CIVIL SURVEY OF SOHAR -2 POWER PLANT Civil Survey Inspection Report for Sohar-2 Power Plant, Sultanate of Oman Inspection Details Customer Location Purchase Order No. Date of Inspection visit STOMO Sohar Industrial Port Area 4600031950 24.8.2021 & 25.8.2021 By: SOGEX Oman Co. LLC. Al Qurum, Street 7, Block 205, Plot 20, Way No.207, Al Rawaq Building,4th Floor, Office No.406, P.O. Box 1739/1170, P.C.112, Ruwi, Sultanate of Oman. Muscat. Phone: +968 2465 9769 Fax: +968 2469 4974 Contact Person: Mr. Harshad Dhada, Area General Manager E-mail: harshad.dhada@sogexoman.com August 2021 Page 1 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT SYNOPSIS: This report documents the Inspection / Investigation of Civil Works defaults & suggested measures for Power Production at Sohar-2 Plant, Inspection undertaken during August 2021 for Suez Tractable Operation and Maintenance Company LLC. (eNGie STOMO), Oman. August 2021 Page 2 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Contents: 1. Introduction 2. Examination of plant structures 2.1 2.2 2.3 Plant inspection visit Inspection units Inspection elements of civil structures 3. Unit wise inspection / observations 3.1 3.2 Seawater intake system 3.1.1 Seawater pipe Support Foundations 3.1.2 Instrument supports & cable trays 3.1.3 Electrical cable chamber & trench foundation Waste water treatment plant 3.2.1 Acti flo unit 3.2.2 Waste water transfer underground pump house 3.2.3 Dosing pump for thickner 3.2.4 Floor at oil water separator and throughout treatment plant 3.2.5 External painting for all process tank, dyke wall of chemical tanks, chemical unloading bay. 3.3 3.4 RO & DM water treatment plant: 3.3.1 HP pump foundations 3.3.2 Building side walls 3.3.3 Floor in chemical storage tanks and dosing pumps area CCW pump house 3.4.1 Gratings 3.4.2 Support foundations & floor damages 3.5 Fuel oil storage tank – 11 3.6 Fuel oil storage tank - 12 3.7 Air compressor house 3.8 Work shop building 3.9 Car parking August 2021 Page 3 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.10 Safety office 3.11 Guard room 3.12 Potable & fire water tanks area 3.13 Fuel gas conditioning skid 3.14 EDG area 3.15 Fire water pump house 3.16 STG 3.17 Common GT-11&12, HRSG 11&12 3.18 Auxiliary boiler 3.19 Feed water pump house 3.20 Main electrical building. 4. Recommendations August 2021 Page 4 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 1. Introduction: The plant (Sohar-2 IPP) is located approximately 200km northwest of Muscat in Oman, within the Sohar Industrial Port Area, between the plot of the existing Sohar-1 IWPP and Sohar Aluminum Power Plant. The facility entered into full commercial operation on 3 April 2013. 2 HRSGs 2 GTGs 1 STG The plant consists of two Siemens AG SGT5-4000F gas turbines (GT), two triple pressure heat recovery steam generators (HRSG) and a Siemens AG SST5-5000 steam turbine (ST). The condenser is cooled via a once through seawater system. Seawater is extracted from the existing common intake (shared facility) and discharged to an existing common outfall channel in accordance with the Seawater Extraction Agreement. The gas turbines are fitted with by-pass stacks to enable the operation in open cycle. Although capable of open cycle operation, the normal operating mode of the plant is in combined cycle (CCGT) for higher thermal efficiency. At site reference conditions of 50°C ambient temperature and 30% relative humidity, the plant has a net power capacity of approximately 744 MW at COD. With this technology, the energy for electricity generation is obtained from the combustion of natural gas. Hot combustion gases formed by the combustion of natural gas drive a gas turbine, which, in turn, rotates an alternator to produce electricity. After driving the gas turbine, the exhaust gases are still hot enough to produce steam in a heat recovery boiler (HRSG). The steam generated in the heat recovery boiler drives a steam turbine, which rotates another alternator to produce additional electricity. August 2021 Page 5 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT The individual gas turbines exhaust hot gases are directed into naturally circulated HRSGs, which generate steam at three pressure levels. The high-pressure steam from each of the heat recovery steam generators is combined in a common header and passes to the steam turbine as is the intermediate pressure and low-pressure steam. A condensate pre-heater is integrated in the HRSG. This arrangement enables higher efficiencies of the combined cycle power plant, by using the exhaust gas energy to preheat the condensate before it passes towards the feed water pump and into the LP-system. This Inspection report is based on discussions with STOMO officials, Physical