Volume I. System Study Report CONSULTANCY SERVICES FOR PACKAGE 1-FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO – METORO ELECTRICIDADE DE MOÇAMBIQUE Financed by Royal Norwegian Embassy September 2016 ELECTRICIDADE DE MOÇAMBIQUE BYUCKSAN POWER CO.,LTD. CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO TABLE OF CONTENTS 1. Introduction 1.1 Overview of Northern Area---------------------------------------------------------1 1.2 Objective of Namialo-Metro Transmission System Study--------------------2 1.3 Power Demand Forecast and Power Development Plan 2. Northern Power System Plan in the Future(2016~2036) 2.1 Power Demand------------------------------------------------------------------------3 2.2 Power Generation Plan 2.3 Transmission System Plan 3. Power System Study 3.1 Transmission Planning Criteria 3.1.1 Minimum Reliability Criteria 3.1.2 Voltage Levels 3.1.3 Maximum Equipment Load Levels 3.1.4 Steady State Transfer Limits 3.1.5 Transient and Dynamic Stability 3.2 Approach Method 3.2.1 Build Scenario Based Namialo-Metoro Transmission Line Planning 3.2.2 Power System Analysis 3.2.2.1 Check Power system status for every 5 years from 2016 to 2036 3.2.2.2 Load Flow Analysis 3.2.2.3 Transfer Capability Analysis based on Voltage Stability 3.2.2.4 Short Circuit Analysis 3.2.3 Determine Optimal Plan Scenario 3.2.4 Simulation cases 3.2.4.1 220kV Namialo-Metoro Transmission line construction 3.2.4.2 400kV Namialo-Metoro Transmission line construction (220kV operation) 3.2.4.3 3.2.5 400kV Namialo-Metoro Transmission line construction (400kV operation) Contingencies Inception Report ELECTRICIDADE DE MOÇAMBIQUE BYUCKSAN POWER CO.,LTD. CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.3 Load Flow Analysis 3.3.1 Present Northern Power System (2016) 3.3.2 Scenario 0 : No Additional Transmission Line 3.3.3 Scenario A : 220kV T/L construction 220kV operation 3.3.4 Scenario B : 400kV T/L construction, 220kV operation 3.3.5 Scenario C : 400kV T/L construction, 400kV operation 3.3.6 summary 3.4 Transfer Capacity Analysis based on Voltage Stability 3.4.1 Present Northern Power System (2016) 3.4.2 Scenario 0 : No Additional Transmission Line 3.4.3 Scenario A : 220kV T/L construction 220kV operation 3.4.4 Scenario B : 400kV T/L construction, 220kV operation 3.4.5 Scenario C : 400kV T/L construction, 400kV operation 3.4.6 summary 3.5 Short Circuit Analysis 3.5.1 present system status in 2016 year 3.5.2 Scenario A : 220kV T/L construction 220kV operation 3.5.3 Scenario B : 400kV T/L construction, 220kV operation 3.5.4 Scenario C : 400kV T/L construction, 400kV operation 3.5.5 summary 3.6 Discussion 3.6.1 Technical Analysis Results 3.6.1.1 Power flow 3.6.1.1.1 System losses 3.6.1.1.2 Must-Run Generation 3.6.1.2 Short Circuit Study Results 3.6.1.3 Transfer Capability 3.6.2 Benefit of the Interconnection with Tanzania Power System 3.6.3 Feasible Solution for Namialo-Metoro transmission upgrade 4. Conclusion Inception Report BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 1. Introduction Mozambique is a large country with abundant natural resources. Therefore, it has a high growth potential, and a proper development of the power system infrastructure will significantly aid the growth of the country. However, even though Mozambique is filled with natural resources, it is suffering from a qualitative and quantitative deficiency in electric power, which is hindering the national growth and the well-being of the citizens of Mozambique. This is due to the concentration of loads and generators in different areas, and the capital cost of transmission line construction to connect the source and sink is very expensive. The power system of Mozambique has been operated and expanded independently with four different areas, which are Northern (ATNO), Mid-Northern (ATCN), Central (ATCE), and Southern (ATSU), shown in Figure 1.1.1. The transmission losses are 24%, 23%, 19%, and 23% for Southern, Central, Mid-Northern, and Northern areas, respectively. In addition, especially higher loss rates are shown in Northern areas due to the long transmission system. Specifically, from the Statistical Summary document of 2012, the loss rate in the transmission network is (13%) higher than the loss rate in the distribution network (11%). Figure 1.1.1 Power system of Mozambique 4 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO The average level of reliability in Mozambique is 46.27 outages/year (in 2012) based on the System Average Interruption Frequency Index (SAIFI), and the Northern system has the highest outage level of 82.6 outages/year. In addition, the average System Average Interruption Duration Index (SAIDI) of Mozambique is 33hours and 46 minutes (based on 2012), and the Northern area displayed the highest interruption time with 71hours and 17minutes. In reality, these levelscan be translated into one or two outages every week, causing a significant negative impact to the economy, hindering their development to an advanced level of industry. In order to address these issues, there have been a steady effort to joint operate the power system networks to procure the economics and security of the power system. In addition, the utility of Mozambique, EDM, is working very hard to install additional transmission network, generation, etc., through international cooperation projects. Furthermore, the new cities in the Northern system, Nacala, Pemba, etc., is displaying much faster increase in the load growth rate, compared to other cities in Mozambique, due to natural gas and coal export industry development in the area. Therefore, in order to better the power transfer capability of the Northern area, projects, such as 400kV transmission network construction between Caia and Namialo, static variable compensator (SVC) installation along the transmission line, and expansion of generators are well under development. In this project, the goal is to provide a technical analysis for constructing a new transmission line between Namialo and Metoro in order to account for the significant increase in the loads in the Northern area (Pemba, Macomia, Ausse, etc). In order to suggest the best transmission construction and operation solution, long term load forecast (from 2016 to 2036) and analysis of generation and transmission expansion plan is conducted. 5 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO A. Overview of Northern Area 1.1.1 Power System Configuration The power system of Northern Mozambique is shown in Figure 1.1.2. Figure 1.1.2 Grid configuration of Northern Mozambique The Northern transmission system is composed with 1500km network connecting the source in the East to the loads in the West. Specifically, the main power sources are located 1300~1500km west of the loads, and the main loads are located near the cities in the coast of Sea of Indonesia. The main transmission lines (T/Ls) connecting the generators and loads are 220kV (main) and 110kV (sub). As a result, the system’s power transfer capability has reached its stability limit, and the active transmission capability (ATC) of the transmission network has been significantly reduced compared to the thermal ratings of transmission lines. In order to address the stability problem, static variable compensators and other equipments are installed and operated. Recently, in order to improve the transfer capability of the system, 400kV T/L is constructed between Caia and Nampula, which will better the stability aspect of the power system. However, due to the long length of transmission lines, lack of alternative transmission routes in case of line faults, and the possibility of system wide collapse if major generator is tripped, the Northern system still has much areas of improvement. Table 1.1.1 Power supply Indices of Northern area of Mozambique Area System Average Interruption Frequency Index(SAIFI) 6 System Average Interruption Duration Index(SAIDI) BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Northern System of 64.75 times/year. Per customer 905 min/year..per customer Mozambique (2014) Mozambique 57 times/year. Per customer 621 min/year per customer Nationalwide(2011) The reliability indices of Northern Mozambique power system is shown in Table 1.1.1 1.1.2 Electric Load Demand The load demand of the Northern area is 150MW in 2011, however, due to a high annual average growth rate of 14% of the coastal cities, Nacala and Pemba, the load is forecasted to reach 783MW in 2026 (JICA Report 2013). Table 1.1.2 load Forecasted data of Northern Power System((JICA Report 2013) Low Load Forecast by Demand (MW) Energy Consumption (GWh) Customer Service Area Custome Regio Provinc 201 201 202 202 203 AA 201 201 202 202 203 AA r Service n e 1 6 1 6 1 G 1 6 1 6 1 G Area 105 Tete AD Tete 29 177 98 105 153 9% 124 474 509 758 10% 2 Cente AD 9 23 25 28 38 7% 39 112 121 132 188 9% r Mocuba Zambez DDC AD ia Quelima 16 43 47 52 74 8% 94 210 234 265 360 7% ne ASC 106 48 74 122 138 188 7% 255 409 698 770 8% Nampula 3 Nampul ASC 124 213 218 457 22 206 350 359 727 21% 112 22% Nacala 8 8 4 5 North Cabo DDN ASC Delgad 17 51 70 77 117 11% 87 238 322 357 534 10% Pemba o AD Niassa 9 14 18 24 32 7% 40 55 70 91 117 6% Lichinga From Table 1.1.2, Nacala and Pemba show a high load growth rate of 22% and 11%, respectively. 7 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 800 700 AD Tete 600 AD Mocuba 500 AD Quelimane 400 ASC Nampula 300 ASC Nacala 200 ASC Pemba 100 AD Lichinga 0 2011 2016 2021 2026 2031 Figure 1.1.3 load growth of northern province[MW] (2011~2031) 1.1.3 Load characteristics The daily load curve of a peak load day in Mozambique is shown in Figure 1.1.4. The peak load is observed between 8~9p.m, and the peak usually occurs in November or December. In addition, in 2014, the peak load was observed in December 15th, at 831MW, and the average load is 606 MW. Figure 1.1.4. Load Profile of Peak day EDM (ref: Annual Statistical Report 2014, EDM) Figure 1.1.5 shows the load characteristics of mid, Northern, and Tete area. It is very similar to the load profile of entire system, where the peak load is 265MW. 8 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 1.1.5. Load profile of Northern Mozambique Peak day EDM(ref : Annual Statistical Report 2014, EDM) B. Objective of Namialo-Metoro Transmission System Study The objective of Namialo-Metoro T/L feasibility study is to determine the most economic and the most reliable transmissionnetwork considering the steep increase of load levels in the Northern area. The objectives can be summarized as follows: 1. Power system security assessment based on the transmission characteristics and transmission system expansion plan of the Northern Mozambique Area. 2. Transfer capability and loss assessment (from 2016 to 2036) of the Namialo-Metoro T/L construction and operation scenario, and developing the optimal installation plan. Three different construction and operation cases are considered: A. 220kV T/L construction, 220kV operation B. 400kV T/L construction, 220kV operation C. 400kV T/L construction, 400kV operation 9 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 2. Power Demand Forecast and Power Development Plan The demand, generation, and transmission line data were taken from EDM’s Master Plan Update Project 1, 2, and 3. The long term forecast data in this document bears high level of uncertainty, since Master Plan Update data is based on short term planning. Especially, the construction and integration of generators and transmission lines can be delayed for several years depending on various reasons, possibly affecting the load growth level. Therefore, the result of this study may have small margin of error. 2.1 Power Demand Forecast Demand forecast of Northern System was based on the long term load forecast of Master plan[2]. The load of Metoro substation in 2016 is estimated as 32.7MW, however, shall be 118MW in 2036. For a systematical analysis of the Northern transmission system, all of the loads connected to other substations were almost forecasted using the annual load growth rate, and the forecasted values of major substations are shown in Table 2.1. Furthermore, in order to account for the forecast error, ±10% of the forecasted value was calculated as low and high forecast values. Table 2.3.1. Power demand forecast of Northern system (2016~2036) AAG Substation Area District 2016 0.06 SE Cuamba AD 3.3 Lichinga 0.06 SE Lichinga AD 7.8 0.06 SE Marrupa AD 4.3 0.22 SE Monapo AD 94.2 Nacala 0.22 SE Nacala AD 115.7 Northern 0.08 SE Moma AD 34.5 Nampula 0.08 SE Nampula AD 53.1 0.1 SE Auasse AD 53.1 0.1 SE Macomia AD 2.1 Pemba 0.1 SE Metoro AD 11.4 0.1 SE Pemba AD 35.3 0.09 SE Alto Molocu AD 1.5 0.09 SE Gurue AD 8.8 Mocuba 0.09 SE Mocuba AD 4.9 0.09 SE Uape AD 8.6 H Transmission 0.07 SE Cerami AD 24.1 Queliman 0.07 SE Chimu AD 25.8 0.1 SE Manje AD 4.5 0.1 SE Matambo AD Tete 167.6 0.1 SE Tete AD 27.2 Total 641.2 Where AAG denotes the annual average load growth rate. 10 2021 4.5 10.3 6.4 157.1 199.2 68.3 71.5 71.5 2.8 12.8 54.6 2 10 6.4 8.8 39.2 27 6 81.6 38.3 813.8 2026 6 13.4 9.8 160.8 208.1 69.3 91 91 3.7 14.6 61.3 2.6 19.5 8.4 9.1 45.8 28.5 7.8 71.6 50.1 889 2031 9 18 11 166 220 68 116 116 5 18 67.6 3 14 11 9 47 30.495 8.58 78.76 55.11 966.545 2036 9.6 19.4 12.2 192.7 245.5 74.5 123 123 5.8 21 78.9 3.1 15.3 12.9 10 49.4 32.62965 9.438 86.636 60.621 1075.325 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 2.2 Power Generation Plan The generation expansion plan of the Mozambique system is shown in Table 2.2. Table 2.2.1. Power Generation Plan Plan Type Plant Name year Capacity[MW] CahoraBassa Cahora Bassa North in 2018 2075 1245 Boroma 2017 200 Contents Increase New Connection and Transmission Line Matambo 64.9km Cataxa 58.7km 400kV(4 tern), 70% Series compensation Matambo 220/33kV Tr. Songo-Matambo T branch MaphandaNukawa 2018 375MW×4 1500 400kV line(4 Tern), 50% Series compensation Hydro CAIA km Lupata 2018 600 Matambo 78km(on Map) 10~15km North of Gurue, 110kV Alto Malema Lurio 2019 50 T/L(71611-71612) - Transformer 100MVA Metro , 2017 180 120MW,2009 71711-71712, 110/33kV Macomia S/S connection Messalo 50 50km-EdM message Ncondezi 2017 400 200MWx2 -No data in USAID Benga 2017 2000 150MW×2 Matambo, 28km, 2cct 300MWx2(2012 present) Thermal 300MW×2 Moatize 2016 2400 180MW×2 600MWx3(Future) Matambo-Moatize T/L : 220kV 2cct 46.5km ENI 2017 75 75MW×1 JICA2011 report Nacala 2020 200 100MW×2 JICA2011 report 2.3 Transmission System Plan 11 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO In this section, the transmission expansion of the Northern Mozambique transmission system is discussed. 2.3.1 Transmission System Length trend (total of Central-Northern and Northern, by 2014. C-km) Table 2.4.1. Annual transmission line growth Voltage 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 220kV 1436 1436 1436 1436 1436 1436 1436 1436 1436 1437 1436 1436 1436 1436 110kV total 275 275 275 375 985 985 1155 1335 1335 1335 1467 1555 1555 1555 1711 1711 1711 1811 2421 2421 2591 2771 2771 2772 2903 2991 2991 2991 2.3.2 Transmission System Plans The transmission system expansion plan of the Northern Mozambique system is shown in Table 2.4. Table 2.3.2.Tansmission system expansion plan of northern system Commissioning Project name Capacity[MVA] Year 220kV line - Caia-Nampula 2015 Series compensation of the existing line 1) SVC in Nampula substation 2016 From To Length[km] Caia Nampula 486 77 Cuamba Marrupa 215 4) 110kV line Metoro-Pemba 77 Metoro Pemba 74 5) 220kV line Namialo-Metoro 239 6) 400kV line ChimuaraNamialo 1300 Namialo Caia Mocuba A.Molocue Metoro Mocuba A.Molocue Namialo 179 218 151 268 7)400/220kV Transformer 500 220kV STATCOM SVC 100/-50 400kV Sh. Reactor 60 400kV Sh. Reactor 60 Alto Molocue Line shunt 400/220kV Transfromer 250 400kV Sh. Reactor 60 400kV Sh. Reactor 60x2 Alto Molocue Line shunt 400/220 Transformer 500 400/110 Transformer 125 220kV STATCOM SVC 100/-50 400kV Sh. Reactor 60 400kV Sh. Reactor 60 2) 110kV line Cuamba-Marrupa 3) New Marrupa Substation 2016 2016 2016 12 Chimuara S/S Alto Molocue 400/220/110kV Namialo S/S Line shunt BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 2016 220kV twin tern line 480 Nampula Namialo 90.5 2016 220kV twin tern line 480 Nampula Evete 41.2 2016 220kV twin tern line 480 2020 220/110kV Transformer 125 Evete NacalaVelha 220kV NacalaVelha S/S 220kV SVC(under construction) 2017 61 220kV Nampula 1) 220kV line Nampula-Nacala Nampula Namialo Evate Nampula 480 2018 110kV line Nampula-Moma Source : Master Plan Update Project, 2012-2027 77 Namialo Evate Nacala Moma 91 41 61 170 2.3.3 Reactive Power compensation The system tools utilized in the Northern Mozambique system for reactive power compensation is discussed in this section. 