Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 1.0 INTRODUCTION ......................................................................................................... 3 2.0 APPLICABLE STANDARDS AND PROCEDURES ..................................................... 4 2.1 2.2 2.3 2.4 3.0 STRESS ANALYSIS.................................................................................................... 5 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 4.0 Document Precedence .................................................................................... 4 Industry Codes or Regulations ......................................................................... 4 Project Specifications ....................................................................................... 5 Definition of Terms ........................................................................................... 5 Methodology for Pipe Stress Analysis .............................................................. 5 Design Consideration ....................................................................................... 6 The Selection of Stress Critical Lines ............................................................... 12 Non-Critical Lines............................................................................................. 14 Stress Analysis Documentation........................................................................ 14 Pipe Stress Design Philosophy ........................................................................ 14 Caeser CFG (Configuration File) and Unit file .................................................. 16 Attachments ..................................................................................................... 16 PIPE SUPPORTS ....................................................................................................... 16 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 Intent................................................................................................................ 16 Guidelines for all Supports ............................................................................... 16 Interface Requirements with Civil Department ................................................. 16 General Design Requirements ......................................................................... 17 Materials of Construction / Standards .............................................................. 19 Pipe Shoes, Cradles and Attachments ............................................................. 19 Spring Supports ............................................................................................... 21 Sleepers and Grade Piers for Supports............................................................ 22 Page 2 of 29 Reliance Industries Limited RIL - OT KGD6 1.0 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 INTRODUCTION Reliance Industries, Ltd. (RIL) is receiving gas from the Block known as Block KG-DWN98/3 (normally referred to as Block KG-D6) which is located in the Krishna Godavari Basin, Bay of Bengal off the East coast of India. The gas field area expands over 7500 km2 and is located 40km and 60 km south east of Kakinada. The Gas Field lies in water depths ranging between 400 meters in the northwest and over 2,700 meters in the southeast. RIL is producing gas from two discoveries, D1 and D3. Production from subsea wells is transported to the Deep Water Pipeline End Manifold (DWPLEM) via subsea manifolds. Two 24” deep water pipelines deliver the well fluids from the DWPLEM to the Control Riser Platform (CRP) located in 100 meter water depth. The CRP serves as a hub for receiving production from the current phase of development and future gas fields. RIL is also operating the D26 (also known as the MA field) where oil and associated gas is produced from a FPSO. The associated gas produced at FPSO is compressed, dehydrated and then transported to the CRP via one 24” pipeline. The piping distribution arrangement on CRP allows transporting of MA gas either after comingling with D1/D3 gas or independently to the OT. Three 24” shallow water / on land pipelines transport the gas from the CRP to the OT. Gas conditioning facilities have been installed at OT to meet the gas sales specification. The OT is situated near Gadimoga village in Taliarevu Mandal, about 30 Km south of Kakinada in East Godavari district, Andhra Pradesh, India. The D1/D3 field operations are controlled and monitored from the CCR located in the OT. The associated gas from the MA field has heavy hydrocarbon fractions which are recovered as condensate at the OT Slug Catcher. Dedicated condensate stabilization, storage and truck loading facilities are installed at the OT. The gas conditioned in OT is metered and delivered to RGTIL for onward transportation to the consumers through on land cross country East/West pipelines (EWPL). Multiple pipeline compressor stations have been built along the EWPL to boost the gas pressure. The first compressor station (CS-01) is located next to OT boundary and immediately downstream of the custody transfer metering facility at OT. The compressor stations including CS-01 are operated by RGTIL. However, CS-01 is connected with plant DCS system which gets information about the critical operating conditions of the CS-01 and pipeline. The main processing facilities and utility systems at OT are designed for continuous sales gas production rates of 80 MMSCMD. MA gas and condensate facilities are designed for a continuous rate of 9 MMSCMD of MA export gas and 30m3/hr of unstabilized condensate feed. Currently D1/D3 gas is being transported to the OT through two pipelines (GTL-1 and GTL-2), while the third pipeline (GTL-3) is dedicated for transporting dry gas from the FPSO of MA field. There are three pressure reducing stations (PRS) upstream of the slug catcher to protect the OT from high pressures. There are three slug catchers which are designed for 45 MMSCMD. The slug catchers separate the rich MEG from the gas and to catch the liquid slugs generated during production ramp up. D1/D3 gas is being processed in slug catcher 1 and 2 while slug catcher 3 is used for MA gas. Page 3 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Tie-in points have been left at all of the required locations to allow for additional modules to be added on later date as required. Also suitable space has been allowed on the plot plan and equipment layout to install future modules. As the reservoir pressure depletes, gas compression is required to deliver the gas at specified suction pressure & temperature to CS-01 compression facility. Considering the long cycle time for installing such facility, and long delivery of critical equipment like gas compressors, RIL intends to start work on the requirements at the earliest so that facilities can be designed and installed in a timely manner. In addition, RIL intends to develop other gas discoveries such as R-Cluster and Satellites; and commence work for integration of these discoveries with the existing facilities at OT. 2.0 APPLICABLE STANDARDS AND PROCEDURES 2.1 Document Precedence Any conflicts between requirements of this specification, related contract documents, datasheets, international standards, code of practice and the contract shall be referred to the Company for clarification. Where conflicts occurs the order of precedence shall be, unless otherwise agreed: a) b) c) d) e) f) Local Regulatory and Statutory requirements Datasheets (where applicable) and relevant drawings This Specification Project Specifications Indian Codes and Standards International Codes and Standards Within each category above, the most stringent requirement shall apply. 