Washington University in St. Louis Washington University Open Scholarship Washington University / UMSL Mechanical Engineering Design Project JME 4110 Mechanical Engineering & Materials Science Summer 2021 JME 4110: Vibratory Parts Feeder Adin Stambolic Washington University in St. Louis, adin.stambolic@wustl.edu Patrick Edward Vastola Washington University in St. Louis, p.vastola@wustl.edu Noah Herrin Washington University in St. Louis, herrinn@wustl.edu Follow this and additional works at: https://openscholarship.wustl.edu/jme410 Part of the Mechanical Engineering Commons Recommended Citation Stambolic, Adin; Vastola, Patrick Edward; and Herrin, Noah, "JME 4110: Vibratory Parts Feeder" (2021). Washington University / UMSL Mechanical Engineering Design Project JME 4110. 47. https://openscholarship.wustl.edu/jme410/47 This Final Report is brought to you for free and open access by the Mechanical Engineering & Materials Science at Washington University Open Scholarship. It has been accepted for inclusion in Washington University / UMSL Mechanical Engineering Design Project JME 4110 by an authorized administrator of Washington University Open Scholarship. For more information, please contact digital@wumail.wustl.edu. Washington University in St. Louis Washington University Open Scholarship Mechanical Engineering Design Project Class Mechanical Engineering & Materials Science Vibratory Parts Feeder Adin Stambolic Patrick Edward Vastola Noah Herrin Follow this and additional works at: https://openscholarship.wustl.edu/mems411 This Final Report is brought to you for free and open access by the Mechanical Engineering & Materials Science at Washington University Open Scholarship. It has been accepted for inclusion in Mechanical Engineering Design Project Class by an authorized administrator of Washington University Open Scholarship. For more information, please contact digital@wumail.wustl.edu. The purpose of a vibratory parts feeder is to move product from one location to another while sorting or reorienting the objects. The prototype we built utilizes a concrete vibration motor (modified) that is attached to a base frame assembly. That base frame is then attached to a sorting through via springs to allow for vibratory oscillations from the motor. JME 4110 Mechanical Engineering Design Project Vibratory Parts Feeder Noah Herrin Patrick Vastola Adin Stambolic Table of Contents 1 2 3 Introduction 1.1 Value proposition / project suggestion 4 1.2 List of team members 4 Background Information Study 4 2.1 Design Brief 4 2.2 Background summary 4 Concept Design and Specification 3.1 4 5 User Needs and Metrics 6 6 3.1.1 Record of the user needs interview 7 3.1.2 List of identified metrics 7 3.1.3 Table/list of quantified needs equations 7 3.2 concept drawings 7 3.3 A concept selection process. 8 3.3.1 Concept scoring (not screening) 8 3.3.2 Preliminary analysis of each concept’s physical feasibility 9 3.3.3 Final summary statement 9 3.4 Proposed performance measures for the design 9 3.5 Revision of specifications after concept selection 9 Embodiment and fabrication plan 10 4.1 Embodiment/Assembly drawing 10 4.2 Parts List 10 4.3 Draft detail drawings for each manufactured part 11 4.4 Description of the design rationale 11 Engineering analysis 5.1 Engineering analysis proposal 5.1.1 5.2 6 4 Signed engineering analysis contract Engineering analysis results 11 11 12 12 5.2.1 Motivation 12 5.2.2 Summary statement of analysis done 13 5.2.3 Methodology 14 5.2.4 Results 14 5.2.5 Significance 14 Risk Assessment 6.1 Risk Identification 15 15 1 7 6.2 Risk Analysis 16 6.3 Risk Prioritization 16 Codes and Standards 7.1 Identification 16 7.2 Justification 16 7.3 Design Constraints 17 7.3.1 Functional 17 7.3.2 Safety 17 7.4 8 9 16 Significance Working prototype 17 18 8.1 Prototype Photos 18 8.2 Working Prototype Video 19 8.3 Prototype components 19 Design documentation 9.1 Final Drawings and Documentation 21 21 9.1.1 Engineering Drawings 21 9.1.2 Sourcing instructions 21 9.2 Final Presentation 22 7 Appendix A - Parts List 22 8 Appendix B - Bill of Materials 22 9 Appendix C – Complete List of Engineering Drawings 23 List of Figures Figure 1 - Basic linear vibrating feeder Figure 2 - Vibratory feeder and base Figure 3 - Patent drawing for a parts feeder Figure 4 - Concept Drawing 1 Figure 5 - Concept Drawing 2 Figure 6 - Concept Drawing 3 Figure 7 - Concept Drawing 4 Figure 8 - Embodiment Drawing Figure 9 - Signed Contract Figure 10 - Vibration Analysis of System Figure 11 - Structural Analysis Equations Figure 12 - Risk Assessment Methology Figure 13 - Prototype Photo 1 Figure 14 - Prototype