inspections during an inspection visit and documents received from STOMO. The remedial measures or technical solutions suggested are indicative and these methods or alternatives may be used for rectification works. References: Doc. No: OM1001-& CEC269-0904-000001 DESIGN CRITERIA FOR CIVIL AND BUILDING WORKS Doc. No: OM1001-&ELH269-OOUZT-077747-077750 AREA CLASSIFICATION STG-10 Doc. No: OM1001-&ELH269-OOUZT-077744-077747 AREA CLASSIFICATION GTG 11 & GTG 12 Doc. No: OM1001-&ELH269-OOUZT-077740 AREA CLASSIFICATION OVERALL AREA Doc. No: OM1001-&CLC129-OOUGX-060201-060203 WATER & WASTE WATER TREATMENT STRUCTURE FOUNDATIONS Doc. No: OM1001-&CLC129-OOUGX-060231-060236 WATER & WASTE WATER TREATMENT ACTIFLO FOUNDATION August 2021 Page 6 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 2. Examination of plant structures: 2.1 Plant inspection visit: A detailed plant inspection was carried out on 24th & 25th of August 2021, after mandatory STOMO HSE induction, receipt of necessary & required Sohar Port entry pass & Sohar-2 plant gate pass, STOMO HSE permits for working inside plant from STOMO. A detailed plant inspection visit was covered with the following points: Review of the overall plant civil structures condition and maintenance & cleaning practices, including available plant building maintenance records, cleaning & painting of concrete structure frequencies and procedures. Studied original As Built GA drawings of the plant to identify exact location & number of default points and further to verify the current status of these defaults and their potential impact on the plant operations. 2.2 Inspection units: The following units were examined: 1. Seawater intake system 2. Wastewater treatment plant 3. RO & DM plant 4. CCW pump house 5. Fuel oil storage tank-11 6. Fuel oil storage tank-12 7. Air compressor house 8. Work shop building 9. Car parking 10. Safety office 11. Guard room 12. Potable & fire water tanks area 13. Fuel gas conditioning skid 14. EDG area 15. Fire water pump house 16. STG 17. Common GT-11&12, HRSG 11&12 18. Auxiliary boiler 19. Feed water pump house 20. Main electrical building August 2021 Page 7 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 2.4 Inspection elements of civil structures: During the physical examination, following civil structural elements were inspected for its present condition and defects: 1. Plinth / Base Slabs 2. Pipe support foundations 3. Fire extinguisher foundations 4. Above & underground tank walls & base slab from outside & inside 5. Chamber/pit walls & base slab from inside 6. Manhole walls & base slab from inside 7. Pipe rack foundations 8. All step / cage ladder support foundations 9. SS grating support foundations 10. Ramps 11. Misc. civil structures like staircases / normal building outside walls / tiles on floor slab 12. Painting / coating on foundations / tank walls 13. Concrete surface finishing 14. Ground plinth beams 15. Concrete floor finishing 16. Reinforcement of columns, beams, walls etc. August 2021 Page 8 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3. Unit wise inspection / observations: 3.1 Seawater intake system: 3.1.1 Seawater intake pump Sea water intake system consists of 2 service cooling water pumps and 4 circulating water pumps, connected piping with valves & instruments inline from intake pump house to facility. Power supply for pumps drawn from switch gear building in intake system through underground cable trenches. All Pumps has concrete pedestal and rested on main base slab. Sea Water Intake August 2021 Page 9 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Observation: Sea water stagnation surrounding the pumps pedestrals, pipe supports and instrument supports. Severe Corrosion & Surface cracks are seen from outside surface of foundation base finishing with erosion of epoxy painting, Concrete Grouting has been broken / damaged. Probable cause & remedial measures: Probable cause: Inappropriate slope in floor to flow back into sump or drain resulting in water stagnation on the floor. This stagnated sea water coming in contact with concrete and metal structures, supports, cable conduits, etc. reacting badly. seawater on concrete may deteriorate from the combined effects of chemical and physical processes below: Sulfate attack Leaching of lime (calcium hydroxide) Alkali-aggregate expansion Salt crystallization from alternate wetting and drying Cracks, spalls, mortar erosion, and corrosion stains are visible signs of deterioration that causes increased porosity and decreased strength. Remedial measures recommended: Corrosion of this sort will surely destroy concrete over time unless it is properly protected. A barrier is needed between the concrete and the salt water that will stop water, chlorides