Uploaded by Linx B

p266001coll1 7381

advertisement
AD 723 397
T E C H N I C A L R E P O R T NO. 6
STATIC AN D DYNAM IC A N A L Y S IS OF
ROCK BOLT SUPPORT
RESEARCH ON
ROCK BOLT REINFORCEMENT
by
RICHARD E. G O O D M A N AND J A C Q U E S D U B O I S
■
J A N U A R Y 1971
mm
OMAHA
gw»?
DISTRICT, C O R P S O F E N G I N E E R S
O M A H A , N E B R A S K A 68102
THI S R E S E A R C H WA S F U N D E D
CHI E F OF E N G I N E E R S ,
BY O F F I C E ,
D E P A R T M E N T OF
THE A R M Y
P R E P A R E D UNDER CONTRACT DACA45-67-C-0015 MOD. P 0 0 2
BY THE UNIVERSITY OF CA LIFO R N IA , B E R K E L E Y , CALIFORNIA
.W 3 ¿ í
m^6
<9 71
I
A p p ro v e d for
public release; distribution u nlim ited
BUREAU OF RECLAMATION LIBRARY
DENVER, CO
Destroy this report when no longer needed.
Do not return it to the originator.
The findings in this report are not to be construed as
an official Department of the Army position unless
so designated by other authorized documents.
IRARY
BUREAU OF RECLAMi
92073860
9207Í
TECHNICAL REPORT NO. 6
STATIC AND DYNAMIC ANALYSIS OF ROCK BOLT SUPPORT^
RESEARCH ON ROCK BOLT REINFORCEMENT
^ by
RICHARD E. GOODMAN AND JACQUES DUBOIS f
y JANUARY
1971
V
OMAHA DISTRICT, CORPS OF ENGINEERS
OMAHA, NEBRASKA 68102
THIS RESEARCH WAS FUNDED BY OFFICE,
CHIEF OF ENGINEERS, DEPARTMENT OF THE ARMY
PREPARED UNDER CONTRACT DACAU5-67-C-0015 MOD. P002
BY THE UNIVERSITY OF’d ALIFORNIA^ BERKELEY^ CALIFORNIA
Approved for public release, distribution unlimited.
60
STATIC AND DYNAMIC ANALYSIS
OF ROCK BOLT SUPPORT
ABSTRACT
This report describes progress in a continuing effort to develop and
evaluate methods which can be used to design underground openings to sur­
vive blast loadings.
It includes discussion of the action of rock bolts
Under static loads and considers aspects of the interaction between rock
and rock bolt under dynamic loads.
Only computational methods were used
in this study.
|
First, closed form solutions for point loads are summed and superim­
posed to examine stresses induced by patterns of rock bolts around tunnels
in linearly elastic material.
The stress fields are compared to rock
strengths according to simplified failure criteria, to appreciate the
relative strengthening effect of different combinations of bolt and rock
parameters.
It was found that very substantial bolt pressures are required,
e.g. 10% of the maximum applied pressure, to restrict rock breakage in
ideally elastic material.
Then elastic-plastic material behavior is considered.
Stresses in­
duced by unequilibrated line loadings on the inner circumference of the
tunnel are used to simulate rock bolt patterns.
It is found that the rock
bolt strengthening effect can more easily be substantiated in weaker
materials.
For example, when rock inside the "plastic" zone was taken as
cohesionless, less than 1% of the blast pressure is a sufficiently high
rock bolt pressure to provide significant strengthening effect.
Dynamic considerations are discussed in terms of an energy balance
for the case of a plane rock wall bolted in a regular pattern which receives
a stress wave impulse from inside.
The problem is examined in two ways:
First a calculation is made of the kinetic energy of the system in the
i
most serious increment of time during the response, assuming the bolt to
behave elastically.
Then, the total work during all of the blast response
period is considered, presuming the bolt damage to be cumulative.
The
objective of these computations is to provide a basis for scaling sur­
vivability conclusions from one experiment to another.
to Hardhat and Piledriver experiments.
ii
Reference is made
PREFACE
This investigation was authorized by the Chief of Engineers
(ENGMC-EM) and was performed in FY 1969 and 1970 under Contract
No. DACAU5-67-C-OOI5, Mod. P002, between the Omaha District, Corps
of Engineers and Dr. Richard E. Goodman, Berkeley, California.
This
work is a part of a continuing effort to develop methods which can
be used to design underground openings in jointed rock to survive
the effects of nuclear weapons.
This report was prepared under the supervision of Dr. R. E.
Goodman, Principal Investigator.
Personnel who contributed to the
report were Dr. Hans EWoldsen, Mr. Jacques Dubois, Mr. Iraj
Farhoomand, and Mrs. Anne Bornstein.
During the work period covered by this report, Colonel William H.
McKenzie III and Colonel B. P. Pendergrass were District Engineers;
Charles L. Hipp was Chief, Engineering Division; C. J. Distefano was
Technical Monitor for the Omaha District under the general supervision
of Kendall C. Fox, Chief, Protective Structures Branch.
D. G.
Heitmann and Dr. J. D. Smart participated in the monitoring work.
iii
TABLE OF CONTENTS
ABSTRACT-----------------------------------------------------------
i
PREFACE------------------------------------------------------------
iii
NOTATION------------
viii
CONVERSION FACTORS, BRITISH TO METRIC UNITS OF MEASUREMENT-------
xi
CHAPTER 1
INTRODUCTION--------------------------------------- —
1
CHAPTER 2
AN ELASTIC APPROACH FOR DESIGN OF PATTERNED ROCK BOLT
SUPPORTS UNDER STATIC ORQUASI-STATIC LOADING---------
2.1 Approach--------------------------------------------------- *
2.2 Global Stress Field Around the Tunnel - Elastic Behavior—
2.3 The Extent of the Slip Zone---- --2.1+ Calculation of Rock Loads--------------------------------2.5 The Principle of the Design Method---------------2.6 Illustrative Example----------------------2.7 Conclusion---------CHAPTER 3
DESIGN APPROACH FOR ELASTIC-PLASTIC ROCK UNDER
HYDROSTATIC LOADING----- -----------------------------
3.1 Mathematical Conditions-----------------------------------3.2 Solution for Stresses and Extent ofPlastic Zone----------3.3 Examples------------------------------------------- ■-------3.3.1 Example No. 1-----------------------------------------3.3.2 Example No. 2-----------------------------------------3.1+ Conclusions-----------------------------------------------CHAPTER 1+
3
3
5
8
9
10
11
13
55
55
57
6l
63
63
6k
DYNAMIC ANALYSIS OF THE TUNNEL SUPPORT PROBLEM-------
86
Introduction---------------------------------------- ---- -—
k.2 Rigid Two Body Analysis-----------------------------------1+.3 Elastic - Two Body Analysis------------------------------1+.1+ Energy Approach to Rock Bolt Problem---------------------l+.l+.l Case 1: Only KineticEnergyConsidered----------------1+.J+.2 Case 2: Total Work Considered-----------------------1*.5 Discussion---------------------------------
86
l+.l
CHAPTER 5
EMPIRICAL APPROACH TO SUPPORT DESIGN AGAINST
BLASTS----------
5.1 Definitions---- •------------------------------------------5.1.1 Wave Travel Time-----------------5.1.2 Energy Absorption by the Support System--------------5.1-3 Energy Dissipation Time of the Support System---------
iv
87
89
90
92
99
102
110
110
110
111
112
5.2 Results of the Pile Driver Tests--------------------------5.2.1 General EmpiricalEnergy Equation-----------------------5.2.2 Application toPile Driver Test-----------------------5-3 Hardhat Drift---------- ----------------------------------—
5 .1+ Conclusion--------------------------------------------- ----
112
113
115
117
11 8
REFERENCES--------------------------------------------------
119
APPENDIX I-------------------------
120
APPENDIX II—
127
-----------------------------------------------------
v
TABLES
2 .1
Economic Comparison of Rock Bolt Design------------------Comparison of Rock Bolt Design I--------------------------Comparison of Rock Bolt Design II---------------------Radius of 3he Plastic Zone for Various Rock Properties_—
Variation of the Plastic Zone with C--------------Example No. 1 Results------------------
2.2
2.3
3.1
3.2
3.3
16
17
18
66
66
66
FIGURES
2 .1
2.2
2.3a
2.3b
2.3c
2.3d
2.k&
2.4b
2.4c
2.4d
2.5a
2.5b
2.5c
2.5d
2.6a
2.6b
2.6c
2.6d
2.7a
2 .7b
2.7c
2.7d
2.8a
2.8b
2.8c
2.8d
Stresses Due to a Single Rock Bolt--- — ______
Comparison of Stresses with Failure Criterion________ ._____
Joint Influence Diagrams for Case (SlAl) - Horizontal
Joint------------------------------------------------------Joint Influence Diagrams for Case (SlAl) - 30° Joint_______
Joint Influence Diagrams for Case (SlAl) - 60° Joint_______
Joint Influence Diagrams for Case (SlAl) - Vertical
Joint-------Joint Influence Diagrams for Case (S1 A 2 ) - Horizontal
Joint------------------------------------------------------Joint Influence Diagrams for Case (S1A2) - 30° Joint------Joint Influence Diagrams for Case (S1A2) - 60° Joint____ 27
Joint Influence Diagrams for Case (S1 A 2 ) - Vertical
Joint— ---------------------Joint Influence Diagrams for Case (S1A3) - Horizontal
Joint------------------------------------------------------Joint Influence Diagrams for Case (S1A3) - 30° Joint______
Joint Influence Diagrams for Case (S1A3) - 60° Joint______
Joint Influence Diagrams for Case (S1A3) - Vertical
Joint---------------------------------Joint Influence Diagrams for Case (S3A2) - Horizontal
Joint------------------------------------------------------Joint Influence Diagrams for Case (S3A2) - 30° Joint-----Joint Influence Diagrams for Case (S3A2) - 60° Joint_____
Joint Influence Diagrams for Case (S3A 2 ) - Vertical
Joint-----------Joint Influence Diagrams for Case (S3A3) - Horizontal
Joint Influence Diagrams for Case (S3A3) - 30° Joint----Joint Influence Diagrams for Case (S3A3) - 60° Joint----Joint Influence Diagrams for Case (S3A 3 ) - Vertical
Joint------- ------------------------------------ ----------Joint Influence Diagrams for Case (L2A1) - Horizontal
Joint----------- — ------------------------------------ ----Joint Influence Diagrams for Case (L2A1) - 30° Joint_____
Joint Influence Diagrams for Case (L2A1) - 60° Joint_____
Joint Influence Diagrams for Case (L2A1) - Vertical
Joint__________
vi
19
20
21
22
23
¿k
25
26
28
29
30
31
32
33
34
35
36
38
39
1^2
42
43
k4
2.9a Joint Influence Diagrams for Case (L2A2) - Horizontal
Joint---------------------------------------------1+5
2.9b Joint Influence Diagrams for Case (L2A2) - 30° Joint-----1*6
2.9c Joint Influence Diagrams for Case (L2A2) - 60° Joint-----1*7
2.9J Joint Influence Diagrams for Case (L2A2) - Vertical
Joint— •---------------------------------------------------1*8
2.10a Joint Influence Diagrams for Case (L2A3) - Horizontal
Joint— ---1+9
2.10b Joint Influence Diagrams for Case (L2A3) - 30° Joint--- 50
2.10c Joint Influence Diagrams for Case (L2A3) - 60° Joint---51
2.10d Joint Influence Diagrams for Case (L2A3) - Vertical
Joint--------52
2.11 The Rock Load--------------------- •------ ---------- :-------53
2.12 Required Ultimate Strength for Rock Bolt Support Scheme-5I*
3.1 Plastic and Elastic Zones------------------------------ ■
---67
3.2 Plastic Stress Criterion----------------------------------68
3.3 Peak and Residual Strength---------------69
3.4 Equilibrium Diagram of anInfinitesimal Element-----------70
3.5 Mohr Circle andFailure Characteristics 4>r»Cr , and <J>p, Cp 71
3.6 Mohr Circle and Failure Characteristics <|>r> Cr , and <}>p, Cp 72
3.7 Mohr Circle and Failure Characteristics <|>r ,C r , and (j>p, Cp 73
3.8 Mohr Circle and Failure Characteristics <f>r »Cr , and <J>p, Cp 7I*
3.9 Radius of Destressed Zone---------------------------------75
3.10 Radius of Destressed Zone---------------------------------76
3.11 Radius of Destressed Zone---------------------------------77
3.12 Radius of Destressed Zone----------78
3.13 Radius of Destressed Zone---------------------------------79
3.11* Radius of Destressed Zone-----------------------80
3.15 Effect of Rock Bolts on Stresses---------81
3.16 Effect of Rock Bolts on Stresses--------------------------82
3.17 Effect of Rock Bolts on Stresses--------------------------83
3.18 Effect of
RockBoltson Stresses-------------------------8U
3.19 Effect of Rock Bolts on Stresses--------------------------85
l+.l Typical Wave Forms for Direct Transmitted Ground Shock
from Explosions---------------------------------------------- 10U
h.2 Model for Rigid Body Analysis------------------------------- 105
1+.3 Rock Bolt Tension and Plate Pressure Variation with Time— 106
l+.U Momentum per Unit Area----------107
U .5 Additional Energy in a Rock Bolt under an Initial Tension
T as a Result of Elastic Stretching------------------------108
1+.6 Plastic Yield Energy Absorption by the Rock Bolt----------- 109
vii
NOTATION
Angle between wave front normal and wall normal
%+V
% +*r/2
Function of t^ and tg (eq h-22)
-
Kinetic energy
erotal-
energy associated with area A of wave front
er * -
Proportion of energy associated with motion perp. to tunnel
eg« -
Proportion of total energy associated with motion parallel to
tunnel
er
Proportion of er * that is not absorbed by the rock, or reflected,
thus which goes to the rock bolts
-
erg -
Maximum energy that can be absorbed by rock bolts
es
Proportion of er ' that is not reflected or absorbed by rock and
therefore is
directed to the supports (same as er if supports
are rock bolts)
-
e0 ’ -
Maximum value of er ' that can be withstood by a tunnel without
support
eQ
e •' per unit area; = eo '/s^ for rock bolts spaced s feet
-
<j>p -
Peak friction angle
<j>r
- Residual friction angle
p
- Mass density
o
- Stress of elastic wave
ar
- Radial stress
<jg
- Tangential stress
Og
-
a_s
-
Bolt stress increment due to blast
Initial bolt stress
viix
Stress tensor
Tij
c
Increment of strain to reach yield in a rock holt under initial
strain
Polar coordinates
Transformation tensor-direction cosines between xyz, and x'y’z'
axes
Area
Cross-section area of rock bolt
Constant = 8q / i;
Constant defined by equation (5-*0
Residual cohesion
Peak cohesion
Phase velocity
Phase velocity of rock bolts
e
Strain
E
Elastic modulus of bolts
F
Force of rock bolts necessary to prevent any displacement
k
Constant - see p. 78
K
Constant that is determined by boundary conditions
K
Constant - see p. 80
1
Length of rigid bodies in chapter 3 } length of rock bolt in
chapters H and 5
M
Mass
-y
M
Momentum vector per unit area
%
Component of momentum vector parallel to tunnel wall
Component of momentum vector perpendicular to tunnel wall
n
R/(tdC)
ix
p
-
Hydrostatic pressure (external) due to rock stress or external
loading
Pg
-
Average internal pressure on wall of tunnel due to bolting
R
R
o
-
Value of r at elastic -
-
Radius of tunnel
R
S
T
- Range —
-
plastic boundary
the distance to the blast point
Spacing between rock bolts on a regular pattern
Initial bolt tension
AT
- Bolt tension increment due to blast
t„
B
- Transit time of stress wave in rock bolt
t
td
-
CB
Rise time of velocity pulse
Duration of positive phase of velocity pulse
U
-
Particle displacement
V
-
Particle velocity
V'
- Particle velocity after impact (in rigid body analysis)
Xrb
- Area under rock bolt stress-strain curve up to maximum allowable
stress
x
CONVERSION FACTORS, BRITISH TO METRIC UNITS OF MEASUREMENT
British units of measurement used in this report can be converted to
metric units as follows:
Multiply
Bj1
To Obtain
inches
2 . 5 1*
centimeters
feet
0.3 0 U 8
meters
cubic inches
16.3871
cubic centimeters
pounds
0.^5359237
kilograms
pounds per square inch
0.070307
kilograms per square
centimeter
pounds per cubic foot
16.0185
kilograms per cubic
meter
inch-pounds
0 .0 1 1 5 2 1
meter-kilogr ams
inches per second
2 5
centimeters per second
.^
xi
CHAPTER 1
INTRODUCTION
In previous work, blast loading was approximated by a static
pressure, i.e., dynamic effects have been ignored.
bolts, and with tunnel liners has
Support with rock
been considered in particular
analyses; in addition, some basic analyses of rock bolt action were
pursued to gain an understanding of their action as structural
elements.
All work has been in the framework of the Piledriver test,
that is, the underlying motive has been to obtain means for analyzing
rock performance in this test.
In this report, background gained in previous studies has been
brought to focus on the question of how to assign design parameters to
structural supports in tunnels subjected to static or dynamic loads.
First, the action of systematic bolting patterns is analyzed in
variably jointed rock masses assuming that elastic theory can be
applied.
Then the case of systematic rock bolting of tunnels with a
"destressed" or "plastic" zone contained within an enveloping elastic
rock mass was considered.
These first two approaches consider only
static or quasi-static loadings.
The next approach attempts to
consider the dynamics of the support problem under impulsive loading.
Some of the ideas presented herein have not been tested in actual
experiments and this must be left to future studies to validate this
approach.
The dynamic analysis presented is based on energy considera­
tions and could be applied to tunnel liner design with some modifications.
Finally, the energy formulations are used to develop an empirical
equation for dynamic design of tunnel supports and evaluates the
constants of the equation from the results of the Piledriver test.
