Luberef Weekly Production Report - Week 2 Lyle review

advertisement
Saudi Aramco Base Oil Company-Luberef
Weekly Report 1
09-01-2024
Project Summary Report: Week 1
Achievements this Period
Activities next Period
Refer to Lookahead plan slide 3&4 for the following;
• VDU LY 1000 Yanbu Proto-type Handbook review received from
• eLearning Heat Transfer Equipment, Turn-around and Inspection for LUB
validation
• U-1000 VDU and U-4100 IDWU HB LUB validation
• Phase1 Handbook ToC Sectioning – LUB validation
• Validation meeting scheduled for 9th January.
• UPP to clenched a tentative date for the eLearning Equipment 3D Model
review strategy with LUB technical team. LUB to confirm SAP SF Team &
Accenture availability
• LUB to provide comments on Level 3 Production Plan Rev0 issued on the 8th
January.
Luberef on 8th January.
• Level 3 Production Plan Rev0 issued on the 8th January.
• Recovery Plan #1 validation escalated to Mr Ibrahim and Mr Hugues for
resolution.
• Review Action plan introduced within the weekly ‘’Action recap’’ file. (As per
Level 3 Production Plan)
Challenges This Period
Issues/Actions Required
• UPP has received 95% of data for the following units listed below however it’s
extremely important to note that the 5% is the critical path that needs to be
included in the Production output, this could further be a hurdle to the Production
Work-Flow.
• LUB to provide the missing data (GAD’s) for U-1000 VDU and U-4100 IDWU by 9th
January. (refer to the note in the ‘’Challenges this Period’’ box.
• UPP will provide in advance the remaining Missing data required to fulfill the
production for PDA/MLDW/HCU. Missing Data to be provided by 12th January.
•
•
•
•
•
Completing missing data for U-1000 VDU Handbook
Completing missing data for the U-4100 IDWU Handbook
Completing missing data for U-4000 HCU Handbook
Completing missing data for U-5000 MLDW Handbook
Completing missing data for U-2000 PDA Handbook
Note: Missing Data will be mitigated as described in Week1 Project meeting
(09-01-2024) with potential impact to the equipment internal drafting. Further
modification would be mitigated in a maintenance step. (After delivery)
Production Plan Lookahead as per Schedule LEVEL3
Missing data impact / Luberef preparation
Production Lookahead for Wk2 and Wk3 (7th January to 21st January)
Deliverable
E -Learning' Heat Transfer
Equipment, Turn-around
and Inspection
E-Learning Mechanical
Equipment
ToC Sectioning
for
PDA/HCU/MLDW/IDWU
1000 VDU HB Final
Submission to client
4100 IDWU HB Final
Submission to client
Lagging Element
Affecting on time delivery
(Missing data/Technical
clarification)
None
None
None
Missing data is proposed to be
mitigated. LUB to validate the
position before 10th January.
Supporting excel sheet is
attached.
Requirement
Prototype Validation
Review
Review
(Vision meeting to be
held to facilitate a quick
validation)
Review
Start date
End Date
(UPP Date of Issuance) (LUB Date of validation)
9th Jan 2023
11th January
9th Jan 2024
20th Jan 2024
20th Jan 2024
21st Jan 2024
18th January
Action Party
(LUBEREF SME)
Mohsin Basheer
Kannath Krishnaprasad
Abdulqudus Shaikh
Hamza Jawaid
Mohsin Basheer
Kannath Krishnaprasad
Abdulqudus Shaikh
Hamza Jawaid
Mohsin Basheer
Anees / Wael (PDA/MLDW)
Dilipbhai Machhi (HCU/IDWU)
Status
Issued to LUB
on 8th Jan
Planned
Review to start 11th Jan
Planned
Review to start 9th Jan
9th Jan 2024
Mohsin Basheer
Anees/Wael (VDU)
Planned
Review to start
20th Jan
Mohsin Basheer
Dilipbhai Machhi (IDWU)
Planned
Review to start
20th Jan
29th Jan 2024
29th Jan 2024
Same as above
Review
Note:
The lookahead deliverables are extracted from the Schedule Level3.
The Luberef review actions are delineated from the Review Action Plan / Refer to weekly ‘’Action recap’’ file.
Production Plan Lookahead as per Schedule LEVEL3
Missing data impact / Luberef preparation
Production Lookahead for Wk3 and Wk3 (21st January to 3rd February)
Deliverable
2000 PDA HB
Submission to client
5000 MLDW HB
Submission to client
4000 HCU HB
Submission to client
Lagging Element
Affecting on time delivery
(Missing data/Technical
clarification)
Requirement
Start date
End Date
(UPP Date of Issuance) (LUB Date of validation)
Missing data is proposed to be
mitigated. LUB to validate the
position before 12th January.
Supporting excel sheet is
attached.
Mohsin Basheer
Anees / Wael (PDA/MLDW)
Review
Missing data is proposed to be
mitigated. LUB to validate the
position before 12th January.
Supporting excel sheet is
attached.
Missing data is proposed to be
mitigated. LUB to validate the
position before 12th January.
Supporting excel sheet is
attached.
Action Party
(LUBEREF SME)
27th Jan 2024
5th Feb 2024
Review
27th Jan 2024
Review
27th Jan 2024
Status
Planned
Review to start 27th
Jan
Mohsin Basheer
Anees / Wael (PDA/MLDW)
Planned
Review to start 27th
Jan
Mohsin Basheer
Dilibhai Machhi (HCU/IDWU)
Planned
Review to start
27th Jan
5th Feb 2024
5th Feb 2024
Note:
The lookahead deliverables are extracted from the Schedule Level3.
The Luberef review actions are delineated from the Review Action Plan / Refer to weekly ‘’Action recap’’ file.
Production Schedule Progress.
Do we provide the Level2 or
level3 progress?
Level2 remains inserted below
IN PROGRESS
COMPLETED
ON HOLD
LATE
Year
Month
Week
CONTRACT AWARD
UBSCO MOBILIZATION PHASE
MATERIAL COLLECTION
QAQC PLAN VALIDATION
KICK OFF MEETING
SCOPE VALIDATION
MILESTONES
E-LEARNING ACHITECTURE
E-LEARNING ACHITECTURE VALIDATION
2023
Nov-23
Oct-23
42
43
HANDBOOK TOC VALIDATION
HANDBOOK PRODUCTION PHASE-1
HANDBOOK REVIEW PHASE-1
HANDBOOK PRODUCTION PHASE-2
HANDBOOK REVIEW PHASE-2
PROCESS PACKAGE INTERACTIVITY
LMS CONFIG and INTEGRATION TEST
PACKAGES REVIEW
PROCESS MODULE PILOT TEST
Note: Double-click on the sheet to view it completely
44
45
46
47
48