DESIGN AND CONSTRUCTION OF AUTOMATIC CHANGE-OVER FOR THREE PHASES ABSTRACT The main aim of any electric power supply in the world is to provide uninterrupted power supply at all times to all its consumers. Although in developing countries, the electric power generated to meet the demands of the growing consumers of electricity is insufficient hence instability and outage. Power instability or outage in general does not promote development in the public and private sector. The inventors do not feel secure to come into a country with constant or frequent power failure. These limit the development of industries. In addition, there are processes that cannot be interrupted because of their importance. For instance, surgery operation in hospitals, transfer of money between bank and lots more. Power instability and outage in developing countries (Nigeria) creates a need for alternative source of power to backup the main supply. Automatic changeover switches find a wide application scope wherever the reliability of electric supply from the utilities is low and it is used in lighting motor circuits wherever continuity of supply is necessary. For switching to an alternative source from main supply and vice versa. This project is a design of an automatic changeover switch this means that when there is any mains failure, the automatic changeover switch will change to an alternative power supply (GENERATOR) and back to the main supply when it is restored. The purpose of this project is to maintain constant supply to the main circuit that is being supplied by making up for the time delay that usually accompanies the manual switching from one source to another. The design comprises of the power connection circuit and control connection circuit. The main components to be used include contactor, relay, timers, rectifiere.t.c. i TABLE OF CONTENTS Title Page i Certification ii Acknowledgements iii Abstract iv Table of Contents v CHAPTER ONE 1.1 Introduction 1 1.2 Aim and Objective of the Project 3 1.3 Scope of the Project 3 CHAPTER TWO 2.1 Literature Review 5 2.2 Manual Change-over Switch 5 2.3 Automatic Change-over Switch 6 2.4 Related Work 10 2.5 Reasons for Automatic Change-over Switch 16 2.6 Problems of Automatic Change-over Switch 17 ii CHAPTER THREE 3.1 Methodology (Material and Methods) 18 3.2 Circuit Conductor 18 3.3 Circuit Breaker 19 3.4 Reset Timer 20 3.5 Contactor 21 3.6 Operation of Timer Delay 24 3.7 Principle of Operation 25 CHAPTER FOUR 4.0 Construction 29 4.1 List of Component Used 29 4.2 Vero Board 29 4.3 Bread Board 30 4.4 Soldering Iron 33 4.5.1 Testing, Maintenance and Discussion 36 4.5.2 Polarity Test 36 4.5.3 Insulation Resistance Test between the Live and Neutral Conductors 37 4.5.4 Earthling Test 37 iii 4.6 Maintenance of Contactor and Installation 37 CHAPTER FIVE 5.1 Conclusion 39 5.2 Recommendation 39 References 40 Bill of Engineering Measurement and Evaluation (BEME) 41 iv CHAPTER ONE 1.1 INTRODUCTION Power instability in developing countries creates a need for automation of electrical power generation or alternative sources of power to back-up the utility supply. This automation is requiring as the rate of power outages become predominantly high. Research in the field of electrical electronics engineering has led to the tremendous discovers and inventions especially in the area of automation and power control. These invention have been useful in solving the over-in (Mustapha, 2006). Creating problem posed by power generation, distribution and control, which has been a cause of concern especially in the third world countries (developing countries) like Nigeria. Most industrial and commercial process is dependents on electric power and if process of a change-over is manual, serious time is not only wasted but it creates room for human error (in the area of change over connections) which could result in great economic loss (Ahmed, Mohammed & Augusibo, 2006). This project is all about the construction of an automatic generator change-over panel with timer which aids in the switching over to alternation power supply authority i.e.Power Holding Company of Nigeria 1 (PHCN) popularly known as NEPA which is the main power regulating body in Nigeria. This project consist of circuit breakers, electromagnetic contactor which carry heavy load current relay which work with the principle of electromagnetic induction because it will receive electrical signal to trigger and neumatic timer all incorporated and interconnected to achieve the desire goal (Jenyo, 2007). Also this project is constructed in such a way that provision is made for manually operation (it can be operated manually) when necessary for required for example, in the situation whereby voltage supplied by the authority (PHCN) is fluctuating and one may decided not to use it, so the constructed automatic change-over panel can be permanently switch to generator set temporarily pending the time that utility supply is stable moreover in the hospital where where surgery operations is needed to be carry out and power outage for even five second cause damages, one may decide to neglect the supply from authority (PHCN) and permanently switch the panel to manual operation pending the time or period by which surgery operation is completed. During the pending period this change-over will be working continuously in manual operation. Fill someone or the operation has to switch over to automatic operation. As said earlier, provision is made for these types of 2 generation in this project and there is separate switch that performed the function. 