CHAPTER 2
AN ELASTIC APPROACH FOR DESIGN OF PATTERNED ROCK BOLT SUPPORTS
UNDER STATIC OR QUASI STATIC LOADING
2.1
APPROACH
The first uses of rock bolts were as dowels —
passive
reinforcement in which the yield force of the bolts is available
as a reaction to rock load after approximately a tenth inch of
rock movement.
Then pretensioning was added to bring the bolts
into their working range without additional rock movement.
Many
convincing demonstrations and models entice the designer to specify
pretensioning but as yet there is no true understanding of rock
bolt behavior.
Present design approach is generally based on
previous experience without a rational scheme for selecting the
principal parameters —
rock bolts.
length, spacing, prestress, and size of
Three theories have been advanced to try to explain
rock bolt action and to guide its design as rock reinforcement.
First, in laminated rock, the bolt stress is thought to increase
interlayer shear strength, thereby stiffening the roof into a load
carrying beam.
Second, the radial confinement that is offered by
the average pressure supplied by the bolts raises the strength of
the rock around the gallery.
Third, that rock bolts are depicted
as passive members preventing large deformations from destroying
the keying action of joint blocks.
Rock bolts are installed in the inner surface of an excavation
carved in an initially stressed body.
3
At the time of installation
the stresses around the excavation approach the final values for
an unlined tunnel.
Depending on the initial stress field, joints
in the rock, and the manner of excavation, the prebolting stress
state may approach the applicable elastic solution, eg. the Kirsch
solution for a circular tunnel, or may contain a destressed zone
of permanently deformed rock.
Some rock blocks fall out during excavation of the gallery or
remain suspended in a delicate equilibrium.
Other blocks become
partially detached from the rock mass but remain entirely stable.
After installation of the rock bolts, the stress state may be
radically altered, as the bolts are tensioned to become active
structural partners with the rock.
Finally, the rock in service
comes under additional live loads imposed by operation of the
gallery and the stiffness of the remaining steel exercises a passive
resistance against further rock movements.
The proportion of the available steel area that should be
assigned to the contrasting active and passive roles depends on the
combination of geological conditions, prebolt installation stress
state, and post installation live loads.
Each gallery is unique
and one cannot hope for a universal design.
By combining solutions
to the relevant components of the total stress field and introducing
an appropriate criterion of failure, it is possible to compare the
relative merits of trial rock bolt designs.
The individual compo­
nents of the final stress state are the stresses imposed by the
anchor and plate of each rock bolt, the prebolting stress field
1
I
I
around the tunnel, and the stresses imposed by live loads.
I
slippage of rock blocks along jointing planes.
I
I
I
I
Ia
a
a
8
I
I
I
I
I
The
criterion of failure most appropriate to use is that describing the
Since the behavior of
jointed rock is nonlinear, and the installation is sequential, no
linear, elastic, one-step analysis cam reproduce rock bolt action.
Initial efforts to represent rock bolts in finite element analysis
were disappointing.
Success is now being achieved using incremented
loading techniques using finite element programs which model joints
and bedding planes and which represent the excavation and construction
sequence.
Still something may be learned from elastic solutions as
demonstrated below.
2.2
GLOBAL STRESS FIELD AROUND THE TUNNEL - ELASTIC BEHAVIOR
Many publications give stress fields about galleries subjected
to various load conditions.
Exact solutions are available for
idealized tunnel shapes in isotropic and orthotropic plastic materials,
as well as for isotropic elastic-plastic materials.
Heterogeneous
materials and complex tunnel shapes have been studied by photoelastic
techniques, as well as by use of the finite-element analysis.
For
the purposes of this discussion, the starting point has been the well
known Kirsch solution (Ref. l) giving the stress field about a cir­
cular gallery excavated in an initially stressed, linearly elastic,
homogeneous and isotropic medium.
Simulation of the loads imposed by the rock bolt is achieved by
superposition of the stress fields of two co-linear point loads, one
5
a surface loading representing the bolt bearing plate, the other an
interior point loading representing the rock bolt anchor.
The first
point load solution is the familiar Boussinesq problem (Boussinesq,
1885 ); the second solution vas developed by Mindlin (1963 ).
If
desired, a more exact simulation could be achieved through the
superposition of a surface plate loading solution and an interior
point load solution.
Investigations have shown that for points of
interest removed from the immediate vicinity of the ends of the
bolt, use of the point load solution is sufficient.
Ewoldsen
(Ref. 2) evaluated the error involved in using point loads on a half
space to represent rock bolts on the wall of a circular tunnel.
In
effect the circular wall is being replaced by a series of planes
normal to each bolt.
For an 8 bolt ring, of 10,000 pound preloaded
bolts in a tunnel 16 feet in diameter, the maximum error is of the
order of 0.5 psi.
The form of the stress component expressions resulting from
superposition of the two point load solutions is:
= P * f (Xi, L)
(2-1)
Where:
P = bolt loading
Xi
= coordinates of the point of interest referenced to the
bolt axis
^
L * length of bolt
ta
Thus for an assumed bolt length, the stress field components
for a given bolt load may be obtained by multiplying previously
6
I
I
i
I
computed unit bolt load stresses by the given loading.
Examples
of single rock bolt stress components are given in Figure 2.1.
In order to ascertain the global stress field existing around
I
the rock bolted tunnel, it is necessary to reference all stress
I
components from individual bolts must be summed, and added to the
I
y-v.
I
1
1
1
M
I
I
I
1
fields, tunnel and rock bolt, to a global coordinate system.
Further,
existing tunnel stress, at every point of interest in the global
coordinate system.
In the present example bolt stresses are initially referenced
to a cylindrical coordinate system whose axis is coincident with
the bolt axis.
These bolt stresses are transformed through the use
of a second rank tensor transformation into components referenced to
the cylindrical tunnel coordinate system.
Tkl x AkiAlJTij
Where:
Amn « direction cosines between the two coordinate systems
k,l refer to tunnel coordinates
ij refer to bolt coordinates
Knowing the location and orientation of each bolt with respect to
the tunnel coordinate system, the stresses due to single bolts may
be summed since we are dealing with a linearly elastic, isotropic
medium-.
This summation is accomplished by first finding the location
of the point of interest with respect to the individual bolt coordi­
nate systems.
This location will vary as the position and orientation
I
7
I
I
of each bolt with respect to the particular point is, in general,
not uniform.
of
As the bolt stresses decrease radially as a function
1/r2 or greater, it is in general only necessary to consider
f
I
bolts lying within a 30° cone around a radial line from the tunnel
centerline through the point of interest.
The transformed stress
components at the point contributed by the several bolts are then
summed.
N
n
“ stress at a point due to n**1 bolt
1
H = total number bolts considered
The resultant multiple bolt stress field is then added to the
existing tunnel stress field.
Tkl
* Vi
+Tkl
(2-4)
total
KXtunnel
xrock bolts
The final transition to the desired global coordinate system is
accomplished through another second rank transformation.
Trs * ^Ltk.As l \ l
(2-5)
From this point, examination of the effects of the rock bolts under
various failure criteria is easily accomplished.
2.3
I
I
I
Where:
Tkl
1
THE EXTENT OF THE SLIP ZONE
The criterion of failure adopted should reflect the way in
which the tunnel would behave if there should be no reinforcement.
In hard rock, the usual failure mode involves the relative movement
8
I
I
I
i
I
I
1
i
I
1
1
I
I
I
t
I
I
I
I
I
I
1
I
I
I
i
1
of blocks bounded by structural surfaces such as joints or bedding
planes; therefore, in the illustrations presented here a criterion
of failure has been selected in which the shearing strength of
geological weakness planes is the sole consideration.
portrays the failure criterion —
Figure 2.2
a linear mohr envelope characterized
by a cohesion and an angle of friction but with no tensile strength.
Any stress field can be examined with such a failure criterion if
the orientations of weakness surfaces are specified.
Examining each point around the tunnel in turn, it is possible
to identify the loci of points having a factor of safety of 1; any
weakness surface of the given orientation passing through the locus
will be critically stressed.
Thus the whole region around the tunnel
is subdivided into subregions within which weakness surfaces of the
given set are either over-stressed or under-stressed according to
the failure criterion.
Actually no rock can be "over stressed" as
the elastic stress distribution must give way to one which is
everywhere acceptable.
The scheme pursued here is simply a calcula­
tion method making use of elastic stress distributions to estimate
the maximum extent of rock requiring support.
Figure 2.3-2.10
gives examples of such charts, which can be considered as joint
influence diagrams to allow examination of the relative influence
of weakness planes at different positions near a tunnel.
2.1+
CALCULATION OF ROCK LOADS
Gravity urges the rock within the over-stressed subregions to
drop into the tunnel.
An upper bound to the rock loads is therefore
9
I
I
calculated by establishing the mass of rock within the joint influence
areas.
Above the tunnel, side restraint does not appreciably reduce
this load, whereas in the tunnel walls, the residual shear strength
along the joint orientation considered partially offsets the rock
load.
Figure 2.11 illustrates the principle of calculation.
The
I
1
I
rock bolts should be anchored behind the farthest extent of the
influence region.
To provide an upper bound to the rock load per
bolt, it is calculated here as simply the wall area per bolt times
the maximum extent of the slip zone for any joint.
2.5
THE PRINCIPLE OF THE DESIGN METHOD
The object of the design is to achieve an optimum reduction of
the influence volume through prestressing the rock bolts, always
allowing sufficient reserve steel area to support the rock load with
the required factor of safety.
The following information must be known:
1.
The diameter of the tunnel
2.
The preferred orientation of each set of planar weaknesses
3.
The cohesion and friction angle for each set of discontinu­
I
I
8
8
8
I
8
ities
h.
The initial principal, stresses near the tunnel
In seeking an optimum design, trial rock bolt parameters are
selected.
The object is to specify the following parameters of the
rock bolts:
10
ft
1
I
I
8
I
I
I
I
.^
I
I
V
I
I
I
I
I
t
I
I
1
1.
Lengths
2.
Spacings
3.
Yield force
U.
Pretension force
Each joint set can "be analyzed separately.
tension loads are low or absent, a relatively large slip volume will
exist and steel dowels sufficient to hold hack this mass of rock
will have to he provided.
By tensioning the rock holts, the mans of
rock to he restrained is reduced.
It is usually desirable in design
against static loads to avoid yielding the rock holts:
the rock mass
may suffer deterioration if allowed the several inches of inward
movement a rock holt of common dimensions will sustain in yield.
By associating costs with the emplacement of rock holts, the
cheapest acceptable design can he found.
A computer program was
employed to cumulate the global stresses, apply the failure criterion
at selected points, and plot the influence regions from which the
costs of each trial design can he calculated.
The solutions are
three dimensional and arbitrary joint orientations can be considered
as well as imbalanced rock holt patterns.
An example will illustrate
the method.
2.6
ILLUSTRATIVE EXAMPLE
A tunnel 16 feet in diameter is to be excavated at a point where the
initial principal stresses are 1000 psi horizontally and 333 psi
I
I
If rock holt pre­
11
vertically.
The rock is divided by cohesionless Joints having a
friction angle of 50°.
Establish the rock bolt design parameters.
Several trial designs are selected as listed in the four left
columns of Table 2.1, Part 1.
The Joint influence diagrams for each
of the eight cases are presented in Figures 2.3-2.10.
In these
figures, "2” denotes the position of a rock bolt, while "1" denotes
a position inside the slip zone.
(In cases S1A1 and L2A1, to save
computation time, bolts were included only in the region affecting
stresses in the upper half of the tunnel.)
The working loads for
the bolts are the sum of the installed tension and resistance for the
rock load, whose maximum value per bolt is calculated from the height
of the biggest slip zone.
For the example cited, Table 2.1, Part 1, the use of low tensions
and wide spacings is cheapest (S1A3); however the large extent of the
slip zone is dangerous for the eight-foot bolts.
would be more reasonable.
Twelve-foot bolts
Table 2.1, Part 2, is for the initial
principal stresses vertically; in this instance, the eight-foot bolts
are too short unless a very close pattern is used.
Table 2.1, Part 3,
is a similar computation where the tunnel is to be subjected to a 5 g
blast acceleration in the horizontal direction.
The basic idea is restated in Figure 2.12.
As the bolt tension
is increased, or spacing reduced, the bolting pressure is increased
and this has the effect of reducing the rock load (curve A).
Since
the rock load reduces the precompression supplied by the bolts to
12
the elastic zone, the volume of broken rock will enlarge unless
the bolting capacity is increased by an amount equal to the rock
load.
The required supporting strength curve (B), the sum of
rock load and bolting pressure, displays a minimum.
(The economic
minimum, however, may be situated differently.)
Prejudices concerning the style of rock bolt installations can
emerge from extensive calculations of the above sort.
This, however,
is not the intention here, but rather the presentation of a particular
train of logic.
the results.
Obviously, the details c m be changed and with them,
The tunnel may be loaded by high or low pressures,
before or after rock bolt installations.
The shape need not be
circular, the bolts need not be radial, and the design need not be
symmetric.
Instead of mathematical solutions, the stress fields can
\
be summed from finite element results.
The criteria of failure
can represent a continuous material about the tunnel rather than
ubiquitous Joints.
Only the sequence of logical steps is at issue.
The bolting scheme is pre-stressed to keep the zones of potential
rock fall from growing too large.
But it must also have additional
untapped strength equal to the load of rock zones that tend to move
into the opening.
Finally, the bolts must be long enough that their
anchors be well behind the slip zones.
2.7
CONCLUSION
The designer of a rock bolt reinforcement scheme has several
options.
He can install ungrouted, untensioned rock anchors;
13
continuously grouted, untensioned reinforcing rods ("Perfo 'bolts");
or highly pretensioned bolts with or without protective grouting.
Prestressing tends to minimize the rock load by altering the stress
field around the gallery and by preventing rock deformations.
In
the illustration presented which was based on an "elastic analysis",
significant reduction of the rock load by increasing the prestress
could not be demonstrated until the average wall pressure exerted
by the bolt pattern reached a significant percentage (about 10?) of
the initial rock stresses (Table 2 . 5 ).
in certain classes of problems.
This can be attained only
A significantly lower threshold
pressure for rock load reduction by bolting is being obtained using
"nonelastic" solution methods where a degree of deformation is
tolerated.
These studies are reported in the next section.
It is
interesting to note that only the average rock bolt pressure and not
the length, and spacing of bolts seems to affect the extent of
reinforcement achieved (Table 2 .1+).
Ihe design approach offered here, which is an elastic analysis,
can be summarized as follows.
estimated.
for reaction
The maximum extent of rock fall-in is
Applying the design acceleration, a total force required
c m
be computed.
If this is quickly applied by a rock
bolt installation, the full extent of the slip zone may not have time
to materialize, and the reinforcement system may be overdesigned.
If
the function relating the slip zone volume to the bolting pattern is
determined, it is possible to balance the reinforcement scheme.
Ik
A large percentage of the cost of a rock holt surrounds the
drilling of the hole, the setting of the anchor, and tensioning
and grouting •
The cost of a large bolt is therefore not much
greater than the cost of a small bolt, and it would seem the
cheapest solution to supply the full required reaction force with
a small number of large capacity bolts.
However, the results of
this elastic analysis suggest that the mechanism of failure may
involve local movements that could occur between the bolts of a
coarse pattern.
Thus the best design is a matter requiring geologic
and engineering analysis.
The enormous differences in reinforcement
costs according to the scheme adopted demand that rational effort
be made to design the rock bolting installation.
15
Table 2 . 1 Economic Comparison of Rock Bolt Design; Free-field Rock Stresses: pi = 1000 psi, P2 — 333 psi. 16 foot diameter, circular tunnel, rock
weighs 170 pounds/cubic foot; friction angle of joints = 50°.
Trial
design
N o.
Bolt
length
(feet)
Bolt
tension
(pounds)
Bolt
:spacing
(feet)
W all area M ax. height of joint slip zone (feet)
from horiz. (°)
per bolt joint inclination**
(feet2)
0
30
60
90
Maximum W orking
Rock load load per
per bolt bolt required
(pounds) (pounds)
Bolt feet Bolt ring Bolting
Selected
ring
cost
1Rock bolt Installed
foot
cost per
(lineal oper
diameter bolt
f tunnel $/foot
$/foot
feet)
(inches)
1. Pi horizontal/ 1 g vertical
384 0.950 912
2.50
18,100
DJa
100
0.0
0.0
0.0
1.1
0.5
18,000 1.05
SI A l
8
256
192 0.475
2.80
21,000
3U
3,000
1.0
4.0
0.0
4.4
2.0
S1A2
8
18,000 2.10
74
0.238
96
3.25
30,100
Vs
12,100
0.0
1.0
4.0
17.7
2.0
4.20
18,000
S1A3
8
420
0.475
192
65,400 1-* la 4.60
400
0.0
0.0
0.5
0.5
4.4
S3A2
8
65,000 2.10
105
96 0.238
74,000 U / s 4.60
9,000
0.0
3.0
2.0
17.7
2.0
S3A3
65,000 4.20
8
2,371
0.950
768
3.25
36,100
Vs
100
0.0
0.0
0.5
1.1
0.5
1.05
L2A1
36,000
16
593
384 0.475
39,000
Vs 3.25
3,000
0.0
4.0
1.0
4.4
2.0
L2A2
16
36,000 2.10
174
0.238
192
3.80
1
48,000
12,000
1.0
4.0
2.0
2.0
17.7
L2A3
16
36,000 4.20
2. p1 vertical, 1 g vertical
384 0.950 912
18,100
Vs 2.50
100
0.0
0.4
0.0
0.5
1.1
S1A1
8
18,000
1.05
192 0.475 257
24,000
V* 2.80
6,000
0.0
4.0
2.5
8.0
4.4
S1A2
8
18,000 2.10
87
96 0.238
3.80
1
40,200
1.0 24,200
4.0
2.5
8.0
17.7
S1A3
8
18,000 4.20
420
0.475
192
4.60
65,400
l-Vs
400
0.0
0.0
0.0
0.5
4.4
S3A2
8
65,000
2.10
151
96 0.238
89,200 l-*/a 6.60
1.0 24,200
4.0
3.0
8.0
S3A3
17.7
8
65,000 4.20
2,371
0.950
768
3.25
36,100
Vs
100
0.5
0.5
0.5
0.5
L2A1
16
1.1
36,000
1.05
3.80 384 0.475 694
1
42,000
6,000
0.0
4.0
3.0
8.0
4.4
L2A2
16
36,000 2.10
210
192 0.238
4.60
60,200 1-V»
1.0 24,200
4.0
2.0
8.0
17.7
L2A3
16
36,000 4.20
3. p1 horizontal, 5 g horizontal
384 0.950 912
18,500
Vs 2.50
500
0.0
0.4
0.0
0.5
S1A1
8
1.1
18.000
1.05
346
192 0.475
3.80
1
48,000
30,000
0.0
4.0
2.5
S1A2
8.0
8
4.4
18,000 2.10
192
0.238
96
1.0 121,000 139,000 1-V* 8.40
4.0
2.5
8.0
8
17.7
S1A3
18,000 4.20
420
0.475
192
4.60
67,000 l-J/8
2,000
0.0
0.0
0.0
0.5
S3A2
8
4.4
65,000 2.10
96 0.238 234
2 10.20
1.0 121,000 186,000
4.0
3.0
8.0
8
S3A3
65,000 4.20
17.7
0.950 2,371
768
36,500
Vs 3.25
500
0.5
0.5
0.5
0.5
16
36,000
1.05
1.1
L2A1
820
0.475
384
4.60
66,000
l-J/8
0.0 30,000
4.0
3.0
8.0
4.4
16
36,000 2.10
L2A2
384
0.238
192
8.40
157,000
1-»/«
121,000
1.0
4.0
2.0
8.0
17.7
16
36,000 4.20
L2A3
* These calculations are based on the joint influence diagrams in Figure 4 which were computed for pi horizontal. But by a simple rotation, they
can be used for the case pi vertical, or in any other orientation.