Photo 2 Figure 15 - Motor Figure 16 - Spring Supports 4 5 5 7 7 8 8 10 12 13 13 15 18 18 19 19 2 Figure 17 - Tube Support Figure 18 - Tray Figure 19 - Top Level Assembly Figure 20 - Sub-Assembly 1 Figure 21 - Sub-Assembly 2 Figure 22 - Part Drawing 1 Figure 23 - Part Drawing 2 Figure 24 - Part Drawing 2 Figure 25 - Part Drawing 3 Figure 26 - Part Drawing 4 Figure 27 - Part Drawing 5 Figure 28 - Part Drawing 6 20 20 23 23 24 24 25 25 26 26 27 27 List of Tables Table 1 - User Design Needs Table 2 - Concept Scoring Table 3 - Parts List Table 4 - Risk Analysis Table 5 - Vibration Severity Standards Table 6 - Purpose Table Table 7 - Bill of Materials 6 8 10 16 17 21 22 3 1 INTRODUCTION 1.1 VALUE PROPOSITION / PROJECT SUGGESTION The parts we envision in project 7 will need to be transported between the mixer, producer, and modification station. Design inexpensive, modular, tunable vibratory feeders to move the parts from one place to another. Ideally, the feeder can be programmed to change shape and size during a run as the parts are modified. 1.2 LIST OF TEAM MEMBERS Noah Herrin - Project Manager Patrick Vastola - Documentation, CAD, and Codes & Standards Adin Stambolic - Design Calculation and Scheduler 2 BACKGROUND INFORMATION STUDY 2.1 DESIGN BRIEF Design an inexpensive, modular and tunable vibratory feeder to move different size particles from one place to another. The feeder can change according to the shape and size of the particles while in use. 2.2 BACKGROUND SUMMARY 1. https://www.mpelettronica.com/en/how-do-electromagnetic-vibratory-feeder-works/ Figure 1 - Basic linear vibrating feeder This link gives a brief explanation how a vibrating feeder works. A linear vibrator works by inducing a current in a coil at high frequency, pulling and pushing a nearby magnet which creates the physical vibration. 2. https://www.goughengineering.com/en/blog/vibratory-feeder-working-principle 4 Figure 2 - Vibratory feeder and base This link gives a more in-depth explanation of a linear vibratory parts feeder. 3.https://patents.google.com/patent/US7413073B2/en?q=linear+vibrating+feeder&oq=linear+ vibrating+feeder Figure 3 - Patent drawing for a parts feeder Above is a figure from a patent for a “piezo-driven parts feeder”. It consists of a moving table mounted on top of a stationary table via an electromagnetic vibrator connected to two elastic parts. There is a magnet fixed to the moving table. A current is induced at a high frequency causing the magnet to move the table back and forth. 5 3 3.1 CONCEPT DESIGN AND SPECIFICATION USER NEEDS AND METRICS Scale; 1 (least important) to 5 (most important) Table 1 - User Design Needs Project/Product Name: Vibratory Parts Feeder Customer: Mark Jakiela Interviewers: Patrick Vastola, Adin Stambolic, Noah Herrin Address: Washington University Willing to do a follow up? Yes Date: June 28, 2021 Type of user: ? Currently uses: ? Question Customer Statement Interpreted Need Importance Type of feeder? Linear track Transportation from one place to another 5 Particles per minute? 1000 ppm Speed 2 General size? Fits on a desk Size 2 Sort by size? Yes Sorting 4 What are your likes of a vibratory feeder? Tunable, durable Variable speed, Durability 3 3 What are the particles being deposited into? bucket Transportation 5 Do they need to be oriented a certain way? Sorting Sorting 4 What kind of shapes will the particles make? Symmetrical? Rolling? Convex hull No angles Sorting 4 How will the particles enter the feeder? Hopper/funnel Transportation 5 6 3.1.1 Record of the user needs interview See table above. 3.1.2 List of identified metrics See table above. 3.1.3 Table/list of quantified needs equations See table above. 3.2 CONCEPT DRAWINGS Figure 4 - Concept Drawing 1 Figure 5 - Concept Drawing 2 7 Figure 6 - Concept Drawing 3 Figure 7 - Concept Drawing 4 3.3 3.3.1 A CONCEPT SELECTION PROCESS. Concept scoring (not screening) Table 2 - Concept Scoring 8 3.3.2 Preliminary analysis of each concept’s physical feasibility Concept 1: For concept 1, there will be some difficulty around sourcing the components for the trough. The sorting tray at the bottom might become difficult to fabricate to the necessary specifications to work in the application of defect sorting. Concept 2: This concept will have some physical limitations around cost. While this design is well built for longevity, its cost might outweigh the gain from its longevity. That being said, the cost of the materials is a necessary component for this project and may not be that big of a factor in the long run. Concept 3: The main concept restraint for this design is the motor. While this design is commonly used in the field for small vibratory feeders, it would be difficult to service and replace. Whereas having an independent motor would greatly simplify the servicing or replacement without having to completely dismantle the whole unit. Concept 4: This concept runs into the same issue as concept 3, the motor might cause complications further down the line if/when service and/or replacement is needed. 