And., Intl.,J., Appl Sci., Eng., Tech, Vol 02, No 02, July 2022 e-ISSN: 2797-0442 RELIABILITY DISTRIBUTION SYSTEM ON LOAD BREAK SWITCH ADDITION AT PT. PLN (PERSERO) ULP LANGSA CITY USING RIASECTION TECHNIQUE COMBINED METHOD ON ETAP 14.1.0 Arnawan Hasibuan1, Andik Bintoro2, Salahuddin3, Rizka Dwi Meutia4 1234 Department of Electrical Engineering, Faculty of Engineering, Malikussaleh University, Lhokseumawe, Indonesia Abstract— PT. PLN (Persero) ULP Langsa city is one part of UP 3 langsa, the LS-05 feeder in section two is the location for placing several office buildings. Continuity stable distribution of electrical energy is one of the most important aspects in the distribution system. Based on these problems, the writer was inspired to consuct research with the aim of testing the reliability of the feeders LS-05 and LL-4 which was installed with LBS manuver motorized at both ends of feeders. The LS-05 feeder with section method SAIFI value is 2.2739 times/ customers/ year and SAIDI Value is 8.41995 hours/ customers/ year. For LL4 feeder witsh the same method SAIFI value is 2.28905 times/ customers/ year, then using RIA-Section technique combined method, LS-05 feeder have SAIFI value is 2,0219 times/ customers/ year, SAIDI value is 8,3082 hours/ customers/ year, LL-4 feeder have SAIFI value is 2.6574 times/ customers/ year and SAIDI 9.3008 hours/ customers/ year. This value indicates thet these two methods have succeeded in showing a reliability index is in accordance with SPLN due to the addition of LBS motorized. Keywords: SAIFI, SAIDI, RIA-Section, and LBS. This article is licensed under the CC–BY-SA license. 1. Introduction Continuity stable distribution of electrical energy is one of the most important aspects in the distribution system, to distribute electrical energy, PLN must use switching devices in network. Such as air break switch, recloser, and load break switch. PT. PLN (Persero) ULP Langsa city is one part of UP 3 langsa, the LS-05 feeder in section two is the location for placing several office buildings, such as the BNN building, the inspectorate office building, the agricultural building, then in section three there is the ummi hospital building, and BPJS.[1] Therefore the distribution of electricity must be stable in that feeder, to reduce the outage area and the number of customer disturbance then on the feeders LS-05 and LL-4 which was installed with LBS manuver motorized at both ends of feeders.[2] The addition pf load break switch wich is integrated with SCADA as a remote control system to regulate the supply of electrical energy to the distribution system when a disturbance occurs from feeder of LS-05 to LL-4 for load maneuvering. [3]To carry out this research, the author uses the combined method (RIA-Section Techniqueby combining the parameter of the momentary failure rate and parameters of the sustained failure rate. Where the parameter of the sustained failure rate pays attention to the temporary failure rate, so that the result are close to the reality on the job.[4] Received:July 2,2022 , Revised:July 10,2022 , Accepted:July 16,2022 https://doi.org/10.25077/aijaset.v2i2.42 AIJASET – Vol. 02, No. 02, July 2022. 57-64 https://doi.org/10.25077/aijaset.v2i2.42 2. Method The electric power system stars fro the transmission stage to distribution to custumers. Such as the power system components can be divided into five primary levels or subsystems, as shown in Figure 1 below:[5] Transmission lines Generator Primary distribution lines Secondary distribution lines Electrical load customers Figure 1. Power System Components The electric power distribution network is the part of the electric power system that deals directly with customers. [6]This system consist of a medium voltage distribution system and a low voltage distribution system. [7] In delivering electric power to consumers from load center, an electric power distribution system must be adapted to local conditions by taking into account factors, future developments, constraints, and economics.