.
** Angle listed is the trace of the joint across the tunnel section. If the real joint planes do not strike parallel to the tunnel axis, their in uence
areas will be smaller than the ones shown.
Table 2.2
COMPARISON OF ROCK BOLT DESIGNS
I.
Design No.
Effect of changing spacing at constant
rock bolt wall pressure
Average Rock Bolt
Wall Pressure
(psi)
Spacing
(feet)
Maximum Rock Load
in Feet of Rock
Case 1
Case II
Case
S1A2
28
2.1
4
8
8
S3A3
26
4.2
4
8
8
S1A1
114
1.05
0.5
0.5
.5
S3A2
103
2.10
0.5
0.5
.5
*
Calculated on basis of wall area.
Tunnel diameter is 16 feet.
Table 2.3
COMPARISON OF ROCK BOLT DESIGNS
II.
Design No.
Effect of changing rock bolt wall pressure
Average Rock Bolt Wall
*
Pressure
(psi)
*
(%PX)
Maximum Rock Load
in Feet of Rock
Case I
Case II
Case
S1A3
7
0.7
4
8
8
L2A3
14
1.4
4
8
8
S3A3
26
2.6
4
8
8
S1A2
28
2.8
4
8
8
L 2A 2
57
5.7
4
8
8
S3A2
103
10.3
0.5
0.5
0.5
S1A1
H4
11.4
0.5
0.5
0.5
L2A1
227
22.7
0.5
0.5
0.5
Calculated on basis of wall area.
Tunnel diameter is 16 feet.
I
LO AD
1 0.0 00 PO U N D S;
LEN G TH
10 FEET; TENSION PO S ITIV E .
T
o -H
r
i
TENSION
SHEAR FAILURE
BOTH
UNSHADED REGION REPRESENTS NEITHER
TENSION NOR SHEAR FAILURE
FIG.2.2 COMPARISON OF STRESSES WITH
FAILURE CRITERION.
After Duncan and Goodman (1968)
*0*0
i
1
min
1
J
}i
iu in
U n i
1111
n
n 11¿1211
U'12
inn
.
.2
2
2
•¿i
¿121211 n
n n li nn
? i¿i
n i n i
12*
i u u
?.
m u
.2
•*
2«
.
.2
..
inn
n.
ii ii
ii ii
m
mi n mi un i
i 11n n u ii m i
n in n u i nn n i i i
i i i u mi m u n i v i
u n i i n i i n n n n m un ni i ii i nni
i
i i
ii
i
inn
40
7 r a Cl
Ju IfjT s
,
ANuLF OF NORMAL WITH Y
axis
= 9 0 . 0 S EC T I ON s ~ 0 ,
>1 A l
Figure 2.3a
Joint Influence Diagram for Case (SlAl) - Horizontal Joint
21
.
I
I
I
I
I
I
I
I
c
I
I
I
K
I
«
i
i
(
i
.•¿.?U^l?i21]
?i*u
121
<
i
l?
ii
?A
•?
i
1
1
2. 1
4
4
?•
2
•••4
(
11 J?
.1 1 i
m
?!
¿1
n
4
*•
.2
a
a
li i
1111
n iiu n
mi
u li
ii n i
a
a
.o
T^Ce.
J'vI'J!
; i<M' ial
v l I fi
i
h«: i i
-
gy, u
ACTION
--o#
SI l
Figure 2.3b
Joint Influence Diagram for Case (SlAl) - 30° Joint
22
I
I
21^1
.2#2
121
•2 -
2.
••
i i
i nn
?1
m i
12
i i i
n
11
21
1
21
i
21
2
1
..••2
1
1
<L
1 12
] 1 1
¿1
1 111
min 1 21
m i l 1111
i i 1 111
n nu
••
.2
• •1
1•«
40.
4u.o
TRACc.
of
Jol'll
=
>)}■
Y AA1S
= yO • u S E C T I O N
"-O*
S 1a 1
! Figure 2.3c
Joint Influence Diagram for Case (SlAl) - 60° Joint
23
\
*
<H).U
. 2.2
*•2m2• ¿•2.2..
2.¿-
.2.
?.
12
U
2.
11
12
21
12
1
12
?
1
21
1
21
2
1
»?. ...
2
2
12
21
1
1
21
U
21
.2
•••
....
••••
. . . .
......
i
0*0
u
T f í ACt
SI Al
r'F
JOI NT
= ^ . ‘y A,( )|J'
<)K (J')Rm a L
-»l íH
Y AXI S
=
S E C T I ON =-Q •
1
Figure 2.3d
Joint Influence Diagram for Case (SlAl) - Vertical Joint
2k
1
i
1 11
i i
1
il
! I•
I I i ) ii¿il; li 1 .i «•l1'•• i
il i i • .2
•
l
i l i
i 1. 2 • 1 1 1 1 1
1.2*t..lI l 111I 1l1 i11 1
?.
i n
i
U
11 1
i
•
I
«
.2
i 11
•2
*
l.l
1..
1 i i
! I
•
i.¿* n
M i l l
1 1 1 Al 1 1 . 2 . 1
\
1
i 111 1 1 * ’l - ^ . l <r 1 . 2 . 1 . 1 X 1 11 1
1• 1• 1
• 1 • !1 i
li
i
i i li
1] 1 l ‘
il
1
t
•
4(
-*+ ••n
HK Jv> i i J' S 1 i* 2
A i Mj !..
IA) K¡., L
;Î
TH
Y
A U : i
=
4^.0
S EC TIO N
=“ 0
•
Figure 2.Ua Jo in t Influence Diagram fo r Case (S1A2) - H orizontal Jo in t
25
x •
\
\
1 1 1)
••¿»•if •11.2*1 1
A.I
2. 1
1.1 1
.2
••
1
•?
.
2
••
1
11
1
1
1. 11
.Il
?•
2
11 £ '
11 I*
1 11
11121
1 1.1
!
.
..'
.2
2*
.2
1. 1
.... 2*1
1.1*^*1 *■ ..2«.
1.1 i.i.i
111
.0
T‘-?a L
4D
l
Of-
JOi'l!
Figure
4!>inLh
2 . kb
Of
NJK-' AL
<ITH
Y AXij,
»
SECTION
=" 0 .
Joint Influence Diagram for Case (S1A2) - 30 Joint
26
'O . U
*2••
1*¿* 1
M n
i
?. 1 i i i
.2
i. i n
i. i
• *
ii
2« 1 1 1
»2
Al
U
Ì
?.
1
1
i
i •
11 i.
1 i
11
i ?A
1
1 11
1 i
.2
1 .1
). \ .2
1
i 1.1
11 . 2.1
.
.2••«
•
o
-'+Ü
TNACL
40
of
jo
X fJT = f
A-JOLH OF N O H ^ a l
v ITH
Y A X l * Ä g O . ü S E C T I O N = **0.
Si..2.
1 Figure 2.he
joint Influence Diagram for Case (S1A2) - 60° Joint
27
.(
n
i i
i
2*
2
.1
l
.
1
}¿
)
► ...
2
I • ¿ # #
40-0
ím
Figure 2.Uà
>
j
3KCTI on
Joint Influence Diagram for Case (S1A2) - Vertical Joint
28
h r..
o
ï
1
1
11 1
?
I l l
1 1
1 1 1 • l . l i . *■. V V . l . l 1
1
1
1 1 .¿.1
)
1 Il
1..1
1
#•
•
Il
1
1
• •
•
• •
*
•3
•
• •
•
•
•
•
•
•
•
1
1
U
1 l
1
1
1
1
1 Ì
Í
A. . 1
11
• •
• •
• •
?..
• •
•
•
•
•
•
,
•
•
•
• •
•
• •
•
•
•
.?
m •
?..
1
• •
•
• •
*
11
1
1
1 1 1 . 1
1
Il
11 . ¿ . 1
1 1
l
1
111
1 1.1 • 1.1
?
1 . 1 , 1 .1
1
1
1
11
1 .1.1
11
11
1
1
•
1
1
1
11
1
1
1 1
1
1
1
11
1
1
1
1
• •
1
1
11
1
1 1
w •
l
11
U
1
X
111
1
l
1
1
1
1
1
11
1
J ,o
T <ACL
40
n.f-
J >!■ T r
.1 i ^ L f
Figure 2.5a
n
ÜOWIAL
wIM
y Axis = VO'V StCTlON * - o 9
Joint Influence Diagram for Case (S1A3) - Horizontal Joint
29
'»■ \ l . I)
• • ••2• •
1
1. .
i 1 11 1. .
11
1 1
i 21
1 1 .1
1 1 .1
1 1.1
.¿.1
•
•
•
•
•
•
•
•
•
•
1
• 1 1 11
U f.1 1 .1 .1 1
1 .4 .
.
A. 1 1
•
1. 1 1
•
1.11
•
1.1
1
•
2. 1 1 1
•'
1. 11
•
. 1 1
•
. 1
•
.
•
•
•
«
•
•
•
»
•.
•
.
•
.2
•
••
•
.•
«
.
1 ^
i.i.i
1 A A
■9j#0
TWACt.
S]AJ
of
JOINT = 3i:.‘ AN^L.I- <)F N O H M a L WITH Y AXIS s 9^.0 SE CT I O N *-f).
Figure 2.5b Jo in t Influence Diagram fo r Case (S1A3) - 30 Jo in t
30
h
l.<* 1
M H li 1
1.111 1
ì« 1 11
t. 1 11
2. 1 1 1
11 U
1
il I.
Ili
11 i 21
l 11 1 •!
1 1 1 1 .1
1
-4
i
1
11*1
11 . ¿ . 1
;•. o
1-i-.L'.
4(
J J l '1
•f.u -, I f H
r ^Àis
= V' J . U
SFC r Tou - - c .
Figure 2.5c Joint Influence Diagram for Case (S1A3) - 60 Joint
31
40 . Ü
-
40.0
SI AJ
] Figure 2.5<1 Joint Influence Diagram for Case (S1A3) - Vertical Joint
32
I
\
» f l ))
0
j i
>4390
a
> O O '> o ^ ® ° i ■» a » 8 a j o «
©
i
l l,UlUloll.Ul i
II
l
alol
o
l«lo
lili
val
o
l<
l Ï
U I
1
i
1
>0 0 0 9 0 3 0
» 0 0 0 3 13399 0 0 0 9 0 1
I I) O 3 9 © 'J 0 0 0 9 9 0 t f © © © © 0 0 l
* oo r
1
l l
l l U
1 I I{
l
I
1
1
1
V
11
« o
O *
oo
3
9339
9999090
oo
O
3 9 9 0 0 0 0 0 9 9 9 0 9 0 0 0 0 00 * 5 O 0 0 0 0 0 0 0 3
*©«3000990
©O© 9 0 0 0 0 * ^ 9 0 0 0 0 0 3
• 0 0 0 9 0 0 0 0 9 9 0
®
»0 0 0 0 0 0 0 0 0 9 3 0 0
«
O
«
’
O
9
9
3 9
O
O O
O
O
11
li
1
l
O
°
—4 O 9 O
lo l » l 9 l
i
l
11
9 O 3 3 3
) o 9990000
9 9 o 9 9 3 O ï 'J 9 •
'
lol<
lo lo lo l
lolol
1
* 0 3 3 9 9 3 0 9 ‘3 9 9 0 0 9 9 0 9 9
300"
rn t 7
r)F
J 'H N T
1
>00909009.»3
l
il
> 0 9 9 3 9 0 9 0 0 9 0 3 0 0 9 0 0 0 0 0 0 0 9 9 0 0 0 0
O
- 40„0
T^'Cf:
l H
i
lili
l l l
1
>loi
i
i
9
O
trai F
Of
isjfpM.M
W ITH
Y
A X IS
=
0 0 :>r» S F C . T U Ì N
--0 ,
Figure 2.6e Joint Influence Diagram for Cane (S3A2) - Horizontal Joinj
33
40
1
A^o0 ®9 :
’ ■■»>■» j o o o o o o o o o o o o o o o o o o n o o o o o o o o o o o o o o o o o o a o o o o o o o o o o o o o o o o o a i o o o o o o o o o o o o o o o ' o o o o o
I
1
I
I
I
1
1
1
1
1
1
1
1
1
0
o
o
o
» o o o o l o I® l i ® l e i
sono
®
Loie
o
u
0
1>
1,
1®
1®
1
11
io
o
1
0
0
> 0 9 0 0
:> O 5 * » » 0 5 o -3 n > 0 0 0 9 0 0 0
1
1
U
9 0 0 0 0 0 9 0 0 9 0 0 9 0
9 0 9 9 0 0 9
0 0 0 9 0 0
9 5 oo<
09
9 0 0
9 0 9 0 0 9 9 0 0 0 9 0 0
9 O
lo
0
l
11
9
9 O
1
O 9
0
lo 1
*
lo 1
O
0 9 0 ®
e
O l 9 1 o 1
oo oooo
lo l, i
•»
0
e
0
©
0
0
-'♦no0
- 4 0 „
, ,,
19 0 0 0 9 0 0 9 0
> 5 59 9 O O 1
> 0 9 9
9 9 9 9 -
> 9 0 9 9 9
9 9 0 0
>9 9 0 9 9 -
>9
5 9 0®
0
0
'*p j >nr
!■
‘:».»LC nf NfinMM WIrM Y ^XTS = <-?n,n SECTION =-0,
i Figure 2.6b
Joint Influence Diagram for Case (S3A2) - 30° Joint
3^
9 * 0 9 0 0 0
9 0 9 9 '
4'ìl
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
r
i
i
40o0
L»—
ooooooooooftoaooooooooooooooooooooooooooooooooooooooooeoooooooooooooo
>990000
oaoo• <
oo
0o
O5
oo
1o
»ÓOOOOOOOO
ioloU1 1
lo 1 l l i
lo
il
Ulo i i 1l
Il1 1
O o 9 8 0 ' > 0 l > 0 > 0 î l ' > 0 a 0 0 î 9 0 i 0 4 « * 9 0 « 0 a 5 i > 9 9 l > ( > i » 0 |,> î 9 0 # 0 a i 0 a
O
l
.
1
1*
9
1
1.
o'
*
Il
11
,
1
il
«I
.
i
l 1 1 -9 1
o
l
1.1
9
O lo l
«
• o oaof
1 1
AOo ^
•> o > o ft n i f
9 0 9 0 0 0 9 0999000*:
-40„ o
•yo^r.fi MF JHTM‘T = '/» n ,n
cv ?
o
>00 0 9 0 9 O0 9 0 0 0 0 9 O 0 0 0 0 0 0 0 0 9 0 0 0 9 0 9 9 a
>0090000
»
9 0 0 9 0
«
fïGI T; n F T»RMM_ WITH Y AXIf' = ‘^QoO SECTION =-0«
Figure 2.6c • Jo in t Influence Diagram fo r Case S3A2) - 60° Jo in t
35
40
>00 0 9 0 9 0 > 0 0 0 0 0 0 0 0 0
o » 8 0 0 ' ) ' ) 0 9 ' ) í ( » n o * o j ‘» 0 9 J o > o « i> * ' > « # o # o o ( » 9 ' > 9 ' » o o e * » n * * o « # #
o
®
O
*
O O• O • O«
8 9 4 10 9 0
9 OO «
9 9 0
99
19
• O
«1
lo
lo
9 1
11
1
11
1
0
9 0 3 9 0 9 9 0 0 0 0 9 0 0 0 0 0 0 0 0
1
.
i
1
9
1
*>0 0 9 0 0 0 0 9 9 0 0 0 0 1 ) 9 0 0 0 0 0 0 0 9 0 9 9 9 9 9 9 0 « 0 0 0 9 « 1 ^
i
.
i
1
•
1•
o
lo
o
1
I
i
• i
1
o
11
o
11
o
1
•
9 9
O
OO
9 O
009
• 9 O
0900
9991
>O 9
00 90 99
O
9
O
9
O
9
9
O
^ Oí n
03 » 3 9 3 0 0 9 93 9 9130 0 90 '> 9.1 0 0 0 0 9 0 . 10 0 « > 0 0 0 0 » 0 0 0 9 0 0 « 0 0 ©0 ©0 0 0 0 0 9 0 0 0 9 0 0 0 0 0 0 0 0 0 0 9 0 0 0 0 0 9 1 0 0 0 0 0 0 0 0 0 9 0 0 0 0
-40*0
t r a c
rv?