1.2 AIM AND OBJECTIVE OF THE PROJECT The aim of the project is to design and construction automatic change-over switch load from the mains power supply (PHCN) to a backup power supply (Generator) with simplicity. The advantages of this project cannot be over emphasized, since outage is a major problem is the advent developing nations like Nigeria, for example, power failure of minute in an airport terminal can create losses that could run into millions of dollars due to loss in air traffic system control the ability for back-up to start and change-over automatically becomes imperative under such circumstances. Also, this project could play a large role in the security in banks and companies i.e. an outage of up to ten minute in an organized setup is enough to do all the damage required with such an automatic changeover device in place the generator backup would no longer have to depend on security men and of course reduced fear of system breakdown in the companies there by ensuring smooth running of economics activities. 1.3 SCOPE OF THE PROJECT 3 Basically, this project is a three phase automatic change-over device with the power capacity of 50KVA. Generator as deducted from my calculations it shows that generator of power rating ranging from 0.5KVA to 50KVA is required to be use for this project though the contacts of electromagnetic contactor relays and circuit breakers. Also the maximum load current should be between the ratings of 10A to 90A load current. Therefore the use of 10Amperes in this project is because of future extension. 4 CHAPTER TWO 2.1 LITERATURE REVIEW The purpose of this project is to design and construct this unique equipment that provider a solution to the power supply problem we are facing in Nigeria today. The automatic change-over switch can be describe as a unique power supply to another as well maintaining constancy in the supply to a particular network load this equipment to be designed and constructed in this project will interface between two different electrical power source (e.g. the main supply and the generator). The main source of supply to the unit is obtained directly from the public supply (PHCN) the relaying and triggering system serve as an interface between the supply and the load hence the load is not directly couple to the public supply. The triggering units sense the failure in supply and immediately the ignition switch of the generator. Power change-over switch are two different mode of operation namely. 2.2 MANUAL CHANGE-OVER SWITCH In this mode of operation when there is any mains failure i.e. (PHCN) outage there is need for personnel to start the generator manually and wait till the generator attains synchronous speed. Only 5 after the generator attains synchronous speed can the operators transfer the load to the generator. In the event that mains supply is restored the operation has to the operation has to transfer the load back to the mains supply and turn OFF the generator this is done by manually relapsing the change-over breaker. To ensure safety of this operation the two breaker of the change-over switch must be operation are quit cumbersome. Restoration of power is usually a prolonged process which cause delay. The process may also result in heavy losses and damage could be done to sensitive loads during this manual process. 2.3 AUTOMATIC CHANGE-OVER SWITCH In this mode of operation when there is any mains failure there is no need of the employment of the personnel as the change-over switch will start automatically it sensing power from the mains supply and there after switch the loads to the generator supply upon it attaining synchronous speed. Upon restoration of the mains supply the switch again sense it and transfer the load back to the mains supply. The type of automatic change-over switch used which differs from the other (semi-conductor controlled switch type) in terms of the type of load transfer or switching panel is the contractors, this design of load transfer panel makes use of mainly relay and contactor combination, its 6 operation is based on the hierarchical rank of contactor relays. It consists of some relays which serves several purpose these are :1. Mains Contactor It carries the bulk of the load its auxiliary when the mains supply (PHCN) in ON, the mains contactor responds to the input by closing its contacts which enable it to get energized causing indicator lamps on the panel to illuminate of these lamps indicate that the mains supply is ON. 2. Mains Auxiliary Contactor It is usually present in the generator circuit when there is power outage in the mains supply the contact of the mains auxiliary contactor which is in the generator circuit close thereby sending a signal to start the generator 3. Generator Contactor After starting the generator automatically, the load is then transferred to the generator contactor 4. Generator Auxiliary Contactor It is the generator auxiliary contactor that is responsible for ensuring that only a power sources gets to the load at point in time. When there is mains supply failure, it break the mains supply line to the load before the generator line is activated. Upon 7 restoration of the mains power supply the generator auxiliary again break the generator line before the