[8] In this study, the author will calculate the reability index value using the RIA-section technique method, then the network configuration index will be compared according to SPLN standard, as shown in the table 1 below[9]: Table 1. reability index value based on SPLN Value Radial SUTM 3.2 times/year Radial SUTM with PBO 2.4 times/year SKTM without SKTM with PPJD PPJD 1.2 times/year 1.2 times/year SAIFI SAIDI 21 hours/year 12.8 hours/year 4.36 hours/year 3.33 hours/year Based on SPLN no.59 of 1985 wehere for each component in a distribution network system has a standard failure rate and component reapir time, as shown in the table 2 below:[10] Table 2. standard failure rate and repair time SPLN no.59 of 1985 component Sustained failure rate Momentary failure rate r (hours/year) 1 SUTM 0.2 0.003 3 2 SKTM 0.007 0.003 10 3 Transformator 0.005 0.003 10 4 FCO (Fuse Cut Out) 0.003 0.003 0.25 5 Recloser 0.005 0.003 10 NO 58 AIJASET – Vol. 02, No. 02, July 2022. 57-64 https://doi.org/10.25077/aijaset.v2i2.42 6 PMT 0.004 0.003 10 7 LBS 0.003 0.003 10 Based on the failure rate and repair time in SPLN no. 59 of 1985 then the data will be used to calculate the reliability of component repair time in each section. Section technique method where this method is assessed simple and can simplify the calculation of the reliability index.The working principle is by dividing the network structure into several parts in analyzing the system, and each section has its own calculation. [11]The results of each section will be added up be the final result of the system reliability index. However, in his calculations, the methodThis section technique only uses the failure rate commonly used for each system components, namely the sustained failure rate (failure rate with repair intervals) long enough). [12] RIA Reliability Index Assessment method is a method that predict disturbances in distribution systems based on system topology and reliability components, RIA records failures that occur in equipment caused by temporary interruption.[13] The weakness of the RIA method is that it only calculates reliability caused by a temporary disturbance. Calculation on method combined method, namely by combining the momentary failure rate parameters in the the calculation. Where the calculation of the momentary failure rate is obtained by using RIA method. [14]The RIA method is used to capture the failure rate caused by temporary disturbance (momentary failure rate), so that the final result of this method is more close to the actual results in the field. The combination of the Section Technique and RIA methods is actually combines the parameters of the sustained failure rate (failure rate with repair interval quite a long time) contained in the Section Technique method with momentary parameters failure rate (failure caused by temporary disturbances) contained in the method RIA. This merger is expected to cover the shortcomings of the RIA method which only has a parameter of momentary failure rate.In addition, this method of merging is expected can meet or approach PLN standards to achieve World Class Service (WCS), the formula is below[15]: ΛLP = Sustained Failure rate x channel length (1) ULP = Λsustained x repair time (2) SAIDI = NLP x ΛLP / Nsection (3) SAIDI = NLP x ULP / Nsection (4) ENS = [ energy not supply kw x time (h) ] (5) Information : ΛLP : value of failure rate ULP : value of repair time 3. Result and Discussion From the data general from feeder LS-05 and LL-4, it can be simulated using ETAP 14.1 software, which consist 1 power grids from each feeder, feeder LS-05 serves 30 transformers, feeder LL-4 serves 22 transformers, and 6 section LBS an 1 maneuver of LBS. Below is an image generated from the ETAP software. 