2.2 Industry Codes or Regulations American Petroleum Institute (API) API 610 Centrifugal Pumps for General Refinery Services API 616 Gas Turbine for Petroleum, Chemical & Gas Industry services API 617 Centrifugal Compressors for General refinery services API 660 Shell and Tube Heat Exchangers for General Refinery Services API 661 Air-Cooled Heat Exchangers for General Services API 674 Positive Displacement - Reciprocating Pumps American Society of Mechanical Engineers (ASME) ASME B 31.3 Process Piping 2008 ASME B 31.8 Gas Transmission and Distribution Piping Systems 2007 (Rev. Nov 30, 2007) ASME B16.5 Steel Pipe Flanges and Flanged Fittings ASME B16.47 Large Diameter Steel Flanges ASME Boiler & Pressure Vessel Code Section II Ferrous and Non-ferrous Material Specifications Section IX Welding and Brazing Qualifications ASME Sec.VIII, Div.I Boiler and Pressure Vessel Code UKOOA - United Kingdom Offshore Operators Association (GRE U/G Piping) Page 4 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Welding Research Council WRC Bulletin No.107 Local Stresses in Spherical and Cylindrical Shell due to external loading WRC Bulletin No. 297 Local Stresses in Cylindrical Shell due to external loading 2.3 Project Specifications All drawing numbers are prefaced by (2001-KGD6-D2-PF-ON-). OTBC-B00-31070484-MES-0702 OTBC-B00-31070484-MES-0721 OTBC-B00-31070484-MES-0718 OTBC-B00-31070484-MES-0722 OTBC-B00-31070484-MES-0723 OTBC-B00-31070484-PPL-0701 OTBC-B00-31070484-PPL-0702 OTBC-B00-31070484-PPS-0703 OTBC-B00-31070484-PPS-0706 OTBC-B00-31070484-PPS-0707 OTBC-B00-31070484-PPS-0708 OTBC-B00-31070484-CIL-0001 OTBC-B00-31070484-PRS-0724 OTMO-B00-31070484-MES-0707 OTMO-B00-31070484-MES-0708 OTMO-B00-31070484-MES-0710 2.4 3.0 Specification for Pressure Vessels Specification for Centrifugal Compressor API 617 Addendum Specification for Air Cooled Heat Exchangers Specification for Gas Turbine API 616 Addendum Specification for Gas Turbine Driven Compressor Package Piping Design Basis Piping Material Specification Piping Standard Details Standard Pipe Support Technical Specification for Pipe Supports Technical Specification for Packaged Equipment Piping Civil / Structural Design Basis General Site & Utility Data and Units of Measurement Specification for Shell and Tube Heat Exchangers Specification for API 610 Centrifugal Pumps Specification for API 674 Reciprocating Pumps Definition of Terms Buyer Reliance Industries Limited (RIL) Seller Party responsible for manufacturing or supplying of equipment and/or goods and/or materials and/or services. STRESS ANALYSIS 3.1 Methodology for Pipe Stress Analysis Stress Analysis of lines shall be called out to demonstrate conformance with the engineering requirements of the piping design code (ASME B31.3 / B31.8 wherever applicable), including both pressure containment and flexibility analysis. The flexibility analysis of lines for formal comprehensive analysis shall be done using the 5.20 version of CAESAR II. Page 5 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 3.2 Design Consideration 3.2.1 Design Code ASME B31.3 - Shall be followed for stress qualification for all the lines except for *6 LB & 15 LB Pipe Spec. ASME B31.8 - Shall be followed for stress qualification of 6 LB & 15 LB Pipe Spec. 3.2.2 Ambient Temperature The ambient minimum and maximum temperatures for design purposes shall be taken as stated in the “General Site & Utility Data and Units of Measurement” specification. As per referenced specification, Table 3.1-2: Maximum Ambient Temp = 45 ºC Minimum Ambient Temp = 16.6 ºC Consider Reference Installation temperature as 16.6 ºC for pipe stress analysis. 3.2.3 Design Temperature Design Temperature (Maximum / Minimum), as specified in line list, shall be used for calculation, except for Part B. The following parameters shall be checked / qualified at Design Temperature: Thermal Stress (Expansion Stress) Pipe Support Load Thermal Displacement Static Equipment Nozzle loads 3.2.4 Operating Temperature Operating temperature, as specified in line list, shall be used for calculation. The following parameters shall be checked / qualified at Operating Temperature: Thermal Stress (Expansion Stress) Pipe Support Load Thermal Displacement All Equipment Nozzle loads 3.2.5 Design Pressure Design pressure as specified in line list shall be used for sustained stress qualification. 3.2.6 Steam Out Temperature Steam out condition per line list. 3.2.7 Fire Case Fire case is not applicable for this project. Page 6 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 3.2.8 Foundation Settlement Differential settlement for all equipment and piping supports on piled foundation shall be considered per the values provided by Civil/Structural Group based on calculations. At UG/AG interface connection, settlement will be considered. 3.2.9 Friction Factor The following coefficient of friction shall be used at support locations: Surface Steel to Steel PTFE to PTFE PTFE to SS Steel to Concrete Graphite to Graphite Friction Coefficient 0.3 0.08 0.1 0.5 0.15 PTFE shall be used only up to Design Temperature of 1200 ºC. For a temperature of more than 1200 ºC, graphite shall be used as an antifriction pad. 3.2.10 External Loading 3.2.10.1 Wind Load Wind load analysis shall be carried out to IS 875 (Part 3 – 1987) on exposed lines as indicated below. The analysis shall include a 3-sec GUST wind velocity of 60 m/s applied at an elevation of 10 m and above from the datum level. Effect of wind shielding from other pipe work and structures can be considered as appropriate. Wind loads are to be considered as a minimum for exposed lines greater than or equal to 10” diameter, including insulation thickness. Based on Indian Standard IS: 875 (Part 3) Basic Wind Speed: Vb = 60m/s (working wind speed) Probability Factor: K1 = 1.07 for process structures Terrain Category Factor: K2 = varies as per IS: 875. classified as Terrain Category 2 Topography Factor: Site Site K3 = 1.0 Negligible Influence of Local Wind loads shall be combined with “Operating Temperature“, and the following parameters shall be checked / qualified: Occasional Stress (Sustained + Wind) Support Loads. Page 7 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 3.2.10.2 Seismic (Earthquake) Loads Seismic loads shall be analyzed by Equivalent Static Method. The earthquake load magnitude are given in terms of the “Gravitational Acceleration constant (g)”. Seismic load analysis is to be performed on all stress critical lines, seismic load analysis to be performed as per the relevant piping code. Seismic design forces shall be in accordance with IS 1893, with a zone factor of Z = 0.22. Values for acceleration with respect to gravity (where g = 9.8065m/s2) are to be calculated using the parameters defined by the Civil / Structural Design Basis document. Refer to Annexure A for the Gravitational Acceleration factor (g). To determine loads on pipes, the following parameters shall be adopted based on the type of superstructure that supports the pipe. Importance Factor I = 1.75 Response reduction factor: R = 4.0 – for pipe work on structural steel R = 5.0 – for pipe work on RCC structures Spectral acceleration coefficient Sa / g = 2.5 corrected for: 2% damping – for pipe work on structural steel 5% damping – for pipe work on RCC structure The Gravitational acceleration factor (g) for all the pipes on concrete structure shall be based on the factors defined for RCC structure. For all the remaining piping, the “g” factor shall be based on structural steel factor. Seismic (earthquake) loads shall be combined with “Design Temperature“, and following parameters shall be checked / qualified: Occasional Stress (Sustained + Seismic) Support Loads 3.2.10.3 PSV Discharge Force Loading caused on piping due to safety valve discharge forces shall be included in the pipe stress analysis and supports shall be located and designed accordingly. The PSV discharge reaction force shall be calculated per APIRP520. For the PSV‟s discharging to atmosphere (open system) it is recommended that maximum dynamic load factor (DLF) of 2.0 to be multiplied to static reaction force. Page 8 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 PSV‟s relieving under steady state flow condition into a closed system do not transfer large forces and bending moment as that of Open system. However, at the point of sudden expansion in discharge piping, there will be inlet piping reaction force. To avoid any vibration to the piping system due to sudden expansion, the piping shall be properly restrained. To calculate the reaction force for closed system, it is recommended that a maximum dynamic load factor (DLF) of 1.25 be multiplied to static reaction force. The PSV reaction force shall be analyzed as “occasional load”. Two occasional loads should not be considered as acting concurrently. Two-phase flow lines subject to slugging: Slug flow is a condition of bolus liquid flow. Such a flow may be created by a sudden flow of high velocity gas over the surface of a slowly moving fluid in pipe. This produces a liquid wave which can become a slug if it crests at the top of the pipe. The impact of this slug generates tremendous force when exerted on the elbow. The magnitude of the impact force depends on the velocity and density of the slug. The slug force shall be analyzed considering as static force with dynamic load factor (DLF) of 2.0. The slug force shall be combined with operating temperature and analyzed as an “occasional” case. Flow-induced vibration studies shall be carried out for big bore lines having large pressure drop across any valve / device. These studies will be performed by MEC (Mustang Engineering) or by external agency under supervision of MEC (Mustang Engineering). Lines requiring these studies will be identified by MEC process. Recommendations of these studies shall be taken into consideration during stress analysis and pipe support design. An acoustic-induced vibrations (AIV) study shall be carried out for blow-down and flare lines. Recommendations of AIV study shall be taken into consideration during stress analysis and pipe support design. 