CCTV method statement

advertisement
Nasa Multiplex
Burj Dubai – The Residences
Client :-
MEP Contractor
(1804)
Emaar Properties
M&E Division
Method Statement Title
Method Statement No.
Installation of CCTV System
ETA/MS/E-019
Rev. No. & Date:
‘0’ – 16.06.2004
Burj Dubai – The Residences
Design Consultant
Woods Bagot
MEP Consultant
Roberts & Partners
0
Rev.
Issued for approval
Description
16.06.04
Date
ETA M&E
ETA M&E
NMX
MACE
Prepared By
Reviewed By
Approved By
Approved By
Page 1 of 5
Nasa Multiplex
Burj Dubai – The Residences
Client :-
Emaar Properties
MEP Contractor
(1804)
M&E Division
Method Statement Title
Method Statement No.
Installation of CCTV System
ETA/MS/E-019
Rev. No. & Date:
‘0’ – 16.06.2004
1.0
Scope
This method statement details the method of installation of CCTV System.
Note
A separate Method Statement Ref. ETA/MS/E- 0 shall be submitted for testing and
commissioning of the Fire Alarm System.
2.0
3.0
Material
2.1
All materials shall be as per approved material submittals.
2.2
Type of cable shall be as per approved shop drawings / system manufacturers
recommendation.
2.3
Type of Cameras shall be as per approved shop drawing.
Applicable Location
3.1
4.0
Tower E1, E2, E3, W1, W2, W3(Entrance Floor)
Method
4.1
Storage
4.1.1
All materials received at site shall be inspected and ensured against
approved material submittal.
4.1.2
Any discrepancies, damages etc. shall be notified immediately for
further action.
4.1.3
Material found not suitable for the project are to be removed from site
immediately.
4.1.4
Co axial cables shall be stored with the factory packing on the flat
surface.
Page 2 of 5
Burj Dubai – The Residences
Client :-
Emaar Properties
Nasa Multiplex
MEP Contractor
(1804)
M&E Division
Method Statement Title
Method Statement No.
Installation of CCTV System
ETA/MS/E-019
Rev. No. & Date:
‘0’ – 16.06.2004
4.2
4.1.5
Materials shall be stacked properly as per manufacturers
recommendation and covered to prevent dust and water / moisture.
4.1.6
CCTV Equipment to be stored as per manufactures recommendation
mentioned / marked in the packing.
4.1.8
Ambient condition of the storage place to be as per manufacturer’s
recommendation.
Installation
4.2.1
Co axial Cable
4.2.1.1
Ensure the relevant current / approved shop drawings are
available with installation team.
4.2.1.2
Transfer the cable to the work place with the help
manpower..
4.2.1.3
Check the cable drum for any external damage during
transportation and ensure the type of cable against area of
usage / application.
4.2.1.4
Type of the cable is as per approved shop drawings.
4.2.1.5
In concealed application pull coaxial cable manually
through conduit installed as per approved shop drawings
and approved method statements.
4.2.1.6
Leave enough length of cable at both ends of panel and
devices for termination.
4.2.1.7
No through joints is allowed without the sanction of the
Consultants.
.
Page 3 of 5
Burj Dubai – The Residences
Client :-
Emaar Properties
Nasa Multiplex
MEP Contractor
(1804)
M&E Division
Method Statement Title
Method Statement No.
Installation of CCTV System
ETA/MS/E-019
Rev. No. & Date:
‘0’ – 16.06.2004
4.2.2 CCTV EQUIPMENTS
4.2.2.1
Ensure the relevant current / approved shop drawings are
available with installation team.
4.2.2.2
Transfer the equipment to the work place with the help
manpower.
4.2.2.3
Location of the panel to be as per approved shop
drawing after coordinating with other services.
4.2.2.4
Fixing holes will be marked properly keeping back box
of the panel in place.
4.2.2.5
Fix back box properly and fix remaining panel
accessories.
4.2.3 CCTV CAMERAS
4.2.3.1
Ensure the relevant current / approved shop drawings are
available with installation team.
4.2.3.2
Exact location of the device to be as per approved
reflected ceiling plan for surface / recessed installation
4.2.3.3
For the Camera, which needs to be fixed on the false
ceiling, fix junction box of the camera above false
ceiling.
4.2.3.4
Install the Camera and terminate the cable properly.
Page 4 of 5
Nasa Multiplex
Burj Dubai – The Residences
Client :-
Emaar Properties
MEP Contractor
(1804)
M&E Division
Method Statement Title
Method Statement No.
Installation of CCTV System
ETA/MS/E-019
Rev. No. & Date:
‘0’ – 16.06.2004
5.0
Records
5.1
QC Installation Check List
5.2
Inspection request duly signed-off by NMX and Consultant.
6.0
6.1
Attachment
QC installation check list formats for the following.
a) Installation of CCTV System
Page 5 of 5