier than air. Installation on return air duct of HVAC system shall be avoided wherever possible. 15. For remote areas / dusty areas, Fresh Air intakes shall be provided with inertial air filters as per TES-K-100.01 16. Coating / painting for HVAC Equipment / Components shall conform to 01-TMSS-01, TES-H-107 and relevant COMPANY Standards as applicable 17. Testing, Adjusting and Balancing of HVAC System. NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 5 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 2.02 PLUMBING SYSTEMS DESCRIPTION 1. Complete Sewerage, Vent and Water Supply System as necessary shall be provided for all Toilets (as applicable). For Security Equipment Building (SEB) and other security systems / buildings (if any), applicable requirements shall be coordinated with security consultant / contractor. 1 2 3 NO. 2. Roof mounted water tank, water transfer pump & booster pump with weather protection sheds shall be provided as per COMPANY standards. REVISIONS Prepared By: MIR Approved By: 3. Battery Rooms shall be provided with Plumbed Emergency Eyewash Equipment as per 90-TMSS-08, hose bib, trap & vented floor drain, piping & chemical dry pit. 4. Underground water storage tank for utility purpose shall be provided near Control building. Capacity of tanks shall be minimum 15,000 liters. System shall comprise of Automatic float switch, level indications and truck filling water line. Valve box with valve and end cap shall be provided near the main gate for future water interconnection to municipality. For Security Equipment Building (SEB) and other security systems / buildings, requirements shall be coordinated with security consultant / contractor 5. All building roofs shall be provided with roof drainage system as per plumbing code and related COMPANY Standards NAO 6. Self-priming pumps with weather protection for oil insulated equipment pits shall be provided in accordance with PTS & TES-P-119.21 to remove rain water. Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 7. Sump pumps with required controls for Basements, Cable tunnels & Trenches shall be provided in accordance with PTS & TES-P-119.19. For Tunnels minimum of two sump pits per tunnel partition shall be provided. Duct Banks converted as Tunnels or trenches based on ampacity calculation or such other reasons, shall also be considered & provided with Sump pumps. Location of Sump Pumps / Pits & channel shall be avoided below cable supports to the extent possible for concern of accessibility, safety & maintenance. A clearance of minimum 0.5m shall be provided where Sump Pumps / Pits & channels are located below cable supports. 75 mm wide x 75 mm deep Drainage channel shall be provided for both tunnels & basements as per TES-P-119.19, it shall be discontinued at location of firewalls. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 6 OF 50 REV. 0 CERT. APP’D CHK’D 8. Main Control Panels for Submersible Sump Pumps shall be provided as follows and the alarm “SUMP PUMP OPERATE” and “SUMP PUMP FAULTY” from each of these panels shall be integrated with Substation Automation System (SAS) as per TES-P-107.02R2: 1 2 3 DESCRIPTION NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY a. Main Control Panel for Submersible Sump Pumps for 380kV GIS Building Tunnels, chutes & Trenches (if any). b. Main Control Panel for Submersible Sump Pumps for 132kV GIS Building-I Tunnels, chutes & Trenches (if any) c. Main Control Panel for Submersible Sump Pumps for 132kV GIS Building-II Tunnels, chutes & Trenches (if any) d. Main Control Panel for Submersible Sump Pumps for Control Room Building Basement, Tunnels, chutes & Trenches (if any) REVISIONS 9. All Air-Conditioning systems shall be provided with condensate drainage piping & condensate drain pit/tank. Prepared By: MIR Approved By: 10. Hose bibs shall be provided at suitable locations for HVAC maintenance / cleaning and shall be connected to the nearest water supply service. The requirement is applicable whether HVAC Equipment is ground mount, roof mount or in HVAC Room. Minimum two hose bibs per system shall be provided and located within 2 meter distance from HVAC Equipment. Adequate means of drainage shall also be provided. Contractor / Designer shall submit detailed proposal for SEC Review and Approval NAO 11. Toilets shall be provided with septic tank & seepage pit. Refer to Appendix VIII for related details Certified By: 12. SEB shall be provided with bottle type drinking water cooler in accordance with 94TMSS-02. 13. Battery Room in Control Building & SEB shall be provided with monthly inspection checklist 1.4.3 attached in SEC 5-Star Safety Element 1.4E. Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 14. Toilets shall be provided with monthly inspection checklist 1.4.1 attached in SEC 5-Star Safety Element 1.4E. 15. Coating / painting for Plumbing Equipment / Components shall conform to 01-TMSS01, TES-H-107 and relevant COMPANY Standards as applicable 16. All piping shall be protected from damage due to heat/expansion & vibrations THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 7 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 2.03 WEIGHT HANDLING SYSTEMS DESCRIPTION 1. EOT Crane in GIS buildings shall have the minimum capacity based on the heaviest GIS section to be lifted but not less than 5 tons. The overhead traveling crane shall be provided with remote controller for remote operation in addition to the pendant type that is usually provided. For other related requirements i.e., crane access ladder with cage, platform, access door, etc., refer to Appendix VIII 1 2 3 NO. 2. Hoist and Rail shall be provided for Fire Pump house REVISIONS 3. Coating / painting for Weight handling equipment / components shall conform to 01TMSS-01, TES-H-107 and relevant COMPANY Standards as applicable Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 8 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY SECTION III - STANDARDS, CODES AND SPECIFICATIONS 1 2 3 NO. DESCRIPTION All WORKS, equipment and material covered by this document shall conform to the latest edition of the COMPANY’S Material Standard Specifications supplemented with latest applicable industry Standards, Codes and Specifications. The latest edition of each Standard and Specification shall mean the latest edition specified hereunder. REVISIONS The CONTRACTOR shall strictly comply with the following Standards, Codes and Specifications, and no deviation shall be accepted unless otherwise accepted by a written waiver from COMPANY. The CONTRACTOR may propose "equivalent" Standards and Specifications if such standards and specifications are equal to or better than those specified herein, and shall be subject to prior approval of the COMPANY. A. COMPANY Materials Standard Specifications Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Standard 01-TMSS-01 73-TMSS-01 73-TMSS-05 75-TMSS-01 75-TMSS-02 83-TMSS-01 90-TMSS-08 94-TMSS-01 94-TMSS-02 Rev. 03 01 00 00 00 00 00 00 00 Title General Requirements for All Equipment/Materials Air Conditioning Units, Packaged Centrifugal Exhaust Fans Plastic Piping for Plumbing System Vitreous China Plumbing Fixtures Submersible Sump Pumps Emergency Shower and Eye (and Face) Wash Equipment Automatic Electric Water Heaters Drinking Water Coolers B. COMPANY Engineering Standards Standard TES-B-106.01 TES-B-106.05 TES-B-106.06 Rev. 00 01 01 TES-H-107.01 TES-H-107.02 TES-K-100.01 TES-P-107.02 TES-P-119.19 TES-P-119.21 TES-P-119.27 TES-W-109.01 01 01 02 02 03 01 01 00 Title Fire Detection and Alarm System HFC-227ea Clean Agent Extinguishing System FK 5-1-12 Fixed Installation Total flooding Clean Agent Fire Extinguishing System Painting Paint Color Codes and Standards Heating, Ventilating and Air Conditioning Systems Design SCADA System for Transmission Substation wih SAS Substation Building And Site Development Fire & Loss Prevention Requirements Supervisory Control and Data Acquisition (SCADA) General Welding Criteria PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 9 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY C. COMPANY Construction Standards Rev. 01 Title HVAC Systems and Equipment Installation 1 2 D. COMPANY Standard Drawings 3 NO. DESCRIPTION Standard TCS-K-100.01 REVISIONS Prepared By: MIR Approved By: Standard SA-421075 SA-421111 TA-800039 TA-800133 Rev. TA-800134 TA-800135 TA-800137 00 00 00 TA-800138 00 TA-800151 TA-800152 00 00 00 00 00 Title HVAC Miscellaneous Details Plumbing Miscellaneous Details Plans, Elevations & Sections For Gatehouse Removable Crash Barrier Location Plan and Detail in Substation Septic Tank Installation Details For Non-Traffic Areas Disposal System Layout and Seepage Pit Installation Details Sanitary Sewer Manhole Precast Concrete Plan, Sections and Details Drainage Sump, Drainage Channel and Sewer Manhole Cover Details HVAC Construction Details HVAC Construction Details NAO E. COMPANY 5 Star Safety Standards Certified By: Element 1.3 Element 1.4 Element 1.10 Ventilation Workplace Hygiene Facilities Color Coding: Plant and Pipelines Fares Al-Amro Division Manager(A) F. HCIS Directives ESD, E&DD 16-02-2021 SAF 2017 SEC 2017 Safety & Fire Protection Directives Security Directives THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 10 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 1 2 3 NO. DESCRIPTION G. Industry Standards ASME American Society of Mechanical Engineers ABMA American Bearing Manufacturers Association AHRI Air Conditioning, Heating, and Refrigeration Institute ANSI American National Standards Institute ASHRAE American Society of Heating Refrigeration & Air Conditioning Engineers ASTM American Society of Testing & Materials IMC International Mechanical Code IPC International Plumbing Code ISO International Organization for Standardization NFPA National Fire Protection Association SASO Saudi Arabian Standards Organization SBC Saudi Building Code UL Underwriters Laboratories UPC Uniform Plumbing Code REVISIONS Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 11 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D SECTION IV – DESIGN CRITERIA 4.01 HVAC DESIGN PARAMETERS DESCRIPTION Outdoor design data for HVAC system from sources indicated in Section VI shall be submitted for SEC review and approval in coordination with Standards & Specification department as per TES-K-100.01. The maximum values at 0.4% occurrence for the monthly design dry bulb and design wet bulb temperatures as per latest ASHRAE Standard shall be submitted for review. 1 2 3 NO. All air conditioning units shall be designed to operate satisfactorily at outdoor ambient conditions at a given location. REVISIONS A. Design Ambient Condition Summer (C) Prepared By: MIR Approved By: Winter (C) Outdoor Temperature Mean Daily Range * - Refer to Section VI * DB / * WB * DB * DB Indoor Temperature Relative Humidity Equipment Operation 25C TES-K-100.01R2 24 Hours / day (Continuous) Basement/Tunnels (Cable Areas) Ventilated NAO B. Noise Level Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED In Room In open air at a distance of 2 meters Refer to TES-K-100 60 dB (A) C. Ambient Air Quality The air conditioning system shall be designed for airborne dust concentration of 1.0 mg/m3 and sandstorm dust concentrations reaching 500 mg/m3 near the ground. Dust particles sizes are as follows: 95% less than 20 micrometers (0.0008 inch) 50% less than 1.5 micrometers (0.00006 inch) No continuous chemical air contamination is considered D. Safety Factors All safety factors to be used in the HVAC load calculations shall be minimum 10%. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 12 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D E. Duct Velocities as per ASHRAE Fundamentals Handbook DESCRIPTION Rectangular Duct (Exposed) Rectangular Duct (Concealed) Velocity in Main Ducts mps (fpm) At NC=45 At NC = 35 Velocity in Branch Ducts mps (fpm) At NC=45 At NC = 35 10.2 (2008) 7.4 (1457) 8.16 (1606) 5.92 (1165) 12.7 (2500) 8.9 (1752) 10.16 (2000) 7.12 (1402) 1 2 3 NO. F: Duct design method: Equal Friction method REVISIONS G: Bell mouth opening shall be sized based on air velocity of 800 fpm maximum as per SMACNA Table 4.3.3. 600fpm shall be considered for communication room & control room. H. Smoke Exhaust ducts shall be sized with air velocity of maximum 1400 fpm Prepared By: MIR Approved By: I. HVAC Load & Duct Sizing Calculations Provide computerized HVAC load and duct sizing calculations J. Lighting and Equipment Heat Dissipation Calculations NAO Certified By: Fares Al-Amro Consider Ballast factor allowance as per ASHRAE for high bay luminaries and fluorescent type lighting fixtures (if any) Provide manufacturer certified data as basis of calculations. Previously approved manufacturer certified documents can be used only as reference. For Equipment heat dissipation (electrical equipment / lighting) contractor shall submit the detailed heat dissipation determination procedure accompanied with manufacturer duly signed & stamped Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 13 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D SECTION V – EQUIPMENT/MATERIALS & TECHNICAL SPECIFICATIONS 5.01 HVAC SYSTEM REQUIREMENTS 1 2 1. 3 NO. DESCRIPTION A. General REVISIONS 2. All air distribution ducts for substations shall be double skin, factory insulated duct work as per TES-K-100.01, rectangular / spiral as per SEC requirement. 3. HVAC ducts in GIS Halls shall be above crane where GIB connections are applicable. HVAC ducts in GIS halls may be proposed below crane if there are no GIB connections for SEC review and approval. HVAC duct location and arrangement shall be coordinated with overall substation architecture and ensure to be inside or concealed. 4. Fresh air make up shall be through the double skin mixing box section provided in the PACUs equipped with sand trap louvers with air filtration, volume damper and removable 13mm stainless steel wire mesh bird screen. Fresh Air intake shall automatically close upon detection of smoke in air by motorized fire smoke damper and system may work in recirculation mode. HVAC System shutdown shall occur only when alarm is received from within the zone. 5. Except for toilet and rooms provided with Mini Split AC, temperature and humidity indicators (hygrometers) shall be installed in all rooms including one outside the building near each main point of egress. Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) Heating, Ventilating and Air Conditioning Systems shall be provided to maintain the desired indoor temperature and environmental condition for efficient equipment operation. HVAC Systems shall conform to the applicable requirements of COMPANY Standard TES-P-119.19. 6. PACUs shall be located on reinforced concrete pad with all necessary vibration isolators as per location / guidelines / notes in substation layout ESD, E&DD 7. Concrete stair access shall be provided when mechanical equipment are located on roof. 8. Separate power sources / feeders shall be used for duty and standby air conditioning units. Redundant power supply is required for HVAC panel 9. Provide motorized combination fire and smoke dampers to isolate areas protected with clean agent fire extinguishing system and to isolate areas provided with HVAC & purging system. 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 14 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 10. All Ductwork accessories shall be applicable for double skin construction 1 2 3 NO. DESCRIPTION 11. Provide permanent steel ladder and metal platform or catwalk ways with safety guard & handrails to serve as an access for maintenance and repair of PACU control panels, condenser fan motors, motorized volume dampers, actuators, sensors, exhaust fans, smoke purging fans etc. REVISIONS Prepared By: MIR Approved By: 12. Voltage level monitors shall be provided to check for available voltage and shut off the PACU in case the voltage is not in permissible range specified by unit manufacturers. When voltage is revert to normal operating range, PACU shall start automatically with consideration of set safety timers. 13. In case of disconnection of any existing duct detectors or any part of the fire alarm system, ISD/FF&LPD should be notified. Also, after the reinstallation of the same duct detectors or any part of the fire alarm system, a test should be conducted and attended by ISD/FF&LPD representative. 14. All raised floor shall be provided with direct-ducted supply and return air 15. Supply air shall be provided to air lock room NAO Certified By: Fares Al-Amro 16. HVAC Openings in Double-Tee or Hollow Core Roofs are not recommended 17. Outdoor exposed ducts shall be protected against weather conditions and against rust, by painting as specified below. Painting color shall match building color a) Epoxy primer b) Epoxy Intermediate Coat c) Polyurethane Topcoat Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 18. Corrosion resistive coating shall meet the following for substations located in areas that have severe conditions like those areas listed below, a multi coating shall be applied for the complete unit including the casing, piping and headers a) For units to be installed in areas listed below anti-corrosion coating shall applied instead. Area Coastal Corroding elements chloride and sulfur Notes Within 15km radial PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 15 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء environment compounds Industrial environment sulfur oxides (S20) and nitrogen oxides(NO) Agricultural environment Heavy polluted urban environment fertilizer ,ammonia distance from the Coastline Within 3.5 km radial distance from the industrial Environment ( Power Plants , Desalination Plants , Sewage Plants, Petrochemical Plants , Refineries , industry Plants, oil fields and rigs) Areas around farms Carbon dioxide (CO2), sulfur oxides (S2O) nitrogen oxides (NOx) , and volatile organic compounds (VOCs) Areas having pollution level exceeding (70) micrograms per cubic meter (mcm) 1 2 3 NO. DESCRIPTION CHK’D APP’D SAUDI ELECTRICITY COMPANY REVISIONS Prepared By: MIR Approved By: * For other areas, an investigation shall be made to determine what atmospheric Corrosion may exist. If any, the same special coating shall be applied. NAO Certified By: b) For unit to be installed in the areas listed above , condenser and evaporator coil shall be sprayed and coated with epoxy phenolic or better material suitable for use in salt laden environment. Coils shall be coated during manufacturing c) For unit to be installed in the areas listed above , outdoor control panel shall Fares Al-Amro Division Manager(A) be NEMA 4X enclosure ESD, E&DD d) The coating shall be factory or field applied. It shall meet the following 16-02-2021 durability test requirement : THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED + 2500 Hrs. (humidity resistance test) D 2247-68. + 3000 Hrs. (neutral-salt spray test) ASTM B 117. + 1500 Hrs. (acid-salt spray test) ASTM B-287 + 250 Hrs. (Water immersion resistance) ASTM D870-92 Cross hatch adhesion of 4B-5B per ASTM D3359-93 PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 16 OF 50 REV. 0 CERT. APP’D CHK’D 1 2 3 DESCRIPTION NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY REVISIONS Up to 150 in./lb (Impact resistance) ASTM D2794-93 Superior hardness characteristics of 2H per ASTM D3363-92A Compatible for Flexibility according to ISO 1520 Standard. Compatible for abrasion test according to ASTM D 4060 Standard. 