and oxygen from reaching the inner reinforcement of the structure i.e a protective coating which resists sea water. Proper slope to be maintained in floor surrounding pump pedestrals towards the drain/sump to avoid stagnation of saline water. Seal cracks, gaps & joints in concrete with durable urethane caulk to prevent reoccurrence and protect the foundations. If the Concrete Grouting layer has totally broken/damaged at any corner of the foundation, then new concrete grouting to be applied with epoxy painting. August 2021 Page 10 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.1.2 Seawater Intake Pipe Support Foundations: Pipe Support Foundations: Observation: The cracks are on seawater pipe foundation base. Concrete Grouting has been broken / damaged. Probable cause & remedial measures: Probable cause: Poorly-graded aggregate. Deviation from mix ratio. Saline water may mixed and incorrect cement grade. Extreme weather conditions. Concrete placement problems. Soil strength under the concrete pedestal. Remedial measures: Seal cracks, gaps & joints in concrete with durable urethane caulk to prevent reoccurrence and protect the foundations. If the Concrete layer has totally broken/damaged at any point of the Foundation then new concrete foundation to be casted, and apply epoxy painting. Before going for new foundation soil under foundation shall be compacted. August 2021 Page 11 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.1.3 Instrument supports and cable trays: Instrument & cable tray support Observation: The impression of corrosion on cable trays, cable conduits and instrument support due to stagnation of saline water, reacting aggressively with metal supports and concrete pedestrals. Cracks are seen on surface. Concrete Groutings has been broken / damaged. August 2021 Page 12 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Probable cause & remedial measures: Probable cause: Inappropriate slope in floor to flow back into sump or drain resulting in water stagnation on the floor. This stagnated sea water coming in contact with concrete and metal structures, supports, cable conduits, etc. reacting badly. seawater on concrete may deteriorate from the combined effects of chemical and physical processes below: Sulfate attack Leaching of lime (calcium hydroxide) Alkali-aggregate expansion Salt crystallization from alternate wetting and drying Cracks, spalls, mortar erosion, and corrosion stains are visible signs of deterioration that causes increased porosity and decreased strength. Remedial measures recommended: Corrosion of this sort will surely destroy concrete over time unless it is properly protected. A barrier is needed between the concrete and the salt water that will stop water, chlorides and oxygen from reaching the inner reinforcement of the structure i.e a protective coating which resists sea water. Proper slope to be maintained in floor surrounding pump pedestrals towards the drain/sump to avoid stagnation of saline water. Seal cracks, gaps & joints in concrete to prevent reoccurrence and protect the foundations. If the Concrete foundation has totally broken/damaged at any corner of the foundation, then new concrete foundation to be casted, apply epoxy painting. August 2021 Page 13 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.1.4 Electrical cable chamber & trench foundation: Electrical cable chamber & trench foundations Observation: Damaged electrical cable chamber & trench base. Concrete has been broken / damaged. Concrete reinforcement is exposed. Probable cause & remedial measures: Probable cause: Poorly-graded aggregate. Deviation from mix ratio. Saline water may mixed and incorrect cement grade. Extreme weather conditions. Concrete placement problems. Remedial measures: Chip and remove debris, Reconstruct the broken area, Replaster the surface where plastering appears damaged, Seal cracks, gaps & joints in concrete with durable urethane caulk to prevent reoccurrence and protect the foundations. If the Concrete layer has totally broken/damaged at any point then new concrete wall to be casted & applied with epoxy painting. August 2021 Page 14 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.2 Waste water treatment plant: 3.2.1 Actiflo unit: Actiflo unit August 2021 Page 15 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Observation: There is serious leakage from the actiflo unit, Though the temporary action (replastering done) taken on concrete wall surface, leakage still exists. Probable cause & remedial measures: Probable cause: Poorly-graded aggregate. Deviation from mix ratio. Saline water and incorrect cement grade. Extreme weather conditions. Concrete placement problems. Insufficient curing Remedial measures: The surface looks