F
OF
o
JOINT
=
00, 9
A N Gl . F
Figure 2.6d
np
NORMAL
W ITH
Y
AXIS
=
9 O „0
S EC T ION
=r*n.
Joint Influence Diagram for Case (S3A2) - Vertical Joint
36
*
•
•
*
•
•
»
*
»
*
•
»
.
*
»
4
1
*
4
*
«kiil i it
«*
**.••••*•*•¿4»*
i
è
_ . i
k
%
■J
•
__ k
k
k
i
%
ï
__ 3
i. i . J
S l
l
U
r yr r n
ï r v a . v u » i m i l . r .i 1- i ï S
^ ■ ¡ w
I r l i
i i f*ii
ì V n ii.i
l w L 11 \ S i
i\ i
i
l
..
k k .............................
kk
2k
»2
kk
i
m• • 4 k • • • • • • • • • kI
» • • k k k • k • k k • 2 Vk k k k k • • k k • • •
k k
k•
k
k
• k • « k k k • k k' kk • k • k k k k 2 k k • • • k k k k k k k k k k k k k ’k k
k
kk
k
• •
k
•2
2.
i1 «
ÌÌ \
Y. l
iv. i i L ï L
Ì \ 1
Yì
k
ïwfe> li il i Y 1
^ \ 11 ^ \ n \ n S . i ; \ ? i ’. v.yiï i
; ï
1\ \ 1
1
U
V .i-.l it
1
1 V W
i
i
Ì
SVa')
I
T
1
\
1
• k k k '1« rVkkl
1
1
1
1
_1
1
*VÒ.'Ò
TRÀCE n‘r Joint
.
1
1
'I
1
Ì
'*6
s
f(.
ang'l'e
or
norNa'l witn v axis
» $o»o
section
*h-ô.
J o i n t In flu e n c e Diagram f o r Case S3A3) - H o riz o n ta l J o i n t
37
V
40,0
.2..
11H
.lM.l
1
..l.*
•••
1.1
1. 1
1.1 1 _
1. 1 1
2. 1 1 1
1. U
.11
•2
11.
1
11 1 .
11
11
1 21
.2
•.
1 1.1
1 .1
1.1
.2.1
U ill
1.1.1
1 • 1i 1• 1
i*
.•2•
......
<►0.0
•<►0
40
TRACE. OF JOINT = 3a. o AN^Lfc OF NORMAL WITH Y AXIS 3 90.0 SECTION *-()•
S3A 3
Figure 2.Jb
Joint Influence Diagram for Case (S3A3) - 30° Joint
V
1/
40.0
.2..
l.¿» 1
l.U Ï 11
ï. 1 1 1 1
i-, 1 11.
1. 1 1 ï
2. 1 1 1
11 11
1
•'
1
1
• ••
••
••
.2
1
1
1
1
11 1.
11
1 1
121
1 11 1 .1
1 1 1 1 .1
•
.
1 11.1
•••
1 11 2.1
- 4 0 •o
2
»• •
ü
r■
40
■
'
I
TRACI: or JOINT s feo.M AMOLE OK NORMAL WITH Y AXIS = 90.0 SECTlpN s-0.
S 3A3
Figure 2.7c
Joint Influence Diagram for Case (S3A3) - 60
39
Joint
•• ìC- r,f JOINT = M9.9 ANGLE OF NORMAL WITH Y AXIS = 90.0 SECTION “-0.
Figure 2.7d
Joint Influence Diagram for Case (S3A3)
1»0
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ì
1
1
uni i
1 11 1
l\
121 ?
11
2
#•
112121122121211
•?!
•2
.
?121
1*.
2
1 11111
.
1 11 1
11 U
2.
2*
2
2
.2
1
1 1
i mi
i l i
l in
?
2.
?•
2
*
.2
.2
2.
.
.?
121
121 1
1121
211212
.2
11111
21211?
1
mi
l l
m
1
l
i
l
40
I
I
I
I ,, r {- Dr j »i ' T =
<) . J
a N'-U.
OK hOPMAL Wt T h Y AXIS = 9 0 . 0 SECTION s -0 00
: J I !
F igure 2 .8 a
J o in t In flu en ce Diagram fo r Case (L2A1) - H o rizo n tal J o i n t
Ul
..2 .2 1 1 2 2 1 H 1 2 U
2.2
2121
•2
1*1
2
21
2
1?
U
•2
21
.2
2
?•
2
2
*
2
2
2
.
2
12
1
?1
2l
1?
2
.2
2.
121
1211
, 211212
..2
2
2 . 2,.2
11 111
0
]'" T =
*r"lt OF NORMAL
"Figure 2.8b
w t Tk
Y AXIS = 90.0 StCUON =-() •00
Joint Influence Diagram for Case (L2A1) - 30° Joint
k2
I
I
H(>.0
I
.2.?
••?•2• ¿•2.2..
2121
1¿1
.2
21
2.
1?
U
.*5
21
.2
21
1
?1
2
1
2
2
2.
12
1
.2
"5 l
21
1?
121
1211
.
»
.
*2
2
• *2.
2.2..?-
2♦2
0.0
o
I^ATF
•
OK J O I N T
= i i .i
a :*.-i.K
OK
I OPMAL
WT T>- Y A X I S
= 90.0
SECTION
40
= - 0»00
i
Figure 2.8c
Joint Influence Diagram for Case (L2A1) - 60° Joint
I'UO
•¿
1
. . .. ?.2,
• 2 • 22 2 2
,2.?
•2•
..
2
2.
1?
11
21
.2
i1
1?
1?
1
)?
2
1
.2.... .
■2i
Î
?1
2
1
.... 2.
?
21
1
12
?
12
1
r>\
2i
.2
2•
.2.
•*2.
•2 «
. 2 ..
2••2•2
2 . 2 . •?
li . o
40.0
fPArt-
Oh
ju p
I
= '<i.v
Af (, t f.
OK
KOHhAL
Y a XTS
= 40*0
StCHON
a " 0 # 00
^ A I
Figure 2.8d
Joint Influence Diagram for Case (L2A1) - Vertical Joint
1+4
/*
u.
0. 0
1
1
11
1 1
1
11
1
1
1
1
1
1
1
1
1
1
11
1 1 1.2
.2 .1
.1
.
11
.
. 2.11.
.2
•
•
•
•
•
•
•
•
•
•
•
•
2
.•
•
V0
i
I
I
. (J
.2
1
1
1
11
.
••
1
11
1
1
H
I
1 .1
1 .2 .1
1 1. 1. 2 . 1
11
1
.
-^C•0
I mU
l
F JOINT =
1
1
1
1
1
1
1
1
•
•
•
•
2
1
2
, •
1
.2.
.2
••
•
l
1
1.
.2
l
1
1
••
•.
11
1
11
2.1
1
.
••
••
2.
••
•
2.
•
1
11
1
1 1
1
11
m
•
•
2
••
.
.2
••
2 .
1. •
11
1.2. l
2
1. 2.1 .1
1 . 1 1 1
1
111
1
1
11
1
1
1
1
1
1
1
l
n
0
0.0
ANOLI
OF NORMAL WITH Y AXIS = 9 0 . 0
SECTION =-0.00
l ,a;
;
Figure 2.9a
Joint Influence Diagram for Case (L2A2) - Horizontal Join
^5
40
,
vO.U
»2 . •1 1
1 1 11
»11 • 2 • 1
1 .2.
1.1
1. 1 1
1. i 1
2.1 1 i
1
.2
2
11 1
.
•
2
11
.
.
1 1 1
11 1 21
1
1 .1
2
.2
1.1
.
2. 1
. 1 . 2. 1
11
.
.. 2 .
.
2 . . 2 ...
1 1.1
l 1
* 0.0
40*
-4 0
TK/Ct:
UF
JOI NT
= 30.0
ANGLF
OF NORMAL
WITH
Y
AXIS
= 90.0
SECTION
=-0.00
L 2 A2
Figure 2.9b
Joint Influence Diagram for Case (L2A2) - 30° Joint
/
I
I
I
0.0
1
I
I
. .1 . 1 1 1
1 2
.2
2
1
.1
1
1 1
1
1.1
11
1.1
11
2. l i i
11
•
I
I
I
I
I
I
1
1
2.
1
1
2
1
1
»2•«
1
1
2
1 l.
I l l
1
11
1 21
11
l .1
1
1 1 1 .2
.
.2
2
1 11.1
1 . 2.1
. . . 2..
». 2 . ..
-4Q.0
I
I
-40.0
IKAC l
CF
0
JO INI = 60. 0 /NOLfc OF NORMAL
WITH Y AXIS
= 90.0
L2A2
Figure 2.9c
Joint Influence Diagram for Case (L2A2) - 60° Joint
1
I
SFCTI ON = - 0 . 00
1*7
40.0
I 2k 2
Figure 2.9d
Joint Influence Diagram for Case (L2A2)
U8
I
i
I
I
I
I
i
(
V
‘1
t0.0
i l l .
i
n
11
Il
l
l
l i
li
11
.11.1.1
i l l.i.ii,
1 1 1 1 .2.1
1
1 11
l
1
1 1 1
1 1
1
..
..
11 1
I
I
k
2.
..
1
11
1
1
1 1 1
1 1 1
1
11
1
l
l
11
1
.
.
1.1
.
11 . 2. 1
111
.
!..
..
..
1 .2 . 11
l 1.1.1.1
2 1.1.1.1 1
Î
11
1.1.1
li
T
.
Ili
1
1
1 11,
1
. ........
2
1
1
lì
1.2. 1 1 1 1 1 1
1..1
1..1
1
1 1
1
1
1
11
1 1 1
11
1
1
1 1 1
1
11
1
1
1
.0
iL"s-..
■I
-4C.Ü
^..V k ACL
CF JOI NT
0
=
0.0
ANGL*
OF NORMAL WITH V AXI S
= 90.0
40.0
SLCT ION = - 0 . 00
Figure 2 .1 0 a J o in t In flu en ce Diagram fo r Case (L2A 3)-H orizontal J o in t
1
1*9
I
I
I
1 1 11
, 1. 2 , 1 1 . 1 . 1 1
1.?.
1.1
1. 1
1. 1 1
1.1
1
2. 1 1 1
1. 11
. 1 l
t 1 .
1
11 1.
11
i
1 1
121
•2
1 .1
1 .1
1.1
.2.1
..
1 1 1.1
• 11
2
. .2.
1.1.1
1 1 1
(
;0. J
—0.0
0
i I oc OF Jiilfv'l - V>.0 / H( |_ OF UmPOIAI
with
Y AXIS = 90.0 SI C7 l LN =- 0 . 00
L,
Figure 2.10b
J o i n t I n f l u e n c e Diagram f o r Case (L2A3) - 3 0 ° J o i n t
50
40
I
I
I
1
X
I
I
I
1
I
1
I
I
I
I
I
t
1.2. 1
1 .1 1 1 11
1.111 1
1.1 11
1.1
11
?. 1 l 1
11 11
l
1
... ?.
l
1
l
1
1
111.
1 11
U 1 21
.2
1.1 1 .1
1 1 1 1 .1
1 1 l.l
1
. 2.
11 . 2 . 1
'.0
f jfU r1
i
f]<.i ,
it
Figure 2.10c
m th
v vx
sr ( i I r r ~ - 1). oo
t
Jqint Influence Diagram fop Case (L2A3) - 60° Joint
51
I
I
I
1
I
1
1
I
I
I
I
'
2
.3
2
.
1.
1«
2•.....
11 1
11
• 1
1
1
.1
.2
11
l 1
1 .
1
1
..2 ........
1
I 1
11
l i.
1
21
12
.1
.2
• •
1
1 l
11
•1
1
2
2
• -
'j. Ü
o
jnira =
s
j
ur-
normal
with y axis
= 90.o
sfction
=-o, oo
F igu re 2 .1 0 d Jo in t In flu en ce Diagram fo r Case (L2A3) - V e r tic a l J o in t
52
I
1
I
I
4G
Joint influence zones for the given stress field
Vertical structural, support required is Mgg on the left roof. On the right
spring line, the supports must supply a reaction parallel to the joint of
magnitude M^g sin a -
£.
FIG. 2.11 The Rock Load
53
FIG. 2.12 REQUIRED ULTIMATE STRENGTH FOR ROCK BOLT
SUPPORT SCHEME-SHOWING A MINIMUM AT A
GIVEN BOLTING PRESSURE
5k
I
I
I
I
I
I
8
I
CHAPTER 3
DESIGN APPROACH FOR ELASTIC-PLASTIC
ROCK UNDER HYDROSTATIC LOADING
Chapter 2 considered an approach to selection of rock bolt
design parameters.
A specific illustration of the suggested
approach to examine the relative influences of bolt length,
spacing, prestress, and diameter made use of elastic stress
distributions assuming the rock bolts to be colinear point loads
in a linearly elastic medium.
Joints were considered as a
criterion of failure, but Joint failures were not allowed to modify
the global stresses.
I
For simple stress states it is possible to obtain an elastic-
8
plastic type of solution in which the failure of specific portions
K
I
I
I
This chapter will draw on the logical steps of Chapter 2 to obtain
I
I
I
I
of the rock around the tunnel changes the conditions of the problem.
a closed form solution for design of rock bolt support of a circular
tunnel in broken rock under a hydrostatic state of stress.
The
rock bolts are replaced by an average bolting pressure Pg.
1
3.1
MATHEMATICAL CONDITIONS
Excavation of the cavity and external loading are considered
to develop a stress state that is plastic near the opening and
elastic beyond as in Figure 3.1.
The stresses in the plastic
1 Ref. 3
55
zone are constrained by the Coulomb strength characteristics of
the broken material Cr and <|>r (Figure 3.2), which may be
approximated by the residual strength parameters deduced from
direct shear tests carried to large deformation.
The dimensions
of the plastic zone are fixed, on the other hand, by the criterion
of failure applicable to the rock mass at the limit of strength
and therefore by Cp and $p, the peak strength values determined
by triaxial or direct shear test.
In a continuous rock mass,
or one with initially tightly closed or incipient extension joints,
Cp and <|>p are essentially the peak strength parameters for rock
substance and greatly exceed Cr and <(>r .
In an open, jointed rock,
or one with shear joints, the values of Cp and <|>p may be close to
Cr and <j>r (Reference *0.
See Figure 3.3.
equilibrium equation (Figure 3.^)
do.
0 -0
r
0
s o
(3-1)
dr
stress relationships in the plastic zone
°n
'
+ C
'
1 + sin <f>
cot
3
?
1
*
----- ---------o + C cot <f>
r
r
r
-M
=
--------- 1 - sin <f>
r
(3-2)
in the elastic zone:
as r -*■ °°, a -► p, the hydrostatic external pressure or initial
stress condition.
The stresses are
56
(3-3)
°0 = p * -2
r
where:
K is to be determined by the boundary conditions
3.2
SOLUTION FOR STRESSES AND EXTENT OF PLASTIC ZONE
Equation (3-2) may be solved to express o Q explicitly in terms
of ar , which may then be substituted in equation (3-1).
do
dr
r
a
r
r
2 sin <|>r
l-sin 6
1
Cr cot <f>r
2 sin $
r
1-sin d>
r
This yields
(3-fc)
or
da
r_____
+ C cot <J>r )
r
dr
2 sin 6
__________ rr
r
(l - sin <f> )
rr
giving
2 sin <f>r
D (r)
°r
r + Cv
r cot *r =
1-sin <{>„
r
(3-5)
^
If Rq = the radius of thetunnel and D is a constant, then the
boundary condition at the wall of the tunnel (r = Rc ) rock bolted
to a pressure Pg is
PB ‘
57
from (3-5)
+ Cr cot <j>r
2 sin <t>r
1-sin <J>r
so that
2 sin
1 -sin 4
or = - Cr cot <|>r + (PB + Cr cot <|>r )
(3-6a)
while substituting (3-6a) in (3-2) yields
1+sin 4>r
a0 =-Cr cot d»r + - - - - -
2 sin <j>_
-------(PB + Cr cot 4r ) / M l - s i n <j>r
\R°/
r
(3-6b)
At the elasto plastic boundary r = R and
(ar )
plastic
elastic
2 sin 4j
giving
K_
p -
R2 = - c
(0
1-sin 4,
cot <J> + (PB + Cr cot 4>r )
(3-7)
The rock is at its peak stress at the elastic plastic boundary
so that the elastic stresses satisfy the criterion of failure
(Equation 3-2), when the peak values of $
and Cp are used
for 4r and Cr respectively.
K_
P + R2 + C_ cot 4
_________ _P______£
1 + sin
p “ R2 + Cp cot 4p
1 - sin é
P
K_
P
(3-8)
Equation (3-8) can be written
K
r 2” =
(p + Cp cot <(>p ) sin <f>p
which can then be substituted in
(3-9)
Equation (3-7) and solved to
give an expression for the thickness of the plastic zone.
1-sin <l>r
p + Cr cot <|>r - (p + Cp cot <j>p ) sin <|>p
2 sin <t>r
P B + Cr cot *r
(3-10*)
The formulas (3-6a) and (3-6b) define the stress state in the
plastic zone, while (3-3) with K and R as given in (3-9) and (3-10)
specify the stresses in the elastic zone.
However, the primary
object of the derivation is Equation (3-10) which gives the extent
of the plastic zone, and consequently the upper bound of the rock
load under gravity (for a given acceleration).
Figure 2.12).
(Compare with
It is seen that the rock load vs. bolting pressure
relationship depends on the external rock pressure p and the bolting
pressure P B as well as the peak and residual strength parameters.