1000 Cycles abrasion test — ASTM D 4060 Standard. 25 Weeks Cycle aging test — ISO 20340 (for fins and Coils) 11 Weeks Cycle aging test — ISO 20340 (for other coated parts) Smooth Surface Characteristic. Good Cutting Edge Protection Excellent Chemical Resistance Pressure Drop: 0-5 % (depending on fin geometry) Thermal Resistance: 0-3 % (depending on fin geometry) e) The coating shall be UV resistant on the following components Prepared By: MIR Coil fin coating HVAC component and enclosure coating Drain pan coating Approved By: NAO Certified By: Fares Al-Amro f) The effect of the Anti-corrosive coating on the thermal conductivity of the coil shall be negligible. The same shall be guaranteed for air pressure drop across the coil. g) The corrosion resistive coating shall allow expansion and contraction for fins and coils. It shall has the ability to comb out damaged and/or bent fins without adhesion loss or flaking of coating. h) The coating shall provide anti-microbial protection (against mould, fungus, mildew and noxious bacteria). Division Manager(A) ESD, E&DD i) The color of the coating system shall be suitable for heat rejection and reflection. 16-02-2021 j) Coating for all Units shall tested. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED k) Anti-corrosion coating shall be applied on all sides of the specified parts . it shall be maintainable at site l) Anti-corrosion coating shall cover the entire Header and a complete coverage of the coil PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 17 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY m) Pre-coated sheet (before it is manufactured into fins) is not acceptable. p) Coating products Material Safety Data Sheets (MSDS) shall be submitted and confirm that usage of them are not harmful to health. 1 2 o) In case the coating got damaged during installation in site , Contractor shall maintain the same at site 3 NO. DESCRIPTION n) Coating process shall guarantee total coverage and penetration to-reach areas and sharp metal edges, especially for the coils in evaporator and condenser , and fans blades. REVISIONS q) For other outdoor material/items and metal parts not covered in this section, they shall be as follows: Weatherproof Corrosion and abrasion resistant IP54 as per IEC 60529 or NEMA Type 4X as per NEMA 250. Prepared By: MIR r) All vibration mountings or spring isolator used in the PACUs and Fans shall be stainless steel or protected with anti-corrosion coating Approved By: s) All fasteners (nuts, bolts and washers etc.) used in the PACUs and Fans shall be zinc coated with a minimum average thickness as specified in Clause 6.1.2 of SEC Standard 01-TMSS-01. NAO t) All exposed items like handles and hinges shall be made of non-corrosive material or shall be hot dip galvanized or stainless steel for outdoor locations and cadmium or chromium plated for indoor equipment. Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 19. Coating layer thickness for different parts shall be as follows: Item 1. 2. 3. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 4. Equipment Part Condenser and evaporator coils Casing Compressors panels, fans, grids, enclosures, pipes, etc. Drain pans, water collectors, PACU bottom panels Thickness 25 - 30 micron 0.17 to 0.26 mm 0.17 to 0.26 mm 1 mm PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 18 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D 20. Heat Resistance of the coating shall exceed 150°C. DESCRIPTION 21. The protection coating shall be maintainable in site and warrantied against climate impact and galvanic corrosion for (10) ten years 22. The Energy Efficiency Ratio (EER) of new PACUs shall meet or exceed the values in Table below, as applicable. It shall be verified thru a performance test (among FAT). Rated cooling capacity (Tons)[kW] Testing method EER(Btu/ W.h) < 5.4 Tons [19.05kW] (excluding window, split ducted, and split non-ducted) ANSI/AHRI 210/240 Or ISO 5151 Or ISO 13253 11.2 1 2 3 NO. Equipment Type REVISIONS Prepared By: MIR Approved By: Air Conditioner, air cooled NAO Certified By: > 5.4 Tons [19.05kW] and < 11 Tons [39.56kW] > 11 Tons [39.56kW] and < 20 Tons [70.32kW] > 20 Tons [70.32kW] and < 63 Tons [222.68kW] > 63 Tons [222.68kW] 11.2 ANSI/AHRI 340/360 Or ISO 5151 Or ISO 13253 11 10 9.7 Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 19 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY B. HVAC Control System DESCRIPTION 1. Supply of HVAC control system by a pre-qualified company specializing in HVAC controls is acceptable. Refer to List of Technically Acceptable Manufacturers (LOTAM). 2. Controls shall be D.D.C. (Direct Digital Controls) type. 1 2 3 NO. 3. Interlock controls shall be provided with SAS to remotely monitor status of the HVAC Systems at designated ECC, modification of set points & parameters. REVISIONS Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 4. Interlock controls shall be provided to receive an input signal from FPSP to shut down the HVAC Systems in case of smoke / fire detection and also to close the motorized fire / smoke dampers associated with the operation of the Clean Agent Fire Suppression System. 5. The Air conditioning units shall not trip up on manual checking of alarm. 6. HVAC Control Schematic Diagram shall be as per attached tender drawing WT-925440 sheet 01 to 08 for Substation Buildings. Dedicated Ventilation Control panel shall be provided for Tunnels and it shall not be integrated with Building HVAC Control panel 7. HVAC Control system shall comply with applicable requirements of latest TES-P-107.02 and TES-P-119.27. Refer to attached tender drawing WT-925441 sheet 01 of 01: Mechanical / HVAC Alarms Logic Diagram based on mentioned standards. 8. Control wiring diagram shall be submitted for review and approval; prior to fabrication by control specialist. 9. HVAC panel shall be equipped with a 7-day / 24-hour timer switch to alternate the operation of the duty and standby units. An automatic transfer switch, with an adjustable time delay, 0 - 300 seconds (5 minutes), shall be provided to start the standby unit in case the duty unit trips or fails to start. 10. Time delay (adjustment from 80 to 250 seconds) shall be provided for Evaporator fan to start when motorized dampers for the units are in fully open positioned. Motorized damper end-switch / limit switch shall be interlock with the Evaporator fan effectively. 11. The Direct Digital Control (D.D.C.) system shall be compact module type and shall contain digital and analogue for input and output points. 12. All alarms and indications (such as pre-filter, bag filter, fans, etc.) shall be considered as input points in D.D.C. system. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 20 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 13. Compact module D.D.C. shall be at least 16 points input and 16 points output. 1 2 15. Control unit shall have digital portable operator's terminal mounted on the panel door at an elevation of 1.5m from finished floor level and shall also provide two communication interface ports for Building Management System (BMS) connections 3 NO. DESCRIPTION 14. D.D.C. shall be ready to communicate with computer system to BMS (Building Management System). REVISIONS 16. Control system shall also include all the necessary pressure and temperature control protective devices as well as control relays, consisting of, but not limited to the applicable requirements defined in COMPANY standards 73-TMSS-01 and in TES-P119.19 17. At least 20% free spare points shall be provided. Prepared By: MIR Approved By: 18. D.D.C. test set shall be provided by the CONTRACTOR for maintenance purposes. 19. A maintenance tool set (lap top computer / accessories) shall be provided including the software program copy / downloaded programming for future use 20. The control system shall have provision for management stations and/or service terminal for future connections NAO Certified By: 21. The DDC shall have an alarm history log and capable of storing at least 20 last events. The latest event(s) shall succeed the previous event(s) and shall have dates & times of occurrences 22. During normal operation, the DDC shall display the Substation name, month, day, year and time. Numeric display i.e., Temperature and hours shall have one decimal point. Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 23. All functions, devices, switches and indicating lights shall be clearly and permanently labelled. All labels shall be in both English and Arabic language 24. HVAC along with all motorized fire dampers shall automatically close within specified time in standards / codes during first stage alarm and / or as required by AHJ 25. As battery room is protected by clean agent fire protection system, duty & standby exhaust fans in battery room along with MF/SD shall shutdown or closed automatically in the event of fire before clean agent discharge PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 21 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D 26. Indoor / Outdoor HVAC Panels enclosure shall be NEMA Class 4 as per 73-TMSS-01 and shall also comply with applicable requirements in COMPANY standard 31-TMSS-02. 1 2 28. Status indication lights (LED type) and switches to be provided in HVAC panel are listed below: 3 NO. DESCRIPTION 27. HVAC panels for control building shall be located in control room REVISIONS Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 1) Ammeter and voltmeter for each compressor motor 2) Ammeter and voltmeter for Evaporator fan motor 3) Ammeter and voltmeter for Electric duct heater 4) Control Switch for Evaporator fan 5) Control switch for Battery Room exhaust fan 6) Control switch for Toilet exhaust fan 7) Control switches for all tunnel ventilation fans 8) Control switches for dampers 9) Lamp Test switch 10) Reset switch for resetting the system back to normal after the faults are corrected. 11) Knob type Hand-Off-Auto selector switch for each A/C Unit 12) Silence Alarm switch 13) GREEN Indicating light for SCADA INTERLOCKED 14) GREEN Indicating light for FPSP INTERLOCKED 15) RED indicating light for HIGH TEMPERATURE 16) RED indicating light for HIGH HUMIDITY 17) RED indicating light for FIRE ALARM 18) RED indicating lights for compressor TRIP condition. 19) GREEN indicating lights for compressor ON or RUNNING (cooling stages). 20) YELLOW indicating lights for compressor OFF condition. 21) RED indicating lights for HIGH DISCHARGE PRESSURE from compressor 22) RED indicating lights for LOW SUCTION PRESSURE to compressor 23) RED indicating lights for HIGH OIL PRESSURE of compressor 24) RED indicating lights for LOW OIL PRESSURE of compressor 25) RED indicating lights for TRIP condition of Evaporator fan 26) GREEN indicating lights for ON or RUNNING condition of Evaporator fan. 27) YELLOW indicating light for NO AIR FLOW or BELT FAILURE condition 28) GREEN indicating lights for ON (heating stages) condition of electric duct heaters. 29) RED indicating lights for TRIP condition of electric heaters. 30) GREEN indicating lights for OPEN position of each motorized fire / smoke damper. 31) RED indicating lights for CLOSED position of each motorized fire / smoke damper. 32) GREEN indicating lights for OPEN position of each motorized volume damper. 33) RED indicating lights for CLOSED position of each motorized volume damper. 34) RED indicating lights for TRIP condition of Battery Room exhaust fan - A & B PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 22 OF 50 REV. 0 CERT. APP’D CHK’D 1 2 3 DESCRIPTION NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY REVISIONS Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 35) GREEN indicating lights for ON or RUNNING condition for Battery Room exhaust fan –A&B 36) RED indicating lights for TRIP condition of Toilet exhaust fan 37) GREEN indicating lights for ON or RUNNING condition of Toilet exhaust fan 38) RED indication lights for TRIP condition of all ventilation & Jet fans (if any) 39) GREEN indication lights for ON or RUNNING condition of all ventilation & Jet fans 40) RED indication lights for TRIP condition of all condenser fans 41) GREEN indication lights for ON or RUNNING condition of all condenser fans 42) GREEN indication light for Power Supply: ON 43) GREEN indication light for EQUIPMENT-A DUTY 44) RED indicating light for EQUIPMENT-A FAULTY 45) GREEN indication light for EQUIPMENT-B DUTY 46) RED indicating light for EQUIPMENT -B FAULTY 47) YELLOW indication light for FRESH AIR FILTER DIRTY 48) YELLOW indication light for PRE-FILTER DIRTY 49) YELLOW indication light for BAG FILTER DIRTY 29. Reading ranges for Ammeter and Voltmeter shall be 0 to 150% of respective equipment rating 30. Below conditions shall result in an Audible and Visual Alarm at HVAC Panel: 1) Power fail 2) Evaporator Fan Trip 3) No Air Flow 4) Filters Dirty 5) Room High Temperature 6) Room High Relative Humidity 7) High Discharge Pressure 8) Low Suction Pressure 9) High Oil Pressure 10) Low Oil Pressure 11) Compressor Trip 12) Condenser Fan Trip 13) Battery Room Exhaust Fan Trip 14) Electric Duct Heater Trip 15) Motorized Fire Smoke damper closed 16) Fire Alarm 17) Motorized volume damper closed. 31. All Audible and Visual alarms shall have latching circuits and they shall persist until corrected or verified. The audible alarm shall be silenced by operating the SILENCE ALARM Switch but the visual indication shall persist until the fault is repaired. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 23 OF 50 REV. 0 CERT. APP’D CHK’D 32. The performance of HVAC system shall be controlled by a thermostat located in the supply air stream at coil discharge OR in the return air stream within the conditioned space. 33. Duct temperature sensors, one in supply and one in return shall be provided to monitor operating air temperature via Portable Operator Terminal DESCRIPTION 1 2 34. Temperature / Humidity room sensors, electronic type, for measuring and controlling of temperature and relative humidity for all considered sensitive area shall be provided and their readings shall be displayed in the Portable Operator Terminal 3 NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY REVISIONS Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 35. Room Thermostat: 1) Room or space thermostat shall be electronically programmable type, microcomputer based, wall-mounted, one or multi-stage cooling and/or heating and with provisions for preset operating schedules. 2) Programming based on weekdays 3) The thermostat shall have the capability to setup up to four (4) separate temperatures per day 4) The thermostat shall have the capability of short cycle protection 5) The thermostat shall have the capability of automatically switching from cooling to heating and vice versa (as applicable). 6) The thermostat shall have the capability of Instant override of set point for continuous or timed period from one hour to thirty-one (31) days. 7) Instant override of set point for continuous or timed period from one hour to thirty-one (31) days. 8) Preferential rate control to minimize overshoot and deviation from set point. 9) The thermostat shall be compatible with DDC controller. 10) A thermostat guard (transparent protective cover), tamper-proof clear plastic cover shall be used for thermostat installation. 11) Switch selection features, including imperial or metric display, 12 to 24- hour clock, keyboard disable, remote sensor, fan on/auto. 12) Display of Thermostat shall include the following: a) Time of day b) Actual room temperature c) Programmed temperature d) Programmed time e) Duration of timed override f) Day of week g) System mode indication: heating, cooling, auto, off, fan auto, and fan on h) Stage (heating or cooling) operation 36. Room Humidistat shall be provided for controlling room humidity and it shall include the following: PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 24 OF 50 REV. 0 CERT. APP’D DESCRIPTION CHK’D 1) 2) 3) 4) Set point range of 20% - 80% RH (Relative Humidity), adjustment shall be external Built-in temperature measuring element Switching differential shall be fixed at 4% RH Removable transparent set point knob cover. When the cover is mounted, the selected set point can be read but cannot be adjusted externally C. HVAC EQUIPMENT AND MATERIALS (As Applicable) 1 2 3 1. NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY REVISIONS Prepared By: MIR Packaged Air Conditioning Units Manufactured Units: Self-contained, single packaged, pre-wired units and pre-charged with refrigerant complying to COMPANY Material Standard 73-TMSS-01, suitable for outdoor installation consisting of cabinet, refrigerant compressors, condensing coil and fans, cooling coil and fan, control wiring and piping, all factory assembled in a weather proof enclosure mounted on a pressed steel base ready for field connections to utilities and ducts. Each unit shall be equipped with hot gas bypass system. Construction and Ratings: In accordance with AHRI 340/360. Testing shall be in accordance with ASHRAE 16. Approved By: Performance Ratings: Energy Efficiency Rating (EER) and Coefficient of Performance (COP) shall not be less than as prescribed in COMPANY Material Standard 73-TMSS-01. NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 Electrical and Componentss i. Motor: NEMA MG-1 and MG-2. ii. Wiring Termination: Provide terminal lugs to match branch circuit conductor quantities, sizes and materials indicated. Enclose terminal lugs in terminal box sized to NFPA 70. iii. All main components of condensing units such as compressos and fan motors shall be UL Listed and shall carry the UL label of approval PACU shall be SASO certified Drip eliminators shall be provided if the maximum velocity through coils exceeds 2.54mps (500 fpm). Whenever provided, the static pressure loss shall be considered in fan selection. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED For Air Conditioning Equipment located near shore, the unit shall be suitable for coastal application and anti-corrosion protection shall be provided on equipment enclosure, coils, compressors, fans and control devices as applicable. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 25 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY DESCRIPTION CHK’D Provide protective coatings on condenser and evaporator coils to minimize effect of deterioration with no or little effect on heat exchange 2. Ventilation Supply and Exhaust / Purging Fans Centrifugal fans complying with COMPANY Material Standard 73-TMSS-05. 1 2 3 NO. Substation Tunnels Ventilation: REVISIONS Shall consist of exhaust and supply air fans complete with back draft dampers, fresh air aluminum filters, fresh air intake louvers and control devices for each tunnel partition. The supply air fans shall be filtered & louvered on all sides. Prepared By: MIR Approved By: NAO Certified By: Minimum TSP for supply fan: 1” wg. Minimum TSP for exhaust fan: 0.5” wg. Direct drive fans shall be preferred to minimize any maintenance issues of Belt tension, adjustment or failure, etc. Battery Rooms ventilation: Refer to COMPANY Standard TES-P-119.19, TES-K-100.01, 73TMSS-05 and TES-P-103.04. The Battery Room exhaust ductwork with its accessories such as supply registers, exhaust grilles, combination motorized smoke dampers and volume dampers shall be made of stainless steel materials Toilet Ventilation: Refer to TES-K-100.01, TES-P-119.19 and 73-TMSS-05 Fire Pump Room Ventilation: Refer to 73-TMSS-05 Fares Al-Amro Division Manager(A) Disconnect Switch: Factory Wired, non-fusible, in-housing for thermal overload protected motor and wall mounted multiple speed switch for direct driven fans ESD, E&DD 16-02-2021 Wiring Termination: Provide terminal lugs to match branch circuit conductor quantities, sizes and materials indicated. Enclose terminal lugs in terminal box sized to NFPA 70. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 26 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 3. Fresh Air Fans: 1 2 3 NO. DESCRIPTION Fan housing shall be of air-tight construction with scroll panel material formed and embedded into the side panels. The housing and bearing supports shall be constructed of welded structural steel members to prevent vibration and rigidly support the shaft and bearing. REVISIONS The fan wheel shall be of the non-overloading backward inclined or airfoil centrifugal type. Wheel shall be statically and dynamically balanced. The wheel cone and fan inlet cone shall be carefully matched and shall have precise running tolerances for maximum performance and operating efficiency. Turned, precision ground and polished steel shaft shall be sized so the first critical speed is at least 25% over the maximum operating speed for each pressure class. Close tolerances shall be maintained when the shaft passes through the bearing. Bearing shall be heavy duty grease lubricated, self-aligning or roller pillow block type. Bearing shall be selected for basic rating fatigue life of 80,000 hours at maximum operating speed for each pressure class. Prepared By: MIR Approved By: Each assembled fan shall be test run at the factory at the specified fan RPM and vibration signatures shall be taken on each in the horizontal, vertical and axial direction. The unit shall be mounted on vibration isolators. 4. Bleed Air Fans (Option for Inertial Air Filter System): NAO Centrifugal belt drive type designed primarily for continuous dust removal. Fan wheels shall be made of steel of side plate type with one- piece cast malleable iron or fabricated steel spider. Certified By: 5. Air Cleaning Fares Al-Amro Inertial Air Filter (For Make-up Air Intake System) Division Manager(A) ESD, E&DD Components: 16-02-2021 All finished components shall be phosphatized and given a coat of zinc chromate primer and finished with a coat of gray enamel. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED - Housing: Shall be constructed of not less than 11 gage steel. The housing shall be of all welded construction and equipped with continuous standing flanges around periphery of both air entering and air exiting sides. Flanges shall have pre-drilled bolt holes to facilitate field installation. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 27 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D - Bleed Air Manifold: Shall have continuous standing flange with pre-drilled bolt holes to facilitate field connection. Manifolds shall be sized to provide uniform airflow through each cells dust bin for proper balance and dust removal. DESCRIPTION Blade packs: blade packs shall be constructed of not less than 20 gage steel with Heli-arc welded construction. Blade packs vanes are to be individually formed and welded. Vanes shall be arranged to provide a circuitous path to the air flow and redirect the air forward the clean air outlet. The air passage ways shall have a minimum width of 48 mm. Blade pack shall be removable to provide for inspection or service 1 2 3 NO. - Bull nose: Shall be aerodynamically formed of 16 gage steel to provide air entry. REVISIONS Prepared By: MIR Approved By: - Bleed Slot: Shall not be less than 16 gages steel. The bleed slot shall be a rounded entry configuration to minimize destruction or plugging under heavy dust concentrations. - Inlet Screen: Shall consist of 26 gages, four meshes, galvanized hardware cloth integrally supported by a double layered 16 gage galvanized steel frame. Inlet screen shall be bolted to the housing. Performance: Self-cleaning inertial air cleaner with a bleed rate of 11.1% of the clean airflow at ambient temperature and dust specific gravity of 2.54 with minimum efficiency of 85% in accordance with ASHRAE 52.1. NAO Certified By: Basic Configuration System: A small auxiliary bleed fan is the most practical method of attaining the recommended 11.1% bleed airflow High Efficiency Air Filters (Bag Filters) Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Media: Ultra-fine fiberglass: - Holding Frame: Galvanized Steel Performance Rating - ASHRAE 52.2-2017 / EUROVENT 4/5 Test Method - Average Efficiency > 95% - Rated Air Flow Capacity at 152 Pa: 1180 L/sec. - Recommended Final Resistance: 250 Pa PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 28 OF 50 REV. 0 CERT. APP’D CHK’D Washable Permanent Panel Filters Media: 14 mesh aluminum, alternate layers of flat and herringbone crimp, four layers per 25mm, rod reinforced. - Frame: 16 gage galvanized steel - Thickness: 50mm thick as per TES-P-119.19 DESCRIPTION 1 2 Performance Rating: - Initial Resistance at 2.54 m/sec. face air velocity: 25 Pa - Recommended Final Resistance at 2.54 m/sec. face air velocity: 125 Pa 3 NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY Filter Gages REVISIONS Direct Reading Dial: 90mm diameter diaphragm actuated dial in metal case, vent valves, black figures on white background, front recalibration adjustment, ranging from 0 to 125 Pa, 2% of full-scale accuracy. Prepared By: MIR Accessories: Static pressure tips with integral compression fittings, 6.35mm aluminum or plastic tubing, 2-way or 3-way vent valves. Approved By: 6. Ductwork Galvanized Steel Ducts: NAO ASTM A653 hot dipped galvanized steel sheet, lock-forming quality, having G60 zinc coating in conformance with ASTM A90. All ductworks shall be insulated, double skin, factory fabricated. Certified By: Exhaust Duct for battery room shall be made of corrosion resistant material (stainless steel) per TES-K-100.01 Fares Al-Amro Insulated Flexible Ducts Division Manager(A) ESD, E&DD UL listed, two-ply vinyl film supported by helically wound spring steel wire, fiberglass insulation, and polyethylene vapor barrier film. 16-02-2021 Pressure Rating: 2.50 kPa positive and 250 Pa negative. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Maximum Velocity: 2.03 m/sec. Temperature Range: -23C to 71C. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 29 OF 50 REV. 0 CERT. APP’D CHK’D 7. Ductwork Accessories Air Turning Devices i. Fabricate in accordance with SMACNA HVAC Duct Construction Standards. ii. Multi-blade device with blades aligned in short dimension, steel construction, with individually adjustable blades, mounting straps. iii. Multi-blade devices with radius blades attached to pivoting frame and bracket, steel construction, with push / pull operator strap with 450 mm long removable key operator 1 2 3 DESCRIPTION a. NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY REVISIONS b. Motorized Volume Dampers i. Multi-Blade Damper: Fabricate of opposed blade pattern with maximum blade sizes 200 x 1825mm. Assemble center and edge crimped blades in prime coat or galvanized channel frame with suitable hardware. ii. End Bearing: Except in round duct 300mm and smaller, provide end bearing. On multiple blade dampers, provide oil impregnated nylon or sintered bronze bearing. Prepared By: MIR Approved By: NAO iii. Operator: UL listed and labeled spring return electric type suitable for available power supply. Provide end switches to indicate damper position. Locate damper operator on exterior of duct and link to damper operating shaft. Actuators located outdoors shall be suitable for outdoor weather application. Certified By: iv. Casing: Double Skin construction Fares Al-Amro Division Manager(A) ESD, E&DD c. Combination Fire and Smoke Dampers 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED i. Fabricate in accordance with NFPA 90A, UMC and SMACNA ii. Provide factory sleeve and collar for each damper. v. Multiple Blade Dampers: Fabricate with 16 gage (1.5mm) galvanized steel frame and blades, oil impregnated bronze or stainless steel sleeve bearings and plated steel axles, stainless steel jamb seals, 3.2 x PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 30 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY 1 2 v. Combination fire and smoke damper shall comply with the requirements of UL 555 for Fire Resistance Rating of 3 hours and UL 555S for Leakage Class I. 3 DESCRIPTION vi. Operators: UL listed and labeled spring return electric type suitable for available power supply. Provide end switches to indicate damper position. Locate damper operator on exterior of duct and connect to damper operating shaft. Actuators located outdoors shall be suitable for outdoor weather application NO. CHK’D 13 mm plated steel concealed linkage, stainless steel closure spring, blade stops and lock, and 13mm actuator shaft. REVISIONS d. Duct Access Doors Prepared By: MIR i. Fabricate in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible. ii. Fabrication Approved By: Rigid and close fitting of galvanized steel with sealing gaskets and quick fastening locking devices. For insulated ductwork, install minimum 25mm thick insulation with sheet metal cover: - Less than 300mm Square: Secure with sash locks. - Up to 450mm Square: Provide two hinges and two sash locks. - Up to 600 x 1200mm: Three hinges and two compression latches with outside and inside handles. - Larger Sizes: Provide an additional hinge. NAO Certified By: iii. Access door shall be connected to the frame using continuous (piano) hinge Fares Al-Amro Division Manager(A) iv Access doors with sheet metal screw fasteners are not acceptable. ESD, E&DD 16-02-2021 e. Duct Test Holes Drill test holes about 6 to 10 diameter of straight duct upstream from its location. Required number of holes and size shall be in conjunction with TAB CONTRACTOR’S requirements. Cap with neat patches, neoprene plugs, threaded plugs, or threaded or twist on metal caps. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED f. Fire Dampers PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 31 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء REVISIONS Fabricate in accordance with NFPA 90A and UL 555. ii. Horizontal Dampers: Galvanized Steel, 22 gage (0.76mm) frame, stainless steel closure spring. ii. Curtain Type Dampers: Galvanized steel with interlocking blades. Provide stainless steel closure springs and latches for closure under airflow conditions. Configure with blades out of air stream except for 250 Pa pressure class ducts up to 300 mm in height. vii. Fusible Links: UL 33, separate at 71°C with adjustable link straps for combination fire/balancing dampers. Prepared By: MIR Approved By: i. iv. Multiple Blade Dampers: 16 gage (1.5 mm) galvanized steel frame and blades, oil impregnated bronze or stainless steel sleeve bearings and plated steel axles, 3.2 x 13mm plated steel concealed linkage, stainless steel closure spring, blade stops and lock. 1 2 3 NO. DESCRIPTION CHK’D APP’D SAUDI ELECTRICITY COMPANY g. Flexible Duct Connections Fabricate in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible. NAO Certified By: Connector: Fabric crimped into metal edging strip. Fabric: UL listed fire retardant neoprene coated woven glass fiber fabric to NFPA 90A, minimum density 1.0 kg/m2. Net Fabric Width: Approximately 75mm wide Fares Al-Amro Division Manager(A) -Leaded Vinyl Sheet: Minimum 14mm thick, 4.2 kg/sq. m, 10dB attenuation in 10 to 10,000 Hz range. ESD, E&DD 16-02-2021 -Materials: Flame spread/smoke developed rating of 25/50 or less in accordance with NFPA 255. h. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Manual Volume Dampers Fabricate in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible. Single Blade Dampers: Fabricate for duct sizes up to 150 x 760mm. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 32 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D Multi-Blade Damper: Fabricate of opposed blade pattern with maximum blade sizes 200 x 1825mm. Assemble center and edge crimped blades in prime coated or galvanized channel frame with suitable hardware. DESCRIPTION End Bearings: Except in round ductwork 300mm and smaller, provide end bearings. On multiple blade dampers, provide oil impregnated nylon or sintered bronze bearings. Casing shall be double skin construction 1 2 3 NO. Quadrants - Provide locking, indicating quadrant regulators on single and multi-blade dampers. REVISIONS On insulated ducts mount quadrant regulators on standoff mounting brackets, bases or adapters. - Where rod lengths exceed 750mm, provide regulator at both ends. Prepared By: MIR Approved By: i. Back Draft Damper Fabrication in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible. NAO Channel Frame: Galvanized steel gauge 16, 50mm width x 13 mm height. Shafting: 13mm diameter round rod, continuous length per blade. Certified By: Fares Al-Amro Blades: Gravity shutter blades made up of galvanized steel gauge 26 with sponge foam gasket on edges. Blade Stopper: Made of gauge 18 galvanized steel. Division Manager(A) ESD, E&DD Type of Construction: Duct mounted, applicable for double skin 16-02-2021 j. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Splitter Dampers Material: Same gage as duct to 600mm size in either direction and two gages heavier for sizes over 600mm. Blade: Fabricate of double thickness sheet metal to streamline shape, secured with continuous hinge or rod. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 33 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY Operator: Minimum 6mm diameter, rod in self-aligning, universal joint action, flanged bushing with setscrew. DESCRIPTION k. Duct Smoke Detectors Photoelectric type smoke detector designed for air handling use in system with air velocity from 2.54 to 15.74 m/sec range, installed with sampling tube. 1 2 3 NO. Unit contains red alarm LED, self-contained to trip fan unit when unit senses product of combustion, reset type. REVISIONS Install as per NFPA 90A, IMC and manufacturer recommendation l. Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) Electric Duct Heater Type: Flanged-type mounted in a duct section with heater control access door on the side of the unit. Heating Element: Open coil 80% nickel, 20% chromium, type A resistance wire, type C alloys containing iron and other alloys are not acceptable. Coil shall be machine crimped into stainless steel. Coils shall be supported by ceramic bushings. Frame and Box: Shall be heavy gage galvanized steel, Terminal box shall be NEMA 1 (for indoor use) and NEMA 4 (for outdoor use) construction and shall be provided with hinged, latching cover and multiple concentric knockout for field wiring. Protection: Furnished with a disk type, automatic reset thermal cutout for primary over temperature protection and load carrying manual reset thermal cutouts, factory wired in series with heater stages for secondary protection. Control: Thermal cutouts, airflow switch, magnetic contactors, fuses, control circuit transformers and built-in snap-acting door interlocked disconnect switch. Provide each stage with monitoring pilot lights. ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Electrical: Rated for the voltage, phase, and minimum of 2 stages. 3-phase heaters shall have equal, balanced, 3-phase stages. All internal wiring shall be stranded copper with 105C insulation. Heater components shall be pre-wired and in most cases, field wiring shall only be limited to making connections to the line voltage, fan interlocked and control terminal blocks from supplied controller, thermostat and other control devices. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 34 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D Heater shall be provided with protective screen, 3/8" (9.5mm) stainless steel wire mesh, to be mounted on both sides of the heater. Pressure drop shall be included in fan selection DESCRIPTION Equipped with door interlock disconnect switch 8. Air Outlets/Inlets 1 2 3 NO. a. Ceiling Diffusers Type: Square, adjustable pattern, stamped, multi-core to discharge air in 360 degrees, fourway pattern with sectorizing baffles where indicated. REVISIONS Fabrication: Aluminum with baked enamel off white finish. Accessories: Radial opposed blade damper and multi-louvered equalizing grid with damper adjustable from diffuser face. Prepared By: MIR Approved By: Select 600 mm x 600 mm ceiling diffusers for air outlets located in open areas b. Supply Registers/Grilles Type: Streamlined and individually adjustable blades, 19mm minimum depth, 19mm maximum spacing with spring or other device to set blades, horizontal face, double deflection. NAO Certified By: Fabrication: Steel with 20 gage (0.90mm) minimum frames and 22 gage (0.80mm) minimum blades, steel and aluminum with 20 gage (0.90mm) minimum frame or aluminum extrusions with factory off-white enamel prime coat finish. Damper: Integral, gang operated opposed blade type with removable key operator, operable from face. Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED c. Exhaust and Return Grilles Type: Streamlined blades, 20mm minimum depth, 20mm maximum spacing, with spring or other device to set blades, horizontal face. Fabrication: Steel with 20 gage (0.90mm) minimum frames and 22 gage (0.80mm) minimum blades, aluminum extrusions with factory off-white enamel prime coat finish. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 35 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D d. Sand Trap Louvers DESCRIPTION Designed for intake applications to separate sand from intake air. Test dust distribution efficiency at 80% on 20 to 200 microns and 50% on 1 to 70 microns. Aluminum Construction: Frame 2mm thick, blades 1.5mm thick. Provided with self-emptying sand drain holes from the base. Size designed at 1.52 m/sec maximum face air velocity. 1 2 3 NO. Louvers REVISIONS Designed for intake applications to prevent rain penetration into the louver Design characteristics: Close blade spacing, low free area, with effective water rejection properties and meets AMCA wind driven rain requirements Prepared By: MIR Approved By: Linear Bar Grilles Type: Streamlined blades, 20mm minimum depth, 12.5 mm typical blade spacing, zero deflection with minimum 3mm bar thickness Fabrication: Steel with minimum 1.5mm thick frames and 6mm thick blades (minimum), extruded aluminium ally with factory off white enamel prime coat finish, powder coated. NAO 9. Instrumentation Certified By: a. Pressure Gauge Glacier filled, ASME B40.1, 65mm diameter drawn steel case, phosphor bronze bourdon tube, rotary brass movement, brass socket, with front recalibration adjustment, black scale on white background, 1% mid-scale accuracy, scale calibrated in both psi and kPa. Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED b. Temperature and Humidity Indicators (Combination) Wall mount, 300mm diameter dial, for indoor and outdoor service, bi-metal sensing mechanism protected by weatherproof aluminum case, temperature range -46 to 60C relative humidity range 20 to 90%. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 36 OF 50 REV. 0 CERT. APP’D CHK’D c. Thermostat DESCRIPTION Low voltage, adjustable to control compressor stages and heating stages in sequence with delay. Minimum two (2) stages for cooling and two (2) stages for heating. d. Humidistat 3-point, control heating or, in conjunction with an impulse relay, floating step control. Low voltage. 1 2 3 e. NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY Duct Type Thermometer (for main Supply, Return, Exhaust & Fresh Air Ducts) REVISIONS 100 mm dial face with raised black numbers on silver face, with red pointer. Scale ranges shall be -5 to 85C. Complete with insertion element and duct mounting screws Prepared By: MIR Approved By: NAO 10. Ductwork Insulation a. Materials: Flame spread/smoke developed rating of 25/50 or less in accordance with ASTM E84, NFPA 255 and UL 723. b. Type: Glass fiberboard, rigid. c. Insulation ESD, E&DD ASTM C612 – Mineral Fiber Block & Board Thermal Insulation, noncombustible. - Thermal Conductivity: 0.033 w/m C at 24 C mean temperatures - Maximum Service Temperature: 121 C - Maximum Moisture Absorption: 0.20% by volume - Thickness: 25mm indoor / 50mm outdoor - Density for Indoor / outdoor rectangular duct: 56 kg/m3 - Density for Indoor spiral duct: 48 kg/m3 16-02-2021 Facing: Factory applied foil reinforced kraft (FRK) vapor barrier Certified By: Fares Al-Amro Division Manager(A) d. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Adhesive Waterproof, mildew resistant, fire retardant type, apply vapor-seal pressure sensitive patches and joint sealing tape. e. Joint and Protrusion PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 37 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D 75mm wide tape shall be used. 11. Vibration Isolators DESCRIPTION Equipment shall be mounted on Vibrational isolators that are combination of mechanical spring & neoprene rubber pad regardless of the components of equipment are already fitted with such items a. Restrained Spring Isolators Spring Isolators 1 2 3 NO. i. - Provide hot dipped galvanized housings and neoprene coated springs. - Code: Color code springs for load carrying capacity. REVISIONS ii. Prepared By: MIR Minimum horizontal stiffness equal to 75% vertical stiffness, with working deflection between 0.30 and 0.60 maximum deflection. Approved By: - Spring Mounts: Provide with leveling devices, minimum 0.6mm thick neoprene sound pads and zinc chromate plated hardware. - Sound Pads: Size for minimum deflection of 1.3mm, meet requirements for neoprene pad isolators. - Restraint: Provide heavy mounting frame and limit stops. NAO Certified By: Springs b. Neoprene Pad Isolators i. Rubber or Neoprene Waffle Pads - 30 durometer - Minimum 13mm thick - Maximum loading 275 kPa - Height of ribs shall not exceed 0.7 times width. ii. Configuration Single layer, 13mm thick waffle pads bonded each side of 6mm thick steel plate. Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 38 OF 50 REV. 0 CERT. APP’D CHK’D D. Execution and Installation 1. General Install the system and equipment in accordance with TCS-K-100, TES-P-119.19 and manufacturer’s instructions. DESCRIPTION 1 2 Provide access around equipment for service not less than the manufacturer’s minimum requirement and/or TCS-K-100.01 3 NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY Install Air Conditioning units on a reinforced concrete foundation above finish grade as specified in TES-P-119.19 with necessary vibration isolation. REVISIONS Smoke purging fans installation on return air duct of HVAC system shall be avoided wherever possible. Prepared By: MIR Approved By: Wall-mounted combination, temperature/humidity indicators (hygrometers) shall be provided inside and outside the building. Basement & Tunnel ventilation fans shall be located to have a minimum clearance of 1.5-meter from building wall or tunnel internal firewall. Registers / Grilles in tunnel or basement wall opening, if any, shall be coordinated with cable tray arrangement and be accessible for commissioning & maintenance. NAO All duct joints along transversal axis shall be slip-on-flanges clamped / bolted with necessary gasket for leak prevention as per TES-K-100.01 Certified By: Fares Al-Amro Division Manager(A) Locate HVAC Equipment and Design ductwork considering the possibility of building expansions in future mainly for GIS and SWGR Buildings. Install Electric duct heater as per manufacturer’s recommendation but shall not be less than the requirement specified in TES-K-100.01 ESD, E&DD Sleeve duct passing through walls & floors 16-02-2021 2. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Ductwork and Duct Accessories Perform WORK in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible, NFPA 90A Standards, TES-K-100 and TCS-K-100. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 39 OF 50 REV. 0 CERT. APP’D CHK’D Fabricate and support in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible. Provide motorized combination fire and smoke dampers in the main supply and return duct penetrations through the walls of the building, to isolate areas protected with clean agent fire extinguishing system and to isolate areas provided with HVAC & purging system. DESCRIPTION 1 2 Provide fusible link operated fire dampers in all other fire duct penetrations and opening for louvers and grilles in fire rated walls and partitions. 3 NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY REVISIONS Provide duct access doors for inspection and cleaning, before and after filters, coils, fans, motorized dampers, fire dampers, combination fire and smoke dampers, electric duct heater and elsewhere as required. Provide duct test holes where required for testing and balancing purposes. Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) Duct access doors for dampers shall be at least 600 x 600mm, large enough to permit body movement for maintenance. Provision shall be made to conduct inspection and maintenance to air ducts near bus bar and energized equipment without power outage. Prior to installation, ductwork and duct accessories delivered to site shall be protected from weather extremes. Suitable storage facilities for protection, especially for the factory insulated, factory fabricated ductworks, shall be provided as per the requirements of TCS-K-100.01 Factory fabricated ducts and duct components, ventilation equipment, and HVAC control systems delivered at site shall be protected with plastic duct wrap made of 3.0 mil polyethylene sheet with a high-tack adhesive for protection against moisture, dust, and debris For GIS halls where GIB / GIL is not used for GIS to Gantry connections, HVAC ducts may be installed below crane level subject to meeting the adequate clearance from GIS Equipment / components. ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED For GIS halls having GIS to Gantry connections through GIB / GIL, the HVAC ducts shall be located above crane level to avoid clearance & coordination issues HVAC Duct & Air Inlet / Outlet devices location shall be avoided over GIS LCC / Electromechanical / communication panels as much as possible PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 40 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 3. Air Inlet/Air Outlet Provide balancing dampers on duct take-off to diffusers, grilles and registers, despite whether dampers are specified as part of the grille and registers assembly. 1 2 a. Paint ductwork visible behind air outlets and inlets back. b. In Battery room, exhaust grilles shall be located at 3 levels – Near Floor, Middle portion and Below Roof 3 NO. DESCRIPTION a. 4. Ductwork Insulation REVISIONS Verify that ductwork has been air leak tested before applying insulation materials. Provide ductwork with external insulation with vapor barrier jackets. Use 25 mm thick insulation for ducts installed inside the building and 50 mm thick insulation for outside ducts. Prepared By: MIR Approved By: For exterior applications, provide vapor barrier jacket. Cover with aluminum jacket with seams located on bottom side of horizontal equipment. 5. NAO Provide vibration isolation on motor driven equipment over 0.35kW, plus connected piping and ductwork, as required. 6. Certified By: Fares Al-Amro Vibration Isolation Mechanical Identification Identify Mechanical equipment, Piping, ductwork, control panels and major control components outside panels with plastic nameplates. 7. Air Cleaning Division Manager(A) ESD, E&DD Install filter gage static pressure tips upstream and downstream of filters. Mount filter gages on outside of filter housing or filter plenum, in accessible position. Adjust and level. 16-02-2021 Provide filter gages on banks, installed with separate static pressure tips upstream and downstream of filters. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 41 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 8. Submittals DESCRIPTION Submit diagrams indicating mechanical system controlled and control system components. Label with settings, adjustable range of control and limits. Include written description of control sequence. Include flow diagrams for each control system, graphically depicting control logic. 1 2 3 NO. Shop drawings indicating components, assembly, dimensions, weights and loading, required clearances, and location and size of field connections. REVISIONS Include schematic layouts showing Air conditioning equipment, supply and return air ducting with accessories required for complete system. Submit product data indicating rated capacities, weights specialties and accessories, electrical nameplate data and wiring diagrams. Prepared By: MIR Approved By: Submit test reports. Indicate pressure tests performed. Include data/duct section tested, test pressure and leakage rate following SMACNA HVAC Air Duct Leakage test manual NAO The contractor shall submit coordination drawings between electrical, civil and mechanical works and confirmation of no conflict between them along with the first submission of the detailed design to avoid any site modifications. The design and drawings of HVAC shall be subject to COMPANY Approval Certified By: All design calculation and drawing submittal shall be stamped and certified by both the design consulting office and the contractor E. Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Start-up Testing and Commissioning Testing and commissioning work required herein shall be in accordance with the applicable requirement of TCS-K-100.01. The WORK includes the following tests: i. Duct Leakage Test ii. Sound Level Test iii. Vibration Test Submit name of Testing and Commissioning Agency for approval within thirty (30) days after award of CONTRACT. Agency shall be specialized in Testing and Commissioning of HVAC systems with minimum three (3) years documented experience. Perform WORK under supervision of NEBB or any other Certified Testing & Commissioning Supervisor acceptable to the COMPANY. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 42 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY Total system balance shall be performed in accordance to ASHRAE System handbook or NEBB procedural Standards for testing, adjusting and balancing of Environmental systems DESCRIPTION Prior to commencing WORK, submit detailed test and commissioning procedures, agenda and draft reports on applicable NEBB forms indicating adjusting, balancing & equipment data required. 1 2 3 NO. Submit draft copies of the report for review prior to final acceptance of the PROJECT. Provide final copies for COMPANY REPRESENTATIVE and for inclusion in operating and maintenance manuals. REVISIONS Prepared By: MIR Provide reports in hard cover, A4 size, 3-ring or 4-ring binder manuals, complete with index page and colored indexing tabs, with cover identification at front and side. Include set of reduced drawings in all material submittals with all equipment identified to correspond with data sheets and indicating thermostat locations. Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 43 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D 5.02 PLUMBING SYSTEMS S.no. 1 Service Compliance Water Piping, PVC Pipe: Buried & Concealed 75-TMSS-01 / per ASTM D1785, Schedule 80 2 Rain Downspout 1 2 Plumbing Piping 3 NO. DESCRIPTION Plumbing system shall be in accordance with COMPANY Standard TES-P-119.19 requirements and as specified below: REVISIONS Prepared By: MIR Approved By: 3 4 NAO Certified By: 5 Fares Al-Amro Fittings Same as pipe materials & suit pipe size & end design Water PVC Pipe: TA-800024R0 75-TMSS-01 / per ASTM D1785, Schedule 80 Water Piping, Above Steel Pipe: per ASTM Malleable Grade & Exposed A53, Schedule 40, iron, per galvanized AN/ASME B16.3 Water Piping, Hot CPVC pipes Same as Water 75-TMSS-01 / pipe per ASTM F441 Sch. materials & 80 suit pipe size & end design Sanitary Sewer PVC Pipe: per ASTM Same as Piping D1785, Schedule 40 pipe materials Joining per ASTM D2855, solvent weld with ASTM D2564 solvent cement Threaded up to 50 mm NPS As per manufacturer Standard & Procedures Solvent weld. Division Manager(A) ESD, E&DD Refer to TES-P-119.19 for specification of Valves, Flanges and Unions 16-02-2021 Plumbing Fixtures THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Plumbing Fixtures to be provided shall be as per COMPANY Standards TES-P-119.19, 75-TMSS02. Plumbing fixtures to be provided shall include Western Water Closets, Eastern Water Closets, Lavatories, Urinals, Ablution faucet and Plumbed Eyewash with hand held hose spray Minimum working pressure for urinal = 173 kpa Refer to 90-TMSS-08 for specification of Eyewash Equipment. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 44 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D Plumbing Specialties 1 2 Plumbing Equipment 3 NO. DESCRIPTION Plumbing Specialties to be provided shall be as per COMPANY Standards TES-P-119.19. Plumbing specialties to be provided shall include Floor Drains, Clean outs, Hose bibs, Water hammer Arrestor, etc. Plumbing Equipment to be provided shall be as per below mentioned COMPANY Standards. Plumbing Equipment to be provided shall include Water Transfer Pump & Booster Pump; Electric Water Heater; Water Storage Tanks; Sump Pumps for Basement, Tunnels & Trenches and Sump Pump for Oil Catch Basin of Transformer & Reactors REVISIONS Water Transfer Pump The pump shall be close-coupled and designed for horizontal installation. Pump parts material specifications shall be as follows: Prepared By: MIR Approved By: Casing: Case Wearing Ring: Impeller: Shaft: Mechanical Seal: Cast Iron Bronze Bronze Stainless Steel Buna N Bellows, Stainless Steel Metal Parts, Ni-Resist Seat and Carbon Washer NAO Certified By: The pump for the Control Building & SEB Toilet shall be designed to deliver 1.58 liters per second & 0.79 liters per second of water respectively. Pump motor shall have a TEFC enclosure and operable at 230 volts/ 1-phase / 60 Hz. with a speed of 3450 rpm. The pump shall be equipped with a complete safety and manual operational controls and shall be provided with galvanized steel sun shed. Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Booster Pump The pump shall be close-coupled and designed for horizontal installation. Pump parts material specifications shall be as follows: Casing: Cast Iron Case Wearing Ring: Bronze Impeller: Bronze Shaft: Stainless Steel Mechanical Seal: Buna N Bellows, Stainless Steel Metal Parts, Ni-Resist Seat and Carbon Washer PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 45 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY DESCRIPTION CHK’D The pump shall be designed to deliver water as required by the system, including the emergency eyewash and hand spray equipment with an inlet supply pressure of 276 kPa. Pump motor shall have a TEFC enclosure and operable at 230 volts, 1-phase, 60 Hz. with a speed of 3450 rpm. The booster system shall be skid mounted and provided with shed when installed outside the building. The skid shall include control panel, pressure tank, pressure gauge and pressure switch. 