CONCRETE POURING ANALYSIS OF LANKA ELECTRICITY COMPANY (PVT)LTD HEAD OFFICE PROJECT AT COLOMBO. Client Lanka Electricity Company (Pvt)Ltd. Consultant University of Moratuwa. Contractor Sripali Constructions (Pvt)Ltd. RMC supplier Capital RMC (Pvt)Ltd. Concrete Pouring summary. The initial order was placed on 11th of January 2024 by the contractor representative / Site Engineer for a C30 quantity of 115 m3 with the pump car to the site at 02.00pm, later the job was cancelled and postponed to 12th of January 2024 at 3.00 am due to unsuitable weather condition. The pump car was at the site by 2.30am with the coordination of the contractor representative / Site Engineer and RMC Staff (Executive Engineer, QA/QC Engineer, Technical Sale Representative). Bellow table provides the summary of the total concrete session. Time analysis No Remark 1 2 3 4 5 6 7 8 Slump Drop 9 10 Rejected 11 12 13 14 15 Truck no LL 9089 LL 9588 LL 9596 LL 9088 LL 9597 LL 9594 LL 9089 LL 9588 LL 9090 LL 9596 LL 9594 LL 9089 LL 9588 LL 9597 LL 9596 Plant Depature Travelling duration from Plant to Site Arrival to Site truck idealing before at the pump 4:05 4:47 6:22 6:48 7:12 7:32 7:49 8:30 9:37 9:57 13:26 13:46 16:50 17:58 19:01 0:40 0:43 0:48 0:42 0:43 0:38 0:56 0:45 0:53 0:53 0:49 0:49 0:55 0:52 0:45 4:45 5:30 7:10 7:30 7:55 8:10 8:45 9:15 10:30 10:50 14:15 14:35 17:45 18:50 19:46 0:00 0:30 0:00 0:35 1:00 1:20 1:40 2:11 2:00 2:25 0:15 2:25 0:05 0:00 0:00 Table 1 Truck at slump start Pump preparaion Unloading before the time (Pump) slump test 4:45 6:00 7:10 8:05 8:55 9:30 10:25 11:26 12:30 13:15 14:30 17:00 17:50 18:50 19:46 0:50 0:10 0:03 0:05 0:05 0:03 0:08 0:24 0:05 0:35 1:35 0:05 0:05 0:05 0:04 5:35 6:10 7:13 8:10 9:00 9:33 10:33 11:50 12:35 13:50 16:05 17:05 17:55 18:55 19:50 Time analysis (Source -Dispatch Notes ) Pumping Duration finish unloading (Pump) 0:23 0:55 0:39 0:35 0:25 0:47 0:50 0:30 0:32 0:25 0:45 0:30 0:35 0:34 0:28 5:58 7:05 7:52 8:45 9:25 10:20 11:23 12:20 13:07 14:15 16:50 17:35 18:30 19:29 20:18 Retention from plant concrete depature to Retention from start plant depature unloading to finish (slump testing unloading point) 1:30 1:53 1:23 2:18 0:51 1:30 1:22 1:57 1:48 2:13 2:01 2:48 2:44 3:34 3:20 3:50 2:58 3:30 3:53 4:18 2:39 3:24 3:19 3:49 1:05 1:40 0:57 1:31 0:49 1:17 ANALYSIS. TRUCK VS RETENTION TIME Relevent Final Retention time (hr) Relevent Initiall Retention time (hr) Acceptable retention time (3.5hr) 4.5 B 4.18 A 4 C 3.53 3.5 3.34 3.5 3.2 3.3 3.49 3.24 3.19 RETENTION (HR) 3 2.48 2.5 2.18 2.13 2.58 2.44 2.39 2.01 2 1.57 1.53 1.5 1.3 1.23 1.3 1.48 1.4 1.22 1.31 1.17 1.05 1 0.57 0.51 0.49 0.5 0 1ST 2ND 3RD 4TH 5TH 6TH 7TH 8TH 9TH 10TH 11TH 12TH 13TH 14TH 15TH TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK TRUCK NUMBER Figure 1 Retention time analysis (source- time analysis Table 01) • • • The above graph represents the time duration of each truck mixture at the point of inspecting the slump. From the 3rd truck to the 8th truck, the graph shows that each truck taken for the slump inspection is nearing to the 3.5hr retention time limit. This shows an increased delay in poring for each of these trucks. Major delays were due to break down of pokers, levelling team lacked knowledge in fixing, clamping and preparing the pipeline, not using level rods and no pouring plan due to lack of knowledge in levelling. Above highlighted points A, B and C were nearing to the 3.5hr retention time limit and after pouring the time durations are reached to 3:50, 4:18, 3:49 respectively