KIMZO WEEKLY PROGRESS REPORT REPORT NO. 011 1. PROJECT SUMMARY PROJECT: PROPOSED HATCHERY. CLIENT: UZIMA CHICKEN KISUMU LOCATION: KERICHO Weekly Report No. 11 Client: UZIMA CHICKEN KISUMU Architect ARC. MELLISSA Quantity Surveyor PLANHOUSE LIMITED. Main Contractor: KIMZO CONSTRUCTION AND TRADE LTD Electrical Contractor KIMZO CONSTRUCTION AND TRADE LTD Plumbing Contractor KIMZO CONSTRUCTIONS AND TRADE LTD. Contract sum Ksh 47,444,470 Amount paid Ksh 33,769,726 Percentage paid 71% Contract start date October 09, 2023 Contract Completion Date: January 09, 2024 Contract Period 90 Days Period elapsed 84 days Percentage time elapsed 93% Project status 78% Page 1 of 12 DATE 30/12/2023 KIMZO Week Starting: 25/12/2023 DATE 30/12/2023 WEEKLY PROGRESS REPORT REPORT NO. 11 Week Ending: 30/12/2023 Reporting Date: 30/12/2023 2.0 PROGRESS ON SITE 2.1 MAIN WORK PROGRESS MAIN WAREHOUSE ITEM NO 1.0 1.1 1.2 1.3 DESCRIPTION % WORK DONE COMPANY 100% 100% 100% 100% KIMZO KIMZO 100% 100% 100% 100% 100% 100% 100% KIMZO 2.1 2.2 2.3 2.4 2.5 2.5 Mobilization and planning Site clearance Employees induction Construction site store, temporary shed, pit latrine and consultant office Excavating to reduced levels Warehouse setting out Trench and column pit excavation Extra over excavation in rock Concrete blinding to strip footing and column bases Formwork to strip footing and column bases Steel reinforcement to strip footing, column bases and sub column starters Casting concrete to strip footing and column bases Foundation walling Ground beams Backfilling and compaction Murram blinding Electrical and mechanical pointing 100% 100% 100% 100% 100% 90% KIMZO 2.6 2.7 2.8 Laying 1000mm brc to sections with masonry wall Casting slab to section outlined by masonry walls Setting column kickers 100% 100% 100% KIMZO 1.4 1.5 1.6 1.7 1.8 1.9 2.0 Page 2 of 14 COMMENTS KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO To finish on 29/1/24 KIMZO DATE 30/12/2023 WEEKLY PROGRESS REPORT REPORT NO. 11 2.9 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 Excavating rock outcrop at A11 Steel reinforcement for superstructure columns Formwork to columns Casting concrete to columns Setting out and superstructure walling Formwork to beam Reinforcement bars to beam Casting beams Rendering and plastering 100% 100% 100% 100% 100% 97% 97% 95% 95% KIMZO 3.8 Roofing and rainwater disposal 15% KIMZO 3.9 Windows 25% KIMZO 4.0 Doors 15% KIMZO 4.1 Ceiling finishes 15% KIMZO 4.2 4.3 Painting Floor slab and floor finishes 15% 25% KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO KIMZO 4.4 Electrical works 15% KIMZO 4.5 Mechanical works 10% KIMZO Cont. KIMZO curing EXTERNAL WORKS SEPTIC TANK AND SOAKPITS 1.0 1.1 1.2 1.3 1.4 1.5 1.6 Excavating for septic tank Ditto extra over excavation to rock Formwork to edges of floor bed 50mm thick concrete blinding 150mm thick sloped floor bed 200mm thick natural stone wall Reinforcement and casting scum baffle walls Page 3 of 14 100% 100% 100% 100% 100% 100% 100% KIMZO KIMZO KIMZO KIMZO KIMZO To finish 6/1/24 To finish 24/1/24 To finish 22/1/24 To finish 22/1/24 To finish 23/1/24 To finish on on on on on 6/2/24 To finish on 29/1/24 To finish on 30/1/24 To finish on 30/1/24 KIMZO 1.7 1.8 1.9 2.0 DATE 30/12/2023 WEEKLY PROGRESS REPORT REPORT NO. 11 100% 100% 100% External rendering Plastering Excavating pits for soak pits FENCE AND GATE 1.0 1.1 1.2 1.3 Excavation and earthworks Chain-link poles erection 4 no. lines barbed wires 2.1m high chain-link fence 100% 100% 100% 0% 1.4 Car and peoples dip and gate 0% KIMZO To finish on 15/1/24 To finish on 20/1/24 1.5 PAVED AREAS 1.0 1.1 1.2 Site preparation and excavation Disposal of excavated materials Surface treatment 100% 100% 0% 1.3 1.4 filling Precast concrete units 0% 0% KIMZO To finish on 12/1/24 To finish on 9/1/24 To finish on 18/1/24 SENTRY 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 Setting out and excavation