1 2 3 NO. Install the pump in such a way that its inlet line is facing directly towards the O/H Water Storage Tank outlet at the same elevation, connected through a straight pipe without an elbow REVISIONS Sump Pump for Basement, Tunnels & Trenches Refer to 83-TMSS-01 and TES-P-119.19. Prepared By: MIR Approved By: NAO Certified By: Fares Al-Amro Sump Pump Main control panel: Refer to TES-P-119.19 Sump Pump Local control panel: Refer to TES-P-119.19 Main Control panel shall provide “SUMP PUMP OPERATE” and “SUMP PUMP FAULTY” alarms at SAS Interface as shown in Mechanical / HVAC Alarm Logic Diagram Indoor Main Control Panel – IP 55 or NEMA 3 Enclosure, Aluminium nameplate, HAND-OFFAUTO Switch, RUN, TRIP & Power LEDs, all applicable motor protection, controls & wiring conforming to NEC. Indoor or Outdoor Local Control panel – IP 67 or NEMA 6 Enclosure, Stainless steel nameplate, ON – OFF Isolation Switch, HAND-OFF-AUTO Switch, RESET Push Button, local SILENCE Push Button, HORN, HIGH / LOW WATER LEVEL, RUN, TRIP & POWER ON LEDs, all applicable motor protection, controls & wiring conforming to NEC. Panel manufacturer / supplier details shall be fixed on the panel door Division Manager(A) ESD, E&DD Sump Pump for Oil Catch Basin of Transformers & Reactors 16-02-2021 Refer to TES-P-119.21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Outdoor Local Control panel –NEMA 4X Enclosure, ON – OFF Isolation Switch, Stainless steel nameplate, RUN, TRIP & Power LEDs, all applicable motor protection, controls & wiring conforming to NEC. PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 46 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D The pump shall be self-priming type designed for horizontal installation. Pump parts material specifications shall be as follows: DESCRIPTION Casing: Ductile Iron Impeller: Ductile Iron Shaft: SAE 4140 Mechanical Seal: Silicon/Silicon Painting/Coating: Refer to TES-H-107.01 requirements. 1 2 3 NO. The pump shall have a discharge capacity of 4.0 lps at rotational speed of 3450 rpm. Pump motor shall have a TEFC enclosure. REVISIONS The pump shall be equipped with complete safety operational controls and shall be provided with a galvanized steel sun shed. Electric Water Heater Prepared By: MIR Approved By: The water heater shall conform to the requirements of COMPANY Standard TES-P-119.19 & 94-TMSS-01. Minimum capacity shall be 57 liters. Water Storage Tank Refer to TES-P-19.19 NAO Drinking Water Cooler Refer to 94-TMSS-02 Certified By: Plumbing Systems Commissioning: Fares Al-Amro Division Manager(A) Hydro-testing shall be performed for all piping & plumbing systems to meet the requirements of TES-P-119.19 & Plumbing codes ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 47 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء APP’D SAUDI ELECTRICITY COMPANY CHK’D 5.03 WEIGHT HANDLING SYSTEMS A. EOT Crane DESCRIPTION Refer to TES-P-119.19R3 B. Hoist for Pump House 1 2 3 NO. 1. Hand Chain Hoist a. Provide hoist with lifting capacity to handle the heaviest load during maintenance of the equipment. REVISIONS b. The hoist shall have enclosed construction, surfaced hardened gears, anti corrosive finish on grade 80 chain, self sustaining maintenance free friction brake, safety hook of alloy steel and protection against overload. Prepared By: MIR c. The hoist shall be hung into hand-geared traveling trolley Approved By: SECTION VI - PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS NAO A list of documents that contractor shall submit at prescribed project phases is attached. Any other documents not mentioned here, but is a requirement shall be provided by contractor at respective PHASE. Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 48 OF 50 REV. 0 CERT. APP’D CHK’D SECTION VII - HVAC CONTROL SCHEMATIC DIAGRAMS & HVAC ALARMS LOGIC DIAGRAM The HVAC control schematic diagrams WT-925440 Sheet 01 to 08 and Mechanical / HVAC Alarms Logic Diagram WT-925441 Sheet 01 of 01 attached with PTS are for guidance of contractor. Contractor shall follow the diagrams for HVAC system design. Any changes necessary during project execution due to changes in substation layout or higher capacity units or any such other reasons shall be incorporated with SEC approval. 1 2 3 DESCRIPTION NO. الشركة السعودية للكهرباء SAUDI ELECTRICITY COMPANY REVISIONS Prepared By: MIR Approved By: NAO Certified By: 1. 2. 3. 4. 5. 6. 7. 8. WT-925440 Sheet 01 of 08: HVAC Control Schematic Diagram – 380kV GIS Building WT-925440 Sheet 02 of 08: HVAC Control Schematic Diagram – 380kV GIS Building WT-925440 Sheet 03 of 08: HVAC Control Schematic Diagram – 380kV GIS Building WT-925440 Sheet 04 of 08: HVAC Control Schematic Diagram – 132kV GIS Building–I WT-925440 Sheet 05 of 08: HVAC Control Schematic Diagram – 132kV GIS Building–II WT-925440 Sheet 06 of 08: HVAC Control Schematic Diagram–Control Room WT-925440 Sheet 07 of 08: HVAC Control Schematic Diagram–Control Building WT-925440 Sheet 08 of 08: HVAC Control Schematic Diagram–SEC Transmission Room 9. WT-925441 Sheet 01 of 01: MECHANICAL / HVAC ALARM LOGIC DIAGRAM SECTION VIII - ANNEXURES The BIDDER shall review PTS and fill the annexures (attached herewith in Appendix XIIB) with signature, stamp and submit the same to serve as Scope of Supply document for Mechanical works as Bid Stage Submission for COMPANY review. Annexure-XIIB-I: HVAC SOW requirement Annexure-XIIB-II: Plumbing SOW requirement Annexure-XIIB-III: Weight handling SOW requirement Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 49 OF 50 REV. 0 CERT. الشركة السعودية للكهرباء CHK’D APP’D SAUDI ELECTRICITY COMPANY 1 2 3 NO. DESCRIPTION SECTION IX - DATA SCHEDULES The following data schedules are attached to Scope of Work and Technical Specifications PTS / Appendix XIIB: REVISIONS Prepared By: MIR 73-TMSS-01 (Rev. 01) Air Conditioning Units, Packaged 73-TMSS-05 (Rev. 0) 75-TMSS-01 (Rev. 0) 83-TMSS-01 (Rev. 0) Centrifugal Exhaust Fans 94-TMSS- 01 (Rev. 0) Automatic Electric Heaters 94-TMSS- 02 (Rev. 0) Drinking Water Coolers Plastic Piping for Plumbing System Submersible Sump Pumps Approved By: NAO Certified By: Fares Al-Amro Division Manager(A) ESD, E&DD 16-02-2021 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PTS-20WN374, 16-02-2021 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132kV NIC CIRCLE BSP JOB ORDER NO. PLANT NO. SE0514 NORTH WEST OPERATING AREA SAUDI ARABIA INDEX A DOCUMENT NO. APPENDIX-XIIB PTS-20WN374 PAGE NO. 50 OF 50 REV. 0 MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132KV NIC CIRCLE BSP ATTACHMENT TO APPENDIX XII-B: DOCUMENT REQUIREMENTS FOR ELECTRO-MECHANICAL SYSTEMS SECTION VI - PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS A. The CONTRACTOR shall submit all design documents, calculations, studies and drawings at various stages of the PROJECT as per below Appendix XIIB Table, as a minimum for Electro-mechanical Systems. Phase 01 Discipline Work Packages Electrical General Submittals Drawing Control Sheet Overall Substation Layout (Equipment arrangement Plan & Sections) Mechanical Others (if any) General Work Packages Prequalification Topics Stage Stage Markup/ As Built Stage WP EHV & HV EHV & HV WP WP ☐ ☐ ☒ ☐ ☐ ☒ ☐ ☒ ☒ ☐ ☐ ☐ ☐ ☒ ☒ ☐ ☐ ☐ ☐ ☒ ☐ Plumbing General Notes & Legend Drawings EHV ☐ ☒ ☒ HVAC General Notes & Legend Drawings EHV ☐ ☒ ☒ WP ☐ ☐ ☐ EHV or HV Bid Design Submittals Topics Stage Stage Markup /As Built Stage Prequalification of Electro-Mechanical Sub-contractors / Vendors WP EHV ☐ ☐ ☐ ☒ ☐ ☐ EHV GIS Room- Technical Submittal for EOT Crane WP EHV ☐ ☐ ☐ ☒ ☐ ☐ HV GIS Room- Technical Submittal for EOT Crane EHV ☐ ☒ ☐ ☐ ☐ ☐ EOT Crane Others (if any) Design EHV Phase 02 Mechanical Bid Scope of Supply for Electromechanical controls, HVAC, Plumbing & Weight Handling systems HVAC System Design Criteria Others (if any) Discipline EHV or HV 1 of 7 Submittal Contents / Document or Drawing Titles / Remarks Submittal to include all electro-mechanical documents & Drawings Locations of all outdoor electro=mechanical equipment to be indicated in overall substation layout. Refer to Annexures attached in PTS/Appendix XIIB. The BIDDER shall fill in these annexures with stamp and submit along with the Technical Proposal. 1. TES-K-100.01 selection criteria 2. ASHRAE references 3. PME / MODA references 4. Other local references 1. General Notes 2. Abbreviations 3. Symbols/Legends 4. Other if any 1. General Notes 2. Abbreviations 3. Symbols/Legends 4. Other if any Submittal Contents / Document or Drawing Titles / Remarks 1. 2. 3. 4. 5. 6. 7. 8. Subcontractor PQ Documents List of similar works completed List of equipment owned or rented Subcontractor ongoing projects list, etc. Subcontractors Schedule (Including Design, material delivery, construction, testing & commissioning, etc.) Subcontractor proposed Manpower chart for project with resumes Subcontractor organization chart Other (if any) 1. 2. 3. 4. 5. 6. 1. 2. 3. 4. 5. 6. Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Equipment Dimensional / Arrangement drawings Equipment wiring diagrams Compliance Statements (PTS, Standards) Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Equipment Dimensional / Arrangement drawings Equipment wiring diagrams Compliance Statements (PTS, Standards) Other if any MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132KV NIC CIRCLE BSP ATTACHMENT TO APPENDIX XII-B: DOCUMENT REQUIREMENTS FOR ELECTRO-MECHANICAL SYSTEMS EHV or HV Bid Design Submittals Topics Stage Stage Markup/ As Built Stage Material Submittal for Pump House Monorail Crane WP EHV ☐ ☐ ☐ ☒ ☐ ☐ Material Submittal for Sliding Gate EHV ☐ ☒ ☐ Material Submittal for Submersible Sump Pumps EHV & HV ☐ ☒ ☐ Technical Submittal for Air Conditioning Units for all rooms / Building(s) EHV & HV ☐ ☒ ☐ Technical Submittal for JIB CRANE / HOIST EHV & HV ☐ ☐ ☐ Technical Submittal for HVAC DDC Control Panel EHV & HV ☐ ☒ ☐ Material Submittal for HVAC Installation Material EHV & HV ☐ ☒ ☐ Technical Submittal for Ventilation Fans (Basement / Tunnels / Battery Room / Toilets / etc.) & Smoke Purge Fans - Substation EHV & HV ☐ ☒ ☐ Material Submittal for Bleed air fan and Inertial air filter (where applicable) EHV & HV ☐ ☒ ☐ Phase 03 Discipline Mechanical Work Packages Mechanical Material 2 of 7 Submittal Contents / Document Titles / Remarks 1. 2. 3. 4. 5. 6. 1. 2. 3. 4. 5. 6. 1. 2. 3. 4. 1. 2. 3. 4. 5. 6. 7. 8. 9. 1. 2. 3. 4. 5. 6. 1. 2. 3. 4. 5. 1. 2. 3. 4. 1. 2. 3. 4. 5. 6. 7. 8. 1. 2. 3. 4. 5. Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Equipment Dimensional / Arrangement drawings Equipment wiring diagrams Compliance Statements (PTS, Standards) Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Panel Internal & External Layout Wiring Diagram Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets, etc. Compliance Statements (PTS, Standards) Other if any Original Equipment (PACU) catalogues PACU Auxiliary Equipment / Component catalogues / data sheets Equipment Dimensional / Arrangement drawings Equipment computer selection sheets Data schedules as per PTS/TMSS Equipment Internal wiring diagrams Equipment Panel Internal Layout Compliance Statements (73-TMSS-01, PTS, 01-TMSS-01, etc.) Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Equipment Dimensional / Arrangement drawings Equipment wiring diagrams Compliance Statements (PTS, Standards) Other if any Original DDC Equipment catalogues / datasheets Field Installation devices catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Other if any Original Equipment (Supply, Exhaust & Smoke Purge Fans) catalogues Fans Auxiliary Equipment / Component catalogues / data sheets Equipment Dimensional / Arrangement drawings Equipment computer selection sheets Data schedules as per PTS/TMSS Equipment wiring diagrams Compliance Statements (73-TMSS-05, PTS, 01-TMSS-01, etc.) Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Conformance Certificates, Approvals, Statements & Reports (as applicable) Other (if any) MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132KV NIC CIRCLE BSP ATTACHMENT TO APPENDIX XII-B: DOCUMENT REQUIREMENTS FOR ELECTRO-MECHANICAL SYSTEMS Material Submittal for Electric Duct Heaters EHV ☐ ☒ ☐ Plumbing Bulk Materials (Pipes, Fittings, Joining, Tanks, Eyewash, Water Cooler, etc.) EHV & HV ☐ ☒ ☐ Material Submittal for Toilet Fixture & Accessories Including Electrical Water Heater EHV ☐ ☒ ☐ WP ☐ ☐ ☐ EHV or HV Bid Design Topics Stage Stage Markup/ As Built Stage WP ☐ ☐ ☐ EHV GIS Room- HVAC System Design Calculation and Drawing EHV ☐ ☒ ☒ EHV GIS Room- Plumbing Design Calculations & Drawings EHV ☐ ☒ ☒ EHV GIS Room- Material Submittal for HVAC Control Panels EHV ☐ ☒ ☒ WP ☐ ☐ ☐ HV GIS Room I- HVAC System Design Calculation and Drawing EHV ☐ ☒ ☒ HV GIS Room II- HVAC System Design Calculation and Drawing EHV ☐ ☒ ☒ Others (if any) Phase 04 Discipline Work Packages Mechanical EHV GIS Room / building Submittals HV GIS Room / building 3 of 7 1. 2. 3. 4. 1. 2. 3. 4. 5. 6. 7. 8. Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Other if any Submittal Contents / Document Titles / Remarks 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 1. 2. 3. 4. 1. 2. 3. HVAC System Design Calculations HVAC Duct & Equipment Layout– Roof HVAC Duct Layout– Ground Floor HVAC Sections HVAC Air Flow Diagram HVAC Control Schematic Diagram HVAC Control Panel Layout HVAC Power Layout (PACU, SPF, Ventilation Fan, EDH, MVD, MFSD, etc.) HVAC Equipment Schedule Other if any Design calculations Roof Drainage System, Layout, Section & Details Equipment Schedules Other if any Panel Internal & External Layout Wiring Diagram Other if any 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. HVAC System Design Calculations HVAC Duct & Equipment Layout– Ground Floor HVAC Duct Layout– Ground Floor HVAC Duct Layout–Basement HVAC Sections HVAC Air Flow Diagram HVAC Control Schematic Diagram HVAC Control Panel Layout HVAC Power Layout (PACU, SPF, Ventilation Fan, EDH, MVD, MFSD, etc.) HVAC Equipment Schedule Other if any HVAC System Design Calculations HVAC Duct & Equipment Layout– Ground Floor HVAC Duct Layout– Ground Floor HVAC Duct Layout–Basement HVAC Sections HVAC Air Flow Diagram HVAC Control Schematic Diagram HVAC Control Panel Layout HVAC Power Layout (PACU, SPF, Ventilation Fan, EDH, MVD, MFSD, etc.) HVAC Equipment Schedule Other if any MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132KV NIC CIRCLE BSP ATTACHMENT TO APPENDIX XII-B: DOCUMENT REQUIREMENTS FOR ELECTRO-MECHANICAL SYSTEMS HV GIS Room I- Plumbing Design Calculations & Drawings EHV ☐ ☒ ☒ HV GIS Room II- Plumbing Design Calculations & Drawings EHV ☐ ☒ ☒ HV GIS Room I- Material Submittal for HVAC Control Panels EHV ☐ ☒ ☒ HV GIS Room II- Material Submittal for HVAC Control Panels EHV ☐ ☒ ☒ MV GIS Room / building MV Metal-Clad Switchgear Room / building WP ☐ ☐ ☐ WP ☐ ☐ ☐ Transformers & Reactors WP ☐ ☐ ☐ Oil Filled Equipment (Plumbing & Drainage) System Design Calculation & Drawings EHV ☐ ☒ ☒ Technical Data of Transformer & Reactor Oil Pit Pump with local control panel EHV ☐ ☒ ☐ WP ☐ ☐ ☐ EHV or HV Bid Design Topics Stage Stage Markup /As Built Stage WP ☐ ☐ ☐ HVAC System Design Calculation and Drawings for Control Building Including Ventilation in Battery Room and Toilet EHV ☐ ☒ ☒ HVAC System Design Calculation and Drawings for Control Room EHV ☐ ☒ ☒ 1. 2. 3. 4. 5. 1. 2. 3. 4. 5. 1. 2. 3. 1. 2. 3. Design calculations Roof Drainage System, Layout, Section & Details Basement Drainage System, Layout, Section & Details Equipment Schedules Other if any Design calculations Roof Drainage System, Layout, Section & Details Basement Drainage System, Layout, Section & Details Equipment Schedules Other if any Panel Internal & External Layout Wiring Diagram Other if any Panel Internal & External Layout Wiring Diagram Other if any 1. Others (if any) Phase 05 Discipline Work Packages Mechanical Control Room / building Submittals 4 of 7 1. 2. 3. 1. 2. 3. 4. 5. 6. Design Calculation Layout, Section, Isometric & Details Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Panel Internal & External Layout Wiring Diagram Other if any Submittal Contents / Document Titles / Remarks 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 1. 2. 3. 4. 5. 6. 7. 8. 9. HVAC System Design Calculations HVAC Duct & Equipment Layout-t– Ground Floor HVAC Duct Layout– Ground Floor HVAC Sections HVAC Air Flow Diagram HVAC Control Schematic Diagram HVAC Control Panel Layout HVAC Power Layout (PACU, SPF, Fan, EDH, MVD, MFSD, etc.) HVAC Equipment Schedule Other if any HVAC System Design Calculations HVAC Duct & Equipment Layout– Ground Floor HVAC Sections HVAC Air Flow Diagrams HVAC Control Schematic Diagrams HVAC Control Panel Layouts HVAC Power Layouts (PACU, SPF, Ventilation Fan, EDH, MVD, MFSD, etc.) HVAC Equipment Schedule Other if any MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132KV NIC CIRCLE BSP ATTACHMENT TO APPENDIX XII-B: DOCUMENT REQUIREMENTS FOR ELECTRO-MECHANICAL SYSTEMS Control Building & Site - Plumbing Design Calculations & Drawings EHV ☐ ☒ ☒ HVAC Duct Factory Submittal EHV ☐ ☒ ☐ Material Submittal for HVAC Control Panel for Control Building EHV ☐ ☒ ☒ Material Submittal for HVAC Control Panel for Control Room EHV ☐ ☒ ☒ Material Submittal for Water Transfer & Booster Pumps with Local Control Panel EHV ☐ ☒ ☐ WP ☐ ☐ ☐ Substation Tunnels Drainage System Design Calculations & Drawings EHV ☐ ☒ ☒ Substation Tunnels Ventilation System Design Calculations & Drawings EHV ☐ ☒ ☒ EHV GIS Room Tunnels - Material Submittal for Ventilation Control Panel EHV ☐ ☒ ☒ HV GIS Room I Tunnels - Material Submittal for Ventilation Control Panel EHV ☐ ☒ ☒ HV GIS Room II Tunnels - Material Submittal for Ventilation Control Panel EHV ☐ ☒ ☒ HVAC System Design Calculation and Drawings for SEC Transmission Room Building EHV ☐ ☒ ☒ Tunnels & Outdoor Rooms 5 of 7 1. 2. 3. 4. 5. 6. 7. 8. 9. 1. 2. 3. 4. 5. 6. 7. 8. 1. 2. 3. 1. 2. 3. 1. 2. 3. 4. 5. 6. Design calculations Roof Drainage System, Layout, Section & Details Basement Drainage, Layout Section, Isometric & Details Water Supply System, Overall Layout, Isometric & Details Riser Diagrams Sewerage and vent system, Layout, Isometric & Details Equipment Schedules Yard Piping Layout & Details Other if any Duct factory PQ Documents Duct factory ongoing projects list, etc. Duct factory Schedule (Including Design, manufacture, material delivery, etc.) Duct factory Manpower chart Conformance Certificates, Approvals, Statements & Reports (as applicable) Fabrication drawings for HVAC Duct work Fabrication drawings for HVAC Duct Fittings Other (if any) Panel Internal & External Layout Wiring Diagram Other if any Panel Internal & External Layout Wiring Diagram Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Panel Internal & External Layout Wiring Diagram Other if any 1. 2. 3. 4. 5. 6. 1. 2. 3. 4. 5. 1. 2. 3. 1. 2. 3. 1. 2. 3. 1. 2. 3. 4. 5. 6. 7. 8. 