load is transferred to the mains supply. Because this design makes use of relay and contactor combination it is said to have the following advantages It can switch alternating current It can switch high voltage It is useful when high current are to be used It is switch many contacts at once. This quality make them flexible It has the following draw back Poor sensing ability to fluctuation due the fact that relays do not function optimally at low voltages. Switching time in the event of mains power supply outage is low because switching is done in the basis of energizing and de-energizing of the relay coil Relays generate a lot of heat during switching action which could caused short circuits which are very hazardous Relays draw a lot of power from the power supply thereby increasing the overall power consumed by the load 8 It time like this, there is really no new invention rather what we have now are just improvement and innovation on fundamental principle of obtaining the desired result. Hence, the automatic change-over switch that is designed and constructed is an improvement on what other have done over the years. A past project was designed such that is being supplied from just three power sources. The present design is such that it would take two different sources to simultaneously and also give preference to this power sources with the unique ability to ensure that there is always power supply to the load at all times. 9 2.4 RELATED WORK The present invention that related to an automatic change over device has been designed for a power sources to automatically switch over system for supplying electric power to an electric load in such a manner that electric power output from an engine generator in supplied to the electric load upon occurrence of the power failure of a regular power sources system as it is been used by used patent on 21st may, 2002. There is an automatic switch-over known, for example from Japanese patent application laid-open No 5-64382 and the likes which is designed so that a switch in change-over to supply electric power output from an engine generator to an electric load upon occurrence of power failure of a regular power source system. In such an automatic switch over device for the power source it is necessary not only to provide an emergency automatic switch-over mechanism, but also to provide a measure for enabling switch by an operator’s manualsoperation in case of failure or the like of a control unit. This automatic switch-over devices for a power source comprise switching unit which has first and second individual contacts which is individually leading to a regular power source system and an engine 10 generator and common contact leading to an electric load where the common contact can be alternatively electrically controlled unit for controlling the switching unit in such a manner that the common contact is electrically connected to the second individual contact in response to the regular power source system being electrically failed and the common contact is electrically connected to the first individual contact in response to the restoration of said regular power source system, where in the switching unit is made of a relay which consist of : A see-sew-type turn member carried on a support frame for turning movement between first turned positions in which the turn member permits the common contact to be electrically connected to the first individual contest and a second turned position in which the turn member permit the common contact to be electrically connected to the second individual contact. A spring member for exiting a spring force for retaining the turn member in one of the first and second turned position in response to the turning movement of the turn member passing through a central point between first and second turned position. A first solenoid capable of exerting an electromagnetic force for driving the turn member toward the turned position against the spring force of the spring member. 11 A second solenoid capable of exerting an electromagnetic for driving the turn member toward the second turned position against the spring force of the spring member. With such arrangement of the feature the supplying of electric power from the engine generator to the regular power source system and the supplying of the electric power from the regular power source system can be automatically switching manner by the control unit. According to a second aspect and feature of the present design in addition to the arrangement of the first feature a neumatic timer is incorporate to achieve the aim of letting the switching system switch OFF the generator set when not required for use in a case where power is not restored by the PHCN (supply). The present design has been achieve with the above circumstances in view and it is an object of the present invention to provide and automatic change-over for a power source where in the switching can be achieved by the operator’s manual operation without provision of a special mechanism. The above and other objectives features and advantages of the design will become appeared from the following description of the preferred embodiment taken in conjunction with the accompanying diagram (us patents issued 21st May, 2002 12 Fig. 2.1 Switching Transistor 13 Fig 2.2 Flip Flop 14 The circuit diagram of the flip flop and switching transistor stage of the related art. Another