2.3.3.1 Existing reactive compensation Existing reactive compensators are listed in Table 2.5. Table 2.3.3.Present reactive compensation devices No. Substation Unom[kV] Installed MVAr No. Items stats Sh. Cap. 1 Alto-Molocue 7.7 30 1 on 2 Lionde 33 8 1 on 3 Matambo 33 10 1 on 4 Chicumbane 33 8 1 Out of service Sh.Reactor 1 Alto-Molocue 7.7 50 1 on 2 Caia 220 20 1 on 3 Caia 33 15 1 on 4 Chibata 33 15 1 on 5 Lichinga 110 15 1 on 6 Matambo 33 5 1 on 7 Mocuba 33 65 1 on 8 Nampula220 33 20 1 on 9 Pemba 110 35 1 on 10 Quelimane 33 5 1 on 11 Songo 33 20 1 on 13 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Single Reactance 1 Macomia 110 50 1 on Source : “Technical Assistance to Strengthen EDM’s Capacity for Investment and Network Development Planning”, Master Plan Update Project, 2012 – 2027, Volume 1 Final System Review Report, 2013-04-15 2.3.3.2 Reactive compensation Plans The planned installation of reactive power compensators are shown in Table 2.3.4. Table 2.3.4.Plan of reactive compensator installation No. Substation Unom[kV] Installed MVAr No. Items stats Sh. Cap. 1 Alto-Molocue 7.7 30 1 on 2 Lionde 33 8 1 on 3 Matambo 33 10 1 on 4 Chicumbane 33 8 1 Out of service Sh.Reactor 1 Alto-Molocue 7.7 50 1 on 2 Caia 220 20 1 on 3 Caia 33 15 1 on 4 Chibata 33 15 1 on 5 Lichinga 110 15 1 on 6 Matambo 33 5 1 on 7 Mocuba 33 65 1 on 8 Nampula220 33 20 1 on 9 Pemba 110 35 1 on 10 Quelimane 33 5 1 on 11 Songo 33 20 1 on 1 on Single Reactance 1 Macomia 110 50 14 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.3 Power Flow Analysis In this section, the results of power flow analysis is provided in order to analyze the operational state of Northern Mozambique power system, using forecasted demand and generation values from section 2. In order to supply power at Metoro, Pemba, Macomia, and Mocimbua substations through Namialo-Metoro transmission line, four different Namialo-Metoro cases were analyzed. 1. No additional T/L construction 2. 220kV T/L construction 3. 400kV T/L construction, 220kV operation 4. 400kV T/L construction, 400kV operation Furthermore, the generators were dispatched considering the cost of generation for each generator. In cases where power flow analysis results diverged, must-run generators were operated in order to make the system operable. From the results, the system’s service standard, security, and reliability was analyzed for the steady state operation using bus voltages, phase angles, and power flows. Also, system power losses on transmission lines have been calculated for each case for economic evaluation. Also, the validity of this analysis may be questioned if the integration of Northern power system components does not follow the schedule. Hence, in order to analyze the sensitivity of the system to the planned integration of power sources, it was assumed that some generators are not online by its commissioning year (Lurio Hydro plant was assumed to be out of service), and additional analysis has been performed. Table 3.3.1 shows different cases which were considered for power flow analysis. The analysis was performed for the normal load level, and 1.1 times the normal load level. For Lurio outage case, normal load levels were used. Table 3.3.1 Power flow analysis cases Year 2016 SC0-2016 Scenario 0 100% SCA-2016 Generators Scenario A 100, 110% commissioned as planned SCB-2016 Scenario B 100, 110% Scenario C SCC-2016 2018 SC0-2018 100% SCA-2018 100, 110% SCB-2018 100, 110% SCC-2018 15 2021 SC0-2021 100% SCA-2021 100, 110% SCB-2021 100, 110% SCC-2021 2026 SC0-2026 100% SCA-2026 100, 110% SCB-2026 100, 110% SCC-2026 2031 SC0-2031 100% SCA-2031 100, 110% SCB-2031 100, 110% SCC-2031 2036 SC0-2036 100% SCA-2036 100, 110% SCB-2036 100, 110% SCC-2036 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Scenario 0 Lurio power plant out in service Scenario A Scenario B Scenario C 100, 110% SC0-2016 100% SCA-2016 100% SCB-2016 100% SCC-2016 100% 100, 110% SC0-2018 100% SCA-2018 100% SCB-2018 100% SCC-2018 100% 100, 110% SC0-2021 100% SCA-2021 100% SCB-2021 100% SCC-2021 100% 100, 110% SC0-2026 100% SCA-2026 100% SCB-2026 100% SCC-2026 100% 100, 110% SC0-2031 100% SCA-2031 100% SCB-2031 100% SCC-2031 100% 100, 110% SC0-2036 100% SCA-2036 100% SCB-2036 100% SCC-2036 100% 3.3.1Present Status of Northern Power System (2016) The modeling of Norther Mozambique power system is shown in Figure 3.3.1. At present, the main power supply to the grid comes from Cahora Bassa hydro plant (415MWx5=2075MW) and Moatize thermal plant (300x2=600MW). Although the total capacity is 2675MW, half (1300MW) is used to supply power to South Africa due to an agreement with Escom, leaving only 1375MW available. In 2016, Caia-Namialo 400kV HVAC backbone was commissioned, and is in parallel operation with 220kV transmission system, transporting half (263MW) of total supplied power (574MW) from the West. Therefore, the system is partly able to withstand few N-1 contingencies, compared to year 2015. Figure 3.3.1 Northern Power System of Mozambique However, since the power supplied to Namialo substation comes from 1300km away through many different system components, the maximum phase angle becomes -96 degrees (Pemba), which may cause instability in case of contingencies. The peak power received at Metoro substation in 2016 is 33+j16.3MVA, come from 110kV Namialo-Metoro T/L (215km). The sending end power is 37.0-j14.6MVA, and the loss is 4-j30.9MVA (10.8%). Also, the loss rate of Northern area was 15.8% due to a long rage power transmission. 16 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.3.6Load, Generation, Length of T/L (2016) Figure 3.3.7Bus Voltages and Phase Angles (2016) 3.3.2 Scenario 0: Not Constructing new T/L (SC0) In this section, the operational state of Northern power system is analyzed assuming that no additional transmission line will be constructed. Also, the transfer capability of 110kV T/L for different load levels is 17 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO analyzed. Figure 3.3.8Namialo-Metoro system diagram for Scenario 0 3.3.2.1 System Analysis (SC0-100%) The system state after 2018 was analyzed assuming that no additional transmission line was constructed to meet the increasing load levels. Table 3.3.2. Analyzed years in Scenario 0 SC0-2018 SC0-2021 SC0-2026 Scenario 0 100% 100% 100% 3.3.2.1.1 Analysis Results in 2018(SC0-2018, 100%) 18 SC0-2031 100% SC0-2036 100% BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a)Load and generation level and T/L length (b) Bus Voltages and Phase Angles Figure 3.3.3No T/L Construction (SC0 2018 100%) 3.3.2.1.2 Analysis Results in 2021(SC0-2021, 100%) 19 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Level and T/L Length (b) Bus Voltages and Phase Angles Figure 3.3.6No T/L Construction (SC0 2021 100%) If no additional T/L is constructed, the 110kV Namialo-Metoro T/L is able to supply 78MW of power to the loads after Metoro substation, and the phase angles of Namialo 110kV bus and Metoro 110kV bus become -82 and -137 degrees, respectively, with a phase angle difference of 67 degrees between two buses. 3.3.2.1.3 Analysis Results in 2026 (SC0 2026 100%) 20 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Level and T/L Length (b) Bus Voltages and Phase Angles Figure 3.3.7No T/L Construction (SC0 2026 100%) 3.3.2.1.4 Analysis Results in 2031 (SC0 2031 100%) 21 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Level, and T/L Length (b) Bus Voltages and Phase Angles Figure 3.3.8No T/L Construction (SC0 2031 100%) 3.3.2.1.5 Analysis Results in 2036(SC0 2036 100%) 22 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Levels, and T/L Length (b) Bus Voltages and Phase Angles Figure 3.3.9No T/L Construction (SC0 2036, 100%) 3.3.2.2Overview of Analysis Results (SC0, 100%) 23 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO In this section, the bus voltages, phase angles, power flows, and losses were calculated assuming that no additional T/L will be constructed. As a result, the T/L reaches its thermal limit in 2019, followed by worse voltage and phase angle values. Therefore, the power transfer limit of the T/L has been reached in 2019. 1,1 METORO 110 1,05 SC0 1 MOCIMBUA 0,95 110 SC0 METRO 2 220 0,9 220 SC0 0,85 METRO 4 SC0 0,8 2018 2021 2026 2031 2036 Figure 3.3.10Bus Voltages of Major Buses if No Additional T/L is Constructed 0 METORO 110 2018 2021 2026 2031 2036 SC0 MOCIMBUA -50 110 SC0 NAMIALO 110 -100 SC0 NAMIALO 220 SC0 -150 Figure 3.3.11Phase Angles of Major Buses if No Additional T/L is Constructed Table 3.3.2 Namialo-MetoroT/LLoading (SC0) 2018 2019 2020 2021 2022 2023 2024 110loading[MVA] 59 76.7 89.8 120.6 125.3 114.1 114 110kVrating[MVA] 77 77 77 77 77 77 77 110kV[%] 76.6 99.6 116.7 156.7 162.7 148.2 148 2025 2026 2027 2028 2029 2030 2031 110loading[MVA] 100.9 103.6 100.5 109.5 100.2 104.1 79.6 110kVrating[MVA] 77 77 77 77 77 77 77 110kV[%] 131 134.5 130.5 142.2 130.1 135.3 103.4 2032 2033 2034 2035 2036 24 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 110loading[MVA] 84.1 100.6 56 55 27.8 110kVrating[MVA] 77 77 77 77 77 110kV[%] 109.2 130.7 72.7 71.4 36.1 Table 3.3.3System andNamialo-MetoroT/L Losses (SC0, 100%) Total Loss[MW] Loss rate[%] 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 188.1 216.9 275.2 291.1 257.5 298 367.1 290.8 258.6 355.7 349.5 17.88 18.90 21.62 21.47 19.14 21.15 24.45 20.08 17.97 22.87 22.28 Namialo-Metoro 110kVLoss[MW] 9.71 16.53 22.9 41.86 45.09 37.53 37.28 29.15 30.99 28.87 34.39 2029 2030 2031 2032 2033 2034 2035 2036 SUM Total Loss[MW] 242.4 344.6 244.2 342.3 352.5 251.7 283.6 258.6 5468.4 16.37 21.51 16.06 20.79 20.93 15.63 16.98 15.46 28.77 31.11 17.85 20.13 28.92 8.94 8.51 2.06 Loss rate[%] Namialo-Metoro 110kVLoss[MW] 480.59 Table 3.3.4Transformers and T/Ls Exceeding 100% Capacity(SC0, 100%) 2021 2026 2031 2036 Scenario0 Rating [MVA] SERIES M to MOCUBA SERIES M to A-MOLOCU SERIES A to A-MOLOCU SERIES A to NAMPULA T-OFF2 to CAIA QUELIM.C to QUELIM.L SONGO A to PST NAMPULA3 to NAMPULA1 NAMPULA1 to NAMPULA NAMPUL.D to NAMPULA NAMPUL.D to NAMPULA NAMPUL.D to NAMPULA A-MOLOCU to A_MOLOCU NAMPULA to NAMP.CEN NAMP.CEN to NAMP.CEN MONAPO to NAMIALO MOMA to MOMA22 GURUE to GURUE METORO to METORO 3 METORO to NAMIALO PEMBA to PEMBA LICHINGA to LICHINGA NAMIALO to NAMIALO NCONDEZI to NCONDEZI 239 239 239 239 477 12 600 16 100 100 100 16 55 99 35 84 25 16 10 77 16 16 125 185 Loading [MVA] 281.2 281.2 303.2 303.2 Overrate [%] 118% 118% 127% 127% Loading [MVA] 267.9 267.9 269.9 269.9 Overrate [%] 112% 112% 113% 113% Loading [MVA] 262.8 262.8 263.4 263.4 Overrate [%] 110% 110% 110% 110% 37.5 1619.4 29.1 313% 270% 182% 45 1620 27.3 103.6 104.3 103.6 375% 270% 171% 104% 104% 104% 55 1624.7 27.8 107.3 107 107.3 458% 271% 174% 107% 107% 107% 151.4 105.8 39.2 128.5 36.8 275% 107% 112% 153% 147% 115.7 49.1 124.3 36.9 117% 140% 148% 148% 134.7 65.6 121.3 36.1 136% 187% 144% 144% 120.6 157% 103.6 135% 79.6 17 19.8 188.2 103% 106% 124% 151% 188.3 151% 186.6 149% Table 3.3.5 Buses with Abnormal Voltage Levels(SC0,100%) 2021 2026 2031 Scenario0 BaseV V[kV] [kV] MARRUPA NAMPULA3 NAMP.CEN CHIMUARA QUELIMAN QUELIM.C QUELIM.R QUELIM.L STAR BUS SERIES M MARROMEU 110 33 33 33 220 33 33 33 1 220 110 V[PU] V[kV] V[PU] 39.835 1.207 38.53 1.168 28.663 0.869 29.691 29.346 0.900 0.889 29.674 29.353 0.899 0.889 0.889 194.44 98.033 0.889 0.884 0.891 0.8895 197.33 0.890 0.897 25 V[kV] 121.39 38.908 29.53 29.086 29.613 0.8814 197.9 Loading [MVA] 281 281 286.4 286.4 487.1 58.5 1622.7 115.1 124.3 147 124.3 115.1 Overrate [%] 118% 118% 120% 120% 102% 488% 270% 719% 124% 147% 124% 719% 148.9 71.6 153.9 40 16.2 15 150% 205% 183% 160% 101% 150% 20.1 21.6 166.9 191.8 126% 135% 134% 104% 2036 V[PU] V[kV] V[PU] 1.104 1.179 0.895 0.881 0.897 0.881 0.900 28.2 0.855 197.82 28.953 28.487 29.042 0.8632 193.68 0.899 0.877 0.863 0.880 0.863 0.880 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO MARROMEU LICHINGA LICHINGA MOCIUMBA MOCIUMBA METORO METORO3 LURIOG1 MACOMIA 33 110 33 110 33 110 33 33 33 29.537 0.895 96.548 28.122 98.577 29.573 29.573 29.578 0.878 0.852 0.896 0.896 0.896 0.896 97.226 26.432 0.884 0.801 28.8 0.873 3.3.3ScenarioA :220kV T/L Construction & 220kV Operation(SCA) In this scenario, power system operating status of Northern area is analyzed considering the construction of 220kV Namialo-Metoro T/L. Annual increase of loads following Metoro substation has been taken into account. Figure 3.3.12System Diagram Considering 220kV Namialo-Metoro T/L Construction 3.3.3.1 System Analysis (SCA-100%) 26 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO The operating status of the system considering the construction of 220kV Namialo-Metoro T/L, in 2018, is analyzed. Scenario A SCA-2016 SCA-2018 SCA-2021 SCA-2026 SCA-2031 100, 110% 100, 110% 100, 110% 100, 110% 100, 110% 3.3.3.1.1 Analysis Results for 2018 (SCA-2018, 100%) (a) Load and Generation Levels and T/L Length 27 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (b) Bus Voltages and Phase Angles Figure 3.3.13Analysis Results Considering 220kV T/L Construction & 220kV Operation(SCA 2018 100%) 3.3.3.1.2 Analysis Results for 2021 (SCA-2021, 100%) (a) Load and Generation Levels and T/L Length 28 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (b) Bus Voltages and Phase Angles Figure 3.3.14220kV T/L Construction & 220kV Operation(SCA 2021 100%) If 220kV T/L is constructed, 110kV and 220kV Namialo-Metoro T/L is capable of sending 78MW to Metoro substation, and the phase angles of Namialo and Metoro 110kV bus are -75 and -72.9 degrees, respectively. As a result, the phase angle difference between two buses have been significantly reduced due to operation of must run generation at Lurio. 3.3.3.1.3 Analysis Results for 2026 (SCA-2026, 100%) 29 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Level and T/L Length (b) Bus Voltages and Phase Angles Figure 3.3.15220kV T/L Construction & 220kV Operation(SCA 2026 100%) 3.3.3.1.4 Analysis Results for 2031 (SCA-2031, 100%) (a) Load and Generation Levels and T/L Length 30 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (b) Bus Voltages and Phase Angles Figure 3.3.16220kV T/L Construction & 220kV Operation(SCA 2031 100%) 3.3.3.1.5 Analysis Results for 2036 (SCA-2036, 100%) (a) Load and Generation Level and T/L Length 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (b) Bus Voltages and Phase Angles Figure 3.3.17220kV T/L Construction & 220kV Operation(SCA 2036, 100%) 3.3.3.2Overview of Analysis Results (SCA, 100%) In this section, bus voltages, phase angles, power flows, and losses of major buses has been analyzed considering the construction and operation of 220kV T/L. The results show that although the line flows do not reach the limit, after 2026, line flow is maintained at 30% of line capacity, and the bus voltages and phase angles becomes worse due to long range power transmission. Furthermore, the voltage level at Metoro substation is higher compared to other buses, which is due to the Ferranti effect. 1,1 METORO 110 1,05 SCA NAMIALO 110 1 SCA 0,95 NAMIALO 220 SCA 0,9 MOCIUMBA 110 SCA 0,85 2018 2021 2026 2031 2036 Figure 3.3.18Voltages of Major Buses Considering 220kV T/L Construction & 220kV Operation 32 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 0 2018 2021 2026 2031 2036 METORO 110 -20 SCA NAMIALO 110 -40 SCA -60 NAMIALO 220 -80 MOCIUMBA 110 SCA SCA -100 Figure 3.3.19Phase Angles of Major Buses Considering 220kV T/L Construction &220kV Operation Table 3.3.6 Namialo-MetoroT/L Loading Levels (SCA, 100%) 2018 2019 2020 2021 110loading[MVA] 14.4 9.5 8.2 7.7 110kVrating[MVA] 77 77 77 77 110kV% 18.7% 12.3% 10.6% 10.0% 220kVloading[MVA] 28.6 43.1 48 57 220kVrating[MVA] 239 239 239 239 220kV% 12.0% 18.0% 20.1% 23.8% 2025 2026 2027 2028 110loading[MVA] 6.4 9.6 5.4 5.3 110kVrating[MVA] 77 77 77 77 110kV% 8.3% 12.5% 7.0% 6.9% 220kVloading[MVA] 57.6 75.4 59.9 63.2 220kVrating[MVA] 239 239 239 239 220kV% 24.1% 31.5% 25.1% 26.4% 2032 2033 2034 2035 110loading[MVA] 7.3 5.3 6.7 4.4 110kVrating[MVA] 77 77 77 77 110kV% 9.5% 6.9% 8.7% 5.7% 220kVloading[MVA] 74.5 71 75.5 77.1 220kVrating[MVA] 239 239 239 239 220kV% 31.2% 29.7% 31.6% 32.3% 2022 6.9 77 9.0% 51.8 239 21.7% 2029 5.6 77 7.3% 65.8 239 27.5% 2036 7.2 77 9.4% 84.5 239 35.4% 2023 6.8 77 8.8% 55.9 239 23.4% 2030 5.6 77 7.3% 67.5 239 28.2% 2024 8.4 77 10.9% 62 239 25.9% 2031 4.9 77 6.4% 67.8 239 28.4% Table 3.3.7System &Namialo-MetoroT/L Losses (SCA, 100%) Total Loss[MW] Loss rate[%] 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 140.1 155.7 187.3 229.8 236.4 243.6 257 269.7 304.6 276.9 295.6 17.85 17.98 18.47 18.90 20.51 Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] 13.95 0.42 0.18 14.33 0.13 15.81 0.1 17.75 0.08 0.08 0.1 0.05 0.1 0.03 0.03 0.05 0.3 0.46 0.77 0.63 0.76 0.98 0.84 1.63 0.97 1.12 2029 2030 2031 2032 2033 2034 2035 2036 SUM Total Loss[MW] 303.3 296.6 246 256.1 219.1 234.2 251.5 270.5 33 4674 18.75 19.52 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Loss rate[%] 19.68 Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] 14.13 14.70 15.35 16.06 0.02 0.02 19.09 0.01 16.16 0.04 16.42 0.01 0.02 0 0.03 1.12 1.33 1.37 1.69 1.58 1.82 1.92 2.33 1.45 21.79 Table 3.3.8 System &Namialo-MetoroT/L Losses (SCA, 110%) 2018 Total Loss[MW] Loss rate[%] Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] 2019 Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] 2022 2023 2024 2025 2026 SERIES M to MOCUBA SERIES M to A-MOLOCU SERIES A to A-MOLOCU SERIES A to NAMPULA T-OFF2 to CAIA QUELIM.C to QUELIM.L SONGO A to PST NAMPULA3to NAMPULA1 MATAMBO to TETE MATAMBO to CAIA A-MOLOCUto A_MOLOCU NAMPULA to NAMP.CEN NAMP.CEN to NAMP.CEN MONAPO to MONAPO MONAPO to NAMIALO MOMA to MOMA22 CAIA to CAIA 4 METORO to METORO 3 PEMBA to PEMBA LICHINGA to 2028 217.5 279.1 278.6 233.2 245.9 261.4 268.4 296 295.1 14.96 16.13 16.51 19.21 18.85 16.00 16.43 17.01 17.10 18.31 18.01 0.52 0.16 0.13 0.1 0.09 0.06 0.06 0.08 0.05 0.05 0.01 1.51 1.45 1.45 0.48 0.69 2030 1.17 2031 2032 1.14 1.07 1.21 1.37 2033 2034 2035 2036 SUM 309.8 304 221.7 253.6 257.1 274.8 270.5 287.3 4919 18.50 17.99 13.78 15.00 14.91 15.51 15.04 15.57 0 0.18 0.42 0.28 0.42 0.59 1.01 1.21 5.42 1.62 0.73 0.26 0.7 0.42 0.34 0.13 0.11 15.97 Table 3.3.9 T/Ls & Transformers Exceeding 100% Capacity(SCA,100%) 2016 2021 2026 2031 ScenarioA Rating [MVA] 2027 197.4 0.12 Loss rate[%] 2021 167.6 2029 Total Loss[MW] 2020 Loading [MVA] Overrate [%] 2036 Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] 239 264.8 111% 331.2 139% 276.4 116% 294.2 123% 239 264.8 111% 331.2 139% 276.4 116% 294.2 123% 239 291.8 122% 316.7 133% 295.3 124% 302.1 126% 239 291.8 122% 316.7 133% 295.3 124% 302.1 126% 540.3 113% 500.3 105% 477 12 27.8 232% 37 308% 47.3 394% 55.5 463% 57.5 479% 600 1607.9 268% 1620.7 270% 1616.7 269% 1622.9 270% 1618.3 270% 29.1 182% 27.9 174% 28 175% 27.3 171% 63.7 106% 16 60 477 55 99.2 180% 99 36 39.2 109% 479.4 101% 261.3 475% 96.4 175% 139.9 254% 114 115% 136.3 138% 142.6 144% 49 136% 65.5 182% 66.2 184% 30.9 103% 30 84 143.1 170% 148.4 177% 137.3 163% 154 183% 25 36.8 147% 36.9 148% 36.1 144% 40.7 163% 275.8 110% 256.3 103% 27.7 277% 250 10 27.7 277% 28.1 281% 28.1 281% 16 17 106% 19.8 124% 16 20.1 126% 20.3 127% 34 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO LICHINGA NAMIALO to NAMIALO NCONDEZI to NCONDEZI MOATIZE to MOATIZE 100 105.3 105% 109.8 110% 185 263.9 143% 198.4 107% 185 254.2 118.6 119% 132.3 132% 185.3 100% 137% Table 3.3.10 Buses with Voltage Level Violation (SCA,100%) ScenarioA NAMPULA NAMPULA NAMPULA3 A-MOLOCU CHIMUARA QUELIMAN QUELIM.C QUELIM.R QUELIM.L CAIA CAIA STAR BUS SERIES M SERIES C MARROMEU MARROMEU NICUADAL MONAPO LICHINGA BaseV [kV] 110 33 33 7.7 33 220 33 33 33 220 110 1 220 220 110 33 220 33 33 2016 V[kV] 123.19 2021 V[PU] V[kV] 2026 V[PU] V[kV] 2031 V[PU] V[kV] 2036 V[PU] V[kV] V[PU] 1.120 36.852 39.82 1.117 1.207 29.065 0.881 36.325 39.011 8.57 27.204 191.5 28.199 27.865 28.27 197.18 95.959 0.844 184.04 191.73 92.849 27.793 192.34 29.068 28.877 1.101 1.182 1.113 0.824 0.870 0.855 0.844 0.857 0.896 0.872 0.844 0.837 0.872 0.844 0.842 0.874 0.881 0.875 36.325 39.011 8.57 27.204 191.5 28.199 27.865 28.27 197.18 95.959 0.844 184.04 191.73 92.849 27.793 192.34 29.068 28.877 1.101 1.182 1.113 0.824 0.870 0.855 0.844 0.857 0.896 0.872 0.844 0.837 0.872 0.844 0.842 0.874 0.881 0.875 38.529 1.168 27.894 195.49 28.772 28.483 28.857 0.845 0.889 0.872 0.863 0.874 98.245 0.863 190.98 196.59 95.047 28.505 196.44 29.457 29.163 0.893 0.863 0.868 0.894 0.864 0.864 0.893 0.893 0.884 3.3.4 ScenarioB :400kV T/L Construction & 220kV Operation(SCB) In this section, the steady state operation of 400kV Namialo-Metoro T/L operating on 220kV is analyzed, considering annual growth of loads connected to Metoro substation. 