EEG CABLE NO.: F-GEN : : : According to IEE, IEC 114 route/type DUCT XLPE CU MDB GEN 30 Design Current , Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET m load 0.380 kV 646 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 2,500 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 981.50 900 4.5 kVA 30.39 kA . % Imped. A TO IEC STANDARD. AT 981 A = 3200 AF 1227 frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.799 = 0.799 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: use = It 365 1,229 365 981 0.8 = 1228.84 A no. of cables 2 for S = 240 mm 5 // cables x 240 1825 A ( catalog ccc ) = S.C.C. Derated Ampacity , Iz= CCC x C.F = 1,458 A I2 <= 1,227 <= no. of trays installation LAID IN DUCT 5 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable ------>> 30 0.80 120 5 0.3m flat 6 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That spacing : formation LAID IN AIR A burial depth 7.22 0.73 7.95 27.6 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 2,114 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 0.212 x 981.495 x 5 = 1.248 V = 0.329 % 2- Accumulated V.D. : Acc V.D.= V.D.1 = 0.329 = 0.329 % (Should be <= . 30 % 2.5 %) DESIGN SUCCEED Page 1 of 17 . VERIFICATION EEG CABLE NO.: F-MDB : : : According to IEE, IEC 114 route/type DUCT XLPE CU MDB MDB 30 Design Current , Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET m load 0.380 kV 1,220 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 3,000 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 1853.60 1600 6 kVA 40.52 kA . % Imped. A TO IEC STANDARD. AT 1,854 A = 3200 AF 2317 frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.799 = 0.799 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: use = It 365 2,321 365 1,854 0.8 = 2320.71 A no. of cables 2 for S = 240 mm 8 // cables x 240 2920 A ( catalog ccc ) = S.C.C. Derated Ampacity , Iz= CCC x C.F = 2,332 A I2 <= 2,317 <= no. of trays installation LAID IN DUCT 6 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable ------>> 30 0.80 120 6 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That spacing : formation LAID IN AIR A burial depth 5.42 0.46 5.87 37.3 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 3,382 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 0.212 x 1853.6 x 8 = 1.474 V = 0.388 % 2- Accumulated V.D. : Acc V.D.= V.D.1 = 0.388 = 0.388 % (Should be <= . 30 % 2.5 %) DESIGN SUCCEED Page 2 of 17 . VERIFICATION EEG CABLE NO.: F-EMCC-TREAT-P destination From To Length : : : MDB EMCC-TREAT-P 180 Design Current , Ib = Nearest Nominal , In= Max.Thermal Current, I2= ELSWEDY CABLES m CABLE / BREAKER SIZING SHEET Proj.No. According to IEE, IEC 114 REV-A Multi-core conductor,Low Voltage,Power cable route/type DUCT XLPE CU Max. Dem. KW 3 x kV x p.f. 1,600 A 1.25 x load GEN 0.380 kV 696 KVA 0.8 p.f. = 1600 6 kVA 40.52 kA . % Imped. 1,058 TO IEC STANDARD. AT 1,058 A 2000 AF 1322 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.730 = 0.7296 soil thermal no. of cables LAID IN GROND target Ampacity, It = Select Cable Size: Ib C.F. ccc >= ccc = use = It 365 1,450 365 1,058 0.73 = 1449.89 A no. of cables for S = = 2 240 mm 5 // cables x 240 1825 A ( catalog ccc ) S.C.C. Derated Ampacity , Iz= CCC x C.F = 1,332 A no. of trays installation LAID IN DUCT 5 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable ------>> 40 0.80 120 5 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That I2 <= 1,322 <= spacing : formation LAID IN AIR A burial depth 5.42 4.41 9.82 22.3 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 1,931 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 0.212 x 1058 x 180 5 = 8.073 V = 2.125 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 2.125 + 0.39 % = 2.512 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 