related art was the development of a single phase automatic change-over switch. This also related to the present invention i.e. it switches electrical power supply from public supply to generator in the event of a power outage or insufficient voltage but it is apply to single phase system while the present invention is apply to three (3) phase system, moreover, the system uses an electronic control circuit involving integrated circuit invention uses electromagnetic contactor and circuitbreaker for its operation. In this related art, the electronic control monitors the incoming public supply voltage and detects when the voltage drops below a level that electrical or electronic gadgets can function depending on the utility supply. In these cases, 160V is the limit in which the system changeover the public supply or generator. The sensor stage monitors the unregulated voltage dropped across R1and R2 as show in the above diagram in Fig.1.1 The voltage feeds an input on ICI which compare this input with a fixed reference across VR1. The drop across at 160V A.C is set as the reference. Any voltage drop below this, send a low to the input of the D15 flip flop to switch the transistor OOF is set mode. Once the transistor 1 switch OFF, the relay in de-energized and the contacts change-over. Two relays are connected in parallel RLA1 is 10A relays which switch the battery 12V to the ignition coil of the generator (starter coil) and switch it OFF once public supply is back. The second relay RLA2 is 30A relay that selects generator or public supply output to load as show in Fig. 1.1 The generator output is normally closed. Hence, once deenergized the generator output is fed to load and one energized (by the presence of public supply) the relay (normally open contacts connects public supply output to load). 2.5 REASONS FOR AUTOMATIC CHANGE-OVER SWITCH The purpose of this project is to design and construct a unique equipment that provide a solution to the erantic power supply problem we are facing in Nigeria today. The automatic change-over switch can be describe as a unique switching system which can be used to change from one power supply to another as well as maintaining constancy in the supply to a particular network or load. This equipment to be designed and constructed in this project will interface between two different electrical power sources. (e.g the main supply (PHCN) and the generator). 16 The mains source of supply to the unit is obtained directly from the public supply (PHCN), the relaying and trigging system serves as an interface between the public supply and the load, hence the loads is not directly coupled to the public supply the trigging unit is also coupled with the generator output to provide a connection between the generator and the load. When there is power outage form the public supply the relay and triggering unit sense the failure in supply and immediately trigger the ignitron switch of the generator 2.6 PROBLEMS OF AUTOMATIC CHANGE-OVER SWITCH Problem that can occur on the automatic change-over switch is when the relay is damaged the changeover switch will not be able to perform automatically. 17 CHAPTER THREE 3.1 METHODOLOGY (MATERIAL AND METHODS) This project is constructed using locally made materials with special consideration on economical, mechanical, electrical and other physical properties of materials. Since, the materials have those properties which are closely to one another; I found it very difficult to discard one from other, but with the advice of my project supervisor and some technician, I am able to choose those one that are that are more appropriate for this project, 3.2 CIRCUIT CONDUCTOR Conductor: is a material which offers a low resistance to the flow of current. And such a conductor for everyday use must be of low electrical resistance. (i) Of low electrical resistance (ii) Mechanical strong and flexible (iii) Relatively cheap for practical purpose Cable is the length of single insulated conductor (solid or stranded). A current carrying conductor form part of a circuit or final sub-circuit, but excluding the earth continually conductor. Note:- for frequency stop-starting, the cable may have to be heavier because starting current 18 Fig 3.1 Circuit Conductors 3.3 CIRCUIT BREAKER This is defined as electro-mechanical device design to make and break the electric circuit under normal and abnormal conductor such as those of short circuit, the circuit being broken automatically. The majority of circuit breaker is either oil or air blast types. Regulation 433-2 require the characteristic of the device (fuse or circuit breaker) protecting the circuit to be coordinated with the conductor forming the circuit such that. (i) Its normal current (fuse rating) or current setting for circuit breaker (IN) is not less than this design current which is the minimum or normal circuit current (IB). 