3.2.11 Equipment Nozzle Load The nozzle loads shall not exceed the requirements specified in the applicable industry standards for that equipment, and shall also comply with the additional equipment nozzle loads per Table 1.0. Also see design temperature and operating temperature discussion above for computing nozzle loads. For pressure vessels, the allowable nozzle loads are specified in the specification for pressure vessels, 2001-KGD6-D2-PFONOTBC-B00-31070484-MES-0702, and for Shell and Tube Heat Exchangers, within specification 2001-KGD6-D2-PF-ON-OTBC-B0031070484-MES-0707(refer to Annexure-F for allowable nozzle loads for vessels and heat exchangers). Page 9 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 Table 1.0 - Allowable Nozzle Loads Equipment Allowable Nozzle Loads Vendor Data Required Centrifugal Pumps 2 x API 610 Table II Pump type, nozzle size* Gas Turbines Packaged equipment spec for inlet and for exhaust vendor allowable to be followed Nozzle locations* Fixed point location, Average casing temperature Nozzle displacements 2 x API 617 Nozzle locations* Fixed point location, average casing temperature Nozzle displacements Vendor to advise Volume bottle nozzle size, fixed point location, nozzle flexibility values* 2 x API 661 * 2 x API 560 Nozzle displacements* Appendix P, API650 Nozzle flexibility* Centrifugal Compressors Reciprocating compressors (volume bottle nozzle sizes) Air cooled heat exchangers Furnaces / Fired Heaters Storage Tanks *Vendor to provide GA drawing and allowable nozzle loads. The situation of nozzle loads exceeding values of Annexure “F” and Table 1.0 can be resolved in either one of the following methods: Using WRC-107 or Nozzle PRO Seek approval from vendor At terminal package limit locations, the package sellers to provide full anchors and allowable terminal loads to ensure the terminal anchors are capable of withstanding the additional affects of loads from the externally connected piping as stated in the “Technical Specification for Packaged Equipment”. 3.2.12 Hydro test case A hydrotest stress qualification is to be performed using hydrotest pressure. A separate hydrotest calculation for support loads shall be performed for lines 10” NB and above where the specific gravity of the contents is ≤0.8. These loads shall also be included in the spring hanger and rod support data sheets for rod sizing. 3.2.13 Local attachments Local attachments stresses (trunnions, etc.) shall be calculated as required using approved company or project methods (e.g., “Kellogg Method”, or Page 10 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 WRC Bulletin No. 107). The attachment size and any required R Pad should be shown on the stress sketch. For packaged equipment, company procedures shall be issued to the buyer for review and acceptance. 3.2.14 Flange leakage calculation Flanges shall be reviewed to ensure leakage does not occur due to the combined effects of internal pressure and external loads. The method used can be based on the standard charts or tables, stress software (Caesar), or the total equivalent pressure method as per ASME III Division 1, NC-36581. The calculated total equivalent pressure should be compared with the maximum rated pressure as per ASME B16.5/B16.47. If these simplified methods predict that leakage could occur, then in-depth flange analysis is required to ASME VIII Div. I, Appendix II. These flange leakage checks shall be done if the following is evident: Sustained stresses If the flanged joint exceeds 50% of the code allowable stress, and/or expansion stresses at the flanged joint exceeds 60% of the code allowable stress (liberal allowable stresses shall not be used for this comparison check). 3.2.15 Liberal allowable stress Liberal allowable stress will be used per code (ASME B31.3). However, it should not be used unless it is properly justified. Wherever liberal allowable stress is used in calculation, it should be highlighted in the stress calculation report. 3.2.16 Hot sustained stress qualification (support lift up) Wherever in hot case (temperature) the pipe is lifting up from the support point, these supports shall be deleted and the piping system shall be qualified in sustained stress. If the sustained stresses are not within the limit, pipe supports shall be reviewed or spring supports shall be used to make the system safe. The stress calculation number shall be same with an extension of “lift”. 3.2.17 Full expansion range In the case of lines with design temperatures ranging from positive to negative design temperatures, the analysis shall be done as follows: e.g., T1 = + 100 C; T2 = -100 C; TINSTALLATION = 16.5 C. The load cases shall be: W+P1+T1 (OPE) W+P1+T2 (OPE) W+P1 (SUS) L1-L3 (EXP) L2-L3 (EXP) L1-L2 (EXP) Operating load case at T1 = + 100 C Operating load case at T2 = - 100 C Expansion from installation to +100 C Expansion from installation to -100 C Full expansion range (+100 C to -100 C) Page 11 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 3.2.18 Spring Support Generally the use of spring supports shall be avoided. However, if required, the spring supports shall be used to qualify the nozzle loads and stresses. The piping system subjected to vibration such as PSV discharge, 2-phase flow lines, and slug prone lines, spring supports should not be used. All-spring supports shall be programmed (C-II) designed at “Operating Temperature”. Spring shall be selected within economic operating range. The load shall be at or around 50% of the range, and also have adequate margin in travel range. Once spring is selected by program (C-II), the spring data (cold load and spring rate) shall be inputted as user defined in calculation, and then the spring variation shall be checked at design or any upset condition. In any design condition, the variation should not be more than 25%. Spring Variation = (movement x spring rate x 100) / (Hot Load) Preferred spring vendor for calculation is “Lisega”. However, after finalization of spring vendor, the stress calculations shall be updated per final vendor information. All spring supports on liquid lines shall be checked for Weight No Content (WNC) case. The equipment nozzle loads and/ or stresses in the piping system should not exceed the allowable in WNC case at installation temperature. All spring supports shall be checked for hydrotest condition, and hydrotest load shall be marked in the spring support schedule. 3.3 The Selection of Stress Critical Lines The criteria for selection of stress critical lines for comprehensive stress analysis are as follows: 1) All CS, AS, and SS lines 3” NB with a design temperature of 175 °C and above, or -46 °C and below. 2) All CS, AS, and SS lines 4” NB to 14” NB with a design temperature of 120 °C and above, or -46 °C and below. 3) All lines 16” NB and above. 4) Where SS = Stainless Steel; AS = Alloy Steel; CS = Carbon Steel 5) All high alloy and non-ferrous metallic lines. 6) All lines 2” NB and above connected to strain sensitive equipment such as pumps, compressors, turbines and glass-lined vessels. For carbon steel centrifugal and vertical in-line pump system with inlet lines 2-1/2” to 6” NB with a maximum operating temperature below 65 °C, analysis is not required. Adequate supports local to the pump nozzles must be provided to minimize weight loads imposed on the machinery. Page 12 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 7) Lines of sizes 2” NB and above connected to air-cooled heat exchangers, fired heaters, waste heat boilers and glass-lined equipment. 8) Thick walled pipe 3” NB and larger (schedule 160 pipe up to and including 24” NB or lines with a wall thickness greater than 10% of the outside diameter). 9) Thin walled pipe of 20” NB or over with a wall thickness of less than 1% of the outside diameter. 10) All pressure relief and blowdown lines 2 ”NB and larger, excluding drains. 11) All lines from relief valves, or bursting discs. For lines connected to open discharge relief valves, lines 2” NB and above (based on inlet diameter), and having a set pressure of 500 kPa and above, are required to be analyzed. Consideration is also required for closed relief systems. The short-term forces for closed systems are to be suitably designed for, including restraints, limiting vibration. A comprehensive stress calculation in these instances may be required on a case by case basis. Similar to open relief systems, only consider lines connected to closed relief valves 6” NB and above with a set pressure of 500 kPa and above. 