35 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.3.20System Diagram Considering 400kV T/L Construction& 220kV Operation 3.3.4.1 System Analysis (SCB-100%) In this section, the system status is analyzed for different years after 2018, considering the construction of 400kV T/L, and operating it on 220kV. Scenario B SCB-2016 SCB-2018 SCB-2021 SCB-2026 SCB-2031 100, 110% 100, 110% 100, 110% 100, 110% 100, 110% 36 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.3.4.1.1 Analysis Results for 2018(SCB-2018, 100%) (a) Load and Generation Level and T/L Length (b) Bus Voltages and Phase Angles Figure 3.3.21400kV T/L Construction and 220kV Operation(SCB 2018 100%) 37 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.3.4.1.2 Analysis Results for 2021(SCB-2021, 100%) (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.22400kV T/L Construction & 220kV Operation (SCB 2021 100%) If 400kV T/L is constructed and operated on 220kV, 110kV and 220kV Namialo-Metoro T/L is able to supply 78MW to loads following Metoro substation, and the phase angles of 110kV buses at Namialo and Metoro substation becomes -74.5 and -71.2, respectively. The phase angles of two 38 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO buses are slightly improved compared to Scenario A, however, not by much. 3.3.4.1.3 Analysis Results for 2026(SCB-2026, 100%) (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.23400kV T/L Construction & 220kV Operation (SCB 2026 100%) 3.3.4.1.4 Analysis Results for 2031(SCB-2031, 100%) 39 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.24400kV T/L Construction & 220kV Operation (SCB 2031 100%) 40 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.3.4.1.5 Analysis Results for 2036 (SCB-2036, 100%) (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.25400kV T/L Construction & 220kV Operation(SCB 2036 100%) 41 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.3.4.2 Overview of Analysis Results (SCB, 100%) In this section, the voltages, phase angles, power flow, and losses of major buses for different years have been analyzed considering 400kV T/L construction and 220kV operation. The results show improved line flows compared to Scenario 0 and A, and that the voltages and phase angles of major buses become worse as year progresses, due to long range transmission. Again, high voltage level at Metoro substation is caused by Ferranti effect. 1,1 METORO 110 SCB 1,05 NAMIALO 110 SCB 1 NAMIALO 220 SCB 0,95 MOCIUMBA 110 SCB 0,9 2018 2021 2026 2031 2036 Figure 3.3.26 Voltages of Major Buses Considering 400kV T/L Construction & 220kV Operation 0 2018 2021 2026 2031 2036 -20 METORO 110 SCB -40 NAMIALO 110 SCB NAMIALO 220 SCB -60 MOCIUMBA 110 -80 SCB -100 Figure 3.3.27 Phase Angles of Major Buses Considering 400kV T/L Construction & 220kV Operation Table 3.3.11 Namialo-MetoroT/L Loading (SCB, 100%) 2018 2019 2020 2021 42 2022 2023 2024 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 110loading[MVA] 110kVrating[MVA] 110kV% 220kVloading[MVA] 220kVrating[MVA] 220kV% 110loading[MVA] 110kVrating[MVA] 110kV% 220kVloading[MVA] 220kVrating[MVA] 220kV% 110loading[MVA] 110kVrating[MVA] 110kV% 220kVloading[MVA] 220kVrating[MVA] 220kV% 16 77 20.8% 37 715 5.2% 2025 9.5 77 12.3% 65.9 715 9.2% 2032 7.2 77 9.4% 81.5 715 11.4% 11 77 14.3% 52.9 715 7.4% 2026 10.1 77 13.1% 80.9 715 11.3% 2033 6.7 77 8.7% 78.4 715 11.0% 10.3 77 13.4% 57.4 715 8.0% 2027 8.8 77 11.4% 68 715 9.5% 2034 7.1 77 9.2% 83.4 715 11.7% 9.4 77 12.2% 65.6 715 9.2% 2028 8.2 77 10.6% 71.8 715 10.0% 2035 7.1 77 9.2% 84.9 715 11.9% 9.6 77 12.5% 59.7 715 8.3% 2029 7.8 77 10.1% 74.5 715 10.4% 2036 6 77 7.8% 90.6 715 12.7% 9.3 77 12.1% 62.8 715 8.8% 2030 7.4 77 9.6% 76 715 10.6% 9 77 11.7% 69.9 715 9.8% 2031 7.5 77 9.7% 74.6 715 10.4% Table 3.3.12 System and Namialo-MetoroT/L Losses (SCB, 100%) Total Loss[MW] Loss rate[%] Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] Total Loss[MW] Loss rate[%] Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 135.7 155.2 186.5 228.2 235.3 242.2 254.8 268.1 288.1 275.4 293.7 13.57 17.78 17.90 18.34 18.81 19.61 0.54 0.25 14.29 0.22 15.75 0.2 17.65 0.18 0.17 0.18 0.16 0.2 0.14 0.13 0.05 0.18 0.25 0.38 0.31 0.35 0.46 0.41 0.66 0.46 0.53 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 SUM 301 294.3 242.8 250.7 217.4 232.1 249.1 263 4613.6 19.55 14.04 14.59 14.86 15.68 0.12 0.11 18.97 0.09 15.98 0.1 16.13 0.07 0.08 0.06 0.06 0.59 0.62 0.61 0.75 0.71 0.82 0.87 1 18.67 19.41 3.06 10.01 Table 3.3.13 System and Namialo-MetoroT/L Losses (SCB, 110%) 2018 Total Loss[MW] Loss rate[%] Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] Loss rate[%] Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] 2020 2021 2022 2023 2024 2025 2026 178.1 196.5 216.8 277.2 276.8 232 246.3 262.5 266.3 293.3 293.9 15.75 16.07 16.47 19.11 18.75 15.93 16.46 17.07 16.99 18.16 17.95 0.39 0.26 0.23 0.2 0.2 0.17 0.17 0.18 0.15 0.15 0.13 0.75 0.68 0.74 0.16 2029 Total Loss[MW] 2019 0.27 2030 0.37 2031 0.59 2032 0.58 0.53 0.6 0.68 2033 2034 2035 2036 SUM 4835.1 285.5 304.7 231.8 245.4 254.7 245.4 260.3 267.6 17.30 18.03 14.15 14.59 14.79 14.26 14.56 14.66 0.1 0.34 0.53 0.58 0.57 1.09 1.26 1.47 8.17 0.72 0.36 0.16 0.3 0.2 0.11 0.19 0.12 8.11 43 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Table 3.3.14 T/Ls and Transformers Exceeding 100% Capacity (SCB, 100%) 2021 2026 2031 ScenarioB Rating 2016 SERIES M to MOCUBA SERIES M to A-MOLOCU SERIES A to A-MOLOCU SERIES A to NAMPULA T-OFF2 to CAIA QUELIM.C to QUELIM.L SONGO A to PST NAMPULA3to NAMPULA1 MATAMBO to TETE MATAMBO to CAIA A-MOLOCUto A_MOLOCU NAMPULA to NAMP.CEN NAMP.CEN to NAMP.CEN MONAPO to MONAPO MONAPO to NAMIALO MOMA to MOMA22 CAIA to CAIA 4 METORO to METORO 3 PEMBA to PEMBA LICHINGA to LICHINGA NAMIALO to NAMIALO NCONDEZI to NCONDEZI MOATIZE to MOATIZE 2036 [MVA] Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] 239 263 110% 317.4 133% 274.9 115% 291 122% 263 110% 239 263 110% 317.4 133% 274.9 115% 291 122% 263 110% 239 292.1 122% 312.3 131% 293.4 123% 298.1 125% 292.1 122% 239 292.1 122% 312.3 131% 293.4 123% 298.1 125% 292.1 122% 525.1 110% 494.7 104% 477 12 36.9 308% 46.6 388% 55.2 460% 56.8 473% 36.9 308% 600 1620.8 270% 1617.5 270% 1623.2 271% 1618.8 270% 1620.8 270% 16 29.4 184% 28.3 177% 28.5 178% 28.1 176% 29.4 184% 63.6 106% 86 156% 39.2 109% 60 477 55 86 156% 99 36 39.2 109% 220 400% 95.9 174% 140.9 256% 112.1 113% 134.8 136% 139.8 141% 49 136% 65.4 182% 66 183% 30.7 102% 30 84 142 169% 148.2 176% 137.2 163% 153.2 182% 142 169% 25 36.8 147% 36.8 147% 36.1 144% 40.6 162% 36.8 147% 270.2 108% 255.6 102% 27.7 277% 27.7 277% 104.1 104% 263.7 143% 250 10 27.7 277% 28 280% 28 280% 16 17 106% 19.8 124% 16 20.1 126% 20.3 127% 116.4 116% 130 130% 100 104.1 104% 107.1 107% 185 263.7 143% 196.4 106% 185 Table 3.3.15Buses with Abnormal Voltage Levels (SCB, 100%) ScenarioB NAMPULA NAMPULA NAMPULA3 A-MOLOCU CHIMUARA QUELIMAN QUELIM.C QUELIM.R QUELIM.L CAIA CAIA STAR BUS SERIES M SERIES C MARROMEU MARROMEU BaseV [kV] 110 33 33 7.7 33 220 33 33 33 220 110 1 220 220 110 33 2016 V[kV] 123.19 2021 V[PU] V[kV] 2026 V[PU] V[kV] 2031 V[PU] V[kV] 2036 V[PU] V[kV] V[PU] 1.120 36.812 39.994 1.116 1.212 36.496 39.248 1.106 1.189 36.603 39.374 1.109 1.193 36.45 1.105 29.108 0.882 27.625 194.25 28.621 28.291 28.691 0.837 0.883 0.867 0.857 0.869 29.298 0.888 29.435 28.99 29.519 0.892 0.878 0.895 28.217 197.86 29.136 28.849 29.219 0.855 0.899 0.883 0.874 0.885 97.343 0.857 187.37 193.85 94.307 28.28 0.885 0.857 0.852 0.881 0.857 0.857 0.878 196.56 0.878 0.893 0.874 192.82 197.76 96.167 28.88 0.874 0.876 0.899 0.874 0.875 44 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO NICUADAL MONAPO LICHINGA 220 33 33 195.08 29.311 28.877 0.887 0.888 0.875 28.151 0.853 29.34 0.889 3.3.5Scenario C:400kV T/L Construction & 400kV Operation(SCC) In this section the steady state operation of 400kV Namialo-Metoro T/L construction and operation is analyzed considering annual load growth levels of the loads connected to Metoro substation. Figure 3.3.28System Diagram for 400kV T/L Construction & 400kV Operation 3.3.5.1 System Analysis (SCC-100%) In this section, the system status considering 400kV Namialo-Metoro T/L construction and 400kV operation is analyzed after 2018. Scenario C SCC-2016 SCC-2018 SCC-2021 SCC-2026 SCC-2031 100, 110% 100, 110% 100, 110% 100, 110% 100, 110% 3.3.5.1.1 Analysis Results for 2018 (SCC-2018, 100%) 45 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.29400kV T/L Construction and 400kV Operation (SCC 2018 100%) 3.3.5.1.2 Analysis Results for 2021(SCC-2021, 100%) 46 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.30400kV T/L Construction and 400kV Operation (SCC 2021 100%) In 2021, if 400kV T/L is constructed and operated on 400kV, 110kV and 220kV Namialo-Metoro T/L is able to supply 78MW to loads connected to Metoro substation, and the phase angles of 110kV buses at Namialo and Metoro substations are -72.3 and -64.7, respectively, showing a significant improvement compared to Scenario A and B. 3.3.5.1.3 Analysis Results for 2026(SCC-2026, 100%) 47 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.31400kV T/L Construction and 400kV Operation(SCC 2026 100%) 3.3.5.1.4 Analysis Results for 2031(SCC-2031, 100%) 48 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.32400kV T/L Construction and 400kV Operation(SCC 2031 100%) 3.3.5.1.5 Analysis Results for 2036(SCC-2036, 100%) 49 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (a) Load and Generation Levels and T/L Lengths (b) Bus Voltages and Phase Angles Figure 3.3.33400kV T/L Construction and 400kV Operation(SCC 2036 100%) 3.3.5.2 Overview of Analysis Results (SCC, 100%) 50 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO The voltages, phase angles, line flows, and losses of major buses for different years have been analyzed considering 400kV T/L construction and 400kV operation. The results show that the line flow is maintained between 10~20% of transmission limit until 2036, and improved voltage levels and phase angles compared to other scenarios. The voltage level at Metoro substation is higher than other substations due to Ferranti effect. 1,1 METORO 110 SCC 1,05 NAMIALO 110 SCC 1 NAMIALO 220 SCC 0,95 MOCIUMBA 110 SCC 0,9 2018 2021 2026 2031 2036 Figure 3.3.34 Voltages of Major Buses Considering 400kV T/L Construction & 400kV Operation400kV 0 2018 2021 2026 2031 2036 METORO 110 SCC -20 NAMIALO 110 SCC -40 NAMIALO 220 SCC -60 MOCIUMBA 110 -80 SCC -100 Figure 3.3.35Phase Angles of Major Buses Considering 400kV T/L Construction & 400kV Operation Table 3.3.16 Namialo-MetoroT/L Loading (SCC, 100%) 2018 2019 2020 110loading[MVA] 19.6 18.9 19.5 110kVrating[MVA] 77 77 77 110kV% 25.5% 24.5% 25.3% 220kVloading[MVA] 119.4 129.4 135.6 220kVrating[MVA] 1300 1300 1300 220kV% 9.2% 10.0% 10.4% 2025 2026 2027 51 2021 20 77 26.0% 146.5 1300 11.3% 2028 2022 20.2 77 26.2% 136.8 1300 10.5% 2029 2023 20.2 77 26.2% 140.8 1300 10.8% 2030 2024 20.1 77 26.1% 146.1 1300 11.2% 2031 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 110loading[MVA] 110kVrating[MVA] 110kV% 220kVloading[MVA] 220kVrating[MVA] 220kV% 20 77 26.0% 151.7 1300 11.7% 2032 18.7 77 24.3% 156.8 1300 12.1% 110loading[MVA] 110kVrating[MVA] 110kV% 220kVloading[MVA] 220kVrating[MVA] 220kV% 19.9 77 25.8% 172.8 1300 13.3% 2033 18 77 23.4% 155.3 1300 11.9% 20.2 77 26.2% 154.5 1300 11.9% 2034 18.2 77 23.6% 159.4 1300 12.3% 20.2 77 26.2% 157.7 1300 12.1% 2035 19.1 77 24.8% 162.9 1300 12.5% 20 77 26.0% 159.6 1300 12.3% 2036 19 77 24.7% 166.8 1300 12.8% 19.7 77 25.6% 159.9 1300 12.3% 18.8 77 24.4% 154.3 1300 11.9% Table 3.3.17 System &Namialo-MetoroT/L Losses (SCC, 100%) Total Loss[MW] 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 135.2 153 182.9 221.8 229.3 235.6 246.6 259.9 278.6 268.1 284.7 Loss rate[%] 13.53 Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] Total Loss[MW] Loss rate[%] 17.41 17.50 17.85 18.34 0.92 0.84 14.11 0.9 0.96 0.97 0.97 0.97 0.98 1.01 0.98 0.98 0.09 0.14 0.18 0.25 0.21 0.23 0.26 0.3 0.46 0.33 0.36 17.24 19.09 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 SUM 291 284.9 235.1 238.4 213.4 227.1 243 254.2 4482.8 19.03 NamialoMetoro110kVLoss [MW] Namialo-Metoro 220kVLoss[MW] 15.49 13.81 14.32 14.91 15.24 0.97 0.94 18.47 0.84 15.55 0.84 15.77 0.78 0.81 0.86 0.86 17.38 0.38 0.39 0.35 0.37 0.37 0.41 0.44 0.48 6 2026 18.26 18.93 Table 3.3.18 System &Namialo-MetoroT/L Losses (SCC, 110%) 2018 Total Loss[MW] Loss rate[%] Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] 2019 Namialo-Metoro 110kVLoss[MW] Namialo-Metoro 220kVLoss[MW] 2022 2023 2024 2025 193.2 212.9 269.8 268.9 227.8 239.7 253.7 259.1 283.8 283 15.55 15.84 16.22 18.69 18.32 15.68 16.09 16.59 16.61 17.67 17.40 0.96 0.95 0.98 1.1 1.07 0.98 1 1 1 0.99 0.98 0.49 0.41 0.42 0.15 Loss rate[%] 2021 175.5 2029 Total Loss[MW] 2020 0.27 2030 0.31 2031 0.47 2032 0.4 0.36 0.4 2033 2034 2035 0.43 2036 SUM 295.7 294.9 220 236.6 248.3 262.7 266.6 252 17.81 17.55 13.69 14.31 14.65 14.93 14.86 14.09 4744.2 0.98 1.32 1.37 1.33 1.54 1.73 2.04 2.72 24.04 0.46 0.32 0.17 0.24 0.2 0.2 0.18 0.14 6.02 Table 3.3.19 T/Ls and Transformers Exceeding 100% Capacity (SCC, 100%) 2021 2026 2031 ScenarioC Rating 2016 SERIES M to MOCUBA SERIES M to A-MOLOCU Loading [MVA] Overrate [%] 2036 Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] Loading [MVA] Overrate [%] 239 251.5 105% 302.3 126% 264.3 111% 278.1 116% 239 251.5 105% 302.3 126% 264.3 111% 278.1 116% [MVA] 52 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO SERIES A to A-MOLOCU SERIES A to NAMPULA T-OFF2 to CAIA QUELIM.C to QUELIM.L SONGO A to PST NAMPULA3to NAMPULA1 MATAMBO to TETE MATAMBO to CAIA A-MOLOCUto A_MOLOCU NAMPULA to NAMP.CEN NAMP.CEN to NAMP.CEN MONAPO to MONAPO MONAPO to NAMIALO MOMA to MOMA22 CAIA to CAIA 4 METORO to METORO 3 PEMBA to PEMBA LICHINGA to LICHINGA NAMIALO to NAMIALO NCONDEZI to NCONDEZI MOATIZE to MOATIZE 239 279.2 117% 305.8 128% 280.5 117% 286.9 120% 239 279.2 117% 305.8 128% 280.5 117% 286.9 120% 518.2 109% 488.4 102% 477 12 27.8 232% 36.6 305% 46 383% 54.4 453% 56 467% 600 1607.9 268% 1621.4 270% 1618.2 270% 1623.8 271% 1619.5 270% 29.6 185% 29.3 183% 29 181% 29.2 183% 63.5 106% 76.3 139% 16 60 477 55 133.9 243% 99 107.7 109% 130.5 132% 134.1 135% 48.9 136% 65.3 181% 65.8 183% 30.5 102% 36 39.2 109% 30 84 138.5 165% 146.8 175% 136.4 162% 151.8 181% 25 36.8 147% 36.8 147% 36.1 144% 40.6 162% 269.9 108% 255.7 102% 27.7 277% 250 10 27.7 277% 27.8 278% 27.8 278% 16 17 106% 19.8 124% 16 20.1 126% 20.3 127% 110.3 110% 124.9 125% 100 185 185 262.9 254.2 142% 101.9 102% 195.1 105% 137% Table 3.3.20 Buses with Abnormal Voltage Levels (SCC, 100%) ScenarioC NAMPULA NAMPULA NAMPULA3 A-MOLOCU CHIMUARA QUELIMAN QUELIM.C QUELIM.R QUELIM.L CAIA CAIA STAR BUS SERIES M SERIES C MARROMEU MARROMEU NICUADAL MONAPO LICHINGA BaseV [kV] 110 33 33 7.7 33 220 33 33 33 220 110 1 220 220 110 33 220 33 33 2016 V[kV] 123.19 2021 V[PU] V[kV] 2026 V[PU] V[kV] 2031 V[PU] V[kV] 2036 V[PU] V[kV] V[PU] 1.120 40.14 1.216 36.752 39.913 1.114 1.209 36.384 39.736 1.103 1.204 36.328 39.903 1.101 1.209 29.373 0.890 27.977 196.64 28.986 28.659 29.055 0.848 0.894 0.878 0.868 0.880 29.657 0.899 28.604 0.867 29.403 0.891 29.555 29.27 29.637 0.896 0.887 0.898 98.499 0.868 191.35 195.5 95.522 28.686 197.45 0.895 0.868 0.870 0.889 0.868 0.869 0.898 0.891 0.891 0.887 196.62 0.887 0.894 97.506 29.326 0.886 0.889 28.877 0.875 29.426 0.892 28.275 0.857 3.3.6Overview of Power Flow Analysis Results The analysis results for different scenarios are discussed in the aspect of system security (phase angle, T/L loading, rating, voltage violation, and T/L and transformer exceeding capacity improvement) and economics 53 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO (loss reduction and must-run generation operation). 