3 of 17 . VERIFICATION EEG CABLE NO.: : : : Proj.No. According to IEE, IEC 114 F-EMCC-RAW MDB EMCC-RAW 210 m Design Current , REV-A Multi-core conductor,Low Voltage,Power cable route/type DUCT XLPE CU destination From To Length CABLE / BREAKER SIZING SHEET load 0.380 kV 238 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 400 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 360.84 1600 6 kVA 40.52 kA . % Imped. A TO IEC STANDARD. AT 361 A 630 AF 451 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.821 = 0.8208 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: use = It 365 440 365 361 0.82 = 439.62 no. of cables 2 for S = 240 mm 2 // cables x 240 730 A ( catalog ccc ) = S.C.C. Derated Ampacity , Iz= CCC x C.F = 599 no. of trays installation LAID IN DUCT 2 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable A ------>> I2 <= 451 <= 40 0.80 120 2 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That A spacing : formation LAID IN AIR A burial depth 5.42 12.85 18.27 12.0 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 869 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 0.212 x 360.844 x 210 2 = 8.032 V = 2.114 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 2.114 + 0.38779 % = 2.502 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 4 of 17 . VERIFICATION EEG CABLE NO.: F-EMCC-TREAT-UNIT : : : EMCC-TREAT-UNIT 170 m Ib = Max. Dem. KW 3 x kV x p.f. 160 1.25 Nearest Nominal , In= Max.Thermal Current, I2= ELSWEDY CABLES According to IEE, IEC 114 route/type DUCT XLPE CU MDB Design Current , Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET load = A x GEN 0.380 kV 81 KVA 0.8 p.f. 1600 6 kVA 40.52 kA . % Imped. 123 AT 123 A = 250 154 TO IEC STANDARD. . frame AF trip BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.821 = 0.8208 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = 123 0.82 It 245 150 245 use = 150 for S = = 2 Sending End + Cable 201 A ------>> Receiving End no. of trays installation LAID IN DUCT 40 0.80 120 2 0.3m flat 9 1 H tray touching no. of cables 2 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = R.E.Imped.(in milli Ohms) = R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That formation 120 mm // cables x 1 120 245 A ( catalog ccc ) CCC x C.F = spacing : no. of cables S.C.C. Derated Ampacity , Iz= A LAID IN AIR A burial depth 5.42 34.06 39.47 5.6 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) I2 <= 154 <= 1.45 Iz , or , 292 SUCCEED . CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 0.347 x 1 7.249 V 1.908 % = = 2- Accumulated V.D. : + Acc V.D.= V.D.1 = 1.908 + = 2.295 % 123 x 170 V.D. on upstream cable 0.39 % (Should be <= 2.5 %) DESIGN SUCCEED Page 5 of 17 . VERIFICATION EEG CABLE NO.: F-EMCC-MECHDEWAT : : : EMCC-MECHDEWAT 200 m Ib = Max. Dem. KW 3 x kV x p.f. 63 A 1.25 Nearest Nominal , In= Max.Thermal Current, I2= ELSWEDY According to IEE, IEC 114 route/type DUCT XLPE CU MDB Design Current , Proj.No. load GEN 0.380 kV 24 KVA 0.8 p.f. = 1600 6 kVA 40.52 kA . % Imped. 36.08 A TO IEC STANDARD. x AT 36 A 100 AF 45 = frame trip . BREAKER SIZING C.F. CABLES installation 30 0.80 120 3 0.3m flat 9 1 H tray touching no. of cables 3 installation 0.25m DUCT Temp. Correction Factor,C.F.= REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET Installation condition Ground Temp x Burial Depth x Cable Group = 0.857 = 0.85748 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = It 120 42 120 use 36 0.857 = 42 for S = = 35 mm2 1 // cables x 35 120 A ( catalog ccc ) CCC x C.F = LAID IN DUCT no. of trays S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = Sending End + Cable 103 A ------>> R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That spacing : formation no. of cables S.C.C. Derated Ampacity , Iz= A LAID IN AIR A burial depth 5.42 116.51 121.92 1.8 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) I2 <= 45 <= 1.45 Iz , or , 149 SUCCEED . CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = x 1.009 1 = 7.282 V = 1.916 % 2- Accumulated V.D. : + Acc V.D.