12) All lines subjected to 2-phase slug flow, lines subjected to external mechanical vibration, or lines subjected to internal forces such as pulsation as defined on the line list. 13) Piping 3” NB and larger connected to vessels, tanks or equipment subject to differential settlement or any significant external displacement. 14) All lines covered by ASME B31.3 - Section 319.4 15) Main flare system lines. 16) Other systems that, in the opinion of the stress engineer/package seller, require special attention. 17) GRE-buried underground fire water piping (by GRE piping vendor). However, the analysis will be reviewed and approved by MEC (Mustang Engineering). 18) All lines which are being connected or tied into existing piping shall be analyzed for assessing the impact on existing supports. Analysis shall be carried out to the first anchor support, and all existing supports shall be checked for revised loads. 19) HDPE buried underground piping. 20) Any lines considered as stress critical by process to be identified on line list. 21) Piping support adequacy check for the slug force: Revised slug-induced forces shall be calculated based on the process input related to possible cases of slug flow for the revised operating envelop. Static equivalent load approach shall be followed to determine / analyze the effects of slug forces on the existing piping system. Based on the stress analysis, modifications will be proposed to maintain the stresses within allowable limits. Scope includes review of process gas piping from the pig receiver launcher through HIPPS to the slug catchers (including slug catchers). Lines Page 13 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 requiring slug flow analysis shall be identified by MEC (Mustang Engineering) process. Existing piping as a part of brownfield modification shall be analyzed for revised operating conditions to ensure that the lines are not overstressed and, if so, revised supporting shall be designed. 3.4 Non-Critical Lines All lines not included in 4.3 above will be considered as non-critical lines and adequately supported and reviewed by piping design. 3.5 Stress Analysis Documentation For all critical lines, a stress isometric shall be prepared, which shall be submitted for review. For packaged equipment, the seller is to submit a copy of the stress input (which includes assumptions, load cases, materials, and restraints), and output results (including a restraint load summary, displacement report, element forces, and a stress summary) to the buyer for review and acceptance. A soft and hard copy in this instance are both required. Stress model shall include the trunnion support. The stress sketch shall be marked clearly to show node numbering, nozzle movements, position and type of supports, large movements (>50 mm), size of dummy supports or attachments, restraint loads, details of springs or special components, and special instructions regarding installation. For all stress calculation, the following documents must be attached as a minimum: 1) 2) 3) 4) 5) Nozzle load comparison sheet (refer to Annexure – D) Caesar II Flange qualification Relevant equipment drawing All vendor data for valves, filters, strainers, etc. PDMS stress isometrics with all the information such as node numbers, type of supports, non-standard guide gaps, spring support details, etc. Any assumptions made in calculation shall be clearly written with proper justification. Stress calculation number - The stress model / calculation shall be identified by the major pipe number part of the stress system. Stress calculation register - Stress calculation register shall be maintained to indicate the progress of the stress work. At the end of project, the final stress calculation register shall be submitted, along with all the calculations. 3.6 Pipe Stress Design Philosophy The two main criteria which define the minimum acceptable flexibility are: The allowable stress range in the pipe The limiting values of the forces and moments which the pipe is permitted to impose on the equipment to which it is connected Page 14 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 To achieve a satisfactory result, the Stress Engineer / Package Seller must select one of the following: Accept the layout on the basis of previous experience, e.g., by comparison to a similar system. Package sellers are to provide background evidence to support the design in this instance (including comprehensive calculations). Accept the layout on the basis of a formal comprehensive analysis. Centrifugal Pump Piping Generally the pumps are arranged in two or three pump hook-up arrangements. The stress calculations shall be done on the basis of the spare pump at ambient temperature and operating pump(s) at design temperature. However, for nozzle loads, the operating pump(s) shall be considered at operating temperature and not at design temperature. The temperature of the spare pump piping from the pump up to the block valve shall be taken as ambient, while the temperature of the dead leg piping from the block valve to the tee junction of the operating pump piping shall be taken as follows: Dead leg temperature - [Ambient + (⅓ differential between operating and ambient temperatures)] The load cases shall be typically built as follows: Table 2.0 - Temperature Cases for Pump Piping (2-Pump System) Temperature Description Pump Condition Check Required Case Code stress T1 Design temperature All pumps operating compliance only Max. operating Operating pump A Nozzle load T2 ambient & dead leg Spare pump B check temperature Max. operating Operating pump B Nozzle load T3 ambient & dead leg Spare pump A check temperature Nozzle alignment check shall be done by freeing the nozzle and checking the displacements in sustained load case (weight without contents). In the case of spring hangers located in the vicinity of nozzles, the support shall be considered as rigid while checking the nozzle alignments. The results shall be recorded in the stress book. The permissible misalignment shall be within the flange bolt-up tolerances (typically 5 mm). If the displacement is more than 5 mm, the location of supports in the proximity of the equipment nozzle requires further review to reduce the initial displacement when the piping is connected to the equipment. The supports shall be located in such a manner that the piping weight should be taken off the nozzles. This can be achieved by providing adjustable supports or spring supports in the vicinity of the nozzles. The springs shall be sized by freeing up the nozzle to ensure that piping weight is taken by the springs. Rigid supports in the vicinity of pump nozzles shall be specified as adjustable pedestal type. Page 15 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 Credit shall not be taken into account for any reduction of nozzle loads caused by friction. 3.7 Caeser CFG (Configuration File) and Unit file The Caesar II configuration set up file and unit file for this project is prepared and attached as Annexure B. 3.8 Attachments Annexure A Annexure B Annexure D Annexure F 4.0 Earthquake calculation Caesar CFG & Unit file Nozzle load comparison sheet Allowable nozzle load table for vessels and heat exchangers PIPE SUPPORTS 4.1 Intent This specification enumerates basic criteria applicable to the design of pipe support components. This specification provides selection criteria for the Engineering Specification, “Technical Specification for Pipe Supports”. 4.2 Guidelines for all Supports All piping of ½” diameter and above shall have supports selected and located. Physical pipe supports (both primary and secondary) shall be modelled in PDMS. All supports shall be designed to satisfy the following requirements: 1) 2) 3) 4) 5) 6) 4.3 Have provisions for reasonable adjustability at the job site. Be readily installable with usual field labor and equipment. All threaded or equivalent adjustments shall be provided with a suitable locking device. All components shall be fabricated and erected so that they cannot become disengaged by movement of the supported piping. Support points shall be selected to optimize load distribution and weight balance, taking into consideration available building structures to which supports can be most readily affixed. „T‟ supports from pavements to be minimized. Interface Requirements with Civil Department (Not applicable to package sellers). Large discrete loads on concrete slabs / floors or steel structures shall be submitted to Civil / Structural Department for design of the secondary support structure / foundation, when they exceed the following conditions: 1) 2) 3) Support TOS higher than 1500mm from grade Maximum vertical load >10 kN Maximum horizontal load >5 kN Page 16 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Where there is an accumulation of horizontal loads, e.g., an anchor bay on a piperack, these shall be tabulated by the stress engineer and submitted to the Civil Department for sizing of columns, and bracing. 