3.3.6.1 System Security Improvement 1. Phase Angle Improvement 150 Scenario0 110kV 100 ScenarioA110kV 50 ScenarioA220kV ScenarioB110kV 0 18 21 26 31 ScenarioB220kV 36 Figure 3.3.36Absolute Value of Phase Angles for Different Scenarios at Metoro Bus The y-axis of the graph shows the phase angle of Metoro bus for different scenarios. It is shown that the Scenario C has the lowest value of phase angle compared to other scenarios. 2. T/L Loading Level Improvement 200,00% ScenarioA 110kV 150,00% ScenarioA 220kV 100,00% ScenarioB 110kV ScenarioB 220kV 50,00% ScenarioC 110kV 0,00% ScenarioC 400kV 19 21 23 25 27 29 31 33 35 Figure 3.3.37 Namialo-Metoro T/L Loading (Scenario A, B, C, 0) The graph above shows the loading levels of Namialo-Metoro T/L in percentages. All scenarios show that the T/L is operated within 30% of its thermal capacity, except Scenario 0. Therefore thermal capacity is not a major problem in this study. 3. Reduction of Voltage Violation Buses 60 0,135 40 0,13 ScenarioA 20 ScenarioB ScenarioC 0 ScenarioA ScenarioB 0,125 Total number of ScenarioC 0,12 off-limit V buses Deviation 54 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.3.38Voltage Violating Buses (Scenario A, B, C) In Figure 3.3.38, the graph on the left shows the total number of buses that have violated the voltage range (0.9~1.1p.u) for all the years under consideration for Scenario A, B, and C. It has been observed that Scenario C has the smallest number of buses violating the voltage range, whereas Scenario A has the largest number of voltage violations. The figure on the right shows the range of voltage deviation from the normal range for various Scenarios, and it also shows that the deviation is smallest in Scenario C and largest in Scenario A. Most voltage violations occurred in Nampula, Queliman, Marromeu, Chimura, Lichinga, Caia, Nicuadal, and Monapo buses, and most violations occurred in 2026 (Table 3.3.10, Table 3.3.15, Table 3.3.20). Therefore, integration of new equipment should be considered to improve voltage characteristics of the system. 4. T/L and Transformer Overrate Reduction 95 90 ScenarioA 85 ScenarioB 80 Total number of ScenarioC overrate branches Figure 3.3.39Total Number of Overrated T/Ls and Transformers for Scenario A, B, and C In Figure 3.3.39, the total number of T/Ls and transformers that are overrated for three scenarios are graphed for all the years under consideration. It has been assumed that the T/L or transformer is overrated if the loading or rating value exceeds one. From this figure, Scenario C has the lowest number of overrated T/Ls and transformers compared to other two scenarios. Most overrated equipment were observed in Mocuba, Alto Molocu, Nampula, Queliman, Caia, Songo, Monapo, Moma, Metoro, Pemba, Lichinga, Namialo, Ncondezi, and Moatize (Table 3.3.9, Table 3.3.14, Table 3.3.19). Therefore, the capacity of T/Ls and transformers should be expanded in order to meet the increasing load levels. 3.3.6.2 Economic Benefits Transmission line loss is an important index to compare the economic benefits of different T/L construction scenarios. When new T/L is constructed and integrated to the power network, the power flows in the network is modified due to change in network impedance and geometry. Therefore, the economic benefit from network loss reduction should be analyzed for the entire system. Another notable point is the operation of must-run generators. In each scenario, as loads increase for each following year, there comes a point where the power flow results diverge, resulting from voltage instability due to long range transmission. This phenomenon is observed after year 2021 for Scenario 0 and after year 2026 for scenario A and B. In order to resolve this issue, must run generations have to be operated near the load area, and 55 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO the generators capable of providing power in the Northern system are NacalaVelha, Palma ENI, and Lurio. From these three options, Lurio hydro plant was exempted due to long and uncertain construction period. So, NacalaVelha and Palma ENI thermal plants were used as must-run generators. Must run generations decrease transmission losses and increase the power supply reliability. The value of these generations differ depending on the system operation status, however, 60~80% loss reduction and voltage instability improvement has been observed from the simulation compared to using the power from slack bus. Hence, when performing economic evaluation, the cost of must run generator operation should be considered depending on whether it is providing real or reactive power to the system. 1. Loss Reduction 25,00% ScenarioA 20,00% ScenarioB 15,00% ScenarioC Scenario0 10,00% 18 21 24 27 30 33 36 Figure 3.3.40Loss percentage for 100% load for Scenario A, B, C and 0 25,00% 20,00% ScenarioA ScenarioB 15,00% ScenarioC 10,00% 18 21 24 27 30 33 36 Figure 3.3.41Loss percentage for 110% load for Scenario A, B, C, and 0 The system losses for different scenarios for 100% load case and 110% load case is shown in Figure 3.3.40 and 3.3.41, respectively. Two different load cases are analyzed for loads growing as forecasted (100%), and loads growing more than the forecasted levels (110%). Scenario 0 is used to compare the losses of Scenario A, B, and C. From the figures above, Scenario C has the lowest loss ratio in both 100% and 110% load cases, followed by Scenario B and Scenario A. Loss ratio is calculated using the equation below. 𝑃𝑙𝑜𝑠𝑠 𝑃𝐺𝑒𝑛 − 𝐻𝑉𝐷𝐶𝑜𝑢𝑡𝑝𝑢𝑡 Ploss, Pgen, and HVDCoutputdenotes total power loss, total generation, and total power send to South Africa 56 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO using the HVDC line, respectively. 2. Must-Run Generation The required generation amount of must-run generators for stable system operation for difference scenarios are shown in the figure below. 600 500 400 300 SC0_MRGen 200 SC0_loss 100 2036 2034 2032 2030 2028 2026 2024 2022 2020 2018 2016 0 Figure 3.3.42 Required must-run generation, Scenario 0 600 500 400 300 SCA_MRGen 200 SCA_loss 100 2036 2034 2032 2030 2028 2026 2024 2022 2020 2018 2016 0 Figure 3.3.43 Required must-run generation, Scenario A 57 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 600 500 400 300 SCB_MSGen 200 SCB_loss 100 2036 2034 2032 2030 2028 2026 2024 2022 2020 2018 2016 0 Figure 3.3.44 Required must-run generation, Scenario B 600 500 400 300 SCC_MRGen 200 SCC_loss 100 2036 2034 2032 2030 2028 2026 2024 2022 2020 2018 2016 0 Figure 3.3.45 Required must-run generation, Scenario C As shown in the figures above, Scenario 0 requires must-run generators after year 2021 to meet the loads connected to Metoro substation. If new T/L is constructed (Scenario A,B, and C), must-run generations are required after year 2026. 3. Power Loss Calculation The power losses and must-run generations are shown in the table below. Loss factor of 0.58 has been applied. Table 3.3.21 Northern system losses and must-run generations for Scenario A, B, C, 0 Scenario 0 Scenario A Scenario B Scenario C System Loss [GWh] 14604 14851 13502 11803 Must-runGeneration[GWh] 12600 7306 7544 7255 Total[GWh] 27,204 22,156 21,047 19,058 각시나리오별로 2018년도부터 2036년간Namialo-Metoro송전선로자체에발생하는선로손실의합은다음 표와같다. 58 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Table 3.3.22 Namialo-MetoroT/L Loss rate for Scenario A, B, C, 0 Loss on each T/L [GWh] Scenario 0 Scenario A Scenario B 110kV T/L 2,492 257 117 220/400kV T/L 0 88 63 Total 2,492 345 180 Scenario C 42 58 100 In Figure 3.3.46, the loss rate of Namialo-Metoro T/L for different scenarios are displayed. 0,6 0,55 0,52 0,470,49 0,43 0,46 0,41 0,40 0,40 0,390,41 0,33 0,280,30 0,27 0,4 0,2 0,19 0,15 0,11 Scenario-A 0,190,18 0.006(SCC) 0.042(SCA) 0.016(SCB) Scenario-B 0,08 Scenario_C 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 0 Senario-0 Figure 3.3.46 Namialo-MetoroT/L Loss Rate (Scenario A, B, C, 0) The T/L in Scenario 0 shows high loss rate after 2018, reaching 27% after 2019. Hence, loss rate is too high to supply power to loads efficiently. On the other hand, Scenario A, B, and C shows the loss rate of 4%, 1.6%, and 0.6%, respectively. 3.3.7 Sensitivity Analysis (If Lurio hydro plant does not follow its planned operation schedule) Earlier sections were analyzed assuming that all the generations, T/Ls, and loads are follow the integration plan or forecast. However, in reality, equipment installation plans may be delayed or modified due to various issues or problems. Therefore, in this section, it has been assumed that the Lurio hydro plant does not follow its integration and operation schedule, and its effect has been analyzed. Year Scenario 0 Lurio hydro plant not integrated & operated as planned 1. Scenario A Scenario B Scenario C 2016 SC0-2016 100% SCA2016 100% SCB2016 100% SCC2016 100% 2018 SC0-2018 100% SCA2018 100% SCB2018 100% SCC2018 100% 2021 SC0-2021 100% SCA2021 100% SCB2021 100% SCC2021 100% Loss rate 59 2026 SC0-2026 100% SCA2026 100% SCB2026 100% SCC2026 100% 2031 SC0-2031 100% SCA2031 100% SCB2031 100% SCC2031 100% 2036 SC0-2036 100% SCA2036 100% SCB2036 100% SCC2036 100% BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 30,00% 25,00% 20,00% Scenario-0 15,00% Scenario-A 10,00% Scenario-B Scenario-C 5,00% 0,00% 18 21 24 27 30 33 36 Figure 3.3.47 Loss rate for Scenario A, B, C, 0 in Lurio off and 100% Load case As previously shown in Figure 3.3.40, if Lurio hydro plant is integrated and operated as scheduled, all the scenarios, except Scenario 0, do not exceed the loss rate of 20%. However, in Figure 3.3.47, all scenarios exceed the loss rate of 20% after 2019. Also, higher loss rate has been observed for 110% load levels, and must –run generations had to be operated after 2022. 2. T/L loading 200,0% SceanrioA 110kV 150,0% SceanrioA 220kV SceanrioB 110kV 100,0% SceanrioB 220kV SceanrioC 110kV 50,0% SceanrioC 400kV Sceanrio0 110kV 0,0% 18 20 22 24 26 28 30 32 34 36 Figure 3.3.48 Namialo-Metoro T/L Loading for Lurio off, 100% Load level (Scenario A, B, C, 0) All scenarios, except Scenario 0, are operated between 30%~50% of T/L thermal limit. 3. Bus Voltage Deviations 60 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 80 0,15 60 0,145 ScenarioA 40 ScenarioB 20 ScenarioC 0 Total out-limit Sceanrio A 0,14 Sceanrio 0,135 B Sceanrio 0,13 C 0,125 V bus number Deviation Figure 3.3.49 Bus Voltage Violations for Lurio off, 100% Load Levels (Scenario A, B, C) The buses with voltage violations become much greater compared to the case where Lurio plant is operated as planned (Figure 3.3.38), reducing the operational stability of the system. 61 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.4 Transfer Capacity In power systems, there are three different categories that impose limits on transfer capability, which are thermal, voltage stability, and angle stability. The transfer capability is determined by the minimum of the three values. The Northern transmission system connects the main power source, CHB, to Nacala and Pemba, which is about 1300km in length, and the voltage throughout this long transmission system is maintained by static variable compensator (SVC) or capacitor bank. Therefore, it is very likely that the overall transfer capability will be determined by either voltage or angle stability transfer limit. In this section, transfer capability of the Namialo-Metoro T/L is determined by analyzing the thermal rating, voltage stability, and angle stability of different operation scenarios. Table 3.4.5. Thermal Transfer Capability of Namialo-Metoro T/L T/L type Operating Thermal Distance[km] [kV] Voltage [kV] Capacity[MVA] 110 110 215 77 220 220 215 239 220 215 715 400 400 215 1300 R[pu] X[pu] C[pu] 0.2861 0.04002 0.01553 0.003883 0.7090 0.2268 0.1560 0.03899 0.07530 0.3422 0.4057 1.3411 As shown in Table 3.4.1, if the T/L between Namialo and Metoro is upgraded to 400kV and operated in 400kV, there will be no problem serving the forecasted demand of 884.8MVA in 2036, calculated in previous section, if only the thermal capacity is considered. However, as previously mentioned, since a voltage instability problem is expected due to the long distance of T/L, the transfer capability considering voltage stability is calculated in the following sections. Furthermore, in order to provide adequate reliability and security for the system, N-1 reliability criterion was considered, which are listed below. Table 3.4.6. Considered N-1 Contingencies C1 C2 C3 C4 N-1 Contingencies Namialo 220/110kV Transformer Trip 110kV Namialo-Metoro T/L Trip 220kV (could be 400kV depending on the Scenario) Namialo-Metoro T/L Trip Namialo 400/220kV Transformer Trip 3.4.1Without New T/L Construction (Base Scenario) 3.4.1.1 2016 year case 62 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.9. PSS/E Modeling of 110kV Namialo-Metoro T/L In order to perform the analysis, the transmission system is modeled as shown in Figure 3.4.1. The blue, green, and red lines indicate 400, 220, and 110kV T/L, respectively. Since the 220kV T/L is not in service in 2016, the transmission capability of 110kV Namialo-Metoro T/L is analyzed. Since the 220kV T/L is not in service, the total thermal capacity of the T/L is 77MVA. Figure 3.4.2. Transfer Capacity Analysis (Scenario A: 2016, N-0) 63 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.3. Transfer Capacity Analysis (Scenario A: 2016, N-1 (C4)) Table 3.4.7. Transfer Capacity Analysis Results (Scenario A, 2016) Power Voltage Bus Voltage [p.u.] Flow[MVA] Cases Contingency [kV] Namialo Metoro from to N-0 N-1 C1 110 1.0337 1.0425 110 1.0551 1.0425 37.0j14.5 36.6j11.8 33.1+j16.2 33.1+j12.5 Loss [MVA] Max Transfer Cap[MW] Max Transfer Cap[MVA] 3.9+j1.7 63.66 88 3.5+j0.7 39.04 43 The additional power that the current system can supplied to the load, and the power flow on the T/Ls considering N-0 and N-1 contingencies are shown in Figure 3.4.2 and 3.4.3. In the base case, the maximum real power transmission capability of 110kV T/L to the loads in Metoro area is 63.66MW, with the line flow of 88MVA. Therefore, the transmission capability of the base case is determined by the voltage stability transfer capability of 63.66MW (88MVA). Furthermore, the N-1 contingency considered in 2016 is the outage of 220/110kV transformer at Namialo. When the transformer was tripped, the maximum real power transmission capability of the system was 39.04MW with line flow of 43MVA. Therefore, the transfer capacity of the system considering N-1 contingency is determined by the voltage stability transfer capacity of 39.04MW (43MVA). 3.4.1.2 2018 year case 64 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.4. PSS/E Modeling of 220kV, 110kV Namialo-Metoro T/L As shown in Figure 3.4.4, it is assumed that the 220kV Namialo-Metoro T/L will be in service by 2018, and is in parallel operation with 110kV T/L. The thermal capacity of each line is 77MVA and 239MVA, with a total of 316MVA. Figure 3.4.5. Transfer Capacity Analysis (Scenario A: 2018, N-0) 65 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.6. Transfer Capacity Analysis (Scenario A: 2018, N-1(C1)) Figure 3.4.7. Transfer Capacity Analysis (Scenario A: 2018, N-1(C4)) 66 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO The voltage stability transfer capacity of the system for N-0 and N-1 cases are shown in Figure 3.4.5, 3.4.6, and 3.4.7. Figure 3.4.5 is displaying the base case, whereas Figure 3.4.6 and 3.4.7 are showing the voltage stability transfer capacity of the system considering C1 and C4 contingencies, respectively. In 2018, the maximum voltage stability transfer capacity of the system in the base case is 116.83MW with line flow of 134MVA, which is much less than the total thermal capacity of 220kV and 110kV T/Ls (316MVA). Therefore, the transfer capacity of the system in the base case is determined by the voltage stability transfer capacity of 116.83MW. Furthermore, when contingencies are considered, the maximum transfer capacity of the system is much reduced, which is summarized in Table 3.4.4. Table 3.4.8. Transfer Capacity Analysis Results (Scenario A, 2018) Power Flow Bus Voltage [p.u.] Voltage [MVA] Cases Contingency [kV] Namialo Metoro From To N-0 C1 C2 N-1 C3 C4 110 1.0527 1.0397 -12.7+j3.7 220 1.0116 1.0397 -10.4-j28.1 Total - - -23.1-j24.4 110 1.0726 1.0398 23.0+j12.8 220 1.0043 1.0398 1.3-j33.2 Total - - -21.7-j20.4 110 1.0528 1.0360 - 220 1.0106 1.0360 -23.6-j24.1 Total - - -23.6-j24.1 110 1.0394 1.0336 -22.2+j7.7 220 1.0090 1.0336 - Total - - -22.2+j7.7 110 1.0489 1.0406 -12.5+j2.9 220 1.0180 1.0407 -10.7-j25.9 Total - - -23.2-j23.0 3.4.1.2 2021 year case 67 Loss [MVA] 13.3j10.5 10.5j7.4 23.8j17.9 25.1j16.1 -1.2j2.0 23.9j18.1 0.6j6.8 0.1j35.5 0.7j42.3 2.1j3.3 0.1j35.2 2.2j38.5 - - 23.9j10.4 23.9j10.4 23.9j11.7 23.9j11.7 13.0j9.8 10.8j10.0 23.8j19.8 0.3j34.5 0.3j34.5 1.7j4.0 1.7j4.0 0.5j6.9 0.1j35.9 0.4j42.8 Max Transfer Cap [MW] Max Transfer Cap[MVA] 116.83 134 108.41 128 0 - 0 - 110.01 125 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.8. Transfer Capacity Analysis (Scenario A: 2021, N-0) The additional real power transfer capability and according power flow in the T/Ls are shown in Figure 3.4.8, in the base case. The 2021 system is able to supply additional load of 12.13MW, and the total line flow at this point is 58.06MW (97.5MVA). Therefore, transfer capacity of the T/L