CE 3221 Construction Technology & Methods Lecture 1 Construction project worksite Planning Site Layout Site Layout and Temporary works, verification of boundaries Site information board, Emergency telephone numbers Fencing, hoarding for the protection of the general public to act as sound and dust screens and to aid security arrangements at the site, Flooding possibilities and Drainage of the site. Ground water table Underground Service lines Adjacent Buildings 2 The Site Office and Access The site office would provide space for administration and for staff welfare. Facilities for first aid and fire fighting equipment, with trained personnel. Temporary water, electricity and sewerage connections. Proper access for the delivery of materials 3 Site Services The diversion of any existing services such as sewer lines, water, gas, power, telephone and drainage lines. Obtaining temporary power, water telephone etc. Disturbance to neighbors etc must be minimized. Determination of manholes to connect up temporary toilet effluent etc. Site Yard Locating yards for rebar bending , Yard for the fabrication of formwork Site welding & fabrication Site maintenance workshop for repairs, servicing Setting up site batching plants etc Location for a tower crane. Access and maneuverability for any mobile crane Scaffolding 4 5 6 Site Storage Bulk materials and storage of materials vulnerable on exposure to elements of nature Timber should be stored under cover and should be stacked such that there is adequate air flow Reinforcement should be stacked off the ground on a hard standing area Combustible material should be identified and stored separately Flammable material should be stored in steel drums and should be isolated from combustible materials Storage of oxy acetylene cylinders 7 Equipment & Tools Safety equipment : fire extinguishers, first aid box, safety helmets, safety eye protection, ear muffs, coveralls, eyebath, Clearing the site : hand axe, long handle chopping blade, wheel barrows, 8 Setting out: Total Station, Theodoloite/level instrument, steel tapes, wire nails, hammer, pegs, nylon rope, knife, timber stakes and red and white marking tape. Plumb bob and line, set square, spirit levels. Excavation : Pickaxes, Shovels, wheel barrows, mamoties, crowbars (jimmy) , buckets, mortar pans, cane baskets, dewatering equipment, materials for planking strutting, shoring, 9 Concrete work : Timber stop boards, masons trowels, straight edge, cube or cylinder moulds, slump cone, shovels, wheel barrows, mortar pans, vibrators, chistles, hammer, Air compressor, jack hammers Formwork : Timber, Plywood, wire nails, Styrofoam, inserts, handsaws, set squares, drills, planers, cross cut saws, bench vices, “G” clamps, Rebar and steelwork : Bar benders, bar cutters, welding plant, angle grinders, files, oxy acetylene flame, hack saws, binding wire, cover blocks, chairs Plumbing : blow torch, Sand paper, PVC adhesive, Teflon thread seal tape, monkey wrench, hack saw pipe vices, 10 The Site Organization Chart The site organization chart shows the hierarchy of the site staff and shows the relationships between the site staff. The organization chart will be constructed by specialization of task and/or function. The organization chart can be used to allocate authorities and responsibilities to the staff associated with the works. 11 Board of Directors Managing Director General Manager HSE & QA Construction Mgr QS & Estimation Dept Personnel Finance & Admin Finance & Accounts Info. Sys. Officer Procurement & Stores Proj. Mgr. 1 Eng. Support Services Proj. Mgr. 2 Conc. Batch Plant & Precast Yard Fabrication Yard Plant Mtce Proj. Mgr. 3 12 13 Features of an organization chart Chain of command (Unbroken line of command : where everyone reports to someone) Each person in the chain of command should have only one direct supervisor to whom he is accountable. (Unity of command ) Span of control (a supervisor has an appropriate number of direct subordinates) 14 Policy Regulations & Procedures From the organizations policies a set of procedures and regulations will be developed for the administration of the project site. This set of procedures and regulations will provide the necessary information and the guidelines for the staff and workmen to do their daily tasks. Procedures and regulations will be available for staff welfare, procurement, quality assurance, equipment maintenance, communication, safety etc. . 15 Regulations, Procedures & Work Instructions For instance the worksite procedures pertaining to safety may require that each supervisor/foreman conducts a daily safety briefing with their workmen prior to commencing work. This safety briefing will discuss the possible hazards that will have to be faced during the course of the work and the steps to be taken to safeguard against these hazards. The set of regulations will specify the disciplinary measures that will be enforced in the event of non compliance. Prohibition of alcohol consumption during working hours. A procedure will comprise of a set of work instructions. 16 Communication Communication within members of the site organization and with all external parties associated with the project is an important aspect in construction management. Communication is a two way process by which information is transmitted by the disseminator and is received and understood by the recipient. Communication can take place via different media such as vocal media, paper telephone etc. 17 Decision Making Managing construction work will require a number of decisions to be taken throughout the construction phase. Decision making will be relevant to every level in the organizational structure. The type and the nature of decisions will be different at different levels of the organizational structure. 