4.4 General Design Requirements 1) 2) 3) 4) 5) 6) 7) Pipe supports span to be followed as per span chart attached OR as proven acceptable by stress analysis. Concentrated loading due to valves, flanges, branches, etc. must be taken into consideration while being supported. Lines on pipe rack / sleeper, to be provided with a resting support on every main grid of pipe rack / sleepers as a minimum. Vertical deflection/sag of a piping system in a horizontal run between two adjacent supports due to sustained loading shall be limited to: 11 m for lines up to 3” NB 8 mm for lines 4” NB & above One leg of control valve stations shall be anchored or guided and pipe legs entering and leaving the station must be flexible enough so as not to exceed allowable stresses in the piping and valves Structural attachments to steel shall have sufficient bearing weld metal to adequately support the maximum calculated load, including hydrostatic test loading. Shims used in the field to achieve full bearing between pipe and / or pipe attachment and the structural steel and / or grade pier shall have sufficient area to carry the load to the structural component. After erection, shims must be securely welded to the structural steel to prevent shim slippage when pipe moves during operation. Unless the support is indicated to be a welded anchor (fixed) shims shall not be welded to the pipe or pipe attachment. If Shims are required to be welded to pipe shoes then they must extend the full length and width of the shoe. Shims whose width does not exceed the width of the supporting structural beam shall be welded to the beam only. 8) 9) 10) 11) 12) 13) Minimum headroom clearance of the lowest projection of any pipe support component shall be limited to the allowable headroom clearance. First piping support from strain sensitive / rotary equipment to be of adjustable type. Horizontal or vertical pipes should preferably be supported at a location of least vertical movement. Horizontal axial movement of a pipe in excess of 4” (100 mm) requires a check on the length of pipe shoe being used. It is imperative that the length of all shoes be such that the required bearing areas remain on the supporting steel during the full anticipated movement of the line. U-bolts can be used up to 6”NB for guiding vertical lines. As far as possible avoid guiding of horizontal lines by U bolts. Hanger rod supports Page 17 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Use of hanger rods shall be minimized At points of support subject to horizontal movements, rod type hangers shall be limited in rod swing to a maximum of 4º from the vertical A catch beam below the pipe near to the point of support should be provided to ensure the pipe will be supported in the event of rod failure. 14) 15) 16) Lines with 2-phase flow conditions (boiler blow down, etc.) shall be supported on rigid supports unless thermal movements dictate otherwise. Long trunnion type supports are to be avoided as far as possible and maximum height of trunnion to be restricted to 1500mm. In the case of trunnions longer than 1500mm, the stress engineer is to be consulted. Supporting of uninsulated and personnel-protected insulated lines, the following should be followed: For thin-walled stainless steel pipes 10” NB and below, wear pad made from parent pipe shall be provided only as shown in the attached span tables. For all pipes 16” NB and above, a wear pad shall be provided. Special care also shall be taken for thin-walled pipe. If the pipe will suffer from environmental deterioration (e.g. for stainless steel lines which may be prone to local cell corrosion), an isolation pad may be required. Stainless steel and carbon steel lines expected to see below zero degree Celsius temperatures for an extended period shall be supported on shoes; i.e., all the HP and LP flare header and blow down lines shall be supported on shoe. 17) 18) 19) 20) 21) 22) 23) All lines of 30” diameter and above shall be supported on shoe / saddle. Reciprocating compressor piping that is prone to vibration shall be designed so that it can be supported from grade sleepers. The span spacing shall be calculated so as to minimize the sympathetic vibrations between the piping and the pulsation of the compressor fluid flow. As far as possible provide independent supports for piping at higher elevations Locations where pipes and shoes are not to be resting on structural steel should be clearly indicated mentioning the required minimum gap. Pick-up supports, i.e. supporting of small diameter pipes by large diameter pipes, are generally to be avoided. In the case of packaged equipment, the seller shall submit the design to the seller for review and acceptance by a stress engineer. Guide gap to be 3 mm unless specified otherwise. Special adjustable “zero gap” guides shall be used to protect sensitive equipment nozzles where specified and be clearly identified on the stress isometric. Special requirements for small bore branch connections: Adequate care shall be taken for small bore (2” NB and below) branches from piping. As a rule, for all lines in 600 LB and above classes, lines Page 18 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 having 2-phase flow and lines having pulsating flow such as suction/discharge of reciprocating compressors and reciprocating pumps, all small bore branches of size 2” NB and below, e.g. vents, drains, orifice taps, pressure tapings, temperature tapings, sample connections, PSV inlet, TRV inlet and small bore line etc. shall be provided with 2 off stiffeners at 90° to each other from the main pipe to impart adequate stiffness to the branch connection. The stiffeners shall be made of 6 mm thick flats of material equivalent to the pipe material. Further, irrespective of line rating, the stiffeners shall be provided for all orifice taps, all small bore tappings from PSV inlet and the outlet lines and all small bore tappings in and near control valve manifolds. For these stiffeners, a standard piping support tag number is to be incorporated on the Piping Isometrics by piping design group. 24) 25) 26) 27) 28) 4.5 Materials of Construction / Standards 1) 2) 3) 4) 4.6 All other lines except plastic can rest directly on steel, except as noted above. All relief valve tailpipes and long drain pipes discharging to grade shall be adequately guided or otherwise restrained unless noted otherwise in the stress isometric. In the case of Polyethylene (PE) pipes ≤ 8”NB (OD 225mm), these shall be continuously supported using cable ladder type supports or inverted angles, depending on the layout, contents, and temperatures expected. Manufacturer recommended span tables should also be sought. Heavy fittings such as valves should be supported independently and large plastic fittings (e.g. flanges, particularly those with metal backing rings) should be supported on each side. Where pipes are continuously supported, flanged connections and other protrusions should be allowed room for movement. Lines with acoustic insulation shall be supported on acoustic isolation units or be supported on shoes with acoustically isolated clamps. Where a fixed attachment identified on the piping isometric is not covered by a standard drawing, a special pipe support sketch is to be produced and shall provide sufficient dimensional data to enable fabrication. They shall be checked by the stress engineer for conformance to project requirements. Materials used for pipe supports, will be shown in the pipe support specification IS (Indian Standard) material standards to be used. For a description of shoes used on insulated hot piping refer to Section 4.6 below. All attachments welded to pipes shall be of a material in accordance with parent pipe material unless noted otherwise. Pipe Shoes, Cradles and Attachments Table 3.0 - Table to be used for selecting type of shoe: Pipe Material Pipe Size Temp ºC Type of Support Page 19 of 29 Shoe Type Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 Pipe Material Pipe Size Temp ºC Type of Support Shoe Type CS All sizes All *Rest, Guide, Anchor CS welded shoe SS All sizes SS All sizes SS welded shoe with CS Base plate; *Rest, Guide 150 Or CS welded shoe with SS wear pad; Or CS clamped shoe with liner > 150 to 300 *Rest, Guide, Anchor SS welded shoe with CS base plate; Or CS clamped shoe with liner *For SS/CS/AS pipe, use long welded shoe at locations of anchors and at locations of large axial pipe movement. For all insulated lines (except personal protection lines), shoe height to be used as follows: Insulation tank 75 mm & below 76 mm to 125 mm inclusive 126 mm to 175 mm inclusive Shoe Height 100 mm 150 mm 200 mm Shoe heights may require modification to ensure that the contact surfaces on concrete beam supports or on structural steel beam supports do not exceed 120 °C or 400 °C respectively. 