19 (ii) The current which operate the fuse or circuit breaker, causing it to disconnect the circuit (RZ). does next exceed 1.45times the lowest of any current carrying capacities (IZ) for the circuit conductor, using formula: IB<IN<IZ and IZ<1.45IZ. (iii) It is not greater than the current-carrying (IZ)of the circuit conductor. Fig 3.2 Circuit Breaker 3.4 RESET TIMER A relay designed to operate after a calculated time delay is called a “timer relay” or timer. If the timer delay is fixed regardless of the input of the relay (in excess of pick-up value) the relay is termed “definite timer”. The amount of time delay may less for greater input to the relay, such relay are called “inverse” very inverse or “extremely inverse” 20 depending on the extent which relay is reduced for an increase in the input to the relay. A relay designed to have no intentional time is said to be instantaneous. START AND STOP BUTTONS These two push buttons are used to close and open the circuit respectively. The start push button is a normally open type (NO) while the stop push button is a normally close (NO) type to breaker the circuit when need arise 3.5 CONTACTOR Is a device designed for repeatedly making and breaking an electronic power circuit. It is usually operated magnetically. It can be operated in line or be remotely governed by pilot devices or relay. And when there is a supply to contactor coil it becomes energized for movements while if there is no supply it will breaker the contact. 21 Fig 3.3 Contactor PROCEDURE (i) A plate of copper metal not thicker than 2mm is taken to the workshop (ii) This is then cut into required dimension by the use of chisel and hammer (iii) After cutting into pieces is then drilled at the required place (iv) A file is used to smooth the shape in none accurate dimension 22 PRECAUTION (i) Tolerance should be given to each dimension of the hole to avoid unnecessary large hole (ii) The contactor must be of the same with the provided for it (iii) The hole for the contactor case should be wide enough to prevent friction during attraction and releasing of contactor (iv) Care should be taken not to use unnecessary high pressure during chiseling, this may damage metal sheet (v) A very sharp chisel should be used to accurate dimension otherwise the gap between the groove maybe chipped up and rendered the useless. ASSEMBLING OF THE AUTOMATIC CHANGE-OVER COMPONENT INTO THE CASING (I) The process of assembling the change-over panel was carried out based the terminal were set into the terminal rail and boded rigidly to prevent vibration (II) The return spring was then fixed to the right place in the contactor case (III) The reset time is then attached to the base of the case together with the rail stand 23 (IV) The contactor and circuit breaker attached to the rail stand and the contactor case is fixed in the right position in the terminal house (V) Pressing the contactor case against the force of the retaining spring and role whether the contactor is or not Fig. 3.4 front view of the 3.6 OPERATION OF TNMER RELAY Timer relay are based on the electromagnetic induction principle which can only be applied where the actuating quantity or quantities A.C, they cannot be operated by D.C, since we are primarily concerned with an A.C system. This may be good place to restate a basic principle which should be kept in the back every operations mind. 24 Relay operate for the reason only (i) The AC quantity to which the relay respond has reached the setting for which the relay is calibrated (ii) The timer relay contactor are closed some mechanism mean. This could be when time of change from utility supply to generator is reach in the panel or by someone poking the contactor either accidentally of intentionally and sometimes removing or replacing a timer relay cover will cause a relay to operate. 3.7 PRINCIPLE OF OPERATION The change-over panel consists of two (2) 100A circuit breaker which serves as a means of isolation and at the same time a protective device. The circuit breaker A is used to feed in the utility supply to the system while circuit breaker B is used to feed in the generator set supply to the system. Also in the panel, there are six (6) contactors, which are electromagnetic device that are design to carry current of difference capacities. Contactor A is load contactor that carries the utility supply to the load while B is equally a load contactor that carries the generator set supply to load. Contactor C is a control contractor which equally serve as relay the contractor is also been in operated with a relay timers monitor the function of the utility power contractor or load contractor. The stop 25 button is connected to supply from the red ohase through the normally close (NC) of the stop button to the contractor. Contractor C is equally meant to carry DC supply through the contractor for the purpose of supplying the contractor F. Contractor D serves the same function as that of C but is only monitor the generator set load contractor with the help of the timer on it. The relay timer on contractor D helps in relaying the operation of contractor D helps in relaying the operation of contractor B so that the generator set will not be loaded before it maintain stability. Contractor E is mean to discharge the work of the kick starter on the generator set and to equally control work of operator D when the generator must have given out an output. Contractor F is a DC contractor of the 12v. it is used to start the kick starter of the generator set. It is connected through the P= IL VcosѲ But it is 3 Phase ...P=3L Vcosϴ P= power supply in watts Where IL= load current in Ampere V= supply voltage in volts 26 Cos = power factor (p.f) but p.f ... cosec 0.8 P = 50KVA IL=? V = 415V (3phase) ... IL = Since we cannot set material for exactly 86.9A, therefore we decide to choose for 100A and also for future extension. 