wet and, in this case, it is recommend to do the PU injection grouting. Then wait for 24 hours to get it dry and once it is dried, grind the surface and give the PU coating. High pressure PU injection grouting: Injection grouting is a process of filling the cracks, open joints, voids, or honeycombs, in concrete or masonry structural members, under pressure with a material that cures in place to produce the desired results like strengthening a structure and prevent water movement Grout is a flowable plastic material and should have negligible shrinkage to fill the gap or voids completely and should remain stable without cracking, de-lamination or crumbling. There are different types of grouts such as cement grout, polymer-cement slurry, epoxy, urethane, and highmolecular-weight methacrylate (HMWM). These grout materials are selected for particular type of concrete or masonry repair work based on the compatibility of the grout with the original material. If Proper grouting material is not selected, the desired objectives of the grouting process would not be achieved. 5steps for injection grouting: 1. Drilling and inserting of injection ports 2. Protection of work areas 3. Grouting using a high-pressure grouting machine 4. Removal of injection ports & sealing up 5. Ensure no leakage For detailed procedure and method statement from international standardized service provider refer Crack Injection Method Statement by “SIKA’’ from www.sika.co.uk August 2021 Page 16 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Recommendations: Outer surface of the Concrete units shall be painted. Internal surface shall be coated with poly urethane/any protective coat for saline & chemical water. Avoid direct contact of sea water with concrete structure. August 2021 Page 17 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.2.2 Waste water transfer underground pump house: Under ground pump house (Leak from skimmed oil pond) Observation: There is serious leakage from the underground pump house of oil water separator in waste water treatment. Though the temporary action (replastering done) taken on concrete wall surface, leakage has not been arrested. August 2021 Page 18 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Probable cause & remedial measures: Probable cause: Poorly-graded aggregate. Deviation from mix ratio. Saline water and incorrect cement grade. Workmanship quality. Remedial measures: The surface looks wet and, in this case, it is recommend to do the PU injection grouting. Then wait for 24 hours to get it dry and once it is dried, grind the surface and give the PU coating. High pressure PU injection grouting: Injection grouting is a process of filling the cracks, open joints, voids, or honeycombs, in concrete or masonry structural members, under pressure with a material that cures in place to produce the desired results like strengthening a structure and prevent water movement Grout is a flowable plastic material and should have negligible shrinkage to fill the gap or voids completely and should remain stable without cracking, de-lamination or crumbling. There are different types of grouts such as cement grout, polymer-cement slurry, epoxy, urethane, and highmolecular-weight methacrylate (HMWM). These grout materials are selected for particular type of concrete or masonry repair work based on the compatibility of the grout with the original material. If Proper grouting material is not selected, the desired objectives of the grouting process would not be achieved. 5steps for injection grouting: 1. Drilling and inserting of injection ports 2. Protection of work areas 3. Grouting using a high-pressure grouting machine 4. Removal of injection ports & sealing up 5. Ensure no leakage For detailed procedure and method statement from international standardized service provider refer Crack Injection Method Statement by “SIKA’’ from www.sika.co.uk Recommendations: Outer surface of the Concrete units shall be painted. Internal surface shall be coated with poly urethane/any protective coat for saline & chemical water. Avoid direct contact of sea water with concrete structure. August 2021 Page 19 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.2.3 Dosing pumps for thickner: Thickner dosing Pumps Observation: Pump base frame, pipe supports corroded badly, floor also have signs of damage. Probable cause & remedial measures: Probable cause: Chemical spillage Remedial measures: Floor & pump pedestal shall be protected from the chemical, Clean rusted surface on the floor, base frame and support structure with wire brush, Paint with Epoxy/PU coating to protect from corrosion. On floor it is recommended for Chemical resistant tiles at rich chemical areas. August 2021 Page 20 