= V.D.1 = 1.916 + = 2.304 % 36.08 x 200 V.D. on upstream cable 0.388 % (Should be <= 2.5 %) DESIGN SUCCEED Page 6 of 17 . VERIFICATION EEG CABLE NO.: F-EMCC-01 : : : Design Current , According to IEE, IEC 114 route/type DUCT XLPE CU MDB EMCC-01 165 Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET m load 0.380 kV 38 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 80 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 1600 6 kVA 40.52 kA . % Imped. 58 TO IEC STANDARD. AT 58 A 100 AF 72 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.857 = 0.85748 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = It 145 67 145 use 58 0.86 = 67 no. of cables 2 for S = 50 mm 1 // cables x 50 145 A ( catalog ccc ) = S.C.C. Derated Ampacity , Iz= CCC x C.F = 124 I2 no. of trays installation LAID IN DUCT 3 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable A ------>> <= 72 <= 30 0.80 120 3 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That A spacing : formation LAID IN AIR A burial depth 5.42 72.78 78.20 2.8 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 180 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 0.764 x 57.7 x 165 1 = 7.278 V = 1.915 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 1.915 + 0.39 % = 2.303 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 7 of 17 . VERIFICATION EEG CABLE NO.: F-EMCC-CHLORINE : : : MDB EMCC-CHLORINE 70 m Design Current , Ib = Proj.No. According to IEE, IEC 114 Max. Dem. KW 3 x kV x p.f. 63 A 1.25 x Nearest Nominal , In= Max.Thermal Current, I2= ELSWEDY CABLES REV-A Multi-core conductor,Low Voltage,Power cable route/type DUCT XLPE CU destination From To Length CABLE / BREAKER SIZING SHEET load GEN 0.380 kV 32 KVA 0.8 p.f. = 1600 6 kVA 40.52 kA . % Imped. 48 TO IEC STANDARD. AT 48 A 100 AF 61 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.737 = 0.7372 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = 48 0.74 66 no. of cables A 66 75 for S = = 2 16 mm // cables x 16 A ( catalog ccc ) 1 75 S.C.C. Derated Ampacity , Iz= 55 installation LAID IN DUCT A 4 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = ------>> 40 0.80 120 4 0.3m flat 9 1 H tray touching no. of cables + Cable R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That no. of trays Sending End CCC x C.F = A spacing : formation LAID IN AIR It 75 use = burial depth 5.42 85.56 90.97 2.4 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) I2 <= 61 <= 1.45 Iz , or , 80 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 2.117 x 48.4 x 70 1 = 7.177 V = 1.889 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 1.889 + 0.39 % = 2.276 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 8 of 17 . VERIFICATION EEG CABLE NO.: F-EMCC-CHEMICAL : : : Design Current , m Ib = Max. Dem. KW 3 x kV x p.f. 63 A 1.25 Nearest Nominal , In= Max.Thermal Current, I2= ELSWEDY According to IEE, IEC 114 route/type DUCT XLPE CU MDB EMCC-CHEMICAL 80 Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET load GEN 0.380 kV 28 KVA 0.8 p.f. = 1600 6 kVA 40.52 kA . % Imped. 43 TO IEC STANDARD. x AT 43 A 100 AF 53 = frame trip . BREAKER SIZING C.F. CABLES DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.807 = 0.80704 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib = C.F. ccc >= ccc = Select Cable Size: 43 0.81 = 53 A no. of cables for S = 53 75 1 = 75 S.C.C. CCC x C.F = 16 mm2 // cables x 16 A ( catalog ccc ) Sending End + Cable 61 A ------>> Receiving End no. of trays installation LAID IN DUCT 30 0.80 120 4 0.3m flat 9 1 H tray touching no. of cables 4 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = R.E.Imped.