In reality, the <|>r and Cr values should vary from truly residual
properties near the tunnel wall where large deformations can occur
to larger values not much different from the peak at points near
the elastic plastic boundary where deformations must be more
restricted.
* If <{>r = <f>p and Cr = C^, (3-10) reduces to the formula
T. A. Lang in Ref. 3.
59
given by
For computations herein a single (average) set of values Cr
and <j>r was adopted to characterize the entire plastic zone.
The
weight of rock in the plastic zone above the tunnel is
y
(R - R0 )(2R0 ).
This is an upper bound to the vertical rock
load (under gravity acceleration only).
(R - R ) also sets the
minimum acceptable length of rock bolts if they are installed
radially.
To allow for anchor slip and to provide a margin of
safety the rock bolts should be at least (U/3) (R - RQ ) long.
Before proceeding with some example calculations one point
has to be examined critically.
Use of Coulomb theory to determine
the limit of the plastic zone infers that shear failure surfaces
be formed at an angle of otp = 1*5 + <j>p/2 with the direction of o-^.
Since o-L is a 0 the surfaces thus formed will be log spirals of
angle (1*5 - 4>p/2) with the radial directions.
Since in the plastic
zone the fracture locus are already determined in terms of peak
strength parameters, the shear surfaces cannot occupy the orientation
most critical with respect to <}>r and Cr , that is
ar
= 1+5 + <|>r/2.
Therefore, use of Equation (3-2) is not justified and the results
are in error.
The error of substituting Op for
ar
in the plastic zone is
not large, however, as shown by Figures 3.5, 3.6, 3.7 and 3.8.
Figures 3.5 and 3.6 consider the case where C_ > C
Jr
60
■*
but 4>_. < <(> ;
ir
A
the rupture according to criterion <j>r , Cr on a surface at
is
according to the dashed Mohr circle Sr in Figure 3.5, or S Q in
Figure 3.6.
That is, if a fracture is formed according to
criterion 6 , C , it is oriented at angle a .
p* p ’
e
P
Therefore, when
considering the strength of the fracture under criterion <t>r , Cr ,
it is not enough that the Mohr circle be tangent to the 4>r , Cr
line (Mohr "envelope"); rather the Mohr circle must enlarge
to cross the <f>r , Cr line until the point representing orientation
otp has been carried to the border of the unsafe region.
Thus
more properly in Equation (3-2) (Oq ) should be replaced by
(o
q
+ d 0 q ) as shown in Figure 3.6, or (ar ) should be replaced by
(or - d or ) as shown in Figure 3.5.
Figures 3.7 and 3.8 present
a similar analysis for the more probable case where <i>p > <f>r .
The
magnitudes of (d ar ) and (d a0 ) are not large, particularly in
view of the uncertainty in estimating <(>r and Cr .
3.3
EXAMPLES
It will be shown that, in contrast to the elastic case
presented earlier, with the assumptions of the elastic-plastic
case considered here the rock bolt pressure can have a considerable
influence on the radius of decompression and consequently a marked
strengthening effect even when the rock bolt pressure is less than
1% of the external load.
This is particularly true when the
residual strength is low.
6l
Several examples have been calculated with characteristics
of the elastic material as follows:
CL = 380 psi; <f> = 60°.
P
P
For the broken material the friction angle (<|>r ) was either
50° or 30° while the cohesion Cr was either 2 psi or 0.
An
external hydrostatic pressure of 2000 psi or of 3000 psi was assumed.
The radius of the decompressed zone was calculated corresponding
to varying rock bolt pressures.
For each set of properties the
curve relating bolting pressure and rock load (compare with Figure
2.12 of Chapter 2) could be sketched as presented in Figures
3.9 to 3.12.
Several values of R/R q corresponding to an external
pressure of 2000 psi are given in Table 3.1.
Figures 3.13 and 3.1^ show another case, —
this one for a
granular soil-like material in which <L, = <b and C = C .
1
P
P
r
Here
the rock bolt pressure is all that preserves the structure from
collapse.
Figure 3.13 corresponds to <j> = 50°, while Figure 3.11*
corresponds to <j> = 30°.
The rock load - vs. bolting pressure
functions are sketched for hydrostatic pressures of 3000, 1000,
and 250 psi.
Figures 3.15 to
3.18 compare the radial and tangential stresses
before and after rock bolting.
The external hydrostatic pressure
is 2500 psi and the rock bolt pressure is 12 psi.
Cr = Cp :
<t>r = <j> = 35°;
P
= 1 psi (Figure 3.15), = 5 psi (Figure 3.16), = 20 psi
62
(Figure 3.17), = 100 psi (Figure 3.18), and = 500 psi (Figure 3.19).
It is evident that the greatest relative strengthening effect
occurs when the rock is weakest.
presented in Table 3.2.
The variation R/R
o
with C is as
Design of the bolting parameters follow
from knowledge of the R/RQ vs P-^ relationship; as described in
Chapter 1.
3.3.1
Two examples follow.
Example Ho. 1 —
A 20 foot diameter tunnel (R0 = 1 0 ' )
is subjected to a hydrostatic residual stress of 2000 psi, and
the properties correspond to Figure 3.12 with <J>p = 60°, C
<J>r = 30°, and Cr = 0.
= 380 psi,
The rock weighs 1 psi per foot, and the
weight of rock to be supported is given by R/R0 .
analysis are given in Table 3.3.
Results of the
Since the bolts are shortest
in case 3, the economic minimum may be closer to case 3 than to
case 2.
Finally, selecting a spacing of bolt; the required
size of bolt is established.
If the bolt spacing is 3 feet with
total bolt pressure of 30 psi, the bolt pretension load is 39,000 lbs.
n
bolt pretension load (pounds)
30 =
3 x 3 x ik\ sq. in.
Pretension 7/8" bolts to 50$ of yield load to install the required
bolt pressure.
'!
3.3.2
'
.
Example No. 2 —
I
A 20 foot diameter tunnel is subjected
to a hydrostatic pressure of 2500 psi, and the plastic zone
i
63
characteristics are 4>r = 35° and Cy = 500 psi.
Figure 3.19
shows that the rock bolt pressure of 12 psi is ineffective in
changing the stresses; the radius of decompression of 1.27 is
relatively unaffected by PB = 1 2 psi.
The most economical
solution appears to be to accept the radius of decompression
corresponding to PB = 0 and supply a light bolt pattern and wire
mesh to act only passively.
10) = 2.7 psi.
The total pressure required is (12.7 -
To supply a pressure of 3 psi with a 5 ’ rock bolt
spacing the required bolt strength is
Total load = 3 x 5 x 5 x l U
« 11,000 lbs.
Light rock anchors 6 feet long are sufficient support.
Do not
pretension.
3.H
CONCLUSIONS
The chapter shows that the correct rock bolt design depends
on the conditions of the rock mass when analyzed by an elastoplastic approach.
The approach can be extended to biaxial conditions
(non-hydrostatic loading) using a finite element analysis.
In cases with significant cohesion, the examples of Figures 3.18
and
3.19 show that rock bolting alters the stress distribution
only slightly.
However, the rock of the unbolted tunnel cannot
be presumed to possess the same long term cohesion as the unbolted
tunnel, due primarily to its gradual deterioration if left unsupported.
6b
This vital aspect of rock bolt strengthening is not evaluated by
the preceding methods.
65
TABLE 3.1
RADIUS OF PLASTIC ZONE FOR VARIOUS ROCK PROPERTIES
Figure
Elastic Zone
Plastic Zone
CP
(pii)
3 .9
60°
3.10
3.11
3.12
Cr
(psi)
50
380
ft
»1
ft
ft
ft
ft
ff
ft
tl
ft
ft
ft
ft
ft
It
50
ff
30
ft
30
ff
2
ft
0
ft
2
If
0
ff
Rock Bolt
R/B0
Pressure (psi)
1
10
1.66
1
10
I .9 2
1.36
1
10
1*.17
2 .1 a
1
10
8 .5 7
2 .7 3
1 .3 3
TABLE 3.2
VARIATION OF THE PLASTIC ZONE WITH C
1
C (psi)
R/Rq
5.02
5
k.kl
20
100
500
3.35
2.08
1.26
TABLE 3.3
EXAMPLE NO. 1 RESULTS
Rock bolt pressure P^
psi
R/R0
Rock Load
psi
Required total
bolt pressure
(1)
5
k.2
32
37
(2)
10
2.9
19
29
(3)
20
I.9U
9.U
30
(U)
30
I .58
5.8
36
66
r
FIGURE
PLASTI C
3.1
AND E L A S T I C
67
ZONES
FIGURE
PLASTIC
STRESS
68
3.2
CRITERION
SHEAR DISPLACEMENT
Peak
and
r e s i d ' Oa l
69
strengths
FI GURE
3.4
EQUILIBRIUM DIAGRAM OF AN INFINITESIMAL ELEMENT
TO
MOHR
C IR C L E
AND FA IL U R E C H A R A C T E R IS TIC S
<j>r , Cf , AND <jbp , C
MOHR CIRCLE AND FAILURE CHARACTERISTICS
d> *,C r '. AND db
C
rp » p
X t
-'« J
U>
MOHR
CIRCLE
AND
FAILURE C H AR AC T ER IS TIC S
<£r , Cr , AND
<pp ,
Cp
MOHR
CIRCLE
AND
FAILURE C H AR AC T ER IS TIC S
<£r , C r , AND <£p , Cp
75
FIGURE 3.10 RADIUS OF DESTRESSED ZONE
76
Ip
FIGURE 3.11
RADIUS OF DESTRESSED ZONE
77
78
________________________ i Pb ROCK BOLT PRESSURE (PSI)
IO
pB
20
FIGURE 3.13 RADIUS OF DESTRESSED ZONE
79
ELASTO-PLASTIC MATERIAL
CHARACTERISTICS OF BROKEN PLASTIC ZONE
FIGURE 3.14 RADIUS OF DESTRESSED ZONE
80
PSI
Ro
FIGURE 3 . 1 5
EFFECT
OF ROCK
81
BOLTS ON STRESSES
82
83
81»
i
1000
p HYDRO STATIC
* 2500 PSI
<f»p
■4>r
* 35*
Cp
s C,
* 500 PSI
PB
« 12 PSI
900
800
700
CTr WITH
/ ROCK BOLTS
Of WITHOUT
ROCK BOLTS
600
500
400
300
200
100
20
F IG U R E 3.19
EFFEC T
OF
85
RO CK
BO LTS
ON
STRESSES
CHAPTER
k
DYNAMIC ANALYSIS OF THE TUNNEL SUPPORT PROBLEM
l+.l
INTRODUCTION
Assume that a rock holt scheme has been accurately designed
to carry the loads caused by excavation of the tunnel in a medium
under an initial state of stress»
If there is no reserve
strength in the rock bolts, a blast will cause yielding in some
of the bolts.
After the blast wave passes, the support scheme
will no longer be able to sustain the steady static loads, and
the tunnel may collapse if it has not done so already.
To
prevent this it is necessary to provide an additional increment
of reserve strength for the rock bolts.
"How much?" is the
subject of this chapter.
Dynamic loads of interest are direct ground shocks from
blasting for additions! construction or from nuclear weapons.
Earthquake waves are not discussed.
Ambrasseys and Hendron
(Ref. 5) present typical wave forms for direct transmitted ground
shock from explosives (Figure lt.l).
This figure will be used
as a model for the incident wave motion to be defended against.
However, the discussion is general and other model particle
velocity, time relations incident on the tunnel, could be sub­
stituted.
The problem posed by rock bolt or steel liner support against
a velocity wave such as that of Figure l».l is complex.
86
There
are three interacting bodies - the "elastic zone", the "plastic
zone", and the support (see Figure 3.1).
Furthermore, the
plastic zone cannot withstand a tensile wave, so that the
equations of propagation of a wave in a free-ended bar are not
wholly meaningful here.
Also, internal energy absorption
mechanisms by reflections, relative slip between supports said rock,
and Joint block movements are ill-defined.
In addition, in the
case of a rock bolt the steel support is "in parallel" with the
plastic zone.
k.2
RIGID TWO BODY ANALYSIS
/
It is instructive to consider, first, the one dimensional
model posed in Figure k . 2 .
The shock is transmitted from material
1 to material 2, and the boundary between 1 and 2 cannot sustain
tension.
It is assumed that the mass density P is constant and
that there is no longitudinal restraint.
Let
be the particle
velocity of material 1 before impact of 1 against 2, and let V^'
be its particle velocity after impact.
- V^' is the change
of particle velocity in material 1 and similarly let V2 - V2 ' be
the change of particle velocity in material 2.
Then, conservation
of momentum gives
M1 (V1 - V
where
) * M 2 (V2 - V2 ')
(U-l)
, and Mg are the respective masses Conservation of energy
gives
1/2 M x [V1 2 - (V.^)2 ] + 1/2 Mg [Vg2 - (Vg’)2 ] = 0
87
(U-2)
Solving Equations (U-l) and (U-2) for V^' and Vg'
v . = -2 M2 V2 + (Mx - M2) Vi
(1»~3)
M! + m2
and
V-' * “2 M1 V1 + ^m2 - Ml) v2
2
^ + m2
If the area is A,
M1 = *1 A P
and
Mg =
A P
Further,
v2 = 0
and
Vj = the particle velocity of the center part of material
1 due to the pressure wave.
Then,
V
=
-2 1 V
d 1 1
*■1 + *2
(U-5)
We can now calculate the kinetic energy of the "plastic zone"
acting as a rigid hody.
It is
* 1/2 Mp (V?*)2 = 1/2
pA
( U x2 )
Vvr
t2
(U-6)
(tx + st!2)
This energy is assumed to he absorbed by the support.
If the
support is a rock bolt behaving elastically and is in a square
pattern with spacing S, then the area A in Equation (U-6) can be
replaced with S2 to determine the change in tension of the bolt
developed by the wave.
88
At first it might seem that such an approach could lead to
a simple, workable formula for calculation of the blast load on a
rock bolted excavation wall.
(l)
The length
However, it has severe shortcomings,
is unknown; at best one might approximate
as a percentage of the incident wave length.
(2)
The approach
ignores interaction between the support and the rock to be sup­
ported.
It applies to a net-like support which "catches" the
rock propelled by the blast.
(3)
Actually the materials involved
are never rigid; deformation in the plastic zone would seem to be
a significant component of the problem.
U.3
ELASTIC - TWO BODY ANALYSIS
The approach was improved by assuming the two parts 1 and 2
of Figure k . 2 to be elastic.
Material 2 is assumed to have a
modulus of elasticity and wave velocity significantly lower than
material 1.
The boundary conditions are:
1.
The strain is a defined function of time at the
left end of material 1.
2.
The strains and displacements in materials 1 and 2
are the same at the contact.
3.
equal to zero.
The displacement at the wall of the excavation is
The analysis computes the reaction force at the
wall necessary to prevent any displacement.
The maximum reaction
force at any time is the required additional support force.
It is
obtained by a Duhamel integration of responses to each unit impulse.
89
00
2 (-l> ”
fl -
(2n-l)
ir cos
008
P*E,
[(*> - !) w
2 ( - l ) n C«
____
ra]l
7 17
<
j~2n-l
ir f l
C
°2
fg
F"
7- 3
f l - cos (2n-l) ir C2 t 1
L
( 2 n -l) ir cos
2
dj
, ik fi"1
T -
[
2n-l
2
°1
*2 J
in vhich t d i s the duration of the p o sitiv e v elo city pulse (Figure
Ir.l).
This solution could be applied to a s t i f f in tegral tunnel
lin e r vhich i s in se rie s with the rock.
I t i s not too meaningful
for rock b olt support vhich i s in p a ra lle l v ith the rock zones.
Again there i s d iffic u lty in defining
A prin cipal objection
i s the use of a no-displacement condition at the tunnel v a i l,
vhich vas necessary to make the problem tra c ta b le .
U.U ENERGY APPROACH TO ROCK BOLT PROBLEM
The t o t a l energy transm itted by the b la st vave includes both
kin etic and poten tial energy.
The kin etic energy i s associated
v ith the acquired p a rtic le v e lo city , vh ile the poten tial energy
i s associated vith strain in g o f the rock.
To represent the boundary conditions of a normally incident
vave approaching a v a il the tvo extremes of boundary fix atio n can
be assumed as illu s tr a te d e a r lie r.
A vave meeting a free boundnT*y
vhere the normal str e s s i s zero can be demonstrated to develop
twice the displacement that i t develops in the free fie ld (Reference
6 ).
At the other extreme a fixed boundary, vhich i s re stric te d
90
(U-7)
so that there is no displacement, develops twice the stress
that it does in the free field.
The rock wall, in the case of a real support, must be
intermediate between free and fixed.
restrains some displacements.
A rock bolt obviously
In case of a free boundary only
kinetic energy need be calculated as there is no strain, con­
sequently no potential energy, at the free boundary.
(This
ignores lateral restraint in the wave front, which develops
tangential stress in the wall).
Some percentage of the total
kinetic energy will have to be assigned to the support.
The
only support that really fits this model is a net.
The case of a fixed boundary is really not approachable in
a hard rock system.
With a stiff support, however, the wall
displacements will be reduced by the support.
be strain energy to be considered.
Then, there will
The kinetic energy at the
wall would be zero if there would be total fixation.
The physics of rock - rock bolt interaction, in the case of
wave advancing on a rock bolted wall, is surely complex.
It
must depend on the anchor response and the rock bolt bond charac­
teristics under the dynamic load.
If we assume the anchor does
not slip and the bond is insignificant, then the response might
have the form indicated in Figure U.3.
Because the steel has a
much higher velocity than the cracked rock it supports, the wave
first advances up and back in the rock bolt before it reaches the
wall.
First it stretches the bolt reducing the bearing plate
91
pressure.
Later the wave displaces the wall stretching the bolt
and increasing the plate pressure at the same time.