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.2.4 Floor at oil water separator area: Floor at oil water separator Observation: The cracks are seen from surface of Floor. Probable cause & remedial measures: Probable causes: Extreme temperature variations, improper mixing of cement, Salt water mixed while mixing, Curing done with sea water, soil shirkange etc. Remedial measures: Seal cracks, gaps & joints in floor with the cement, and do apply protective coating also or tiles to protect from further damage due to sea water and chemical spillage August 2021 Page 21 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.2.5 External painting for all process tanks, dyke walls of chemical tanks, chemical unloading bay: Concrete tanks and walls in waster water treatment plant Observation: In Wastewater Treatment area all process structures like clarifier, thickener, Dyke walls of chemical storage tanks, Unloading Bay found un painted. Anticipated defects: Due to not painting of concrete structures in chemical & Saline atmosphere and at high temperatures, fumes of strong acids and chemical spillages damage concrete, develop cracks and leakages occur. Action required: Suitable Painting for chemical and Saline atmosphere shall be done at the earliest. August 2021 Page 22 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.3 RO & DM plant: 3.3.1 HP pump foundations: HP pump base frame with foundation Observation: Floor, Foundation, cable trays & supports are badly corroded surrounding the pump. Probable cause & remedial measures: Probable cause: Sea water and chemical spillage. Remedial measures: All corroded area to be cleaned and painted with suitable protective coating, as per OEM recommended painting procedures. Floor also should be cleaned and coated or flooring to be with chemical resistant tiles. Arrest leaks. August 2021 Page 23 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.3.2 Building side walls: Side walls Observation: Damage in cement plastered wall near by the door on both sides, steel reinforcement is exposed. Probable cause & remedial measures: Probable cause: Curing done with sea water Poorly-graded aggregate. Deviation from mix ratio. Saline water and incorrect cement grade. Concrete placement problems. Remedial measures: Cement exposed area should be chipped, replastered and painted before the steel get corroded and spread though out the wall. August 2021 Page 24 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.3.3 Floor in chemical storage tanks and dosing pumps: Chemical day tanks & RO rack Observation: Due to chemical and sea water spillage, floor at chemical day tank and RO skids floor is damaged and grating is being corroded badly. Probable cause & remedial measures: Probable cause: Chemical & sea water spillage. Remedial measures: Suitable tiles for chemical area and FRP gratings are Suggested. Arrest the leaks if any. August 2021 Page 25 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.4 CCW pump house: 3.4.1 Gratings: CCW pump house Observation: All gratings in closed cooling water system are badly corroded. Probable cause & remedial measures: Probable cause: Resistance of GI is not durable to harsh corrosive atmosphere of saline water spillage. Remedial measures: Recommended to replace GI with FRP gratings. August 2021 Page 26 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.4.2 Foundation & floor damage: Pump foundations and pipe supports Observation: Pump foundation, floor, pipe supports corroded. Probable cause & remedial measures: Probable cause: Sea water spillage No protective coating on the floor and foundations. Remedial measures: All corroded area to be cleaned and painted with suitable protective coating, as per OEM recommended painting procedures. Floor also should be cleaned and coated or flooring to be with chemical resistant tiles. Arrest leaks. August 2021 Page 27 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.5 Fuel oil storage tank -11 Fuel oil storage tank-11 Observation: Roof of tank corroded aggressively. This is carbuncle type pitting corrosion, starts as blisters & results in isolated holes. This is form of corrosion under insulation (CUI). CUI damage may be highly localized. In some localized cases, the corrosion can appear to be carbuncle type pitting (usually found under a failed paint/coating system) August 2021 Page 28 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Probable cause & remedial measures: Probable cause: Defective blasting and painting application. Intruding moisture is the key problem causing CUI. Major cause suspected as the moisture during blasting and painting. Remedial measures: CUI Mitigation is best achieved by using appropriate paints/ coatings and maintaining the insulation/sealing/vapor