Murram blinding and strip footing Foundation walling Backfilling and compaction Soil sterilization, dpm and floor bed Superstructure walling Ring beam Roofing and rainwater disposal 100% 100% 100% 100% 100% 100% 100% 0% 1.8 Doors and windows 0% 1.9 internal, external and floor finishes 50% 2.0 Painting 0% Page 4 of 14 KIMZO To finish on 20/1/24 To finish on 20/1/24 To finish on 20/1/24 To finish on 20/1/24 KIMZO DATE 30/12/2023 WEEKLY PROGRESS REPORT REPORT NO. 11 GENERATOR HOUSE 1.0 Excavation 100% 1.1 Disposal of excavated materials 100% 1.2 Sub structure works 100% 1.3 Reinforced concrete frame 100% 1.4 Superstructure walling 100% 1.5 Roofing and rainwater disposal 0% 1.6 Window grills and door 0% To finish on 20/1/24 To finish on 20/1/24 To finish on 20/1/24 To finish on 20/1/24 To finish on 20/1/24 To finish on 20/1/24 To finish on 20/1/24 2.2 WEEK PLAN FOR THE NEXT ONE WEEK DATE Monday 1/1/2024 Tuesday 2/1/24 Activity Ring beam formwork, reinforcement bars and concreting Rendering and plastering Roofing Casting slab at washroom area Electrical pointing Ring beam formwork, reinforcement bars and concreting Rendering and plastering Roofing Page 5 of 14 Targets Company 95% KIMZO 65% 15% 100% 90% 95% 90% 15% KIMZO KIMZO Wednesday 3/1/2024 Thursday 4/1/2024 Friday 5/1/2024 Saturday 6/1/2024 DATE 30/12/2023 WEEKLY PROGRESS REPORT REPORT NO. 11 Ring beam formwork, reinforcement bars and concreting Rendering and plastering Roofing 95% Electrical pointing Barbed wire 90% 95% Ring beam formwork, reinforcement bars and concreting Rendering and plastering Roofing Formwork, steel reinforcement for septic tank Electrical pointing Doors and windows Barbed wire Ring beam formwork, reinforcement bars and concreting Rendering and plastering Truss fabrication Casting slab for septic tank Doors and windows Barbed wire 95% Rendering and plastering Roofing Doors and windows Barbed wire Page 6 of 14 90% 15% 90% 50% 100% 60% 100% 90% 65% 100% 15% 95% 100% 15% 30% 95% KIMZO WEEKLY PROGRESS REPORT DATE 30/12/2023 REPORT NO. 11 2.3 WORK PLAN UNTIL 16/2/2024 ITEM 1.1 1.2 1.3 1.4 1.5 1.6 1.7 DESCRIPTION DESCRIPTION Main warehouse Builders work at the warehouse Chain-link fence and gates Paved areas Septic tank Roofing and rainwater disposal Electrical and mechanical works Sentry and generator house %ANTICIPATED 100% 100% 100% 100% 100% 100% 100% Page 7 of 14 REASONS FOR DELAY EFFECTS OF DELAY ACTION KIMZO DATE 30/12/2023 WEEKLY PROGRESS REPORT REPORT NO. 11 3 WORK PROGRAMME AND PROGRESS ITEM 1.1 DESCRIPTION REASONS FOR DELAY EFFECTS OF DELAY COMMENTS General work General change in design More time used progressing well even though we’ve experienced some delays Unexpected topography More time used leading to mass excavations and filling Bad weather Mitigated to compensate Hours wasted 4. QUERIES REPORT AND RFIs, SUMMARY 4.1 RFIs RFI DESCRIPTION No 1.1 Date of issue 4.2 Issues discussed and decision reached 1.1 Prepare 75mm spacers to be used in BRC laying 1.2 Introduce short columns all round 1.3 Use of water while compacting Page 8 of 14 Comments ACTION Work overtime/ engage more labour per action Work overtime/ engage more labour per action Work overtime/ engage more labour per action KIMZO 1.4 1.5 WEEKLY PROGRESS REPORT DATE 30/12/2023 REPORT NO. 11 Excavate rock outcrop to achieve suitable depth for column base Cast strip slab to section with walls with overlapping BRC mesh and slab sloping after 225mm from wall to 100mm for proper connection when laying overall slab 4.3 Concerns and assistance needs 1.0 Depth of channel grating 1.1 Does the slab need to slope towards the channel gratings 1.2 Advise on surplus excavated materials 1.3 Mechanical and Electrical engineers plan for site visit to give guidance at the initial stage 1.4 Do we need consumer units to partition power supply to avoid too many conduits and cables crossing the expansion joint 1.5 Can we have the channel grating