(in milli Ohms) = R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That spacing : formation It use Derated Ampacity , Iz= A LAID IN AIR 75 burial depth 5.42 97.78 103.20 2.1 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) I2 <= 53 <= 1.45 Iz , or , 88 SUCCEED . CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 2.117 x 1 = 7.237 V = 1.904 % 2- Accumulated V.D. : + Acc V.D.= V.D.1 = 1.904 + = 2.292 % 42.7 x 80 V.D. on upstream cable 0.39 % (Should be <= 2.5 %) DESIGN SUCCEED Page 9 of 17 . VERIFICATION EEG EEG CABLE NO.: F-DB-ADM : : : Design Current , According to IEE, IEC 114 route/type DUCT XLPE CU MDB DB-ADM 125 Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET m load 0.380 kV 31 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 63 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 1600 6 kVA 40.52 kA . % Imped. 47 TO IEC STANDARD. AT 47 A 100 AF 59 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.737 = 0.7372 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = It 102 64 102 use 47 0.74 = 64 no. of cables for S = = CCC x C.F = 75 2 25 mm 1 // cables x 25 102 A ( catalog ccc ) S.C.C. Derated Ampacity , Iz= I2 no. of trays installation LAID IN DUCT 4 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable A ------>> <= 59 <= 40 0.80 120 4 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That A spacing : formation LAID IN AIR A burial depth 5.42 98.87 104.29 2.1 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 109 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 1.370 x 47.5 x 125 1 = 8.131 V = 2.140 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 2.140 + 0.39 % = 2.527 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 10 of 17 . VERIFICATION EEG CABLE NO.: F-DB-GAURD : : : According to IEE, IEC 114 route/type DUCT XLPE CU MDB DB-GAURD 100 m Design Current , Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET load 0.380 kV 5 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 32 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 1600 6 kVA 40.52 kA . % Imped. 8 TO IEC STANDARD. AT 8 A 100 AF 9 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.783 = 0.783275 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = 8 0.78 10 no. of cables A 10 45 for S = = 2 1 45 S.C.C. Derated Ampacity , Iz= CCC x C.F = 35 6 mm // cables x 6 A ( catalog ccc ) I2 no. of trays installation LAID IN DUCT 3 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable A ------>> 40 0.80 120 3 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That A spacing : formation LAID IN AIR It 45 use = burial depth 5.42 319.51 324.92 0.7 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) <= 9 <= 1.45 Iz , or , 51 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 5.534 x 7.6 x 100 1 = 4.204 V = 1.106 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 1.106 + 0.39 % = 1.494 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 11 of 17 . VERIFICATION EEG CABLE NO.: F-DB-GEN : : : Design Current , According to IEE, IEC 114 route/type DUCT XLPE CU MDB DB-GEN 30 Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET m load 0.380 kV 13 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 32 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 1600 6 kVA 40.52 kA . % Imped. 