is determined by voltage stability transfer capability of 58.06MW, instead of the thermal rating of the T/Ls (316MVA). The maximumpower transfer capability of the system considering the base and N-1 contingency is shown in Table 3.4.3.In 2021, the system is unable to provide power to the in the case of C1, C3, and C4 contingencies. Table 3.4.9. Transfer Capacity Analysis Results (Scenario A, 2021) Power Flow Bus Voltage [p.u.] Voltage [MVA] Cases Contingency [kV] Namialo Metoro From To N-0 Max Transfer Cap [MW] Max Transfer Cap[MVA] 30.7+j15.2 24.5+j12.2 0.1j8.0 0.8j32.0 0.9j40.0 58.06 97.5 110 1.0350 220 1.0001 Total - 110 1.0197 1.0590 - - - 220 0.9924 1.0590 25.2j49.4 24.5+j17.3 0.7j32.1 C1 N-1 -6.1j5.0 31.51.0590 j47.2 25.4j52.2 Diverge 1.0590 Loss [MVA] C2 68 6.2-j3.0 0 28.5 - BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Total C3 C4 - - 25.2j49.4 Diverge Diverge 24.5+j17.3 0.7j32.1 0 0 3.4.1.3 2026 year case The transfer capability of parallel operation of 110 and 220kV Namialo-Metoro T/L is analyzed. Same system diagram is used, with forecasted load level at 2026. Figure 3.4.9. Transfer Capacity Analysis (Scenario A: 2026, N-0) In the base case, maximum voltage stability transfer capability of the system is 46.71MW, with the line flow of 91MVA, as shown in Figure 3.4.9. Therefore, the transfer capacity of the base case in 2026 is determined by the voltage stability transfer capacity of 46.71MW, instead of the thermal capacity (316MVA). The voltage stability transfer capacity of the system considering various contingencies are summarized in Table 3.4.6. It is shown that the system collapses in C1 and C3 contingencies. However, the system is able to withstand C2 and C4 contingencies. Table 3.4.10. Transfer Capacity Analysis Results (Scenario A, 2026) Power Flow Max Max Bus Voltage [p.u.] Voltage [MVA] Loss Transfer Transfer Cases Name [kV] [MVA] Cap Cap Namialo Metoro From To [MW] [MVA] N-0 110 1.0203 1.0622 -4.95.0+j0.0 0.146.71 91 69 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 220 0.9879 Total - C1 110 1.0103 220 0.9854 Total - C2 N-1 C3 110 1.0375 220 0.9881 Total - C4 j7.9 41.11.0621 j53.8 36.261.7i Diverge 1.0622 36.01.0621 j54.4 36.0j54.4 Diverge -4.01.0622 j6.0 40.21.0621 j53.7 36.2j59.7 39.9+j25.0 34.9+j25.0 j7.9 1.2j28.8 1.3j36.7 0 34.9+j24.8 34.9+j24.8 1.1j29.6 1.1j29.6 43.9 - 0 4.0-j2.1 38.9+j24.6 34.9+j22.5 0.0j8.1 1.3j29.1 1.3j37.2 34.9 - 3.4.1.4 2031 year case In this section the transfer capacity of 110kV and 220kV T/L is analyzed for the load levels of 2031. Figure 3.4.10. Transfer Capacity Analysis (Scenario A: 2031, N-0) 70 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO The additional real power transfer capacity and the line flow of Namialo-Metoro T/L considering the base case is shown in Figure 3.4.10. In the base case, the maximumreal power that could be transferred to the load is 57.66MW, with the line flow of 89MVA. Therefore, the transmission capacity of the system in the base case is determined by voltage stability transfer capacity of 57.66MW, instead of the thermal rating of both lines (316MVA). Furthermore, when contingencies are considered, the system failed to supply the load in all N-1 contingences except the outage of 110kV T/L. The results of the simulation is summarized in Table 3.4.7. Table 3.4.11. Transfer Capacity Analysis Results (Scenario A, 2031) Case s Contingenc y N-0 Voltag e [kV] Bus Voltage [p.u.] Namial Metor o o 110 1.0328 220 0.9952 Total - C1 110 1.0238 220 0.9911 C2 N-1 Total - 110 220 Total - C3 C4 Power Flow [MVA] Fro To m -1.41.0406 1.4-j3.5 j4.6 51.91.0406 50.5+j14. j42.5 7 50.549.1+j11. j47.3 2 Diverge 1.0386 50.41.0386 49.1+j15. j43.1 3 50.449.1+j15. j43.1 3 Diverge - Loss [MVA ] Max Transfe r Cap [MW] Max Transfe r Cap [MVA] 57.66 89 0.0j8.1 1.4j27.8 1.4j35.9 0 1.3j27.8 53.1 1.3j27.8 0 - 0 3.4.1.5 2036 year case The power transfer capability of 110, 220kV Namialo-Metoro T/L is analyzed for 2036 load levels in this section. In 2036, the system is unable to operate if must-run generators are not added near the Metoro area due to low voltage levels resulting from fast load growth. Hence, it has been assumed that Palma ENI, Lurio, and Nacala2 generation plantsare in operation with the output values of 0.0+j28.5MVA, 55+j11.2MVA, and 200j2.8MVA, respectively. 71 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.11. Transfer Capacity Analysis (Scenario A: 2036, N-0) The additional real power transfer capability of the system along with the line flows are shown in Figure 3.4.11. Considering the load levels of 2036, the maximum real power transfer capability of the system is 68.93MW, with line flow of 92MVA. Therefore, transfer capacity of Namialo-Metoro T/L is determined by the voltage stability transfer capacity of 68.93MW, instead of the thermal capacity (316MVA). Furthermore, if N-1 contingency is considered in the system of 2031, all the considered cases failed to converge, and the results are summarized in Table 3.4.8. Table 3.4.12. Transfer Capacity Analysis Results (Scenario A, 2036) Bus Voltage Power Flow [p.u.] [MVA] Case Contingenc Voltag s y e [kV] Namial Metor Fro To o o m 0.5110 1.0198 1.0399 -0.5-j0.9 j7.0 68.6220 0.9847 1.0399 66.3+j24. N-1 j46.6 6 69.1Total 66.8+j23. j53.6 7 N-1 C1 Diverge 72 Loss [MVA ] Transfe r Cap [MW] Transfe r Cap [MVA] 68.93 92 0.0j7.9 2.3j22.0 2.3j29.9 0 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO C2 C3 C4 Diverge Diverge Diverge 0 0 0 3.4.1.6 Transfer Capacity of 2032~2035 After 2032, must-run generations are required near the load area for a stable operation, and its capacity ranges from j21.9MVA to j25.0MVA in the case of Palma ENI generation plant. Also, since the base case does not converge, N-1 contingencies are not considered in this section. Table 3.4.13. Transfer Capacity Analysis Results (2032~2035) Bus Voltage Power Flow [MVA] [p.u.] Voltag Year Name e [kV] Namial Metor From To o o Namialo -Metoro 203 2 203 4 110 1.0142 1.0378 -1.5-j6.6 1.5-j1.2 0.0j7.8 220 0.9828 1.0377 55.8-j46.0 54.1+j20. 4 1.7j25.6 PalmaENI Lurio Nacala2 11 - - 0.0+j24.7 - - 33 220 - - 55+j11.6 135.0-j3.7 - Total - - - 54.3-j52.6 52.6+j19. 2 110 1.0331 1.0429 -0.6-j5.2 0.6-j2.9 0.0j8.1 220 1.0038 1.0429 58.3-j40.6 56.7+j13. 7 1.6j26.9 - - Namialo -Metoro 203 3 Loss [MVA ] PalmaENI 11 - - Lurio 33 - - Nacala2 220 - - Total - - - 110 1.0221 220 0.9980 Namialo -Metoro 0.0+j21.9 55.0+j10. 6 190.0j50.5 Ref. 0 Base case Must -run Gen. Req. 0 Base case Must -run Gen. Req. 0 Base case Must -run Gen. 1.7j33.4 - - - - 57.7-j45.8 56.1+j10. 8 1.6j35.0 1.0417 -0.4-j6.6 0.5-j1.4 0.1j8.0 1.0416 62.0-j42.4 60.2+j17. 0 1.8j25.4 73 Additiona l Transfer Capabilit y [MW] BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO PalmaENI Lurio Nacala2 11 - - 0+j24.9 - - 33 220 - - 55+j10.9 190-j33.2 - Total - - - 61.6-j49.0 59.7+j15. 6 110 1.0443 1.0439 0.7-j4.3 -0.7-j3.9 0.0j8.2 220 1.0012 1.0438 64.5-j42.2 62.6+j17. 2 1.9j25.0 - - - - - - 63.3+j13. 3 1.9j33.2 Namialo -Metoro 203 5 PalmaENI 11 - - Lurio 33 - - Nacala2 220 - - Total - - - 0.0+j25.0 55.0+j10. 4 190.0j48.6 65.2-j46.5 Req. 1.9j33.4 0 Base case Must -run Gen. Req 3.4.2.7 Results on 220kV T/L construction In the system of 2016, its transfer capacity is determined by the thermal capacity of the Namialo-Metoro T/L. However, after the 220kV T/L construction in 2018, the transfer capacity in all the following years is determined by the voltage stability transfer capacity, ranging from 46.71MW to 116.83MW. The system is able to serve load until 2031, however after 2031, must run generations have to be operated in order to operate the system reliably and securely. 3.4.2Scenario B: 400kV T/L Construction, 220kV Operation In this section, the parallel operation of 110kV T/L and 400kV T/L operating in 220kV is analyzed. The thermal capacities of 110kV and 400(220)kV T/Ls are 77MVA and 715MVA, respectively. Therefore the total thermal capacity of the Namialo-Metoro transmission system is 792MVA. 3.4.2.1 2018 year case The transfer capability of 110kV and 400(220)kV T/L between Namialo and Metoro is analyzed under 2018 load levels, and the modeled system is shown in Figure 3.4.11. 74 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.12. PSS/E Modeling of 110, 220kV Namialo-Metoro T/L Operation (2018) Figure 3.4.13. Transfer Capacity Analysis (Scenario B: 2018, N-0) 75 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.14. Transfer Capacity Analysis (Scenario B: 2018, N-1 (C1)) Figure 3.4.15. Transfer Capacity Analysis (Scenario B: 2018, N-1 (C3)) 76 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.16. Transfer Capacity Analysis (Scenario B: 2018, N-1 (C4)) The additional real power transfer capability and line flows in the base case and N-1 contingency case of 2018 are shown in Figure 3.4.13, 3.4.14, 3.4.15, and 3.4.16. In the base case, the maximum real power transfer capability of the system is 89.24MW with the line flow of 106MVA. Therefore, the transfer capacity of the transmission system is determined by the voltage stability transfer capacity (89.24MW), instead of the thermal capacity (792MVA). Furthermore, the system was able to be operated even when N-1 contingencies were considered, and the results are summarized in Table 3.4.10. Table 3.4.14. Transfer Capacity Analysis Results (Scenario B, 2018) Bus Voltage Power Flow [MVA] [p.u.] Case Contingenc Voltag s y e [kV] Namial Metor From To o o 110 1.0572 1.0489 10.9+j2. 11.9-j9.3 0 400 N-0 -2.3(220 1.0156 1.0489 2.3-j0.2 j42.4 oper.) -13.2Total 14.2-j9.5 j40.4 24.3N-1 C1 110 1.0443 1.0489 22.6+j6. j10.9 7 77 Loss [MVA ] Max Transfe r Cap [MW] Max Transfe r Cap [MVA] 89.24 106 86.15 119 1.0j7.3 -j42.6 1.0j49.9 1.7j4.2 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO C2 C3 C4 400 (220 oper.) 1.0042 1.0489 Total - - 110 400 (220 oper.) 1.0368 1.0489 1.0088 1.0489 Total - - 110 1.0345 1.0489 400 (220 oper) 1.0009 1.0489 Total - - 110 1.0452 1.0489 400 (220 oper) 1.0147 1.0489 Total - - 10.8j50.2 -11.8j43.5 - 10.7+j8. 9 0.1j41.3 - 1.8j45.5 - -13.5j45.2 13.6+j3. 4 0.1j41.8 -13.5j45.2 -13.1j0.1 13.6+j3. 4 0.1j41.8 0.5j6.9 - 13.6-j2.0 13.6-j6.8 - - 13.6-j6.8 0.5j6.9 11.2-j7.6 0.4j7.4 -2.4j42.9 2.4+j0.4 0.0j42.5 -13.2j42.7 13.6-j8.0 0.4j49.9 -13.1j0.1 10.8+j0. 2 7.4 - 50.15 - 86.21 101 3.4.2.2 2021 year case The transfer capability of 110kV and 400(220)kV Namialo-Metoro T/L is analyzed for 2021. The system model is the same, and only the loads have been changed to the levels of 2021. 78 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.17. Transfer Capacity Analysis (Scenario B: 2021, N-0) Figure 3.4.18. Transfer Capacity Analysis (Scenario B: 2021, N-1 (C4)) The additional real power transfer capability of the system and the line flows for Namialo-Metoro 79 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO transmission system in the base and N-1 contingency case in 2021 is shown in Figure 3.4.17 and 3.4.18. The maximum real power transfer capacity of the system is 63.63MW with the line flow of 106MVA. Therefore, the transfer capacity of the Namialo-Metoro T/L in 2021 is determined by the voltage stability transfer capacity of 63.63MW, instead of the thermal capacity (792MVA). Accordingly, when N-1 contingency is applied to the system, the system was unable to supply power to loads in the case of C1 and C3 contingencies. However, the system was able to withstand other contingencies. The results of the simulation for Scenario B in 2021 are summarized in Table 3.4.11. Table 3.4.15. Transfer Capacity Analysis Results (Scenario B, 2021) Case s Contingenc y N-0 Voltag e [kV] Bus Voltage [p.u.] Namial Metor o o 110 1.0413 400 (220 oper.) 1.0065 Total - C1 C2 N-1 110 400 (220 oper.) 1.0349 Total - 1.0042 C3 C4 110 1.0258 400 (220 oper) 0.9953 Total - Power Flow [MVA] Fro To m -8.61.0590 8.8-j4.9 j3.0 33.71.0590 33.3+j17. j56.8 2 25.124.5+j12. j59.8 3 Diverge 1.0590 24.81.0590 24.5+j17. j57.6 5 24.824.5+j17. j57.6 5 Diverge -8.71.0590 8.9-j2.6 j5.0 33.91.0590 33.4+j24. j63.0 9 25.224.5+j22. j68.0 3 Loss [MVA ] Max Transfe r Cap [MW] Max Transfe r Cap [MVA] 63.63 106 0 - 40.5 - 0 - 50.19 109 0.2j7.9 0.4j39.6 0.6j47.5 0.3j40.1 0.3j40.1 0.2j7.6 0.5j38.1 0.7j45.7 3.4.2.3 2026 year case In this section, the transfer capability of 110kV and 400(220)kV Namialo-Metoro T/L is analyzed for the load levels of 2026. 80 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.19. Transfer Capacity Analysis (Scenario B: 2026, N-0) Figure 3.4.20. Transfer Capacity Analysis (Scenario B: 2026, N-1 (C1)) The additional real power transfer capability and its line flow of the base and N-1 case in 2026 are shown in 81 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.19 and 3.4.20. In 2026, the system is able to transfer maximum real power amount of 50.78MW to the load with the line flow of 107MVA in the base case. Therefore, the transfer capacity of transmission system in 2026 is determined by the voltage stability transfer capacity (50.78MW), instead of the thermal capacity (792MVA). Furthermore, when the N-1 reliability standard was applied, the system collapsed when 220kV T/L and Namialo 400/220kV transformer was tripped. Also, tripping 110kV T/L did not have much effect on the system. The results are summarized in Table 3.4.10. Table 3.4.16. Transfer Capacity Analysis Results (Scenario B, 2026) Case s Contingenc y Voltag e [kV] 110 N-0 C1 Power Flow [MVA] From To -8.3-j6.0 8.5-j1.7 400 (220 oper.) 0.9922 1.062 1 44.1j67.1 Total - - 35.8j73.1 110 1.0092 1.062 2 24.8+j1. 0 400 (220 oper.) 0.9843 1.062 1 62.6j71.5 Total - - 37.8j70.5 110 1.0151 1.062 2 - 400 (220 oper.) 0.9901 1.062 0 35.5j67.9 Total - - 35.5j67.9 N-1 C2 Bus Voltage [p.u.] Namial Metor o o 1.062 1.0236 2 C3 C4 Diverge Diverge 43.4+j30. 8 34.9+j29. 1 26.8-j4.7 61.5+j39. 6 34.7+j34. 9 34.9+j30. 8 34.9+j30. 8 Loss [MVA ] Max Transfe r Cap [MW] Max Transfe r Cap [MVA] 50.78 107 35.14 123 0.2j7.7 0.7j36.3 0.9j44.0 2.0j3.7 1.1j31.9 3.1j35.6 - 45.9 0.00 0.00 3.4.2.4 2031 year case In this section, the transfer capability of 110kV and 400(220kV) Namialo-Metoro T/Ls are analyzed for the year of 2031. 82 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.21. Transfer Capacity Analysis (Scenario B: 2031, N-0) The additional real power transfer capability and the line flow of the transmission system in 2031 for the base case are shown in Figure 3.4.21. The system is able to supply up to 61.23MW of real power to the load in the base case with the line flow of 97MVA. Therefore, the transfer capacity of Namialo-Metoro T/L is determined by the voltage stability transfer capacity of 61.23MW instead of the thermal capacity (792MVA). Furthermore, when N-1 reliability standard was applied, the system was unable to supply power to the loads, except in C2 contingency. The results are summarized in Table 3.4.13. Table 3.4.17. Transfer Capacity Analysis Results (Scenario B, 2031) Case s Contingenc y N-0 Voltag e [kV] Bus Voltage [p.u.] Namial Metor o o 110 1.0263 1.0398 400 (220 oper.) 0.9932 1.0398 Total - 83 Power Flow [MVA] Fro To m -5.96.0-j4.4 j3.4 55.755.1+j17. j52.6 2 49.8j56.0 49.1+j12. Loss [MVA ] Max Transfe r Cap [MW] Max Transfe r Cap [MVA] 61.23 97 0.1j7.8 0.6j35.4 0.7j43.2 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 8 C1 N-1 C2 C3 C4 110 400 (220 oper.) 1.0175 Diverge 1.0376 - 0.9892 1.0376 49.7j53.3 Total - - 49.7j53.3 0 49.1+j17. 4 49.1+j17. 4 Diverge Diverge 0.6j35.9 53.1 0.6j35.9 0 0 3.4.2.5 2036 year case The transfer capability of 110kV and 400(220)kV Namialo-Metoro T/Ls are analyzed for year 2036. In 2036, due to a lengthy transmission system and high load levels, the system is unable to operate without must-run generation plants due to low voltage levels in the loads. Therefore, in order to make the system operable for simulation, Palma ENI, Lurio, and Nacala2 generation plants were assumed to be in operation with generation amounts of 0.0+j25.5MVA, 55.0+j10.4MVA, and 200.0-j23.9MVA, respectively. Figure 3.4.22. Transfer Capacity Analysis (Scenario B: 2036, N-0) 84 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO The additional real power transfer capability and the line flow of Namialo-Metoro T/L in 2036 is shown in Figure 3.4.22. The maximum real power transfer capacity of the system in the base case is 72.83MW with the line flow of 105MVA. Therefore, the transmission capacity of the system is determined by the voltage stability transfer capacity (72.83MW), instead of its thermal capacity (792MVA). The system failed to supply power to the loads in C1, C3, and C4 contingency cases. However, tripping 110kV T/L did not have much effect on the transfer capacity of the system. The summary of the simulation results is shown in Table 3.4.14. Table 3.4.18. Transfer Capacity Analysis Results (Scenario B, 2036) Bus Voltage Power Flow [p.u.] [MVA] Case Contingenc Voltag s y e [kV] Namial Metor Fro To o o m -4.6110 1.0326 1.0433 4.7-j4.3 j3.6 400 72.4(220 0.9957 1.0433 71.4+j21. N-0 j53.4 oper.) 2 67.8Total 66.7+j16. j57.0 9 C1 Diverge 110 1.0212 1.0407 400 67.7(220 0.9903 1.0407 66.8+j22. j54.8 C2 oper.) 2 N-1 67.7Total 66.8+j22. j54.8 2 C3 Diverge C4 Diverge Loss [MVA ] Max Transfe r Cap [MW] Max Transfe r Cap [MVA] 72.83 105 0.1j7.9 1.0j32.2 1.1j40.1 0 0.9j32.6 69.8 0.9j32.6 0 0 3.4.2.6 Transfer capacity for the years 2032~2035 In this section, the operation limit year of 110kV and 400(220)kV transmission system is identified. After 2032, the system is required to operate must-run generation plants in order to be operable, and additional power ranging from j23.2MVA to j23.8MVA is needed in the case Palma ENI generation plant. Table 3.4.19. Transfer Capacity Analysis Results (Scenario B, 2032~2035) Bus Voltage [kV] Power Flow [MVA] Loss Voltag Year Name [MVA Namial Metor e [kV] From To ] o o 85 Additiona l Transfer Capabilit y [MW] Ref. BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 110 1.0216 1.0394 -5.8-j4.0 5.9-j3.7 0.1j7.7 220 0.9902 1.0394 59.3-j54.0 58.5+j19. 