3.3.3 Final summary statement 3.4 PROPOSED PERFORMANCE MEASURES FOR THE DESIGN Overall, the concept that we decided to go with was concept 2. While concept 4 did technically win the scoring, we are unable to source the motor that would be required and therefore cannot proceed on with it. However, concept 2 – being only two points away - was so close to concept 4 so it will not be a noticeable downgrade in any way. Because of this we had no reservations going with this concept instead. 3.5 REVISION OF SPECIFICATIONS AFTER CONCEPT SELECTION Compared to the other concepts, its ability to transfer products effectively, efficiently, and in the manner that we want goes above the other options. It will have greater adjustability and will be able to move more products – hopefully hitting that 1000 parts per minute goal. Even though it will be compact in nature, it will be able to manage these large loads due to effective designs and proper movement of products. While it may slightly lack in its orientation goal of the product, the result of transferring the product to a bucket will be unmatched. Because of the design and certain features within that design, this feeder will save on some of the intricate welding that will be required, and more importantly, will save on some of the very large costs this project will entail. There are obviously some things we are worried about such as the orientation of parts and some certain components, however, we will be able to make adjustments as we go and figure out mechanisms to ensure our feeder delivers the parts in the most efficient way possible. 9 4 EMBODIMENT AND FABRICATION PLAN 4.1 EMBODIMENT/ASSEMBLY DRAWING Figure 8 - Embodiment Drawing 4.2 PARTS LIST Table 3 - Parts List No. Item Description Vendor Part Number Unit Unit Cost Qty. Material 1 US Stock 110V, 100W Motor eBay 164178084183 Each $69.99 1 2 Tempered Steel Compression Spring McMaster Carr 96485K135 Each $11.75 4 Carbon steel 3 Plywood, 11/32" x 4' x 8' sheet Home Depot 112590 Each $33.33 1 Pine Wood 4 1in x 3in x 8ft. Kiln-Dried Whitewood Home depot 418545 Each $10.42 1 Whitewood 5 Vibration-Damping Mount w/ Unthreaded Hole McMaster Carr 60525K25 Each $4.08 4 PVC Plastic 6 #8 x 1-1/2 in. R4 Multi-Purpose Star Drive Flat Head Screw Home Depot 96085 Box $9.98 1 Steel 7 Titebond III 8 oz. Ultimate Wood Glue Home Depot 202960636 Each $5.97 1 Glue 10 4.3 DRAFT DETAIL DRAWINGS FOR EACH MANUFACTURED PART See appendix C for detailed drawings. 4.4 DESCRIPTION OF THE DESIGN RATIONALE During the embodiment design part of this project, we narrowed down some of the features and materials ideal for this build. I will discuss those rationales and engineering analysis below. First, the subject of features was heavily discussed during the embodiment part of the project. We discussed the necessary components needed for this design and some other ones that would be beneficial but not critical. Of those, we decided on the base-frame design for the project. This design allowed for us to build the parts feeder to last and use less expensive materials, of which I will get into later. Additionally, this design was allotted for us to build it in the time frame allotted for this class. Second, we chose the material of wood as the primary choice for our vibratory parts feeder. This material allowed us to be proficient in our delivery time and meet the deadline for this project. This was primarily driven by the lead-times/availability of materials and the commonality of tools available to build wooden projects. While a steel version might last a little longer, the materials would be difficult to get within the timeframe of this project. Finally, the size of the vibratory parts feeder was decided upon via the approximate size of a desktop. Due to the size of the particles from Group 7’s project, the size of the feeder would not need to be larger than that would fit on a desktop. The particles that Group 7 is creating will be ~6mm tetrahedral shaped. 