19 TO IEC STANDARD. AT 19 A 100 AF 24 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.829 = 0.82935 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = 19 0.83 23 no. of cables A 23 45 for S = = 2 1 45 S.C.C. Derated Ampacity , Iz= CCC x C.F = 37 6 mm // cables x 6 A ( catalog ccc ) I2 no. of trays installation LAID IN DUCT 2 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable A ------>> <= 24 <= 40 0.80 120 2 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That A spacing : formation LAID IN AIR It 45 use = burial depth 5.42 95.85 101.27 2.2 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 54 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 5.534 x 19 x 30 1 = 3.153 V = 0.830 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 0.830 + 0.39 % = 1.218 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 12 of 17 . VERIFICATION EEG CABLE NO.: F-DB-LV : : : Design Current , According to IEE, IEC 114 route/type DUCT XLPE CU MDB DB-LV 30 Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET m load 0.380 kV 13 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 32 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 1600 6 kVA 40.52 kA . % Imped. 19 TO IEC STANDARD. AT 19 A 100 AF 24 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.829 = 0.82935 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = 19 0.83 23 no. of cables A 23 45 for S = = 2 1 45 S.C.C. Derated Ampacity , Iz= CCC x C.F = 37 6 mm // cables x 6 A ( catalog ccc ) I2 no. of trays installation LAID IN DUCT 2 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable A ------>> <= 24 <= 40 0.80 120 2 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That A spacing : formation LAID IN AIR It 45 use = burial depth 5.42 95.85 101.27 2.2 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 54 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 5.534 x 19 x 30 1 = 3.153 V = 0.830 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 0.830 + 0.39 % = 1.218 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 13 of 17 . VERIFICATION EEG CABLE NO.: F-DB-SITE : : : Design Current , According to IEE, IEC 114 route/type DUCT XLPE CU MDB DB-SITE 100 Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET m load 0.380 kV 25 KVA 0.8 p.f. Ib = Max. Dem. KW 3 x kV x p.f. Nearest Nominal , In= 63 A Max.Thermal Current, I2= 1.25 x ELSWEDY CABLES GEN = 1600 6 kVA 40.52 kA . % Imped. 38 TO IEC STANDARD. AT 38 A 100 AF 47 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.829 = 0.82935 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = 38 0.83 46 no. of cables A 46 75 for S = = 2 1 75 S.C.C. Derated Ampacity , Iz= CCC x C.F = 62 16 mm // cables x 16 A ( catalog ccc ) I2 no. of trays installation LAID IN DUCT 2 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = + Cable A ------>> <= 47 <= 40 0.80 120 2 0.3m flat 9 1 H tray touching no. of cables Sending End R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That A spacing : formation LAID IN AIR It 75 use = burial depth 5.42 122.23 127.64 1.7 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1.45 Iz , or , 90 SUCCEED CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 2.117 x 38 x 100 1 = 8.041 V = 2.116 % 2- Accumulated V.D. : Acc V.D.= V.D.1 + V.D. on upstream cable = 2.116 + 0.39 % = 2.504 % (Should be <= . 2.5 %) DESIGN SUCCEED Page 14 of 17 . VERIFICATION EEG CABLE NO.: F-RAW WATER PUMP : : : EMCC-RAW Ib = Max. Dem. KW 3 x kV x p.f. 160 A 1.25 Nearest Nominal , In= Max.Thermal Current, I2= ELSWEDY According to IEE, IEC 114 route/type DUCT XLPE CU RAW WATER PUMP 50 m Design Current , Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET load GEN 0.380 kV 103 KVA 0.8 p.f. = 1600 6 kVA 40.52 kA . % Imped. 156 TO IEC STANDARD. x AT 156 A 250 AF 195 = frame trip . BREAKER SIZING C.F. CABLES DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.821 = 0.8208 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib = C.F. ccc >= ccc = Select Cable Size: 156 0.82 = 190 use A no. of cables for S = = 120 mm2 1 // cables x 120 245 A ( catalog ccc ) CCC x C.F = Sending End + Cable 201 A ------>> Receiving End no. of trays installation LAID IN DUCT 40 0.80 120 2 0.3m flat 9 1 H tray touching no. of cables 2 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = R.E.Imped.