6 0.8j34.4 PalmaENI 11 - - 0.0+j23.2 - - Lurio 33 - - - - Nacala2 220 - - 55.0+j11. 4 135-j17.4 - Total - - - 53.5-j58.0 52.6+j15. 9 110 1.0342 1.0442 -5.2-j3.3 5.3-j4.6 0.1j7.9 220 1.0059 1.0442 62.1-j48.3 61.4+j12. 8 0.7j35.5 Namialo -Metoro 203 2 Namialo -Metoro 203 3 203 4 11 - - 0.0+j20.7 - - 33 - - - - Nacala2 220 - - 55+j10.2 190.0j54.2 - - Total - - - 56.9-j51.6 -56.1+j8.2 110 1.0240 1.0429 -5.3-j4.4 5.4-j3.4 220 1.0005 1.0429 66.0-j50.5 65.1+j16. 3 0.9j34.2 - - - - - - 203 5 11 - - Lurio 33 - - Nacala2 220 - - Total - - - 60.7-j54.9 59.7+j12. 9 1.0j42.0 110 1.0460 1.0453 -4.5-j2.1 4.5-j5.9 0.0j8.0 0.9j33.9 Namialo -Metoro PalmaENI Lurio 55.0+j10. 6 190.0j37.9 220 1.0038 1.0453 68.7-j50.2 67.8+j16. 3 11 - - 0.0+j23.6 - - 33 - - 55.0+j10. - - 86 0 Base case Must -run Gen. Req. 0 Base case Must -run Gen. Req 0.8j43.4 0.1j7.8 PalmaENI 0+j23.8 0 Base case Must -run Gen. Req. 0.9j42.1 PalmaENI Lurio Namialo -Metoro 0 Base case Must -run Gen. Req. BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Nacala2 220 - - 0 190-j53.4 Total - - - 64.2-j52.3 63.3+j10. 4 0.9j41.9 3.4.2.7 Results on 400kV T/L construction and 220kV operation If the new T/L between Namialo and Metoro is constructed as 400kV rating, and operated on 220kV, the transfer capacity of the Namialo-Metoro transmission system is always determined by the voltage stability transfer capacity, and the maximum real power transfer capability ranges from 50.78MW to 89.24MW in the base case. The system is unable to supply the load after 2031. After this year, the limit of 110kV and 400(220)kV transmission system has been reached, and the must-run generation, in the load side, is required to operate the system. 3.4.3Scenario C: 400kV T/L Construction, 400kV Operation In this section, the parallel operation of 110kV and 400kV T/L between Namialo and Metoro is considered. The thermal capacities of 110kV and 400kV linesare 77MVA and 1300MVA, respectively. Therefore, the thermal rating of the transmission system is 1377MVA. 3.4.3.1 2018 year case In this section, the transfer capacity of 110kV and 400kV Namialo-Metoro T/L is analyzed. The system diagram used for the simulation is shown in Figure 3.4.23. 87 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.23. PSS/E Diagram used for simulating 110, 400kV Namialo-Metoro T/L Analysis From Figure 3.4.23, it is shown that the loads in Metoro area is supplied by 400kV (blue) and 110kV (red) T/Ls. 88 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.24. Transfer Capacity Analysis (Scenario C: 2018, N-0) Figure 3.4.25. Transfer Capacity Analysis (Scenario C: 2018, N-1 (C1)) 89 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.26. Transfer Capacity Analysis (Scenario C: 2018, N-1 (C4)) The additional real power transfer capacity and the line flow of Namialo-Metoro transmission system for the base and contingency cases are shown in Figure 3.4.24, 3.4.25, and 3.4.26. The maximum real power transfer capacity in the base case is 104.44MW with the line flow rating of 191MVA. Therefore, the transfer capacity of this system is determined by the voltage stability transfer capacity (104.44MW), instead of the thermal rating (1377MVA) of the transmission system. Moreover, the system was able to be operated stably in all contingency cases when N-1 reliability criterion was applied. The summary of the results is provided in Table 3.4.16. Table 3.4.20. Transfer Capacity Analysis Results (Scenario C, 2018) Bus Voltage [p.u.] Cases Contingenc y N-0 N-1 Power Flow [MVA] Voltage [kV] Namialo Metoro From 110 1.0532 1.0489 -16.0+j4.1 400 1.0607 1.0795 3.4-j127.1 Total - - -12.6j123.0 110 1.0516 1.0489 -27.3+j10.9 400 1.0578 1.0779 16.5-j131.3 C1 90 To Loss [MVA] 16.8j10.4 -3.3j25.6 13.5j36.1 29.9j13.0 16.4- 0.8j6.3 0.1j152.7 0.9j159.0 2.6j2.1 0.1j151.7 Max Transfer Cap [MW] Max Transfer Cap [MVA] 104.44 191 103.5 213 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO j20.4 C2 C3 Total - - -10.8j120.4 13.5j33.4 2.7j153.8 110 1.0537 1.0489 - - - 400 1.0604 1.0796 -13.4j126.1 13.5j26.5 0.1j152.6 Total - - -13.4j126.1 110 1.0345 1.0489 -13.0-j0.2 400 1.0197 1.0706 - Total - - -13.0-j0.2 1.0489 -19.9+j6.4 13.5j26.5 13.5j6.8 13.5j6.8 21.3j11.5 -7.8j33.2 13.5j44.7 0.1j152.6 0.5j7.0 0.5j7.0 1.4j5.1 0.0j154.1 1.4j159.2 110 C4 1.0535 400 1.0661 1.0822 7.8-j120.9 Total - - -12.1j114.5 8.5 - 6.5 - 103.13 199 3.4.3.2 2021 year case In this section, the transfer capacity of 110kV and 400kV Namialo-Metoro T/L is analyzed for the year of 2021. 91 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.27. Transfer Capacity Analysis (Scenario C: 2021, N-0) Figure 3.4.28. Transfer Capacity Analysis (Scenario C: 2021, N-1 (C1)) 92 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.29. Transfer Capacity Analysis (Scenario C: 2021, N-1 (C4)) The additional real power transfer capacity and the line flow of the system considering the load levels of 2021 is shown in Figure 3.4.27, 3.4.28, and 3.4.29. In the base case, the system was able to supply maximum real power of 103.98MW, with the line flow rating of 201MVA. Hence, the transfer capacity of 2021 is determined by the voltage stability transfer capacity (103.98MW), instead of the thermal capacity (1377MVA) of the transmission system. Furthermore, it has been verified that the system was able to be operated stably in all contingencies, except in the case of 400kV T/L outage. The result of the simulation is summarized in Table 3.4.17. Table 3.4.21. Transfer Capacity Analysis Results (Scenario C, 2021) Bus Voltage Power Flow [MVA] [p.u.] Case Contingenc Voltag s y e [kV] Namial Metor From To o o 1.059 18.4110 1.0612 0 17.4+j4.5 j10.6 1.082 43.3-43.0N-0 400 1.0565 3 j148.6 j2.2 25.9-24.6Total j144.1 j12.8 1.059 35.8N-1 C1 110 1.0519 32.3+j12. 0 j12.6 8 93 Loss [MVA] Max Transfe r Cap [MW] Max Transfe r Cap [MVA] 1.0j6.1 0.3j150.8 1.3j156.9 103.98 201 3.5+j0. 2 87.95 234 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO C2 400 1.0517 1.079 6 60.8j154.7 Total - - 28.5j141.9 60.5+j5. 9 -24.7j6.7 110 1.0614 1.059 0 - - - 400 1.0562 1.082 4 24.8j148.1 -24.6j3.2 0.2j151.3 Total - -24.6j3.2 0.2j151.3 C3 C4 24.8j148.1 Diverge 1.059 0 22.7+j6.5 - 110 1.0538 400 1.0546 1.081 2 49.2j151.0 Total - - 26.5j144.5 0.3j148.8 3.8j148.6 45.6 0 24.3j10.9 48.9+j0. 9 -24.6j10.0 1.6j4.4 0.3j150.1 93.6 211 1.9j154.5 3.4.3.3 2026 year case In this section, the transfer capacity of 110kV and 400kV Namialo-Metoro T/L is analyzed for the load levels of 2026. 94 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.30. Transfer Capacity Analysis (Scenario C: 2026, N-0) Figure 3.4.31. Transfer Capacity Analysis (Scenario C: 2026, N-1 (C1)) 95 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.32. Transfer Capacity Analysis (Scenario C: 2026, N-1 (C4)) The additional real power transfer capability and line flow of the system 2026 load levels are shown in Figure 3.4.30, 3.4.31, and 3.4.32. The system is able to supply maximum real power of 75.75MW with the line flow of 221MVA in the base case. Therefore, the transfer capacity of the transmission system is determined by the voltage stability transfer capacity of 75.75MW instead of its thermal capacity of 1377MVA. Continuing, the system operated stably in all considered contingencies, except the outage of 400kV T/L. The results are summarized in Table 3.4.18. Table 3.4.22. Transfer Capacity Analysis Results (Scenario C, 2026) Bus Voltage Power Flow [MVA] [p.u.] Case Contingenc Voltag s y e [kV] Namial Metor From To o o N-0 110 1.0423 1.0622 18.6+j1. 9 400 1.0406 1.0758 55.2j171.4 Total - - 36.6j169.5 96 19.7-j7.8 54.7+j25. 8 35.0+j18. Loss [MVA] Max Trans . Cap [MW ] Max Trans. Cap [MVA ] 75.75 221 1.1-j5.9 0.5j145.6 1.6j151.5 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 0 C1 N-1 C2 110 1.0258 1.0622 34.3+j9. 9 400 1.0369 1.0736 73.7j175.8 Total - - 39.4j165.9 110 1.0405 1.0622 - 400 1.0403 1.0760 35.4j171.1 Total - - 35.4j171.1 C3 C4 Diverge 1.0622 24.3+j3. 9 110 1.0318 400 1.0381 1.0745 61.7j174.3 Total - - 37.4j170.4 38.0-j8.9 73.1+j32. 3 35.1+j23. 4 35.0+j24. 8 35.0+j24. 8 3.7+j1. 0 0.6j143.5 65.35 254 4.3j142.5 0.4j146.3 51 0.4j146.3 0 26.1-j7.8 61.1+j29. 7 35.0+j21. 9 1.8-j3.9 0.6j144.6 68.44 232 2.4j148.5 3.4.3.4 2031 year case In this section, the transfer capability of 110kV and 400kV Namialo-Metoro T/L is analyzed for the load levels of 2031. 97 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.33. Transfer Capacity Analysis (Scenario C: 2031, N-0) Figure 3.4.34. Transfer Capacity Analysis (Scenario C: 2031, N-1 (C1)) 98 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.35. Transfer Capacity Analysis (Scenario C: 2031, N-1 (C4)) The additional real power transfer capability and line flow of the transmission system for 2031 load levels is shown in Figure 3.4.33, 3.4.34, and 3.4.35. The maximum real power that the system can supply to the load is 92.95MW at line flow of 318MVA in the base case. Therefore, the transfer capacity in the base case is determined by the voltage stability transfer capacity of 92.95MW, instead of the thermal capacity (1377MVA). Furthermore, when the N-1 reliability criterion was applied, the system was still able to withstand all considered contingencies, except the outage of 400kV T/L. The summary of simulation results is shown in Table 3.4.19. Table 3.4.23. Transfer Capacity Analysis Results (Scenario C, 2031) Bus Voltage Power Flow [MVA] [p.u.] Case Contingenc Voltag s y e [kV] Namial Metor From To o o 1.051 17.1110 1.0528 5 16.2+j3.8 j10.0 1.074 66.7-66.3N-0 400 1.0487 0 j147.5 j0.1 50.5-49.2Total j143.7 j10.1 1.050 36.4N-1 C1 110 1.0416 32.8+j13. 2 j12.4 1 99 Loss [MVA] Max Transfe r Cap [MW] Max Transfe r Cap [MVA] 0.9j6.2 0.4j147.6 1.3j153.8 92.95 318 3.6+j0. 7 75.61 319 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO C2 400 1.0458 1.071 6 86.2j149.4 Total - - 53.4j136.3 85.7+j3. 7 -49.3j8.7 110 1.0526 1.048 7 - - - 400 1.0478 1.072 4 49.5j144.1 -49.2j4.0 0.3j148.1 Total - -49.2j4.0 0.3j148.1 C3 C4 110 1.0485 400 1.0493 Total - 49.5j144.1 Diverge 1.051 7 20.9+j5.8 1.074 71.93 j147.3 51.0j141.5 - 0.5j145.7 4.1j145.0 72.2 0 22.3j10.7 -71.5j0.2 -49.2j10.9 1.4j4.9 0.4j147.5 1.8j152.4 84.58 317 3.4.3.5 2036 year case In this section, the transfer capacity of 110kV and 400kV Namialo-Metoro transmission system is analyzed for 2036 load levels. 100 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.36. Transfer Capacity Analysis (Scenario C: 2036, N-0) Figure 3.4.37. Transfer Capacity Analysis (Scenario C: 2036, N-1 (C1)) 101 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.4.38. Transfer Capacity Analysis (Scenario C: 2036, N-1 (C4)) The additional real power transfer capability and line flow of the transmission system for the year of 2036 is shown in Figure 3.4.36, 3,4,37, and 3,4,38. The maximum real power transfer capability of the system is 108.9MW with the line flow rating of 234MVA. Therefore, the transfer capacity of the system is determined by the voltage stability transfer capability of 108.9MW, instead of the thermal rating of 1377MVA. In addition, the system was able to be operated in all considered contingency cases except for the case of tripping the 400kV T/L. The results of the simulation are summarized in Table 3.4.20. Table 3.4.24. Transfer Capacity Analysis Results (Scenario C, 2036) Bus Voltage Power Flow [MVA] [p.u.] Case Contingen Voltag s cy e [kV] Namial Metor From To o o 1.053 110 1.0539 17.3-j10.0 0 16.4+j3.8 1.073 84.7N-0 400 1.0463 -84.2+j6.8 3 j152.7 68.3Total -66.9-j3.2 j148.9 1.050 N-1 C1 110 1.0319 35.3+j13. 39.6-j11.3 6 5 102 Loss [MVA] Max Transf er Cap [MW] Max Transf er Cap [MVA] 0.9j6.2 0.5145.9i 1.4j152.1 108.9 234 4.3+j2. 2 85.78 248 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO C2 400 1.0418 1.069 3 107.1j154.5 106.5+j11 .6 0.6j142.9 Total - - 71.8j141.0 -66.9+j0.3 4.9j140.7 110 1.0541 1.050 4 - - - 400 1.0455 1.071 9 67.2j149.6 -66.9+j3.0 0.3j146.6 Total - -66.9+j3.0 0.3j146.6 C3 C4 110 1.0508 400 1.0472 Total - 67.2j149.6 Diverge 1.053 4 20.8+j5.9 1.073 89.78 j152.3 68.9j146.4 - 88.9 0 22.2-j10.8 -89.2+j6.5 -67.0-j4.3 1.4j4.9 0.5j145.8 1.9j150.7 101.63 236 In 2036, the transferred power to Metoro area flows in opposite direction for 400kV and 110kV T/L. Although the system fails in the case of largest contingency (tripping 400kV T/L), this problem may be mitigated through operating a must-run generation near the load side. The required amount of generation in the load side for a stable operation is 28+j12.6MVA and 20+j20.2MVA for Lurio G1 and Palma ENI, respectively. 103 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.4.4.Simulation Results The summarized results for each scenario for the considered years are displayed in Table 3.4.21. Due to complexity of the table, several notations are used, which are: B: Base Case D: Diverge U: Unstable N-1 Cases: 1. C1: Namialo 220/110kV Transformer Trip 2. C2: 110kV Namialo-Metoro T/L Trip 3. C3: 400kV or 220kV Namialo-Metoro T/L Trip (Could be 400kV or 220kV T/L depending on the Scenario) 4. C4: Namialo 400/220kV Transformer Trip 104 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Table 3.4.25. Summary of transfer capability analysis results for 2016~2036 Scenario A: 110kV, 220kV Scenario B: 110kV, 400(220)kV Max Max Max Max Thermal Thermal Transfer Transfer Transfer Transfer Capacity Capacity Capacity Capacity Capacity Capacity [MVA] [MVA] [MW] [MVA] [MW] [MVA] N-0 63.66 88 ‘16 N-1 C1 39.04 43 C2 - - C3 - C4 - - - - - - - - - - - - - - - - - - - 116.83 134 89.24 106 104.44 191 C1 108.41 128 86.15 119 103.5 213 C2 0 - 7.4 - 8.5 - C3 0 - 50.15 - 6.5 - C4 110.01 125 86.21 101 103.13 199 58.06 97.5 63.63 106 103.98 201 C1 0 - 0 - 87.95 234 C2 28.5 - 40.5 - 45.6 - C3 0 - 0 - 0 - C4 0 - 50.19 109 93.6 211 46.71 91 50.78 107 75.75 221 0 - 35.14 123 65.35 254 45.9 - 51 - N-0 ‘18 N-1 N-0 ‘21 N-1 N-0 C1 ‘26 N-1 N-1 N-1 316 792 43.9 - C3 0 - 0 - 0 - C4 34.9 - 0 - 68.44 232 57.66 89 61.23 97 92.95 318 C1 0 - 0 - 75.61 319 C2 53.1 - 53.1 - 72.2 - C3 0 - 0 - 0 - C4 0 0 0 - 84.58 317 68.93 92 72.83 106 108.9 234 C1 0 - 0 - 85.78 248 C2 0 - 69.8 - 88.9 - C3 C4 0 0 - 0 0 - 0 101.63 236 N-0 ‘36 77 C2 N-0 ‘31 Scenario C: 110kV, 400kV Max Max Therma Transfer Transfer Capacit Capacity Capacity [MVA [MW] [MVA] - Inception Report 1 / 31 1377 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.5 Short Circuit Analysis 3.5.1 Current System Status (2016) For the substations that will be affected by the installation of new transmission line (T/L) between Namialo and Metoro, a three phase to ground short circuit analysis was conducted, and the results are shown in Table 3.5.1. Table 3.5.26 Short Circuit MVA and Fault current of substation (2016 year) Source Impedance[pu] Bus Voltage[kV] SCMVA[pu] Fault current[A] Metoro 110 1.38 724.7519 Z+:0.462897+j0.593838 Macomia 110 0.91 477.9161 Z+:0.612170+j0.936092 Mocimbua 110 0.71 372.8796 Z+:0.725866+j1.203414 Pemba 110 1.22 640.7227 Z+:0.503492+j0.668175 Namialo 110 4.79 2515.624 Z+:0.178264+j0.121104 Namialo 220 5.90 1549.288 Z+:0.144386+j0.085400 Namialo 400 5.89 850.6644 Z+:0.140811+j0.095019 The results show that the fault current flowing through the 400/110kV Namialosubstation was 2.5kA, and 1.5kA for the 400/220kV Namialosubstation, both of which are about five times the normal rating. For other substations, the fault current did not exceed 1kA, showing a moderate fault characteristics. Furthermore, since the substations at Macomia and Mocimbuahas a source impedance of 0.6~0.7p.u.,difference between the base and fault current was very small. 