18 For example the decision making that will confront the project engineer will be different to the decisions that will have to be taken by the plant and equipment foreman. Most often decisions require a choice to be made between two or more alternatives. Whilst a prudent decision will be beneficial to the project an unwise decision will be detrimental to the overall project. 19 Meetings Meetings are the common method used in a worksite to collectively discuss the construction work. The consultant/client may initiate a weekly or a fortnightly meeting to discuss the progress and other matters directly related to the construction work. In addition to the meetings that are organised by the client/consultant the project engineer may arrange for more frequent meetings with his site staff in order to co-ordinate and execute the work activities. One of the main areas for discussion will be the sharing of resources such that it will give the best benefit for the project. 20 A typical agenda for a site meeting The progress of work: Material procurement and material quality assurance Labour; If adequate skilled and unskilled workmen are available Plant ; If adequate plant with proper certification and with competent operators is available Health, Safety and Environment issues Quality issues Site instructions, change orders and variations Progress payment certificates Nominated sub contractors Financial cash flows 21 Planning & Monitoring at the work site Planning is the determining in advance of what is to be done to execute the project within the required time and to the specified quality. Planning is essential as tasks have become more complex and lengthy. Planning of the construction work is a continuous ongoing process. The plans will require constant adjustment to accommodate delays, construction constraints and other contingency requirements. 22 Control and reporting Control measures are necessary to ensure that the project objectives are realized throughout the construction phase. The first step in establishing controls is to communicate the specific targets and goals that have to be achieved. Once every officer is aware of these targets, then they would be expected to perform to these targets. 23 Controlling would involve the periodic and systematic assessment of performance against the set targets. Any under achievement will be apparent early enough to take steps towards its rectification. The most common methods of enforcing controls are to set up a system of report generation, and their evaluation 24 Project Planning Planning is essential for all projects no matter how small they are. Planning is to study the project and analyze its resources requirements in terms of: 1) Time 2) Materials 3) Money 4) Men 5) Machines Planning is to arrange in a logical order and to sequence the operations in a manner that gives the best results in terms of minimizing the consumption of the above five resources. 25 Project Scheduling Project Scheduling deals with the breakdown of the project into identifiable activities, (WBS) ascertaining the requirements of time and resources for the completion of the activities and identifying the relationships between the activities. Project scheduling will enable the various resources such as finance, materials, equipment and personnel to be optimally deployed within the planned time framework. 26 Scheduling will integrate the estimated duration’s of all the activities and highlight the critical activities. It will determine the logical and technological precedence in the performance of the activities and emphasize the constraints that may be imposed by the availability of resources 27 Planning & scheduling can be divided into the following steps: 1) Collect information about the Job, ‘The Project’. This information is available from the drawings, the specifications, the site, the Bill of Quantities, productivity of men and machines, etc. 2) Breakdown the Job into small tasks. (These are called activities). 28 3) Select the most appropriate method of doing each task (Activity) and allocate the most likely time that the activity will require for completion. 4) Define the precedence relation between tasks. For each task you ask the question which task must be completed before this task can start? The word ‘must’ is used for physical or dependence logic such as the roof can not start unless the walls or columns under it are completed”. 29 The Bar Chart/ Gantt Chart A bar chart or Gantt chart is the most common scheduling tool used for the planning of a project. This is a graphical time scaled representation of the project. The project is first broken down into discrete identifiable activities. The relationships between the activities are then identified so that a sequence of activities can be established. The time duration’s for each of the activities are then estimated together with the resources required to complete the activities. Each activity is represented by a horizontal BAR. The length of the bar is scaled proportional to its duration. 