The first
response may be termed uncoupled as the bolt and the wall move
independently; the latter may be termed a coupled response as
the bolt is moved by the wall.
We will base the design approach on a determination of AT
(Figure U.3), the increase in bolt tension produced by the coupled
response.
AT might be termed the maximum passive force increment
in the rock bolt.
The procedure will be, approximately, to
multiply the average power of the wave in the rock by the transit
time of the wave in the rock bolt (tB ).
The transit time of the
wave in the rock bolt is basic because some energy is leaving
the bolt while some is entering.
The maximum duration in which
energy can be stored in the bolt, assuming the bolt to behave
elastically, is the transit time (tg) which equals the rock bolt
length divided by its velocity.
t
B =
(l»-8 )
where:
% is the rock bolt length
Cfi is the wave velocity in the bolt.
|
That is, the latest time that energy, which enters the bolt at
time
t
, can still be stored in the bolt is T + tg.
^•*+•1
Case 1:
Only Kinetic Energy Considered
We will calculate the maximum kinetic energy of the
rock acquired by a momentum impulse beginning at time
92
t
and ending
at t + tfi.
The momentum per unit area transmitted by the wave
over time dt is odt, where o is the average stress of the wave
in the time interval (Figure U.U).
Then the momentum vector
per unit area is
t * t + t
M =
T + tB
B
odt
P C V dt
(U-9)
t = T
A simplified way to calculate the associated kinetic energy would
be by analogy to a rigid body.
Then, the kinetic energy ejj is
ek = 1/2 MV2
(U-10)
where V is the incident particle velocity in Equation (4-9)*
(Case 2 to be considered later is more refined).
Solving for the
magnitude of the particle velocity
V
- I ¡S I
—¡r
(‘‘-id
A
. . .
which gives
Ck - 1/2
Ul^
a2
(ll_12)
The momentum vector has a component perpendicular to the
wall, and another parallel to the wall
M * M 0 + Mr
(U-13)
^
^
i
Me
(H-lk)
93
A =» the area of the wave front which impinges on the wall of the
tunnel.
If the rock bolts are in a square pattern with spacing
S, the wall area of interest is Ay ■ S^.
Let a be the angle
between the normal (the radial direction) and the wave advance
direction, then
A = Ay cos
a
*
cos a
(^-15)
Also
Mj.| = |M | cos a
(1*-16)
and
Me| = IM I sin a
then,
o
c = 1/2
k
Ay
+
1/2
2
cos
-
ns
cos
2
a
|M|2 sin2 a
(^-17)
2
a
|M|2 COg2 a
The first term of Equation (U-17) gives the kinetic energy
associated with Mg which is to be dissipated parallel to the wall,
while the second term is the energy associated with S
r
which is to
be dissipated perpendicular to the wall.
As a further simplification the kinetic energy associated
with Mg can be presumed to be tolerable because of the confinement
afforded by contiguous material.
The energy associated with Mr must be borne partly by the
rock bolts, partly by reflection of the momentum, and partly by
9k
/
internal energy absorption.
Let k be the proportion of energy
which can be withstood by the rock system.
Then the kinetic
energy to be taken by the bolting scheme is
c
. (1 - k) A,2 co.11 a iMl2
r
2M
If the rock bolt length is l and the cross section area of the
rock bolts is A , the energy which can be taken by the bolt
assuming elastic behavior is (Figure 4.5):
e
=11/2
L
E
+ ^ ¿ 1 Agi
E J
(4-19)
k
where
is the increase in bolt stress caused by the blast, and
is the bolt stress installed before the blast.
If the initially
installed tension is T, the increase in tension ÀT required to
absorb the energy elastically is (other energy absorption
mechanisms are possible -- yielding anchor slip, or special
slipping bolts ):
Asl
erb
[(AT)2 + 2TAT]
5 E
(4-20)
Assuming a plastic behavior
e., * Te Ik
rb
p
s
where
(U-20)b
i8 the plastic yield at load T (cf Figure 4.6)*
The mass M is calculated from the dimension of the rock body
assumed to be incapable of withstanding the blast without support.
95
This dimension is related to the rock holt if the bolts have
been properly designed.
In any event the rock bolt length
defines the largest value of M.
This gives
(U-21)
M = (As2 ) P
where p is the mass density of the rock.
The momentum ft can be computed by integration in a given
case.
As noted, Reference 5 presents a typical wave form for
the velocity of a blast (Figure U.l).
We will approximate this
by two straight lines as shown in Figure U.U.
In these figures
R is the distance between the tunnel and the blast, while C is
the phase velocity of the medium.
As stated previously, the maximum duration energy is stored
in the bolt for tg equal to the transit time of the wave in the
bolt.
It can be shown (Appendix 2) that the greatest momentum
that can be calculated by integration of Figure U.U over an
interval tg is as shown in Figure U.U, beginning at t such that
V (r) * V (x + tB ).
Let:
(k-22)
As shown in Appendix 2, the ruled area S of Figure k.k is given by
S = Vmax
(l-S2 )
(^-23)
2
Since o * pCV, where C is the phase velocity and V is the particle
velocity of a solid, the momentum per unit area is then
T+t
B
M
odt
<>c W d
(1-b2)
( k-2h)
Substituting Reference 5's estimate for t^,
d ~
2C
(U-25)
where R is the distance from the blast, and C is the phase
velocity, the absolute value of momentum per unit area becomes
IA I „ oVmax ^
II
<1-S2 )
E---
(U26)
If there will be no failure, the kinetic energy associated
with the radial momentum component equals the elastic energy
4r
absorbed by the rock bolt.
er “ erb
giving for an elastic rock bolt behavior
(l-k) S2 cos^
2p*
[-
-][
PRV___(1-B2 )
max
]
"12
A s &TAT2 + TATI (U-27)
2E
The required increase in bolt tension is T given by:
[ at2 +
tat]
^P
[l-k|
*W
1- s2) cos2 •
Vs_
Roc.
Material
bolt
properties
properties
Blast
Characteristics
(lt-28)
97
where
E
A_
is the elastic modulus of the rock bolt
s
is the area of the rock bolt
S
is the spacing of rock bolts (in a square pattern)
<-
is the rock bolt length
p
is the mass density of the rock
R
is the distance from the blast
V
is the maximum particle velocity of the incident blast
m&x
vave
a
is the angle between the blast direction and the normal
to the rock wall
8
as defined in Equation (U-22)
k
is a dimensionless coefficient indicating the percentage
of normally incident wave energy that the rock takes
without transference to the rock bolts,
k is a
measure of the rock restitution, strength, and
plastic deformability.
k would approach 0 for a
"plastic" zone where all.stresses corresponded to
limiting equilibrium and should approach 1 for a
hard unjointed and unweathered rock mass at inter­
mediate or distant range.
It also depends on the
blast intensity.
The increase in tension required to accommodate the blast
depends on the initial tension T.
If T ■ 0, then AT is
98
l A R Vmax(l"e2)
v
cos2
(U-29)
If there is an initial tension T, then the quadratic equation can
be used to solve (U— 28) for AT.
Assuming a plastic behavior, er *
erb gives
p R V
(l-k) S 2 Cos** a
2pl
max
u
(l-B2 )
P
»(1-k),
tep
Rock bolt
energy
absorbator
properties
k.k . 2
Caae 2:
Rock bolt
properties
l A
= Te
Material
properties
(U-30)
s
Cos
R V,
max d - e 2 )
Blast characteristics
A-31)
Total Work Considered
The above (Case l) assumed that only the momentum
component perpendicular to the wall needs to be considered in
calculating the energy to be absorbed by the rock bolt.
Further
it assumes that the energy can be calculated from the momentum
b y Equation A-12 ) .
If the rock is deformable, the total work done on the
rock by the traveling wave may be a more fundamental quantity
on which to base analysis.
A calculation for this case follows.
The total energy traveling during the transit time of
the rock bolt is equal to the work.
Therefore,
99
T+t
S
(It-32)
adU
etotal “ ^
T
where U is the particle displacement and A is the area of the
wave considered.
dU = Vdt
and
a a pCV
so that
T+t
B
T
The integration is contained in Appendix 2.
etotal =
3
^
Vmax2
*d i1” **3 )
The result is
(U -3 U )
where as before 3 is defined by Equation (U-22).
By analogy with the previous case we will divide the total
energy into a portion associated with the tangential component
of the wave motion Gq ' and a portion associated with the radial
component of the wave motion er '•
(^-3 5 )
etotal * e0 f + er '
100
As before
( 1^ 36 )
etotal cos
and the area
o
A « S
cos o
(U-37)
(compare eq. (U-15))
which gives
V
- S 2 cos^o
(U— 38)
td (l-B3 )
Let K be the proportion of er ' vhich can be withstood by
the rock system.
Then the proportion of energy to be taken by
the bolts is:
er = (1-K) S 2 cos3 o
V 2^
td (l-S3 )
(U-39)
Again, we can substitute for t, from Equation (U-25).
a
For design,
Er * Erb
(U-UO)
giving for an elastic behavior:
R (1-B3 ) Vmax cos3«,
Blast
^
properties
Rock
Material
bolt
properties
properties
(U-Ul)
Again, solving for AT yields an expression defining the required
increase in bolt tension to accommodate a blast.
The symbols in
equation (h—hi) are explained below Equation (h—28).
101
K in
Equation (1*-Ul) must b e different than k in Equation
as
it is the proportion of the total energy that can be vi+nstood
by the rock in Equation (b— i»l).
For a plastic behavior, e
Te
* e
rb
gives
Cos 3o ( ^ g 3)
P
Rock
bolt
energy
behavior
k.5
r
Rock
bolt
properties
Material
properties
(W»2)
Blast
properties
DISCUSSION
Equations (lt-28) and (U-l+1 ) could allow calculation of the
increase in bolt tension necessary to accommodate a blast.
This
was the object of the analysis (compare with Figure U. 3).
According to the previous discussion, Equation (U-28) should be
closer to the correct calculation if the rock bolt system stiff­
ness, as compared to the rock stiffness, is such that wall dis­
placements are essentially unimpeded by the bolting pattern.
Equation (U-Ul) seems more appropriate in the case of a very stiff
rock bolt support scheme in which wall displacements are severely
restricted.
This approach, however, assigns unknown rock properties to
a quantity k or K which might in fact be a non-linear function.
However, in the case of a nuclear blast the coefficients k and
ÏC
depend heavily on the state of the rock, the support pressure, and
on the nature of the blast.
They can be constant over a small
102
range of support pressure, and they can be very close to 1
when the support pressure is high.
Some experimental data are available that allow a more
general relationship between the previous quantities
and e
This chapter has calculated the energy of the traveling wave,
which is, in itself a meaningful physical quantity.
The next
chapter will discuss how the actual support system will carry
this energy.
103
VELOCITY
ACGEL. a
DISPL. d
FIGURE
4.1
T Y P I C A L W AVE FORMS FOR
DI RECT T R A N S M I T T E D GROUND
SHOCK FROM E X P L O S I O N S .
FROM AMBRASSEYS AND
H E l f ORON (1 9 6 8 ) p. 221
101+
INFINITESSIMAL GAP
I
FIGURE
MODEL
4.2
FOR RIGID BODY
105
ANALYSI S
COUPLED
RESPONSE
PLATE
PRESSURE
B OL T T E N S I O N
DECOUPLED
RESPONSE
WAVE F R O N T
AT TIME t,
ROCK W A L L
PLATE
ROCK
8 NUT
BOLT
ROCK WALL
P L A T E 8 NUT
ROCK B O L T
WAVE F R O N T
AT T I M E t «
FI G U R E
4.3
R OC K BOLT T E N S I O N AND P L A T E
V A R I A T I O N WI TH T I M E .
106
PRESSURE
FIGURE
T H E MOMENTUM
IS T H E R U L E D
4.4
PER U N I T AREA
ARE A ( S )
107
FIGURE
4.5
ADDITIONAL ENERGY IN A ROCK BOLT UNDER AN
INITIAL TENSION T AS A R E S U L T OF ELASTI C
STRETCHING.
108
T E N S IO N
BOLT
T
BOLT ELONGATION PER UNIT LENGTH
b= T
Ag
FIG. 4 .6
PLASTIC YIELD ENERGY ABSORPTION
109
BY THE ROCK BOLT
CHAPTER 5
EMPIRICAL APPROACH TO SUPPORT DESIGN AGAINST FLASTS
In this chapter the previously calculated energy quantities of
the propagating waves of the blast will be generalized to mf.tch
underground support for any kind of blast.
Experimental data will
be used to find an empirical energy relationship between es , the
maximum energy that can be absorbed by the support system, and
er ', the energy normal to the wall that is transmitted by the
blast wave (compare equation (U—38) previous chapter).
5.1
DEFINITIONS
5.1.1
Wave Travel Time
In a nuclear explosion the duration t<j may not follow
the relationship of Equation (U-25).
A more general form would be
where n is a constant of the type of explosive device used.
Examples
a.
Data was taken from POR HOIO (draft copy), Omaha District,
Corps of Engineers, Protective Structures Branch.
110
Pile Driver Section
Range (feet)
____________
td Blast
Wave Directi.vn
__
Particle
Velocity
Measured
C Drift
9k0
106.8
1»0 fps
D Drift
8k0
90.6
53 fps
000 fps
*4=st
__
n
R
T —Z
tdc
C Drift: n = O.U95
D Drift: n = 0.51
nav = 0.5
b.
Free field ground motion in granite measured in Pile Driver
from data from W. R. Perret.
e Drift
9ko feet
66 ms
62.37
D Drift
81*0 feet
62 ms
102.50
n
C - 18,000
R
tdC
C Drift: n = .79
D Drift: n ■ .75
5.1.2
Energy Absorption by the Support System
The total energy es that can be absorbed by the support
system has to be evaluated.
In the rock bolt case it is
T2*.
es = erb = ^rb ^ s “ 2EA
where Xrb is the allowable energy absorption per unit of volume.
2
In the case of ultimate strength design the second term
2EAS
is much smaller than the first and can be removed.
Ill
(5-2)
$•1.3
Energy Dissipation Time of the Support System
The blast can have a long positive duration ta
to 106 ms in the previous examples).
(62
ms
In these conditions the
support system might have the time to dissipate the first energy
part of the traveling wave before the arrival of the end of the wave.
This time tB is fundamental in the energy dissipation mechanism
and has been calculated previously in the case of rock bolt support.
tB *, _L
CB
where:
l
= length of the bolt
CB * wave velocity in the rock bolt
For other support methods another expression for tg will be necessary.
5.2
RESULT OF THE PILE DRIVER TESTS
The
16 '
long rock bolts in C Drift were spaced at one bolt
per 3.25 square feet giving an ultimate support pressure Pr,
of
Bult
Bult
92,000
3.25 X l U
192
psi
then
pB
— -
BRo
,
= 1 . 0 0 pounds/in'3
These results are all for a given experiment, which means the
weapon size is a constant.
Thus the strain and the duration of
strain levels above some given value vary with the range according
112
to a definite function.
To extrapolate the Pile Driver results
to sane other experiment, vhere strain and duration vary with
range according to a different function defined "by a different
weapon size, we will attempt to generalize the form of presentation
by calculating the energy per unit area that is tolerable.
The Pile Driver results can be expressed in the following
relationship
rB
2R,
where: PB
RQ
Aq
(5-3)
^
is the support pressure
is the radius of the tunnel
cr ' is the traveling energy per unit area given in
the previous chapter (Equation h-36).
e0
is the energy per unit of area that can be
accepted without support.
e0 is a function of the rock properties and takes the place of the
quantities k and K of the previous chapter.
This Equation (5-3)
can predict the safe-unsafe limit for all kinds of blasts once the
rock properties are given.
Moreover the formula can be extended to
all kinds of supports.
$.2.1
General Empirical Energy Equation
Equation (5-3) can be written in a more general sense.
I
113
S2 1
(5-*>
a Bo An
where: S
3
support spacing
A
3
broken rock depth
-2— 3
ultimate support energy per unit of broken rock.
S^A
R0
3
opening radius (acts as the scale factor; it
expresses the confining effect of the circular
geometry)
B0
3
er' 3
a constant
wave energy traveling in the rock in the direction
perpendicular to the tunnel axis.
This quantity
has been computed in the previous chapter.
er' 3
S2
cos3 a
td (l-U3)
(U-36)
e _ *d - tB
td
eD' 3
Total energy that can be supported without a support system.
A
Substituting in Equation
(5—1*)»
with
e0* * eQ S
thus
3 B_
s2 n
An
cos'3 o p V“
..IBM
3n e0
Ilk
R(l-B
(5-5)
This Equation (5-5) (or 5-*0 is the same as Equation (5-3).
For
example, for the elastic design of a rock holt system with small
installed tension T and w ith yield force equal to T + AT
AAT2
es 85 2Ei£
(cf. W 2 0 )
therefore,
es
_
AT
S2 AR
2R
EAg
AT
is the increment of strain to cause yielding.
EAg
Let this quantity he called £
then
es
-X
-- « --
S2 tR
(5-6)
X £
2R
Substituting Equation (5-6) in Equation (5-5) and letting A Q = B 0 /£
gives:
7
^
- A „ *n
/
..2
v
°°°3 («>
— /.
„ 3\
P
(5-7)
3n eQ
or if t d is known,
PB
2R
cos3 (a) pCV^WY t d (l-e3 )
=
A© *n
(5-8)
3e0
Equation (5-8) can he used for design in a given environment if the
two constants of the medium, A q and e0 , are determined.
5.2.2
Application to Pile Driver Test
The quantities A q and e0 will he calculated from data
of the Pile Driver test.
eQ , the energy per unit area Just tolerable
115
;
without support, can be calculated using the limiting safe
strain for an unsupported tunnel given in Reference 7.
The maximum
particle velocity corresponding to a safe strain e can be calculated
from the relationship e ■
V * 3.6 ft/sec * 2*3.2 in/sec
Using Equation (l*-36) with e0 in place of ll ! ,
S2
e0 *
cos3« pCV2^
------ ----- i
(i-e3 )
3
3 *
while to is the travel time through the
td
broken rock.