barriers. Repair procedure to be followed as per API standard. Thorough surface preparation to be carried out either by dry or wet blasting. Repaint with specified paint as per the Design approved August 2021 Page 29 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.6 Fuel oil storage tank -12 Fuel Oil Storage tank -12 Observation: Roof of tank corroded aggressively. This is carbuncle type pitting corrosion, starts as blisters & results in isolated holes. This is form of corrosion under insulation (CUI). CUI damage may be highly localized. In some localized cases, the corrosion can appear to be carbuncle type pitting (usually found under a failed paint/coating system) August 2021 Page 30 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Probable cause & remedial measures: Probable cause: Defective blasting and painting application. Intruding moisture is the key problem causing CUI. Major cause suspected as the moisture during blasting and painting. Remedial measures: CUI Mitigation is best achieved by using appropriate paints/ coatings and maintaining the insulation/sealing/vapor barriers. Thorough surface preparation to be carried out either by dry or wet blasting. Repainted with specified paint as per the Design approved. August 2021 Page 31 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.7 Air compressor house: Compressor foundation: Compressor foundation: Observation: Surface cracks on compressor foundation. Probable cause & remedial measures: Probable cause: Poorly-graded aggregate. Vibration of the system Remedial measures: Seal cracks, gaps & joints in concrete with durable urethane caulk to prevent reoccurrence and protect the foundations. If the Concrete layer has totally broken/damaged at any corner of the Foundation then new concrete grouting to be applied with epoxy painting. August 2021 Page 32 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.8 Workshop building: Work shop building Hair line crack Edges of wall damage Tile damage in washroom Observation: Hair line cracks on the wall, corner edges of the wall damaged in several places, tile in washroom about to fall. Probable cause & remedial measures: Probable cause: • Poorly-graded aggregate. • Deviation from mix ratio. • Workmanship quality. • Concrete placement problems. • Alkali-Aggregate reactions. Remedial measures: Cleaning of Crack: This is the first and foremost step in the repair of hairline cracks in the concrete. Inspection of crack is done if any stains have penetrated the crack and have discolored the concrete, the stains have to be addressed before the repairing the crack. August 2021 Page 33 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 2. Selection of Sealant The sealant is a filler material that is penetrated into the crack. The ideal sealant must have low surface tension and low viscosity. These two characteristics allow the liquid sealer to penetrate deeply into the crack. Crack repair materials for concrete are often polymer-modified cement grouts, silicone or latex caulking, or epoxies. Polymer-modified cement grout is the typical material used to fill pinholes and voids in concrete during manufacture. If cracks occur before the concrete is sealed, this is often the material used to repair them. 3. Application of Sealant The selected sealer is applied on the substrate by using a squeegee and/or in combination with a roller. The application process must be carried out for at least 5-10 mins to ensure penetration. 4. Curing Proper curing must be ensured to complete hardening of sealant. The warmer the temperature, faster the curing, lower the temperature, the longer it will take. ** Precautions Repairing hairline cracks can be challenging because making the cracks vanish takes skill, forbearance, practice and a good eye for colour matching. One definition of a hairline crack is a crack that hasn't opened up. That means there is very little room to fill it with anything but a very low-viscosity liquid. Since most hairline cracks don't affect the structural integrity of a countertop, sealing and concealing the crack are the main goals of a repair. Edges of the wall to be brushed with layer of cement and painted. Damaged tile in wash room to be fixed with durable urethane caulk to prevent reoccurrence. August 2021 Page 34 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.9 Car parking: Car parking area Observation: Severe corrosion on the roof and steel structure. Probable cause & remedial measures: Probable cause: Saline atmosphere, improper painting. Remedial measures: Repair the corroded areas, perform surface preparation by buffing, emery or wire brush, clean corroded areas, apply primer and 2 coats of epoxy or poly urathene paint of each 100 microns. August 2021 Page 35 