9. Tunnels Drainage System Design calculations 380kV Building Tunnels Drainage System – Layout, Section & Details 132kV Building Tunnels Drainage System – Layout, Section & Details 13.8kV Building Tunnels Drainage System – Layout, Section & Details Equipment Schedules Other if any Ventilation System Design calculations 380kV Building Tunnels Ventilation System –Layout, Section & Details 132kV Buildings Tunnels Ventilation System –Layout, Section & Details Equipment Schedules Other if any Panel Internal & External Layout Wiring Diagram Other if any Panel Internal & External Layout Wiring Diagram Other if any Panel Internal & External Layout Wiring Diagram Other if any HVAC System Design Calculations HVAC Duct & Equipment Layout– Ground Floor HVAC Sections HVAC Air Flow Diagrams HVAC Control Schematic Diagrams HVAC Control Panel Layouts HVAC Power Layouts (PACU, SPF, Ventilation Fan, EDH, MVD, MFSD, etc.) HVAC Equipment Schedule Other if any MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132KV NIC CIRCLE BSP ATTACHMENT TO APPENDIX XII-B: DOCUMENT REQUIREMENTS FOR ELECTRO-MECHANICAL SYSTEMS Material Submittal for HVAC Control Panel for SEC Transmission Room Building EHV ☐ ☒ ☒ HVAC Electrical Material Submittal EHV ☐ ☒ ☐ Technical submittal of Main Control Panel for Submersible Sump Pumps in 380kV GIS Building Tunnels & Trenches. EHV ☐ ☒ ☒ Technical submittal of Main Control Panel for Submersible Sump Pumps in 132kV GIS Building I Tunnels & Trenches. EHV ☐ ☒ ☒ Technical submittal of Main Control Panel for Submersible Sump Pumps in 132kV GIS Building II Tunnels & Trenches. EHV ☐ ☒ ☒ Technical submittal of Main Control Panel for Submersible Sump Pumps in Control Room Building Basement, Tunnels & Trenches-If any) EHV ☐ ☒ ☒ WP ☐ ☐ ☐ EHV or HV Bid Design Topics Stage Stage Markup As Built/ Stage WP ☐ ☐ ☐ HVAC Design Calculation and Drawings for Security Equipment Building EHV ☐ ☒ ☒ HVAC Control Panel for Security Equipment Building EHV ☐ ☒ ☒ HVAC System Design Calculation, Drawings and material submittal for Split Units EHV ☐ ☒ ☒ HVAC Construction Details Plumbing Constructions Details Pump House Ventilation System Design Calculation and Drawings EHV EHV EHV ☐ ☐ ☐ ☒ ☒ ☒ ☒ ☒ ☒ Plumbing System Design Calculation and Drawings for Security Equipment Building EHV ☐ ☒ ☒ WP ☐ ☐ ☐ Others (if any) Phase 06 Discipline Work Packages Mechanical Design Calculations & Drawings Others (if any) Submittals 6 of 7 1. 2. 3. 1. 2. 3. 4. 1. 2. 3. 1. 2. 3. 1. 2. 3. 1. 2. 3. 1. Panel Internal & External Layout Wiring Diagram Other if any Original Equipment catalogues / datasheets Auxiliary Equipment / Component catalogues / data sheets Compliance Statements (PTS, Standards) Other if any Panel Internal & External Layout Wiring Diagram Other if any Panel Internal & External Layout Wiring Diagram Other if any Panel Internal & External Layout Wiring Diagram Other if any Panel Internal & External Layout Wiring Diagram Other if any Submittal Contents / Document Titles / Remarks 1. HVAC System Design Calculations 2. HVAC Duct & Equipment Layout 3. HVAC Sections 4. HVAC Control Panel Layout 5. HVAC Power Layout (AHU, ACCU, Exhaust Fan, MFSD, etc. as applicable) 6. HVAC Equipment Schedule 7. Other if any 1. Panel Internal & External Layout 2. Wiring Diagram 3. Other if any 1. HVAC System Design Calculations 2. HVAC Power & Equipment Layout 3. HVAC Sections 4. HVAC Equipment Schedules 5. Other if any HVAC Construction Details Plumbing Construction Details 1. Ventilation System Design Calculations 2. Ventilation Equipment Layout, Sections, & Details 3. Other if any 1. Design Calculation 2. Roof Drainage System, Layout, Section & Details 3. Cold & Hot Water Supply System, Layout, Isometric & Details 4. Riser Diagrams 5. Sewerage, Drainage and vent system, Layout, Isometric & Details 6. Equipment Schedules 7. Other (if any) MECHANICAL SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR CONSTRUCTION OF 380/132KV NIC CIRCLE BSP ATTACHMENT TO APPENDIX XII-B: DOCUMENT REQUIREMENTS FOR ELECTRO-MECHANICAL SYSTEMS EHV or HV Bid Design Topics Stage Stage Markup As Built / Stage WP ☐ ☐ ☐ FAT for Air Conditioning Units (PACU / AHU-ACCU, etc) FAT for Control Panels FAT for Weight handling equipment HVAC Systems Method Statement EHV & HV EHV & HV EHV & HV EHV & HV WP ☐ ☐ ☐ ☐ ☐ ☒ ☒ ☒ ☒ ☐ ☐ ☐ ☐ ☐ ☐ Test Procedure documents Test Procedure documents Test Procedure documents Testing, Adjusting & balancing Method Statement FATR for Air Conditioning Unit (PACU / AHU-ACCU, etc) FATR for Control Panels FATR for Weight handling equipment HVAC Systems TAB Report EHV & HV EHV & HV EHV & HV EHV & HV ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☒ ☒ ☒ ☒ Test Reports Test Reports Test Reports Balancing Report WP ☐ ☐ ☐ EHV or HV Bid Design Topics Stage Stage Markup As Built / Stage WP ☐ ☐ ☐ EHV & HV ☐ ☐ ☐ Phase 07 Discipline Work Packages Mechanical ITP submission for Electro-mechanical Equipment Submittals FAT reports for Electro-Mechanical Equipment Others (if any) Phase 08 Discipline Work Packages Mechanical REMOTE END WORKS MECHANICAL Submittals Submittal Contents / Document Titles / Remarks Submittal Contents / Document Titles / Remarks ☒ - Indicates requirement for submission under this Project. The time schedule for the submittal of each phase shall be finalized prior/during initiating the submission of the design submittals. Partial submittal of calculations/drawings for any submittal in any phase will not be accepted. 7 of 7 OW NER. K NOTES JOB ORDER NO. INDEX SE0514 WT-925440 DRAWING NUMBER PLANT NO. 01 OF 08 SHEET NO. 00 REV. NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE OF I TS NECESSARY DURING PROJECT EXECUTION SHALL BE INCORPORATED WITH SEC APPROVAL CONSENT 2. PLUS SIGN INDICATES ADDITIONAL POINTS PER PROJECT REQUIREMENT / APPROVED CALCULATION SHALL BE INCORPORATED LEGEND RETURN DX COOLING COIL DPS DIFFERENTIAL PRESSURE SWITCH DSD DUCT SMOKE DETECTOR DTS DUCT TEMPERATURE SENSOR EF EXHAUST FAN EDH DPS ELECTRIC DUCT HEATER FACP FIRE ALARM CONTROL PANEL S.A DAMPER FD FIRE DAMPER HDP SUPPLY FAN HP FROM BAG FILTER CONROL CABLE TUNNEL HIGH DISCHARGE PRESSURE HIGH OIL PRESSURE SHALL BE OBTAI NED PREFILTER CCT HVAC HEATING, VENTILATING & AIR CONDITIONING FRESH AIR MB M M FROM FACP MOORIZED DAMPER MB MIXING BOX MF/SD MOTORIZED FIRE/SMOKE DAMPER M DPS EDH DPS R.A. DAMPER SUPPLY M PREFILTER BAG FILTER CONDENSER FRESH AIR FILTER (STL) DX COOLING COIL AIR SECTION ( FANS) STANDBY / DUTY DSD DTS S.A DAMPER ZONE # 1 MF/SD SUPPLY FAN RA RETURN AIR RHS ROOM HUMIDITY SENSOR RTS ROOM TEMPERATURE SENSOR SAS SUBSTATION AUTOMATION SYSTEM SF SUPPLY FAN SPF SMOKE PURGE FAN STL SAND TRAP LOUVER STATUS I N RHS M M TIHI M FIRE SM OKE DAM PERS STATUS REFERENCE DRAWINGS DRAWING TITLE DRAWING NO. DRAWING CONTROL SHEET WT-925429 SUBSTATION LAYOUT WT-925438 SAUDIELECTRI CI TY FIRE SM OKE DAM PERS COM M AND ( OPEN / CLOSE) SPF ISOLATION DAM PER STATUS SPF ISOLATION DAM PER COM M AND STATUS SPF COM M AND HUM IDITY ROOM SPF ON-OFF/TRIP TEM PERATURE SPF ROOM FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND EDH ON-OFF/TRIP/STAGES STATUS HEATER COM M AND RETURN AIR TEM PERATURE ( DUCT) SUPPLY AIR TEM PERATURE ( DUCT) ( OPEN / CLOSE) SUPPLY AIR DAM PER COM M AND SUPPLY AIR DAM PER STATUS M SUPPLY FAN ON-OFF/TRIP/FLOW SUPPLY FAN COM M AND CONDENSER FAN ON-OFF/TRIP STATUS HDP/LSP STATUS COM PRESSOR-1&2 COM M AND BAG FILTERS DIRTY STATUS PRE-FILTERS DIRTY STATUS ( OPEN / CLOSE) RETURN AIR DAM PER STATUS RETURN AIR DAM PER COM M AND FIRE SM OKE DAM PERS STATUS DPS COM PRESSOR-1&2 ON-OFF/TRIP/LP/HP/ RTS DPS FIRE SM OKE DAM PERS COM M AND FRESH AIR FILTERS DIRTY STATUS MB DPS POWER CABLE TUNNEL ECC ENERGY CONTROL CENTER MF/SD M PCT TIHI TEMPERATURE & HUMIDITY INDICATOR TIHI FRESH AIR LOW OIL PRESSURE SCADA SUPERVISORY CONTROL & DATA ACQUISTION 380kV GIS HALL (33.3%) DPS LP I N DPS LOW SUCTION PRESSURE FULL OR DUTY / STANDBY LSP PART MVD MOTORIZED VOLUME DAMPER DDC MODULES DIGITAL INPUT (DI) 2+ 1 2 2 2 2 2 3 24+ 16+ 4+ 6 2 4+ 1 1 1 1 2 2 4+ 1 1 1 1 ANALOG INPUT (AI) ARE THE SOLE PROPERTY OF DIGITAL OUTPUT (DO) 2 REPRODUCTI ON FRESH AIR FILTER (STL) 16 POINT NO M 16P CO. CONDENSER R.A. DAMPER SECTION ( FANS) DTS TO FACP THI S AIR DSD DOCUMENT WI THOUT THE W RI TTEN HVAC CONTROL SCHEMATIC DIAGRAM - 380kV GIS BUILDING 2 2 AS-BUILT BY DATE } DO AI MIR DRAWN BY 80 32 16 16 DATE STARTED CHECKED BY 04-01-2021 ENG. DEPT. MODULES (MIN.) THIS DRAWING IS NOT TO BE USED FOR 5 2 1 1 NAO CERT. APPD. NTS SCALE: 16-02-2021 DATE COMPLETED OPR'G. DEPT. NO. OF 16P DDC CHKD. DESCRIPTION AO NO. OF DDC POINTS (MIN.) BY THE I NFORMATI ON DI DATE EHV-E&DD/ESD APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED DDC NO. REV. NO. DRAW I NG DDC EQUIPMENT REV. NO. HVAC CONTROL SCHEMATIC DIAGRAM 380KV GIS BUILDING 380/132KV NIC CIRCLE BSP NWOA JOB ORDER NO. SAUDI ARABIA INDEX PLANT NO. DRAWING NUMBER SHEET NO. K SE0514 WT-925440 01 OF 08 REV. NO. 00 SEC-A (2004/10) DMS VECTOR AND DDC EQUIPMENT SCHEDULE CONTAI NED HEREI N FOR MORE DETAILS REFER TO ATTACHED HVAC ALARMS LOGIC DIAGRAM SECA00 THI S TO SAS FROM FACP ANALOG OUTPUT (AO) OW NER. K NOTES JOB ORDER NO. INDEX SE0514 WT-925440 DRAWING NUMBER PLANT NO. 02 OF 08 SHEET NO. 00 REV. NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE OF I TS NECESSARY DURING PROJECT EXECUTION SHALL BE INCORPORATED WITH SEC APPROVAL CONSENT 2. PLUS SIGN INDICATES ADDITIONAL POINTS PER PROJECT REQUIREMENT / APPROVED CALCULATION SHALL BE INCORPORATED LEGEND RETURN DX COOLING COIL DPS DIFFERENTIAL PRESSURE SWITCH DSD DUCT SMOKE DETECTOR DTS DUCT TEMPERATURE SENSOR EF EXHAUST FAN EDH DPS ELECTRIC DUCT HEATER FACP FIRE ALARM CONTROL PANEL S.A DAMPER FD FIRE DAMPER HDP SUPPLY FAN HP FROM BAG FILTER CONROL CABLE TUNNEL HIGH DISCHARGE PRESSURE HIGH OIL PRESSURE SHALL BE OBTAI NED PREFILTER CCT HVAC HEATING, VENTILATING & AIR CONDITIONING FRESH AIR MB M M FROM FACP MOORIZED DAMPER MB MIXING BOX MF/SD MOTORIZED FIRE/SMOKE DAMPER M DPS EDH DPS R.A. DAMPER SUPPLY M PREFILTER BAG FILTER CONDENSER FRESH AIR FILTER (STL) DX COOLING COIL AIR SECTION ( FANS) STANDBY / DUTY DSD DTS S.A DAMPER ZONE # 2 MF/SD SUPPLY FAN RA RETURN AIR RHS ROOM HUMIDITY SENSOR RTS ROOM TEMPERATURE SENSOR SAS SUBSTATION AUTOMATION SYSTEM SF SUPPLY FAN SPF SMOKE PURGE FAN STL SAND TRAP LOUVER STATUS I N RHS M M M FIRE SM OKE DAM PERS STATUS REFERENCE DRAWINGS DRAWING TITLE DRAWING NO. DRAWING CONTROL SHEET WT-925429 SUBSTATION LAYOUT WT-925438 SAUDIELECTRI CI TY FIRE SM OKE DAM PERS COM M AND ( OPEN / CLOSE) SPF ISOLATION DAM PER STATUS SPF ISOLATION DAM PER COM M AND STATUS SPF COM M AND HUM IDITY ROOM SPF ON-OFF/TRIP TEM PERATURE SPF ROOM FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND EDH ON-OFF/TRIP/STAGES STATUS HEATER COM M AND RETURN AIR TEM PERATURE ( DUCT) SUPPLY AIR TEM PERATURE ( DUCT) ( OPEN / CLOSE) SUPPLY AIR DAM PER COM M AND SUPPLY AIR DAM PER STATUS M SUPPLY FAN ON-OFF/TRIP/FLOW SUPPLY FAN COM M AND CONDENSER FAN ON-OFF/TRIP STATUS HDP/LSP STATUS COM PRESSOR-1&2 COM M AND BAG FILTERS DIRTY STATUS PRE-FILTERS DIRTY STATUS ( OPEN / CLOSE) RETURN AIR DAM PER STATUS RETURN AIR DAM PER COM M AND FIRE SM OKE DAM PERS STATUS DPS COM PRESSOR-1&2 ON-OFF/TRIP/LP/HP/ RTS DPS FIRE SM OKE DAM PERS COM M AND FRESH AIR FILTERS DIRTY STATUS MB DPS POWER CABLE TUNNEL ECC ENERGY CONTROL CENTER MF/SD M PCT TIHI TEMPERATURE & HUMIDITY INDICATOR TIHI FRESH AIR LOW OIL PRESSURE SCADA SUPERVISORY CONTROL & DATA ACQUISTION 380kV GIS HALL (33.4%) DPS LP I N DPS LOW SUCTION PRESSURE FULL OR DUTY / STANDBY LSP PART MVD MOTORIZED VOLUME DAMPER DDC MODULES DIGITAL INPUT (DI) 2+ 1 2 2 2 2 2 3 24+ 16+ 4+ 6 2 4+ 1 1 1 1 2 2 4+ 1 1 1 1 ANALOG INPUT (AI) ARE THE SOLE PROPERTY OF DIGITAL OUTPUT (DO) 2 REPRODUCTI ON FRESH AIR FILTER (STL) 16 POINT NO M 16P CO. CONDENSER R.A. DAMPER SECTION ( FANS) DTS TO FACP THI S AIR DSD DOCUMENT WI THOUT THE W RI TTEN HVAC CONTROL SCHEMATIC DIAGRAM - 380kV GIS BUILDING 2 2 AS-BUILT BY DATE } DO AI MIR DRAWN BY 80 32 16 16 DATE STARTED CHECKED BY 04-01-2021 ENG. DEPT. MODULES (MIN.) THIS DRAWING IS NOT TO BE USED FOR 5 2 1 1 NAO CERT. APPD. NTS SCALE: 16-02-2021 DATE COMPLETED OPR'G. DEPT. NO. OF 16P DDC CHKD. DESCRIPTION AO NO. OF DDC POINTS (MIN.) BY THE I NFORMATI ON DI DATE EHV-E&DD/ESD APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED DDC NO. REV. NO. DRAW I NG DDC EQUIPMENT REV. NO. HVAC CONTROL SCHEMATIC DIAGRAM 380KV GIS BUILDING 380/132KV NIC CIRCLE BSP NWOA JOB ORDER NO. SAUDI ARABIA INDEX PLANT NO. DRAWING NUMBER SHEET NO. REV. NO. K SE0514 WT-925440 02 OF 08 00 SEC-A (2004/10) DMS VECTOR AND DDC EQUIPMENT SCHEDULE CONTAI NED HEREI N FOR MORE DETAILS REFER TO ATTACHED HVAC ALARMS LOGIC DIAGRAM SECA00 THI S TO SAS FROM FACP ANALOG OUTPUT (AO) OW NER. K NOTES JOB ORDER NO. INDEX SE0514 WT-925440 DRAWING NUMBER PLANT NO. 03 OF 08 SHEET NO. 00 REV. NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE OF I TS NECESSARY DURING PROJECT EXECUTION SHALL BE INCORPORATED WITH SEC APPROVAL CONSENT 2. PLUS SIGN INDICATES ADDITIONAL POINTS PER PROJECT REQUIREMENT / APPROVED CALCULATION SHALL BE INCORPORATED LEGEND RETURN DX COOLING COIL DPS DIFFERENTIAL PRESSURE SWITCH DSD DUCT SMOKE DETECTOR DTS DUCT TEMPERATURE SENSOR EF EXHAUST FAN EDH DPS ELECTRIC DUCT HEATER FACP FIRE ALARM CONTROL PANEL S.A DAMPER FD FIRE DAMPER HDP SUPPLY FAN HP FROM BAG FILTER CONROL CABLE TUNNEL HIGH DISCHARGE PRESSURE HIGH OIL PRESSURE SHALL BE OBTAI NED PREFILTER CCT HVAC HEATING, VENTILATING & AIR CONDITIONING FRESH AIR MB M M FROM FACP MOORIZED DAMPER MB MIXING BOX MF/SD MOTORIZED FIRE/SMOKE DAMPER M DPS EDH DPS R.A. DAMPER SUPPLY M PREFILTER BAG FILTER CONDENSER FRESH AIR FILTER (STL) DX COOLING COIL AIR SECTION ( FANS) STANDBY / DUTY DSD DTS S.A DAMPER ZONE # 3 MF/SD SUPPLY FAN RA RETURN AIR RHS ROOM HUMIDITY SENSOR RTS ROOM TEMPERATURE SENSOR SAS SUBSTATION AUTOMATION SYSTEM SF SUPPLY FAN SPF SMOKE PURGE FAN STL SAND TRAP LOUVER STATUS I N RHS M TIHI M M FIRE SM OKE DAM PERS STATUS REFERENCE DRAWINGS DRAWING TITLE DRAWING NO. DRAWING CONTROL SHEET WT-925429 SUBSTATION LAYOUT WT-925438 SAUDIELECTRI CI TY FIRE SM OKE DAM PERS COM M AND ( OPEN / CLOSE) SPF ISOLATION DAM PER STATUS SPF ISOLATION DAM PER COM M AND STATUS SPF COM M AND HUM IDITY ROOM SPF ON-OFF/TRIP TEM PERATURE SPF ROOM FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND EDH ON-OFF/TRIP/STAGES STATUS HEATER COM M AND RETURN AIR TEM PERATURE ( DUCT) SUPPLY AIR TEM PERATURE ( DUCT) ( OPEN / CLOSE) SUPPLY AIR DAM PER COM M AND SUPPLY AIR DAM PER STATUS M SUPPLY FAN ON-OFF/TRIP/FLOW SUPPLY FAN COM M AND CONDENSER FAN ON-OFF/TRIP STATUS HDP/LSP STATUS COM PRESSOR-1&2 COM M AND BAG FILTERS DIRTY STATUS PRE-FILTERS DIRTY STATUS ( OPEN / CLOSE) RETURN AIR DAM PER STATUS RETURN AIR DAM PER COM M AND FIRE SM OKE DAM PERS STATUS DPS COM PRESSOR-1&2 ON-OFF/TRIP/LP/HP/ RTS DPS FIRE SM OKE DAM PERS COM M AND FRESH AIR FILTERS DIRTY STATUS MB DPS POWER CABLE TUNNEL ECC ENERGY CONTROL CENTER MF/SD M PCT TIHI TEMPERATURE & HUMIDITY INDICATOR TIHI FRESH AIR LOW OIL PRESSURE SCADA SUPERVISORY CONTROL & DATA ACQUISTION 380kV GIS HALL (33.3%) DPS LP I N DPS LOW SUCTION PRESSURE FULL OR DUTY / STANDBY LSP PART MVD MOTORIZED VOLUME DAMPER DDC MODULES DIGITAL INPUT (DI) 2+ 1 2 2 2 2 2 3 24+ 16+ 4+ 6 2 4+ 1 1 1 1 2 2 4+ 1 1 1 1 ANALOG INPUT (AI) ARE THE SOLE PROPERTY OF DIGITAL OUTPUT (DO) 2 REPRODUCTI ON FRESH AIR FILTER (STL) 16 POINT NO M 16P CO. CONDENSER R.A. DAMPER SECTION ( FANS) DTS TO FACP THI S AIR DSD DOCUMENT WI THOUT THE W RI TTEN HVAC CONTROL SCHEMATIC DIAGRAM - 380kV GIS BUILDING 2 2 AS-BUILT BY DATE } DO AI MIR DRAWN BY 80 32 16 16 DATE STARTED CHECKED BY 04-01-2021 ENG. DEPT. MODULES (MIN.) THIS DRAWING IS NOT TO BE USED FOR 5 2 1 1 NAO CERT. APPD. NTS SCALE: 16-02-2021 DATE COMPLETED OPR'G. DEPT. NO. OF 16P DDC CHKD. DESCRIPTION AO NO. OF DDC POINTS (MIN.) BY THE I NFORMATI ON DI DATE EHV-E&DD/ESD APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED DDC NO. REV. NO. DRAW I NG DDC EQUIPMENT REV. NO. HVAC CONTROL SCHEMATIC DIAGRAM 380KV GIS BUILDING 380/132KV NIC CIRCLE BSP NWOA JOB ORDER NO. SAUDI ARABIA INDEX PLANT NO. DRAWING NUMBER SHEET NO. REV. NO. K SE0514 WT-925440 03 OF 08 00 SEC-A (2004/10) DMS VECTOR AND DDC EQUIPMENT SCHEDULE CONTAI NED HEREI N FOR MORE DETAILS REFER TO ATTACHED HVAC ALARMS LOGIC DIAGRAM SECA00 THI S TO SAS FROM FACP ANALOG OUTPUT (AO) OW NER. K NOTES JOB ORDER NO. INDEX SE0514 WT-925440 DRAWING NUMBER PLANT NO. 04 OF 08 SHEET NO. 00 REV. NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE OF I TS NECESSARY DURING PROJECT EXECUTION SHALL BE INCORPORATED WITH SEC APPROVAL CONSENT 2. PLUS SIGN INDICATES ADDITIONAL POINTS PER PROJECT REQUIREMENT / APPROVED CALCULATION SHALL BE INCORPORATED LEGEND RETURN DX COOLING COIL DPS DIFFERENTIAL PRESSURE SWITCH DSD DUCT SMOKE DETECTOR DTS DUCT TEMPERATURE SENSOR EF EXHAUST FAN EDH DPS ELECTRIC DUCT HEATER FACP FIRE ALARM CONTROL PANEL S.A DAMPER FD FIRE DAMPER HDP SUPPLY FAN HP FROM BAG FILTER CONROL CABLE TUNNEL HIGH DISCHARGE PRESSURE HIGH OIL PRESSURE SHALL BE OBTAI NED PREFILTER CCT HVAC HEATING, VENTILATING & AIR CONDITIONING FRESH AIR MB M M FROM FACP MOORIZED DAMPER MB MIXING BOX MF/SD MOTORIZED FIRE/SMOKE DAMPER M DPS EDH DPS R.A. DAMPER POWER CABLE TUNNEL RA RETURN AIR RHS ROOM HUMIDITY SENSOR (100 % FOR CAPACITY RTS ROOM TEMPERATURE SENSOR BELOW 60 TONS AND SAS SUBSTATION AUTOMATION SYSTEM SUPPLY PREFILTER BAG FILTER CONDENSER FRESH AIR FILTER (STL) DX COOLING COIL AIR SECTION ( FANS) STANDBY / DUTY DSD DTS SCADA SUPERVISORY CONTROL & DATA ACQUISTION 50% FOR CAPACITY RANGE 60-120 TONS) DPS S.A DAMPER MF/SD SUPPLY FAN SPF SMOKE PURGE FAN STL SAND TRAP LOUVER STATUS I N RHS M M TIHI M FIRE SM OKE DAM PERS STATUS REFERENCE DRAWINGS DRAWING TITLE DRAWING NO. DRAWING CONTROL SHEET WT-925429 SUBSTATION LAYOUT WT-925438 SAUDIELECTRI CI TY FIRE SM OKE DAM PERS COM M AND ( OPEN / CLOSE) SPF ISOLATION DAM PER STATUS SPF ISOLATION DAM PER COM M AND STATUS SPF COM M AND HUM IDITY ROOM SPF ON-OFF/TRIP TEM PERATURE SPF ROOM FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND EDH ON-OFF/TRIP/STAGES STATUS HEATER COM M AND RETURN AIR TEM PERATURE ( DUCT) SUPPLY AIR TEM PERATURE ( DUCT) ( OPEN / CLOSE) SUPPLY AIR DAM PER COM M AND SUPPLY AIR DAM PER STATUS M SUPPLY FAN ON-OFF/TRIP/FLOW SUPPLY FAN COM M AND CONDENSER FAN ON-OFF/TRIP STATUS HDP/LSP STATUS COM PRESSOR-1&2 COM M AND BAG FILTERS DIRTY STATUS PRE-FILTERS DIRTY STATUS ( OPEN / CLOSE) RETURN AIR DAM PER STATUS RETURN AIR DAM PER COM M AND FIRE SM OKE DAM PERS STATUS DPS COM PRESSOR-1&2 ON-OFF/TRIP/LP/HP/ RTS DPS FIRE SM OKE DAM PERS COM M AND FRESH AIR FILTERS DIRTY STATUS MB DPS SUPPLY FAN ECC ENERGY CONTROL CENTER MF/SD M SF TIHI TEMPERATURE & HUMIDITY INDICATOR TIHI FRESH AIR LOW OIL PRESSURE PCT 132kV GIS HALL-I M LP I N DPS LOW SUCTION PRESSURE FULL OR DUTY / STANDBY LSP PART MVD MOTORIZED VOLUME DAMPER DDC MODULES DIGITAL INPUT (DI) 2+ 1 2 2 2 2 2 3 24+ 20+ 4+ 6 2 4+ 2 1 1 2 2 2 4+ 2 1 1 2 ANALOG INPUT (AI) ARE THE SOLE PROPERTY OF DIGITAL OUTPUT (DO) 2 REPRODUCTI ON FRESH AIR FILTER (STL) 16 POINT NO M 16P CO. CONDENSER R.A. DAMPER