5 5.1 ENGINEERING ANALYSIS ENGINEERING ANALYSIS PROPOSAL Analysis done before build 1. Identify major areas for errors – NH a. We will work through to identify areas with potential error within our chosen prototype. These errors can/will include: i. Ease of build ii. Cost of project iii. Longevity of product/machine iv. Tools available for prototype construction – will dictate what materials can be used v. Feasibility of design – too complex and we will not meet the deadline 2. Plan the build timeline for the project - PV 3. Identify long-lead items – AS 11 Analysis done after build 1. Structure analysis – NH, PV, AS a. Verify the base frame and trough are structurally sound b. Verify the frame to trough connection is secure and will retain longevity during operation. 2. Motor analysis - PV a. Analyze motor at different speeds to determine which one(s) work the best 3. Parts sorting analysis - AS a. Allow vibratory parts feeder to operate with tetrahedral parts to determine if the trough and sorting features work as intended. 4. Cost analysis - NH a. Verify project was done within budget. b. If not; i. Identify the sources of overspending in the project. Noah Herrin - NH Patrick Vastola - PS Adin Stambolic - AS 5.1.1 Signed engineering analysis contract Figure 9 - Signed Contract 5.2 ENGINEERING ANALYSIS RESULTS 5.2.1 Motivation The points of analysis were carefully chosen to fully look at the critical aspects of this project. The main motivation behind these analysis points is to be as efficient as possible in preparation for the prototype build and generate the best outcome after the prototype is complete. Before the prototype build, we will identify some major areas of possible error. These areas include; ease of build, cost projection, longevity of machine, tools available for construction, and feasibility of design. Identifying these areas will help us plan to avoid mishaps along the way. After the prototype, we have a set list of areas to review. Those areas are as follows; structural analysis, motor analysis, parts sorting analysis, and cost analysis. Each of these points will be driven off the whole process of prototype development and execution. Retaining documents and notes from along the way will be vital to analyzing the prototype in retrospect. 12 5.2.2 Summary statement of analysis done To summarize the engineering analysis done on this project, I have broken it down into several categories; vibrations, structural, and functional. For the vibration’s analysis (figure 1), we used formulas below to calculate the oscillating motion of the trough/springs. Next, we used statics to calculate the structural rigidity of the build (figure 2). Lastly, we formulated guidelines that we wanted the function of the operation to follow. Figure 10 - Vibration Analysis of System Figure 11 - Structural Analysis Equations 13 5.2.3 Methodology In order to perform the described analysis above, we had to break it down into several sections. For the initial analysis, we used the risk predictor tool to project areas where our attention should be focused on. We outlined 10-15 risks that we believe could cause the project to be delayed. The top items generated from that tool were out of focus before going into the prototyping stage of the project. The main areas for concern evolved around the schedule and budget for the project. For the schedule, we used the Microsoft project timeline created for the project management and collaboration appendix 3 to project the deadlines of each task. This helped us identify some areas of error based on current standing and expected hours to complete. For the cost, we utilized the cost breakdown spreadsheet from project management and collaboration appendix 5 to track out materials needed and ordered to verify we stayed on budget. The analysis done after the prototype build was more hands-on, whereas the “before” analysis was more hypothetical. We analyzed the frame members by loading the system down with the expected product weight and measuring any deflection in the frame or trough. Additionally, we visually inspected the trough supports and springs when the system was underweight to verify it was handling the load properly. Next, we analyzed the motor by means of dropping the product on the trough and calculating the speed at which it passed and fell off the end. The motor speed can be altered by how fast the product stream is moving. Furthermore, while the product is running through the trough, we inspected how the parts sorting feature was working by visually identifying the parts were being oriented properly. Lastly, a cost analysis will be done on the final cost of the build. This can be calculated by adding up the materials purchased. 