Jumeirah Park Villa 2 work Schedule

advertisement
ID
Task Name
Duration
Start
Finish
Nov
1
2
Jumeirah 2 Villa - Project Duration
251 days
Wed 20/12/23 Wed 04/12/24
3
Moblization
Fencing, Porta Cabin and Signage
Sub Structure
Excavation
6 days
12 days
Wed 20/12/23 Wed 27/12/23
Wed 20/12/23 Thu 04/01/24
4
5
6
6 days
Mon 08/01/24 Mon 15/01/24
Dewatering (N/A as per recived
drawings/soil report) )
Soil Compation and Testing
5 days
Fri 12/01/24
Thu 18/01/24
12
Road base 2 layers
Pcc work
Footing
Block work for Foundation
10 days
3 days
12 days
10 days
Mon 15/01/24
Fri 26/01/24
Tue 30/01/24
Sat 10/02/24
Fri 26/01/24
Tue 30/01/24
Wed 14/02/24
Thu 22/02/24
13
Water proofing on block wall (Bitumin)
3 days
Mon 19/02/24 Wed 21/02/24
14
Neck Column
Back filling with compaction
3 days
6 days
Wed 21/02/24 Fri 23/02/24
Fri 23/02/24
Fri 01/03/24
7
8
9
10
11
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
Tie Beam (Steel, form work and concrete 10 days
with all approval
Super Structure
Grade Slab (Steel work with concrete) 6 days
Fri 01/03/24
Column work Ground Floor (Steel work, 10 days
form work, concrete work)
Ground floor slab
15 days
Tue 19/03/24
Mon 01/04/24
Thu 28/03/24
Wed 17/04/24
Ground floor slab deshuttring
Block work for Ground floor
Internal plaster for Ground floor walls
with MEP containments
Column work first Floor (Steel work,
form work, concrete work)
First Floor Slab
First Floor Slab deshuttring
12 days
9 days
11 days
Wed 17/04/24 Thu 02/05/24
Sat 04/05/24
Wed 15/05/24
Fri 17/05/24
Fri 31/05/24
7 days
Fri 19/04/24
15 days
12 days
Tue 30/04/24 Mon 20/05/24
Mon 20/05/24 Tue 04/06/24
Block work First Floor
Internal plaster for Ground floor walls
with MEP containments
Parapet Wall
Outer plaster
Compound Wall, Pcc, Footing, Block
works
Electrical works - Containment
wall/flooring, Cabling,
HVAC works
Joinery Works
9 days
11 days
Wed 05/06/24 Sat 15/06/24
Mon 17/06/24 Mon 01/07/24
9 days
8 days
18 days
Mon 20/05/24 Thu 30/05/24
Thu 30/05/24 Sun 09/06/24
Fri 31/05/24
Tue 25/06/24
50 days
Thu 02/05/24
Wed 10/07/24
60 days
50 days
Fri 10/05/24
Tue 20/08/24
Thu 01/08/24
Mon 28/10/24
Fire Fighting works
IT works
Authority Approvals
Site Handover with Deep cleaning
45 days
50 days
22 days
3 days
Fri 10/05/24
Sat 11/05/24
Fri 01/11/24
Mon 02/12/24
Thu 11/07/24
Thu 18/07/24
Mon 02/12/24
Wed 04/12/24
Project: Jumeirah 2 Villa
Date: Mon 15/01/24
Dec
Qtr 1, 2024
Jan
Feb
Mar
Qtr 2, 2024
Apr
May
Jun
Qtr 3, 2024
Jul
Thu 14/03/24
Mon 11/03/24 Mon 18/03/24
Mon 29/04/24
Task
Project Summary
Manual Task
Start-only
Deadline
Split
Inactive Task
Duration-only
Finish-only
Progress
Milestone
Inactive Milestone
Manual Summary Rollup
External Tasks
Manual Progress
Summary
Inactive Summary
Manual Summary
External Milestone
Page 1
Aug
Sep
Qtr 4, 2024
Oct
Nov
Dec
Qtr 1, 2025
Jan
Download