59 AIJASET – Vol. 02, No. 02, July 2022. 57-64 https://doi.org/10.25077/aijaset.v2i2.42 Figure 2. Single Line Diagram LS05-LL4 The picture above is a single line diagram Feeder LS-5 and LL-4 before LBS maneuver is installed. This single line diagram is used to simulate several scenarios of disturbance value to the feeder. Division of section on the feeder The number of customers for the LS-5 feeder in section one is 373 customers with 3 distribution transformers, in the second section there are 1,579 customers with 15 distribution transformers, in the third section there are 997 customers with 12 distribution transformers, if the total number of customers is on the LS-5 feeder are 2,449 customers with a total distribution transformer of 30 transformers. The division of section on the LS-05 feeder is shown in the table below[16]: Table 3. Section divion LS-05 NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 60 Trafo LSA-571 RENGGALI LSA-393 PERTANIAN LSA-522 PJR LSA-27 LHOKBANI LSA-687 PERUM TONY LSA-223 PERUM ALFATIH LSA-513 BTN POLRI LSA-392 BNN LSA-201 SPBU LSA-422 BTN ASAM MERA 2 LSA-383 BTN ASAM MERA 1 LSA-333 LANGSA KUPI LSA-438 KTR.INSPEKTORAT LSA-252MASJID LOR.KB LSA-544 LOR.KB LSA-381 LOR.TPI LSA-465 SAMSAT LSA-24 SLB LSA-347TKMTG.SEULIMENG LSA-614 PERUM M.K customers 149 75 149 149 25 25 149 75 149 75 149 149 37 149 149 149 1 149 120 50 Normal power (KVA) 80 40 80 128 40 40 80 40 80 40 80 80 20 80 80 80 20 160 80 80 Section division Section 1 Section 2 Section 3 AIJASET – Vol. 02, No. 02, July 2022. 57-64 https://doi.org/10.25077/aijaset.v2i2.42 21 22 23 24 25 26 27 28 29 30 LSA-537 RADIO GIPSI LSA-211 BTN SEI PAUH 1 LSA-98 BTN SEI PAUH 2 LSA-337 PERUM PUSONG 1 LSA-331 PERUM PUSONG 2 LSA-249 BTN SEI PAUH 3 LSA-632 MUQ.WAHYU RIZKI LSA-285 MUTIA RESIDENCE LSA-455 RS.UMMI LSA-281 BPJS KESEHATAN 75 239 75 75 149 75 3 40 95 1 40 128 40 40 80 40 128 40 80 80 The LL-4 feeder in the first section has 821 customers with 5 distribution transformers, in the second section there are 1,284 customers with 5 distribution transformers, in the third section there are 969 customers with 11 distribution transformers, the LL-4 feeder has a total of 3,074 customers with 22 transformers distribution. The division of section on the LL-04 feeder is shown in the table below. Table 4. Section divion LL-4 NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Trafo Customers LSA-447 Tugu LSA LSA-200 Simp. 3 kampung blang LSA-495 blang seunibong rel II LSA-345 Blang seunibong rel I LSA-346 Dr. Jepang kp.Blang LSA-542 Kp.Blang II LSA-16 Kp. Blang I LSA-453 Alue berawe LSA-129 alue Berawe II LSA-332 Pukesmas Langsa Kota LSA-84 Simpang Kw.Langsa LSA-560 Kuala Langsa I LSA-382 Kuala Langsa II LSA-199 Simp 3 BTN Sei Pauh LSA-389 Ktr Geuchik Sei Pauh LSA-104 Kim 3 LSA-128 Kim 5 LSA-329 Perum Pusong Kuala LSA-121 Mesjid Kuala LSA-631 Kuala KM 8 LS0A-340 TPI Kuala LSA-118 Pelabuhan Kuala 149 299 149 75 149 149 299 299 149 149 239 149 149 75 70 75 75 75 149 75 3 74 Normal power (KVA) 100 200 100 50 100 100 200 200 100 100 160 100 100 50 50 50 50 50 100 50 200 160 Section division Section 1 Section 2 Section 3 After performing calculations on the two feeders using the section method and also the combined RIA-section method, the results of the two feeders were found as shown in the table below: Table 5. reability index LS-05 feeder with section method SAIFI SAIDI ENS 2.2739 8.41995 6 61 AIJASET – Vol. 02, No. 02, July 2022. 