30 Preparing a bar chart Breakdown project into activities. Estimate durations Establish relationships between activities (dependencies) Decide sequence and logic. Determine any overlaps, lags, simultaneous starts. Draw bars (activities) on the time scale in the appropriate order that they will be carried and on the basis of their earliest starts. Observe that some activities may have floats 31 Time Spans of Plans Monthly or weekly short term plans are usually prepared based on the overall Gantt chart. From these short term plans the tasks necessary to complete the activities are delegated appropriately to each member of the site organization For the proper execution of the work it is imperative that each person in the site organization is made aware of his exact tasks. To fulfill his tasks the requisite resources should be made available and he should be delegated with the authority necessary to execute the work. 32 Hierarchy of Plans Work plans will have hierarchies. This means that every work group understands its specific goals. Achieving this will depend on how well the objectives and goals have been defined and delegated. For instance the project engineer will have to plan for the proper execution of the entire project. The plant and equipment foreman will concentrate mainly on the planning in relation to plant requirements, maintenance and deployment as well as arranging for competent operators. The site safety officer will concentrate on safety planning for the entire project. 33 Delegation of work activities Once the work activities have been identified responsibilities in executing the work is delegated based on the organization chart. Delegation completeness : Every necessary task is assigned Delegation sufficiency : Each person should be delegated sufficient authority to meet his responsibility. Non-delegateable responsibility : No one can relieve himself of responsibility by delegating his authority downwards. 34 Materials Scheduling A listing of all the materials required for a project has to be ascertained and scheduled during the planning stages of the project. Suppliers should be prequalified and selected well ahead of the commencement of the work. The selection of the suppliers should be based on price, their ability to supply to a schedule and the quality of their supplies. 35 Once the suppliers have been selected they should be informed of the material delivery schedule so that they too can plan out their strategies for supply. Prior to placing any orders samples of materials should be tested for conformance to the specifications and approval obtained from the consultants. Procurement orders should be placed such that there is adequate time for the materials to be supplied to the worksite for incorporation in the work. Similarly materials should not be ordered very much ahead so that they will just be taking up storage space and also lead to possibilities of spoilage and wastage. 36 Maintaining Records Maintaining proper records is extremely important as construction work at times lead to various disputes. Most of these disputes could be eliminated by maintaining proper records. It is good practice to request each site officer to maintain a diary in which the daily activities are recorded. This will enable a review of the daily activities to be made and if it so requires a proper record initiated. 37 Quality Assurance Most contracts may require a quality plan to be made by the contractor prior to the commencement of the construction work. The purpose of the quality plan is to ensure that the work is carried out in accordance to the work specifications. The quality plan will incorporate procedures to ensure that the materials and workmanship conforms to the requirements 38 Method Statements A method statement is a document that describes how to do a task safely with the optimum utilization of resources. A method statement is a set of instructions or a plan for the work. It describes in a logical sequence exactly how a job is to be carried out in a safe manner and without risks to health. It includes all the risks identified in the risk assessment and the measures needed to control those risks. This allows the job to be properly planned and resourced. Whilst procedures and site instructions are more generic method statements are more specific. 39 The contents of a method statement will vary with the work, however, it may contain: Details of the individual responsible for the activity. A description of the activity. A description of how the work will be managed. The location of the activity, its boundaries, means of access and how it is segregated from other activities. Plant and equipment required. The procedure for changing the proposed method of work if necessary. 40 A step by step description of the activities to be undertaken. Precautions necessary to protect workers, and other people that could be affected, including personal protective equipment and ventilation requirements. Training procedures if required . The need for specially-trained operators for certain activities. Emergency procedures, including the location of emergency equipment. The handling and storage of materials and pollution prevention procedures. Temporary works designs. The method for safeguarding existing structures. 41 Setting out is the process of developing the physical positions of the grid lines and corners of a building and is done by transferring dimensions form the layout plan to the ground. The setting out clearly defines the center lines, excavation outlines and enables construction to be carried out according to the plans During the design process when drawings are prepared a plan providing the setting out details is prepared. During the setting out process a datum level is also established 42