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.10 Safety office: Safety training office Observation: Tile at the corner edge of the wash basin in wash room damaged. Probable cause & remedial measures: Probable cause: Deviation from mix ratio. Saline water and incorrect cement grade. Workmanship quality. Concrete placement problems. Remedial measures: Seal cracks, gaps & joints in concrete with durable urethane caulk to prevent reoccurrence. August 2021 Page 36 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.11 Guard room: Guard room Observation: Repaired areas on walls are unpainted. Probable cause & remedial measures: Remedial action: Apply suitable paint to protect from cracks August 2021 Page 37 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.12 Potable & fire water tanks: Potable and fire water tanks area pipe supports Observation: The cracks are seen from outside surface of potable water tank area support. Probable cause & remedial measures: Probable cause: Poorly-graded aggregate. Deviation from mix ratio. Saline water may mixed and incorrect cement grade. Extreme weather conditions. • Concrete placement problems. • Soil strength under the concrete pedestal. Remedial measures: Seal cracks, gaps & joints in concrete with durable urethane caulk to prevent reoccurrence and protect the foundations. If the Concrete layer has totally broken/damaged at any point of the Foundation then new concrete foundation to be casted, and apply epoxy painting. Before going for new foundation soil under foundation shall be compacted. August 2021 Page 38 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.13 Fuel gas conditioning skid: Fuel gas conditioning skid: Observation: Honey comb type of concreting defect in the foundation. Probable cause & remedial measures: Probable cause: Defect due to which cavities and hollow pockets are formed and coarse aggregates become prominently visible in the concrete structure. It may occur due to improper concrete workability and concrete pouring practice, excessive water in the concrete mix, inadequate formwork rigidity and waterproofing, etc. Remedial measures: The repair process involves removing loose material, cleaning the affected area, applying suitable repair material, and then curing to gain adequate strength. August 2021 Page 39 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.14 EDG area: EDG area: Observation: Cracks on the floor and foundation. Probable cause & remedial measures: Probable cause: • Rapid drying of the concrete • Excess water in the concrete mix • Pouring of improper strength concrete on the floor • Inadequate control joints • Pouring concrete on the frozen ground Remedial measures: seal the patches to keep the water-resistance as well as stain-resistance of the concrete. You can use polyurethane to seal the floor. Apply the polyurethane using a brush or a roller to work the coat deep into the rough patch. August 2021 Page 40 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.15 Fire water pump house: Fire water pump house : Observation: Cracks on the floor and foundation. Probable cause & remedial measures: Probable cause: • Rapid drying of the concrete • Excess water in the concrete mix • Pouring of improper strength concrete on the floor • Inadequate control joints • Pouring concrete on the frozen ground Remedial measures: seal the patches to keep the water-resistance as well as stain-resistance of the concrete. You can use polyurethane to seal the floor. Apply the polyurethane using a brush or a roller to work the coat deep into the rough patch. August 2021 Page 41 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.16 STG: STG building Observation: Cracks on the Floor and foundation. No painting for the floor. Probable cause & remedial measures: Probable cause: • Rapid drying of the concrete • Excess water in the concrete mix • Pouring of improper strength concrete on the floor • Inadequate control joints • Pouring concrete on the frozen ground Remedial measures: seal the patches to keep the water-resistance as well as stain-resistance of the concrete. You can use polyurethane to seal the floor. Apply the polyurethane using a brush or a roller to work the coat deep into the rough patch. Floor should be painted for longer life to protect from saline atmosphere, high temperatures. August 2021 Page 42 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.17 Common GT-11&12, HRSG 11& 12 Common GT-11&12, HRSG 11& 12 GT-11area GT-1 GT-11 Transformer area hydrant pipe pedestral crack HRSG Observation: Cracks on the floor and foundation. Paint peeled off . Probable cause & remedial measures: Probable cause: • Rapid drying of the concrete • Excess water in the concrete mix • Paint damaged due to improper