SECTION ( FANS) DTS TO FACP THI S AIR DSD DOCUMENT WI THOUT THE W RI TTEN HVAC CONTROL SCHEMATIC DIAGRAM - 132kV GIS BUILDING - I 2 2 AS-BUILT BY DATE } DO AI MIR DRAWN BY 96 32 16 16 DATE STARTED CHECKED BY 04-01-2021 ENG. DEPT. MODULES (MIN.) THIS DRAWING IS NOT TO BE USED FOR 6 2 1 1 NAO CERT. APPD. NTS SCALE: DATE COMPLETED OPR'G. DEPT. NO. OF 16P DDC CHKD. DESCRIPTION AO NO. OF DDC POINTS (MIN.) BY THE I NFORMATI ON DI DATE 16-02-2021 EHV-E&DD/ESD APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED DDC NO. REV. NO. DRAW I NG DDC EQUIPMENT REV. NO. HVAC CONTROL SCHEMATIC DIAGRAM 132KV GIS BUILDING-I 380/132KV NIC CIRCLE BSP NWOA JOB ORDER NO. SAUDI ARABIA INDEX PLANT NO. DRAWING NUMBER SHEET NO. K SE0514 WT-925440 04 OF 08 REV. NO. 00 SEC-A (2004/10) DMS VECTOR AND DDC EQUIPMENT SCHEDULE CONTAI NED HEREI N FOR MORE DETAILS REFER TO ATTACHED HVAC ALARMS LOGIC DIAGRAM SECA00 THI S TO SAS FROM FACP ANALOG OUTPUT (AO) OW NER. K NOTES JOB ORDER NO. INDEX SE0514 WT-925440 DRAWING NUMBER PLANT NO. 05 OF 08 SHEET NO. 00 REV. NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE OF I TS NECESSARY DURING PROJECT EXECUTION SHALL BE INCORPORATED WITH SEC APPROVAL CONSENT 2. PLUS SIGN INDICATES ADDITIONAL POINTS PER PROJECT REQUIREMENT / APPROVED CALCULATION SHALL BE INCORPORATED LEGEND RETURN DX COOLING COIL DPS DIFFERENTIAL PRESSURE SWITCH DSD DUCT SMOKE DETECTOR DTS DUCT TEMPERATURE SENSOR EF EXHAUST FAN EDH DPS ELECTRIC DUCT HEATER FACP FIRE ALARM CONTROL PANEL S.A DAMPER FD FIRE DAMPER HDP SUPPLY FAN HP FROM BAG FILTER CONROL CABLE TUNNEL HIGH DISCHARGE PRESSURE HIGH OIL PRESSURE SHALL BE OBTAI NED PREFILTER CCT HVAC HEATING, VENTILATING & AIR CONDITIONING FRESH AIR MB M M FROM FACP MOORIZED DAMPER MB MIXING BOX MF/SD MOTORIZED FIRE/SMOKE DAMPER M DPS EDH DPS R.A. DAMPER POWER CABLE TUNNEL RA RETURN AIR RHS ROOM HUMIDITY SENSOR (100 % FOR CAPACITY RTS ROOM TEMPERATURE SENSOR BELOW 60 TONS AND SAS SUBSTATION AUTOMATION SYSTEM SUPPLY PREFILTER BAG FILTER CONDENSER FRESH AIR FILTER (STL) DX COOLING COIL AIR SECTION ( FANS) STANDBY / DUTY DSD DTS SCADA SUPERVISORY CONTROL & DATA ACQUISTION 50% FOR CAPACITY RANGE 60-120 TONS) DPS S.A DAMPER MF/SD SUPPLY FAN SPF SMOKE PURGE FAN STL SAND TRAP LOUVER STATUS I N RHS M M TIHI M FIRE SM OKE DAM PERS STATUS REFERENCE DRAWINGS DRAWING TITLE DRAWING NO. DRAWING CONTROL SHEET WT-925429 SUBSTATION LAYOUT WT-925438 SAUDIELECTRI CI TY FIRE SM OKE DAM PERS COM M AND ( OPEN / CLOSE) SPF ISOLATION DAM PER STATUS SPF ISOLATION DAM PER COM M AND STATUS SPF COM M AND HUM IDITY ROOM SPF ON-OFF/TRIP TEM PERATURE SPF ROOM FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND EDH ON-OFF/TRIP/STAGES STATUS HEATER COM M AND RETURN AIR TEM PERATURE ( DUCT) SUPPLY AIR TEM PERATURE ( DUCT) ( OPEN / CLOSE) SUPPLY AIR DAM PER COM M AND SUPPLY AIR DAM PER STATUS M SUPPLY FAN ON-OFF/TRIP/FLOW SUPPLY FAN COM M AND CONDENSER FAN ON-OFF/TRIP STATUS HDP/LSP STATUS COM PRESSOR-1&2 COM M AND BAG FILTERS DIRTY STATUS PRE-FILTERS DIRTY STATUS ( OPEN / CLOSE) RETURN AIR DAM PER STATUS RETURN AIR DAM PER COM M AND FIRE SM OKE DAM PERS STATUS DPS COM PRESSOR-1&2 ON-OFF/TRIP/LP/HP/ RTS DPS FIRE SM OKE DAM PERS COM M AND FRESH AIR FILTERS DIRTY STATUS MB DPS SUPPLY FAN ECC ENERGY CONTROL CENTER MF/SD M SF TIHI TEMPERATURE & HUMIDITY INDICATOR TIHI FRESH AIR LOW OIL PRESSURE PCT 132kV GIS HALL-II M LP I N DPS LOW SUCTION PRESSURE FULL OR DUTY / STANDBY LSP PART MVD MOTORIZED VOLUME DAMPER DDC MODULES DIGITAL INPUT (DI) 2+ 1 2 2 2 2 2 3 24+ 20+ 4+ 6 2 4+ 2 1 1 2 2 2 4+ 2 1 1 2 ANALOG INPUT (AI) ARE THE SOLE PROPERTY OF DIGITAL OUTPUT (DO) 2 REPRODUCTI ON FRESH AIR FILTER (STL) 16 POINT NO M 16P CO. CONDENSER R.A. DAMPER SECTION ( FANS) DTS TO FACP THI S AIR DSD DOCUMENT WI THOUT THE W RI TTEN HVAC CONTROL SCHEMATIC DIAGRAM - 132kV GIS BUILDING - II 2 2 AS-BUILT BY DATE } DO AI MIR DRAWN BY 96 32 16 16 DATE STARTED CHECKED BY 04-01-2021 ENG. DEPT. MODULES (MIN.) THIS DRAWING IS NOT TO BE USED FOR 6 2 1 1 NAO CERT. APPD. NTS SCALE: DATE COMPLETED OPR'G. DEPT. NO. OF 16P DDC CHKD. DESCRIPTION AO NO. OF DDC POINTS (MIN.) BY THE I NFORMATI ON DI DATE 16-02-2021 EHV-E&DD/ESD APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED DDC NO. REV. NO. DRAW I NG DDC EQUIPMENT REV. NO. HVAC CONTROL SCHEMATIC DIAGRAM 132KV GIS BUILDING-II 380/132KV NIC CIRCLE BSP NWOA JOB ORDER NO. SAUDI ARABIA INDEX PLANT NO. DRAWING NUMBER SHEET NO. K SE0514 WT-925440 05 OF 08 REV. NO. 00 SEC-A (2004/10) DMS VECTOR AND DDC EQUIPMENT SCHEDULE CONTAI NED HEREI N FOR MORE DETAILS REFER TO ATTACHED HVAC ALARMS LOGIC DIAGRAM SECA00 THI S TO SAS FROM FACP ANALOG OUTPUT (AO) OW NER. JOB ORDER NO. WT-925440 SE0514 K NOTES INDEX DRAWING NUMBER PLANT NO. 06 OF 08 SHEET NO. 00 REV. NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE OF I TS NECESSARY DURING PROJECT EXECUTION SHALL BE INCORPORATED WITH SEC APPROVAL CONSENT 2. PLUS SIGN INDICATES ADDITIONAL POINTS PER PROJECT REQUIREMENT / APPROVED CALCULATION SHALL BE INCORPORATED 3. BEST LOCATION OF DUCT SMOKE DETECTOR SHALL BE HVAC CONTROL SCHEMATIC DIAGRAM - CONTROL ROOM THE W RI TTEN DECIDED IN DESIGN STAGE IN ACCORDANCE WITH DOCUMENT WI THOUT NFPA 90A, IMC & MANUFACTURER GUIDELINES RETURN AIR DX COOLING COIL DPS S.A DAMPER SUPPLY FAN 16 POINT CCT CONROL CABLE TUNNEL DPS DIFFERENTIAL PRESSURE SWITCH DSD DUCT SMOKE DETECTOR DTS FRESH AIR M THI S 16P MB EF DUCT TEMPERATURE SENSOR EXHAUST FAN EDH FROM FACP FROM BAG FILTER PREFILTER SHALL BE OBTAI NED FRESH AIR FILTER (STL) ELECTRIC DUCT HEATER FACP FIRE ALARM CONTROL PANEL FD HDP M EDH M AIR LOCK ROOMS M HVAC HEATING, VENTILATING & AIR CONDITIONING M TIHI R.A. DAMPER MB BAG FILTER PREFILTER CONDENSER FRESH AIR FILTER (STL) DX COOLING COIL AIR SECTION ( FANS) STANDBY / DUTY MVD MOTORIZED VOLUME DAMPER FPE ROOM-1 M 1 EF DSD DTS TIHI DPS S.A DAMPER CONTROL ROOM SUPPLY FAN M M MB STATUS TIHI LP LOW OIL PRESSURE PCT POWER CABLE TUNNEL RA RETURN AIR RHS ROOM HUMIDITY SENSOR RTS ROOM TEMPERATURE SENSOR SAS SUBSTATION AUTOMATION SYSTEM SF SUPPLY FAN SPF SMOKE PURGE FAN STL SAND TRAP LOUVER TIHI EXHAUST FAN ON-OFF/TRIP STATUS TEMPERATURE & HUMIDITY INDICATOR ECC ENERGY CONTROL CENTER CCC CONTROL CABLE CHUTE REFERENCE DRAWINGS DRAWING TITLE DRAWING NO. DRAWING CONTROL SHEET WT-925429 SUBSTATION LAYOUT WT-925438 SAUDIELECTRI CI TY EXHAUST FAN COM M AND FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND STATUS SPF ON-OFF/TRIP SPF COM M AND SPF ( OPEN / CLOSE) SPF ISOLATION DAM PER STATUS SPF ISOLATION DAM PER COM M AND TEM PERATURE HUM IDITY ROOM ROOM FIRE SM OKE DAM PERS STATUS M FIRE SM OKE DAM PERS COM M AND EDH ON-OFF/TRIP/ STAGES STATUS HEATER COM M AND RETURN AIR TEM PERATURE ( DUCT) SUPPLY AIR TEM PERATURE ( DUCT) ( OPEN / CLOSE) SUPPLY AIR DAM PER COM M AND SUPPLY AIR DAM PER STATUS M SUPPLY FAN ON-OFF/TRIP/FLOW SUPPLY FAN COM M AND CONDENSER FAN ON-OFF/TRIP STATUS HDP/LSP STATUS COM PRESSOR-1&2 ON-OFF/TRIP/LP/HP/ COM PRESSOR-1&2 COM M AND PRE-FILTERS DIRTY STATUS ( OPEN / CLOSE) RETURN AIR DAM PER STATUS RETURN AIR DAM PER COM M AND FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND BAG FILTERS DIRTY STATUS FRESH AIR FILTERS DIRTY STATUS DPS LOW SUCTION PRESSURE SCADA SUPERVISORY CONTROL & DATA ACQUISTION RHS TIHI DPS LSP M RTS DPS MIXING BOX MF/SD MOTORIZED FIRE/SMOKE DAMPER SUPPLY M FRESH AIR MOTORIZED DAMPER PART DPS I N DPS HIGH OIL PRESSURE FULL OR DPS HIGH DISCHARGE PRESSURE HP I N DUTY / STANDBY FIRE DAMPER DDC MODULES DIGITAL INPUT (DI) 2+ 1 2 2 2 2 2 3 24+ 16+ 4+ 6 2 4+ 2+ 1 2 2+ 2+ 2 2 4+ 2+ 1 2 2+ 1 2 ANALOG INPUT (AI) ARE THE SOLE PROPERTY OF DIGITAL OUTPUT (DO) 2 REPRODUCTI ON M LEGEND NO CONDENSER R.A. DAMPER SECTION ( FANS) DTS TO FACP CO. DSD 2 AS-BUILT BY DATE } DO AI AO 16 16 BY NO. OF DDC POINTS (MIN.) 96 48 MIR DRAWN BY DATE STARTED CHECKED BY 04-01-2021 MODULES (MIN.) 6 3 1 1 NAO ENG. DEPT. THIS DRAWING IS NOT TO BE USED FOR CERT. APPD. NTS SCALE: 16-02-2021 DATE COMPLETED OPR'G. DEPT. NO. Of 16P DDC CHKD. DESCRIPTION THE I NFORMATI ON DI DATE EHV-E&DD/ESD APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED DDC NO. REV. NO. DRAW I NG DDC EQUIPMENT REV. NO. HVAC CONTROL SCHEMATIC DIAGRAM CONTROL ROOM 380/132KV NIC CIRCLE BSP NWOA JOB ORDER NO. SAUDI ARABIA INDEX PLANT NO. DRAWING NUMBER SHEET NO. K SE0514 WT-925440 06 OF 08 REV. NO. 00 SEC-A (2004/10) DMS VECTOR AND DDC EQUIPMENT SCHEDULE CONTAI NED HEREI N FOR MORE DETAILS REFER TO ATTACHED HVAC ALARMS LOGIC DIAGRAM SECA00 THI S TO SAS FROM FACP ANALOG OUTPUT (AO) OW NER. K NOTES JOB ORDER NO. WT-925440 SE0514 INDEX DRAWING NUMBER PLANT NO. 07 OF 08 SHEET NO. 00 REV. NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE OF I TS NECESSARY DURING PROJECT EXECUTION SHALL BE INCORPORATED WITH SEC APPROVAL CONSENT 2. PLUS SIGN INDICATES ADDITIONAL POINTS PER PROJECT REQUIREMENT / APPROVED CALCULATION SHALL BE INCORPORATED 3. BEST LOCATION OF DUCT SMOKE DETECTOR SHALL BE HVAC CONTROL SCHEMATIC DIAGRAM - CONTROL BUILDING THE W RI TTEN DECIDED IN DESIGN STAGE IN ACCORDANCE WITH AIR DX COOLING COIL DUCT SMOKE DETECTOR DTS DUCT TEMPERATURE SENSOR EXHAUST FAN EDH DPS M S.A DAMPER M TIHI MV SWGR ROOM FD M FPE ROOM-2 (IF ANY) FROM FACP FIRE DAMPER HDP TOILET MB ELECTRIC DUCT HEATER FACP FIRE ALARM CONTROL PANEL HP 1 EF M DIFFERENTIAL PRESSURE SWITCH DSD EF SUPPLY FAN FRESH AIR DPS FROM BAG FILTER CONROL CABLE TUNNEL HIGH DISCHARGE PRESSURE HIGH OIL PRESSURE SHALL BE OBTAI NED PREFILTER CCT HVAC HEATING, VENTILATING & AIR CONDITIONING TIHI 1 EF M MOTORIZED DAMPER MB RELAY TEST ROOM (REFER SOW) MIXING BOX MF/SD MOTORIZED FIRE/SMOKE DAMPER M M M 2 EF EDH DPS TIHI OTHER (IF ANY) M SUPPLY M CONDENSER DX COOLING COIL POWER CABLE TUNNEL M RA RETURN AIR RHS ROOM HUMIDITY SENSOR RTS ROOM TEMPERATURE SENSOR SAS SUBSTATION AUTOMATION SYSTEM OFFICE ROOM (REFER SOW) M DSD DTS TIHI DPS M S.A DAMPER SCADA SUPERVISORY CONTROL & DATA ACQUISTION M AUXILIARY ROOM COMM. ROOM (RAISED FLOOR) M M SUPPLY FAN SPF SMOKE PURGE FAN STL SAND TRAP LOUVER ECC M TEMPERATURE & HUMIDITY INDICATOR ENERGY CONTROL CENTER STATUS I N RHS TIHI FIRE SM OKE DAM PERS STATUS REFERENCE DRAWINGS DRAWING TITLE DRAWING NO. DRAWING CONTROL SHEET WT-925429 SUBSTATION LAYOUT WT-925438 SAUDIELECTRI CI TY FIRE SM OKE DAM PERS COM M AND EXHAUST FAN COM M AND STATUS SPF COM M AND SPF ON-OFF/TRIP SPF ( OPEN / CLOSE) SPF ISOLATION DAM PER STATUS SPF ISOLATION DAM PER COM M AND TEM PERATURE HUM IDITY ROOM ROOM FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND EDH ON-OFF/TRIP/STAGES STATUS HEATER COM M AND RETURN AIR TEM PERATURE ( DUCT) SUPPLY AIR TEM PERATURE ( DUCT) ( OPEN / CLOSE) SUPPLY AIR DAM PER COM M AND SUPPLY AIR DAM PER STATUS M EXHAUST FAN ON-OFF/TRIP STATUS M SUPPLY FAN ON-OFF/TRIP/FLOW SUPPLY FAN COM M AND CONDENSER FAN ON-OFF/TRIP STATUS HDP/LSP STATUS DPS COM PRESSOR-1&2 COM M AND PRE-FILTERS DIRTY STATUS ( OPEN / CLOSE) RETURN AIR DAM PER STATUS RETURN AIR DAM PER COM M AND FIRE SM OKE DAM PERS STATUS DPS COM PRESSOR-1&2 ON-OFF/TRIP/LP/HP/ DPS FIRE SM OKE DAM PERS COM M AND TIHI RTS BAG FILTERS DIRTY STATUS FRESH AIR FILTERS DIRTY STATUS MB SF TIHI COMMUNICATION ROOM M LOW OIL PRESSURE PCT SUPPLY FAN FRESH AIR LP M AIR SECTION ( FANS) STANDBY / DUTY BAG FILTER LOW SUCTION PRESSURE TIHI R.A. DAMPER PREFILTER LSP M CORRIDOR FRESH AIR FILTER (STL) MVD MOTORIZED VOLUME DAMPER PART DPS M M BATTERY ROOM I N DPS TIHI M FULL OR DUTY / STANDBY M DDC MODULES DIGITAL INPUT (DI) 2+ 1 2 2 2 2 24+ 2 5 24+ 4+ 6 2 4+ 11+ 1 1 8+ 13+ 2 2 4+ 11+ 1 1 4 13+ 2 2 ANALOG INPUT (AI) ARE THE SOLE PROPERTY OF DIGITAL OUTPUT (DO) 2 REPRODUCTI ON FRESH AIR FILTER (STL) M AIR LOCK ROOMS 16 POINT NO M M 16P CO. CONDENSER R.A. DAMPER SECTION ( FANS) DTS TO FACP THI S LEGEND RETURN DSD DOCUMENT WI THOUT NFPA 90A, IMC & MANUFACTURER GUIDELINES AS-BUILT BY DATE } DATE BY CHKD. DESCRIPTION CERT. APPD. DDC EQUIPMENT DI DO AI AO MIR DRAWN BY NO. OF DDC POINTS (MIN.) DATE STARTED 128 64 16 THE I NFORMATI ON DDC EQUIPMENT SCHEDULE 16 CHECKED BY 04-01-2021 NAO 16-02-2021 DATE COMPLETED ENG. DEPT. OPR'G. DEPT. THIS DRAWING IS NOT TO BE USED FOR NTS SCALE: EHV-E&DD/ESD APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MODULES (MIN.) 8 4 1 1 DDC NO. REV. NO. DRAW I NG NO. Of 16P DDC MATERIAL UNTIL CERTIFIED AND DATED HVAC CONTROL SCHEMATIC DIAGRAM CONTROL BUILDING 380/132KV NIC CIRCLE BSP NWOA JOB ORDER NO. INDEX K SAUDI ARABIA PLANT NO. DRAWING NUMBER SHEET NO. SE0514 WT-925440 07 OF 08 REV. NO. 00 SEC-A (2004/10) DMS VECTOR AND REV. NO. CONTAI NED HEREI N FOR MORE DETAILS REFER TO ATTACHED HVAC ALARMS LOGIC DIAGRAM SECA00 THI S TO SAS FROM FACP ANALOG OUTPUT (AO) OW NER. K NOTES JOB ORDER NO. INDEX SE0514 WT-925440 DRAWING NUMBER PLANT NO. 08 OF 08 SHEET NO. 00 REV. NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE OF I TS NECESSARY DURING PROJECT EXECUTION SHALL BE INCORPORATED WITH SEC APPROVAL CONSENT 2. PLUS SIGN INDICATES ADDITIONAL POINTS PER PROJECT REQUIREMENT / APPROVED CALCULATION SHALL BE INCORPORATED LEGEND RETURN DX COOLING COIL DPS DIFFERENTIAL PRESSURE SWITCH DSD DUCT SMOKE DETECTOR DTS DUCT TEMPERATURE SENSOR EF EXHAUST FAN EDH DPS 1 EF M S.A DAMPER M ELECTRIC DUCT HEATER FACP FIRE ALARM CONTROL PANEL FPE-ROOM FD FIRE DAMPER HDP SUPPLY FAN HP FROM BAG FILTER CONROL CABLE TUNNEL HIGH DISCHARGE PRESSURE HIGH OIL PRESSURE SHALL BE OBTAI NED PREFILTER CCT HVAC HEATING, VENTILATING & AIR CONDITIONING FRESH AIR MB M TRANSMISSION ROOM FROM FACP M M MOORIZED DAMPER MB RAISED FLOOR MIXING BOX MF/SD MOTORIZED FIRE/SMOKE DAMPER M M DPS EDH DPS M TRANSMISSION ROOM M R.A. DAMPER SUPPLY M PREFILTER BAG FILTER CONDENSER FRESH AIR FILTER (STL) DX COOLING COIL AIR SECTION ( FANS) STANDBY / DUTY COMMUNICATION ROOM DSD DTS M M RAISED FLOOR DPS S.A DAMPER COMMUNICATON ROOM RA RETURN AIR RHS ROOM HUMIDITY SENSOR RTS ROOM TEMPERATURE SENSOR SAS SUBSTATION AUTOMATION SYSTEM M SF SUPPLY FAN SPF SMOKE PURGE FAN STL SAND TRAP LOUVER ECC ENERGY CONTROL CENTER STATUS I N RHS TIHI M FIRE SM OKE DAM PERS STATUS REFERENCE DRAWINGS DRAWING TITLE DRAWING NO. DRAWING CONTROL SHEET WT-925429 SUBSTATION LAYOUT WT-925438 SAUDIELECTRI CI TY FIRE SM OKE DAM PERS COM M AND ( OPEN / CLOSE) SPF ISOLATION DAM PER STATUS SPF ISOLATION DAM PER COM M AND STATUS SPF COM M AND HUM IDITY ROOM SPF ON-OFF/TRIP TEM PERATURE ROOM STATUS EF ON-OFF/TRIP SPF EF COM M AND FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND EDH ON-OFF/TRIP/STAGES STATUS HEATER COM M AND RETURN AIR TEM PERATURE ( DUCT) SUPPLY AIR TEM PERATURE ( DUCT) ( OPEN / CLOSE) SUPPLY AIR DAM PER COM M AND SUPPLY AIR DAM PER STATUS M SUPPLY FAN ON-OFF/TRIP/FLOW SUPPLY FAN COM M AND CONDENSER FAN ON-OFF/TRIP STATUS HDP/LSP STATUS COM PRESSOR-1&2 ON-OFF/TRIP/LP/HP/ COM PRESSOR-1&2 COM M AND DPS BAG FILTERS DIRTY STATUS PRE-FILTERS DIRTY STATUS ( OPEN / CLOSE) RETURN AIR DAM PER STATUS RETURN AIR DAM PER COM M AND FIRE SM OKE DAM PERS STATUS FIRE SM OKE DAM PERS COM M AND FRESH AIR FILTERS DIRTY STATUS RTS DPS POWER CABLE TUNNEL TIHI TEMPERATURE & HUMIDITY INDICATOR MB DPS PCT M TIHI M LOW OIL PRESSURE SCADA SUPERVISORY CONTROL & DATA ACQUISTION SUPPLY FAN FRESH AIR LP I N DPS LOW SUCTION PRESSURE FULL OR DUTY / STANDBY LSP PART MVD MOTORIZED VOLUME DAMPER DDC MODULES DIGITAL INPUT (DI) 2+ 1 2 2 2 2 2 3 24+ 20+ 4+ 6 2 4+ 3 2 1 1 3 2 2 4+ 3 1 1 1 3 ANALOG INPUT (AI) ARE THE SOLE PROPERTY OF DIGITAL OUTPUT (DO) 2 REPRODUCTI ON FRESH AIR FILTER (STL) 16 POINT NO M 16P CO. CONDENSER R.A. DAMPER SECTION ( FANS) DTS TO FACP THI S AIR DSD DOCUMENT WI THOUT THE W RI TTEN HVAC CONTROL SCHEMATIC DIAGRAM - SEC TRANSMISSION ROOM BUILDING (IF APPLICABLE) 2 2 AS-BUILT BY DATE } DO AI MIR DRAWN BY 96 48 16 16 DATE STARTED CHECKED BY 04-01-2021 ENG. DEPT. MODULES (MIN.) THIS DRAWING IS NOT TO BE USED FOR 6 3 1 1 NAO CERT. APPD. NTS SCALE: DATE COMPLETED OPR'G. DEPT. NO. OF 16P DDC CHKD. DESCRIPTION AO NO. OF DDC POINTS (MIN.) BY THE I NFORMATI ON DI DATE 16-02-2021 EHV-E&DD/ESD APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED DDC NO. REV. NO. DRAW I NG DDC EQUIPMENT REV. NO. HVAC CONTROL SCHEMATIC DIAGRAM SEC TRANSMISSION ROOM BUILDING 380/132KV NIC CIRCLE BSP NWOA JOB ORDER NO. SAUDI ARABIA INDEX PLANT NO. DRAWING NUMBER SHEET NO. K SE0514 WT-925440 08 OF 08 REV. NO. 00 SEC-A (2004/10) DMS VECTOR AND DDC EQUIPMENT SCHEDULE CONTAI NED HEREI N FOR MORE DETAILS REFER TO ATTACHED HVAC ALARMS LOGIC DIAGRAM SECA00 THI S TO SAS FROM FACP ANALOG OUTPUT (AO) OW NER. S/P NOTES JOB ORDER NO. 1. THE DRAWING IS FOR GUIDANCE ONLY. ANY CHANGE INCORPORATED WITH SEC APPROVAL PACU-1B FAULTY 2. HIGH TEMPERATURE-1 DRAWING INTENDS TO ONLY EXPLAIN LOGIC TO AID HIGH HUMIDITY-1 IN PROGRAMMING. SUPERIOR METHODS / DEVICES PER EHV-BLDG-VENTILATION FAULTY SAS INTERFACE EHV-BLDG-HIGH HUMIDITY ARE PERMITTED TO BE USED WITH SEC APPROVAL (ENERGY CONTROL CENTER) 3. FAULT SIGNAL TO BE CONSIDERED HIGH PER PROPOSED PACU-3A FAULTY S.NO. S.NO. ALARMS PACU-3B FAULTY REMARKS 1. <STN NAME> NON URGENT ALARM REFER TES-P-107.02R2 2. <STN NAME> URGENT ALARM REFER TES-P-107.02R2 <STN NAME> NON URGENT ALARM 1. HIGH TEMPERATURE-3 EHV-BLDG-AIR CONDITION FAULTY <STN NAME> URGENT ALARM 2. EHV-BLDG-VENTILATION FAULTY 3. EHV-BLDG-HIGH TEMPERATURE EHV-BLDG-SUMP PUMP OPERATE 4. EHV-BLDG-HIGH HUMIDITY EHV-BLDG-SUMP PUMP FAULTY 5. EHV-BLDG-SUMP PUMP OPERATE 6. EHV-BLDG-SUMP PUMP FAULTY 7. HV-BLDG-I AIR CONDITION FAULTY 8. HV-BLDG-I VENTILATION FAULTY 9. HV-BLDG-I HIGH TEMPERATURE HIGH HUMIDITY-3 VENTILATION FAULTY SUMP PUMP OPERATE HV-BLDG-I HIGH HUMIDITY HV-BLDG-I AIR CONDITION FAULTY 11. HV-BLDG-I SUMP PUMP OPERATE HV-BLDG-I VENTILATION FAULTY 12. HV-BLDG-I SUMP PUMP FAULTY 13. HV-BLDG-II AIR CONDITION FAULTY 14. HV-BLDG-II VENTILATION FAULTY 15. HV-BLDG-II HIGH TEMPERATURE 16. HV-BLDG-II HIGH HUMIDITY 17. HV-BLDG-II SUMP PUMP OPERATE 18. HV-BLDG-II SUMP PUMP FAULTY 19. CONTROL ROOM-AIR CONDITION FAULTY 20. CONTROL ROOM-HIGH TEMPERATURE 21. CONTROL ROOM-HIGH HUMIDITY 22. CONTROL ROOM - VENTILATION FAULTY 23. CONTROL ROOM-SUMP PUMP OPERATE 24. CONTROL ROOM-SUMP PUMP FAULTY HV-BLDG-II SUMP PUMP OPERATE 25. CONTROL BLDG-AIR CONDITION FAULTY HV-BLDG-II SUMP PUMP FAULTY 26. CONTROL BLDG-BATTERY ROOM EF FAIL SUMP PUMP OPERATE 27. CONTROL BLDG-HIGH TEMPERATURE SUMP PUMP FAULTY 28. CONTROL BLDG-HIGH HUMIDITY 29. CONTROL BLDG-BATTERY ROOM HIGH H2 30. TRANSMISSION ROOM BLDG-AIR CONDITION FAULTY 31. TRANSMISSION ROOM BLDG-HIGH TEMPERATURE 32. TRANSMISSION ROOM BLDG-HIGH HUMIDITY 33. SEB-AIR CONDITION FAULTY 34. SEB-HIGH TEMPERATURE 35. SEB-HIGH HUMIDITY VENTILATION FAULTY HV-BLDG-I HIGH TEMPERATURE 1 0 ROOM HIGH TEMPERATURE 1 0 BATTERY ROOM EF FAIL 1 0 VENTILATION FAIL 1 0 HIGH HYDROGEN 1 0 HV-BLDG-I HIGH HUMIDITY HV-BLDG-I SUMP PUMP OPERATE HV-BLDG-I SUMP PUMP FAULTY SUMP PUMP OPERATE SUMP PUMP FAULTY PACU-5A FAULTY PACU-5B FAULTY 132kV GIS