57-64 https://doi.org/10.25077/aijaset.v2i2.42 Table 6. reability index LS-05 feeder with combined method (RIA-Section) SAIFI SAIDI ENS 2.0219 8.3082 6.0934 The comparison of the reliability index of the distribution system according to the PLN standard (SPLN 68-2) in 1986 above can be seen as the bar chart below. DIAGRAM PERBANDINGAN INDEKS KEANDALAN SISTEM DISTRIBUSI PENYULANG LS-05 SAFI 21 SPLN 8.3082 Gabungan 8.41995 3.2 2.0219 2.2739 Section Technique SAIDI Figure 3. LS-05 feeder distribution system reliability index comparison chart Like the blog diagram above, we can analyze the reliability index value of the distribution system in the section method with the value of the sustained failures rate, which we can see in table 3.2 above, which shows a SAFI value of 2.2739 times/customer/year, then in the combined RIA-Section method. with the addition of the momentary failures rate of 0.003 according to the PLN standard, getting a result of 2,019 times/customer/year (in 2020 with 6 feeder interruptions) there is a decrease of 0.2549 and it is still in accordance with the PLN standard. Likewise with the SAIDI value in the section method of 8.41995 hours/customer/year, the combined method of 8.3082, a decrease of 0.1117 hours/customer/year is still very far from the PLN standard SAIDI limit which states that these two methods have successfully demonstrated achievement of the distribution system reliability index. calculations LL-4 feeder using the section method and also the combined RIA-section method, the results were found as shown in the table below: Table 7. reability index LL-4 feeder with section method SAIFI SAIDI ENS 2,28905 8,48047 10,3253 Table 8. reability index LL-4 feeder with combined method (RIA-Section) SAIFI SAIDI ENS 2,6574 9,3008 11,6606 The comparison of the reliability index of the distribution system according to the PLN standard (SPLN 68-2) in 1986 above can be seen as the bar chart below. 62 AIJASET – Vol. 02, No. 02, July 2022. 57-64 https://doi.org/10.25077/aijaset.v2i2.42 DIAGRAM PE RB ANDINGAN INDE KS KE ANDAL AN S IS T E M DIS T RIB US I PE NYUL ANG L L -4 SAFI 21 SPLN 9.3008 Gabungan 8.48047 3.2 2.6574 2.28905 Section Technique SAIDI Figure 4. LSL-4 feeder distribution system reliability index comparison chart Like the blog diagram above, we can analyze the reliability index value of the distribution system in the section method with the value of the sustained failures rate that we can see in table 3.2 in chapter 3 above, the SAFI value is 2.28905 times/customer/year, then the combined method RIASection with the addition of a momentary failures rate of 0.003 according to the PLN standard gets a result of 2.6574 times/customer/year (in 2020 with 12 feeder disturbances) there is an increase of 0.36835 but it is still in accordance with the PLN standard. Likewise, the SAIDI value in the section method is 8.48087 hours/customer/year, the combined method is 9.308, an increase of 0.8272 hours/customer/year is still very far from the PLN standard SAIDI limit which states that these two methods have succeeded in showing the achievement of the index. reliability of the distribution system in both feeders. 4. Conclusion Based on the results of the calculation of the reliability of the LS-4 and LS-5 feeders which are installed with LBS maneuvers at both ends of the feeder using the combined RIA-section method, the following conclusions can be drawn: 1. The SAIFI value for the LS-5 feeder using the section method is 2.2739 times/customer/year and the SAIDI value is 8.41995 hours/customer/year. For LL-4 feeders, the SAIFI value is 2.28905 times/customer/year and the SAIDI value is 8.48047 hours/customer/year. 2. The RIA-Section Combined Method with the addition of a momentary failure rate parameter of 0.003 decreased the SAIFI value on the LS-5 feeder by 0.2549 to 2.0219 times/customer/year, and SAIDI decreased by 0.1117 to 8.3082 hours/customer/year. In contrast to the LS-5 feeder, which has decreased in SAIDI and SAIFI values. in the LL-4 feeder, the reliability index using this combined method increased for SAIFI value increased by 0.36835 to 2.6574 times/customer/year, the SAIDI value increased by 0.8272 to 9.308. This difference can occur because the LL-4 feeder has a longer distribution channel and has more customers than the LS-5 feeder. 