3.5.2 Scenario A : 220kV T/L construction, 220kV operation The three phase to ground fault currents for the years between 2018 and 2036 are shown in Table 3.5.2 in the case of constructing a 220kV T/L between Namialo and Metoro. After 2016, the fault currents in each scenario increases every year. The fault current of 110kV Metoro bus displayed a 410% increase in 2036 compared to the fault current level of 2016, and Pemba substation displayed a 570% increasein 2036 compared to the fault current level of 2016. On the contrary, the substations in Namialo, Macomia, and Mocimbua, displayed only a slight increase of around 210~320% compared to the fault current levels of 2016. Table 3.5.27 short circuit current of secnarioA(220kV T/L) Base 2016 2018 2021 2026 Bus voltage Fault current [kA] [kV] 110 0.725 2.962 3.219 3.351 Metoro 220 0.909 1.610 1.675 Macomia 0.478 0.583 0.940 0.961 Mocimbua 110 0.373 1.481 0.599 0.609 Pemba 0.641 1.786 1.896 1.959 110 2.516 3.293 3.766 3.934 Namialo 220 1.549 2.279 2.673 2.831 400 0.851 1.245 1.450 1.522 Inception Report 2031 2036 4.685 2.342 1.513 0.777 3.587 4.165 3.070 1.638 4.769 2.382 1.513 0.777 3.640 4.349 3.232 1.704 2 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 6000 5000 Metoro110kV Metoro220kV 4000 Macomia110kV 3000 Pemba110kV Namialo110kV 2000 Namialo400kV 1000 Namialo220kV 0 2016 Figure 2018 2021 2026 2031 2036 3.5.10 short curcuit currenttrends of scenario A (220kV T/L) 3.5.3 Scenario B : 400kV T/L construction, 220kV operation The three phase to ground fault currents for constructing the Namialo-Metoro T/L as a 400kV line and operating it with 220kV are shown in Table 3.5.3. Although the fault current of 110kV Metoro substation increases by 110% in comparison with Scenario A, the fault current calculations of other substations were very similar to the results of Scenario A. This shows that the changes in transmission line coefficients from 400kV T/L installation do not have a significant impact on the magnitude of the fault currents. Table 3.5.28 short circuit current of scenario B(400kV construction, 220kV operation) Base 2016 2018 2021 2026 2031 Bus voltage Fault current [kA] [kV] 110 0.725 3.309 3.435 3.435 5.136 Metoro 220 1.654 1.657 1.657 2.568 Macomia 0.478 0.935 1.423 1.423 1.534 Mocimbua 110 0.373 0.599 0.751 0.751 0.783 Pemba 0.641 1.906 3.141 3.141 3.713 110 2.516 3.282 3.802 3.802 4.165 Namialo 220 1.549 2.295 2.820 2.820 3.138 400 0.851 1.251 1.508 1.508 1.665 Inception Report 2036 5.252 2.626 1.539 0.783 3.771 4.349 3.298 1.735 3 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 6000 5000 Metoro110kV Metoro220kV 4000 Macomia110kV 3000 Pemba110kV Namialo110kV 2000 Namialo220kV 1000 Namialo400kV 0 2016 2018 2021 2026 2031 2036 Figure 3.5.11 short circuit current of scenario B(400kV construction, 220kV operation) 3.5.4Scenario C : 400kV T/L construction, 400kV operation The calculated three phase to ground short circuit currents when constructing the Namialo-Metoro T/L as 400kV and operating it on 400kV are shown in Table 3.5.4. Similarly, although the 110kV Metoro substations bus and 110kV Pemba bus showed a 130% and 110% increase in the level of fault current, respectively, the fault currents of other substations did not show much difference with the fault currents calculated in Scenario A. This result, again, verifies that the change in T/L coefficients does not have much impact on the magnitude of the fault currents. Table 3.5.29 short circuit current of scenario C(400kV operation) Base 2016 2018 2021 2026 Bus voltage Fault current [kA] [kV] 110 0.725 3.850 4.333 4.564 Metoro 220 1.102 1.254 1.327 Macomia 0.478 0.977 1.014 1.029 Mocimbua 110 0.373 0.614 0.630 0.635 Pemba 0.641 2.085 2.243 2.300 110 2.516 3.225 3.655 3.860 Namialo 220 1.549 2.195 2.542 2.734 400 0.851 1.242 1.443 1.547 Inception Report 2031 2036 5.971 1.616 1.570 0.793 3.907 4.128 3.075 1.787 6.155 1.672 1.576 0.798 3.976 4.312 3.225 1.860 4 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 6000 5000 Metoro110kV Metoro220kV 4000 Macomia110kV 3000 Pemba110kV Namialo110kV 2000 Namialo220kV 1000 Namialo400kV 0 2016 2018 2021 2026 2031 2036 Figure 3.5.12 short circuit current of scenario C(400kV operation) 3.5.5Summary of short circuit study The three phase to ground short circuit current is usually affected by the location of the fault in the Theveninequivalent circuit. When the Northern part of the power system is supplied by the source that is more than 1300km away from Namialo substations, the impact of change in transmission line coefficients for Namialo-Metoro T/L, is relatively small. The summary of the results for different scenarios are as follows: 1. Since the 400kV Namialo substation is a source terminal, it is merely affected by the higher voltage operations (220, 400kV, shown in Figure 3.5.4, 3.5.5). 2. On the contrary, the fault current of 220/110kV Metoro substation increases by 410~660% for 220kV operation, and 530~850% for 400kV operation compared to the base case. Therefore, relays with higher capacity should be considered for higher voltage operations (Figure 3.5.6, 3.5.7). 3. The change in the magnitude of the fault currents of other substations, (Pemba, Macomia, and Mocimbua), are relatively small (within 110% range). Therefore, the T/L upgrade will not have a significant impact on the relay capacities of these substations. Inception Report 5 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 5000 4000 Namialo110kV 220kVup 3000 Namialo110kV 2000 400/220kVup Namialo110kV 400kV up 1000 0 2016 2018 2021 2026 2031 2036 Figure 3.5.13 fault currents of Namialo S/S 110kV bus 4000 3000 Namialo220kV 220kVup 2000 Namialo220kV 400/220kVup 1000 Namialo220kV400kVup 0 2016 2018 2021 2026 2031 2036 Figure 3.5.14 Fault current of Namialo S/S 220kV bus 8000 6000 Metoro110kVBus_220kVup 4000 Metoro110kVBus_400/220k Vup 2000 Metoro110kV Bus_400kV up 0 2016 2018 2021 2026 2031 2036 Figure 3.5.15 Fault current of Metoro S/S 110kV bus Inception Report 6 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3000 2500 Metoro220kV_200kVup 2000 1500 Metoro220kV_400/220kVu 1000 p Metoro220kV_400kVup 500 0 2016 2018 2021 2026 2031 2036 Figure 3.5.16 Fault current of Metoro S/S 220kV bus 5000 4000 Pemba110kV Bus 220kVup 3000 Pemba110kV Bus 2000 400/220kVup Pemba110kV Bus 400kVup 1000 0 2016 2018 2021 2026 2031 2036 Figure 3.5.17 Fault current of Pemba S/S 110kV bus 2000 1500 Macomia110kV Bus_220kV up 1000 Macomia 110kV Bus 400/220kVup 500 Macomia 110kV Bus 400kVup 0 2016 2018 2021 2026 2031 2036 Figure 3.5.18 Fault current of Macomia S/S 110kV bus Inception Report 7 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.6 Discussion 3.6.1 Technical Analysis Results 3.6.1.1. Power Flow 3.6.1.1.1 System losses The benefits from the construction of Namialo-Metoro T/L should not only be accounted for the loss reduction between Namialo and Metoro but also the system-wide loss reduction effect. Therefore, in order to compare this effect, the system and T/L losses are analyzed in this section. A. Loss for 100% Load Level A-1. System Loss 1200 1000 814 800 600 889 1075 967 641 total demand growth[MW] 400 200 0 2016 2021 2026 2031 2036 Figure 3.6.19 demand growth of northern system(2016~2036) 350 300 Loss-SCA100% 250 200 Loss SCB100% 150 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 100 Loss SCC100% Figure 3.6.20 annual system losses for each scenario Annual load forecast and system loss [MW] is shown in Figure 3.6.1 and 3.6.2. System loss has been calculated using the forecasted load values, and for three different T/L construction scenarios. Inception Report 8 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Table 3.6.30System losses in peak load [MW] Year 2018 2019 2020 2021 2022 SCA 100% 136.31 155.44 187.28 229.75 236.42 SCB 100% 135.73 155.23 186.52 228.25 235.32 SCC 100% 135.25 153.01 182.87 221.96 229.29 2027 2028 2029 2030 2031 2032 276.89 295.64 303.28 296.59 249.21 256.12 275.43 293.72 301.02 294.3 242.78 250.7 268.13 284.66 290.96 284.89 235.07 238.39 Loss reduction effect for three scenarios are shown in Figure 3.6.3. Table 3.6.31 electric energy losscomparision [GWh/year] Year 2018 2019 2020 2021 SCA 100% 693 790 952 1167 SCB 100% 690 789 948 1160 SCC 100% 687 777 929 1128 2027 2028 2029 2030 2031 1407 1502 1541 1507 1266 1399 1492 1529 1495 1234 1362 1446 1478 1447 1194 2022 1201 1196 1165 2032 1301 1274 1211 2023 243.61 242.21 235.56 2033 219.12 217.41 213.43 2024 257.04 254.79 246.6 2034 234.24 232.08 227.15 2025 269.66 268.08 250.9 2035 251.46 249.12 243.03 2026 290.2 288.08 278.58 2036 270.48 262.99 254.21 2023 1238 1231 1197 2033 1113 1105 1084 2024 1306 1295 1253 2034 1190 1179 1154 2025 1370 1362 1275 2035 1278 1266 1235 2026 1474 1464 1415 2036 1374 1336 1292 Loss reduction effects[MW.peak] 손실차:400/220-220kV 손실차:400kV-220kV 18,76 2036 2035 2034 2033 2032 2031 2030 2029 2028 2027 2026 2025 2024 2023 2022 2021 2020 2019 2018 17,73 16,27 14,14 12,32 1 1,7 11,62 10,98 10,44 8,76 8,43 7,797,138,05 6,435,425,697,09 7,49 4,41 2,43 2,251,582,121,461,922,262,29 1,712,162,34 0,74 0,260,210,761,5 1,1 1,4 Figure 3.6.21Comparison of loss reduction effect (Scenario A base) The total system loss and transmission losses for 20 years have been calculated in Table 3.6.2 using the loss values at peak loads and loss rate value of 0.58. If loss reduction benefit factor of 0.18 $/kWh (2021년예상전기 요금: 정산진 16.0524), loss cost is $4261, $4219, $4092 million for Scenario A, B, and C, respectively. Furthermore, loss cost can be reduced by $169 million in case of Scenario C. Table 3.6.32System power loss cost for scenarios [Million USD/year] Annual Loss 2018 2019 2020 2021 2022 2023 SCA 100% 125 142 171 210 216 223 SCB 100% 124 142 171 209 215 222 SCC 100% 124 140 167 203 210 215 2027 2028 2029 2030 2031 2032 2033 253 270 277 271 228 234 200 Inception Report 2024 235 233 226 2034 214 2025 247 245 229 2035 230 2026 265 263 255 2036 247 9 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 252 245 269 260 275 266 269 261 222 215 229 218 199 195 212 208 228 222 241 232 A-2.Namialo-Metoro T/L Losses The T/L losses using peak load for years from 2018 to 2036 is shown in Figure 3.6.4 and Table 3.6.4. Figure 3.6.22Transmission route power losses, 100% load [MW/peak] 3 2,5 2 SCA 100%ED 1,5 SCB 100%ED 1 SCC 100% ED 0,5 Table 3.6.33 transmission line energy losses, 100% load [GWh/year] T/L Losses 2018 2019 2020 2021 2022 SCA 100% 0.51 1.52 2.03 4.06 3.05 SCB 100% 0.51 1.02 1.02 2.03 1.52 SCC 100% 0.51 0.51 1.02 1.52 1.02 2027 2028 2029 2030 2031 2032 5.08 6.10 6.61 6.61 7.11 12.70 2.03 3.05 3.05 3.05 3.05 4.06 2.03 1.52 2.03 2.03 2.03 2.03 2036 2035 2034 2033 2032 2031 2030 2029 2028 2027 2026 2025 2024 2023 2022 2021 2020 2019 2018 0 2023 3.56 2.03 1.02 2033 8.13 3.56 1.52 2024 5.08 2.54 1.52 2034 9.15 4.06 2.03 2025 4.06 2.03 1.52 2035 9.65 4.57 2.03 2026 6.61 3.05 2.54 2036 11.69 5.08 2.54 Table 3.6.34 transmission line loss costs, 100% load [Million USDollar/yr] Loss Cost [M$/yr] 2018 2019 2020 2021 2022 2023 2024 2025 2026 SCA 100%ED 0.09 0.27 0.37 0.73 0.55 0.64 0.91 0.73 1.19 SCB 100%ED 0.09 0.18 0.18 0.37 0.27 0.37 0.46 0.37 0.55 SCC 100% ED 0.09 0.09 0.18 0.27 0.18 0.18 0.27 0.27 0.46 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 0.91 1.10 1.19 1.19 1.28 2.29 1.46 1.65 1.74 2.10 0.37 0.55 0.55 0.55 0.55 0.73 0.64 0.73 0.82 0.91 0.37 0.27 0.37 0.37 0.37 0.37 0.27 0.37 0.37 0.46 Losses for the system and T/L from 2018 to 2036, for different scenarios are shown in Table 3.6.6. Inception Report 10 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Table3.6.35Comparison between system losses and Transmission line losses, 100% load System Transmission Lines Incremental dWloss[GWh] dWloss[GWh] Loss[GWh] Loss Line loss[Gwh] SCA SCA cost[M$] SCA 23,670 0 0 113.3 0 SCB 23,442 229 41 51.3 62.0 SCC 22,731 939 169 31.0 82.3 Incremental Loss cost[M$] 0 11 15 From the table above, it has been shown that the system loss is much larger compared to the T/L losses, which is due to the long range power transmission, coming from the sources located in the Northwest area. Furthermore, as the system load increases continuously, loss is affected by composition of generation sources. After 2026, the system reaches power transfer limit if hydro or coal power plant is used to meet the loads. Hence, must run generations located in eastern area have to be operated. Although must-run generations bring the benefit of loss reduction, increased system wide generation cost should also be considered during economic evaluation. For instance, if loads after Metoro substation is increased by 10MW, 16MW is required to meet this load level using CBNB, whereas only 8.5MW is needed using NacalaVelha. B. 110% Load Level B-1.System Loss for 110% Load Level If loads follow 110% of the forecasted load level, its system losses are shown in Figure 3.6.5. In this case, for each scenario, must-run generation should be operated to meet the increasing loads, and also to be operated stably. Total system loss for each scenario, keeping the must-run generation at a constant level, is shown in Table 3.6.7. 400 350 300 SCA110%ED Loss SCB110%ED Loss 250 SCC110%ED Loss 200 Inception Report 2036 2035 2034 2033 2032 2031 2030 2029 2028 2027 2026 2025 2024 2023 2022 2021 2020 2019 2018 150 11 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.6.23 system losses for 110% load, peak [MW] Table 3.6.36 System losses for each scenario, 110% load, [GWh/yr] 2018 2019 2020 2021 2022 2023 2024 2025 2026 SCA 898.6 1003.3 1105.6 1343.5 1470.7 1515.6 1545.3 1569.6 1585.2 SCB 898.5 1001.4 1102.9 1336.4 1463.7 1507.0 1535.3 1551.1 1567.2 SCC 895.3 988.5 1088.9 1314.7 1431.6 1477.2 1501.9 1554.9 1532.7 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 1487.8 1486.5 1562.2 1538.5 1379.9 1360.7 1362.7 1550.2 1542.1 1769.6 1487.1 1479.2 1553.2 1528.6 1376.3 1305.3 1351.2 1548.7 1542.1 1768.3 1451.8 1452.4 1523.3 1499.6 1329.3 1290.3 1315.7 1505.0 1523.8 1731.7 B-2.Namialo-MetoroT/L Losses The transmission losses of Namialo-Metoro corridor for 110% load level of each scenario is shown in Figure 3.6.6. Although the total power loss for each scenario through the projected period (2018~2016) is 102.63, 59.45, and 56.40 [GWh], for SCA, SCB, and SCB, in order to minimize the losses, the new T/L should be constructed as 400kV T/L, and operated as 220kV until 2022, and stepped up to 400kV at 2023 (Total loss reduced to 49.28GWh). 6 5 4 SCA110% N-Mloss 3 SCB110% N-Mloss SCC110% N-Mloss 2 1 0 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Figure 3.6.24Namialo-Metoro T/L loss(110% Load, Peak) The figure below shows annual loss of Namial-Metoro T/L for three scenarios. Inception Report 12 / 31 ELECTRICIDADE DE MOÇAMBIQUE BYUCKSAN POWER CO.,LTD. CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 6 5 4 3 A110kV 2 A220kV 1 0 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 6 5 4 3 B110kV 2 B220kV 1 0 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 6 5 4 3 C110kV 2 C400kV 1 0 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Figure 3.6.25 Transmission line loss composition of Namialo-Metoro Corridor C. System planning not on schedule (100% Load level, Without Lurio hydro plant) C-1.System Losses In this section, power flows analysis was performed assuming that the Lurio hydro plant is out of service, and Inception Report 13 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO system loss was derived from the power flow analysis results. The system loss at peak loads and must run generations for different scenarios are obtained by dispatching the generators evenly throughout the system, and the results are shown in the figure below. 600 SC0100% 500 mustrun 400 600 300 200 200 100 100 0 0 16 18 20 22 24 26 28 30 32 34 36 16 18 20 22 24 26 28 30 32 34 36 600 600 400 SCA100% Loss 400 300 500 SCA100% mustrun 500 SCB100% mustrun SCB100% Loss 500 400 SCC100% mustrun SCC100% Loss 300 300 200 200 100 100 0 0 16 18 20 22 24 26 28 30 32 34 36 16 18 20 22 24 26 28 30 32 34 36 Figure 3.6.26 T/L Loss and must-run generation of N-M corridor for scenario (100% Load, Lurio off) For Scenario 0 (No new T/L construction), power flow analysis does not converge after 2020 if must-run generations are not operated, meaning that the power cannot be transferred to the loads. Furthermore, generation has been evenly dispatched throughout the system in order to compare the loss reduction effect in three scenarios, therefore, must-run generation levels have not been changed. Inception Report 14 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 400 350 300 250 SCA100% Loss 200 SCB100% Loss 150 SCC100% Loss 100 50 0 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Figure 3.6.27.System loss for three scenarios assuming Lurio is not in service[MW] The annual system loss [GWh/yr] for each scenario is shown in Table 3.6.8. Table 3.6.8 Power loss inNamialo-MetoroT/L [GWh/yr : 100% Load, Lurio not in service) 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 SC0100% 646 766 956 1102 1398 1479 1308 1514 1865 1478 1314 SCA100% 646 766 865 923 1119 1547 1469 1523 1623 1723 1349 SCB100% 646 766 860 915 1110 1529 1454 1500 1593 1686 1288 SCC100% 646 766 848 899 1086 1468 1416 1450 1528 1635 1293 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 Total SC0100% 1807 1776 1232 1751 1241 1739 1791 1279 1441 1381 27851 SCA100% 1814 1785 1775 1770 1329 1796 1673 1227 1472 1440 28224 SCB100% 1777 1748 1729 1729 1326 1751 1627 1191 1385 1440 27636 SCC100% 1701 1676 1645 1658 1286 1684 1560 1181 1435 1400 26852 From the table above, using SCA as the base case, loss reduction of 588GWh and 1372GWh can be realized for SCB and SCC, respectively. The annual loss difference, using Scenario A as base case, for Scenario B and C is shown in the Figure below. Inception Report 15 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 140,0 128,9 120,0 113,0 100,0 95,4 88,6 80,0 78,2 60,0 0,0 87,2 A-B 73,2 61,4 56,5 53,5 46,2 40,0 20,0 111,8 112,3 111,5 109,3 37,8 33,3 17,3 5,5 24,1 7,9 9,8 37,1 37,4 41,1 42,6 30,2 17,5 15,2 A-C 45,2 46,5 45,9 39,3 35,7 36,8 23,3 2,3 0,0 18 19 20 21 22 23 24 25 26 27 228 29 30 31 32 33 34 35 36 Figure 3.6.28Annual power loss between scenarios using SCA as the base case[GWh/yr] C-2.T/L loss in Namialo – Metoro Corridor 각시나리오의해당년도최대전력에대한손실계산결과선로손실의추이는그림과같다. 부하증가에따라손 실증가가균일하지않은것은 must-run 발전기들이병입되기때문이다. 