ID Task Name Duration Start Finish Nov 1 2 Jumeirah 2 Villa - Project Duration 251 days Wed 20/12/23 Wed 04/12/24 3 Moblization Fencing, Porta Cabin and Signage Sub Structure Excavation 6 days 12 days Wed 20/12/23 Wed 27/12/23 Wed 20/12/23 Thu 04/01/24 4 5 6 6 days Mon 08/01/24 Mon 15/01/24 Dewatering (N/A as per recived drawings/soil report) ) Soil Compation and Testing 5 days Fri 12/01/24 Thu 18/01/24 12 Road base 2 layers Pcc work Footing Block work for Foundation 10 days 3 days 12 days 10 days Mon 15/01/24 Fri 26/01/24 Tue 30/01/24 Sat 10/02/24 Fri 26/01/24 Tue 30/01/24 Wed 14/02/24 Thu 22/02/24 13 Water proofing on block wall (Bitumin) 3 days Mon 19/02/24 Wed 21/02/24 14 Neck Column Back filling with compaction 3 days 6 days Wed 21/02/24 Fri 23/02/24 Fri 23/02/24 Fri 01/03/24 7 8 9 10 11 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Tie Beam (Steel, form work and concrete 10 days with all approval Super Structure Grade Slab (Steel work with concrete) 6 days Fri 01/03/24 Column work Ground Floor (Steel work, 10 days form work, concrete work) Ground floor slab 15 days Tue 19/03/24 Mon 01/04/24 Thu 28/03/24 Wed 17/04/24 Ground floor slab deshuttring Block work for Ground floor Internal plaster for Ground floor walls with MEP containments Column work first Floor (Steel work, form work, concrete work) First Floor Slab First Floor Slab deshuttring 12 days 9 days 11 days Wed 17/04/24 Thu 02/05/24 Sat 04/05/24 Wed 15/05/24 Fri 17/05/24 Fri 31/05/24 7 days Fri 19/04/24 15 days 12 days Tue 30/04/24 Mon 20/05/24 Mon 20/05/24 Tue 04/06/24 Block work First Floor Internal plaster for Ground floor walls with MEP containments Parapet Wall Outer plaster Compound Wall, Pcc, Footing, Block works Electrical works - Containment wall/flooring, Cabling, HVAC works Joinery Works 9 days 11 days Wed 05/06/24 Sat 15/06/24 Mon 17/06/24 Mon 01/07/24 9 days 8 days 18 days Mon 20/05/24 Thu 30/05/24 Thu 30/05/24 Sun 09/06/24 Fri 31/05/24 Tue 25/06/24 50 days Thu 02/05/24 Wed 10/07/24 60 days 50 days Fri 10/05/24 Tue 20/08/24 Thu 01/08/24 Mon 28/10/24 Fire Fighting works IT works Authority Approvals Site Handover with Deep cleaning 45 days 50 days 22 days 3 days Fri 10/05/24 Sat 11/05/24 Fri 01/11/24 Mon 02/12/24 Thu 11/07/24 Thu 18/07/24 Mon 02/12/24 Wed 04/12/24 Project: Jumeirah 2 Villa Date: Mon 15/01/24 Dec Qtr 1, 2024 Jan Feb Mar Qtr 2, 2024 Apr May Jun Qtr 3, 2024 Jul Thu 14/03/24 Mon 11/03/24 Mon 18/03/24 Mon 29/04/24 Task Project Summary Manual Task Start-only Deadline Split Inactive Task Duration-only Finish-only Progress Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress Summary Inactive Summary Manual Summary External Milestone Page 1 Aug Sep Qtr 4, 2024 Oct Nov Dec Qtr 1, 2025 Jan