surface preparation and application. Remedial measures: seal the patches to keep the water-resistance as well as stain-resistance of the concrete. You can use polyurethane to seal the floor. Apply the polyurethane using a brush or a roller to work the coat deep into the rough patch. Remove damage paint, clean the surface , apply primer and repaint. August 2021 Page 43 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.18 Auxiliary boiler : Auxiliary boiler Observation: Cracks on the Floor and foundation. No painting on the floor & foundation. grating corroded. Probable cause & remedial measures: Probable cause: Rapid drying of the concrete Excess water in the concrete mix Paint damaged due to improper surface preparation and application. Remedial measures: seal the patches to keep the water-resistance as well as stain-resistance of the concrete. You can use polyurethane to seal the floor. Apply the polyurethane using a brush or a roller to work the coat deep into the rough patch. GI Grating replace with FRP Grating. August 2021 Page 44 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.19 Feed water pump house: Feed water pump house Observation: A diagonal crack on the wall, cracks are seen on pump foundation. Probable cause & remedial measures: Probable cause: Poorly-graded aggregate. Vibration of the system Excess water in the concrete mix Remedial measures: Seal cracks, gaps & joints in concrete with durable urethane caulk to prevent reoccurrence and protect the foundations. If the Concrete Grouting layer has totally broken/damaged at any corner of the Foundation then new concrete grouting to be applied with epoxy painting. August 2021 Page 45 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 3.20 Main electrical building: Main electrical building stair and wall Observation: Surface cracks observed of the wall, under the stair, few areas unpainted. Probable cause & remedial measures: Probable cause: Poorly-graded aggregate.. Extreme weather conditions. Workmanship quality. Concrete placement problems. Remedial measures: Seal cracks, gaps & joints in concrete with durable urethane caulk to prevent reoccurrence and protect the foundations. If the Concrete Grouting layer has totally broken/damaged at any corner of the Foundation then new concrete grouting to be applied with epoxy painting. August 2021 Page 46 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT 4.0 Summary: The civil structures in the plant, are generally look good the plant Table 4 presents the recommendations with respect to civil work defects / problems and other general points for STOMO. Table 4: Sr. Name of Unit Major Civil work Issues Recommendation No. 1 Seawater intake system Pump foundations 1. Proper slope should be cracked / broken, maintained in floor to avoid corrosion. stagnation of sea water. 2. New concrete grouting to be made &applied with epoxy painting. 2 Waste water treatment Severe leaks from 1. Suggested to do Poly-urathene concrete tanks, No injection grouting to avoid leaks. painting on concrete 2. Painting should be done for all structures. the concrete structures, 3. Rich Chemical area should be with chemical resistant tiles. 3 RO &DM water Heavy corrosion on base 1. Surface preparation treatment plant frame of pumps, Gratings with painting should be corroded, floor at done. chemical day tank is 2. Recommends for FRP being damaged due to gratings. chemical spillage. 4. Reconcreting damaged areas 5. Recommends Chemical resistant tiles at chemical tanks area to protect the floor. 4 CCW pump house Gratings are badly 1. Recommends for FRP corroded. gratings 5 Fuel oil storage tank-11 6 Fuel oil storage tank-12 8 Air compressor House August 2021 Severe corrosion on roof due to poor workmen ship. Severe corrosion on roof due to poor workmen ship. Surface cracks on Compressor foundation. Reblasting and repainting as per API 650 Reblasting and repainting as per API 650 New concrete grouting to be made &applied with epoxy painting. Page 47 of 48 CIVIL SURVEY OF SOHAR -2 POWER PLANT Sr. No. 9 10 11 12 13 14 Name of Unit Work shop building Major Civil work Issues Recommendation Cracks on wall, Tile damage in wash room. Structural repair with new concrete grouting to be applied. Car parking Corroded steel structure To be re painted. Safety office Tile damage in wash room Structural repair with new concrete grouting to be applied. Guard room Unpainted repaired patches Painting to be done. Main electrical building Cracks in outside surface wall New concrete grouting plaster to be applied with painting Auxiliary boiler area. Cracks in concrete support New concrete grouting foundations & concrete finish to be applied with epoxy erosion painting. Signed by: Name: Date: August 2021 Page 48 of 48