3. The frequency and duration of disturbances in the system are not only affected by sustained interruptions in the section method, but also be affected by momentary interruptions. 4. Based on the final results of each method used, it can be seen that with the addition of LBS which is installed maneuverably for the LS-5 and LL-4 feeders which maintains the stability of the distribution of electricity, it also reduces the blackout area and time of blackout on both feeders. References [1] [2] E. Syahputra et al., “Analisis Stabilitas Sistem Tenaga Listrik Menggunakan Matlab,” sSistem Inf., vol. 2, no. 2, pp. 29–48, 2018. A. Hasibuan, Badriana, and A. Z. Hasibuan, “Simulation Analysis of Power Flow Sub Aceh 150 Kv,” 63 AIJASET – Vol. 02, No. 02, July 2022. 57-64 https://doi.org/10.25077/aijaset.v2i2.42 [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] 64 vol. 3, no. 1, pp. 42–52, 2019. P. I. Dharmawati, S. Anam, and A. Soeprijanto, “Peningkatan keandalan sistem distribusi tenaga listrik 20 kV PT . PLN ( Persero ) APJ Magelang menggunakan static series voltage regulator ( SSVR ),” pp. 1–6, [Online]. Available: https://d1wqtxts1xzle7.cloudfront.net/49033122/ITS-paper-221922208100020-Paper-with-cover-pagev2.pdf?Expires=1651589707&Signature=CdmOa4~zaNlXNXjpvBw3ZEnlbzhai9YQYBcZVuNkYAEcQpTOWFBFz~Wsg30U000BKiRY89OA3gbw6fAYNTaTNVzWl6EOtw8BKpjmUGzGeKI5h5DLBjp5CQvbs. R. Santoso, “Evaluasi Tingkat Keandalan Jaringan Distribusi 20 kV Pada Gardu Induk Bangkinang Dengan Menggunakan Metode FMEA (Failure Mode Effect Analysis),” Jom FTEKNIK, vol. 3, no. 2, p. 1, 2016. G. P. B. Arigandi, R. S. Hartati, and A. I. Weking, “Analisa Keandalan Sistem Distribusi Penyulang Kampus Dengan Menggunakan Penggabungan Metode Section Tecknique Dan Ria,” Maj. Ilm. Teknol. Elektro, vol. 14, no. 2, p. 1, 2015, doi: 10.24843/mite.2015.v14i02p01. A. Hasibuan, “Analisis Stabilitas Sistem Tenaga Listrik Single Mesin Menggunakan Metode Runge Kutta Orde 4,” J. Elektro dan Telkomunikasi, vol. Vol 4, no. No. 2, p. 24, 2017. H. Prabowo, Hernanda, I. G. N. Satriyadi, and O. Penangsang, “Studi Analisis Keandalan Sistem Distribusi Pabrik Semen Tuban Menggunakan Metode Reliability Index Assessment (RIA) dan Program Analisis Kelistrikan,” J. Tek. ITS, vol. 1, no. 1, pp. 87–90, 2012. et al., “Analisa Aliran Daya Pada Sistem Tenaga Listrik Dengan Metode Fast Decoupled Menggunakan Software Etap,” RELE (Rekayasa Elektr. dan Energi) J. Tek. Elektro, vol. 3, no. 1, pp. 37–45, 2020, doi: 10.30596/rele.v3i1.5236. M. Jufrizel and R. Hidayatullah, “Analisa Keandalan Sistem Distribusi 20KV Menggunakan Metode Section Technique dan Ria – Section Technique pada Penyulang Adi Sucipto Pekanbaru,” Semin. Nas. Teknol. Informasi, Komun. dan Ind., vol. 9, pp. 417–423, 2017. PT. PLN (Persero), “Buku 2 Standar Konstruksi Sambungan Tenaga Listrik,” PT PLN, vol. 2, pp. 1–83, 2010, [Online]. Available: http://hendrapola.my.id/fileku/pln-buku-2.pdf. S. Proteksi and T. Mva, “Analisis Penggunaan Rele Diferensial Di Pltmg Sumbagut 2 Peaker Power Plant 250 Mw,” vol. 10, pp. 9–13, 2021. PT. PLN (Persero), “Buku 5 Standar Konstruksi Jaringan Tegangan Menengah Tenaga Listrik,” PT. PLN, p. 213, 2010. “Jse-323 Jse-324,” vol. 4, no. 1, pp. 323–330, 2019. F. Yaser and A. A. Zakri, “Analisis tingkat keandalan jaringan distribusi 13,8 kv dengan menggunakan metode ria,” Jom Fteknik, vol. 6, no. 2, pp. 1–9, 2019. A. I. Karpov and D. A. Akimov, “Integral indicators improvement (SAIFI) of power supply reliability in electric distribution systems based on reclosers placement optimization,” Proc. 2018 IEEE Conf. Russ. Young Res. Electr. Electron. Eng. ElConRus 2018, vol. 2018-Janua, pp. 663–666, 2018, doi: 10.1109/EIConRus.2018.8317182. F. N. Illahi and Y. Sumaryana, “Sistem informasi ketersedian material pemeliharaan jaringan distribusi di pt pln (persero) area tasikmalaya,” Jumantaka, vol. 01, no. 01, pp. 271–280, 2018.