(in milli Ohms) = R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 1- That spacing : formation LAID IN AIR S.C.C. Derated Ampacity , Iz= A It 245 190 245 burial depth 5.42 10.02 15.43 14.2 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) I2 <= 195 <= 1.45 Iz , or , 292 SUCCEED . CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 0.347 x 1 = 2.702 V = 0.711 % 2- Accumulated V.D. : + Acc V.D.= V.D.1 = 0.711 + = 3.213 % 156 x 50 V.D. on upstream cable 2.5 % (Should be <= 5 %) DESIGN SUCCEED Page 15 of 17 . VERIFICATION EEG CABLE NO.: : : : Proj.No. According to IEE, IEC 114 F-TREATED WATER PUMPS route/type DUCT XLPE CU EMCC-TREAT-P TREATED WATER PUMPS 50 m Design Current , Ib = Max. Dem. KW 3 x kV x p.f. 630 1.25 Nearest Nominal , In= Max.Thermal Current, I2= ELSWEDY CABLES load GEN 0.380 kV 336 KVA 0.8 p.f. = 1600 6 kVA 40.52 kA . % Imped. 511 TO IEC STANDARD. A x AT 511 A 800 AF 639 = frame trip . BREAKER SIZING C.F. DUCT Temp. Correction Factor,C.F.= REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET Installation condition Ground Temp x Burial Depth x Cable Group = 0.821 = 0.8208 soil thermal no. of cables LAID IN GROND target Ampacity, It = Ib C.F. ccc >= ccc = Select Cable Size: = 511 0.821 It 365 622 365 use = 622 no. of cables for S = = CCC x C.F = 2 240 mm 2 // cables x 240 730 A ( catalog ccc ) S.C.C. Derated Ampacity , Iz= A spacing : formation LAID IN AIR A burial depth no. of trays installation LAID IN DUCT no. of cables 2 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = Receiving End R.E.Imped.(in milli Ohms) = Sending End + Cable 599 A ------>> R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 40 0.80 120 2 0.3m flat 9 1 H tray touching 5.42 3.06 8.47 25.9 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1- That I2 <= 639 <= 1.45 Iz , or , 869 SUCCEED . CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = x 0.212 2 2.708 V 0.713 % = = 2- Accumulated V.D. : Acc V.D.= V.D.1 = 0.713 = 3.225 + + % 510.9 x 50 V.D. on upstream cable 2.512 % (Should be <= 5 %) DESIGN SUCCEED Page 16 of 17 . VERIFICATION EEG CABLE NO.: F-AIR COMPRESSOR : : : Design Current , Ib = Nearest Nominal , In= Max.Thermal Current, I2= ELSWEDY According to IEE, IEC 114 route/type DUCT XLPE CU EMCC-TREAT-UNIT AIR COMPRESSOR 50 Proj.No. REV-A Multi-core conductor,Low Voltage,Power cable destination From To Length CABLE / BREAKER SIZING SHEET m Max. Dem. KW 3 x kV x p.f. 63 A 1.25 x load GEN 0.380 kV 23 KVA 0.8 p.f. = 1600 6 kVA 40.52 kA . % Imped. 35 TO IEC STANDARD. AT 35 A 100 AF 44 = frame trip . BREAKER SIZING C.F. CABLES DUCT Temp. Correction Factor,C.F.= Installation condition Ground Temp x Burial Depth x Cable Group = 0.829 = 0.8294 soil thermal no. of cables LAID IN GROND target Ampacity, It = Select Cable Size: Ib = 35 0.83 C.F. ccc >= It ccc = 75 use = 42 for S = 42 75 = 1 75 CCC x C.F = 62 A spacing : formation no. of cables S.C.C. Derated Ampacity , Iz= A LAID IN AIR A burial depth 16 mm2 // cables x 16 A ( catalog ccc ) Sending End + Cable ------>> Receiving End no. of trays installation LAID IN DUCT no. of cables 2 installation 0.25m S.E.Imped.(in milli Ohms) = Cab.Imped.(in milli Ohms) = R.E.Imped.(in milli Ohms) = R.E.Symm.Fault (in kA) = CHECK PROTECTION CRITERIA : 40 0.80 120 2 0.3m flat 9 1 H tray touching 5.42 61.11 66.53 3.3 (=kV*1000/sqrt(3)*R.E.Imped.milli Ohms) 1- That I2 <= 44 <= 1.45 Iz , or , 90 SUCCEED . CHECK VOLTAGE DROP CRITERIA : 1- Individual V.D. : V.D.1 = mV/A/m / # cables x Ib x L = 2.117 x 1 = 3.719 V = 0.979 % 2- Accumulated V.D. : + Acc V.D.= V.D.1 = 0.979 + = 3.274 % 35.1 x 50 V.D. on upstream cable 2.3 % (Should be <= 5 %) DESIGN SUCCEED Page 17 of 17 . VERIFICATION