6 5 4 Corri Loss SCA 3 Corri Loss SCB 2 Corri Loss SCC 1 0 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Figure 3.6.29Namialo-Metoro corridor의선로손실(MW : peak load case) The losses occurring in high and low voltage lines for each scenario is shown in Figure 3.6.12 and Table 3.6.9.According to these results, most loss occurs in high voltage transmission lines, and transmission loss reduction of 257GWh can be realized throughout the project period (‘18~’36) if SCC (400kV) is used. Inception Report 16 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 6 4 SCA-110kV SCA-220kV 2 0 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 5 3 SCB-110kV SCB-220kV 1 -1 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 5 3 SCC-110kV SCC-400kV 1 -1 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Figure 3.6.30 Loss comparison of N-M Corridor for different Scenario (In the order of Scenario A, B, C)(MW, 100% Load, Lurio off) Table 3.6.9 Annual Loss of N-M Corridor T/L for each scenario(GWh/yr, 100%, Lurio off) [GWh] 18 19 20 21 22 23 24 25 26 27 Loss SCA 7 9 11 15 14 16 18 17 16 18 Loss SCB 3 6 5 7 6 7 8 7 8 8 Loss SCC 1 2 1 2 2 2 2 2 2 2 28 29 30 31 32 33 34 35 36 total Loss SCA 19 22 21 14 20 26 7 10 15 295 Loss SCB 8 9 8 7 8 11 4 6 15 138 Loss SCC 3 3 3 2 2 3 3 2 2 38 Inception Report 17 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 3.6.1.1.2 Must-Run Generation Typically, dispatching generators in power systems are performed in the order of generator with the lowest cost to generator with the highest cost, called economic dispatch. However, for systems like Northern Mozambique, where distant power source is used to supply the load, generations near the load area must be operated in order to supply power securely and reliably. These generations are called must-generations, and they must be operated for secure operation of the system regardless of its high operation costs. A. 100% Load Level In 100% load level, power flow analysis results show that all three scenarios require must-run generations after 2027. Must run generations include Nacala 2, Palma ENI, Lurio, and Messalo, however, Lurio and Messalo, are exempted from consideration since it is a hydro plant, and its operation can be affected by the water level of the system. Therefore, Nacala 2 and Palma ENI was selected as must-run generations, and the annual generation levels of these sources are shown in Table 3.6.9 and Figure 3.6.13. Table 3.6.37. Required Must-run Gen capacities for 3 scenarios Must-runGen Nacala2 Scenario A PalmaENI Nacala2 Scenario B PalmaENI Nacala2 Scenario C PalmaENI 2027 30 0 30 0 30 0 2028 30 0 30 0 30 0 2029 40 0 40 0 40 0 2030 60 0 60 0 60 0 2031 120 0 120 0 120 0 2032 135 0 135 0 135 0 2033 190 0 190 0 190 0 2034 190 0 190 0 190 0 2035 190 0 190 0 190 0 2036 200 0 200 0 200 0 250 200 220kV Nacala2 220kV PalmaEni 150 400/220kV Nacala2 100 400/220kV PalmaEni 400kV Nacala2 50 400kV PalmaEni 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 0 Figure 3.6.31. Required Must-run Gen capacities for three scenarios B. 110% Load Level The must-run generation levels are shown in Table 3.6.9 and Figure 3.6.14 for 110% load level. Compared to 100% load levels, it requires earlier operation of must-run generations, which is due to the operation of Lurio hydro plant. For SCA and SCB, NacalaVelha must-run generation is operated in 2020, and even though the generation amount for each case is different, it shows that must run generation is required to operate the system. Inception Report 18 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Table 3.6.38Must-run generation (110% Load) 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 SCA110% 0 55 55 55 85 85 85 85 95 105 175 SCB110% 0 55 55 55 85 85 95 95 95 105 120 SCC110% 0 55 55 55 55 95 95 95 95 95 110 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 sum SCA110% 155 172 180 200 245 270 290 280 280 280 3232 SCB110% 225 172 180 185 250 260 290 283 280 275 3245 SCC110% 116 150 150 170 245 250 275 270 270 305 3006 350 300 250 200 SCA110% 150 SCB110% 100 SCC110% 50 2036 2035 2034 2033 2032 2031 2030 2029 2028 2027 2026 2025 2024 2023 2022 2021 2020 2019 2018 2017 2016 0 Figure 3.6.32Must-run generation (110% load) The system loss for 110% load level is shown in Figure 3.6.15. In 2020, SCA and SCB utilize 30MW output from NacalaVelha for secure operation of the system, and reduce the loss rate to 16%. However, must –run generations are not required for SCC, and the loss rate is around 18%. If NacalaVelha is operated in SCC with output level of 40MW, the loss rate was reduced to 17.5%. Inception Report 19 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 0,22 0,2 0,18 SCA110%EDsys손실률 0,16 SCB110%EDsys손실률 0,14 SCC110%EDsys손실률 0,12 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 0,1 Figure 3.6.33System loss ratios (110% load) C. System components not following construction/operation schedule (Lurio off, 100% Load level) The required amount of must run generation is shown in Table 3.6.10 and Figure 3.6.16, in case of Lurio hydro plant (180MW) not following the construction/operation schedule. For SC0 (no new T/L construction), great amount of generation is required from NacalaVelha after 2021, for system operation. Must run generation is required after 2026 for SCA, SCB, and SCC. Table 3.6.39 Must-run generation (MRG) (Lurio Generation off, 100% Load) MRG[MW] 16 17 18 19 20 21 22 23 24 25 26 SC0100% 0 0 0 0 0 65 128 92 40 105 160 SCA100% 0 0 0 0 0 0 0 0 0 0 90 SCB100% 0 0 0 0 0 0 0 0 0 0 90 SCC100% 0 0 0 0 0 0 0 0 0 0 90 MRG[MW] 27 28 29 30 31 32 33 34 35 36 sum SC0100% 80 110 215 140 225 150 180 250 215 250 2405 SCA100% 30 48 67 81 170 122 140 237 227 235 1447 SCB100% 30 48 67 81 170 122 140 237 227 235 1447 SCC100% 30 48 67 81 170 122 140 237 227 235 1447 Inception Report 20 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 300 250 200 SC0100% SCA100% 150 SCB100% 100 SCC100% 50 0 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Figure 3.6.34Must-run generation (Lurio generation off, 100% load) 3.6.1.2 Short Circuit Study Results The short circuit current analyses of three different scenarios are as follows: 1) 400kV Namialo substation is source of Namialo-Metoro T/L, hence, it is merely affected by the change in NamialoMetoro T/Ls(Figure 3.5.4, ~3.5.5). 2) For 110kV bus at 220/110kV Metoro substation, the short circuit current becomes 4.1~6.6 times and 5.3~8.5 times the original short circuit current for 220kV and 400kV step up, respectively. Therefore, the capacity of current relays may need to be increased (Figure 3.5.6 and 3.5.7). 3) The short circuit currents of other substations (Pemba, Macomia, Mosimbua) remained within 1.1 times its original short circuit current values, hence, the capacity of current relays do not have to be changed (Figure 3.5.8 and 3.5.9). 3.6.1.3 Transfer Capability There is much limitation to applying N-1 reliability standard to the Northern Mozambique power system. Therefore, the transfer capability has been calculated using N-0 criterion, and only outages of equipment related to Namialo-Metoro T/L has been considered. Table 3.6.40. Transfer Capability for three scenarios Reliability Standard No parallel T/L Scenario A ScenarioB ScenarioC Inception Report N-0 N-1 N-0 N-1 N-0 N-1 N-0 Thermal Capacity [MVA] 77 316 792 1377 Voltage Stability Transfer Capacity(N-0/N1) 2018 2021 2026 2031 2036 0 88 43 157 106 185 0 105 0 112 44 170 0 119 0 94 0 89 0 93 0 93 0 105 170 93 109 ATC [MVA] 89 93 93 21 / 31 BYUCKSAN POWER CO.,LTD. ELECTRICIDADE DE MOÇAMBIQUE CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO N-1 N-M Demand 62 59 65 50.7 77.3 87.2 101.6 118.4 3.6.1.3.1 Transfer Capacity Analysis applying N-0 reliability standard 200 150 118,4 100 87,2 77,3 50 시나리오 A 시나리오 B 101,6 시나리오 C N-M Demand 50,7 0 2018 2021 2026 2031 2036 Figure 3.6.35. Demand and Available transfer capability The relation between transfer capability and demand for Namialo-Metoro interconnection is shown in Figure 3.6.5, when N-0 standard is applied. As shown, transfer capacity decreases as load level increases, and is the greatest in Scenario C. The load exceeds transfer capacity around 2031, requiring the operation of must-run generations. 3.6.1.3.2 Transfer Capacity Analysis using N-1 Reliability Standard In order to apply N-1 reliability standard, the failure probability of each component within the system is required. Since this data could not be obtained N-1 standard could not be applied. However, if Namialo-Metoro T/L is constructed and operated in 400kV, it has been identified that the system could withstand certain outages of system components, which was not possible in case of Scenario A. This result shows that the system reliability can be improved if 400kV backbone in extended to Metoro substation. Furthermore, 400kV T/L construction and operation has greater amount of transfer capacity compared to 220kV operation. 3.6.2 Benefit of the Interconnection with Tanzanian Power system 3.6.2.1 Overview of Tanzanian Power System Inception Report 22 / 31 ELECTRICIDADE DE MOÇAMBIQUE BYUCKSAN POWER CO.,LTD. CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.6.36 System(2002) Network Figure 3.6.37 Number of Customers Connected (Source : TANESCO OVERVIEW, FelchesmiMramba, 14-Aug-2015) Tanzania is the country which is next to the North border of Mozambique, and its power system is operated by TANESCO(Tanzania Electric Supply Company). The population of Tanzania is 49.6 million, and 38% of the population is supplied with electricity. Furthermore, there are 1,501,162 households (2015. 6. 30), and the annual power usage of each household is 101kWh/year. Recently, the electrification of Tanzania has reached 23%~38% annually, due to Tanzanian government and international cooperation and support. Inception Report of Tanzanian Power 23 / 31 ELECTRICIDADE DE MOÇAMBIQUE BYUCKSAN POWER CO.,LTD. CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Figure 3.6.38 Master Plan of TANESCO The master plan of Tanzanian system, until 2035, is shown in Figure 3.6.20. In 2015, total generation capacity was 1250MW (Hydro 45%, gas 35.3%, liquid oil 19.4%, SPP 0.3%), with the peak load of 934.62MW. An independent grid is located in the South with the generation capacity of 73.77MW, and peak load of 48.58MW. The power consumption in 2014 was 6000GWh, and although the load growth rate compared to the previous year was 5%, the annual average load growth rate was estimated to be between 8% and 15% in the master plan. The transmission system uses voltage levels of 220kV, 132kV, and 66kV, where 220kV is mainly used, and the distribution network is composed with 33kV, 11kV, and 400V/230V low voltage lines. The power network of TANESCO is constantly expanding, and according to the master plan, 400kV network will be the main power transmission line in the future. The 400kV transmission line is planned to be expanded to Mtwara, which is very close to the North border of Mozambique, and is planned to be interconnected with Mozambique to exchange power (220kV T/L, 100MW capacity). Inception Report 24 / 31 ELECTRICIDADE DE MOÇAMBIQUE BYUCKSAN POWER CO.,LTD. CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO Table 3.6.41 Participation in Power Trading (source : Master Plan of TANESCO, page 45) 3.6.2.2 Benefit of Interconnection between Mozambique and Tanzania Selecting the best scenario for Namialo-Metoro T/L construction depends on the procurement of transfer capacity, to supply the loads connected to Metoro substation, and T/L losses. However, even though the 400kV backbone transmission network has been constructed in the Northern transmission system, the transfer capacity is still very limited due to 1300km of distance between the source and load. However, if new generations located near the east coast (Palma ENI, NacalaVelha), system loss can be reduced, transfer capacity can be increased, and the system can be operated more securely and reliably. If the Tanzania transmission network follows the master plan, 400kV T/Ls can be used to exchange power between Tanzania and Mozambique, which can be seen as another power source to supply the loads in Metoro area. Furthermore, this interconnection will increase the reliability of the system, and Northern Mozambique system may then be able to satisfy N-1 reliability standard. Therefore, 400kV T/L construction may be more beneficial due to greater transfer capacity, compared to 220kV T/L, in this respect. 3.6.3 Feasible Solution for Namialo-Metoro Transmission upgrade In this section, the construction of T/L between Namialo and Metoro for different scenarios has been analyzed for 100% and 110kV load levels, and for the case of generations not following the construction and operation schedule. As a result, SCC (400kV T/L construction) displayed the best characteristics compared to other two scenarios. However, when 110% load levels were considered, SCC showed a low level of losses after 2022, which may be due to high level of reactive power exchange on 400kV T/L. Therefore, it is better to operate the T/L on 220kV, during low load levels. In addition, SCC displayed better transfer capacity than other scenarios; however, must-run generations have to be operated after 2031. Therefore, considering all the technicalities, and for minimum loss and maximum transfer capacity, 400kV T/L should be constructed, and operated on 220kV until 2022, and stepped up to 400kV after 2022. Inception Report 25 / 31 ELECTRICIDADE DE MOÇAMBIQUE BYUCKSAN POWER CO.,LTD. CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO 4. Conclusion This study has been conducted in order to identify the most adequate T/L construction scenario between 400kV Namialo and 110kV Metorosubstations in order to provide a secure and reliably power to the fast growing areas in Northern Mozambique, Pemba, Macomia, and Ausse until 2036. The considered scenarios are: Scenario 0: No T/L construction (Increasing load levels only served by current 110kV T/L) Scenario A: Constructing 220kV T/L and operating it in parallel with current 110kV T/L. Scenario B: In order to account for future expansion of the transmission system and the tie-line interchange with other African countries, constructing 400kV T/L and operating on 220kV until the load growth is manageable. Scenario C: Constructing and operating the T/L with 400kV. Power flow, voltage stability transfer capability, and fault analysis was conducted for each scenario in order to: Identify whether the system is capable of serving the load in each scenario Identify potential problems and security concerns in the system, and if there are any factors that jeopardize system security Calculate the power losses and the capacities of must-run generations for economic evaluation 4.1 Results The main generation used to supply power to Metoro substation comes from the hydro and thermal power generations, which are located more than 1000km away from the load area. Due to the length of the transmission, the T/L losses amount to almost 60% of the supplied power. On the other hand, if new generations, which are constructed near the load, are used to supply the load, it may significantly reduce the transmission losses. After analyzing the three different scenarios, Scenenario A, 220kV T/L construction and operation, Scenario B, 400kV T/L construction and 220kV operation, and Scenario C, 400kV construction and operation, the results show that it is optimal to construct the Namialo-Metoro T/L as 400kV T/L, and operate it on 220kV until 2023, then step up the voltage to 400kV after 2023. However, must-run generators have to be operated after 2031 for all three scenarios due to insufficient transfer capacity. The economic value of must run generators should be taken into account in future feasibility studies. Furthermore, after analyzing the system losses throughout the project period (2018~2036), the results show that Scenario C is able to reduce system losses by 939GWh and Namialo-Metoro T/L losses by 82.3GWh compared to Scenario A, in 100% load levels. In 110% load levels, Scenario C reduced system losses by 682GWh and Namialo-Metoro T/L losses by 46.2GWh, compared to Scenario A. Lastly, if Lurio hydro plant (must-run generation) is assumed to be out of service throughout the project period, Scenario C is able to save 1372GWh of system losses and 275GWh of Namialo-Metoro T/L losses compared to Scenario A. The operation of must-run generations has significant effect on system security for Northern power system operation. In 100% load levels, must-run generation have to be operated since 2027 and since 2020 for 110% load levels even if Lurio is assumed to be operating. If Lurio plant is out of service, NacalaVelha generation must be operated since 2021 in Scenario A for stable system operation. Constructing the T/L between Namialo and Metoro as 400kV T/L provides another advantage as the Northern system may be interconnected with the Tanzanian power system, which can increase the system security, stability, and reliability. Also, 400kV T/L will serve as the core network of renewable energy source integration in Africa, promoting energy source and industrial development. Inception Report 26 / 31 ELECTRICIDADE DE MOÇAMBIQUE BYUCKSAN POWER CO.,LTD. CONSULTANCY SERVICES FOR PACKAGE-1 FEASIBILITY STUDY FOR THE 220kV INTERCONNECTION NAMIALO - METORO References [1] “Technical Assistance to Strengthen EDM’s Capacity for Investment and Network Development Planning - Master Plan Update Project, 2012 - 2027 -Volume 1–Final System Review Report”, 2013-04-15 [2] “Technical Assistance to Strengthen EDM’s Capacity for Investment and Network Development Planning, Master Plan Update Project, 2012 – 2027” , Draft Final Master Plan Update Report, Volume II - Load Forecast Report, Norconsult, 2013-04-15 [3] “Chimuara - Nacala Transmission Project Feasibility Study”, Volume II: Norconsult , May 2013 Load Forecast, Final Report - Assignment no.: 5009957 [4] Gilberto Mahumane, Peter Mulder e David Nadaud, “Energy outlook for Mozambique 2012-2030 LEAP-based scenarios for energy demand and power Generation”, IESE conference paper n 16, 4~5 September 2012 [5] “Mozambique Regional Transmission Backbone Project (“CESUL”): Technical & Economic Feasibility Study”, Presentation of Feasibility Study Report, CESUL Launch Workshop, Centro de Conferências Joaquim Chissano, Maputo, 24 November 2011 [6] Judy W.Chang, et.el, July 2013. “The benefits of Electric Transmission : Identifying and Analyzing the Value of Investments”, The Brattle Group, [7] EDM Annual Report 2014, Electricidade De Mocambique [8] Statistical Summary 2012, ,Electricidade De Mocambique Inception Report 27 / 31