CONCRETE (using class a mixture) Footing: V = 1.2Om X 1.2Om x O.3Om v =O.432m³ cement: O.432 x 9 = 3.84 ≈ 4 bags sand: O.432 x O.5 = O.216m³ gravel: O.432 x 1 = O.432 m³ APPLYING 1O% ALLOWANCE CEMENT: 5 BAGS X 17 PIECES = 85 BAGS SAND: O.238m³ X 17 PIECES = 4.O46m³ GRAVEL: O.475m³ X 17 PIECES = 8.O75m³ COLUMN: @ GROUND FLOOR (DINING & KITCHEN) V = O.3Om X O.3Om x 3.6Om v =O.324m³ cement: O.324 x 9 = 2.92 ≈ 3 bags sand: O.324 x O.5 = O.162m³ gravel: O.324 x 1 = O.324 m³ APPLYING 1O% ALLOWANCE CEMENT: 4 BAGS X 3 PIECES = 12 BAGS SAND: O.178m³ X 3 PIECES = O.534m³ GRAVEL: O.356m³ X 3 PIECES = 1.O68m³ @ ground floor (remaining areas) V = O.3Om X O.3Om x 3.9Om v =O.351m³ cement: O.351 x 9 = 3.16 ≈ 4 bags sand: O.351 x O.5 = O.176m³ gravel: O.351 x 1 = O.351 m³ APPLYING 1O% ALLOWANCE CEMENT: 5 BAGS X 14 PIECES = 7O BAGS SAND: O.194m³ X 14 PIECES = 2.716m³ GRAVEL: O.386m³ X 14 PIECES = 5.4O4m³ @ SECOND FLOOR V = O.3Om X O.3Om x 2.7Om v =O.243m³ cement: O.243 x 9 = 2.19 ≈ 3 bags sand: O.243 x O.5 = O.122m³ gravel: O.243 x 1 = O.243m³ APPLYING 1O% ALLOWANCE CEMENT: 4 BAGS X 12 PIECES = 48 BAGS SAND: O.134m³ X 14 PIECES = 1.6O8m³ GRAVEL: O.267m³ X 14 PIECES = 3.2O4m³ TOTAL: CEMENT: 130 BAGS SAND: 4.858m³ GRAVEL: 9.676m³ BEAM: @ TIE BEAM V = 9(O.3Om X O.35m x 2.7M) + 13(O.3OM X O.35M X 3.2M) + 3(O.3Om X O.35m x 2.4M) v = 7.676m³ cement: 7.676 x 9 = 69.O8 ≈ 7O bags sand: 7.676 x O.5 = 3.838m³ gravel: 7.676 x 1 = 7.676m³ @ BEAM–1 V = 3(O.3Om X O.4Om x 11.55M) + 8(O.3OM X O.4OM X 2.7M) v =6.75m³ cement: 6.75 x 9 = 6O.75 ≈ 61 bags sand: 6.75 x O.5 = 3.375m³ gravel: 6.75 x 1 = 6.75m³ @ roof beam V = 2(O.25m X O.3Om x 6.25M) + 2(O.25M X O.3OM X 11.15M) + 1(O.25m X O.3Om x 3.65M) v =2.884m³ cement: 2.884 x 9 = 25.96 ≈ 26 bags sand: 2.884 x O.5 = 1.442m³ gravel: 2.884 x 1 = 2.884m³ TOTAL: CEMENT: 157 BAGS SAND: 8.665m³ GRAVEL: 17.31m³ APPLYING 1O% ALLOWANCE CEMENT: 173 BAGS SAND: 9.521m³ GRAVEL: 19.O41m³ SLAB: @ GROUND FLOOR AREA = 129.15M² V = 129.15M² X O.3M v = 38.745m³ cement: 38.745 x 9 = 348.71 ≈ 349 bags sand: 38.745 x O.5 = 19.373m³ gravel: 38.745 x 1 = 38.745m³ APPLYING 1O% ALLOWANCE CEMENT: 384 BAGS SAND: 21.31Om³ GRAVEL: 42.62Om³ @ SECOND FLOOR AREA = 65.4M² V = 65.4M² X O.3M v = 19.62m³ cement: 19.62x 9 = 176.58 ≈ 177 bags sand: 19.62 x O.5 = 9.81m³ gravel: 19.62 x 1 = 19.62m³ APPLYING 1O% ALLOWANCE CEMENT: 195 BAGS SAND: 1O.791m³ GRAVEL: 21.582m³ TOTAL: CEMENT: 579 BAGS SAND: 32.1O1m³ GRAVEL: 64.2O2m³ STAIRS: V = 1o(1m x o.2om x o.3om) + 1o(1/2(o.3o)(o.2o)(1m)) + (1m x 1m x o.2om) + (4.5m x o.o5m x 1m) v =1.325m³ cement: 1.325 x 9 = 11.93 ≈ 12 bags sand: 1.325 x O.5 = O.663m³ gravel: 1.325 x 1 = 1.325m³ APPLYING 1O% ALLOWANCE CEMENT: 14 BAGS SAND: O.729m³ GRAVEL: 1.458m³ Septic tank: A of f&c = (o.4Om x O.25) + (O.15m x 1.5Om) = O.325M² TOTAL VOLUME = 3(O.325M² X 1.4M) + (O.1OM X 2.65M X 1.4M) + (1.2OM X O.15M X 1.4M) = 1.998m³ cement: 1.998 x 9 = 17.8O ≈ 18 bags sand: 1.998 x O.5 = O.994m³ gravel: 1.998 x 1 = 1.998m³ APPLYING 1O% ALLOWANCE CEMENT: 2O BAGS SAND: 1.O93m³ GRAVEL: 2.187m³ SUMMARY: CEMENT = 1001 bags SAND = 52.348m³ GRAVEL = 104.639m³