Let us suppose that the broken rock length was 10 feet and that the
phase velocity in the broken rock was 10,000 fps
tB =
4
» _
mm
td “
2 x 10
10,000
R_
nc
td-tfi
3
=
td
=
2.0 x 10
0
sec »' 2 milleseconds
2.UUO ft
0.75 x 18,000 ft/sec
180 - 2.0
180
1-83 * (l-3)(l+ B+B2 ) = 3(1-3) =
*o *
j
= 180 milleseconds
3x2
180
= .033
x 1 x 3 x 10”3 x (18.0 x 103 x 12) (1*3.2)2 x 0.180 x (0.033)
■ 2,390 pound inches/in
p
We now calculate the constant A q for the point ^1- ® 1.0 pounds/in^
2R
vising the value for e in Reference 7 and Vmax = 5l*0 inches/sec.
116
At this range
x _
__ * _
16’
_ ,
t d = 62 ms, t B * ig-^doTn/s^T ~ l
( l - 3 3) * 3 (1 -$) *
«
k
.9
0 _ 62-1 _ 61
3 ' "62“ " 62
m
x 10"2
and from Formula ( 5 - 8 )
. .
.
1 x 3 x 10”3 (5^0)2 .062
It.9 x 10-2 x (18 x 103 x 12
1 . 0 » A_ In --------------------------- --------------=----------------------- --------0
( 3 ) (2.39 x 103)
* °*23 P°und/in3
*o =
Thus the Pile Driver data suggest a formula for the support pressure
required to insure stab ility of a tunnel as follows (cf. Equation (5 - 6 ))
, o .23 *n
00,3 °
3 x 2,390
(a ll units in pounds, inches and seconds)
5.3
HARDHAT DRIFT
/
This can be checked against data from the Hardhat experiment
in an 8 foot diameter drift at a range of U57 feet supported by
5 foot long rock bolts.
At this range the strain was 2.0 x 10 “3;
li
the maximum velocity at this range is therefore, 1.8 x 10
36 ft/sec; t d = . ys' x l l ^boo
* 0,° 3U 8econd;
Then
117
^
j,
x 20 x 10“H =
( l"e3) “ 2,7 x 10~2,
P , . ( D , 12) (0.23) tn ■Ol°~3)(36xl2)2(lfeao3xl2)(0.3l.)(2.7xl0-2)
3 x 2390
psi
PB « 22.0 x An (15.3)
P b * 59.5 psi
The holts in this Hardhat drift were at 3 foot spacing, meaning the
required yield force per holt was
Ty = 9 x 1UU x 59.5 - 77,000 pounds
Since only 3/4" bolts were used, the gallery should have failed
according to the method of calculation.
The rock in this Hardhat
drift broke to a depth of 1 1/2 to 2 feet.
5.4
CONCLUSION
An empirical relationship has been presented by the Omaha District
of the Corps of Engineers which gives the support pressure required
to preserve a given size of tunnel when subjected to a given level
of strain.
By casting this relationship in the form o f an energy
comparison it is possible to assess the effect of differing weapon
sizes and wave durations, thus the results of one experiment with
a given characteristic ground motion can be related to another
experiment with different wave parameters.
118
REFERENCES
1.
Ambraseys, N. N. and Hendron, A. J., "dynamic Behavior of Rock
Masses". Rock Mechanics in Engineering Practice. J g ...i Wiley and
Sons, New York, 1968.
'
2.
Bonssinesq, J., "Application des potentials it 1 etude de la
equilibre et du movement des solides elastique", Gauthers-Viliars,
Paris, 1895.
3.
Duncan, J. M. and Goodman, R. E., "Finite Element Analyses of
Slopes in Jointed Rock", Report No. TE-68-1, U. S. Army Engineers
Waterways Experiment Station, Vicksburg, Mississippi, 1968.
1*.
Ewoldsen, H. M. and McNiven, H. D., "On the Theory and Design of
Rock Bolted Tunnels", Report No. 68-15, Structural Engineering
Laboratory, University of California, Berkeley, 1968.
5.
Goodman, R. E. "Analysis of Structures in Jointed Rock", Tech.
Report No. 3, U. S. A m y Corps of Engineers, Omaha District, 1967*
6.
Goodman, R. E., "Effects of Joints on the Strength of Tunnels",
Tech. Report No. 5* U. S. Army Corps of Engineers, Omaha District,
1968.
7.
Jaeger, J. C. and Cook, G. W . , Fundamentals of Rock Mechanics,
Methuen and Co. LTD., 1969.
8.
Lang, T. A., "Rock Behavior and Rock Bolt Support in Large
Excavations", Civil Engineering, Vol. 28, 1958.
9.
Lang, T. A., Unpublished Course Notes for Rock Mechanics, 1965*
s
10.
Kolsky, H., Stress Waves in Solids, Dover Publications, Inc.,
New York, 1963.
11.
Mindlin, R. D., "Force at a Point in the Interior of a Semi-infinite
Solid", Proc. First Midwestern Conference of Solid Mechanics,
University of Illinois, 1953.
12.
Smart, J. D. and Heitmann, D. G., "Factors Which Influence Survival
of Backpacked Sections Subjected to Nuclear Explosions", Operation
Flint Lock, Event Pile Driver and Operation Nougat, Shot Hard Hat,
to be published by U. S. Army Corps of Engineers, Omaha District,
SECRET.
APPENDIX I
by Iraj Farhoomand
Elastic two body analysis applied to tunnel support problem
(see Chapter 3).
120
Assumptions
a) I and II are elastic
b) Modulus of elasticity of I is different from modulus of elasticity i
c) Wave is in the direction of the system
«
d)
e) ^
#
l 2
„2
9 U1
3x2
4
3t2
for
X
3u_
z
3x
for
X = o
U1 = u2
for
X = 0 — =►
u
for
X = ¿2 = *
3x
= 0
oux
-a,x
A1 e
+ B e 'L
►
with a, = —
(1)
P = a,
(2)
Ol A 1 - ax B 1
(3)
*1 - h = 0
a
a2
e^
zkr
e
-on
-
A n
+
b2 e
*l,x" ^2 ,x
(2)
e
a2 A2 + a2 B2 =
- 0
n
= 0
121
*1
-
a» = —
C1
A1 + B1 - A2 - B2 = 0
(4)
*2
(1)
<t>2
=0
oux
-oux
A2 e
+ B2 e
ot^t
(
3
P(s)
*l,x-
1
*2
-M
2
(j)
= s
,xx
C1
p (t)
ou-
¡2
A
oo
X =0
*1
i 3 ui
=
»
1
x«—
1
A
oo
C2
C1
3u
i.
9x
*L
2
c2
(3)
(4)
Al “
C1 s
B1 e
-<Vi)
I
- a ^
e
(3) becomes i f we re p la c e
â- e
- V i
+
B1 e
by i t s v alu e
- 2V i
+ B! - A j - B2
-
0
Í- “V lA y B 2 - Mle
1 -
(m)
i - 2 0 .1 .
11
1 + e
I f we re p la c e A1 by i t s v alu e in (2)
“ 1 *1
(2) g iv e s
B1 =
“ 2 A2 - \
a
P
n A0 + n B^ - n 77“ e
2
“ OL
(n -
mCl^) A2 + (n +
e
h
- P e
-2V
—ot 0
l 1
=
(n)
i 1
-Il
mût A0 - mOL B0 - m e
mo^) B2
2
»
2
2
1e -2V 1
\
- 2 P e
A2 = - b2 e
2
,1
- 1■ - e
-a £
1X
-2V i
1
" 2 a2Â2
- (n - mo^) B2 e
- 2 a 2£2
) B
= - 2 P e
- 2 P e“ V l
B2 =
-a 0
il
1,
- 2 a2 h \
n il - e
1 + md2 f1 + e - 2a2Â2|
V
'
, x , 11 +. e -2x = e -x (e + e 'x ) = 2 e "x «
X
But /
-2x
“X , X
- x N 0 -x . ,
1 -e
= e
(e - e ) = 2 e
sin h x
122
-PL JL
11
,
- 1
J
P e
" a i Âl
-a^l
B„ =
-a ^ 4 e
- ‘M i
(sin h a^A^) e
-a-A_
(sin h
+ 4 a2 e
-(a.JL + M o)
(cosh O j£^) (cosh 0.2 ^ 2 ^
B„ =
B„ *
A_ =
“OC^A—
* 2 ,x (V
= a2 A2 e
F = E2 *2,* (V
" a2 B2 6
. a2Ä2
A2 6
= E2 a2
_a2Ä2
-
B2 e
- E2 s 2 (P c x )
F =
2 s
M / sinh s —M
c 0 (sinh s —
21
Cl /
l
- c.
c2
F =
123
/
M (cosh
/
cosh s —
1
C1
Ä2
s — 1
c2
tHj
-2 P e
Assumption;
If c2 «
(safe side)
P E
F =
Assumption
2
c
2
✓
S
= i (2 n-1)
1
d_
ds
1
cosh
x
G
F
j
z
S1
i
2n_! c1
2
I
1
cosh s —
c2
G(w)
F ^
wt
6
w
(w roots of F)
f
12k
+00
a
-1
,2 n - l
V
o
t
(- 1 )° e
cosh — I (cosh — |
„no
+00
+
W
4
2ii-l C1 . 12
i cos —y — * -s- Tr
2 c2
K1
M
~
C1
,2 n - l
2
CL7T
...( - D n
22 <
c2 1
2 n -l
2 * ¿1
—
(2 n - l )i r c . t
2 “ i « -1 *
.
—
s r ^
2 n -l n
*1 c° s —
22
^ * *7 *
+00
2 c2 ( - l ,
(2 n - l)ir c _ t
s in ------ j j — 2 -
, c°s 2 n - l
22
2 *. j21- ^n
(2 n - l)ir c 1 ( t - x )
F = 2 E„
P (x ) s i n j
(- l ) n
. .
2»t cos
dx
2 JL
_2n—1 —1 *. _£2 s
(2 n - l)7 r c2 ( t - x )
P ( ) s in
+ ( - 1) ” c .
¿2 cos
125
2 A,
dx
2 n - l 2 . £1 1
—
^ * 2 7 ”)
This is the pressure which is required to hold the part 2 in its place.
If
P (t ) = cst
max
1 - COS
2 (-1)“ cx
(2n-l) nrc. tdI
1
1
2%x
JJ
F = E,
(2n-l)
^2iHl- C1
2 C„
'l
2
ttcos I
+
\
17
n
i /
*2
|(2n-l) tt c2td^j
'
2(-l)n c2
|,1 - COS *
(2n-l)
^2n-l fl
2 c2
2^2
4
ttcos I
An over estimation of force required to resist the dynamic impulse is
K P
max
1 <K<2
which is measured at the first crack.
126
APPENDIX II
by Jacques DuBois
1.
Most critical integration of the velocity with time.
part, velocity
V
Let S = the surface abed.
A shift to the left (or to the right) by dt causes a change in S
ds * (v - tan a
) dt - (v + tan y
) dt
dt2
= - (tan a + tan y)
= - (tan
a + tan y)
which goes to zero as dt goes to 0.
Thus abed is the maximum area
127
2.
Value of the momentum integrated from
to Tcr^t + tg where Tcr^t - a
in section (1) of this appendix;
time — — ---^
t
(1 - 6) td
B
fcd " CB
e = :---------fcd
(1 - e> fcd _ vm ~ v
fcd
"
giving
3 ym
v
128
vm
fcd
Momentum M = pc
1
«y
o
v
vdt =
id
/•
/
pc
ci
vdt -
id_
J
J
o
L o
J
t2
(3v ) (3 tr)
in
tj
L
s- m d
i
f vdt -
S
>
vdt
J
. (Bv.) (8 (td - tr)
2
32 v
S1 + s2 =
S -
(S. + s 2 ) =
(tr
Vm fcd
+ td -
g2 V
pcv t
Momentum = ----2— SL
fcd
3.
the total energy
Integration of V dt
t
B
I
Jl
V
(1 - 3) td
t - (1 - 3) td
129
vm (1 " ß2) fcd
,
(1 - g"6)
2
tr )
o
J
2
E
= pc
p 'd
ci
-,
H
2
2
v 3d t
=
pc
J
v2dt
-
f
v 2d t
-
J
v 2d t
=
PC
S
o V
3
“ o
o
"*
m
Cs1 + s 2 >
3
8vm
$ \ -i
-
fcl
J?ߣ
3
vm
2
td - ßft e t r
evm + % e (td - t r ) ßvm)
130
(i - ß3)
I
DISTRIBUTION LIST
(Number of Copies of Report Shown in Parentheses)
No. of Copies
Form 1^73
Chief of Research and Development: Department of the Army;
ATTN: CRDNCB, CRDSTI (l), CRDPES, CRDES (l); Washington,
D. C. 20310
Chief of Engineers; Department of the Army; ATTN: CER (l),
ENGAS-I (2), ENGAS-IL (1), ENGBR (l), ENGCE (l), ENGCW-E (2),
ENGCW-EC (1), ENGCW-ED (l), ENGCW-EG (l), ENGCW-ES (l),
ENGCW-RR (1), ENGCW-Z (l), ENGMC-D (l), ENGMC-DE, ENGMC-E (l),
ENGMC-EA (1), ENGMC-ED (l), ENGMC-EP (1), ENGMC-ER (1),
ENGMC-M (1), ENGME-E (l), ENGME-EF (l), ENGME-ER (l),
ENGME-ET (l), ENGME-RD (2), ENGME-S (1), ENGML (1), ENGSA
Division Engineers, U. S. Army
(2)
Huntsville
Lower Mississippi Valley (2)
(2)
Missouri River
(2)
New England
North Atlantic (Resume only)
Engineer Divisions
(2)
North Pacific
(2)
Ohio River
South Atlantic (2)
South Pacific
(2)
(2)
Southwestern
Directors, U. S. Army Engineer Division Laboratories
South Atlantic (1)
(2)
New England
(2)
South Pacific
North Atlantic
(1)
(2)
Southwestern
(2)
North Pacific
(2)
Ohio River
Missouri River (2)
District Engineers, U. S. Army
(2)
Alaska
(2)
Albuqueroue
(2)
Baltimore
(2)
Buffalo
(2)
Charleston
(2)
Chicago
(2)
Detroit
(2)
Fort Worth
(2)
Galveston
(2)
Huntington
(2)
Jacksonville
(2)
Kansas City
(2)
Little Rock
Los Angeles
(2)
(2)
Louisville
(2)
Memphis
(2)
Mobile
(2)
Nashville
Engineer Districts
(2)
New Orleans
New York
(2)
Norfolk
(2)
(2)
Omaha
Philadelphia
(2)
Pittsburgh
(1)
Portland
(2)
Rock Island
(2)
Sacramento
(2)
St. Louis
(2)
St. Paul
(2)
San Francisco
(2)
Savannah
(2)
Seattle
Tulsa
(2)
(2)
Vicksburg
(2)
Walla Walla
Wilmington
131
2
(Number of Copies of Report Shown in Parentheses)
No. of Copies
Fora ÏI+73
President; Mississippi River Commission; CE; P. 0. Box
80; Vicksburg, Mississippi 39180 (l)
Research Center Library; U. S. Army Engineer Waterways
Experiment Station; P. 0. Box 631; Vicksburg,
Mississippi 39180 (10)
U. S. Army Cold Regions; Research and Engineering
Laboratory; (USA CRREL); Hanover, N. H. 03755 (l)
U. S. Army Engineer School Library; Thayer Hall
(Bldg. 270); Fort Belvoir, Virginia 22060
1
Ballistic Research Laboratories; ATTN: AMXRD-BD;
Aberdeen Proving Ground, Maryland 21005
1
Coastal Engineering Research Center; ATTN: Library;
5201 Little Falls Rd. N. W . ; Washington, D. C. 20016
1
U. S. Army Engineer Nuclear Cratering Group; Lawrence
Radiation Laboratory; P. 0. Box 808; Livermore, Calif.
9^550
1
DEPARTMENT OF THE AIR FORCE
Research and Applications Br.; ATTN: AF/Preer;
Directorate of Civil Eng.; HQ USAF; Pentagon;
Washington, D. C. 20030
1
Office of Director of Defense Research and Engineering;
ATTN: Director Strategic Weapons; Rocm 3E129; Pentagon,
Washington, D. C. 20301
1
Headquarters, SAMS0 (AFSC); A1TN: MMHFI-Luedeking (l),
XRTBN; Norton A F B , California 921*09
1
SAMS0/DEE; ATTN: William A. Platt; AF Unit Post Office;
Los Angeles, California
900U5
1
DEPARTMENT OF THE NAVY
Naval Civil Engineering Laboratory; ATTN: Technical
Library L31; Port Hueneme, California 9301+1 (l)
Naval Facilities Engineering Command; Navy Department;
ATTN: William J. Bobisch, Chief Engineer; Washington,
D. C. 20390
132
1
No. of Copies
Form lit7 3
(Number of Copies of Report Shown in Parentheses)
OTHER DOD AGENCIES
Advanced Research Projects Agency; ATTN: Nuclear
Monitoring Research Office; lUOO Wilson Bird.;
Arlington, Va. 22209
1
Director; Defense Atomic Support Agency; Washington,
D. C. 20305 (1)
Test Command; ATTN:
TCDT-E; Sandia Base, New Mexico
87115
1
Administrator; Defense Documentation Center; Cameron Station;
(12), Building 5; Alexandria, Virginia 2231**
Director of Defense Research and Engineering; ATTN:
Assistant Director Nuclear Programs; Assistant Director
Strategic Weapons; Technical Library; Washington, D. C.