27 Automatic Change-Over Panel 28 CHAPTER FOUR CONSTRUCTION 4.1 LIST OF COMPONENT USED The following electronic components used in the project are list below (1) Voltmeter (2) Casing (3) Vero-Board (4) Transformers DC 12V (5) Diodes (6) Capacitors 100 (7) Resistors 4k (8) Contactors (9) 16mm2 Cables (10) 1ooAmp connector (11) Bolt and Nuts (12) Indictor light (13) Relay three phase (14) 555IC timer 4.2 VERO BOARD: is a brand of strip-board, a per-formed circuit board material of cooper strip on an insulating board which 29 originated and developed in the early 19960s by the Electronics introduced as a general purpose material for use in constructing electronic circuit differing from purpose-designed printed circuit board (PCBs)in that a variety of electronic circuits may be constructed using a standard wiring board. The first single-size Vero-board which, with world-wind use over five decades, have become knownas strip-board are own taken to be synonymous. The VPE Electronics department was formed early in 1959 when managing director Geoffrey Virden-Roe hired two former Saunders-Reo Ltd employees, peter H Winter (aircraft design department) and Tony Fitz Patrick (Electronics division). After the failure of a project to develop machine tool control equipment the department remained remain operative as a result of electronics material Vero-board. The printed circuit board (PCB) had become commonplace in electronics production by the mid 1905s and new equipment utilizing PCBs was displayed at the 1959 Radio and Electronics components manufactures federation (RECMF) exhibition held in Dorchester hotel. Production of the proposed new product, Vero-board, was undertaken by the machine tool department. 30 Bought in sheet of 1.6mm (0.2in) copper-clad SRBP printed circuit material were out to give 122mm x 456mm (48in x 18in) size boards with the individual boards then being machined to form the final product according to the original Vero-board specification. A multiple milling cutter with suitably shaped cutting teeth, was fabricated to be used in removing part of the bonded copper on each board leaving twenty one (21) conductive strip. The machining problems were encountered due to the nonavailability in 1960, of advanced printed circuit board milling and drilling techniques production rates improved and on 1961 Vero electronics Ltd was formed as a separate company to market the increasing sales of Vero-board Fig 4.1 Vero Board 4.3 BREAD BOARD (or proto-board): - is usually a construction base for prototyping of electronics the term “Breadboard” is commonly 31 used to refer to a solder less breadboard (plug board). A breadboard was originally was a flat wooding cutting board use to support to a loaf of bread (or other foods) while it was been shed; this original meaning is still in use but has a new additional meaning as “ a base for prototyping” the concept of “breadboarding” as prototyping is not confined to be use by mechanical engineers. Because the solderless breadboard for electronics does not require soldering, it is reusable this makes it easy to use for creating temporary prototypes and experimenting with circuit design.Older breadboard types did not have this property.A stripboard (Vero-board) and similar prototyping printed circuit board, which are used to build semi-permanent soldered prototypes or one-offs, cannot easily be reused. A variety of electronic systems may be prototyped by using breadboard for small analog and digital circuit to complete central processing unit (CPUs) In early days of radio, amateurs nailed bare copper wire or terminal strips to a wooden board (often literally a cutting board for bread) and soldered electronic component to them. Sometimes paper schematic diagram was first glued to the board as a guide to placing terminal then components and wires installed over their 32 symbol on the bread board schematic. Using thumbtacks or small nails as mounting post was also common. Breadboards have overtime, with the term now being used for all kind of prototype electronic devices for example. Us patent 3,145,483, field in 1961 and granted in 1964; describe a wooden plate breadboard with mounted springs and other facilities. Us patent 3,496,419. The breadboard most pluggable (solderless) breadboard it was designed by Ronald Portugal of El. Instrument inc. in 1871. Fig 4.2 Breadboard 4.4 SOLDERING IRON:-is a hand tools use in soldering it supplies heat to melt the solder so that it can flow into the joint between two work pieces. A soldering iron is composed of heated metal tip and an 33 insulated handle. Heating is often achieved electrically by passing an electric current (supplied through an electrical cord or battery cables) through a resistive heating element. Cordless iron can be heated by combustion of gas stored in a small tank. Often using a catalytic heater rather than flames simple irons loss commonly use than in the past where simply a large copper bit in a handle, heated in a flame. Soldering irons are most often used for installation, repairs and limited production work in electronics assembly. High volume production lines use other soldering methods. Lines irons may be used for soldering joint in sheet metal object less common uses include pyrography (burning designs into wood) and plastic welding. Fig 4.4 Soldering Iron 34 Voltmeter Voltmeter is used to indicate the voltage of the generator and that of the utility supply Casing This is the