1) The reduction factor is 50°C per inch of shoe height from the outside surface of the pipe for determining shoe heights to reduce support contact temperatures. 2) Shoes for sloping lines to be cut suitably to suit slope of pipe. 3) All pipes with personal protection (PP) insulation shall be directly resting on support structure. Insulation to be cut locally. 4) All not traced (NT) small bore pipes (1.5” NB or less) with HC or PP insulation shall be directly resting on support structure. Insulation is to be cut locally. 5) Bare pipes shall rest directly on support if the contact area temperature does not exceed 120°C on concrete beam supports or 400°C on structural steel beam supports, otherwise shoes of sufficient height shall be provided such that the contact area temperature does not exceed the above limitations. 6) At support points for piping requiring cold insulation, 0°C and below, a molded high density polyurethane insert and steel cradle type support shall be provided to protect the insulation against failure during erection and operation. Page 20 of 29 Reliance Industries Limited RIL - OT KGD6 4.7 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 7) Welded trunnions or lugs shall be the same material as the pipe to which they are welded and shall be welded to the pipe by the piping fabricator unless specified otherwise. 8) Welding shall be in accordance with ASME B31.3 / 31.8 (Wherever applicable) 9) For stress relieved piping, the attachments shall be welded prior to stress relieving pipe. Spring Supports 1) Spring support shall be used if the use of a rigid support would cause and over stress in the piping or excessive equipment loading. 2) At points of support subject to vertical movement, springs of suitable design shall be used so that variation in supporting effect does not exceed permissible percentages of the calculated piping load through its total vertical travel. 3) The amount of variation that can be tolerated shall be based on such consideration as bending effect, control of piping elevation, allowable terminal loading, amount of load transfer to adjacent supports, etc. 4) The variation in supporting effect shall be generally limited to 25% of the calculated pipe load through its total vertical movement. 5) For all systems a greater allowance in percent load change is permissible where the load variation in supporting effect is transferred directly to a rigid support or terminal connection specifically designed for the resulting loading conditions. 6) Calculation for the variation of the support effort shall be based on the following formula: Variation % = (Travel) x (Spring Constant) x 100 (Operating Load) 7) Where variable spring hangers are specified they shall be initially pre-set at the installed load position so that the piping system is fully supported during normal operating conditions. 8) Constant support hangers shall be of substantial construction, with springs and moving parts suitably covered or protected. Each unit shall be individually shop calibrated to support the specified operating load with provision for possible field adjustment equal to plus or minus 10% of the operating load. 9) 10) Load deviation shall not exceed 6% throughout the total travel range. Components of spring supports shall be capable of adequately supporting piping during hydrostatic test loading. All can / bottom type spring supports to have Teflon pad on top of slide plate of spring. Load column of these spring supports shall be internally guided. Page 21 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 11) Accurate weight calculation shall be made to determine the supporting force at each spring support location and the pipe weight loading at each rotating equipment location. 12) The weight calculation at all spring support locations shall include the weight of pipe, fittings, valves and specialties, the weight of the medium transported, weight of insulation used. 13) The total travel for constant supports shall be equal to the actual travel plus 20%. In no case shall the difference between actual and total travel be less than 1” (25 mm). 14) Constant and variable springs shall be provided with travel stops: 15) These stops shall be installed at the factory where the spring shall be preset to the specified installed load, and shall be strong enough to resist the hydrostatic test loading on the unit. These stops shall be re-usable and either stored in attached storage pouches or permanently attached to the spring housing, when not in use. 16) The travel range of each spring selected shall be checked to ensure that any upset temperature or steam-out condition can be satisfied within the limits of the working range of the spring. 17) Where pipelines have been analyzed by the Pipe Stress Engineer and line movements are available on the computer output sheets, these movements shall be used for the spring computations. 18) All the Variable Spring Supports (VSS) and Constant Spring Supports (CSS) shall be properly numbered and area wise spring log shall be maintained. Following philosophy shall be adopted for numbering the spring hangers: VSS – 01 – 001 Sequence numbers Area Number Type of Spring Support VSS for Variable Spring Support and CSS for constant spring support 19) 20) 4.8 Separate sequence numbers shall be maintained for VSS and CSS. Wherever the Base Type springs (CSH / VSH) are used on horizontal big bore lines of dia. 20” and above, instead of single spring, double spring should be used to avoid the rotation. For all the pedestal type spring hangers provided for lines of Dia. 20” and above separate sketch (with SPS nos. as well as Spring Tag nos.) shall be prepared to indicate the installation details etc. Sleepers and Grade Piers for Supports 1) Sliding base supports with pipe loads, which do not exceed 10kN shall rest directly on pedestals as specified in support standard. 2) Where anchors and / or stops specified at sleepers or base piers, the calculated reactions exceeding 10kN vertical or 5kN horizontal shall be transmitted to the Civil Engineering Group. The Civil Engineering Group Page 22 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 shall design the appropriate foundations to sustain the reactions (NB. Not applicable to Package Sellers). Page 23 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 PIPE SPANS Assumptions and Notes Material: The properties of Carbon Steel have been used. Modulus of Elasticity (E) = 210 Gpa (210,000 N/mm^2) Density = 7900 kg/m^3 Density of contents, for liquid filled case (for all cases where insulation reads 0, 40, 75, & 100mm) = 1000 kg/m^3 Density of insulation (where insulation reads 40, 75, & 100mm) = 177kg/m^3 (from MEC documentation) Three different methods for assessing the maximum permissible span length have been used: 1. Maximum span based on the maximum allowable bending stress at the mid-span of the beam. Based on a simply supported beam. Maximum allowable stress limited to 0.25 x Sh. For CS less than 200C, Sh = 137.9 Mpa. Therefore S = 34.5 Mpa. Formula for length based on mid-span bending stress is: L 2. L Where: S = Allowable Stress, 34.5MPa I = Second Moment of Area mm^4 w = Weight per unit length of pipe, N/mm D = Outside diameter of pipe in mm. L = Span length in mm. Maximum span based on the deflection allowed at the mid-point of the span. Limited this to 10 mm for less than 4" NB, and 8 mm for pipes 4" NB and above. For simply supported beam: Deflection 3. 16 SI wD 5 384 wL4 EI Where: w = Weight per unit length of pipe, N/mm I = Second Moment of Area mm^4 L = Span length in mm. E = Youngs modulus MPa. Deflection = 8mm, or 10mm (see above). Maximum span based on the indentation at the pipe support. Typically this comes into effect with large bore thin walled pipe. The calculation tabulated based on bare pipe resting on beams 100mm long. In this case the local stress is limited to 0.67Sh (or 92.4MPa for carbon steel pipe less than 200C). In many cases a shoe will be used, and the onus is on the stress engineer to check spans as required. Local stress in shell under local loading gives: S (d b )t 2 0 . 