5.2.4 Results The results from our analysis above provided two things. First, the analysis of the physical components allowed for us to see how this would hold up. Second, the hypothetical analysis showed us the risks possible, the costs of delays, the overall projected cost of the project, and the added cost by delays. Looking at the analysis of physical components, we can surmise that the structure will hold up to the expected forces exerted by the vibrations of the motor and springs. Also, reviewing the results from the hypnotical analysis we can determine that the project has a few sources of possible risk. These areas of risk can be combated with extra attention, so they do not fall behind. 5.2.5 Significance How will the results influence our prototype? What materials did we use and what dimensions? The results from our two types of analysis have meant that the design of our vibratory parts feeder will slightly change. Due to structural forces, the base of the feeder will need to increase in overall size. Additionally, the motor originally spec'd will need to be changed due to function of the trough and base. Furthermore, the trough design will change slightly depending on how well the 14 sorting feature works. This is something we have theorized but not proven in a real-world test. This will be tested during the building of the project and improved upon as time progresses. The material needed for this project was originally going to be steel. However, during the risk analysis we discovered that the metal shops we originally thought would be available to us were closed due to maintenance and/or upgrades. From this information, we then decided on wood as our primary material for the project. The base frame and trough would be made of wood and most of the other components would use steel, such as fasteners and springs. Next, the dimensions of the build would need to change due to the material changes and structural forces needed. Originally, the design called for 18” base length by 6” base width. This area will increase by a factor of one and a half. That being said, the design will be as-built from this point on and we will make updates when we have built the actual project. Additionally, the height will inevitably change due to springs available to us within the spec we need. 6 RISK ASSESSMENT Figure 12 - Risk Assessment Methology 6.1 RISK IDENTIFICATION The risks of this project include, but are not limited to: ● ● Short-term rigidity Schedule Alignment 15 ● ● ● ● ● ● ● ● ● ● 6.2 Task Delegation Materials Ordering Budget Testing Analysis and documentation Long-term reliability Initial Project Scope Limited Access to Tools Limited access to specific parts Motor speed control RISK ANALYSIS Table 4 - Risk Analysis 6.3 RISK PRIORITIZATION Given the analysis of the risks, we decided to focus on the following items; materials used to address long-term concerns, ordering parts ahead of time to address the lead times concern, and fine tuning the project scope to address the delays concern. The aforementioned risks, among the rest of the risks, can be found in the photo above. 7 7.1 CODES AND STANDARDS IDENTIFICATION With the knowledge that springs would be an integral part to the performance, they were a logical piece of the assembly to compare to current codes and standards. Springs are manufactured to very specific sizes and properties. Values such as K-value, inner and outer diameter, type of steel, wire diameter, length when compressed and max load all dictate when and where they can be used. The compression springs used in this assembly needed to be a certain length and stiffness to produce effective vibration. The following standards indicate recommended range of vibration for springs in different applications. 7.2 JUSTIFICATION 16 The first code was chosen because the springs would be directly behind how our tray would vibrate. If our springs were too stiff or too loose, the tray wouldn’t vibrate enough or vibrate too much, respectively. Taking into account the shape of the spring, naturally, a cylindrical helical compression spring would be our best option. The codes and standards allowed us to further learn about the values that would impact performance. The second code was chosen because knowing the severity of vibration for our motor would be paramount to identifying if our project would fail or succeed. Too little and there'd be little more than a murmur. Too much and the project itself may collapse. The code helped us identify if the vibration would be good or satisfactory in this regard. 7.3 DESIGN CONSTRAINTS See below. 