structure which enclose the main construction of the automatic change-over panel. It is constructed using metal sheet of thickness 2mm. the shape of the change-over panel is first drawn on a plane paper with dimension that will adequately accommodate the change-over panel. The required dimension is then traced out on the iron sheet chisel and hammers where used to cut the traced end. After this, each part are joined together by the use of welding machine and the necessary holes for both and screw where drilled on the change-over house required. After the construction, this change-over panel is then painted. The tools used for the construction are: Chisel Hammer File Welding machine 35 4.5.1 Testing, maintenance and discussion Testing is an important process in the engineering field especially in both electrical and electronics engineering. Therefore, testing can be define as the process by which any faulty condition is detected before a dangerous situation arose. Having designed and construction or installed s system with an appropriate selected materials component and equipment what now remain is to put the system into use. However, before the system is put use, it must be tasted and inspected to ensure that is complies with regulation of installation. Below is the test carried out. Polarity test Insulation resistance test between the alive and neutral conductors Insulation resistance test between earth and non-earthling conductors Earthling test 4.5.2 POLARITY TEST This test is carried out on the construction of automatic change- over panel to ensure that only live conductor is taken through the beaker on the load contactor. 36 4.5.3 INSULATION RESISTANCE TEST BETWEEN THE LIVE AND NEUTRAL CONDUCTORS An insulation resistance test was made between live and neutral conductor to ensure that there are no short-circuit in the wiring One lead from the insulation tester was connected to the outgoing live terminal and the other to the neutral of the main switch. The instrument is operated and accurate reading was reading out. 4.5.4 EARTLING TEST This test carried out to ensure that there is no leakage to the body of appliance. On led of ohm meter is placed on conductor and the other lead to the body of appliance. Zero resistance indicates that there is no leakage to the body. 4.6 MAINTENANCE OF CONTACTOR AND IINSTALLATION Generally the contact and wiring of the contactor should be properly maintained for adequate functioning of the contactors. In addition, the following should be a also be put into consideration. To replace an operating coil, the contactor must be removed from enclosure and the following procedure must be under taken. 37 (i) Remove the spring-clip on either side of the contactor, carefully live the auxiliary contact compress coil magnet slight and take whole magnet system and moving contact carries from auxiliary contact button (ii) Invert the assembly and lift out the lift magnet and coil vertically, taken care that the magnet spring remain in place. Note the position of the coil terminations. (iii) Change the coil and re-assemble the unity by reversing the above procedure, remembering to compress slightly the magnet when replacing the auxiliary contact. 38 CHAPTER FIVE 5.1 CONCLUSION The automatic change-over switch has immense advantage in every area where power is required it is a fact that there is hardly any aspect of human life were electrical power is not required, at home, offices, hospital, etc. It find a wide application scope, wherever the re-ability of electrical supply is necessary, for switching to an alternative source from main. 5.2 RECOMMENDATION The automatic change-over switch is needed in every home and offices because of the fact that it’s reliable, it’s durable, and it’s affordable and is ability to provide immediate automatic switching from the public power source to other sources. It is recommended that further work be done on this change-over switch on large scale, for instant an automatic change-over switch that can be use in an industry. 39 REFERENCE B.L. and A.K. Theraja (1997): Electrical Technology, S. chand company LTD Engr. A.O Aduloju (2003): Electrical Power System, Evidence Nigeria Venture Engr. M.B Jenyo (2007): Electrical Power System III & IV lecture Notes, Unpublished Engr. T.A. Mustapha (2006): Electrical Power System I & II inn lecture Notes, unpublished Internet Research: http://www.electricalsolution.com M.S. Ahmed, A.S. Mohammed & C.B. Augusibo (2006): Development of a single Automatic change-over switch Federal University of Technology Minna. US patent issued (2002):Automatic Generator switch-over Device for power source, http://www.patentstorm.us 40 BILL OF ENGENEERING MEARSUREMENT AND EVALUTION (BEME) The table below shows the cost estimate in naira and kobo of constructed automatic change-over panel. Bill of Engineering Measurement and Evaluation S/No Description of Quantity Rate Amount materials with Required N:k N:k complete specification 1. Transformers 2 500 1,000:00 2. Diodes 8 50 400:00 3. Capacitor 4 50 200:00 4. Resistors 6 10 60:00 5. 555lc 2 150 300:00 6. Relays 4 150 600:00 7. Contactors 2 1500 3,000:00 8. Vero-board 1 150 150:00 9. 16mm2 5yard 200 1,000:00 10. 100Amp connector 5 piece 200 1,000:00 11. Casing 1 8000 8,000:00 12. Timer (neumatic) 1 250 250:00 13. Bolt and nuts 100 100:00 14. Indicator light 50 150:00 15. Labour cost 3 7,790:00 Total Cost 24,000:00 41