644 w Rt Page 24 of 29 Where: w = Weight per unit length of pipe, N/mm S = Allowable Stress, 92.4MPa. L = Span length in mm R = Radius of pipe mm t = corroded thickness of pipe mm Deflection = 8mm, or 10mm (see above) d = bearing length = 100mm b = bearing width mm, 16.5mm for 42"NB pipe and directly proportional for other sizes Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 NB - The following tabulated results have been rounded up to the nearest hundred. SPAN CHART FOR 1” TO 10” (Up to 200 C Max) Schd No 10S STD 40 XS 80 160 XXS Insulation Thickness mm EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 1" 1.5" 2" 3" 4" 6" 8" 10" Max Span Length mm Max Span Length mm 4900 4400 4100 3600 3100 Max Span Length mm 5500 4900 4500 4100 3600 4800 4500 4300 3900 3600 4800 4500 4300 3900 3600 4700 4500 4300 4000 3800 4500 4500 4300 4000 3900 5300 5100 4800 4500 4300 5300 5100 4800 4500 4300 5200 5100 4900 4600 4400 5100 5000 4800 4600 4500 Max Span Length mm 6300 5400 5200 4900 4600 6200 5700 5500 5200 5000 6200 5700 5500 5200 5000 6200 5800 5600 5400 5200 6200 5800 5600 5400 5200 6000 5800 5700 5500 5300 5900 5800 5600 5500 5400 Max Span Length mm 7200 6000 5700 5500 5300 7100 6400 6200 6000 5800 7100 6400 6200 6000 5800 7000 6500 6400 6200 6000 7000 6500 6400 6200 6000 6900 6600 6500 6300 6200 6800 6600 6500 6300 6200 Max Span Length mm 8700 7000 6800 6500 6400 8600 7600 7400 7300 7100 8600 7600 7400 7300 7100 8500 7900 7700 7600 7400 8500 7900 7700 7600 7400 8400 8000 7900 7800 7700 8300 8000 7900 7800 7700 Max Span Length mm 10000 7700 7600 7400 7200 9900 8600 8400 8300 8100 9900 8600 8400 8300 8100 9800 8900 8800 8600 8500 9800 8900 8800 8600 8500 9500 9100 9000 8900 8800 9500 9100 9000 8900 8800 Max Span Length mm 11100 8440 8271 8106 7974 10975 9425 9284 9141 9032 10975 9425 9284 9141 9032 10907 9717 9591 9464 9365 10859 9846 9730 9611 9518 10598 10103 10021 9935 9868 10659 10083 9995 9904 9832 4000 3800 3400 2800 2300 3900 3800 3500 3000 2600 3900 3800 3500 3000 2600 3800 3700 3500 3200 2800 3700 3700 3400 3200 2800 Page 25 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 SPAN CHART FOR 12” TO 20” (Up to 200C Max) Schd No 10S STD 40 XS 80 160 Insulation Thickness mm 12" 14" 16" EMPTY Max Span Length mm 12100 Max Span Length mm 12700 4.78 Max Span Length mm 13600 4.78 Max Span Length mm 14400 5.54 Max Span Length mm 15200 0 9100 9000 4.78 9900 4.78 10100 5.54 10800 40 9000 8400 4.78 9700 4.78 9900 5.54 10600 75 8800 7900 4.78 9400 4.78 9600 5.54 10400 Pad thick mm 18" Pad thick mm 20" Pad thick mm 100 8600 7600 4.78 9200 4.78 9500 5.54 10200 EMPTY 12000 12600 9.53 13500 9.53 14300 9.53 15100 0 10100 10500 9.53 11000 9.53 11500 9.53 11900 40 10000 10400 9.53 10900 9.53 11400 9.53 11800 75 9900 10200 9.53 10800 9.53 11300 9.53 11700 100 9800 9900 9.53 10700 9.53 11200 9.53 11600 EMPTY 12000 12600 12.70 13500 14300 15100 0 10200 10700 12.70 11400 12100 11500 40 10100 10600 12.70 11300 12000 11100 75 10000 10500 12.70 11200 11900 10800 100 9900 10400 12.70 11100 11800 10500 EMPTY 12000 12600 13500 14300 15100 0 10500 10900 11400 11000 8900 40 10300 10700 11300 10600 8600 75 10200 10600 11200 10200 8300 100 10100 10500 11100 9900 8100 EMPTY 11900 12500 13300 14100 14900 0 10800 11300 12000 12700 13400 40 10600 11200 11900 12600 13300 75 10500 11100 11800 12600 13200 100 10500 11000 11800 12500 13200 EMPTY 11600 12200 13000 13800 14500 0 11100 11600 12400 13100 13800 40 11000 11500 12300 13000 13800 75 10900 11400 12200 13000 13700 100 10800 11400 12200 12900 13700 Page 26 of 29 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 SPAN CHART FOR 24” TO 48” (10S to 20mm thick) (Up to 200 C Max) Schd No 10S STD 40 XS 80 160 20 mm Insulatio n Thicknes s mm EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 EMPTY 0 40 75 100 24" Pad thick mm Max Span Length mm 6.35 6.35 6.35 6.35 6.35 9.53 9.53 9.53 9.53 9.53 17.48 17.48 17.48 17.48 17.48 12.70 12.70 12.70 12.70 12.70 30.96 30.96 30.96 30.96 30.96 59.54 59.54 59.54 59.54 59.54 16100 11100 10700 10300 10000 16100 12300 12200 12100 12000 16000 13400 13300 13200 13200 16000 12800 12700 12700 12600 15800 14200 14100 14000 14000 15400 14600 14600 14500 14500 30" Pad thick mm Max Span Length mm 7.92 7.92 7.92 7.92 7.92 9.53 9.53 9.53 9.53 9.53 18000 9100 8800 8600 8400 18000 8900 8600 8400 8200 36" Pad thick mm Max Span Length mm 12.70 12.70 12.70 12.70 12.70 17900 13500 13100 12800 12600 19.05 19.05 19.05 19.05 19.05 12.70 12.70 12.70 12.70 12.70 20.00 20.00 20.00 20.00 20.00 17800 14800 14700 14700 14600 20.00 20.00 20.00 20.00 20.00 Page 27 of 29 42" Pad thick mm Max Span Length mm 19600 15200 14900 14600 14400 19700 8800 8600 8400 8300 12.70 12.70 12.70 12.70 12.70 21300 6700 6500 6400 6300 19600 15800 15700 15600 15400 20.00 20.00 20.00 20.00 20.00 21200 12400 12100 11900 11800 48" Pad thick mm Max Span Length mm 20.00 20.00 20.00 20.00 20.00 22700 9500 9300 9200 9100 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 Reliance Industries Limited RIL - OT KGD6 SPAN CHART FOR 24” TO 48” (25 mm to 70 mm thick) (Up to 200 C Max) Schd No Insulation Thickness mm 24" 25 mm 30 mm 40 mm 50 mm 60 mm 70 mm 36" 42" 48" Pad thick mm Max Span Length mm Pad thick mm Max Span Length mm Pad thick mm Max Span Length mm Pad thick mm Max Span Length mm EMPTY 25.00 17800 25.00 19500 25.00 21100 25.00 22600 0 25.00 15200 25.00 16300 25.00 16300 25.00 12600 40 25.00 15100 25.00 16200 25.00 16100 25.00 12400 75 25.00 15100 25.00 16200 25.00 15800 25.00 12200 100 25.00 15000 25.00 Pad thick mm Max Span Length mm 30" 16100 25.00 15700 25.00 12100 EMPTY 17700 16000 30.00 21100 30.00 22600 0 12700 8600 30.00 17700 30.00 15700 40 12400 8400 30.00 17600 30.00 15500 75 12200 8300 30.00 17500 30.00 15300 100 12100 8200 30.00 17500 30.00 15100 EMPTY 17600 19400 16300 13600 0 15900 12000 9400 7300 40 15800 11800 9200 7200 75 15800 11600 9100 7100 100 15700 11500 9000 7100 EMPTY 17500 19300 18900 15700 0 16100 15200 12000 9400 40 16100 15000 11800 9300 75 16000 14800 11700 9200 100 16000 14700 11600 9100 EMPTY 17400 19200 20800 17600 0 16300 17700 14500 11400 40 16200 17600 14300 11300 75 16200 17600 14200 11200 100 16100 17500 14000 11100 EMPTY 17300 19100 20700 19400 0 16300 17800 16900 13300 40 16300 17700 16700 13200 75 16200 17700 16500 13100 100 16200 17700 16400 13000 Page 28 of 29 Reliance Industries Limited RIL - OT KGD6 Pipe Stress Analysis & Pipe Supports Design Criteria OTBC-B00-31070484-PPL-0001 REDUCTION GUIDE FOR ALLOWABLE SPANS BASED ON CONFIGURATION. Pipe spans listed previously have been based on straight pipe between supports. For cases A through G below, multiply the allowable pipe span by the appropriate coefficient. Page 29 of 29 Doc.No. : 2001-KGD6-D2-PF-ON-OTBC-B00-31070484-PPL-0001 Sht. 1 of 1 Annexure - A SEISMIC FACTOR CALCULATION The horizontal seismic co-efficient is calculated by response spectrum method, as per IS 1893-2002. Seismic Zone III The horizontal seismic co-efficient is calculated as follows: Z I Ah area 2 R area Sa g I Z Ah Piperack 2 R piperack 0 .1684 0 .169 Sa 0 .0963 g Vertical Seismic coefficient for Area Design = 2/3 x Ah Area = 0.113 Vertical Seismic coefficient for piperack Design = 2/3 x Ah Piperack = 0.0642 Steel strcture seismic parameter is considered for the Area. RCC structure seimic parameter is considered for the Piperack Where; Ah = Horizontal seismic coefficient Z = Seismic zone factor = 0.22 I = 1.75 RArea = 4 RPiperack =5 Sa /g Area = 2.5 with 2% damping factor = 3.5 Sa /g Piperack = 2.5 with 5% damping factor = 2.5 (Damping factor as per table 3) (Damping factor as per table 3) " g " Factor For Area Piping Design Caeser II input to use "g" option for uniform load ( in X & Z direction ) , = 0.169 Caeser II input to use "g" option for uniform load ( in Y direction ) , = 0.113 " g " Factor For Concrete Piperack Piping ( Area 01 , 02 , 04 ) Caeser II input to use "g" option for uniform load ( in X & Z direction ) , = 0.0963 Caeser II input to use "g" option for uniform load ( in Y direction ) , = 0.0642 Referenced doc. 2001-KGD6-D2-PF-ON-OTBC-B00-31070484-CIL-0701 OTBC-B00-31070488-PPL-0001-Attach B OTBC-B00-31-7070484-PPL-001 Doc. No. : 2001-KGD6-D2-PF-ON-OTBC-B00-31070484-PPL-0001 Annexure B ( Caesar II Configuration set up ) Ver. 5.300 EGAMEMORY = 128K 10 CONNECT_GEOMETRY_THRU_CNODES = YES 34 1. MIN_ALLOWED_BEND_ANGLE = 0.5000000E+01 36 MAX_ALLOWED_BEND_ANGLE = 0.9500000E+02 37 BEND_LENGTH_ATTACHMENT_PERCENT = 0.1000000E+01 38 MIN_ANGLE_TO_ADJACENT_BEND_PT = 0.5000000E+01 39 LOOP_CLOSURE_TOLERANCE = 0.1000000E+01 42 THERMAL_BOWING_HORZ_TOLERANCE = 0.1000000E-03 92 AUTO_NODE_NUMBER_INCREMENT= 0.1000000E+02 109 Z_AXIS_UP= NO 