BUILDING-II ROOM HIGH HUMIDITY HCP-05 HIGH TEMPERATURE HIGH HUMIDITY VENTILATION FAULTY HV-BLDG-II AIR CONDITION FAULTY THI S HIGH HUMIDITY HV-II-SSP MAIN PANEL 0 FROM HIGH TEMPERATURE LOGIC/PROGRAM M ING 132kV GIS BUILDING-I HCP-04 HV-IIVCP-12 1 DOCUMENT 10. PACU-4B FAULTY HV-I-SSP MAIN PANEL PACU- #B FAULTY SHALL BE OBTAI NED PACU-4A FAULTY HV-IVCP-11 0 SUMP PUMP FAULTY LOGIC/PROGRAM M ING EHV-SSP MAIN PANEL 1 LOGIC/PROGRAM M ING EHVVCP-10 PACU- #A FAULTY HV-BLDG-II VENTILATION FAULTY HV-BLDG-II HIGH TEMPERATURE HV-BLDG-II HIGH HUMIDITY LEGEND BR BATTERY ROOM CC CABLE CHUTE CCC CONTROL CABLE CHUTE CCT CONROL CABLE TUNNEL EF PART HCP-03 ALARMS NO YES LIST OF ALARMS TO BE PROVIDED AT SCADA (ECC) INTERFACE WI THOUT INPUT LIST OF HVAC ALARMS TO BE PROVIDED AT SAS INTERFACE THE W RI TTEN LOGIC (SEE BELOW TRUTH TABLE) EXHAUST FAN INCOMER CABLE TUNNEL OG OUTGOING CABLE TUNNEL OR OR LOGIC GATE PCT POWER CABLE TUNNEL SAS SUBSTATION AUTOMATION SYSTEM FULL OR IC I N HVAC HEATING, VENTILATING & AIR CONDITIONING SCADA SUPERVISORY CONTROL & DATA ACQUISTION SUPPLY FAN ECC I N SF ENERGY CONTROL CENTER FPSP FIRE PROTECTIVE SIGNALLING PANEL PACU PACKAGE AIR CONDITIONING UNIT (F) FUTURE H2 HYDROGEN REFERENCE DRAWINGS WT-925429 SUBSTATION LAYOUT WT-925438 HVAC CONTROL SCHEMATIC DIAGRAM - SUBSTATION BUILDINGS WT-925440 SAUDIELECTRI CI TY DRAWING CONTROL SHEET NO DRAWING NO. CO. DRAWING TITLE MECHANICAL / HVAC ALARM LIST IS UPDATED BASED ON PROJECT SCOPE AND REQUIREMENT IN TES-P-107.02R2. PACU-06 FAULTY CONTROL ROOM-AIR CONDITION FAULTY PACU-06 FAULTY OF CONTROL ROOM-HIGH TEMPERATURE HCP-06 CONTROL ROOM-HIGH HUMIDITY CONTROL ROOM HIGH HUMIDITY-I CRBVCP-13 CR-SSP MAIN PANEL LOGIC/PROGRAM M ING HIGH TEMPERATURE-I CONTROL ROOM - VENTILATION FAULTY VENTILATION FAULTY SUMP PUMP OPERATE CONTROL ROOM-SUMP PUMP OPERATE SUMP PUMP FAULTY CONTROL ROOM-SUMP PUMP FAULTY (U) BATTERY ROOM EF FAIL HIGH TEMPERATURE HCP-07 HIGH HUMIDITY BY DATE CONTROL BLDG-AIR CONDITION FAULTY CONTROL BLDG-BATTERY ROOM EF FAIL CONTROL BLDG-HIGH TEMPERATURE HEREI N PACU-07 FAULTY LOGIC/PROGRAM M ING BUILDING) ( BATTERY ROOM CONTROL BUILDING AS-BUILT PACU-07 FAULTY CONTROL BLDG-HIGH HUMIDITY CONTROL BLDG-BATTERY ROOM HIGH H2 BATTERY ROOM HIGH H2 H2 DETECTOR HIGH TEMPERATURE HCP-08 HIGH HUMIDITY DATE BY HCP-09 HIGH TEMPERATURE HIGH HUMIDITY LOGIC/PROGRAM M ING BUILDING SECURITY EQUIPM ENT AHU/ACCU-09B FAULTY CERT. APPD. TRANSMISSION ROOM BLDG-AIR CONDITION FAULTY TRANSMISSION ROOM BLDG-HIGH TEMPERATURE TRANSMISSION ROOM BLDG-HIGH HUMIDITY MIR DRAWN BY AHU/ACCU-09A FAULTY CHKD. DESCRIPTION THE I NFORMATI ON PACU-08 FAULTY LOGIC/PROGRAM M ING BUILDING TRANSM ISSION ROOM REV. NO. PACU-08 FAULTY REPRODUCTI ON LOGIC/PROGRAM M ING 380KV GIS ( EHV)BUILDING SCADA INTERFACE EHV-BLDG-HIGH TEMPERATURE ARE THE SOLE PROPERTY HIGH TEMPERATURE-2 HIGH HUMIDITY-2 CONSENT SYSTEM SUPPLIER / MANUFACTURER RECOMMENDATIONS PACU-2B FAULTY DATE STARTED CHECKED BY 05-01-2021 NAO DATE COMPLETED SEB-AIR CONDITION FAULTY ENG. DEPT. OPR'G. DEPT. NTS SCALE: 16-02-2021 EHV-E&DD/ESD SEB-HIGH TEMPERATURE SEB-HIGH HUMIDITY THIS DRAWING IS NOT TO BE USED FOR APPROVAL/CERTIFICATION INFORMATION CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED DDC NO. REV. NO. MECHANICAL/HVAC ALARMS LOGIC DIAGRAM 380/132KV NIC CIRCLE BSP BY ELECTRO-MECHANICAL CONTRACTORS (E&DD) MECHANICAL/HVAC ALARMS LOGIC DIAGRAM NWOA BY SAS / ELECTRICAL CONTRACTOR (TESAD) JOB ORDER NO. SAUDI ARABIA INDEX PLANT NO. S/P SE0514 DRAWING NUMBER WT-925441 SHEET NO. REV. NO. 01 OF 01 00 SEC-A (2004/10) DMS VECTOR CONTAI NED HCP-02 EHV-BLDG-AIR CONDITION FAULTY SECA00 AND PACU-2A FAULTY DRAW I NG HCP-01 OF I TS PACU-1A FAULTY THI S INDEX NECESSARY DURING PROJECT EXECUTION SHALL BE SE0514 PLANT NO. WT-925440 DRAWING NUMBER 01 OF 01 SHEET NO. 00 REV. NO. Annexure: XIIB-I Project Title / PTS Number: RFx Number: The BIDDER shall fill in the below annexure for Heating, Ventilation & Air Conditioning System (HVAC) and submit along with the Technical Proposal. Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement 1 2 3 4 5 #A 6 7 8 9 10 11 12 13 Remarks Package Air Conditioning Units (PACU) for EHV (380kV) GIS building Package Air Conditioning Units (PACU) for EHV (230kV) GIS building Package Air Conditioning Units for HV (69kV or 110kV or 115kV or 132kV) GIS building Package Air Conditioning Units for MV (33kV or 34.5kV) Switchgear buildings, where applicable Package Air Conditioning Units for MV (11kV or 13.8kV) Switchgear buildings, where applicable Package Air Conditioning Units for Control building vital support rooms (Auxiliary room, Battery Room, Communication Room, MV SWGR Room, FPE Room, etc.,) as applicable per SOW / substation layout Package Air Conditioning Units for Control Rooms Package Air Conditioning Units for Customer / Interface Rooms, where applicable Split Package Air Conditioning Units for Security Equipment Building (included in New Control Building) HVAC Requirement for Tunnel Utility Rooms as per PTS Ventilation / Cooling System Requirement for outdoor Tunnels (if any) Vertical Package Air Conditioning Units for Telecom Shelter, if any Split Air Conditioning Units for control building support rooms (Office, Conference, Relay Test, Records, etc.) as applicable per SOW / substation layout Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-I Project Title / PTS Number: RFx Number: Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement #B Remarks 14 Split AC (if any) for EHV GIS halls – store room 15 Split AC (if any) for HV GIS halls – store room Split Air Conditioning Units for Gate House, where 16 applicable Duty / Standby Split AC for HGIS Container 17 Rooms 18 Dehumidification system (Electric duct heater) Humidification system for locations where 19 necessary based on SEC / NG standards. 20 Bleed air fans & Inertial air filter HVAC for Elevator Machine Room, where 21 applicable 22 Ventilation for Elevator Hoist way (natural / forced) 23 Rectangular duct for GIS Halls 24 Spiral duct for GIS Halls, if applicable per PTS 25 Laptop accessories HVAC duct proposed above crane in EHV 26 (380kV) GIS hall HVAC duct proposed above crane in HV (69kV or 27 110kV or 115kV or 132kV) GIS hall Third party inspection / FAT for Air Conditioning 28 Units (as applicable) Third party inspection / FAT for HVAC Control 29 Panels (as applicable) EHV GIS Buildings ventilation system for Control 30 cable tunnel below EHV building EHV GIS Buildings ventilation system for Control 31 cable tunnel between EHV building & control building EHV GIS Buildings ventilation system for Control 32 cable chute, where applicable EHV GIS Buildings ventilation system for 33 Incomer/Outgoing Power cable tunnels Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-I Project Title / PTS Number: RFx Number: Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement 34 35 36 37 38 39 40 41 #C 42 43 44 45 46 47 48 49 Remarks EHV GIS Buildings Basement Ventilation, where applicable EHV GIS Buildings Basement, where applicable provided with Air conditioning HV GIS Buildings ventilation system for Control cable tunnel HV GIS Buildings ventilation system for Control cable chute, where applicable HV GIS Buildings ventilation system for Incomer Power cable tunnels from EHV Transformers HV GIS Buildings ventilation system for Outgoing Power cable tunnels HV GIS Buildings Basement Ventilation HV GIS Buildings Basement provided with Air conditioning MV SWGR Buildings (33kV or 34.5kV) ventilation system for Control cable tunnel MV SWGR Buildings (33kV or 34.5kV) ventilation system for Control cable chute, where applicable MV SWGR Buildings (33kV or 34.5kV) ventilation system for Incomer Power cable tunnels from EHV or HV Transformers MV SWGR Buildings (33kV or 34.5kV) ventilation system for Outgoing Power cable tunnels MV SWGR Buildings (33kV or 34.5kV) Basement Ventilation MV SWGR Buildings (33kV or 34.5kV) Basement provided with Air conditioning MV SWGR Buildings (11kV or 13.8kV) ventilation system for Control cable tunnel MV SWGR Buildings (11kV or 13.8kV) ventilation system for Control cable chute, where applicable Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-I Project Title / PTS Number: RFx Number: Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement #D Remarks MV SWGR Buildings (11kV or 13.8kV) ventilation 50 system for Incomer Power cable tunnels from HV Transformers MV SWGR Buildings (11kV or 13.8kV) ventilation 51 system for Outgoing Power cable tunnels MV SWGR Buildings (11kV or 13.8kV) Basement 52 Ventilation MV SWGR Buildings (11kV or 13.8kV) Basement 53 provided with Air conditioning 54 Control Building Basement Ventilation Control Building Basement provided with Air 55 conditioning 56 LV Power cable chute Ventilation system 57 Communication cable chute ventilation systems Ventilation system for cable floors, where 58 applicable 59 Cable floors provided with Air conditioning Ventilation system for Duct banks / trenches 60 proposed as tunnels, if any 61 Ventilation system operation is continuous 62 Jet fans for ventilation system, if any 63 Ventilation system operation is Intermittent Separate control panel for ventilation fans, where 64 necessary 65 Exhaust system / fans for all Battery Rooms Exhaust systems / fans for all Clean Agent Fire 66 Protection Equipment Rooms 67 Exhaust system / fans for all Toilets 68 Exhaust systems / fans for all Fire Pump Room 69 HVAC Control panels for EHV GIS Buildings 70 HVAC Control panels for HV GIS Buildings HVAC Control panels for MV Switchgear 71 buildings, where applicable Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-I Project Title / PTS Number: RFx Number: Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement 72 72 74 75 76 77 78 #E 79 80 81 82 83 84 85 86 87 88 89 90 91 Remarks HVAC Control panels for Control building support rooms (Auxiliary room, Battery Room, Communication Room, MV SWGR Room, FPE Room, etc.,) as applicable per SOW / substation layout HVAC Control panels for Control Rooms HVAC Control panels for Customer / Interface Rooms, where applicable HVAC Control panels for Security Equipment Buildings (included in new control building) Dedicated HVAC / Ventilation Control panel for each Tunnel Utility Room Automatic operation of HVAC Manual operation of HVAC Mechanical / HVAC Alarm list as per PTS / standard HVAC System Interlocked to Fire Detection / Alarm System HVAC Interlocked to Substation Automation System (SAS) HVAC Interlocked to Energy Control Center (ECC) Smoke purging fans Duct work, accessories, Insulation, etc., as per PTS Conduits, fittings & accessories for mechanical works as per PTS Site Testing & commissioning (as applicable) Documentation (as per PTS) Operational Spare parts as per PTS / Appendix V Operational Spare parts as per TMSS / Standards HVAC Training as per PTS / Appendix X General Induction / Orientation for systems operation & maintenance Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-I Project Title / PTS Number: RFx Number: S.no. SOW requirement Bidder Compliance Yes No (✗) (✔) Remarks 92 Equipment & component tags Manufacturer as per SEC/NG Approved 93 manufacturer list 94 SEC / NG Approved subcontractor / vendor Supports for device/equipment mounting & 95 installation 96 Remote End substations works per PTS 97 Pre-bid clarifications incorporated 98 Other if any (specify as attachment) Bidder Notes / remarks: ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… #F ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-II Project Title / PTS Number: RFx Number: The BIDDER shall fill in the below annexure for Plumbing systems and submit along with the Technical Proposal. Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement A Remarks 1 Water supply system for toilets, Hose bibs, etc. Drainage and vent system for toilets, hose bibs, 2 etc. 3 Roof mounted water storage tanks as per PTS 4 Under ground water storage tanks as per PTS Water transfer pumps with local control panel & 5 weather protection Booster pumps with local control panel & 6 weather protection 7 Eyewash for Battery rooms 8 Drainage and vent system for Battery rooms 9 Drainage system for all building roofs Storm water drainage system (provide applicable 10 civil and / or mechanical proposal based on results of geotechnical investigation) 11 Neutralization pit / tank for Battery rooms Self-priming pump with weather protection for oil 12 insulated electrical equipment pits (specify quantity in remarks) Sump pumps with local control panels for all 13 Building Basements as applicable Sump pumps with local control panels for all Building tunnels (control cable tunnels & Power 14 Cable Tunnels & all applicable outdoor Tunnels) as applicable Sump pumps with local control panels for all 15 control / power cable chutes as applicable Sump pumps with local control panels for all 16 control / power cable trenches as applicable. Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-II Project Title / PTS Number: RFx Number: Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement 17 18 19 20 B 21 22 23 24 25 26 27 28 Remarks Sump pumps with local control panels for Fire Hydrant Trench / pit if any Main control panels for sump pumps of EHV (380kV) GIS building (basement-if applicable, control & power cable tunnels, etc.) (specify quantity in remarks) Main control panels for sump pumps of EHV (230kV) GIS building (basement, control & power cable tunnels, etc.) (specify quantity in remarks) Main control panels for sump pumps of HV (69kV or 110kV or 115kV or 132kV) GIS building (basement, control & power cable tunnels, etc.) (specify quantity in remarks) Main control panels for sump pumps of MV (33kV or 34.5kV) switchgear building, where applicable (basement, control & power cable tunnels, etc.) (specify quantity in remarks) Main control panels for sump pumps of MV (11kV or 13.8kV) switchgear building where applicable (basement, control & power cable tunnels, etc.) (specify quantity in remarks) Main control panels for sump pumps in Control Room / Building basement Dedicated Main control panels for sump pumps in all outdoor tunnels to be provided & located in Tunnel Utility Room Automatic operation of sump pumps Manual operation of sump pumps Main control panels of sump pumps interlocked to Substation Automation System (SAS) Main control panels of sump pumps interlocked to Energy Control Center (ECC) through SAS Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-II Project Title / PTS Number: RFx Number: Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement C Remarks 29 Mechanical (Plumbing) Alarm list as per PTS Condensate drainage piping & holding / seepage 30 tanks for Air conditioning equipment 31 Hose bibs for Air conditioning equipment Plumbing requirements, if any for Customer 32 Interface Room (Provide details if necessary) Plumbing requirements, if any for Security 33 Equipment Building (Provide details if necessary) Plumbing requirements, if any for Gate House, if 34 applicable (Provide details if necessary) Plumbing requirements, if any for Elevator 35 Machine Room (Provide details if necessary) Plumbing requirements, if any for Elevator Hoist 36 way (Provide details if necessary) Plumbing requirements, if any for Telecom Shelter 37 (Provide details if necessary) 38 Septic tank and seepage pits for toilets Piping, fittings, fixtures, valves & accessories (as 39 applicable) Conduits, fittings & accessories for mechanical 40 works as per PTS 41 Electric water heaters 42 Drinking water coolers 43 Site Testing & commissioning (as applicable) 44 Documentation (as per PTS) General Induction / Orientation for systems 45 operation & maintenance 46 Operational Spare parts as per PTS / Appendix V 47 Operational Spare parts as per TMSS / Standards 48 Equipment & component tags Manufacturer as per SEC/NG Approved 49 manufacturer list Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-II Project Title / PTS Number: RFx Number: S.no. SOW requirement Bidder Compliance Yes No (✗) (✔) Remarks 50 SEC / NG Approved subcontractor / vendor Supports for device/equipment mounting & 51 installation 52 Remote End substations works per PTS 53 Pre-bid clarifications incorporated 54 Other if any (specify as attachment) Bidder Notes / remarks: ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… D ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-III Project Title / PTS Number: RFx Number: The BIDDER shall fill in the below annexure for Weight handling systems and submit along with the Technical Proposal. Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement Remarks Double Girder Electric overhead travelling crane for 1 EHV GIS Building (Specify number in remarks) Double Girder Electric overhead travelling crane for 2 HV GIS Building (Specify number in remarks) Electric overhead travelling crane for MV Building, if #A 3 applicable (Specify number in remarks) 4 Pendant control 5 Radio Remote control 6 Manual Hoist for control building 7 Manual Hoist for multi-purpose building 8 Electric hoist for control building 9 Electric hoist for multi-purpose building 10 Jib crane for control building 11 Jib crane for multi-purpose building 12 Service elevator for multi-purpose building 13 Manual Hoist for Fire Pump room 14 Site Testing & commissioning (as applicable) 15 Documentation (as per PTS) General Induction for system operation & 16 maintenance 17 Operational Spare parts, if any as per PTS/Appendix V Operational Spare parts, if any as per TMSS / 18 Standards 19 Equipment & component tags Manufacturer as per SEC/NG Approved manufacturer 20 list 21 SEC / NG Approved subcontractor / vendor Bidder name: Signature: Representative Name: Bidder Stamp & Date: Annexure: XIIB-III Project Title / PTS Number: RFx Number: Bidder Compliance Yes No (✗) (✔) S.no. SOW requirement 22 23 24 24 Remarks Supports for device/equipment mounting & installation Remote End substations works per PTS Pre-bid incorporated Other if any (specify as attachment) Bidder Notes / remarks: ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… #B ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… ……………………………………………………………………………………………………… Bidder name: Signature: Representative Name: Bidder Stamp & Date: PTS-20WN374 * * * * 400 3 230 1 > 2.6 400 3 2 Min. 400 3 3 Min. 400 3 5.5 Min Open Wire 400 3 NA Ducted PTS-20WN374 * * 55 Ambient * Centrifugal * * * * * ODP/Exp. Proof * * 1.15 400/3/60 or 230/1/60 * * * 73-TMSS-05 PTS-20WN374 PVC/UPVC * * * * * * * * * * * * * * 75-TMSS-01 PTS-20WN374 SUBMERSIBLE 4 * * TEFC * 230/1/60 3450 As Required Ground Water 1 Ambient 50 83-TMSS-01 PTS-20WN374 57 DEWATERING * 1.50 230/1/60 38.6 94-TMSS-01 PTS-20WN374 50 * * * 230 60 1 * * * 4 * 10 * 50 * * * * * * 3.50 * N.A. N.A. N.A. N.A.