7.3.1 Functional ISO 22705 - Cold Formed Cylindrical Helical Compression Springs 7.3.2 Safety ISO 10816 - Vibration Severity Standards Table 5 - Vibration Severity Standards 7.4 SIGNIFICANCE Identifying codes and standards before the prototype or engineering work has begun is crucial to the success of the build. Recognizing the standards similar to what is followed in the field can greatly improve the odds of identifying mishaps early into the project. It is for this reason that identifying and following ISO standards is so significant to the success of the project. 17 8 8.1 WORKING PROTOTYPE PROTOTYPE PHOTOS Figure 13 - Prototype Photo 1 Figure 14 - Prototype Photo 2 18 8.2 WORKING PROTOTYPE VIDEO Vibratory Parts Feeder 8.3 PROTOTYPE COMPONENTS Figure 15 - Motor 1. Motor – Our motor was a 110V, 3.8A, 6.5kg, 3600 RPM, with two 0.6lb offset weights located on either end of the motor. Because this provided too powerful of a vibration, it was modified so that the weights were cut in half in order to provide a more stable vibration. The motor was bolted into our frame. Figure 16 - Spring Supports 2. Spring Supports – Our spring supports were created by taking angled pieces of wood and screwing in a plastic pipe support on both pieces. A metal bracket was then 19 screwed into both the angled piece of wood and the frame to give some rigidity to the support. A spring was then placed within the supports to give it additional bounce. This was done 4 times (2 on each side of the frame) to give proper support to the tray. Figure 17 - Tube Support 3. Tube Support – Tube support that was placed in the middle of our design. This was done in a similar fashion by taking 2 angled pieces of wood and screwing in the plastic pipe support. 2 different pieces of pipe (one goes inside the other) were then placed with the plastic to act as a sort of pseudo-pneumatic system to connect our frame to the tray. Figure 18 - Tray 20 4. Tray – Tray made from plywood with the dimensions of 23.75 in by 15 in. The border was made using plastic corners. This was then connected to the 4 spring supports on the side with the middle tube support as well. 9 DESIGN DOCUMENTATION 9.1 FINAL DRAWINGS AND DOCUMENTATION 9.1.1 Engineering Drawings See Appendix C for the individual CAD models. 9.1.2 Sourcing instructions Given the bill of materials below (appendix B), sourcing the materials required for this project should be relatively easy. The majority of the components are from McMaster Carr and a home improvement store (Lowes or Home Depot). The motor was purchased on eBay, but another online seller would also suffice. Table 6 - Purpose Table No Item Description Purpose 1 US Stock 110V, 100W Motor The motor is intended to vibrate the trough and will be mounted to the base 2 Tempered Steel Compression Spring These springs transpose the force/vibrations of the motor to the trough. 3 Plywood, 11/32" x 4' x 8' sheet The plywood will be used not only for the bottom of the base but also the bottom of the trough 4 2in x 4in x 8ft. Kiln-Dired Whitewood This wood is used for the base assembly 5 Vibration-Damping Mount w/ Unthreaded Hole These will be used as the feet for the base unit 6 #8 x 1-1/2 in. R4 MultiPurpose Star Drive Flat Head Screw These screws will be used to fasten the base frame together 21 7 Titebond III 8 oz. Ultimate Wood Glue The wood glue is used to secure the base and trough 8 SharkBite Plastic Suspension Clamps These clamps are used to attach the base from to the trough 9.2 7 FINAL PRESENTATION See link in section 8.2 APPENDIX A - PARTS LIST See section 4.2 for parts list. 8 APPENDIX B - BILL OF MATERIALS Table 7 - Bill of Materials No Item Description Vendor Part Number Unit Unit Cost Qty Material Total 1 US Stock 110V, 100W Motor eBay 393426794827 Each $69.99 1 N/A $69.99 2 Tempered Steel Compression Spring McMaster Carr 96485K135 Each $11.75 4 Carbon steel $47.00 3 Plywood, 11/32" x 4' x 8' sheet Home Depot 112590 Each $33.33 1 Pine Wood $33.33 4 2in x 4in x 8ft. Kiln-Dired Whitewood Home depot 418545 Each $10.42 1 Whitewood $10.42 5 Vibration-Damping Mount w/ Unthreaded Hole McMaster Carr 60525K25 Each $4.08 4 PVC Plastic $16.32 6 #8 x 1-1/2 in. R4 MultiPurpose Star Drive Flat Head Screw Home Depot 96085 Box $9.98 1 Steel $9.98 7 Titebond III 8 oz. Ultimate Wood Glue Home Depot 202960636 Each $5.97 1 Glue $5.97 8 SharkBite Plastic Suspension Clamps Lowes 818224 Each $0.55 1 Plastic $4.40 22 9 APPENDIX C – COMPLETE LIST OF ENGINEERING DRAWINGS Figure 19 - Top Level Assembly Figure 20 - Sub-Assembly 1 23 Figure 21 - Sub-Assembly 2 Figure 22 - Part Drawing 1 24 Figure 23 - Part Drawing 2 Figure 24 - Part Drawing 2 25 Figure 25 - Part Drawing 3 Figure 26 - Part Drawing 4 26 Figure 27 - Part Drawing 5 Figure 28 - Part Drawing 6 27