129 0. USE_PRESSURE_STIFFENING = DEFAULT 65 2. ALPHA_TOLERANCE = 0.5000000E-01 33 RESLD-FORCE = NO 44 0. HGR_DEF_RESWGT_STIF = 0.1000000E+13 49 DECOMP_SNG_TOL = 0.1000000E+11 50 BEND_AXIAL_SHAPE = YES 51 1. FRICT_STIF = 0.1000000E+07 45 FRICT_NORM_FORCE_VAR = 0.1500000E+00 47 FRICT_ANGLE_VAR = 0.1500000E+02 48 FRICT_SLIDE_MULT = 0.1000000E+01 46 ROD_TOLERANCE = 0.1000000E+01 59 ROD_INC = 0.2000000E+01 58 INCORE_NUMERICAL_CHECK = NO 60 0. OUTCORE_NUMERICAL_CHECK = NO 61 0. DEFAULT_TRANS_RESTRAINT_STIFF= 0.1000000E+13 98 DEFAULT_ROT_RESTRAINT_STIFF= 0.1000000E+13 99 IGNORE_SPRING_HANGER_STIFFNESS = NO 100 0. MISSING_MASS_ZPA = EXTRACTED 101 1. MIN_WALL_MILL_TOLERANCE = 0.1250000E+02 107 WRC-107_VERSION = MAR_79_1B1/2B1 119 3. WRC-107_INTERPOLATION = LAST_VALUE 120 1. DEFAULT_AMBIENT_TEMPERATURE= 0.7000000E+02 135 = 16.6 C BOURDON_PRESSURE= NONE 136 0. COEFFICIENT_OF_FRICTION_(MU) = 0.3000000E+00 140 INCLUDE_SPRG_STIF_IN_HGR_OPE = NO 141 0. INCLUDE_INSULATION_IN_HYDROTEST = YES 147 1. REDUCED_INTERSECTION = B31.1(POST1980) 32 1. USE_WRC329 NO 62 0. NO_REDUCED_SIF_FOR_RFT_AND_WLT NO 53 0. B31.1_REDUCED_Z_FIX = YES 54 1. CLASS_1_BRANCH_FLEX NO 55 0. ALL_STRESS_CASES_CORRODED = NO 35 0. ADD_TORSION_IN_SL_STRESS = DEFAULT 66 2. ADD_F/A_IN_STRESS = YES 67 0. OCCASIONAL_LOAD_FACTOR = 0.0000000E+00 41 DEFAULT_CODE = B31.3 43 3. B31.3_SUS_CASE_SIF_FACTOR = 0.7500000E+00 40 ALLOW_USERS_BEND_SIF = NO 52 0. OTBC-B00-31-7070484-PPL-001 Doc. No. : 2001-KGD6-D2-PF-ON-OTBC-B00-31070484-PPL-0001 Annexure B ( Caesar II Configuration set up ) USE_SCHNEIDER YIELD_CRITERION_STRESS = USE_PD/4T BASE_HOOP_STRESS_ON_? = NO MAX_3D_SHEAR NO ID Page 1 63 108 64 57 0. 0. 0. 0. OTBC-B00-31070488-PPL-0001-Attach B EN13480_USE_IN_OUTPLANE_SIFS= NO 133 LIBERAL_EXPANSION_ALLOWABLE= YES 137 B31.3_SEC_319.2.3C_SAXIAL= (|Sa|+Sb)^2 146 B31.3_WELDING/CONTOUR_TEE_ISB16.9 FALSE 139 PRESSURE_VARIATION_IN_EXP_CASE= DEFAULT 143 IMPLEMENT_B313_APP-P NO 144 IMPLEMENT_B313_CODE_CASE_178 NO 145 IGNORE_B31.1/B31.3_Wc_FACTOR= NO 148 USE_FRP_SIF = YES 110 USE_FRP_FLEX = YES 111 BS_7159_Pressure_Stiffening= Design_Strain 121 FRP_Property_Data_File= CAESAR.FRP 122 FRP_Emod_(axial) = 0.3200000E+07 113 FRP_Ratio_Gmod/Emod_(axial) = 0.2500000E+00 114 FRP_Ea/Eh*Vh/a = 0.1527300E+00 115 FRP_Laminate_Type = THREE 116 FRP_Alpha = 0.1200000E+02 117 FRP_Density = 0.6000000E-01 118 EXCLUDE_f2_FROM_UKOOA_BENDING = NO 134 INTRO_EXIT_SCREENS ON 85 YES/NO/ARE_YOU_SURE_PROMPTS ON 86 OUTPUT_REPORTS_BY_LOAD_CASE YES 87 DISPLACEMENT_NODAL_SORTING YES 89 DYNAMIC_INPUT_EXAMPLE_TEXT MAX 94 TIME_HIST_ANIMATE YES 104 OUTPUT_TABLE_OF_CONTENTS ON 105 INPUT_FUNCTION_KEYS_DISPLAYED YES 106 ENABLE_AUTOSAVE YES 130 AUTOSAVE_TIME_INTERVAL 0.3000000E+02 131 PROMPTED_AUTOSAVE YES 132 DISABLE_UNDO/REDO NO 128 STRCT_DBASE= AISC89.BIN 70 VALVE_&_FLANGE= CADWORX.VHD 90 EXPANSION_JT_DBASE= FLEXPATH.JHD 91 PIPING_SIZE_SPECIFICATION DIN 88 DEFAULT_SPRING_HANGER_TABLE= 0.5000000E+01 112 SYSTEM_DIRECTORY_NAME= SYSTEM 123 UNITS_FILE_NAME= KGD6.FIL 124 ENABLE_ODBC_OUTPUT= NO 125 APPEND_RERUNS= NO 126 LOADCASE_TEMPLATE= LOAD.TPL 142 Valve/Flange_Dbase_File_Location= CAESARII_DIR 149 User_Material_File_Name= UMAT1.UMD 150 ODBC_DATABASE_NAME= <none> 127 0. 1. 2. 0. 2. 0. 0. 0. 1. 1. 1. 1. 3. 0. 1. 1. 1. 1. 0. 1. 1. 1. 1. 1. 0. 1. 1. 1. 3. 1. 0. 0. 0. 1. 1. 1. 0. OTBC-B00-31-7070484-PPL-001 Doc. No. : 2001-KGD6-D2-PF-ON-OTBC-B00-31070484-PPL-0001 Annexure B ( Caesar II Configuration set up ) INPUT UNITS USED... UNITS= SI (mm) NOM/SCH INPUT= ON LENGTH inches FORCE pounds MASS(dynamics) pounds MOMENTS(INPUT) inch-pounds MOMENTS(OUTPUT) inch-pounds STRESS lbs./sq.in. TEMP. SCALE degrees F. PRESSURE psig ELASTIC MODULUS lbs./sq.in. PIPE DENSITY lbs./cu.in. x 25.400 x 4.448 x 0.454 x 0.113 x 0.113 x 6.895 x 0.556 x 0.069 x 6.895 x 27680.000 Page 2 = = = = = = = = = = mm. N. kg. N.m. N.m. KPa C bars KPa kg/cu.m. INSULATION DENS. FLUID DENSITY TRANSL. STIF ROTATIONAL STIF UNIFORM LOAD G LOAD WIND LOAD ELEVATION COMPOUND LENGTH DIAMETER WALL THICKNESS OTBC-B00-31070488-PPL-0001-Attach lbs./cu.in. x 27680.000 = lbs./cu.in. x 27680.000 = lbs./in. x 1.751 = in.lb./deg. x 0.113 = lb./in. x 0.175 = g's x 1.000 = lbs./sq.in. x 6.895 = inches x 0.025 = inches x 25.400 = inches x 25.400 = inches x 25.400 = Page 3 B kg/cu.m. kg/cu.m. N./cm. N.m./deg N./mm. g's KPa m. mm. mm. mm. Sht. 1 of 1 Doc. No.: 2001-KGD6-D2-PF-ON-OTBC-B00-31070484-PPL-0001 ANNEXURE :- D NOZZLE LOADING COMPARISON SHEET CALCULATION NO. EQUIPMENT / NOZZLE NO. Nozzle Nozzle Dia, Rating. Node No.:Forces (N) Fa Fl Moments (N-m) Fc Mc Ml Mt Allowable Loading Calculated Loading For Design condition (Max) Design condition (Min) Operating condition EQUIPMENT / NOZZLE NO. Nozzle Nozzle Dia, Rating. Node No.:Forces (N) Fa Fl Moments (N-m) Fc Mc Ml Mt Allowable Loading Calculated Loading For Design condition (Max) Design condition (Min) Operating condition EQUIPMENT / NOZZLE NO. Nozzle Nozzle Dia, Rating. Allowable Loading Calculated Loading For Design condition (Max) Design condition (Min) Operating condition Notes : Node No.:Forces (N) Fa Fl Moments (N-m) Fc Mc Ml Mt Sht. 1 of 1 Doc. No. : 2001-KGD6-D2-PF-ON-OTBC-B00-31070484-PPL-0001 Annexure - F NOZZLE LOADS FOR PRESSURE VESSEL, SHELL & TUBE HEAT EXCHANGERS AT THE FACE OF FLANGE TABLE 1:SIZE (150#) DN FA=FL inches FC (300#) MC=ML MT FA=FL FC (600#) MC=ML MT FA=FL FC (900#) MC=ML MT FA=FL FC (1500#) MC=ML MT FA=FL FC (2500#) MC=ML MT FA=FL FC SIZE MC=ML MT inches 2 50 3000 2250 390 450 4000 3000 520 600 5000 3750 650 750 6000 4500 780 900 8000 6000 1040 1200 11200 8400 1456 1680 2 3 80 4500 3375 878 1013 6000 4500 1170 1350 7500 5625 1463 1688 9000 6750 1755 2025 12000 9000 2340 2700 16800 12600 3276 3780 3 4 100 6000 4500 1560 1800 8000 6000 2080 2400 10000 7500 2600 3000 12000 9000 3120 3600 16000 12000 4160 4800 22400 16800 5824 6720 4 6 150 9000 6750 3510 4050 12000 9000 4680 5400 15000 11250 5850 6750 18000 13500 7020 8100 24000 18000 9360 10800 33600 25200 13104 15120 6 8 200 12000 9000 6240 7200 16000 12000 8320 9600 20000 15000 10400 12000 24000 18000 12480 14400 32000 24000 16640 19200 44800 33600 23296 26880 8 10 250 15000 11250 9750 11250 20000 15000 13000 15000 25000 18750 16250 18750 30000 22500 19500 22500 40000 30000 26000 30000 56000 42000 36400 42000 10 12 300 18000 13500 14040 16200 24000 18000 18720 21600 30000 22500 23400 27000 36000 27000 28080 32400 48000 36000 37440 43200 67200 50400 52416 60480 12 14 350 21000 15750 19110 22050 28000 21000 25480 29400 35000 26250 31850 36750 42000 31500 38220 44100 56000 42000 50960 58800 78400 58800 71344 82320 14 16 400 24000 18000 24960 28800 32000 24000 33280 38400 40000 30000 41600 48000 48000 36000 49920 57600 64000 48000 66560 76800 89600 67200 93184 107520 16 18 450 27000 20250 31590 36450 36000 27000 42120 48600 45000 33750 52650 60750 54000 40500 63180 72900 72000 54000 84240 97200 100800 75600 117936 136080 18 20 500 30000 22500 39000 45000 40000 30000 52000 60000 50000 37500 65000 75000 60000 45000 78000 90000 80000 60000 104000 120000 112000 84000 145600 168000 20 22 550 33000 24750 47190 54450 44000 33000 62920 72600 55000 41250 78650 90750 66000 49500 94380 108900 88000 66000 125840 145200 123200 92400 176176 203280 22 24 600 36000 27000 56160 64800 48000 36000 74880 86400 60000 45000 93600 108000 72000 54000 112320 129600 96000 72000 149760 172800 134400 100800 209664 241920 24 26 650 39000 29250 65910 76050 52000 39000 87880 101400 65000 48750 109850 126750 78000 58500 131820 152100 104000 78000 175760 202800 145600 109200 246064 283920 26 28 700 42000 31500 76440 88200 56000 42000 101920 117600 70000 52500 127400 147000 84000 63000 152880 176400 112000 84000 203840 235200 156800 117600 285376 329280 28 30 750 45000 33750 87750 101250 60000 45000 117000 135000 75000 56250 146250 168750 90000 67500 175500 202500 120000 90000 234000 270000 168000 126000 327600 378000 30 32 800 48000 36000 99840 115200 64000 48000 133120 153600 80000 60000 166400 192000 96000 72000 199680 230400 128000 96000 266240 307200 179200 134400 372736 430080 32 34 850 51000 38250 112710 130050 68000 51000 150280 173400 85000 63750 187850 216750 102000 76500 225420 260100 136000 102000 300560 346800 190400 142800 420784 485520 34 36 900 54000 40500 126360 145800 72000 54000 168480 194400 90000 67500 210600 243000 108000 81000 252720 291600 144000 108000 336960 388800 201600 151200 471744 544320 36 38 950 57000 42750 140790 162450 76000 57000 187720 216600 95000 71250 234650 270750 114000 85500 281580 324900 152000 114000 375440 433200 212800 159600 525616 606480 38 40 1000 60000 45000 156000 180000 80000 60000 208000 240000 100000 75000 260000 300000 120000 90000 312000 360000 160000 120000 416000 480000 224000 168000 582400 672000 40