BMGT485 Pop Quiz, Monday, May 8th Version B NAME: ______________________________ Topics: Reducing Project Duration Monitoring Project Performance Project Selection Guidelines: This assessment is closed-book, closed notes. Electronics are NOT allowed except for a calculator. Raise your hand to seek clarification about questions. Topic/content questions cannot be answered during the quiz. Students are not allowed to leave the classroom while taking the quiz. For quiz grading and feedback, keep the last page and submit answers on Canvas. Honor Pledge: “I pledge on my honor that I have not given or received any unauthorized assistance on this examination.” Signature: _____________________________________ Good luck! 1) (5 points) Below is the network representation of a project. Estimate the project duration. Calculate the earliest start, earliest finish, latest start, latest finish, and slack for each activity. Report the critical path. Project Duration: Critical Path: 2) (15 points) Find the crash point for the previous project network. Compress one time unit per move using the least-cost method. Assume the total indirect cost for the project is $1300 and there is a savings of $80 per time unit reduced. Record the total direct, indirect, and project costs for each duration. Reduce project duration until crash point. Activity Slope A B C D E F Iteration (Duration) 100 60 50 30 110 Max Crash 1 1 2 1 1 Activities Crashed Normal $200 $140 $80 $100 $60 $200 Crashed Cost Total Direct Cost Total Indirect Cost Total Cost What is the optimal project duration? What is the minimum total cost? Create a graph to show Total Direct Cost, Total Indirect Cost and Total Cost for different project durations. (You may skip the graph as it will not be graded for the quiz.) 3) Below is the budget for each task in the previous project network. Create a time phased budget for the project. Task A 3 4 4 B 2 3 C 2 D 2 2 2 3 3 E 3 2 3 2 3 F 2 2 2 a. (5 points) Create a time-phased budget for the project. Task Budget 0 A B C D E F Total Cumulative 1 2 3 4 5 6 7 8 9 10 11 12 b. (10 points) At the end of week 7, the amount of work completed and actual cost so far for each task is as follows: Task A B C D E F AC 100% 10 100% 4 100% 2 60% 7 80% 10 Calculate cost variance and cost performance index. Calculate schedule variance and schedule performance index. What percentage of the project has been completed based on the budgeted cost? PCIB Plot the planned value, variances, and performance indices in the appropriate chart. (You may skip the graph as it will not be graded for the quiz.) What is the overall status of the project? A) B) C) D) Over budget and ahead of schedule Over budget and behind schedule Under budget and ahead of schedule Under budget and behind schedule Explain: 4) The Uber Bike Company has set up a weighted scoring matrix for evaluation of potential software applications to enhance its service. a. (3 points) Calculate the payback period for each project. The Alpha project needs a $280,000 initial investment and it will generate $120,000 the first year and $60,000 annually after. The Beta project needs a $240,000 initial investment and it will generate $45,000 annually. Lastly, Gamma needs $380,000 and it will generate $200,000 on the first year and $300,000 on the second year. What is the payback period for each project? Show your work. Project Alpha Beta Gamma Payback Period (in years) b. (9 points) Complete the scoring matrix and calculate the weighted total score for each project. For cost, the company uses the following scoring system: Estimated cost Score $250,000 or less 5 More than $250,000 to $500,000 4 More than $500,000 2 For payback period, the company uses the following scoring system: Payback period Score Less than 2 years 5 2 to 5 years 4 More than 5 2 Criteria Weight Alpha Beta Gamma Supports Business Cost Strategy 20 40 5 3 2 Payback Period 40 Weighted Total -------- c. (3 points) Interpret results. Answer the following questions: Which project should be selected based on weighted total score? ___________________ If “supports business strategy” is a must objective for the company (project must have a score of 3 or higher in that criterion for consideration), Which project should be discarded? __________________ Quiz Scoring (due by the end of the day) To quickly receive a score for your quiz, you will enter your answer in the grayed boxes on a quiz on Canvas: Pop Quiz 2 scoring. Make sure to copy them exactly. You are not allowed to share these answers with anybody. You are not allowed to copy any additional information from the quiz besides your answers. A random check will be conducted to ensure that answers on your paper submitted quiz and on Canvas match. If there is a discrepancy between them, the score quiz will be updated to zero and it will not be dropped from your final course grade. Please make sure to copy your answers correctly! Version: A or B Question 1 Project Duration: Critical Path: Question 2 What is the optimal project duration? What is the minimum total cost? Question 3 Calculate cost variance and cost performance index. Calculate schedule variance and schedule performance index. What percentage of the project has been completed based on the budgeted cost? PCIB A) B) C) D) Question 4 Project selected? ___________________ Project discarded? __________________