at setter room exit at alternative point to avoid crossing the expansion joint 1.6 Can we have wall separating electrical room and clean egg store be masonry 1.7 Provide detailed electrical drawings 1.8 Provide details for proposed channel at generator house 1.9 Do we need to more than the 4lines of barbed that is provided for?. 2.0 Provide final details of paved area 5.0 Test certification Page 9 of 14 provided provided advised pending Approved though no official instruction pending executed KIMZO WEEKLY PROGRESS REPORT DATE 30/12/2023 REPORT NO. 11 5.1 Test carried out Description Murram testing Drilling test Machine cut block test Concrete cube test Status Approved Progress Failed Progress 5.2 Certificates Description Murram test certificate Machine cut block test Status Available Available 6. Permits, License or Approvals Received Description N.C.A Status progress 7. SAMPLES ON SITE No. 1 DESCRIPTION Wall panel Comments 8. HEALTH, SECURITY AND SAFETY REPORT Item Issue Comments Attached safety report 9. WEATHER REPORT ITEM No. DESCRIPTION Rainy days in the afternoon 2hrs lost each day due Page 10 of 14 KIMZO WEEKLY PROGRESS REPORT DATE 30/12/2023 REPORT NO. 11 to evening rains in the first and second months of the project time 10. MACHINE AND WORKFORCE ON SITE Machine list No company Excavator 1 Kimzo Mixer Roller Vibrator 1 0 2 Kimzo Kimzo Kimzo Average no of workers per day 70 laborers 11. MATERIALS ON SITE Ballast 30 tons Quarry dust 45 tons Foundation blocks 200 Ft Concrete blocks 1200 pcs Binding wire 3 rolls DPM Polythene 5 rolls Reinforcement bars lots A142 BRC Mesh 1 rolls Hoop iron 18 rolls Cement 200 bags Damp proof course[dpc] 6rolls Page 11 of 14 KIMZO WEEKLY PROGRESS REPORT DATE 30/12/2023 REPORT NO. 11 Roofing materials All on site River sand 60 tons Page 12 of 14 KIMZO DATE 30/12/2023 WEEKLY PROGRESS REPORT REPORT NO. 11 Weekly Safety Report Report Number: 0011 Date: 30/12/23 Week Start Date:25/12/2023 Week Ending Date: 30/12/23 Weekly Cumulative Safety Statistics S/# COMPANY AVERAGE WEEKLY POB 1 KIMZO 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Fatality Case (Fatal). Lost Workday Case (LWC). Restricted Workday Case (RWC). Medical Treatment Case (MTC). First Aid Case (FAC). Property Damage (PD). Near Miss (NM). Motor Vehicle Accident (MVA). Fire Incident (FI). Environmental Incident. Total Number of First Aid Cases. Total Number of Recordable Injuries. Number of Lost Work Days. Number of Restricted/ Job Transfer Days. Total Number of Days Lost. Safe Man Days. THIS WEEK FIGURES CUMULATIVE 70 0 0 0 0 3 0 0 0 0 0 3 0 0 0 0 7 0 0 0 0 3 0 0 0 0 0 3 0 0 0 0 70 UTILITIES WEEKS READINGS 1. 2. N/A Electricity consumption Water consumption 180,000 Ltrs/day Page 13 of 14 INITIAL READINGS N/A CONSUMPTION N/A KIMZO WEEKLY PROGRESS REPORT DATE 30/12/2023 REPORT NO. 11 Narration of Incident/Accident and Near Miss Reported This Week No incident recorded Other HSE Activities Description Safety Walkthrough This Week 3 Cumulative 30 Safety Audits 1 9 Workplace inspections 6 60 Safety inductions (Client) 0 0 Safety inductions (Kimzo) 1 10 Visitors induction 0 0 Safety Highlights Observations (Current Week) Sr. No Contractor Name N1. Kimzo construction and trade limited Observations Pending Closed 0 3 Observation Ensure all personnel are on closed shoes 1. Ensure timber with nails are properly handled 2. 3. Proper use of PPES at site 4. All visitors must be admitted to the site office before proceeding to the site area Page 14 of 14 KIMZO DATE 30/12/2023 WEEKLY PROGRESS REPORT REPORT NO. 11 Toolbox Topics / Training Delivered This Week Cumulative 60 6 List of Tool Box Topics TOPIC PERSONNEL TIME 1 Manual handling 45 15 minutes 2 Adverse Weather 45 15 minutes 3 Unsafe act & Unsafe condition 60 15 minutes 4 Tool & Equipment 60 15 minutes 5 Traffic control 15 15 minutes 6 Material handling 45 15 minutes 7 Means of communication 45 15 minutes Page 15 of 14