20301
3
OTHER GOVERNMENT AGENCIES
U. S. Bureau of Mines; ATTN: Leonard Obert, Science
Adviser-Mining Research; Building 20, Denver Federal
Center; Denver, Colorado 80225 (l)
U. S. Bureau of Mines; ATTN: J. R. McWilliams, Division
of Mining Systems; Washington, D. C. 2021*0 (5)
U. S. Bureau of Reclamation; ATTN: M. H. Logan, Chief,
Geology and Geotechnology Branch; Bldg. 67 , Denver
Federal Center; Denver, Colorado 80225 (l)
U. S. Bureau of Reclamation; ATTN: D. L. Misterek,
Code 1512; Bldg. 56 , Denver Federal Center, Denver,
Colorado 80225 (l); Mr. G. B. Wallace (l)
U. S. Department of Commerce; N0AA - National Ocean
Survey Lake Survey Center; 630 Federal Bldg. & U. S.
Courthouse; Detroit, Michigan 1*8226 (2)
California Dept. Water Resources; ATTN: L. B. James,
Chief Geologist; P. 0. Box 388; Sacramento, Calif. 95802
California Dept. Water Resources; ATTN: J. A. Wineland,
Chief, Design Branch, Div. of Design & Construction;
P. 0. Box 388, Sacramento, California 95802 (l)
133
(l)
No. of Copies
Form 1^73
(Number of Copies of Report Shown in Parentheses)
OTHER GOVERNMENT AGENCIES (Gont'd)
Federal Highway Administration; bOO Seventh Street, S.W.;
Washington, D. C. 20591 (l)
Federal Highway Administration; Office of Research;
ATTN: W. J. Halstead, Chief, Materials Division;
Washington, D. C. 20591 (l)
\
Highway Research Board; ATTN: Librarian; 2101 Constitution
Avenue N . W . ; Washington, D. C. 20bl8 (l)
U. S. Geological Survey; ATTN: H. W. Olsen, Engineering
Geology Branch; 3^5 Middlefield Road; Menlo Park,
California 9b025 (l)
U. S. Geological Survey; ATTN: E. C. Robertson; Acorn
Bldg.; 8001 Newell St.; Silver Spring, Maryland 20910
(l)
Tennessee Valley Authority; ATTN: R. B. Connelly,
Manager's Office, Engineering Design and Construction;
700 Union Bldg.; Knoxville, Tenn.
37902 (2)
Tennessee Valley Authority; ATTN: J. H. Coulson;
300 Arnstein Bldg.; Knoxville, Tenn.
37902 (l)
FOREIGN OFFICE
Chief of Engineers; Department of the Army;
ATTN: ENGME-AS; Washington, D. C. 2031b
1
FOR FORWARDING T O :
AWRE; Foulness Island; Southend-on-Sea; Essex, England
1
Canadian Forces Liaison Officer (Engr); USAMERDL,
Fort Belvoir, Va. 22060 for: Dr, N. B. Hutcheon;
Canadian Joint Staff; Department of Transport: Div. of
Bldg. Research, National C Research Council of Canada;
Ottawa; Construction Engineer; Air Service Branch;
Ottawa, Ontario, Canada
5
Nova Scotia Technical College; ATTN: Dr. G. G. Meyerhof,
Dept, of Civil Engineering; Halifax, N. S., Canada
1
13b
No. of Copies
Fora 1^73
(Number of Copies of Report Shown in Parentheses)
UNIVERSITY
1
University of California; ATTN: R. E. Goodman,
Assoc. Prof.; Dept, of Civil Engineering; U75 Davis Hall;
Berkeley, California 9^720 (l)
University of California; ATTN: Lawrence Radiation
Laboratory Technical Information Dept. L-3; P. 0. Box 808;
Livermore, California 9^550 (l)
University of California; Los Alamos Scientific Laboratory;
ATTN: Report Librarian; P. 0. Box 1663; Los Alamos,
N. Hex. 8 7 5 M
Colorado School of Mines; ATTN: John J. Reed, Dept, of
Mining Engineering; Golden, Colorado 80U01 (l)
Cornell University; ATTN: G. A. Kiersch, Chairman;
Dept, of Geological Sciences; 125 McGraw Hall,
Ithaca, N. Y. 1U850 (l)
Colorado State University; Foothills Engineering Research
Station; ATTN: Prof. K. S. Lane; Ft. Collins, Colorado
80521
(1 )
Cornell University; ATTN: Dr. D. A. Sangrey, Assoc. Prof.,
Dept, of Geotechnical Engineering; School of Civil and
Environmental Engineering; Ithaca, New York 1U850 (l)
Florida State University; ATTN: E. G. Henneke; School of
Engineering Science, Tallahassee, Florida 32306
Harvard University; ATTN: Prof. A. Casagrande; Pierce
Hall; Cambridge, Mass. 02138
University of Illinois; ATTN: E. J. Cording; 2221 CE Bldg.,
Urbana, Illinois 61801 (l); R. B. Peck; 2230 CE Bldg,
(l)
University of Illinois; Dept, of Civil Engineering; ATTN:
Dr. D. U. Deere (l); Dr. N. M. Nevmark (l); Prof. A. J.
Hendron, Jr. (l); Metz Reference Roooi, B106 C. E. Bldg.;
Urbana, Illinois 6l801 (l)
University of Illinois; Department of Geology; ATTN:
Dr. F. A. Donath (l); F. D. Patton (l); Urbana, 111.
Iowa State University; ATTN: L. V. A. Sendlein,
Department of Earth Science; Ames, Iowa 50010 (1)
I
135
61801
No. of Copies
Form 1^73
(Number of Copies of Report Shown in Parentheses)
UNIVERSITY (Cont*d)
Louisiana State University; ATTN j Dr. 0. A. Nance,
Consultant to RAND and DASA; P. 0. Box 16006-LSU;
Baton Rouge, La. 70803
1
Massachusetts Institute of Technology; ATTN: R. C.
Hirschfeld, Room 1-330 (l); Asst. Prof. H. H. Einstein,
Room 1-380 (1); Prof. W. F. Brace, Roam 5^-720 (l);
Cambridge, Mass. 02139
University of Minnesota; ATTN: Prof. C. Fairhurst;
Dept, of Civil and Mineral Engineering; Minneapolis,
Minnesota 55^55 (l)
University of Missouri at Rolla; ATTN: Dr. N. B. Aughenbaugh,
Chairman; Dept. Mining, Petr., & Geol. Engrg. (l);
Dr. G. B. Clark; Director, Rock Mechanics & Explosives
Research Center (l); Rolla, Missouri 65^01
University of New Mexico;
Research Facility; ATTN:
Triandafilidis; Mr. P. A.
P. 0. Box 188; University
Eric H. Wang Civil Engineering
Dr. E. Zvcyer; Dr. G. E.
Abbott; Mr. D. E. Calhoun;
Station, Albuquerque, New Mexico
City College of New York; Dept, of Civil Engineering;
ATTN: Prof. C. A. Miller; New York, N. Y. 10031
(l)
Pennsylvania State University; ATTN: R. Stefanko,
Assistant Dean, Earth & Mineral Sciences Continuing
Education; 110 Mineral Sciences Building; University
Park, Pa. 16801 (l)
(l)
South Dakota School of Mines & Technology; Department
of Mining Engineering; ATTN: Dr. E. Hoskins (l);
Prof. E. H. Oshier (l); Rapid City, South Dakota 57701
University of Texas at Austin; Dept, of Petr. Engineering;
ATTN: Dr. K. E. Gray; Austin, Texas 78712 (l)
136
H
1
Pennsylvania State University; Dept, of Architectural
Engineering; ATTN: J. S. Futrick, Admin. Aide;
101 Engineering "A" Bldg., diversity Park, Pa. 16802
Purdue University; School of Civil Engineering;
ATTN: Prof. Wm. R. Judd; Lafayette, Indiana ¿7907
87106
(Number of Copies of Report Shovn in Parentheses)
No. of Copies
Form 1473
UNIVERSITY (Confd)
Texas A & M University; Center for Tectonophysics;
ATTN: Dr. Melvin Friedman (l); Prof. J. Handin,
Director (l); College Station, Texas 77843
Texas A & M University; College of Geosciences; Center
for Tectonophysics; College Station, Texas 77843 (l)
Utah State University; Engineering Experiment Station;
ATTN: Dr. R. K. Watkins, Associate Director;
Logan, Utah 84321
1
Virginia Polytechnic Institute; Mining Engineering
Department; ATTN: Lawrence Adler (l); Dr. C. Haycocks (l);
Blacksburg, Va. 24060
INDUSTRY
The Aerospace Corporation; P. 0. Box 5866 ; San Bernardino,
California 92408; ATTN: S. B. Batdorf, B2/2020;
M. Watson; W. Pfefferle (l)
2
Analytic Services, Inc.; ATTN: Geo. Hesselbacher;
5613 Leesburg Pike; Falls Church, Va. 22041
1
Applied Theory, Inc.; ATTN: Dr. J. Trulio; 1010 Westwood
Blvd., Los Angeles, California 90024
1
AVC0 Systems Division; Research Library; 201 Lowell
Street, Wilmington, Mass. OI 887
1
Battelle Memorial Institute; ATTN: Dr. R. W. Klingensmith;
505 King Avenue; Columbus, Ohio 43201
1
Bell Telephone Laboratories; ATTN: G. F. Weissmann,
Roan 1A-105A; Mountain Avenue, Murray Hill, N. J. 07974
1
Bell Telephone Laboratories; ATTN: R. W. Mayo;
Whippany Road, Whippany, N. J. 07981
1
Boeing Company - MASD Library; ATTN: 23-99 R. E. Shipp
for L. E. Fleishman; P. 0. Box 3955; Seattle, Wash. 98124
1
Boeing Company - ATTN: J. A. Blaylock, 2-5410, 8C-4l;
K. Levien, Orgn. 2-5511 M/S 89-70; Mr. H. G. Leistner,
Aerospace Group, Research Division, M/S 89-70; P. 0. Box
3999, Seattle, Washington 98124
3
137
No. of Copies
Fora i r b
(Number of Copies of Report Shown in Parentheses)
INDUSTRY (Contfd)
Boeing Company; ATTN: Technical Library; P. 0. Box
3999; Seattle, Washington 9812It
1
Engineering Societies Library; ATTN: Howard Gordon;
3t5 East l*Tth Street, New York, N. Y. 10017 (l)
General American Research Division; ATTN: Dr. L. B.
Holmes; 7 ^ 9 N. Natchez Avenue; Niles, 111. 606U 8
1
LIBRARY, General Electric Company Space & RESD Divs.,
ATTN: Mr. L. Chasen, Manager; P. 0. Box 8555;
Philadelphia, Pa. 19101
1
General Electric TEMPO; ATTN: DASIAC; P. 0. Drawer QQ,
Santa Barbara, California 93102
1
General Motors Technical Center; Manufacturing
Development /33/; ATTN: W. M. Isbell; Warren, Mich.
1
L8090
Gulf Radiation Technology; ATTN: H. R. Kratz;
P. 0. Box 608; San Diego, California 92112
1
IIT Research Institute; 10 West 35th Street;
ATTN: Document Library (l); Dr. K. E. McKee (l);
Chicago, Illinois 6o6l6
Lockheed Missiles & Space Company, ATTN: Dr. R. E.
Meyerott/C. C. Old; P. 0. Box 50U; Sunnyvale,
California 9^088
2
Mueser, Rutledge, Wentworth & Johnston; ATTN:
Rutledge; 1*15 Madison Avenue, New York, N. Y.
1
N0AA Environmental Research Laboratories; ATTN:
Rinehart; Boulder, Colorado
80302
P. C.
10017
Dr. J. S.
1
The RAND Corporation; ATTN: Dr. H. L. Brode; Dr. C. C. Mow;
1700 Main Street, Santa Monica, California 90U 06
2
Research Analysis Corporation; ATTN:
Route 123; McLean, Virginia
22101
1
Documents Library;
Sandia Laboratories; ATTN: M. L. Merritt, Dept. 9150;
W. R. Perret, Division 9111; P. 0. Box 5800,
Albuquerque, N. M. 87115
138
2
Ho, Of Copies
P o m 1^73
(Number of Copies of Report Shown in Parentheses)
INDUSTRY (Cont*d)
Test Command, ATTN:
New Mexico 87115
TCDT-E; Sandia Base,
1
Shannon & Wilson, Inc.; ATTN: Dr. R. P. Miller;
1105 N. 38th Street, Seattle, Washington 98103 (l);
S. D. Wilson (1)
Southwest Research Institute; ATTN: R. C. DeHart;
8500 Culebra Road; San Antonio, Texas 78228
1
Systems, Science & Software; ATTN: Document Control;
P. 0. Box 1620; La Jolla, California 92037
1
TRW Systems (Rl/1138); ATTN: Norman Lipner;
1 Space Park; Redondo Beach, California 90278
1
TRW Systems Group; ATTN: Dr. J. L. Merritt (l);
F. A. Pieper; P. 0. Box 1310, San Bernardino,
California 92U02
1
Paul Weidlinger, Consulting Engineer; 110 East 59th
Street, ATTN: Dr. M. L. Baron; New York, N. Y. 10022
1
Woodward-Clyde & Associates; ATTN: A. T. Harrigan,
Librarian; P. 0. Box 2U075; Oakland, California 9^623
Woodward-Clyde & Associates; ATTN:
758 N. Batavia; Orange, California
R. L. McNeill;
92668 (l)
Woodward-Clyde & Associates, Inc.; ATTN: Dennis Leary;
31 Orton Road; West Caldwell, New Jersey 07012 (l)
Woodward-Lundgren & Associates; ATTN:
C-Y Chemg;
P. 0. Box 21*075; Oakland, California 9^623 (l)
139
(l)
rr:
UNCLASSIFIED
•
*
; ?t N
. f
Security C la ssific a tio n
D O C U M EN T C O N T R O L D A T A - R & D
(S e c u rity c la s s ific a tio n o t t it le , body o f a b s tra c t and in d e xin g an n o ta tio n m ust be entered when the o v e ra ll re p o rt Is c la s e ilia d y
. O R I G I N A T I N G A C T I V I T Y (C orporate au thor)
2a» R E P O R T S E C U R I T Y C L A S S ! Ft C A r f ë â
1
UNCLASSIFIED
Omaha District, Corps of Engineers
Omaha, Nebraska 68102
2b. G R O U P
3. R E P O R T T I T L E
Static and dynamic Analysis of Rock Bolt Support
4. D E S C R I P T I V E N O T E S (T y p e o t re p o rt end In c lu s iv e de tee)
Interim
8. A U T H O R ( S )
( F ir s t name, m id d le in it ia l, le e t neme)
Richard E« Goodman and Jacques DuBois
«. R E P O R T D A T E
January
Be.
7 «. T O T A L N O . O P P A O E S
1971
C O N T R A C T OR G R A N T NO.
DACAU5-67-C-OOI5
6. P R O J E C T
lb .
NO. O F RE FS
12
lUl
»«. O R I G I N A T O R ' S R E P O R T N U M f e E R ( S )
Mod. P002
Technical Report No. 6
NO.
UDM7Ö012A0K1
9b. O T H E R R E P O R T N O ( S ) ( A n y o t h e r n u m b e r s t h a t m a y b e a s a i g n e d
TASK:
th is re p o rt)
09
<*■ WORK UNIT:
002
1 0. D I S T R I B U T I O N S T A T E M E N T
Approved for public release; distributioi1 unlimited.
I I. SU PPLEM EN TAR Y NOTES
12. S P O N S O R I N G M I L I T A R Y
Reference: Technical Reports Nos. 2,
3 and 5s September 1966, 1967 and 1968;
same originating agency
A C T IV IT Y
Department of the Army
Office of the Chief of Engineers
Washington, D. C. 20315
13. A B S T R A C T
This report describes progress in a continuing effort to develop and evaluate
methods which can be used to design underground openings to survive blast loadings.
It includes discussion of the action of rock bolts under static loads and considers
aspects of the interaction between rock and rock belt under dynamic loads. Only
computational methods were u s e d in this study.
First, closed form solutions for point loads are summed and superimposed to
examine stresses induced by patterns of rock bolts around tunnels in linearly
elastic material. The stress fields are compared to rock strengths according to
simplified failure criteria, to appreciate the relative strengthening effect of
different combinations of bolt and rock parameters. It was found that very
substantial bolt pressures are required, e.g., 10% of the maximum applied pressure,
to restrict rock breakage in ideally elastic material.
Then elastic-plastic material behavior is considered. Stresses induced by
unequilibrated line loadings on the inner circumference of the tunnel are used to
simulate rock bolt patterns. It is found that the rock bolt strengthening effect
can more easily be substantiated in veaker materials. For example, vhen rock
inside the "plastic” zone was taken as cohesionless, less than lji of the blast
pressure is a sufficiently high rock bolt pressure to provide significant
strengthening effect.
dynamic considerations are discussed in terms of an energy balance for the
case of a plane rock wall bolted in a regular pattern which receives a stress
I
I p!nBr"ToS5r"77Sw3r^«^!Sc5?oSlvo5rMS9»rTJ!^51^!HiSBu?
1473
U U
i m v h
« M O ttt.r o i.iW Y u .« .
.
UNCLASSIFIED
USULABSIFUSP
èecurlty Clamlficatlon
wave impulse from inside. The problem is examined in two ways: First a
calculation is made of the kinetic energy of the system in the most serious
increment of time during the response, assuming the holt to behave elastically.
Then, the total vork during all of the blast response period is considered,
presuming the bolt damage to be cumulative. The objective of these computations
is to provide a basis for scaling survivability conclusions from one experiment
to another. Reference is made to Hardhat and Piledriver experiments.
LINK A
ROLE
WT
K E Y WO R DS
LINK
ROLE
Energy Absorption
Elastic Analysis
Elasto-Plastic Analysis
Joint Influence
Joint Properties
Jointed Rock
Rock
Rock Bolts
Rock Failure
Rock Mechanics
Rock Stress
Ihi
UNCLASSIFIED
I
I
I
//so zs.
I
I
I
4
I
I
I
I
I
I
I
I
I
1
I
I
I
i
Gì i
V)
ave
Download